civil engineering materials - · pdf filecivil engineering materials sab 2112 ... 35 •...

17
8/18/2010 1 Civil Engineering Materials SAB 2112 Introduction to Concrete Dr Mohamad Syazli Fathi Department of Civil Engineering RAZAK School of Engineering & Advanced Technology UTM International Campus August 18, 2010 Introduction to Concrete Objectives of the lecture • The main objective of this lecture is to explain to students: 1. Workability, test of fresh concrete, segregation and bleeding in concrete 2 Concrete on site - method of production concrete strength 2. Concrete on site - method of production, concrete strength and grade 3. Concrete proportions - standard, nominal; Hardened concrete tests-destructive and non-destructive tests New blog: SAB2112.wordpress.com Leonard P. Zakim Bunker Hill Bridge in Boston. (Image courtesy of the Federal Highway Administration .) Introduction Concrete is one of the most common construction materials and is used in a wide variety of applications, ranging from piles, multistory buildings, dams, foundations, pavements, storage tanks and many other structures. Bridge over the Sungai Selangor, Kuala Selangor, Malaysia The asymmetric cable stay bridge has a main span of 232m and 114m back span along a 1000m radius. It is a pre-stressed concrete structure with a 25m wide deck comprising a glued segmental spine and precast side frame. The deck is supported from an inclined tower on a single plane of pre-stressed stays in the median which are anchored on the back span to a precast boom. An outrigger beam is employed to stabilize the tower with transverse stays anchored to the beam below deck level. Sources: http://www.bandraworlisealink.com/abroad-pro.html

Upload: vuongdieu

Post on 18-Mar-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

1

Civil Engineering MaterialsSAB 2112

Introduction to Concrete

Dr Mohamad Syazli Fathi

Department of Civil EngineeringRAZAK School of Engineering & Advanced Technology

UTM International Campus

August 18, 2010

Introduction to Concrete

Objectives of the lecture

• The main objective of this lecture is to explain to students:1. Workability, test of fresh concrete, segregation and

bleeding in concrete2 Concrete on site - method of production concrete strength2. Concrete on site - method of production, concrete strength

and grade3. Concrete proportions - standard, nominal; Hardened

concrete tests-destructive and non-destructive tests

New blog: SAB2112.wordpress.comLeonard P. Zakim Bunker Hill Bridge in Boston. (Image courtesy of the Federal Highway Administration.)

IntroductionConcrete is one of the most common

construction materials and is used in a wide variety of applications, ranging from piles, multistory buildings, dams, foundations, pavements, storage tanks and many other structures.

Bridge over the Sungai Selangor, Kuala Selangor, Malaysia

• The asymmetric cable stay bridge has a main span of 232m and 114m back span along a 1000m radius.

• It is a pre-stressed i hconcrete structure with a

25m wide deck comprising a glued segmental spine and precast side frame.

• The deck is supported from an inclined tower on a single plane of pre-stressed stays in the median which are anchored on the back span to a precast boom. An outrigger beam is employed to stabilize the tower with transverse stays anchored to the beam below deck level.

Sources: http://www.bandraworlisealink.com/abroad-pro.html

Page 2: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

2

Introduction• It is one of the most economical materials of construction and is very

versatile in nature and application.

The cube-shaped building consists of an irregular concrete structure enveloped in glass. Sources: http://www.dezeen.com/2008/12/07/nordwesthaus-by-baumschlager-eberle/

This is a hostel in Austria, designed by art college graduate Andreas StraussSource: http://slog.thestranger.com/2008/08/future_concrete

Sources: http://www.core.form-ula.com/2008/04/16/c-space-adrlten-pavilion/

Advantages of Concrete1. Economical in long run compared to other engineering material (low cost)

2. Possesses a high compressive strength 3. Corrosive & the weathering effects are

minimal.4. Fresh concrete can be easily handled &

moulded in any shape / size. 5. Formwork can be re-used6 C b d & fill d h k6. Can be sprayed on & filled the cracks

for repairing process.7. Durable & fire resistant & requires little

maintenance.8. Can be pumped and hence it can be laid

in the difficult position9. Protection of embedded steel10. Variety of finishes obtainable.

Introduction• Concrete is made by mixing: Cement, water, course fine aggregates

and admixtures (if required). • The aim is to mix these materials in measured amounts to make

concrete that is easy to: Transport, place, compact, finish and which will set, and harden, to give a strong and durable product.

• The amount of each material (ie cement, water and aggregates) affects the properties of hardened concretep p

Sources: http://www.transport.vic.gov.au/DOI/Internet/transport.nsf/AllDocs/74164766E0CEAF95CA25700500122952?OpenDocument

Properties of Concrete

A. Properties of Fresh Concrete1. Workability, 2. Segregation,

B. Properties of Hardened Concrete1. Strength2. Deformation

3. Bleeding, 4. Heat of Hydration

3. Creep4. Shrinkage

10

Properties of Fresh Concrete

Workability

1. Generally implies the ease with which a concrete mix can be handled from mixer to it’s finally compacted shape

11

finally compacted shape– Consistency - fluidity– Mobility - ease of flow– Compactability - ease of compaction

2. Internal work required to produce full compaction.

Tests to Measure Workability

Four widely used testsFour widely used tests

1.1.Slump TestSlump Test

12

pp2.2.Compacting factor testCompacting factor test3.3.VebeVebe time testtime test44 Flow testFlow test

Page 3: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

3

Slump Test• Developed in 1913 in

US, by Chapman• BS 1881 Part 102• Required

100100

13

– Slump cone– Tamping Rod– Ruler

• Suitable for normal mixes of med to high workability

200200

300300

14

Sources: http://www.concrete-curb.com/tag/concrete-structure/

Slump Test (cont)Slump Test (cont)

• Method– Concrete put in cone in

3 layers, each layer tamped 25 timesT k ff

Slump (mm)Slump (mm)

16

– Top struck off– Cone carefully lifted

off– Slump measured

• Not suitable for dry mixes

True slumpTrue slump

Shear slumpShear slump Collapse slumpCollapse slump

Adding more water to a mix will create a weaker hardened concrete!

Source: http://hia.com.au/HIA/Content/IS/BPS/NAT%20Change%20in%20slump%20helps%20straighten%20your%20back.aspx

ReferenceCement Concrete & Aggregates Australia (2008) Premixed concrete delivery to domestic house floor slabs and footings –changes to the Australian standard: Important information for concrete placers, www.ccaa.com.au

Compacting Factor TestStandards: BS 1881-103, BS 5075

• The Apparatus enables a check to be made on the weight of concrete when it is falls from fixed heights into a cylindrical container of standard capacity.

18

Comprises:• The Apparatus consists of two

conical hoppers each with a hinged trap with quick release mechanism to allow free flow of theconcrete sample.

• A cylindrical mould is fitted beneath the hoppers.

Sources: http://geotechnical-equipment.com/Concrete.html

Page 4: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

4

Compacting Factor Test

• Thought to be more sensitive than the slump test

• Suitable for all mixes• Method

19

– mixed concrete put in top hopper– allowed to fall into 2nd hopper then

cylinder– cylinder stuck off, concrete weighed

and compared with weight of fully compacted cylinder

VebeVebe testtestStandards: EN 12350-3, ASTM C1170

•The vebe test is a variation of the simple slump test where the concrete is subject to vibration after removal from the slump cone to determine the workability of fresh concrete.

A l i di i l d i i h h

20

• Vebe test - time for standard cone to be compacted flat by glass plate on vibrating table eg for workable concrete the Vebe time = approx 3s

•A plastic disc is placed into contact with the upper surface of the concrete, the vibrating table underneath operates at a fixed amplitude allowing the lower surface of the disc to be completely coated with cement.

Sources: http://geotechnical-equipment.com/Concrete.html

Flow Flow teststestsStandards: EN 12350-5, BS 1881-105

• The Flow Table test is used for determining the consistency and workability of fresh concrete.

• The conical mould for casting the flow specimen and the calliper for measuring the diameter of the mortar after it has been

21

diameter of the mortar after it has been spread on the flow table.

• The apparatus consists of a double steel table, the upper table measuring 700x700 mm and hinged at one side to the lower table.

••Flow test Flow test -- the measured spread in mm of a standard cone on a the measured spread in mm of a standard cone on a dropping table (40mm, 15 times)dropping table (40mm, 15 times)••Neither Neither VebeVebe nor Flow test popular on sitenor Flow test popular on site

Sources: http://geotechnical-equipment.com/Concrete.html

Flow Test

22

Comparisons Between TestsComparisons Between Tests

me

(sec

)m

e (s

ec) 2020

(mm

)(m

m)

00

66

6633

23

3,63,6

Vebe

Tim

Vebe

Tim

Slump (mm)Slump (mm) Compacting FactorCompacting Factor

00

1010

00 5050 100100 0.60.6 0.80.8 1.01.0

Slum

p (

Slum

p (

5050

100100

Compacting FactorCompacting Factor0.60.6 0.80.8 1.01.0

For aggt/cement ratio = 3,6For aggt/cement ratio = 3,6

33

66

Effect of Time and Temperature Effect of Time and Temperature on Workabilityon Workability

2002001:2:4 mix 1:2:4 mix

24

??

Time (h)Time (h)

00

100100

00 22 44Temp (Temp (ooC)C)

55 2020 4040

with with w/c=0.775w/c=0.775

Page 5: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

5

Segregation

• The tendency for – sand-cement mortar

to separate from coarse aggregates

25

– cement mortar to separate from fine aggregates

Segregation

• Caused by1. Excessive vibration2. Dropping fresh concrete

from a height

26

3. Poor grading4. High workability5. Mixes with no air

entrainment

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Page 6: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

6

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Concrete handling techniques to prevent segregation.

• Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Bleeding

• Tendency for water to rise to the surface

• This will cause

34

weakness or dustiness of the surface of the finished concrete, or a line of weakness between pours

Bleeding

• Bleeding affected largely by the properties of the cement.

35

• Avoided by– a finer cement– high C3A content– richer mix

Aggregate Grading

• Although the aggregate grading has little or no direct affect on strength, it does affect workability, and hence w/c ratio

36

w/c ratio.• The fundamental idea is that

finer stones fill up the gaps between larger stones, and so on, and the remaining space is filled by cement paste.

Page 7: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

7

Typical Grading Curves (BS882)

100100

8080

G di MG di M

37

7575 150150 300300 600600 1.181.18 2.362.36 55 1010 2020 37.537.5

6060

00

4040

2020

Grading MGrading Mfine aggtfine aggt 20 mm20 mm

coarsecoarseaggtaggt

mmmmμμmm

Proportioning and mixing concrete

• A concrete mix is designed to produce concrete that can be easily placed at the lowest cost.

• The concrete must be workable and cohesive when plastic then set andcohesive when plastic, then set and harden to give strong and durable concrete.

• The mix design must consider the environment that the concrete will be in; ie exposure to sea water, trucks, cars, forklifts, foot traffic or extremes of hot and cold.

Sources: http://www.enco.ch/pns.htm

Proportioning and mixing concrete

1. PROPORTIONING Concrete is a mixture of Cement, Water, Coarse and Fine Aggregates and Admixtures.

2. The proportions of each material in the mixture affects the properties of the finalmixture affects the properties of the final hardened concrete.

3. These proportions are best measured by weight.

4. Measurement by volume is not as accurate, but is suitable for minor projects.

Batching, Mixing, Placing and Compaction of Concrete

Batching• Is the process of measuring concrete mix ingredients either by

volume or by mass and introducing them into the mixture. • Traditionally batching is done by volume but most specifications

i h b hi b d b h h lrequire that batching be done by mass rather than volume.

Batching of Concrete

Sources: http://www.crusher2.com/machine-concrete_batching_plant.htm

Batching, Mixing, Placing and Compaction of Concrete

Mixing• The mixing operation consists of rotation or stirring, the objective

being to coat the surface the all aggregate particles with cement paste, and to blind all the ingredients of the concrete into a uniform mass; this uniformity must not be disturbed by the process ofmass; this uniformity must not be disturbed by the process of discharging from the mixer.

Page 8: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

8

Type of Mixer – Batch MixerThe usual type of mixer is a batch mixer, which means that

one batch of concrete is mixed and discharged before any more materials are put into the mixer. There are four types of batch mixer.1. Tilting drum mixer:

• A tilting drum mixer is one whose drum in which mixing take place is tilted for discharging. The drum is conical or bowl shaped with internal vanes, and the discharge is rapid and unsegregated so that these mixers are

i bl f i f l k bili d fsuitable for mixes of low workability and for those containing large size aggregate.

2. Non tilting drum mixer:• A non tilting drum is one in which the axis of

the mixer is always horizontal, and discharge take place by inserting a chute into the drum or by reversing the direction or rotation of drum. Because of slow rate of discharge, some segregation may occur.

Type of Mixer – Batch MixerThe usual type of mixer is a batch mixer, which means that one

batch of concrete is mixed and discharged before any more materials are put into the mixer. There are four types of batch mixer.3. Pan type mixer:

• A pan type mixer is a forced–action mixer, as distinct from drum mixer which relies on the free fall of the concrete inside the drum. The pan mixer consist of a circular pan rotating about its axis with one or two stars paddles rotating about vertical axis

fof pan. 4. Dual drum mixer:

• A dual drum is sometimes used in highway construction. Here there are two drums in series, concrete being mixed part of the time in one and then transferred to the other for the remainder of the mixing time before discharging.

Type of Mixer

Continuous mixers:– These are fed automatically by a continuous weigh-batching system.

Batching Plant

Batching Plant

Source: http://www.hi-unique.com/productdetail.aspx?cpid=98

Page 9: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

9

Mobile Concrete Mixing PlantUniformity of mixing

Mixing time:• It is important to know the minimum mixing time necessary to

produce a concrete of uniform composition, and of reliable strength.• The mixing time or period should be measured from time all the

cementing materials and aggregates are in mixer drum till taking out the concrete.

• Mixing time depends on the type and size of mixer, on the speed ofMixing time depends on the type and size of mixer, on the speed of rotation, and on the quality of blending of ingredients during charging of the mixer. Generally, a mixing time of less than 1 to 1.25 minutes produces appreciable non-uniformity in composition and a significant lower strength; mixing beyond 2 minutes causes no significant improvement in these properties.

• Table: Recommended minimum mixing times

Recommended minimum mixing times

Capacity of mixer (yd³) Mixing time (Minutes)

Up to 1 1

2 1.25

3 1.5

4 1.75

5 2

6 2.25

10 3.25

Prolong mixing:• If mixing take place over a long period, evaporation of

water from the mix can occur, with a consequent decrease in workability and an increase in strength.

• A secondary effect is that of grinding of the aggregate, particularly if soft; the grading thus becomes finer and the workability lower.

• In case of air entrained concrete, prolong mixing reduces the air content.

Ready mixed concrete:• If instead of being batched and mixed on site, concrete is

delivered for placing from a central plant. It is referred to as ready-mixed or pre-mixed concrete. This type of concrete is used extensively abroad as it offers numerous advantages in comparison with other methods of manufacture:

• Close quality control of batching which reduces the variability of the desired properties of hardened concrete.

• Use on congested sites or in highway construction where there is little space for a mixing plant and aggregate stockpiles;

Ready mixed concrete:

• Use of agitator trucks to ensure care in transportation, thus prevention segregation and maintaining workability

• Convenience when small quantities of concrete or• Convenience when small quantities of concrete or intermittent placing is required.

• There are two categories of ready-mixed concrete:1. central-mixed - mixing is done in a central plant and then

concrete is transported in an agitator truck. 2. transit mixed or truck mixed - the materials are batched at a

central plant but are mixed in a truck.

Page 10: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

10

Placing and compaction

• The operation of placing and compaction are interdependent and are carried out simultaneously.

• They are most important for the purpose of ensuring the requirements• They are most important for the purpose of ensuring the requirements of strength, impermeability and durability of hardened concrete in the actual structure.

• As for as placing is concerned, the main objective is to deposit the concrete as close as possible to its final position so that segregation is avoided and the concrete can be fully compacted. The aim of good concrete placing can be stated quite simply.

• It is to get the concrete into position at a speed, and in a condition, that allow it to be compacted properly.

Placing and compactionTo achieve proper placing following rules should be kept in mind:

1. The concrete should be placed in uniform layers, not in large heaps or sloping layers.

2. The thickness of the layer should be compatible with the method of vibration so that entrapped air can be removed from the bottom of each layer.

3. The rate of placing and of compaction should be equal. If you proceed too slowly, the mix could stiffen so that it is no longer sufficiently workable. On no account should water ever be added to concrete that is setting. On the other hand, if you go too quickly, you might race ahead of the compacting gang, making it impossible for them to do their job properly.

4. Each layer should be fully compacted before placing the next one, and each subsequent layer should be placed whilst the underlying layer is still plastic so that monolithic construction is achieved

5. Collision between concrete and formwork or reinforcement should be avoided.6. For deep sections, a long down pipe ensures accuracy of location of concrete

and minimum segregation.7. You must be able to see that the placing is proceeding correctly, so lighting

should be available for large, deep sections, and thin walls and columns.

Placing Concrete PlacingPlacing

• By skip, wheelbarrow, shute, shovel or concrete pump

• Place at final position - do not vibrate into position

58

• Vibrate using poker - approx 10 seconds at 0.5 metre intervals

• Level with wooden float, leave for a while, then finish with steel float

Concrete placing techniques

Sources: https://rdl.train.army.mil/soldierPortal/atia/adlsc/view/public/9708-1/accp/en5466/lsn4.htm

Compaction• Once the concrete has been placed, it is ready to be compacted. • The purpose of compaction is to get rid of the air voids that are

trapped in loose concrete.

• Why It Matters?

Page 11: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

11

CompactionIt is important to compact the concrete fully because:

1. Air voids reduce the strength of the concrete. For every 1% of entrapped air, the strength falls by somewhere between 5 and 7%. This means that concrete containing a mere 5% air voids due to incomplete compaction can lose as much as one third of its strength.

2. Air voids increase concrete's permeability. That in turn reduces its durability. If the concrete is not dense and impermeable, it will not be watertight. It will be less able to withstand aggressive iquids and its exposed

f ill h b dlsurfaces will weather badly.3. Moisture and air are more likely to penetrate to the reinforcement causing

it to rust.4. Air voids impair contact between the mix and reinforcement (and, indeed,

any other embedded metals). The required bond will not be achieved and the reinforced member will not be as strong as it should be.

5. Air voids produce blemishes on struck surfaces. For instance, blowholes and honeycombing might occur.

Compaction• Summing up, fully compacted concrete is dense, strong and

durable; badly compacted concrete will be porous, weak and prone to rapid deterioration. Sooner or later it will have to be repaired or replaced. It pays, therefore, to do the job properly in the first place.

• Stiff mixes contain far more air than workable ones. That is one of the reasons why a low-slump concrete requires more compactive effort than one with a higher slump - the compaction needs to continue for a longer time, or more equipment has to be used.

Compaction1. Even air-entrained concrete needs to be compacted to get rid of

entrapped air voids. 2. The difference between air voids and entrained air bubbles should be

noted at this stage. 3. The air bubbles that are entrained are relatively small and spherical in

shape, increase the workability of the mix, reduce bleeding, and increase frost resistance.

4. Entrapped air on the other hand tends to be irregular in shape and is detrimental to the strength of the mix.

5. It is to remove this air that the concrete must be properly compacted. 6. There is little danger that compaction will remove the minute air

bubbles that have been deliberately entrained, since they are so stable.

Compaction - Vibration• Vibration:

– To compact concrete you apply energy to it so that the mix becomes more fluid. Air trapped in it can then rise to the top and escape. As a result, the concrete becomes consolidated, and you are left with a good dense material that will, after proper curing, develop its full strength and durability.

– Vibration is the next and quickest method of supplying the energy. Manual techniques such as rodding are only suitable for smaller projects. Various types of vibrator are available for use on site.

Compaction – Poker Vibrators• Poker Vibrators

– The poker, or immersion, vibrator is the most popular of the appliances used for compacting concrete. This is because it works directly in the concrete and can be moved around easily.

– Sizes:• Pokers with diameters ranging from 25 to 75mm are readily available, and these are suitable for

most reinforced concrete work. Larger pokers are available - with diameters up to 150mm - but these are for mass concrete in heavy civil engineering.

Compaction – Poker VibratorsRadius of action:

– When a poker vibrator is operating, it will be effective over a circle centred on the poker. The distance from the poker to the edge of the circle is known as the radius of action.

– However, the actual effectiveness of any poker depends on the workability of the concrete and the characteristics of the vibrator itself. As a general rule, the bigger the poker and the higher its tse . s a ge e a u e, t e b gge t e po e a d t e g e tsamplitude, the greater will be the radius of action. It is better to judge from your own observations, as work proceeds on site, the effective radius of the poker you are operating on the concrete you are compacting.

Page 12: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

12

Compaction – Poker VibratorsThe length of time it takes for a poker vibrator to compact

concrete fully depends on:1. The workability of the concrete: the less workable the mix, the

longer it must be vibrated.2. The energy put in by the vibrator: bigger vibrators do the job

faster.3 The depth of the concrete: thick sections take longer3. The depth of the concrete: thick sections take longer.

Heat of HydrationHeat of Hydration

•• The exothermic reaction during setting can The exothermic reaction during setting can cause a significant temperature rise in large cause a significant temperature rise in large concrete pours. concrete pours.

70

pp•• This causes expansion, then setting, then This causes expansion, then setting, then

contraction.contraction.•• If the pour is restrained, or has a If the pour is restrained, or has a

temperature differential, cracking may temperature differential, cracking may occuroccur

((oo C)

C) 6060 InteriorInterior InteriorInterior

2020ooCC 2020ooCC

Heat of Hydration (large pours)Heat of Hydration (large pours)

71

Tem

p (

Tem

p (

00

2020

4040

00 11 22 33 00 11 22 33Time (days)Time (days) Time (days)Time (days)

SurfaceSurface SurfaceSurface

2020 CC 2020 CC reng

thre

ngth VibrationVibration

Hand CompactionHand Compaction

Hardened Concrete

StrengthPredominantly affected by the

amount of pores in the hardened concrete.

A hi i l ff d b

72

WaterWater--Cement ratioCement ratio00 0.50.5 1.01.0

Com

pres

sive

Str

Com

pres

sive

Str

InsufficientlyInsufficientlyCompactedCompacted

Fully CompactedFully CompactedConcreteConcrete

As this is strongly affected by the non-hydrated water remaining after hardening, the water-cement ratio is taken to be the main determinant of strength.

Page 13: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

13

Fineness of Cement

• The finer the cement, the faster it sets, and the faster

ngth

(Nm

mng

th (N

mm

--11))

4040

6060

7 days7 days28 days28 days

1 year1 year

73

compressive strength is gained.

Fineness of Cement (mFineness of Cement (m22kgkg--11))400400 800800600600

Com

pres

sive

Stre

nC

ompr

essi

ve S

tren

00

2020

4040

1 day1 day

yy

Different Cement Composition

A - High C3S, C3AB - Med high C3S, C3AC - Med low C3S, C3AD - Low C3S C3A ng

th (N

mm

-1)

40

60

74

D - Low C3S, C3A

Cements C and D may gain 50% of their strength after 28 days

Com

pres

sive

Stre

n

0

20

40

Age (log days)1 10 365

A B

C

D

Curing

• If left in contact with water, concrete will continue to gain strength for many months

• Otherwise all free water i d i h

75

evaporates or is used up in the hydration process, and no further hydration can continue

• Curing ensures that water for hydration is available as long as possible

Sources: http://www.larsenbuildingproducts.com/products/range/2/category/8/-/0/product/66/

Concrete curing

Concrete's Age-Compressive strength with different curing temperature.Source: http://commons.wikimedia.org/wiki/File:Age-Compressive_strength_(concrete-curing).png

New Technology: Internal Concrete Curing

• There's a renewed interest in developing methods to incorporate internal curing as a tool to reduce cracking.g

• More info:http://www.theconcreteproducer.com/industry-

news.asp?sectionID=1423&articleID=466478

CuringCuring

100 Moist cured, moist at test

Moist-cured, dry at test

Water curing after 9 monthsAir-cured after 1 month,dry at test

Air-cured after 1 and 3 months,dry at test

78Age (months)0 6 12

50

0

Air-cured, saturated at testAir-cured, dry at test

dry at test

Page 14: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

14

Compression Testing

• Two compression tests are used– The most common in the UK is the

cube test– However a cylinder with a height-

diameter ratio of 2 can be usedli d h b h ve

Stre

ngth

ve S

treng

th

79

– cylinder strength = cube strength x 0.87

Height/diameterHeight/diameter11 22

1.01.00.870.87

Rel

ativ

Rel

ativ

81

Compression testing on cube and its various failure modes

• Compression test of “concrete specimen” is the most widely used test to measure its compressive strength. Two types of concrete specimen: Cubes & Cylinders are used for this purpose:

• Cubes of size 150mm are more common in Asia, Russia & European countries while Cylinders of 150mm in diameter & 300mm high are common in U.S and Australia.

Sources: http://buildingresearch.com.np/services/mt/mt1.php

Deformation of Concrete

• To sense the deformation of concrete, cement or rock specimens under compression.

Standards ASTM C469ISO 6784DIN 1048UNI 6556ASTM D2664 (R k i )

84

ASTM D2664 (Rock testing)ASTM D2938 (Rock testing)ASTM D3148 (Rock testing)ASTM D5407 (Rock testing)

Applications 1. For determining the Elastic Modulus and strength

characteristics.2. To be directly glued to the specimens for the

measurement of deformation as alternative to the Electronic Compressometer.

Page 15: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

15

Deformation of Concrete

E=Stress/StrainBut the stress-strain curve

for concrete is non-linear

ess

ess

85

E varies from 15 to 40 Mpa, but the tangent modulus at high stress gets much lower

Stre

Stre

StrainStrain

Creep

ImmediateImmediateelasticelasticrecoveryrecovery

Load sustainedLoad sustained Load removedLoad removed

86TimeTime

CreepCreep

Elastic deformation Elastic deformation on loadingon loading

CreepCreeprecoveryrecovery

PermanentPermanentdeformationdeformation

Creep

• Concrete creep is defined as: deformation of structure under sustained load.

Basically, long term pressure or stress on concrete can make it change shape. This deformation usually occurs in the direction the force is being applied. Like a concrete column getting more compressed, or a beam bending.

Creep does not necessarily cause concrete to fail or break apart. Creep is factored in when concrete structures are designed.

CreepCreep

• Concrete naturally shrinks as it cures. If the pour is large enough, cracks WILL occur.

• Structural designers introduce so-called "control joints" in large pours so that cracking either does not occur, or occurs in predictable areas.

• If you look at a typical concrete driveway for instance you will notice lines

88

If you look at a typical concrete driveway for instance, you will notice lines scored across the concrete every few feet. Any stress cracks that occur are more likely to happen in the joint, where they will be less noticeable.

• This can be a huge problem in certain structures such as dams or the containment building at a nuclear power plant.

• Concrete for these types of structures has to be carefully engineered and layed. Concrete gives off heat as it cures (an 'exothermic' chemical reaction) and this can make the problem much worse.

• It is common to mix the concrete for a dam with chilled water and pour it in many thin layers to minimize creep and shrinkage caused cracks and flaws.

CreepCreep

• This can be a huge problem in certain structures such as dams or the containment building at a nuclear power plant.

• Concrete for these types of t t h t b f ll

89

structures has to be carefully engineered and layed. Concrete gives off heat as it cures (an 'exothermic' chemical reaction) and this can make the problem much worse.

• It is common to mix the concrete for a dam with chilled water and pour it in many thin layers to minimize creep and shrinkage caused cracks and flaws.

CreepCreep

• The magnitude of creep is affected by– More cement in mix - more creep– Higher w/c ratio - more creep– Higher relative humidity - lower creep– Greater age - lower creep

90

g p– Rapid Hardening - lower creep

Source: http://www.ndt.net/article/ndtce03/papers/p028/p028.htm

Time relationship of creep coefficients on bended and pressed specimens.

Page 16: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

16

Standard creep test frames.

ASTM C512 - Compressive Creep• The standard creep test consists of a frame

and hydraulic loading system to applyconstant stress to 150X300 mm (6x12 in.)cylindrical specimens (Figure).

• Deformation is monitored periodically over

Standard creep test frames. (Courtesy of CTLGroup)

p ytime and compard to compansion unloadedspecimens to obtain the creep strain of theconcrete, which can then be used to calculatethe creep compliance, or “specific creep” ofthe material.

• Tests are typically started at 7 or 28 days ofage, but this test can be modified for earlyage by starting the test as early as 24 hours.

• Sealed tests are used to evaluate “basic”creep and unsealed tests incorporate thePickett Effect, or “drying” creep.

Source: http://www.cement.org/tech/cct_cracking.asp

ShrinkageShrinkage

3 principal types of shrinkage/expansion:1. Plastic Shrinkage - caused by settlement of

solids and loss of free water from plastic concrete

92

concrete.2. Autogenous Shrinkage - Cement gel has a

lower volume than the water and cement that makes it. So at a constant water content shrinkage takes place.

3. Drying Shrinkage - Loss of water from cement gel, after loss of water from pores and capillaries. Can be as high as 1.5E9.

Image Source: http://www.inspectapedia.com/structure/FoundationOccur2.htm

Drying ShrinkageDrying Shrinkage

1. Because almost all concrete is mixed with more water than is needed to hydrate the cement, much of the remaining water evaporates, causing the concrete to shrink.

2. Restraint to shrinkage, provided by the subgrade, reinforcement,

93

or another part of the structure, causes tensile stresses to develop in the hardened concrete.

3. Restraint to drying shrinkage is the most common cause of concrete cracking.

4. In many applications, drying shrinkage cracking is inevitable. 5. Therefore, contraction (control) joints are placed in concrete to

predetermine the location of drying shrinkage cracks.

More info: http://www.cement.org/tech/faq_cracking.asp

Avoidance of Cracked Concrete

•• If concrete is If concrete is restrained,restrained, movement joints or antimovement joints or anti--crack crack reinforcement must be used. Heat of hydration, and drying reinforcement must be used. Heat of hydration, and drying shrinkage must be minimised.shrinkage must be minimised.

•• If concrete is not restrained, differential heat of hydrationIf concrete is not restrained, differential heat of hydration

94

If concrete is not restrained, differential heat of hydration If concrete is not restrained, differential heat of hydration and drying shrinkage should be minimised.and drying shrinkage should be minimised.

Page 17: Civil Engineering Materials -   · PDF fileCivil Engineering Materials SAB 2112 ... 35 • Avoided by – a finer cement ... • The mix design must consider the

8/18/2010

17