clean water act permitting and agricultural activities in minnesota
DESCRIPTION
Clean Water Act Permitting and Agricultural Activities in Minnesota. By: Desiree Morningstar Acting Chief, Northwest Section St. Paul District U.S. Army Corps of Engineers June 27, 2014. Presentation Topics. Section 404 of the Clean Water Act Permitting Exempt Activities - PowerPoint PPT PresentationTRANSCRIPT
US Army Corps of Engineers
BUILDING STRONG®
Clean Water Act Permitting and Agricultural Activities in Minnesota
By: Desiree Morningstar Acting Chief, Northwest SectionSt. Paul DistrictU.S. Army Corps of Engineers
June 27, 2014
BUILDING STRONG®2
Presentation Topics
• Section 404 of the Clean Water Act
• Permitting
• Exempt Activities
• Points of Contact
BUILDING STRONG®
Section 404 of the Clean Water Act
3
A section 404 permit is required for the discharge of dredged or fill material into waters of the United States
The mission of our Regulatory Program is to ensure protection of the Nation’s aquatic resources while allowing reasonable development through fair and balanced decisions.
BUILDING STRONG®
Section 404 of the Clean Water Act
Discharges of Dredged Material Dredged material is defined as “material that is excavated or
dredged from waters of the U.S.” A discharge of dredged material means “any addition of
dredged material into, including redeposit of dredged material other than incidental fallback within, the waters of the U.S.”
Discharges of Fill Material Fill material is defined as “material placed in waters of the
United States where the material has the effect of (1) replacing any portion of a water of the U.S. with dry land or (2) changing the bottom elevation of any portion of a water of the U.S.”
A discharge of fill material means “the addition of fill
material into waters of the U.S.”
4
BUILDING STRONG®
Section 404 of the Clean Water Act
Under Section 404 of the Clean Water Act the Corps requires permits for discharges of dredged or fill material into waters of the United States in association with many types of activities
5
BUILDING STRONG®
Section 404 of the Clean Water Act
6
BUILDING STRONG®
Section 404 of the Clean Water Act
7
BUILDING STRONG®8
BUILDING STRONG®9
The Bottom Line……..
Every permit application we evaluate follows a predictable evaluation process
The rigor of the analysis is dependent on the type of resource being impacted, the degree and magnitude of the impact, the extent of the overall project that is subject to Federal control, and the extent of the effects to the public interest
It is our job to objectively evaluate the application and determine if the activity complies with the Section 404(b)(1) guidelines and is not contrary to the public interest
Section 404 Permitting
BUILDING STRONG®10
Section 404 Permitting
How we conduct our evaluations
Our permit evaluation process has three primary components: a NEPA evaluation, public interest determination, and a Section 404(b)(1) compliance determination
NEPA is a procedural requirement, the public interest review and Section 404(b)(1) compliance determination are substantive
BUILDING STRONG®11
Section 404 Permitting
Public Interest ReviewSection 404(b)(1)
GuidelinesNEPA Evaluation
Combined Decision Document
Permit Decision
BUILDING STRONG®12
Section 404 Permitting
General PermitsDeveloped for similar activities that individually and cumulatively have minimal effects
GPs include nationwide permits and regional general permits
Use of GPs provides for efficient and effective decision making
Letters of PermissionAn individual permit evaluated consistent with abbreviated processing procedures established by the district for impacts that are not controversial but do not comply with any available GP
Standard Individual PermitsAn individual permit with public comment opportunity and project-specific evaluation including Guidelines analysis, NEPA documentation and public interest review
BUILDING STRONG®
RGP-002-MN
Recognized Need Increase in potentially regulated activities on
agricultural lands Increased workload associated with regulated
activities on agricultural lands Trailing NRCS and state processes, resulting in time
delays for producers Timeframes associated with proposed work Complexities associated with jurisdictional
determinations/resource evaluations on agricultural lands
13
BUILDING STRONG®
RGP-002-MN
14
Issued in August 2013 and expires in August 2018. Provides a predictable permit review time frame for
activities that have been determined to have individually and cumulatively minimal effects on the environment.
To extent possible, aligns with NRCS and state Wetland Conservation Act programs
Gives MN producers a permit process similar to neighboring states, which have access to Nationwide Permit 40
BUILDING STRONG®
RGP-002-MN
15
Three primary categories of activities covered
1. Linear tile and culvert installation projects
2. Farmed wetland drainage projects
3. Installation of non-perforated drain tile in wetlands Structured to mimic the process in the nationwide
permits Relies on a well-established process used across
the country Corps must request more info within 30 days of
application, and make a decision within 45 days from receipt of a complete application
BUILDING STRONG®
Clean Water Act Exemptions
Section 404(f)(1)(A) of the CWA exempts certain agricultural activities from the permitting requirements of the Clean Water Act.
These activities include “normal farming, silviculture, and ranching activities such as plowing, seeding, cultivating, minor drainage, harvesting for the production of food, fiber, and forest products, or upland soil and water conservation practices.”
16
BUILDING STRONG®
Interpretive Rule
On April 21, 2014, the U.S. EPA and Army Civil Works published in the Federal Register an interpretive rule
This interpretive rule clarifies the permitting exemption provided under section 404(f)(1)(A) of the CWA to discharges of dredged or fill material associated with certain agricultural conservation practices based on Natural Resources Conservation Service conservation practice standards designed and implemented to protect and enhance water quality.
The IR became effective on April 3, 2014
17
BUILDING STRONG®
Interpretive Rule
18
The interpretive rule clarifies that 56 specific NRCS agricultural conservation practices are considered “normal farming” activities and are exempt from permitting under 404(f)(1)(A).
To qualify for this exemption, the activities must be part of an “established (i.e., ongoing) farming, silviculture or ranching operation” and the activities must be implemented in conformance with NRCS technical conservation practice standards.
BUILDING STRONG®
Interpretive Rule
19
Landowners do not need to determine whether discharges associated with these conservation practices are in waters of the United States and they do not need to obtain site-specific pre-approval from either the Corps or the EPA before implementation of these specified agricultural conservation practices.
CWA section 404(f)(2) is not affected by the interpretive rule and continues to apply.
The EPA, the Corps, and the USDA also have entered into a Memorandum of Understanding (MOU) to guide future coordination on the exemption.
BUILDING STRONG®
Interpretive Rule
20
The interpretive rule was first published in the Federal Register on April 21, 2014
Comments were requested by June 5th The comment period was re-opened on June 10th Comments are being accepted on the interpretive rule
until July 7th
Docket ID No. for submitting comments: EPA-HQ-OW-2013-0820
BUILDING STRONG®
Clean Water Act Exemptions
21
Specific Conservation Practices Listed as Exempt under 404(f)(1)(A)
(http://water.epa.gov/lawsregs/guidance/wetlands/CWAwaters.cfm)
BUILDING STRONG®
Clean Water Act Exemptions
22
Practice # Practice Name Creation Date Notes
314 Brush Management Sep-09
315 Herbaceous Weed control Apr-10
320 Irrigation Canal or Lateral Sep-20
326 Clearing and Snagging Sep-10
327 Conservation Cover Sep-10
338 Prescribed Burning Sep-10
342 Critical Area Planting Sep-10
353 Monitoring Well Sep-10
380 Windbreak/Shelterbelt Establishment
May-11
BUILDING STRONG®
Clean Water Act Exemptions
23
Practice # Practice Name Creation Date Notes
382 Fence Apr-13
383 Fuel Break Apr-05
386 Field Border Sep-10
388 Irrigation Field Ditch Apr-11
390 Riparian Herbaceous Cover Sep-10
391 Riparian Forest buffer Jul-10
393 Filter Strip Sep-10
394 Firebreak Sep-10
395 Stream Habitat Improvement and Management
Sep-10
396 Aquatic Organism passage Apr-11
BUILDING STRONG®
Clean Water Act Exemptions
24
Practice # Practice Name Creation Date Notes
398 Fish Raceway or Tank Sep-09399 Fishpond Management Sep-11400 Bivalve Aquaculture Gear
and Biofouling ControlApr-11
412 Grassed Waterway Apr-10 activities that convert waters to non-waters are not exempt
422 Hedgerow Planting Sep-10423 Hillside Ditch May-08453 Land Reclamation,
Landslide TreatmentFeb-05
455 Land Reclamation, Toxic Discharge Control
Apr-05
460 Land Clearing Sep-11484 Mulching Apr-11
BUILDING STRONG®
Clean Water Act Exemptions
25
Practice # Practice Name Creation Date Notes
490 Tree/Shrub Site Preparation Jan-06
500 Obstruction Removal Jan-10
511 Forage Harvest Management Apr-10
512 Forage and Biomass Planting Jan-10
528 Prescribed Grazing Sep-10
533 Pumping Plant May-11
544 Land Reclamation, Abandoned Mined land
Aug-06
544 Land Reclamation, Currently Mined Land
Aug-06
548 Grazing Land Mechanical Treatment
Sep-10 chiseling or deep ripping in wetlands is not exempt
550 Range Planting Apr-10
BUILDING STRONG®
Clean Water Act Exemptions
26
Practice # Practice Name Creation Date Notes568 Trails and Walkways Jan-10
575 Animal Trails and Walkways Apr-10
578 Stream Crossing Sep-11587 Structure for Water Control Apr-10
601 Vegetative Barrier Jan-10
612 Tree/Shrub Establishment May-11
643 Restoration and Management of Rare and Declining Habitats
Sep-10
644 Wetland Wildlife Habitat Management
Sep-10
646 Shallow Water Development and Management
Sep-10
647 Early Successional Habitat Development / Management
Sep-10
BUILDING STRONG®
Clean Water Act Exemptions
27
Practice # Practice Name Creation Date Notes650 Windbreak/Shelterbelt
RenovationJul-10
654 Road/Trail/Landing Closure and Treatment
Nov-08
655 Forest Trails and Landings Sep-11657 Wetland Restoration Sep-10659 Wetland Enhancement Sep-10660 Tree/Shrub Pruning Jan-06666 Forest Stand Improvement May-11
BUILDING STRONG®
Corps Points of Contact
28
BUILDING STRONG®
Points of Contact
Corps Project Managers currently are assigned by geographic area.
29
BUILDING STRONG®
Points of Contact
30
BUILDING STRONG®
Questions?
31