civl446 - report - april4 [ready for printing].pdf

Upload: bpaxton

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    1/72

    CIVL446 DETAILED

    DESIGN REPORTBrandon Paxton

    Derek Rempel

    Navid Shakibi

    D t Mi

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    2/72

    CIVIL446 Engineering Design and Analysis II

    CIVL446 DETAILED DESIGN REPORT

    Group #15

    Members:

    Brandon Paxton 44770089

    Derek Rempel 35255090

    Navid Shakibi 56175086

    Dernanto Mirwan 70846084Curtis Saunders 92191071

    Matthew Ridley 36007102

    April 5, 2012

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    3/72

    CIVIL446 Engineering Design and Analysis II

    Table of Contents

    1. EXECUTIVE SUMMARY ................................................................................................................................ 5

    2. INTRODUCTION .............................................................................................................................................. 6

    2.1 DESIGN PROJECT AND COMPONENTS ............................................................................................................ 6

    2.2 DISCIPLINES &DESIGN SCOPE...................................................................................................................... 6

    2.2.1 Transportation ....................................................................................................................................... 6

    2.2.2 Structures ............................................................................................................................................... 7

    2.2.3 Construction Management .......... ........... .......... ........... .......... ........... .......... .......... ........... .......... ........... .. 7

    2.3 DESIGN GOALS ............................................................................................................................................. 7

    2.3.1 Transportation ....................................................................................................................................... 7

    2.3.2 Structures ............................................................................................................................................... 7

    2.3.3 Construction Management .......... ........... .......... ........... .......... ........... .......... .......... ........... .......... ........... .. 7

    3. TRANSPORTATION ......................................................................................................................................... 8

    3.1 NEW DUNSMUIRON-RAMP ........................................................................................................................... 8

    3.1.1 Design Scope ............. .......... ........... .......... ........... .......... .......... ........... .......... ........... .......... ........... ......... 8

    3.1.2 Design Objectives ......... ........... .......... ........... .......... ........... .......... .......... ........... .......... ........... .......... ...... 8

    3.1.3 Design Overview .......... .......... ........... .......... .......... ........... .......... ........... .......... ........... .......... ........... ....... 8

    3.1.4 Theory and Design Criteria ................................................................................................................... 8

    3.2 TRANSPORTATION PLAN REVIEW ............................................................................................................... 14

    3.2.1 Current Traffic Characteristics and Patterns ...................................................................................... 14

    3.3 TRANSPORTATION PLAN ............................................................................................................................. 16

    3.3.1 Analysis and Past Studies ................ ........... .......... ........... .......... ........... .......... ........... .......... ........... ..... 17

    3.3.2 During Construction .......... ........... .......... ........... .......... ........... .......... ........... .......... ........... .......... ......... 18

    3.4 POST CONSTRUCTION ................................................................................................................................. 20

    4. STRUCTURES .................................................................................................................................................. 21

    4.1 DESIGN SCOPE ............................................................................................................................................ 21

    4.2 DESIGN OBJECTIVES ................................................................................................................................... 21

    4.3 DESIGN STANDARDS ................................................................................................................................... 21

    4.4 SELECTION OF STRUCTURAL SYSTEM ......................................................................................................... 22

    4.4.1 Glulam Arches ..................................................................................................................................... 22

    4.4.2 Precast Segmental Concrete Box Girders ............ ........... .......... ........... .......... ........... .......... ........... ..... 23

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    4/72

    CIVIL446 Engineering Design and Analysis II

    4.5.3 Design Summary .......... .......... ........... .......... .......... ........... .......... ........... .......... ........... .......... ........... ..... 33

    5. CONSTRUCTION MANAGEMENT ............................................................................................................. 34

    5.1 DESIGN SCOPE ............................................................................................................................................ 345.2 COST ESTIMATE .......................................................................................................................................... 34

    5.3 CONSTRUCTION SEQUENCE......................................................................................................................... 36

    5.4 CRANE LOADING ........................................................................................................................................ 38

    5.5 SAFETY CONSIDERATIONS &BYLAW RESEARCH ....................................................................................... 41

    6. ECONOMIC ANALYSIS ................................................................................................................................ 44

    6.1 DIRECT PROJECT COSTS.............................................................................................................................. 446.2 USERBENEFITS........................................................................................................................................... 44

    6.3 NEGATIVE IMPACTS .................................................................................................................................... 45

    6.4 COST-BENEFIT ANALYSIS SUMMARY ......................................................................................................... 46

    7. CONCLUSION ................................................................................................................................................. 47

    7.1 DESIGN GOALS &ACHIEVEMENTS ............................................................................................................. 47

    7.1.1 Transportation ..................................................................................................................................... 477.1.2 Structures ............................................................................................................................................. 47

    7.1.3 Construction Management .......... ........... .......... ........... .......... ........... .......... .......... ........... .......... ........... 48

    7.2 CLOSURE .................................................................................................................................................... 48

    8. BIBLIOGRAPHY ............................................................................................................................................. 49

    List of Tables

    Table 1: Design Goals & Achievements ........................................................................................................................ 5

    Table 2: Critical Stations for Design ........................................................................................................................... 12

    Table 3: Glulam Arch Performance Summary ............................................................................................................ 22

    Table 4: Precast Box Girder Performance Summary ................................................................................................... 23

    Table 5: Composite Steel Girders Performance Summary .......................................................................................... 24

    Table 6: Design Summary ........................................................................................................................................... 33

    Table 7: Summary of Cost Estimate ............................................................................................................................ 35

    Table 8: Summary of Construction Sequence ............................................................................................................. 38

    Table 9: Crane Comparison ......................................................................................................................................... 38

    T bl 10 120 T K M d l 100 GMT Lifti Ch t 40

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    5/72

    CIVIL446 Engineering Design and Analysis II

    Table 14: Structural Design Achievements ................................................................................................................. 47

    Table 15: Construction Management Design Achievements ....................................................................................... 48

    List of Figures

    Figure 1: Areas of Focus for Detailed Design ............................................................................................................... 6

    Figure 2: MoT Figure 340.A: Spiral Curve Geometry ................................................................................................ 10

    Figure 3: Horizontal Geometry .................................................................................................................................... 11Figure 4: Finalized Horizontal Alignment ................................................................................................................... 11

    Figure 5: Road Cross Section ...................................................................................................................................... 12

    Figure 6: Finalized Vertical Alignment Layout ........................................................................................................... 14

    Figure 7: Local Vehicular Travel Patterns Using Dunsmuir Viaduct .......................................................................... 16

    Figure 8: Local Vehicular Travel Patterns Using Georgia Viaduct ............................................................................. 16

    Figure 9: Post-Construction Traffic Flow .................................................................................................................... 20

    Figure 10: Design Scope General Area (Top) and Typical Span (Bottom) ................................................................. 21

    Figure 11: a) Elevation and b) Plan View of Loading ................................................................................................. 25

    Figure 12: Rear Elevation ............................................................................................................................................ 25

    Figure 13: Design Girder Loading ............................................................................................................................... 26

    Figure 14: SAP2000 Load Analysis ............................................................................................................................ 26

    Figure 15: Slab Section and Structural Idealization..................................................................................................... 27

    Figure 16: Slab Design a) Top View b) Section View ................................................................................................ 28

    Figure 17: Typical Girder ............................................................................................................................................ 29

    Figure 18: Elevation View of Pier Arms ..................................................................................................................... 30

    Figure 19: Elevation View of Pier ............................................................................................................................... 32

    Figure 20: N-M Interaction Diagram ........................................................................................................................... 33

    Figure 21: Sample Cost Estimate ................................................................................................................................ 34

    Figure 22: Major Construction Phases......................................................................................................................... 36

    Figure 23: Construction Sequence Example ................................................................................................................ 37

    Figure 24: Crane Stability Free-Body Diagram ........................................................................................................... 40

    Fi 25 G d k th t ff t d b th t ti 45

    http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318729http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318729http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318730http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318730http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318731http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318731http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318732http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318732http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318734http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318734http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318735http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318735http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318736http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318736http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318738http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318738http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318738http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318736http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318735http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318734http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318732http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318731http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318730http://c/Users/Brandon/Dropbox/CIVL445%20-%20Group%2015/CIVL%20446/Report/CIVL446%20-%20Report%20-%20April4.docx%23_Toc321318729
  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    6/72

    CIVIL446 Engineering Design and Analysis II

    1. Executive Summary

    The conceptual design for the Georgia and Dunsmuir viaducts completed by group 13 has beenused as the baseline for the extent of this design project. The Georgia viaduct is to be completely

    demolished, connecting to Pacific Blvd at Abbott St; the Dunsmuir viaduct to be partially

    removed, with a new onramp from Expo Blvd at Carrall St. The remaining parts of Dunsmuir

    viaduct are to be converted to green space for pedestrians and cyclists. Traffic currently entering

    onto the Dunsmuir viaduct from the east will follow an alternate route through Prior St to Expo

    Blvd. The design goals and achievements are described in Table 1below.

    Table 1: Design Goals & Achievements

    Design Objective Methods Achieved

    Transportation

    Dunsmuir On-ramp Location Placed to minimize land disturbance and cost

    On-ramp Roadway Geometry Designed following TAC and MoT guidelines

    Minimize Impacts on Traffic

    Flow

    Traffic planning during construction

    Traffic planning after construction

    Structures

    Speed of Construction Precast deck slab allows for prefabrication

    Tilt-up concrete piers limits the need for formwork

    Minimize Structural Depth Composite girders reduces girder depth

    Headed shear reinforcing reduces slab depth

    Durability Post-tensioning reduces cracking

    Precast concrete less vulnerable to deterioration

    Construction M anagement

    Detailed Cost Estimate RS Means data used to estimate construction related

    activities

    Construction Schedule

    Microsoft Project used to produce Gantt Chart for

    project activities Gantt Chart used to determine critical path

    Crane Selection and Loading Choose an appropriate method of lifting the major

    loads identified through the duration of the project.

    Worksafe BC & Workers Compensation Act used to

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    7/72

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    8/72

    CIVIL446 Engineering Design and Analysis II

    2.2.2 Structures

    Structural engineering considerations include the design of the new Dunsmuir on-ramp.

    Design included conceptual layout, gravity load design, and seismic design. Variousstructural systems were compared.

    2.2.3 Cons truc tion Managemen t

    Construction management aspects include detailed cost estimate, construction sequencing,

    material removal methods, noise & particulate matter considerations, safety planning, and

    a crane loading plan.

    2.3 Design Goals

    2.3.1 Transportation

    The primary goals in transportation aspect of this project that were identified at the outset

    of the project include:

    New on-ramp location to be determined and designed

    Modified traffic pattern to maintain traffic flow to/from the downtown core Minimizing traffic disturbance or impact on the traffic flowdue to construction

    process or the changes in traffic patterns.

    2.3.2 Structures

    Three primary design goals were identified at the outset of the project:

    Speed of constructionto reduce economic losses due to down time

    Minimizing structural depthdue to limited clearances of existing structures

    Durabilitythe bridge code (CSA S6) specifies a minimum service life of 75 years

    2.3.3 Cons truc tion Managemen t

    The main design goals were identified at the onset of the project:

    Detailed cost estimate for construction related activities

    Construction sequencing and critical path determination Crane selection and loading considerations

    Safety considerations & bylaw research

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    9/72

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    10/72

    CIVIL446 Engineering Design and Analysis II

    Spirals which follows before and after a curve allow for smooth and comfortable driving.

    The length of spiral (Ls) required is calculated by the following equation:

    Four checks must be met when designing the spiral length Ls:

    Comfort

    Relative slope

    Aesthetics

    TAC Criterion

    The comfort check minimizes the change in centripetal acceleration and the Ls can be

    calculated as follows:

    The relative slope check is to ensure that the development of superelevation takes place

    mainly in the spiral section of the total spiral-curve section and the Ls is calculated as

    follows:

    Where w = the total pavement width (2x3.6m + 3x0.3m +1.0m = ~9.1m)

    Where v = design speed (13.89m/s)C = the max comfort value (0.6m/s3)

    R = the curve radius (100m)The equation yields Ls = 44.65m

    Where R = radius of the curveA = the s iral arameter

    Where V = the design speed (50km/hr)e = the maximum rate of superelevation (4%)

    f = the max lateral friction TAC Table 2.1.2.1 (0.16)

    The equation yields Rmin = 98.43mRmin = 100m

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    11/72

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    12/72

    CIVIL446 Engineering Design and Analysis II

    The ramp curve geometry has been drafted and stations calculated using AutoCAD Civil

    3D 2012 while conforming to the above parameters. Stations and angles for construction

    layout are summarized in a calculation output table shown below in Figure 3. The ramp

    consists of two curves and corresponding spirals; the first spiral leading into the first curve

    had to be omitted due to alignment constraints.

    Figure 3: Horizontal Geometry

    A draft of the finalized horizontal on ramp layout is shown below in Figure 4. The on-ramp

    allows for two vehicle lanes travelling westbound along with a pedestrian walkway. Two

    lanes travelling westbound along Expo Blvd will be permitted to merge onto the Dunsmuir

    on ramp. The outside lane travelling west must make the merge onto the ramp or turn right

    onto Carrall St, while the other merge lane will be permitted to either continue along Expoor merge onto the on-ramp.

    Fi 4 Fi li d H i t l Ali t

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    13/72

    CIVIL446 Engineering Design and Analysis II

    3.60m wide with a 1.2m right of way for pedestrians as can be seen in the Figure 5below.

    Gutters on either side of the road are to be 0.03m and the concrete barrier will have an

    allowable 0.03m placement area.

    Figure 5: Road Cross Section

    3.1.4.3 Superelevation

    Superelevation has been utilized for the ramp to make it a more comfortable ride. Criteria

    for the superelevation were followed from TAC figure 2.1.2.8 with a max superelevation to

    be 4%.

    3.1.4.4 Vertical Alignment

    The vertical alignment of the Dunsmuir on-ramp has been allotted to ensure proper

    elevation clearances. Clearance points of concern are the areas where the ramp crossesover Expo Blvd at the Abbott Street intersection, the Skytrain track and where the ramp

    connects to the existing Dunsmuir viaduct which are outlined in Table 2below. A 5.0m

    clearance over roadways is specified by MoT and through observation of current Skytrain

    track clearances; a 4.00m clearance has been used as a baseline requirement.

    Table 2: Critical Stations for Design

    Critical Stations (m) Elevation Required (m) Comments0+065.610 5.00* Ramp Starts to swing above Expo Blvd

    0+110.530 5.00* 1st cross point over Abbott St

    0+130.000 11.62* Ramp Starts to swing above Skytrain at this station

    0+145.140 11.62* Directly over middle of Skytrain track

    0+166 630 11 62* R f ll Sk t i t k

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    14/72

    CIVIL446 Engineering Design and Analysis II

    Following MoT design guidelines, a parabolic curve has been used for the vertical design

    along with a maximum allowable grade of 10%. A sag curve exists at the start point of the

    ramp, a crest curve over the Skytrain track, and a sag curve where the ramp joins with

    Dunsmuir viaduct; between the curves are sections of continuous grade. The extent of

    curvature of sag and crest curves are controlled by a factor K. These K factors ensure a

    curvature which allows for a safe stopping sight distance and or comfort for the driver.

    Based on a design speed of 50km/hr the appropriate K values are outlined below.

    Minimum K crest = 7 (TAC Table 2.1.3.2)

    Minimum K sag = 4 allowable at intersections/adequate lighting (TAC Table 2.1.3.4)

    Having previously completing the horizontal alignment and noting the stations of special

    concern along the alignment, the vertical alignment can be begin. The K factor is

    calculated from the following equation:

    Vertical stationing is in accordance with the horizontal station. For the areas with curvature

    the following equation is used to calculate the elevation (y) along the curve:

    Figure 6 below shows the final vertical alignment of the Dunsmuir on-ramp; note the

    vertical scale is being exaggerated and overall is not to scale. The minimum Skytrain track

    clearance proved to be the governing parameter of this design. Because of that, the on-

    ramp actually must be elevated upwards of 1m above the existing viaduct at one point and

    then gently meet grade as the ramp is further aligned with the viaduct. To have the on-ramp

    connect flush with viaduct when the two first meet would require the other ramp option

    starting 65m before Carrall St which would relax the governing Skytrain track clearances

    as vertical elevations can be easier achieved by that point. Roadway grading will have to

    be done at the Carrall St intersection to incorporate the approach of the ne on ramp

    Where EBVCS = Elevation at start of curve

    X = horizontal distance from start of curve station BVCS

    a = slope change constant =

    g1 = grade of incoming tangentg2 = grade of outgoing tangent

    Where L = horizontal length of vertical curve (BVCSEVCS station)

    A = the algebraic difference between grade 1 and grade 2

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    15/72

    CIVIL446 Engineering Design and Analysis II

    Figure 6: Finalized Vertical Alignment Layout

    3.1.4.5 LimitationsThe drafting for the on-ramp alignment has followed only an orthophoto of the area and is

    therefore not completely accurate. Roadway boundaries and existing structures have been

    limited to drafting following the orthophoto and exact placement of those features cannot

    be known without a professional survey team. Another limitation being that existing

    topographic data and elevations pertaining to the existing Dunsmuir viaduct and Skytrain

    track could not be obtained and were therefore estimated by the best of our ability. A

    request for such data was made to the City of Vancouver but could not be released. For the

    educational purpose of this project using just the orthophoto will have to be good enough.

    3.2 Transportation Plan Review

    Transportation plans and viaducts studies and data collected from existing transportation

    reports and observations were reviewed to get a better overview and understanding of the

    traffic characteristics and patterns of the Georgia and Dunsmuir viaducts as well as the

    surrounding streets and regions. This information were acquired and reviewed in depth to

    understand further and anticipate the impacts of transportation plan changes caused by the

    proposed new Georgia off-ramp and Expo on-ramp as a solution to the old Georgia and

    Dunsmuir viaduct problem. A summary is provided below.

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    16/72

    CIVIL446 Engineering Design and Analysis II

    The Georgia viaduct currently has 3 vehicular lanes with traffic directed from East

    Vancouver/Chinatown to Vancouver downtown core.

    The Dunsmuir viaduct has 2 vehicular lanes and 1 lane dedicated for cyclists and

    pedestrians and the traffic is directed the opposite way from the Georgia viaduct.

    Expo Boulevard is currently a one-way street with traffic directed to Vancouver

    downtown area. It has 3 active vehicular lanes with 1 side lane for cyclists/parking.

    Pacific Boulevard has the same characteristic with the Expo Boulevard except that the

    traffic is directed to Vancouver Eastside.

    Currently, there are no transit services on the viaducts as well as on Expo and Pacific

    Boulevard. However, the Expo Skytrain Line runs adjacent to the viaducts. Based on the

    current study of the viaducts by Halcrow Consulting Inc., there are approximately 160

    heavy trucks (including trucks with three or more axels) and 800 light trucks (including

    cube van with two axles) that are using the Georgia and Dunsmuir viaducts daily.

    Additionally, the number of light trucks has found to remain relatively constant since 1996

    and the number of heavy trucks dropping by approximately 50% (Halcrow Consulting Inc.,

    2011).

    The approximate numbers of daily vehicular traffic are summarized below (Halcrow

    Consulting Inc., 2011):

    Expo Boulevard:

    Dunsmuir Viaduct:

    Georgia Viaduct:

    Pacific Boulevard:

    12,300 Vehicles

    19,000 Vehicles

    24,000 Vehicles

    13,000 Vehicles

    The following maps (Figure 7 & Figure 8) summarize the local vehicular travel patterns

    using both viaducts during morning and afternoon peak periods. (Halcrow Consulting Inc.,

    2011)

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    17/72

    CIVIL446 Engineering Design and Analysis II

    Figure 7: Local Vehicular Travel Patterns Using Dunsmuir Viaduct

    Figure 8: Local Vehicular Travel Patterns Using Georgia Viaduct

    3 3 T t ti Pl

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    18/72

    CIVIL446 Engineering Design and Analysis II

    observed traffic patterns were utilized to determine the best traffic planning to better serve the

    City of Vancouvers transportation system.

    3.3.1 An alysis and Past Studies

    Past case studies regarding transportation and/or urban impacts from freeway/viaduct

    removal were collected to be used as comparison and basic understanding on analyzing

    Vancouvers Georgia and Dunsmuir viaducts. While Vancouvers Georgia and Dunsmuir

    viaduct case is unique, it can learn important lessons from other past freeway removal

    projects. Some examples of the lessons that Vancouver can learn and apply are as follows:

    Absorbing the spillover traffic by distributing it over a network. Vancouvers

    viaducts capacities are properly utilized most of the time while the surrounding streets

    and networks are under-utilized. By removing the viaducts and properly plan the

    transportation network in the region, it might not only achieve its goal of connecting

    the downtown core to Vancouver eastside, but might also improve the traffic system in

    that region.

    Removal of an urban freeway or viaducts will change travel patterns significantly.

    However, traffic will eventually find alternate routes and select the most convenientmode for their travel. Although removing Vancouvers viaducts may seems to be

    posing many transportation problems for the future, past experiences from various

    cities in the world proves that people and traffic will adjust and adapt to the new

    system and will even create a better vibrant community without the freeway/viaducts.

    Based on the recent case study by the City of Seattle for the Alaskan Way viaducts

    removal, it was found that various cities also are or has experienced similar challenges withviaducts or highway. Two cases (San Franciscos Embarcadero Freeway and Seouls

    Cheonggye Expressway) with the most similarity were chosen as model cities for this

    project and the summary of the key findings are provided below.

    Embarcadero Freeway

    The Embarcadero Freeway in San Francisco, California shows similarity with Vancouvers

    Georgia and Dunsmuir viaduct in its function as a major route for industrial vehicle.

    Besides, this freeway is also located along the downtown waterfront of San Francisco and

    was a barrier to the waterfront region, which is now a tourist destination after the freeway

    is removed. This is a similar problem created by Vancouvers viaducts, the viaducts

    created barrier between downtown core and downtown eastside as well as acting as a

    barrier to the beautiful side of False Creek region in Vancouver

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    19/72

    CIVIL446 Engineering Design and Analysis II

    their own unique problems and characteristics. Nevertheless, this example of Embarcadero

    Freeway offers few potential insights that might be useful (City of Seattle, 2008):

    The freeway removal does not appear to have negative impact on the economies of

    nearby region or neighborhood. Instead, the net economic impact of the freeways

    removal for both the immediate region and system or city as a whole appears to have

    been positive.

    It was only after the removal of the freeway that San Franciscos waterfront emerged

    to be one of the most attractive destinations for locals and tourists.

    Cheonggye Expressway

    Cheonggye Expressway is similar to Vancouvers Georgia and Dunsmuir viaducts in terms

    of location, the importance of the structure to the city as well as the impacts it created

    when removed. The expressway was adjacent to the central business district of Seoul and

    primarily served as a bypass for regional traffic, which is really similar to the function of

    Vancouvers viaducts. Besides, the expressway and the roads were removed and the stream

    underneath the expressway was restored. This replacement of expressway restored open

    spaces access as well as water, and as proven by this model, the removal of the expresswayimproved the quality of-life of the city residents, workers and visitors.

    As compared and analyzed using two model cities mentioned above, the summary of some

    the impacts may be created by removing the viaducts are:

    Improve the net economic benefits in the immediate regions and the city as a whole.

    Improve traffic flow, as drivers will adjust to the changes and utilize the surrounding

    roads and will thus improve the traffic network.

    Improve the sustainability of City of Vancouver by creating open spaces and access to

    False Creek area that may be improved to be tourist destination.

    3.3.2 During Cons truc tion

    Traffic flow during construction of the Expo on-ramp and Georgia on-ramp needs to be

    carefully planned and maintained to avoid significant traffic disturbance andinconveniences. Routes and traffic are planned based on observation on traffic volumes

    data acquired from studies done by Halcrow Consulting Inc. for the viaducts. The

    transportation plan or traffic re-routing during construction are provided below.

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    20/72

    CIVIL446 Engineering Design and Analysis II

    Stage 1: Pre-Construction Activities

    No road closures, signs will be posted to inform the public about future traffic

    changes.

    Stage 2: Georgia Viaduct Demolition

    Georgia viaduct will be closed permanently days before demolition, this is so the

    traffic will be used to the changes in traffic pattern before demolition; traffic from

    Georgia St. heading eastbound will be rerouted to Cambie St. and/or adjacent streets.

    During the whole process of demolition and construction, a portion of the Abbott St.

    that is in between of the viaduct will be closed.

    Quebec St., Expo Blvd., Main St. and Prior St. will be closed accordingly when the

    demolition stage reaches the area near the mentioned streets. The mentioned streets

    will be opened again once the demolition process is done.

    Stage 3: Dunsmuir Viaduct Demolition

    Dunsmuir Viaduct will be closed permanently before demolition. Traffic heading

    westbound to downtown area will be possible using the adjacent streets such as Pender

    St. and Hasting Street.

    As only some portion of the Dunsmuir Viaduct will be demolished/removed, only the

    immediate adjacent streets (Prior St., Main St. Quebec St. and Expo Blvd.) will be

    temporarily closed.

    Stage 4: Expo On-ramp Construction

    During the course of the columns and entry-ramp construction, Expo Boulevard willbe serving as 1-lane street. Parking lanes will be removed and parking will be

    prohibited at all times along Expo Boulevard until the finish of construction.

    Transition will start at Expo Blvd. (After Quebec St.) from 3 lanes to 2 lanes and

    eventually 1 lane at the intersection of Carrall St. and Expo Boulevard.

    Expo Boulevard will serve as 3-lanes street again after Abbott St.

    Traffic from Union St heading to Expo Blvd. will be prohibited.

    A portion of Carrall St. between Keefer St. and Pacific Blvd. will be temporarilyclosed during the course of construction and traffic will only be allowed for

    construction vehicles.

    During the placement of the ramp sections, Expo Boulevard will be temporarily closed

    and traffic heading to Expo Blvd. from Quebec St. will be directed to north side of

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    21/72

    CIVIL446 Engineering Design and Analysis II

    3.4 Post Construction

    A short summary of the traffic patterns after construction is provided below:

    Expo/Dunsmuir and Georgia rampThe new Expo/Dunsmuir on-ramp will be located just after Carrall St. with traffic heading

    one-way westbound. There will be vehicular 2 lanes on the ramp with 1 lane for

    pedestrian/cyclist (Refer to section 2.1.5) Oncoming traffic will be directed up to

    Dunsmuir St. The new Georgia off-ramp will drop down just before Abbott St. and the

    design details of the ramp is not covered in this report. The ramp will have 2 vehicular

    lanes and 1 pedestrian lane. The traffic on this ramp is directed eastbound and will merge

    with the intersection at Abbott St. and Pacific Blvd. Traffic at Abbott St. at this intersectionwill be one-way southbound.

    Carrall Street and Expo Boulevard

    There will be some changes to the traffic patterns on Carrall St. in the area. Traffic at

    Carrall St. and Pacific Blvd. will merge with left-turn only option. Traffic going

    northbound on the Carrall St. at the intersection Expo Blvd. will only have a through-only

    traffic (no turns allowed at this intersection). And traffic going southbound on Carrall St.and Expo Blvd. will have a separate lane for entry to the new on-ramp to Dunsmuir St.The

    parking lanes on Expo Boulevard after Carrall Street will be removed and parking before

    Carrall St. will be allowed only from 10 PM 6 AM every day. The most extreme right

    lanes of Expo Blvd. will have an on-ramp only option, the middle one will have an option

    of going straight off to the on-ramp, and the most left lane will only have a through-only

    option.

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    22/72

    CIVIL446 Engineering Design and Analysis II

    4. Structures

    4.1 Design Scope

    The focus for structural design was the new Dunsmuir on ramp. This includes the bridge deck,

    the substructure, and the piers. A general structural layout is provided for the entire new ramp

    (SSK-1Appendix B). Detailed calculations and design sketches were prepared for elements of

    a typical span (SSK-1/SSK-2). The figures below summarize the design scope.

    Figure 10: Design Scope General Area (Top) and Typical Span (Bottom)

    4.2 Design Objectives

    The design objective was to provide a structure to support the new elevated roadway, spanning

    over the streets below. Key considerations for the design included:

    Speed of construction (to minimize disruption & economic losses)

    Structural depth (to fit into the available clearances)

    Durability (proven performance in a similar exposure)

    4 3 D i St d d

    General layout for entire ramp structure

    Typical Span Detailed Design Calculations

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    23/72

    CIVIL446 Engineering Design and Analysis II

    4.4 Selection of Structural System

    Selection of the structural system was regarded as the single most important factor in producing

    a successful design and, therefore, a significant effort was made in identifying and selecting asystem. The following structural systems were evaluated on the basis of the aforementioned

    objectives:

    Glulam Arches

    Precast Segmental Concrete Box Girders

    Composite Steel Girders with Precast Deck

    Ultimately, the structural system chosen was Composite Steel Girders with a Precast Deck.Sections 4.4.1 to 4.4.3 summarize the expected performance and the selection rationale.

    4.4.1 Glulam Arc hes

    In accordance with B.C.s WoodFirst Act, designers and developers are to consider using

    timber as the primary structural material for all publicly funded project. Because of the

    limited allowable structural depth (4.0m at one point due to the skytrain), a glulam arch

    superstructure was considered the most feasible timber system. Similar bridges in theNetherlands (Jett, 2011) and Austria (Unterwieser, 2007) were used as case studies in

    assessing performance. Table 3 summarizes the performance:

    Table 3: Glulam Arch Performance Summary

    Objective Meets Reqs? Comments/References

    Constructability Glulam elements are relatively light and could be

    lifted into place with readily available cranes, or

    the entire structure could be prebuilt and

    transported to the site (see Photo 1)

    Structural Depth With an arched superstructure, the depth belowthe deck could easily be limited to

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    24/72

    CIVIL446 Engineering Design and Analysis II

    4.4.2 Precast Segmen tal Conc rete Bo x Girders

    Precast, post-tensioned segmental concrete box girders, similar to those employed in the

    Canada Line, are currently a popular structural system. Table 4 outlines their performance:

    Table 4: Precast Box Girder Performance Summary

    Objective Meets Reqs? Comments/References

    Constructability The precast segments can be quickly assembled

    The use of an overhead erection girder reduces

    obstruction to the streets below

    StructuralDepth

    The minimum practical depth of a box girder is

    1.8m (6ft) to allow adequate space for formworkand inspection inside the box

    Durability Precast & post-tensioned concrete has commonlybeen used in similar environmental exposure

    Photo 1Sneek Bridge, NetherlandsPhoto Credit: http://www.contemporist.com/2009/02/03/

    akkerwinde-bridge-by-oak-architects/

    Photo 2Mur River Bridge, Austria

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    25/72

    CIVIL446 Engineering Design and Analysis II

    4.4.3 Composite Steel Girders with Precast Deck

    Composite Steel Girder Bridges are a traditional structural form that is still in common use.

    However, such bridges typically employ cast in place decks and, as such, require formworkand curing time. As speed of construction is expected to govern the economy of the

    design, the use of precast and post-tensioned deck segments was considered.

    Table 5 summarizes the performance:

    Table 5: Composite Steel Girders Performance Summary

    Objective Meets Reqs? Comments/References

    Constructability The steel girders could easily be lifted into place

    by readily available cranes

    The precast deck segments could be quickly

    assembled

    Blockouts provided for shear studs (seePhoto 6)

    Structural Depth Structural depth can be reduced in selecting thesteel girder

    Durability The precast & post-tensioned deck offers good

    durability

    Similar bridges have commonly been used in

    similar exposures

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    26/72

    CIVIL446 Engineering Design and Analysis II

    4.5 Analysis & Design

    Having selected Composite Steel Girders with a Precast Deckas the structural system, detailed

    analysis and design was performed. The structure was designed for both vertical and lateral

    loading.

    4.5.1 Gravity Load Design

    4.5.1.1 Load Effects

    CSA S6 specifies several load effects for ULS, including Dead, Live, and Ice (accretion).

    The governing load case for gravity load design was found to be:

    The live load represents one or more 625kN trucks (or a portion thereof for smallercomponents) of a given length and wheelbase. Figure 11 and Figure 12below depict the

    CL-625 Truck.

    Because new Dunsmuir ramp is to be 9.9m wide, it classifies as having two design lanes

    (per CSA S6-06) and is thus subject to two simultaneous CL-625kN trucks; however, a

    modification factor of 0.9 applies when both design lanes are loaded. Finally, a dynamic

    load allowance of 25% in added to the full weight of the truck (up to 50% is added forsmall components such as deck joints under single wheel loads). Thus the total live load

    tributary to a single girder was taken as:

    D*D + L*L, where:D = 1.11.5 (depending on material and function)

    L = 1.7D = 9.5kPa (Structure self-weight + allowance for other components)L = CL-625 Truck Loadin as described below

    a)

    CIVIL446 E i i D i d A l i II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    27/72

    CIVIL446 Engineering Design and Analysis II

    This load was distributed as shown in Figure 13, added to the dead loads, and then

    multiplied by the appropriate load factors. Using this information, a moving load analysis

    for a single girder was performed in SAP2000 (see Figure 14). This required only a very

    simple model, while fully capturing the influence of the moving load and allowing for

    quick assessment of design changes.

    The results of these analyses were then used for design of the deck slab; the composite

    girders, and the pier supports as described in sections 4.5.1.2 to 4.5.2.2.

    2*(625kN/2)*0.9*1.25 = 703kN

    Dynamic Load AllowanceMulti-lane modifier

    Half to each girder

    Two Trucks

    = Truck #1 + Truck #2

    Single Design Girder

    Single Design Girder

    Figure 13: Design Girder Loading Figure 14: SAP2000 Load Analysis

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    28/72

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    29/72

    CIVIL446 Engineering Design and Analysis II

    One-way shear resistance was found to govern the slab design, because the span is so short.

    Punching shear and moment resistances were also calculated but did not govern; therefore,

    moment resistance and punching shear calculations are not shown. In order to determine

    the shear resistance, it was necessary to determine the effective width of the slab resistingthe point loads. The effective width was calculated as 1580mm (Westergaard).

    Resistances were calculated in accordance with CSA A23.3-04. See the referenced code

    clauses and commentary for calculation background information.

    Figure 16 shows the final design of the deck slab. Note the longitudinal bonded post

    tensioning and the headed shear reinforcing. The headed shear reinforcing was required

    due to the insufficient shear resistance of the concrete slab alone. The longitudinal P/T

    strands are required to tie the segments together, but are not used in strength calculations.

    One-Way Shear Check:

    Vr = Vc + Vs [CSA A23.3 Cl. 11] Cl 11.3.6.2 dv=0.9*d

    Vc = c***(fc)*bw*dv = (.65)*(1)*(.21)*(50MPa)*(1580mm)(150mm) = 229kNVs = s*Avs*Fyv*dv/s = (.85)*(3*127mm

    2)*(345MPa)*(150mm)/(75mm) = 223kN

    Vr = 229kN + 223kN = 452kN > 430kN OK!

    A A

    Section A-A

    Shear Stud Blockouts to

    provide composite action

    Longitudinal BondedPost Tensioning

    (One er Tooth)

    Head ShearReinforcing

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    30/72

    CIVIL446 Engineering Design and Analysis II

    4.5.1.3 Composite Girder Design

    The composite girders are comprised of: the structural steel wide flange section; the

    concrete deck slab, and the steel shear studs. The typical girders span approximately 32m

    between concrete piers (recall Figure 10). Figure 17 shows a detail section for a typical

    girder. It should be noted that the W690x548 section selected is a much stockier section

    than would normally be used; this is because of the limited allowable structural depth (see

    Section 3.1.4.4) and the need to provide a large area of steel.

    Factored load effects (listed below) were determined based on the moving load analysis

    performed in SAP2000. The values were also validated using simple hand calculations.

    The strength design was performed in accordance with CSA S16-09, using a formatted

    spreadsheet (See Appendix B), which helped to optimize the design. Resistances were

    calculated for the moment, vertical shear (of the web), and horizontal shear (of the shear

    studs). The final design parameters and resistances were determined as follows:

    200mm Concrete

    Deck Slab

    Typical Girder

    10mm Stiffeners @ Points

    to Prevent Web Crippling

    L76x76 x13 Bracing @

    Points for Stability

    2-25mm Nelson

    Studs Each BlockoutLow Shrinkage

    Concrete Encasing

    Factored Load Effects:

    Mf= 8849kNm

    Vf= 1163kN

    Final Design Parameters & Resistances:

    fc = 50MPa

    Shear Transfer = 40% (Min for Strength)

    Stud Spacing = 2-25mm @ 1200o/c

    Mr = 9108kNm > 8849kN OK!

    Vr,v = 4402kN > 1162kN OK!

    Vr,h = 8916kN > 8807kN OK!

    Figure 17: Typical Girder

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    31/72

    g g g y

    4.5.1.4 Pier Arm Design

    The pier arms are to be constructed of reinforced concrete, and have a tapered section to

    more efficiently meet moment and shear demands, while reduced dead loads. The

    reduction in dead load is particularly beneficial in reducing the rotational mass of the pier

    arms under seismic loading. Figure 18 shows an elevation of the pier arms:

    Based on the load analysis in SAP2000, the factored load

    transmitted by a typical girder is 2278kN. The outer girders

    transmit half this load (1139kN) because they have half the

    tributary area. Thus the factored load effects are:

    Resistances were calculated per CSA A23.3 as follows:

    10-45M To for M-

    10-20M Skin

    Reinf. For

    Crack Control

    Nominal Reinf. for

    Bar Support and

    Creep Control

    Tapered Section to

    Reduce Dead LoadsPier Reinforcing

    (See Section 3.5.2)

    20M Stirrups

    @ 600o/c

    Pf/2Pf Pf Pf Pf

    Pf/2

    Critical Section for

    Shear (35)

    Critical Section forFlexure

    Factored Load Effects:

    Mf= 1139kN*(3.6m)+2278kN*(1.8m) = 8200kNm

    Vf= 1139kN + 2278kN = 3417kN

    Final Design Parameters & Resistances:

    fc = 50MPa 10-45M 400MPa Steel

    Mr = s*As*fy*(d-a/2) = (.85)*(15000)*(400)*(2247-167/2) = 11,034kNm > 8849kN OK!

    Figure 18: Elevation View of Pier Arms

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    32/72

    4.5.2 Lateral Load Design

    4.5.2.1 Load Effects

    CSA S6 specifies several lateral loads including wind, collision, and earthquake loads.

    Earthquake loading was found to govern, given Vancouvers high seismic hazard. The

    governing load combination was as follows:

    Earthquake loading per CSA S6 is based on a peak ground acceleration with a 10% in 50-

    Years probability of exceedance (475 year event). This is similar to past editions of the

    National Building Code (eg. NBCC 1995). The specified base shear for the structure is as

    follows:

    4.5.2.2 Pier Column Design

    The pier column is to be constructed of reinforced concrete and have a rectangular section;

    the strong axis is set perpendicular to the roadway, since the piers must act solely as

    cantilevered columns in this direction. Figure 19 (next page) shows an elevation of the

    pier. For the aforementioned load combination, the factored load effects are as follows:

    D*D + 1.0*E, where:D = 0.8 or 1.25 (whichever produces the more critical effect)D = 9.5kPa (Structure self-weight + allowance for other components)

    E = Specified Earthquake Lateral Load (a base shear, as described below)

    Code Specified Base Shear:V = 2.5*A*I *W/R

    A = 0.2g (CSA S6-06 Zonal Acceleration for Vancouver)

    I = 1.5 (Importance Factor for Emergency Response Routes)

    W = 1.25*D = 1.25*(9.5kPa)*(9.9m*32m) = 3762kN

    R = 2.0 (Ductility Factor for a Single Column)

    Factored Load Effects:

    Nf= W = 3762kNkN

    Vf= 1410kN

    Mf= (1410kN)*(12m) = 16,920kNm

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    33/72

    Figure 19: Elevation View of Pier

    The column section was designed and detailed to resist the aforementioned seismic

    loading. Of particular note, are the closely space ties at the top and bottom of the column

    Seismic Load V = 1410kN

    (Applied in Either Direction)

    Base Overturning Moment = 16,920kNm

    (Based on Max. Design Height = 12m)

    Equivalent Static

    Seismic Force

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    34/72

    4.5.2.3 Foundation Design

    Because the geotechnical discipline was not selected for detailed design, foundation design

    was not in the design scope. However, it should be noted that due to the significant

    vertical and lateral loads, that deep foundations such as piles would likely be required.

    4.5.3 Design Summary

    The following is a summary of the structural design and rationale.

    Table 6: Design Summary

    Design Item Description Rationale/Comments

    Structural

    System

    Composite Girders with Precast

    Segmental Deck Slab

    This system best met the 3 primary

    design objectives: Constructability,Structural Depth, and Durability

    Gravity

    Load

    Gov. Load Case: D*D + L*LD = 9.5kPa

    L = CL-625kN Moving Trucks

    Moving load analysis performed for

    typical girder. Various load patterns

    considered

    Nf=3762kN, Mf=16920kNm OK!

    Figure 20: N-M Interaction Diagram

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    35/72

    5. Construction Management

    The following sections describe the detailed design for the construction management discipline.

    5.1 Design Scope

    The design scope for the Construction Management portion of the project included cost

    estimating, construction sequencing, crane loading considerations, safety resources, and bylaw

    research. These items were completed under the scope that they would include the construction

    of the Dunsmuir on-ramp and Georgia off-ramp as well as the demolition of the whole Georgia

    Viaduct and part of the Dunsmuir Viaduct. Concrete works were the focus of the cost estimate

    and construction sequencing and items such as project overhead or soil remediation were notincluded.

    5.2 Cost Estimate

    A cost estimate was prepared using data from RS Means (Waier, 2009). A sample cost estimate

    is shown in Figure 21 which outlines the costs for the removal of steel guardrails, the removal of

    the viaduct concrete, and the ground remediation following demolition. The full cost estimate is

    found in Appendix C.

    Construction Activity Crew

    Daily

    Output Base Unit Days

    Cost of Crew

    per Day Labour Cost

    Remove steel guardrails B-80A 30.5 m per day 24.60 $758.40 $18,655

    Grind/chip away at centre of spans Two B-9 7.08 m3 per day 211.89 $3,678.50 $779,430

    Remove Piers Two B-9 8.50 m3 per day 94.17 $4,414.20 $415,696

    Remediate ground where piers were loca ted

    and where equipment damaged land B-37 929 m2

    per day 0.11 $1,592.40 $171

    Labour

    Ma te ri al s Ba se U ni t Amo un t

    Cost per

    Unit

    Materials

    Cost Equipment Rental Time

    Equipment

    Cost RS Means Ref Notes/Totals

    m 750 $0.00 $0

    Crane enabled flat-bed truck,

    grinder, steel cutter 5 weeks $5,978 02 41 13.33-0800

    m3 1500 $0.00 $0

    Crane, Air compressor, 2 Breakers,

    2 50' Ai r Hos es , Wa te r Mis ter 4 3 we eks $405,766 02 41 19.16-1050

    Assuming avg 0.3 m thick

    freespans

    m3 800 $0.00 $0

    Crane, Air compressor, 2 Breakers,

    2 50' Ai r Hos es , Wa te r Mis ter 1 9 we eks $216,408 02 41 19.16-1050

    Fill m2 100 $2.69 $269 1 tandem roller, 5 ton 1 day $11 31 23 23.17-0500

    Assume average 4" depth

    improvements

    Materials Equipment

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    36/72

    was the most important aspect of determining costs and durations for each activity. For the steel

    guardrail, Google Earth was used to measure the length of the guardrail on the Georgia Viaduct.

    For span grinding/chipping, section 02 41 19.16-1050 was used. The average depth was assumed

    to be 0.3 m and the area to be removed was measured using Google Earth. Specific equipment

    needs were taken from the RS Means data and judgment was applied to determine whether or not

    the specific data set matched the viaduct removal project. It was assumed that the crews working

    on the viaduct demolition could work 1.5 times faster than what was suggested in RS Means, so

    that data was adjusted accordingly.

    A list of cost items considered is as follows: Public information campaign to notify travelers of

    road closures, equipment storage area ground improvement, hauling, equipment procurement,

    ground improvement where heavy machinery will operate, removal of lamp-posts and electrical

    circuitry, removal of steel guardrails, grinding/chipping away at center spans of viaduct,

    removing piers of viaduct, remediating ground where piers were located, tree removal, re-

    grading of soils, layout surveys, abutment footing construction, abutment engineered fill

    placement, abutment wall construction, pier footing formwork, pier footing rebar, pier footing

    concrete, pier column formwork, pier column rebar, pier column concrete, tilt-up column

    activities, steel beam placement, concrete connection pour, shear stud blockout placement, deck

    placement, utility placement, and commissioning.

    These data were tabulated in 7 sections corresponding to overall portions of the project. A

    summary of component costs is given in Table 7.Table 7: Summary of Cost Estimate

    Labour Materials Equipment Total

    Pre-Construction Activities $30,242 $24,672 $16,973 $71,887

    Georgia Viaduct Demolition Pt 1 $1,237,546 $24,748 $637,495 $1,899,789

    Dunsmuir On-Ramp Const. $255,142 $2,083,387 $161,148 $2,499,677

    Dunsmuir Viaduct Partial Demo. $1,561,189 $27,169 $823,357 $2,411,715

    Dunsmuir Greenway Chg-Ovr Not in Scope

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    37/72

    The data obtained from RS Means was generic data that covered average costs across North

    America. Therefore, it had to be changed to represent Vancouver in 2013. To change from the

    North America average to the Vancouver average, the costs were multiplied by a factor of

    110.5/100. To change from 2009 to 2013, an average yearly inflation factor was calculated byexamining construction cost index increases from 1993 to 2009. This factor was determined to

    be 1.039, and the 2013 cost was calculated using a factor of 1.0394. Following these changes, the

    total construction cost was estimated as $17,181,206.

    5.3 Construction Sequence

    Following the detailed cost estimate, a construction sequence was put together. The activities

    corresponded to the activities in the cost estimate, and the calculated durations from the costestimate were used. Microsoft Project was used as a tool to put the activities into a logical order.

    The project was assumed to start in November of 2012 with pre-construction activities and then

    in January 2013 for actual demolition and construction.

    There were six major divisions in the sequence, illustrated in Figure 22below.

    1. Pre-construction activities

    2. Georgia Viaduct demolition,3. Dunsmuir Viaduct demolition

    4. Dunsmuir on-ramp construction

    5. Georgia off-ramp construction

    6. Dunsmuir Greenway change-over*

    5

    6

    3

    4

    1 Various Locations

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    38/72

    *Note: The greenway was not considered part of the scope, but it was noted as a part of the

    construction sequence.

    It was important to understand finish start relationships in the determination of the project

    critical path. The Georgia Viaduct demolition was split into two phases to better take advantageof co-existing construction activities. Part 1 of this demolition is used as an example for this

    report (Figure 23).

    Figure 23: Construction Sequence Example

    The beginning of the demolition was preceded by the closure of the viaduct itself as well as

    Griffiths Way below the structure. Once the streets were closed, physical work could begin on

    ground improvement for machinery to operate on. This involved hauling materials to and from

    the site, so these activities overlap. The removal of steel guardrails could only start once the

    electrical circuitry and lamp-posts were removed, so it had a finish-start relationship. The same

    concept applied for the grinding/chipping away of the concrete mid-spans and pier removal

    respectively. Finally, the ground could be remediated where the piers had been removed. Using

    duration data from the detailed cost estimate and the path logically determined, a length of 335

    days was found for this portion of the project.

    The same process was followed for the other 5 project sections and an overall project length of

    891 days resulted (note that these are work days and could be changed to include weekends if the

    project needs to be fast-tracked). A summary of the section dates follows in

    Critical Path (partial)

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    39/72

    Table 8: Summary of Construction Sequence

    Start Date Finish Date

    Pre-Construction Activities 1 November 2012 1 January 2013

    Georgia Viaduct Demolition Part 1 2 January 2013 16 April 2014

    Dunsmuir On-Ramp Construction 2 January 2013 25 July 2013

    Dunsmuir Viaduct Partial Demolition 25 July 2013 26 March 2015

    Dunsmuir Greenway Change-Over 25 July 2013 12 December 2013

    Georgia Off-Ramp Construction 16 April 2014 19 March 2015

    Georgia Viaduct Demolition Part 2 16 April 2014 1 April 2016

    The critical path of the project was determined using Microsoft Project and included all of the

    activities involved in pre-construction and both Georgia Viaduct demolition parts.

    5.4 Crane Loading

    Note: The evaluation and analyses from this section have been adapted fromCranes & Derricks

    (Shapiro, 2000) to suit the viaducts redevelopment project requirements.

    The construction of all major infrastructure projects requires that material and components be

    physically moved during demolition, staging, and final assembly. For this reason, equipment

    must be chosen to efficiently lift, translate, hold, and lower many different magnitudes and types

    of loads. Conventional lifting equipment readily available in the Vancouver area includes tower

    jib cranes, overhead gantry cranes, and mobile cranes. Each of these types has operational

    advantages and disadvantages based on the required task as illustrated in Table 9.

    Table 9: Crane Comparison

    Crane Type Mobility Lifting Capacity Space Required

    Tower/Jib Low High Low

    Overhead Gantry Moderate Very High High

    Mobile High Moderate Low

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    40/72

    Investigating the specific project needs shows the major loads as follows:

    Demolition components and rubble

    On-ramp pre-cast concrete tilt-up piers

    On-ramp steel girders

    On-ramp pre-cast concrete slab decking

    Construction materials & equipment

    Selection of a suitable crane must first begin with an investigation of the expected loads during

    construction. In particular, the current load scenario must always be pre-determined prior to

    performing the actual lift; this will ensure the crane is not underpowered and prevent equipment

    damage or injury. For this reason, the careful engineer will investigate the maximum expected

    load case and then specify the appropriate crane.

    By examining the list of major loads, it can be seen that not only do the loads vary in size and

    shape, but also the site location where they will be required. For example, demolition of the

    Georgia Viaduct takes place over a distance of approximately 1.0 km. In addition the heaviest

    load (concrete slab decking) is expected to be:

    Finally, it must be noted that the aerial maps and site visit conducted by our group on February

    29th, 2012 indicated that there is very limited space to work and stage materials.At the recommendation of Darryl Matson, P. Eng, the VP of Buckland & Taylor Ltd., the

    appropriate crane was selected from the Burnaby-based GWIL Crane Service Company. Initially

    a tower crane with lattice boom was contemplated; however, the mobility and functionality, in

    addition to the simple site set-up made the mobile truck-based crane the best choice. The lifting

    charts from the 120-Ton Krupp Model 100GMT specify the acceptable load limits under specific

    configurations. Table 10 is an excerpt from the full lifting chart and gives the maximum load

    rating in 1000s of lbs. In addition the specified loads are reduced to less than 85% of the tippingload. It is also important to note that these capacities reflect the mobile crane with the outriggers

    fully extended.

    Where = uni t area slab weight, l=segment l ength and w=roadway width.

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    41/72

    Table 10: 120-Ton Krupp Model 100 GMT: Lifting Chart

    In summary, the 120-Ton Krupp Model 100 GMT is a suitable crane for lifting the 320kN

    concrete deck to a maximum height of 77 feet, given:

    A minimum 65-ton rated hook is used;

    The outriggers are fully extended (247 span)

    No excessive lateral loads are applied

    These constraints can easily be managed during the construction project and will not

    significantly alter the crane performance.

    84,000lb (374kN) @ 30ft. Radius

    (Maximum hook height of 77 ft.)

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    42/72

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    43/72

    CIVIL446 Engineering Design and Analysis II

    ddi i ifi Ci f b l h d i l h i b l

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    44/72

    In addition, specific City of Vancouver bylaws were researched. In particular, the noise bylaw

    regulation will apply to the construction project.

    Noise Bylaw (No. 6555) (City of Vancouver, 2010)

    Construction on private property must be carried out between 7:30 am and 8 pm on any

    weekday that is not a holiday, and between 10 am to 8 pm on any Saturday that is not a

    holiday. Construction is not permitted on Sundays.

    Street construction must be carried out between 7 am and 8 pm on any weekday or

    Saturday, and between 10 am and 8 pm on any Sunday or holiday.

    The collection of refuse must only occur:- outside the downtown area from 7 am to 8 pm on any weekday, or from 10 am to

    8 pm on any Saturday, Sunday, or holiday.

    - within the downtown area from 6 am to 12 midnight on any weekday, or from 10

    am to 12 midnight on any Saturday, Sunday, or holiday.

    Each of the aforementioned standards will be followed during the construction project.

    CIVIL446 Engineering Design and Analysis II

    6 E i A l i

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    45/72

    6. Economic Analysis

    6.1 Direct Project Costs

    Our cost estimate is $17,000,000 (see section 5.2) equating to approximately 20% of the totalexpected cost (~$100M). Thus, to make a just comparison in the cost-benefit analysis, the

    benefits and negative impacts will be scaled to 20% of their total calculated value.

    6.2 User Benefits

    Property value increase

    Property values along False Creek using VanMap from the City of Vancouver (City of

    Vancouver, 2011).

    88 Pacific Blvd $400,000 Concord Pacific 412,000 ft2

    10 Pacific Blvd $13,000,000 Next to Concord Pacific 103,000 ft2

    750 Pacific Blvd $9,000,000 Plaza of Nations 624,000 ft2

    The value of the land will significantly increase with the removal of the viaduct. The value couldpossibly increase by $30,000,000 based on neighboring property values per square foot.

    Tour ism & commerce benefi ts of marketplace and sur rounding area

    Assuming the foreshore area could be developed into an active small business market and

    cultural hub, the potential exists to encourage tourism of a similar nature to Granville Island. The

    development at Granville Island has been incredibly successful, generating approximately $130million in economic activity value each year (CMHC, 2012). The foreshore and parking lots

    south of the existing Georgia viaduct represent an area of 22 acres, roughly 58% of the size of

    Granville Island (38 acres). Following the reasoning that a similar proposal was created in the

    foreshore area it would thus have the potential of generating upwards of 1500 jobs and $75

    million in economic value annually. However, this figure should be reduced significantly to

    reflect reduced productivity compared to Granville Island. Therefore, a value of $50,000,000 was

    used for the expected tourism benefit over the lifespan of the area.

    Opening ci ty owned properti es to sell

    A primary motivation for removing the viaducts is the potential revenue generated through the

    l f i d l d A i l 10 f i d l d i b l h

    CIVIL446 Engineering Design and Analysis II

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    46/72

    6.3 Negative Impacts

    Road closures

    The economic impacts of road closures during construction is an important consideration in the

    cost benefit analysis. Road closures create economic losses by delaying shipping, reducing local

    commerce, and increasing road user travel time. Based on a survey of recent estimates, the

    economic losses associated with a road closure can be expected to range between $100,000 and

    $500,000 per month; since there is no city transit currently using the viaducts, and limited local

    commerce, the economic losses can be expected to fall in the lower range. Assuming losses of

    $200,000/month and a total downtime (for all roads collectively at any given time) of 15%, thecost of the 39-month project is estimated at approximately $1.2M.

    Park space reduction duri ng construction

    From an economical point of view, parks stimulate development and investment, increase land

    values and enhance tourist attraction. Destruction of green spaces whether temporary or

    permanent - imposes a negative benefit to the project which has to be taken in account ineconomic viability studies. Figure 25 shows the areas that will be either destroyed or inaccessible

    during construction in this project. The total area of these green spaces is about 14000 square

    meters (150000 square foot). The economic loss in terms of green space in Vancouver area is

    estimated to be around 20 dollars per square meter per year. That is, $1,400,000 economic loss

    over the length of the construction project (3 years).

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    47/72

    CIVIL446 Engineering Design and Analysis II

    7 Conclusion

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    48/72

    7. Conclusion

    7.1 Design Goals & Achievements

    The following section summarizes how each time achieved its design goals.

    7.1.1 Transportation

    Table 13: Transportation Design Achievements

    Design GoalMet

    Objectives?Methods Achieved

    Dunsmuir On-ramp

    Location Placed to minimize land disturbance and costOn-ramp Roadway

    Geometry Designed following TAC and MoT guidelines

    Minimize Impacts on

    Traffic Flow Traffic planning during construction

    Traffic planning after construction

    7.1.2 StructuresStructural designers met the design objectives through careful selection of structural

    system, and creative design solutions. The table below outlines the achievements.

    Table 14: Structural Design Achievements

    Design GoalMet

    Objectives?Methods Achieved

    Speed of Construction Precast deck slab allows for prefabrication

    Tilt-up concrete piers limits the need for

    formwork

    Minimize Structural

    Depth Composite girders reduces girder depth

    Headed shear reinforcing reduces slab depth

    Durability Post-tensioning reduces cracking Precast concrete less vulnerable to deterioration

    CIVIL446 Engineering Design and Analysis II

    7.1.3 Cons truc tion Managemen t

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    49/72

    7.1.3 Cons truc tion Managemen t

    Table 15: Construction Management Design Achievements

    Design Goal MetObjectives?

    Methods Achieved

    Detailed Cost

    Estimate RS Means data used to estimate construction

    related activities

    Construction

    Sequencing

    Microsoft Project used to produce Gantt Chart for

    project activities

    Gantt Chart used to determine critical path

    Crane Selectionand Loading

    Chose an appropriate method of lifting usingmobile cranes. (Krupp GMT100)

    Safety

    Considerations

    & Bylaw

    Research

    Worksafe BC used to outline key safety

    considerations

    City of Vancouver Bylaws researched to determine

    construction methods

    7.2 Closure

    Coalition Engineering (Group 15) has completed its scope of services for the Vancouver

    Viaducts Redevelopment project. We trust that this report meets the requirements set forth for

    CIVL 446. Should you have any questions or comments, please feel free to contact the design

    team, as noted below.

    Sincerely,

    Brandon Paxton (44770089)

    Curtis Saunders (92191071)

    Derek Rempel (35255090)

    Dernanto Mirwan (70846084)

    Navid Shakibi (56175086)Matthew Ridley (36007102)

    CIVIL446 Engineering Design and Analysis II

    8. Bibliography

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    50/72

    8. Bibliography

    City of Seattle. (2008). Case Studies of Freeway Removal. Seattle: City of Seattle.

    City of Vancouver. (2010, May 5). Sound Smart. Retrieved February 1, 2012, from City ofVancouver: http://vancouver.ca/engsvcs/projects/soundsmart/bylaws.htm

    City of Vancouver. (2011, August 8). VanMap. Retrieved April 2, 2012, from City ofVancouver: http://vanmapp.vancouver.ca/pubvanmap_net/default.aspx

    CMHC. (2012). Granville Island. Retrieved from Canada Mortgage Housing Corp.:http://www.cmhc-schl.gc.ca/en/corp/about/about_001.cfm

    Halcrow Consulting Inc. (2011). Vancouver Georgia and Dunsmuir Viaduct Study. Vancouver:

    City of Vancouver.

    Jett. (2011, November 19). Sneek Bridge. Retrieved February 24, 2012, from Arch Daily:http://www.archdaily.com/184653/sneek-bridge-achterbosch-architectuur-with-onix/

    Shapiro. (2000). Cranes and Derricks (3rd ed.). New York: McGraw-Hill.

    Unterwieser. (2007). From the Fabrication to the maintenance - a report of hte history of theMur River Wooden Bridge in Styria/Austria. Graz University of Technology. Graz,

    Austria: 5th International Conference of Arch Bridges.Waier, P. R. (2009).RS Means Building Construction Cost Data.

    Westergaard. (n.d.). Effective Width. Retrieved March 30, 2012, from StructuralPedia:http://structuralpedia.com/index.php?title=Effective_Width

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    51/72

    APPENDIX A:

    TRANSPORTATIONDISCIPLINE

    CONTENTS:

    VERTICALALIGNMENT CALCULATIONS (5PAGES)

    Vertical Alignment Calculations For Dunsmuir Viaduct On-Ramp

    CIVL 446 Design Project

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    52/72

    CIVL 446 Design Project

    Designer: Matt Ridley

    January - April 2012

    Critical Elevations for Design:m ft

    ramp start 0 0

    skytrain track 7.620 25

    viaduct 12.497 41

    Critical Stations for Design:

    Station X (m)Required

    Elev. (m)

    0+065.610 5.00*

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    53/72

    76 0.1 8.100 77 7.700 6.728

    77 0.1 8.200 78 7.800 6.828

    78 0 1 8 300 79 7 900 6 928

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    54/72

    78 0.1 8.300 79 7.900 6.928

    79 0.1 8.400 80 8.000 7.028

    80 0.1 8.500 81 8.100 7.128

    81 0.1 8.600 82 8.200 7.228

    82 0.1 8.700 83 8.300 7.328

    83 0.1 8.800 84 8.400 7.428

    84 0.1 8.900 85 8.500 7.528

    85 0.1 9.000 86 8.600 7.628

    86 0.1 9.100 87 8.700 7.728

    87 0.1 9.200 88 8.800 7.828

    88 0.1 9.300 89 8.900 7.928

    89 0.1 9.400 90 9.000 8.028

    90 0.1 9.500 91 9.100 8.128

    91 0.1 9.600 92 9.200 8.228

    92 0.1 9.700 93 9.300 8.328

    93 0.1 9.800 94 9.400 8.428

    94 0.1 9.900 95 9.500 8.528

    95 0.1 10.000 96.51 9.651 8.679

    96 0.1 10.100 97 9.700 8.728

    97 0.1 10.200 98 9.800 8.828

    98 0.1 10.300 99 9.900 8.928

    99 0.1 10.400 100 10.000 9.028

    100 0.1 10.500 101 10.100 9.128

    101 0.1 10.600 102 10.200 9.228102 0.1 10.700 103 10.300 9.328

    103 0.1 10.800 104 10.400 9.428

    104 0.1 10.953 105 10.500 9.528

    105 0.1 11.000 106 10.600 9.628

    106 0.1 11.100 107.46 10.746 BVCS 9.774

    107 0.1 11.200 108 10.800 9.828

    108 0.1 11.300 109 10.898 Vertical Curve Parameters 9.926

    109 0.1 11.400 110 10.995 g1: 0.1 10.023

    110.53 0.1 11.500 111 11.091 a: -0.00071 10.119

    111 0.1 11.600 112 11.185 g2: -0.0499 10.213112 0.1 11.700 113 11.278 A: 0.1499 10.306

    113 0.1 11.800 114 11.369 k: 7 10.397

    114 0.1 11.900 115 11.459 10.487

    115 0.1 12.000 116 11.548 10.576

    116 0.1 12.100 117 11.635 10.663

    117 0.1 12.200 118 11.721 10.749

    118 0.1 12.300 119 11.805 10.833

    119 0.1 12.400 120 11.888 10.916

    120 0.1 12.500 121 11.969 10.997

    121 0.1 12.600 122 12.049 11.077122 0.1 12.700 123 12.128 11.156

    123 0.1 12.800 124 12.205 11.233

    124 0.1 12.900 125 12.280 11.308

    125 0.1 13.000 126 12.354 11.382

    skytrain

    131 0.1 13.600 132 12.770 4.178 11.620 7.620 11.798

    132 0.1 13.700 133 12.834 4.242 11.620 7.620 11.862

    133 0 1 13 800 134 12 897 4 305 11 620 7 620 11 925

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    55/72

    133 0.1 13.800 134 12.897 4.305 11.620 7.620 11.925

    134 0.1 13.900 135 12.958 4.366 11.620 7.620 11.986

    135 0.1 14.000 136 13.018 4.426 11.620 7.620 12.046

    136 0.1 14.100 137 13.077 4.485 11.620 7.620 12.105

    137 0.1 14.200 138 13.134 4.542 11.620 7.620 12.162

    138 0.1 14.300 139 13.189 4.597 11.620 7.620 12.217

    139 0.1 14.414 140 13.244 4.652 11.620 7.620 12.272

    140 0.1 14.500 141 13.296 4.704 11.620 7.620 12.324

    141 0.1 14.600 142 13.348 4.756 11.620 7.620 12.376

    142 0.1 14.700 143 13.398 4.806 11.620 7.620 12.426

    143 0.1 14.800 144 13.446 4.854 11.620 7.620 12.474

    144 0.1 14.900 145 13.493 4.901 11.620 7.620 12.521

    145.14 0.1 15.000 146 13.539 4.947 11.620 7.620 12.567

    146 0.1 15.100 147 13.583 4.991 11.620 7.620 12.611

    147 0.1 15.200 148 13.626 5.034 11.620 7.620 12.654

    148 0.1 15.300 149 13.667 5.075 11.620 7.620 12.695

    149 0.1 15.400 150 13.707 5.115 11.620 7.620 12.735

    150 0.1 15.500 151 13.746 5.154 11.620 7.620 12.774

    151 0.1 15.600 152 13.783 5.191 11.620 7.620 12.811

    152 0.1 15.700 153 13.819 5.227 11.620 7.620 12.847

    153 0.1 15.800 154 13.853 5.261 11.620 7.620 12.881

    154 0.1 15.900 155 13.886 5.294 11.620 7.620 12.914

    155 0.1 16.000 156 13.917 5.325 11.620 7.620 12.945

    156 0.1 16.100 157 13.947 5.355 11.620 7.620 12.975157 0.1 16.200 158 13.976 5.384 11.620 7.620 13.004

    158 0.1 16.300 159 14.003 5.411 11.620 7.620 13.031

    159 0.1 16.400 160 14.028 5.436 11.620 7.620 13.056

    160 0.1 16.563 161 14.052 5.460 11.620 7.620 13.080

    161 0.1 16.600 162 14.075 5.483 11.620 7.620 13.103

    162 0.1 16.700 163 14.097 5.505 11.620 7.620 13.125

    163 0.1 16.800 164 14.117 5.525 11.620 7.620 13.145

    164 0.1 16.900 165 14.135 5.543 11.620 7.620 13.163

    165 0.1 17.000 166 14.152 5.560 11.620 7.620 13.180

    166.63 0.1 17.100 167 14.168 13.196167 0.1 17.200 168 14.182 13.210

    168 0.1 17.300 169 14.195 13.223

    169 0.1 17.400 170 14.206 13.234

    170 0.1 17.500 171 14.216 13.244

    171 0.1 17.600 172 14.225 13.253

    172 0.1 17.754 173 14.232 13.260

    173 0.1 17.800 174 14.237 13.265

    174 0.1 17.900 175 14.242 13.270

    175 0.1 18.000 176 14.244 13.272

    176 0.1 18.100 177 14.246 13.274177 0.1 18.200 178 14.246 13.274

    178.54 0.1 18.300 179 14.244viaduct

    road (m)

    viaduct

    bottom (m)13.272

    179 0.1 18.400 180 14.241 12.497 11.297 13.269

    191 0.1 19.600 192 14.095 12.497 11.297 13.123

    192 0.1 19.700 193 14.074 12.497 11.297 13.102

    193 0.1 19.810 194 14.051 12.497 11.297 13.079

  • 7/27/2019 CIVL446 - Report - April4 [Ready for Printing].pdf

    56/72

    193 0.1 19.810 194 14.051 12.497 11.297 13.079

    194 0.1 19.900 195 14.026 12.497 11.297 13.054

    195 0.1 20.000 196 14.000 12.497 11.297 13.028

    196 0.1 20.100 197 13.973 12.497 11.297 13.001

    197 0.1 20.200 198 13.945 12.497 11.297 12.973

    198 0.1 20.300 199 13.915 12.497 11.297 12.943

    199.1 0.1 20.400 200 13.883 12.497 11.297 12.911

    200 0.1 20.500 201 13.850 12.497 11.297 12.878

    201 0.1 20.600 202 13.816 12.497 11.297 12.844

    202 0.1 20.700 203 13.780 12.497 11.297 12.808

    203 0.1 20.800 204 13.743 12.497 11.297 12.771

    204 0.1 20.900 205 13.704 12.497 11.297 12.732

    205 0.1 21.000 206 13.664 12.497 11.297 12.692

    206 0.1 21.100 207 13.623 12.497 11.297 12.651

    207 0.1 21.200 208 13.580 12.497 11.297 12.608

    208 0.1 21.300 209 13.535 12.497 11.297 12.563

    209 0.1 21.400 210 13.490 12.497 11.297 12.518

    210 0.1 21.500 211 13.442 12.497 11.297 12.470

    211 0.1 21.600 212.39 13.374 EVCS 12.497 11.297 12.402

    212 0.1 21.700 213 13.344 12.497 11.297 12.372

    213 0.1 21.800 214 13.294 12.497 11.297 12.322

    214 0.1 21.900 215 13.244 12.497 11.297 12.272

    215 0.1 22.000 216 13.194 12.497 11.297 12.222

    216 0.1 22.100 217 13.144 12.497 11.297 12.172217 0.1 22.200 218 13.095 12.497 11.297 12.123

    218 0.1 22.300 219 13.045 12.497 11.297 12.073

    219 0.1 22.400 220 12.995 12.497 11.297 12.023

    220 0.1 22.500 220.02 12.994 BVCS 12.497 11.297 12.022

    221 0.1 22.600 221 12.946 12.497 11.297 11.974

    222 0.1 22.700 222 12.900 Vertical Curve Parameters 12.497 11.297 11.928

    223 0.1 22.800 223 12.856 g1: