Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019
Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA
www.cleanteq.com
Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019
Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA
www.cleanteq.com
Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019
Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA
www.cleanteq.com
Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019
Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA
www.cleanteq.com
Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019
Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA
www.cleanteq.com
Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019
Clean TeQ Holdings Limited12/21 Howleys RoadNotting Hill VIC 3168AUSTRALIA
www.cleanteq.com
Clean TeQ Sunrise
CCC Meeting – 5 June 2019
Clean TeQ Sunrise
Project update
Community engagement update
Environmental management update
CCC member questions
Summary
CCC Meeting Presentation – 5 June 2019 Page 2
Project update
Page 3
Clean TeQ Sunrise
• 4 June 2019
– Clean TeQ commences a partnering process for our Sunrise Project, working with Macquarie Capital
• 30 April 2019 – Quarterly Update
– Construction and commissioning of three commercial-scale ion-exchange metal recovery and water purification plants nearing completion in DRC, Australia & Oman
– Clean TeQ Sunrise front end engineering and design progressing steadily with approximately 20% complete
– Market conditions remain favourable for EV battery materials – nickel was the best performing base metal on the LME in Q1 2019
Recent ASX announcements
CCC Meeting Presentation – 5 June 2019 Page 4
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019 Page 5
Project update – early works
• Vegetation Screen
– Initial works have commenced to establish mine site vegetation screens
– Exact positioning of vegetation screens to be determined based on results of final designs and survey
Vegetation Screens
Clean TeQ Sunrise
Project update – early works
CCC Meeting Presentation – 5 June 2019 Page 6
• Fibre Optic Cable
– Fibre optic cable from Fifield to the mine site and accommodation camp installed
– Works conducted by Telstra
Clean TeQ Sunrise
Our presence in the region
CCC Meeting Presentation – 5 June 2019 Page 7
• Parkes office is now operational
– Branding to be installed this month
• Our shopfronts at Condobolin and Trundle continue to be managed by the community team
Clean TeQ Sunrise
• Land Management
– Spraying for Bathurst Burr
– Feral pig eradication program underway
– Fox baiting commenced
– Repairs & protection to groundwater monitoring bores
– Grazing stock keeping fire hazard down
• Emergency Management
– Upgrade to communications for emergency purposes
• Accommodation Camp
– Layout approval received from DP&E
Site management update
CCC Meeting Presentation – 5 June 2019 8
Clean TeQ Sunrise
• Appointment of Statutory Roles
– Quarry Manager
– Electrical Engineer
• Safety Management System
– Development of SMS progressing
• Metalliferous Industry Safety and Health Engagement Forum
– Inclusion as a participant in MISHEF
Resources Regulator
CCC Meeting Presentation – 5 June 2019 9
Community engagement update
Page 10
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 5 June 2019 Page 11
• Building relationships across the community
– Provided six project update presentations at Rotary, Lions and Probus Club meetings across Forbes (3), Parkes (2) and Condobolin (1) between April & May
– Condobolin Probus – attending June meeting
• Actively participating in our community
– Attended the Bedgerabong Country Fair
– April & May coffee carts held in Trundle jointly with Trundle Central School
– Hosted the Clean TeQ School Holiday BBQ in Condobolin with the Lake Cowal Conservation Centre, Condobolin Landcare and DPI Fishcare
– Attended the fabba-ulous ABBA Festival in Trundle
Clean TeQ Sunrise
• Newspaper advertisements
– Continue to feature in local media
• Keeping our community updated
– Newsletter published in April
– May eNews communication distributed to more than 800 subscribers
– Fact Sheets under review, with a view to publishing soon
– Community updates on Facebook reached 50,166 impressions attracting more than 2700 engagements
• Future newsletters to include a CCC column
– Profile CCC members
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 12
Clean TeQ Sunrise
• Website
– Complaints register published
– Zero complaints received for the period 1 Jan –31 May 2019
• Shop fronts
– Condobolin shopfront continues to be busy with enquiries relating to business or employment opportunities
– Visiting Trundle shopfront a minimum of one day per week
• Groundwater Management Plan consultation
– Consultation with key stakeholders regarding the progress of the GWMP
Keeping people informed
CCC Meeting Presentation – 5 June 2019 Page 13
Clean TeQ Sunrise
Community framework
CCC Meeting Presentation – 5 June 2019 Page 14
• Developing key document frameworks
– Community engagement policy now on website
– Community engagement delivery plan
– Community investment plan – prior to FID and thereafter
• Education engagement & investment
– Pilot Fundraising program
– Supporting Forbes North Public School - Science kit
Clean TeQ Sunrise
On the Calendar
CCC Meeting Presentation – 5 June 2019 Page 15
• Continue to actively engage with our local communities
– Women’s Wellness Expo – Condobolin
– Fifield community - Christmas in July evening planned
– Supporting and attending regional shows – commencing in August
Environmental management update
Page 16
Clean TeQ Sunrise
• EMPs prepared for the “initial construction activities”
• All EMPs (excluding Water Management Plan) submitted to the DP&E
for review
• Two EMPs (incorporating Modification 4) have been approved by the
DP&E:
– Blast Management Plan
– Road Upgrade Maintenance Strategy
– EMPs are published on the website following approval
• EMPs will be revised for re-approval before commencement of any
works after the “initial construction activities”
Environmental Management Plans
CCC Meeting Presentation – 5 June 2019 Page 17
Clean TeQ Sunrise
• Attended monitoring (conducted quarterly)
commenced in March 2019
• Monitoring sites consistent with
Environment Protection Licence and Noise
Management Plan
• No exceedances of criteria recorded
Environmental monitoring – noise monitoring
CCC Meeting Presentation – 5 June 2019 Page 18
Clean TeQ Sunrise
• Dust deposition gauges installed in January 2019 and
collected monthly
• Monitoring sites consistent with Environment Protection
Licence and Air Quality Management Plan
• Depositional dust data located on the Clean TeQ
website:
https://www.cleanteq.com/sunrise-project/reports/
Environmental monitoring – air quality monitoring
CCC Meeting Presentation – 5 June 2019 Page 19
Clean TeQ Sunrise
• ML 1770 – salvage works undertaken in
accordance with Aboriginal Heritage Impact
Permit
• Registered Aboriginal Parties participated in
salvage works
• Aboriginal cultural heritage objects stored in
“Keeping Place”
Aboriginal cultural heritage – salvage works
CCC Meeting Presentation – 5 June 2019 Page 20
CCC member questions
Page 21
Clean TeQ Sunrise
• Nil questions received
CCC member questions
CCC Meeting Presentation – 5 June 2019 Page 22
Clean TeQ Sunrise CCC Meeting Presentation – 5 June 2019