civil engineering - semspub.epa.gov · long-polluted gowanus canal, a super fund site in the new...
TRANSCRIPT
Civil Engineering NEWS
B.VIRO.MB.'IAL
••••••••••• US. EPA Proposes Plan for Cleaning Up Long-Polluted Canal In New York City
A PLAN RECENTI.Y released by the U.S. Environmental Protection
Agency (EPA) calls fur cleaning up the long-polluted Gowanus Canal, a Superfund site in the New York City borough ofBrooklyn that is considered one of the most contaminated waterways in the
REMEDIATION TARGET AREAS
nation. The proposed plan would include dredging and capping the entire length of the nearly 2 mi long canal, removing contamination from adjacent industrial properties, and reducing the volume of combined sewer overflows entering the waterway. All told, the EPA estimates that the project will cost between $467 million and $504 million and require nine years to complete.
The 100ft wide, 1.8 mi long Gowanus Canal was once a tidal creek draining to Upper New York Bay. By the 1860s the creek had been lined with bulkheads and converted into a canal to facilitate barge traffic associated with the many industrial facilities that had taken up residence along its shores. Such industries eventually included manufactured gas plants, chemical plants, tanneries, soapmaking enterprises, paint and ink producers, machine shops, and oil re-
[ 24 ] C i vi I En 9 in e e r in 9 MucH z o u
fineries. Significant quantities of waste from these operations fOund their way into the canal, which initially served as an open sewer. Meanwhile, combined sewer overflows from the local combined sewer system have long entered the Gowan us Canal after periods of wet weather, contributing to pollutant loads in the canal's sediments. Other sources of pollutants include nearby properties that continue to discharge contaminated groundwater to the canal.
In recent decades, many industrial facilities along the canal have closed. Today the Gowanus Canal flows by a mix of industrial, commercial, and residential development. Although some businesses continue to rely on the canal fur maritime commerce, the waterway is also used for such recreational purposes as canoeing, kayaking, and diving. Despite watnings, anglers try their
luck in the canal, particularly near its mouth. By removing or capping contaminated sediment, the EPA intends to "reduce the risk that the canal sediment poses both to humans and the benthic population," says Christos Tsiamis, the EPA's project manager fur the cleanup.
In March 2010, pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, the EPA designated the Gowanus Canal a fedetal SuperlUnd site. In its examination of the canal, the EPA distinguishes between the soft sediments that have accumulated in the canal and the native sediments that originally underlay it. Depending on the location, the soft sediments range in depth from 1 to 20ft. Sampling of the soft sediments has fOund high levels of polycyclic aromatic hydrocarbons, polychlorinated biphenyls, non-aqueousphase liquids (NAPLs), and such metals as mercury, cadmium, lead, and copper. High levels of polycyclic aromatic hydrocarbons and NAPI..s have also been fOund in the native sediment. The highest levels of contamination are fOund in the middle section of the canal, while the upper section exhibits intermediate levels of contamination. The lower section has the lowest contamination levels. For the purposes of its
I
COMMERCIAL & STRUCTURAL
STRENGTHE TYFO" FIBRWRAP" SYSTEMS STRENGTHEN VITAL
INFRASTRUCTURE SUCH AS BRIDGES, PIPELINES,
BUILDINGS AND OTHER STRUCTURES.
The Tyfoe Fibrwrape system can be used to add
structural properties to bridges so they can
carry heavier loads, restore damaged concrete
on waterfront structures, repair and strengthen
pipelines or reinforce building foundations and
bridges to withstand seismic and blast loads.
This light-weight, low-profile material provides
the equivalent structural strength compared to
heavier and obtrusive concrete and steel solutions.
Fyfe engineers provide personalized technical
support with comprehensive design and specification
support packages with no obligation and at no cost.
Be sure to visit us at the Structures Congress 2013
Conference, booth 1143 in Pittsburg, PA.
FVFE An Aeg/on Company
858.642.0694 www.fyfeco.com
Fyfc Company IS proud to be a part of the Aeg10n CommerCial & Structural platform.
, ~ ?0 13 Acg on Corporallon
~... : -- ·- '
[26] Civil Engineering MARCH zou
Civil Engineering NEWS
plan, the EPA has designated the upper, middle, and lower sections of the canal as respectively remediation target areas (RTAs) 1, 2, and 3.
Released in late December, the EPA's proposed plan would entail dredging a total of nearly 590,000 cu yd of contaminated sediment from the canal, which has a maximum depth of15 ft in its main channel at low tide. Approximately 307,000 cu yd of sediment would be dredged from RTAs 1 and 2, while another 281,000 cu yd would be dredged from RTA 3. All dredged areas then would be capped with various layers of clean material to confine any contamination remaining in the canal's native sediments and prevent that confined material from being disturbed by canal traffic or water currents. The cap would include a treatment layer of oleophilic clay designed to capture any contamination passing upward from underlying sediments. What is more, in situ stabilization of native sediments would be conducted within certain areas ofRTAs 1 and 2 in which NAPU are expected to remain. Before capping is conducted in these areas, the native sediment would be stabilized to depths of3 to4 ft by means of concrete or similar marerials. In this way, the stabilized material would be expected to impede the upward movement of the underlying NAPU.
Highly polluted material removed ftom RTAs 1 and 2 would be treated by means of thermal desorption at an offsite fucility to remove organic contaminants, and the treated material could then be used beneficially elsewhere. Meanwhile, less contaminated material removed from RTAs 1 and 3 would probably be stabilized and reused off-site. However, the plan also includes an option for stabilizing sediments ftom RTA 3 on-site and placing them in a confined disposal fucility that would be constructed on-site.
To reduce the volume of combined sewer overflows entering the canal, the EPA's plan calls for installing in-line storage tanks neat two outf.ills. The latger of the twO outfulls discharges approximately 130 million gal to the canal each yeat, while the other outf.ill discharges neatly half this volume, Tsiamis says. The tanks are expected to reduce the total volume of discharges from the two outfulls by 58 to 7 4 percent on an ovetall annual basis. Meanwhile, the New York Stare Department of Environmental Conservation is overseeing efforts to address contamination entering the canal from former manufuctured gas plants.
The EPA estimates that its proposed plan for cleansing the Gowanus Canal would have capital costs of$286 million and operations and maintenance costs of $2 million annually. The cost to treat and dispose of dredged material is expected to range from $179 million to $216 million.
The EPA has set an April 27 deadline for accepting written comments on its proposed plan. The agency expects to announce its final decision regarding a plan for the Gowanus Canal by the end of summer, Tsiamis says. Design work will begin shortly thereafter and will probably be completed in 2016. Construction is expected to last roughly six years.
- JAY LANDERS