cladding& fitting
TRANSCRIPT
-
8/7/2019 cladding& fitting
1/56
FLEXIBLE CLOSED CELL
PIPE COVERING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
2/56
FIELD AND FACTORY-APPLIED
NON-METAL JACKETING
1 PRE-FORMED PIPE INSULATION2 VAPOUR BARRIER ADHESIVE
(NOT REQUIRED WITH SELF-SEAL LAP)3 STAPLES COATES WITH VAPOUR BARRIER COATING
(NOT REQUIRED WITH SELF-SEAL LAP)4 INSULATION FASTENING
(NOT REQUIRED WITH FACTORY APPLIED JACKET)
5 BUTT STRIP SECURED WITH VAPOUR BARRIER ADHESIVE OR SESEAL
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
3/56
FIELD-APPLIED
METAL JACKET
1 PRE-FORMED PIPE INSULATION2 INSULATION FASTENING3 JACKET OVERLAPPED (POSITION TO SHED WATER)4 JACKET FASTENING OR5 JACKET FASTENING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
4/56
STANDARD SPLIT RING
HANGERS
1 PRE-FORMED PIPE INSULATION
2 INSULATION FACTORY JACKET
3 BUTT STRIP
4 INSULATION NEATLY UT TO ACCOMMODATE
HANGER
5 INSULATION ON HANGER ROD
M.W.BARVE LECTURE NOTES
file:///C|/Documents%20and%20Settings/Administrator/Desktop/INSULATION%20&%20CLADDING%20-figers.pdf
-
8/7/2019 cladding& fitting
5/56
CLEVIS HANGER
HIGH DENSITY INSERTS
1 PRE-FORMED PIPE INSULATION2 HINGH DENSITY INSULATION
(EXTEND 50mm BEYOND ENDS OF SHIELD)3 FACTORY APPLIED VAPOUR BARRIER
4 FINISH JACKET (METAL SHOWN)5 METAL SHIELD (SUPPLIED BY OTHERS)
M.W.BARVE LECTURE NOTES
file:///C|/Documents%20and%20Settings/Administrator/Desktop/INSULATION%20&%20CLADDING%20-figers.pdf
-
8/7/2019 cladding& fitting
6/56
PIPE SHOE
ON ROLLER SUPPORT
1 PRE-FORMED PIPE INSULATION2 INSULATION FASTENING IF NOT FACTORY
JACKET3 FINISH JACKET (METAL SHOWN)4 PIPE SHOE SUPPLIED AND INSTALLED BY
OTHERS5 INSULATION IN PIPE SHOE CAVITY
M.W.BARVE LECTURE NOTES
file:///C|/Documents%20and%20Settings/Administrator/Desktop/INSULATION%20&%20CLADDING%20-figers.pdf
-
8/7/2019 cladding& fitting
7/56
TRACED PIPING
1. TUBING TRACER (BY OTHERS)2. PRE-FORMED PIPE INSULATION (FACTORY JACKET)3. HEAT TRANSFER COMPOUND (OPTIONAL)4. HEAT TRANSFER COMPOUND CHANNEL
(OPTIONAL)5. BANDING SECURING CHANNEL TO PIPE6. MULTIPLE TUBING TRACER (BY OTHERS)7. ELECTRIC CABLE OR TAPE TRACER (BY OTHERS)
M.W.BARVE LECTURE NOTES
file:///C|/Documents%20and%20Settings/Administrator/Desktop/INSULATION%20&%20CLADDING%20-figers.pdf
-
8/7/2019 cladding& fitting
8/56
-
8/7/2019 cladding& fitting
9/56
PRE-FORMED ELBOW INSULATION
1. PRE-FORMED PIPE INSULATION (SHOWN WITH METALJACKET)
2. PRE-FORMED FITTING COVER
3. BANDING OR SCRES TO SECURE FITTING COVER
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
10/56
MITRED INSULATION ELBOW
OVERSIZE APPLICATION
1. PRE-FORMED INSULATION2. MITRED SEGMENTS OF PIPE INSULATION3. FINISH JACKET4. WIRE OR BANDING5. FITTING COVER
(METAL CORE TYPE SHOWN)6. FASTENING (SCREWS OR POP REVETS)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
11/56
PVC / GLASS FIBRE ELBOW
INSULATION SYSTEM
1 PRE-FORMED PIPE INSULATION WITH FACTORY JACKET
2 COLLAR OF OVER-SIZED PIPE INSULATION
3 FLEXIBLE INSULATION INSERT
4 PVC FITTING COVER SECURED WITH SERRATED
FASTENERS
5 VAPOUR BARRIER END CAP
6 PVC FITTING COVER
7 VAPOUR BARRIER TAPE OR ADHESIVE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
12/56
FIELD OR FACTORY FABRICATED
VALVE INSULATION
1 PRE-FORMED PIPE INSULATION WITH METAL JACKET
2 COLLAR OF PIPE INSULATION SIZED TO CLEARFLANGES
3 COLLAR OF PIPE INSULATION SIZED TO CLEARVALVE BODY
4 COLLAR OF PIPE INSULATION SIZED TO COVERBONNET (OPTIONAL)
5 COVER OF RIGID INSULATION OF BONNETINSULATED
6 INSULATION ADHESIVE AT JOINTS7 FLEXIBLE INSULATION FILL (OPTIONAL)8 CAULKING ON OUTDOOR INSTALLATIONS
9 METAL JACKET MATERIAL COVER
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
13/56
PVC / GLASS FIBRE
VALVE INSULATION
1 PRE-FORMED PIPE INSULATION2 OVER-SIZED PIPE INSULATION COLLAR3 FLEXIBLE INSULATION INSERT4 PVC COVER (SEAM SECURED WITH SERRATED TACKS,
ADHESIVE OR TAPE)5 END COVER
6 CAULKING TO SEAL
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
14/56
IN-LINE FLANGE INSULATION
BUILT-UP AND BEVELLED
1 PRE-FORMED PIPE INSULATION WITH FACTORY JACKET2 PRE-FORMED PIPE INSULATION WITH METAL JACKET3 COLLAR OF OVER-SIZED PIPE INSULATION4 SLEEVE OF OVER-SIZED PIPE INSULATION5 FLEXIBLE INSULATION (OPTIONAL)6 FABRICATED COVER7 CAULKING8 PIPE INSULATION (BEVELLED)9 BARRIER COATING INDOORS / WEATHER COATING
OUTDOORS
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
15/56
-
8/7/2019 cladding& fitting
16/56
FLEXIBLE DUCT INSULATION
ON RECTANGULAR DUCTS INDOORS
1 FLEXIBLE DUCT INSULATION WITH VAPOUR BARRIER
2 JOINTS LAPPED AND STAPLED; SEAL WITH VAPOUR
BARRIER ADHESIVE OR VAPOUR BARRIERE TAPE
3 MECHANICAL FASTENERS
4 VAPOUR BARRIER TAPE ON BREAKS & PENETRATIONS
OF VAPOUR BARRIER
2* & 4* VAPOUR BARRIER TAPE OR SEAL NOT REQUIRED ON
HOT DUCTS
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
17/56
RIGID DUCT INSULATION ON RECTANGULAR
EXPOSED DUCTS INDOORS
1 RIGID DUCT INSULATION
2 MECHANICAL FASTENERS
3 VAPOUR BARRIER TAPE ON JOINTS, BREAKS AND
PENETRATIONS
4 CANVAS FINISH JACKET APPLIED WITH LAGGING
ADHESIVE
5 METAL CORNER BEAD
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
18/56
HIGH TEMPERATURE
BLOCK OR BOARD
INSULATION
BREECHINGS,
FLUES AND KITCHEN
EXHAUST DUCTS
1 RIGID BLOCK INSULATION (JOINTS STAGGERED)2 METAL MESH OVER STIFFENERS (BY OTHERS)3 STIFFENER OR FLANGED CONNECTION4 MECHANICAL FASTENERS OR BANDING TO SECURE
INSULATION5 METAL JACKET FINISH
6 RIGID BOARD INSULATION7 METAL CORNER BEAD8 REINFORCEDMESH EMBEDDED IN INSULATION CEMENT
AND CANVAS FINISH JACKET APPLIED WITH LAGGINGADHESIVE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
19/56
VESSEL BOTTOM HEAD,
LEG, SKIRT INSULATION
AND SECUREMENT
1 VESSEL, INSULATION AND JACKET2 FIREPROOFING (BY OTHERS, IF REQUIRED)3 MECHANICAL FASTENERS4 TIE WIRES5 REINFORCING WIRE MESH & INSULATING CEMENT
6 INSULATION SUPPORT RING (BY OTHERS)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
20/56
PIPE AND TUVE EXCHANGERS ENCASED
1 PIPE INSULATION SECURED WITH BANDING2 BLOCK INSULATION SECURED WITH BANDING3 FINISH JACKET (METAL SHOWN SECURED WITH
BANDING)4 SHEET METAL SCREWS5 BEVEL INSULATION AND FINISH WITH COATING6 BLOCK INSULATION AND FINISH WITH COATING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
21/56
LARGE DIAMETER
VERTICAL VESSELS
BLOCK AND BLANKET
INSULATION
1 SUPPORT RING FORHEAD INSULATION
2 BLOCK OR BLANKETINSULATION
3 MECHANICALFASTENERS OR
4 BANDING TO SCUREINSULATION
5 SUPPORT RING (BYOTHERS)
6 METAL JACKET7 SHEET METAL SCREWS8 BANDING9 BLOCK INSULATION
MITRED TO FIT10 FABRICATED HEAD COVER11 METAL FLASHING12 BOTTOM HEAD INSULATION13 VESSEL SKIRT
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
22/56
LARGE DIAMETER HORIZONTAL VESSELS
INSULATION SUPPORT AND SECUREMENT
1 RIGID INSULATION
2 BANDING SUPPORT BARS
3 BANDING
4 FINISH JACKET SECURED WITH BANDING OR
SCREWS
5 HEAD COVER
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
23/56
FLEXIBLE CLOSEDCELL SHEETS
1 INSULATION ADHESIVE (CONTACT TYPE)2 FLEXIBLE CLOSED CELL INSULATION (CUT TO FIT
TIGHTLY)3 JOINTS SEALED WITH CONTACT TYPE ADHESIVE4 LEGS & PROTRUSIONS INSULATED (OPTIONAL)
5 PROTECTIVE COATING WHERE REQUIRED
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
24/56
EXTREME TEMPERATURE VESSELS
BLOCK INSULATION
1 FLEXIBLE INSULATION2 INSULATION JOINTS STAGGERED3 FINISH JACKET (METAL SHOWN)4 BANDING5 INSULATION ATTACHMENT FOR HEAD
6 FABRICATED HEAD COVER7 CLOSED CELL INSULATION FOR FIRST 300mm
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
25/56
SMALL DIAMETER VESSELS / EXHAUST
PIPE COVERING
1 INSULATION SUPPORT RING (BY OTHERS)2 PIPE INSULATION SECURED WITH BANDS OR WIRE3 RIGID INSULATION CUT TO FIT4 FLEXIBLE INSULATION FILLER5 FINISH JACKET (METAL SHOWN)6 SHEET METAL SCRES OR POP RIVETS7 BANDING AS REQUIRED8 BEVEL INSULATION FOR BOLT REMOVAL AND FINISH
WITH COATING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
26/56
FIELD APPLIED LINING
1 HOUSING OR SHAFT
2 RIGID DUCT LINER
3 ADHESIVE WHERE NECESSARY
4 MECHANICAL FASTENERS5 JOINTS SEALED WITH INSULATION COATING
EMBEDDED IN REINFORCING MEMBRANE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
27/56
CURVED SURFACES RIGIDBOARD INSULATION
1 INSULATION SCORED OR BEVELLED TO FIT
CURVATURE
2 MECHANICAL FASTENERS
3 BANDING
4 CELLULAR GLASS INSULATION ON BOTTOM 300mm
5 METAL JACKET6 HEAD FLASHING
7 CAULKING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
28/56
NOZZLES AND INSULATED MANWAYS
1 VESSEL INSULATION
2 METAL OR REINFORCING MEMBRANE BANDED TO
NOZZLE
3 WEATHER BARRIER COATING OR CAULKING
4 METAL COVER LINED WITH RIGID INSULATION
5 METAL SEAM OR END CAP
6 MECHANICAL FASTENER AS REQUIRED
7 FLASHING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
29/56
BLOCKS AND PRE-FORMED PIPE INSULATION
AROUND BREECHINGS AND EXHAUST DUCTS
1 AIR SPACE MATERIAL (BY OTHERS)2 RIGID BLOCK INSULATION3 WIRE OR BANDING4 METAL JACKET FINISH
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
30/56
HEAD INSULATION SECUREMENT
AND COVER FABRICATION
1 HEAD INSULATION 6 METAL FINISH JACKET
2 FLOATING RING 7 FLEXIBLE INSULATION
3 BANDING 8 SHEET METAL SCREWS
4 SHELL INSULATION 9 HIGHT COMPRESSIVE
5 HEAD INSULATION STRENGTH RIGID INSULATION
SUPPORT RING 10 REINFORCED MASTING
11 CAULKING / FLASHING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
31/56
PIPING (0C THROUGH -40C)
1 INSULATION INNER LAYER
2 INSULATION OUTER LAYER WITH JOINTS
STAGGERED
3 LONGITUDINAL LAP ON VAPOUR BARRIER SEALED
4 BUTT JOINT VAPOUR BARRIER SEALED5 BANDING, WIRE OR TAPE AS REQUIRED
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
32/56
FITTINGS (0C THROUGH -40C)
1 MULTI-LAYER INSULATION; VAPOUR BARRIER
ON OUTER LAYER
2 PREFORMED INSULATION COVER
3 BANDING, WIRE OR TAPE
4 VAPOUR BARRIER TAPE
5 LONGITUDINAL LAP ON VAPOUR BARRIER
SEALED
6 PREFORMED FITTING COVER
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
33/56
FLEXIBLE INSULATION BLANKETS
1 SHAPED INSULATION BLANKET2 QUILTER WASHER
3 LACING HOOKS AND WIRE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
34/56
REMOVABLE AND REUSABLE INSULATION
1 SEAMS STITCHED
2 QUILTING WASHERS3 LACING HOOKS AND WIRE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
35/56
REMOVABLE INSULATED
METAL EQUIPMENT COVERS
1 METAL CASING LINED WITH INSULATION
2 SECTIONS OF THE FABRICATED COVER
3 SLIP JOINT OR LAP SEAM WITH SHEET METALSCREWS, POP RIVETS OR STANDING SEAM
4 CUT-OUTS FOR PIPES OR SHAFTS
5 CAULKING WHERE REQUIRED
6 SHEET METAL SCREWS OR POP RIVETS
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
36/56
REMOVABLE AND REUSABLE INSULATION
1 FLEXIBLE CLOSED CELL INSULATION
2 METAL FRAME
3 REMOVABLE TOP FORM FITTED
4 ADHESIVE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
37/56
ELASTOMERIC REMOVABLE COVERS
1 PERMANENT INSULATION
2 COVERS FROM FLEXIBLE CLOSED CELL
INSULATION
3 ADHESIVE
4 THICKNESS OF INSULATION FILLER EQUAL TO
BOLT HEAD SIZE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
38/56
TYPICAL FIRE STOP COMPONENTS FOR
FLOOR EXPANSION JOINT
1 COMPRESSION SEAL
2 ULC APPROVED FIRE STOP SEALANT3 COMPRESSABLE FIRE STOP (MINERAL WOOL)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
39/56
TYPICAL FIRE STOP COMPONENTS
FOR FLOORS EXPANSION JOINT
1 ULC APPROVED FIRE STOP SEALANT2 COMPRESSABLE FIRE STOP (MINERAL WOOL)3 JOINT COVER (GALVANIZED STEEL)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
40/56
TYPICAL FIRE STOP
FOR WALL PENETRATIONS
1 STEEL SLEEVE (OPTIONAL)2 ULC APPROVED FIRE STOP SEALANT
3 COMPRESSIBLE FIRE STOP (MINERAL WOOL)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
41/56
TYPICAL FIRE STOP
FOR WALL PENETRATIONS
1 STEEL SLEEVE (OPTIONAL)2 ULC APPROVED FIRE STOP SEALANT
3 COMPRESSIBLE FIRE STOP (MINERAL WOOL)4 PIPE INSULATION (INSTALLED AFTER FIRESTOP)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
42/56
TYPICAL FIRE STOP
FOR WALL PENETRATIONS
1 STEEL SLEEVE
2 ULC APPROVED FIRE STOP SEALANT3 COMPRESSIBLE FIRE STOP (MINERAL WOOL)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
43/56
TYPICAL FIRE STOP
FOR WALL PENETRATIONS
1 STEEL SLEEVE2 ULC APPROVED FIRE STOP SEALANT3 COMPRESSIBLE FIRE STOP (MINERAL WOOL)4 PIPE INSULATION (INSTALLED AFTER FIRE
STOP)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
44/56
TYPICAL FIRE STOP
FOR WALL PENETRATIONS
1 STEEL SLEEVE (OPTIONAL)2 ULC APPROVED FIRE STOP SEALANT
3 COMPRESSIBLE FIRE STOP (MINERAL WOOL)4 PIPE INSULATION (INSTALLED AFTER FIRE
STOP)
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
45/56
TYPICAL FIRE STOP FOR DEFLECTION
OF METAL STUD WALLS
1 ULC APPROVED FIRE STOP SEALANT2 COMPRESSIBLE FIRE STOP (MINERAL WOOL)3 METAL CHANNEL SIZED TO SUIT ALLOWANCE
FOR DEFLECTION & SIZE OF STUDS4 GYPSYM BOARD FIXED TO STUD AND FREE TO
SLIDE5 TAPE BREAKER
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
46/56
TYPICAL FIRE STOP COMPONENTS FOR
THE TOP OF THE MASONRY WALL
1 ULC APPROVED FIRE STOP SEALANT2 COMPRESSIBLE FIRE STOP (MINERAL WOOL)3 AIR SPACE
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
47/56
PRE-FORMED PIPE INSULATION
MULTIPLE LAYER CONSTRUCTION
1 PRE-FORMED PIPE INSULATION (AS SPECIFIED)2 INSULATION WITH STAGGERED JOINTS3 INSULATION FASTENING4 FINISH JACKET5 JACKET FASTENING
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
48/56
RECEIVING
When receiving the pipe and/or fittings shipment at the job site, the
contractor or purchaser should exercise established precautions.
Each shipment should be inventoried and inspected with care upon
arrival. The pipe and fittings are inspected and loaded with due
care at the factory using methods acceptable to the carrier. It is the
carrier's responsibility to deliver the shipment in good condition,
and it is the receiver's responsibility to ensure that there has been
no loss or damage.
The following procedures are recommended for acceptance of
delivery:
1. Conduct overall examination of the load. If the load is intact,
ordinary inspection while unloading should be sufficient to ensure
hat the pipe has arrived in good condition.
2. If the load has shifted, has broken bundles, or shows rough
reatment, carefully inspect each piece for damage.
3. Check total quantities and details of each item against shipping
documents.
4. Note any damaged or missing items on the delivery receipt.
5. Notify the carrier immediately and make a claim according to his
nstructions.
6. Do not dispose of any damaged material. The carrier will notify
you of the procedure to follow.
7. Replacements for shortages and damaged materials are not
reshipped without request. If replacement materials are needed,
reorder from your ROYAL distributor or representative.
UNLOADING
The means by which pipe and fittings are unloaded in the fie
the decision and the responsibility of the receiver.
The following recommendations should be followed:
1. Remove restraints from the bundles. These may be str
ropes, or chains with padding.
2. Remove any boards on the top or sides of the load that are
part of the pipe/fittings packaging.
3. When unloading fittings use industry-accepted means.
extreme caution when unloading fittings with any type
machinery, as fittings may be fiberglass wrapped for ad
strength. Damage to wrapping could reduce strength of fabric
fitting. Do not drop or throw fittings into trench. ROYAL isresponsible for damage to mishandled fittings.
4. Using a forklift (or a front-end loader equipped with fo
remove the top bundles of pipe, one at a time from the truck.
5. If a forklift is not available, use a spreader bar with fabric st
capable of carrying the load. Space straps approximately
metres (8 ft) apart. Loop straps under the load.
6. During the removal and handling, ensure that the bundle
not impact anything (especially in cold weather).
7. Place pipe bundles on level ground.
8. Do not handle bundles with individual chains or single ca
even if padded.
9. Do not attach lifting cables to bundles or bands.
10. Do not stack bundles more than 2.4 metres (8 ft) high.
11. Protect bundles with packing materials the same way
were protected while on the truck.
12. To unload lower bundles, repeat the unloading pro
described above.
13. Do not unload pipe bundles by hand.
14. If unloading equipment is not available, pipe may be unloa
by removing individual pieces. Care should be taken to ensure
pipe is not dropped or damaged.
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
49/56
STORAGE
The following procedures are recommended to prevent damage to
he pipe:
1. Store the pipe at the site in bundles.
2. Avoid compression, deformation or damage to bell ends of the
pipe.
3. When bundles are stacked, ensure that the weight of upper
bundles does not cause deformation to pipe in lower bundles.
4. Support pipe bundles at 2.4 metre (8 ft) intervals (1.2 metres (4
ft) from each end) on wood blocking to prevent damage to the
bottom surfaces during storage.
5. Store lubricant in tightly sealed containers under cover.
6. Do not store pipe/fittings where gaskets may be exposed to
ozone, UV radiation, or contamination (ie. grease, oil etc).
7. Protect the interior and sealing surfaces of pipe and fittings from
dirt and foreign material.
8. When the bundles are stacked, ensure that the stack remains
stable.
9. When pipe/fittings are being stored for a prolonged period, the
bundles should be covered with a translucent cover, to protect
against exposure to direct sunlight.
HANDLING
The following procedures are recommended:
1. When using mechanical equipment, exercise care to pre
damage to the pipe/fittings.
2. Lower pipe/fittings carefully from trucks and into trenches.
not drop pipe/fittings. Dropped pipe/fittings can be damaged
should not be used.
3. In sub-zero (freezing) temperatures, use caution to pre
impact damage. Handling methods considered acceptable
warm weather are unacceptable during very cold weather.
4. When distributing the pipe along a trench (stringing), place
on the opposite side of the trench from the excavated earth. P
pipe with bell ends in the direction of the work progress.
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
50/56
PIPE INSTALLATION INSTRUCTIONS
Alignment and GradeAll pipe should be laid to, and maintained at required lines and
grades established by the pipe system Design Engineer. Fittings,
valves, air vents and hydrants should be installed at the required
ocations with valve and hydrant stems plumb.
Trench Width
Trench width at the ground surface may vary with and depend
upon the depth, type of soils, and the position of the surface
structures. The minimum clear width of the trench, measured at
he spring line of the pipe should be 300mm (1ft) greater than the
outside diameter of the pipe. The maximum clear width of the
rench at the top of the pipe should not exceed a width equal to the
pipe diameter plus 600mm (2 ft). If the above defined trench widths
must be exceeded, or if the pipe is installed in a compacted
embankment, the pipe embedment should be compacted to a point
of at least 2.5 pipe diameters from the pipe on both sides of the
pipe or to the trench wall, whichever is less.
Preparation of Trench Bottom
The trench bottom should be constructed to provide a firm, stable
and uniform support for the full length of the pipe.
Bell holes should be provided at each joint to permit proper joint
assembly and pipe support. Any part of the trench bottom
excavated below grade should be backfilled to grade and should
be compacted as required to provide firm pipe support.
When an unstable sub-grade condition which will provide
nadequate pipe support is encountered, additional trench depth
should be excavated and refilled with a suitable foundation material
as recommended by the project's Geotechnical Engineer. Ledge
rock, boulders and large stones should be removed to provide
100mm (4") of soil cushion on all sides of the pipe and accessories.
Laying of Pipe
Proper implements, tools and equipment should be used
placement of the pipe in the trench to prevent damage.
Under no circumstances should the pipe or accessories
dropped into the trench. All foreign matter or dirt should
removed from the pipe interior. Pipe joints should be assem
with care. When pipe laying is not in progress, open ends o
installed pipe should be closed to prevent entrance of trench w
dirt and foreign matter into the line.
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
51/56
Mechanical Joint Restraint
ROYAL will recognize the use of any restraint device that ca
third party certification to ASTM F1674 (American Society
Testing and Materials), FM (Factory Mutual) and UL (UnderwrLaboratories). It is the responsibility of the restrainer manufact
to supply the necessary support data to prove that their pro
complies with these requirements and is compatible with
pipe/fittings.
It is important to note that ROYAL does not assume any lia
arising from the use of any restrainers on pipe or fitt
manufactured by ROYAL.
Thrust Blocking
Concrete reaction or thrust blocking should be provided at each
hydrant, valve, bend, tee and at reducers or fittings where changes
occur in pipe diameter or direction. Concrete thrust blocks shall becast in place, poured against undisturbed soil. Pre-cast blocks are
not permitted.
1
87
6
5
4
3
2
1. Through line connection
2. Through line connection (crossused as tee)
3. Direction change (tee used as
elbow)
4. Direction change (elbow)
5. Direction change (cross used
as elbow)
6. Vertical direction change
(elbow)7. Direction change
8. Through line connection (w
9. Hydrant runout
9
1. Through line connection (tee)2. Through line connection (cross
used as tee)
3. Direction change (elbow)
4. Change line size (reducer)
5. Direction change (tee used as
elbow)
6. Direction change (cross usedas elbow)
7. Hydrant Tee
8. Hydrant Boot
9. Valve Anchor
10. Vertical direction change
(bend anchor)
1 2
3 4
56
7 8
910
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
52/56
Pipe Embedment
PVC pipe should be installed with proper bedding providing
uniform longitudinal support under the pipe. Backfill material
should be worked under the sides of the pipe to providesatisfactory haunching. Initial backfill material should be placed to
a minimum depth of 300mm (1ft) over the top of the pipe. All pipe
embedment material should be selected and placed carefully.
Stones, frozen lumps and debris are not considered suitable for
use in the embedment area of the pipe. Proper compaction
procedures should be exercised to provide soil densities as
specified by the Design Engineer.
Final Backfill
After placement and compaction of pipe embedment materials, the
balance of backfill material may be machine placed. The final
backfill should contain no large stones or large rocks, frozen
material or debris. Proper compaction procedures should be
exercised to provide required soil densities.
Assembly of Gasket Joints
The patented "Double-Seal" gaskets are "Locked-In" to the be
the factory.
1. Clean the gasket, bell interior, and spigot area with a clean
brush or paper towel to ensure all debris is removed from bell
spigot ends of the pipe. Check the gasket position. Inspec
gasket, pipe spigot bevel and sealing surfaces for damag
deformation. Be sure that the gasket is installed properly. Do
remove gasket as it is locked in during manufacturing. Once
gasket is removed, it cannot be reinstalled.
2. Use only ROYAL recommended lubricant supplied with the p
Liberally apply lubricant to the spigot up to the reference mark
to the face of the gasket. Use of non-approved lubricants
promote bacterial growth and cause damage to the gasket
pipe, as well as void the manufacturer's warranty.
3. After lubrication, the pipe is ready to be joined. Good alignm
of the pipe is essential for ease of assembly. Align the spigot
the bell, and insert the spigot into the bell until it contacts
gasket uniformly. Do not suspend the pipe and "stab" it onto
bell. The spigot end of the pipe will be marked by ROYA
indicate the proper depth of insertion. The insertion line shoul
exposed in front of the face of the bell. Do not over insert the j
NOTE: Dual-Durometer gaskets are available upon reques
100 - 300mm (4 -12 in) diameter DR18 and DR25 pipe.
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
53/56
Field-Cut Pipe to Pipe
To join field-cut pipe, it is necessary to first prepare the pipe
end. A square cut is essential for proper assembly. The pipe
can be easily cut with a hacksaw, handsaw or a power sawwith a steel blade or abrasive disc. It is recommended that the
pipe be marked around its entire circumference prior to cutting
to ensure a square cut. The insertion line should be marked
on the cut piece of pipe.
The location of the insertion line is determined by using the
pipe bell as a guide. Measure the insertion depth of the bell.
This is the distance from the end of the bell to the start of the
bell taper. Subtract 13mm (in) from the insertion depth
distance. The result is the distance from the end of the spigot
to the insertion line.
Use a factory-finished beveled end as a guide for proper bevel
angle and depth of bevel plus the distance to the insertion
reference mark. The end may be beveled using a pipebeveling tool or a wood rasp which will cut the correct taper. A
portable sander or abrasive disc may also be used to bevel the
pipe end. Round off any sharp edges on the leading edge of
the bevel with a pocket knife or file.
Longitudinal Bending of Pipe and Pipe Joint Deflection
There are three common methods used to achieve change
direction for Royal PVC pressure pipe:
(A) Longitudinal Bending of Pipe (ROYAL C900 DR 18 pi
only)
ROYAL C900 DR18 Pressure Pipe can be bent to obtain
maximum angle of deflection as shown in the following table
To obtain this result, please follow the guidelines given in t
Uni-Bell Handbook of PVC Pipe.
NOTE: Do not install service taps of any kind into bent pip
because it is under stress.
(B) Pipe Joint Deflection (ROYAL C900 DR 18 pipe only)
ROYAL C900 DR18 Pressure Pipe can be deflected at the jo
by a maximum angle of deflection as shown in the followin
table:
The close tolerances of ROYAL joints limit the amount
unstressed deflection. The procedure is as follows:
Make a concentric assembly, but push the spigot into the b
only to a point about 13mm (1/2 in) short of the insertion lin
This incomplete assembly permits more movement of the en
of the pipe at the bottom of the bell. Do not exceed t
recommended maximum offset and use only manual effort.
NOTE: Do not combine Methods A and B.
ROYAL does not recommend longitudinal bending of pipe
deflection of joint to achieve change in direction for pip
diameters larger than 12".
(C) Use of Fittings (All pressure pipe)
Angle fittings or bends are available to obtain change
direction as required.
2
INSERTION LINE
PIPE
DIAMETER
15 BEVEL
Pipe DiameterMax. Angle of
Deflection
150mm (6) 4.0
200mm (8) 3.0
250mm (10) 2.5
300mm (12) 2.1
Pipe DiameterMax. Angle of
Deflection
150mm (6) 3.0
200mm (8) 3.0
250mm (10) 3.0
300mm (12) 2.5
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
54/56
FITTING INSTALLATION INSTRUCTIONS
1. Make sure both the bell and spigot are clean.
2. Cut the pipe square to the required length and bevel the pipe to
match that of a factory bevel. Use a piece of pipe with a factory
made bevel as a guide when making field bevels. Remove any
burrs or other sharp pieces that may harm the gasket when the
pipe is inserted into the bell.
3. Measure the insertion depth of the bell and mark the spigot with
his dimension. Mark the spigot with a line 360 around the pipe.
The insertion depth is from the lip of the bell to the beginning of the
aper inside the bell. Over insertion of PVC pipe is one of the
primary causes of failure for both PVC pipe and fittings. Over
nsertion of the spigot is characterized by a crushing of the spigot
n the bell, which causes the bell to crack at the taper of the fitting.
The crack will then move in both directions until it splits the bell,releasing the stress on the bell and causing a failure of the fitting.
4. Lubricate both the bell and the spigot with the lubricant supplied
by the manufacturer. The lubricant shall be applied in a 1 mm
hickness to the bell lip and gasket area and to 76mm (3in) from the
end of the spigot. This distance on the spigot includes the chamfer
of the pipe.
5. Check again that the bell and spigot are still free of debris, and
hen place the spigot at the bell lip positioning the spigot such that
he chamfer is resting against the edge of the gasket. Then, push
he spigot into the bell until the assembly line on the spigot is even
with the lip of the bell. See notes below.
Field-Cut Pipe To Fittings
Field cutting pipe to fittings should follow the procedure on p
12. Along with those instructions, the following procedure sh
be used. Cut pipe to required length. Measure the insertion leon the fitting as described in the "Field-Cut Pipe to Pipe" sec
and transfer that measurement to the pipe end, after the pipe
is beveled. Mark the measured length on the pipe with a ma
ensuring the mark is easily visible. Once the pipe is beveled
the insertion line is marked, insert the pipe into the fitting
suggested in previous sections.
NOTE: Do not insert the pipe past the measured insertion
Over insertion of the pipe into the fitting can cause failure of
fitting.
Cast iron fittings have shallower bells than PVC fittings. For
cast iron fittings, the edge of the PVC pipe should be square
For push-fit cast iron fittings, a small chamfer is required. For mdetailed information about assembly to cast iron fittings, ple
contact the fitting manufacturer.
Deflecting the Joint at Fittings
PVC pressure fitting joints by nature of their gasket design
insertion depth cannot accommodate large deflection angles.
maximum deflection should be 1 for all sizes of PVC pres
fittings. This is equivalent to 100mm (4in) of deflection over a
metres (20 ft) length of pipe. If the deflection exceeds 1, failu
characterized by a crack in the lip of the bell of the fitting w
propagates back towards the gasket causing a failure of the fit
When deflecting the pipe/fitting joint, use the following proced
1. When assembling the pipe/fitting joint, push the spigot into
bell until the assembly line on the spigot is 13mm (1/2in) sho
the lip of the bell. The 13mm gap allows for more movement a
end of the pipe being inserted.
2. Shift the end of the pipe being inserted by 100mm (4in) for a
metre (20 ft) length. This is equal to 1 of deflection.
3. If a large resistance force to the insertion of the spigot is fe
the installer, it could mean that the gasket has become dislod
In this case, disassemble the joint and re-assemble as per
instructions above.
ROYAL has the production capacity to make any degree brequired (from 5 to 89 degrees) in addition to our standard 11
22.5, 45 and 90 bends. Please contact your RO
representative for more details.
NOTES
For small diameters the assembly effort should be able to be
delivered by hand using a block and bar. Never push directly
against the pipe.
Always keep a piece of wood between the face of the pipe bell
and the bar used for pushing. This protects the pipe as well as
ensures even distribution of the force pushing the pipe into the
bell.
For larger diameters, mechanical assembly methods may be
required such as a come-along, jacks, pulleys and even the
backhoe bucket. Of all the methods the backhoe bucket is the
least preferred. A backhoe bucket cannot feel the resistance tothe spigot entering the bell and therefore cannot tell if the joint is
going together correctly. Over insertion by the backhoe will
damage the fitting joint and may also damage other joints
previously installed.
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
55/56
INSPECTION AND TESTING
Good practice dictates pressure testing portions of lines as they
are completed in advance of the entire system. Before testing, the
pipeline must be backfilled and braced sufficiently to prevent
movement under pressure.
The following three points should be considered when testing:
1. The pipe to be tested must be sufficiently backfilled to prevent
movement while under test pressure.
2. Thrust restraint at fittings should be permanent and constructed
o withstand test pressure. If concrete thrust blocks are used,
sufficient time must be allowed before testing to permit the
concrete to cure.
3. Test ends should be capped and braced to withstand the thrustshat are developed under test pressure.
Pressure and Leakage Test
A combined pressure and leakage test is recommended. The test
pressure and duration shall be as specified by the Design
Engineer. The test pressure should never exceed the pressure
rating of the pipe being tested.
Relieving Air From Pipe Line
The pipeline should be filled as slowly as possible (not more than
1 ft/sec) to avoid any unnecessary surges. Venting air from the line
s of utmost importance.
Pressure pipe is seldom laid to grade, so there are high and lowsections along the line. If the high section elevation is considerably
above the low part of the line, a larger amount of air will be trapped.
Corporation stops or automatic air relief valves should be installed
at these points. Air can be blown from hydrants in pipe sizes up to
200mm (8in). In larger diameter pipes, air will not enter the hydrant
branch, therefore it will be necessary to install air release valves at
high points.
The line should then be filled with water to static pressure, and all
air vents opened to allow air to escape. It is recommended practice
o let the line remain under static pressure for at least 15 minutes.
All air vents should then be opened again to allow any remaining
air to be released from the line, after which the line may be brought
up to full test pressure. The leakage shall not exceed that specifiedby the Design Engineer. Test pressure should never exceed the
pressure rating on the pipe being tested.
Air pressure testing of installed PVC pressure pipe is expressly
prohibited for safety reasons.
SERVICE CONNECTIONS AND TAPPING
Service lines can be connected to ROYAL PVC Pressure Pip
the following methods:
Direct Tapping
Up to 25mm (1in) corporation stops can be used.
Only 150 - 300mm (6 - 12in) diameter AWWA C900 Pressure
Class 150 (DR 18) and Pressure Class 200 (DR 14) pipe. Do
direct tap Pressure Class 100 (DR 25) pipe.
"Wet" (under-pressure) or "dry" (no-pressure) taps are permi
Approved Service Saddles for PVC Pressure Pipe
Can be used with any size or class of pipe.
Maximum outlet permitted is 50mm (2in).
Saddles must be sized to provide even support around the f
circumference of the pipe.
The strapping must provide a minimum of bearing width of 50(2in) along the axis of the pipe.
The design of the saddle should not have lugs that will inden
pipe when the saddle is tightened.
Can be used with wet or dry taps.
Tapping Sleeves and Valves
Should be used for services requiring larger than 50mm (2in
taps.
Should be supported independently of the pipe.
Thrust restraints are required.
Can be used with wet or dry taps.
M.W.BARVE LECTURE NOTES
-
8/7/2019 cladding& fitting
56/56
General Tapping Recommendations
1. AWWA C800 (Mueller) threads are required.
2. Shell cutters (with or without slots) are necessary to retain andremove the coupon. The throat depth should be sufficient to handle
heavier DR 14 pipe. Do not use single slot cutters.
Do not use twist drill bits for tapping PVC. It is required that a sharp
apping tool and tapping lubricant be used in the tapping process.
3. The tapping machine shall have an independent boring bar feed
mechanism. Manufacturers instructions for operating the tappingmachine should be followed.
This is a sample of a proper tapping coupon.
4. The tapered thread of the corporation stop shall be spirally
wound with 2-3 layers of Teflon tape. This procedure is also
required when installing corporation stops in tap couplings.
5. A torque wrench should be used to tighten the corporation stop
using 36.6Nm (27ftlb), 2-3 threads should be showing after
removal of the tapping machine. If leakage is apparent after final
orque tightening of 47.5Nm (35ftlb), the corporation stop will
have to be reinstalled. The line pressure should be relieved; the
corporation stop removed; new Teflon tape wrapped on the
hreads and the corporation stop reinstalled to a torque of 36.6Nm
(27ftlb).
6. Taps should be made at 10 o'clock or 2 o'clock on the pipe.
7. Horizontal goose-necks of the service line are suggested to
allow the expansion and contraction of the service line.This is a sample of a proper tapping coupon.
8. Pipe temperature should be between 0 - 40C (32 - 104F)
when direct tapping under pressure. Be extremely cautious when
9. When making more than one tap on a length of pipe the
locations should be staggered at least 600mm (2ft) a
longitudinally.
10. Taps should not be made in areas of the pipe that h
become discoloured.
11. NEVER DIRECT TAP IN AN AREA OF THE PIPE THAT
BEEN BENT.
12. Do not tap closer than 600mm (2 ft) from the ends of the p
Basic Safety Precautions
When drilling or tapping any pressurized water pipe, basic sa
precautions are advised to assure personal safety of the work
in the event of a sudden and unexpected pipe failure. Altho
such failures are extremely infrequent, the following sapractices are recommended.
A second workman or supervisor should always be present in
immediate vicinity when making "wet" taps.
Normal protective clothing: including hard hat, safety shoes,
goggles or face mask, should be worn.
A heavy protective blanket, 1.2 metres x 1.8 metres (4ft x 6f
should be used to cover the exposed pipe in the area of the
The blanket should have a hole in the center permitting acce
and operation of the drilling and tapping machine.
M.W.BARVE LECTURE NOTES