Page 1: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

City of CuritibaInstitute for Research and Urban Planning of Curitiba

Cléver Ubiratan Teixeira de AlmeidaPresident

Energy Efficiency in Cities: Curitiba’s Green LineWorld Bank’s Energy Week April 2009

Page 2: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

Curitiba: Seeking Energy Efficiency through a continuous urban planning process, resulting on creative, fast, economic, and integrated measures.

(video)

Page 3: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

The Green LineA new development axis in the city (under construction), integrating

land use to public transport and street network, promoting the integration of several areas and directly reaching 23 districts.

Page 4: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

PROJECT SITEPROJECT SITE CURRENT SITUATION

1. Former Federal road crossing the city;

2. Average of 45,000 vehicles/day

3. Service Zone

4. Automobile and heavy truck oriented

(low pedestrian safety)

5. Low urban integration (the road is a

urban barrier)

Page 5: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

SÃO JOSÉDOS PINHAISARAUCÁRIA

CAMPOLARGO

CAMPO MAGRO

ALMIRANTE TAMANDARÉCOLOMBO

PINHAIS

CENTENÁRIO

PINHAIS

BOQUEIRÃO

SÍTIO CERCADO

12 v/h

CAMPO COMPRIDO

PINHEIRINHO

20.000 PASS/PICO

130.000 PASS/D.U.NORTE - 23 v/h

OESTE - 14 v/h

SUL - 67 v/hBOQUEIRÃO - 41v/h

LESTE - 35 v/h

SANTA CÂNDIDA11.000 C. MÁXIMA

80% EIXO N/S

10.000 PASS/PICO

80.000 PASS/D.U. **

6.000 C. MÁXIMA

60% EIXO L/O

38.000 PASS/PICO

260.000 PASS/D.U.

21.000 C. MÁXIMA

80% EIXO N/S19.000 PASS/PICO

125.000 PASS/D.U.

11.000 C. MÁXIMA

75% RENOVAÇÃO

17.000 PASS/PICO

115.000 PASS/D.U. *

11.500 C. MÁXIMA

60% EIXO L/O

DIAGRAMA DASCARGAS MÁXIMAS

LEGENDA

BIARTICULADOLINHA DIRETA

6.0005.000

2.500

9.000

4.0007.000

7.000

14.000

3.000

3.000

* EXCLUSO PINHAIS/GUADALUPE - 14.739 PASS/D.U.** INCLUSO LIGEIRINHO CTBA/CAMPO LARGO - 7.865 PASS/D.U.

NÚMEROS ARREDONDADOS

CURRENT LOAD ON THE CURITIBA´S PUBLIC TRANSPORT SYSTEM:

1.Pressure and demand on the

existing North-South Axes

NORTH A

XIS

SO

UT

H A

XIS

GREE

N LIN

E

WEST AXIS

EAST AXIS

BO

QU

EIR

ÃO

AX

IS

Page 6: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

Specific Objectives

• Reduce the load on the north-south axes transport system;

• Increase the reach of the public transport system;

• Modernize the fleet of buses, using Bio Fuel;

• Reduce travel time;

• Increase the safety to pedestrians: public lighting, signaling;

• Improve road safety;

• Implement bike ways and sidewalks;

• Implement a boulevard along the axis, using native plants;

•Transform a former service zone into a mixed-use area increasing

density and providing services;

• Recover three existing urban parks along the axis.

Main Objectives

•Transform a former Federal road into an urban avenue, increasing the integration between districts in the city;

•Modernize the public transport system and broaden its access, specifically reaching the north, central, and south areas, following measures to assure environmental conservation.

GREEN LINE PROJECT

Page 7: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

(FUTURA)

THE GREEN LINE PROJECT

Total length: 18km23 districts affected(287,000 people)

The project is divided into 2 phasesPHASE 1: Extension 10kmBeginning of construction works: Jan 2007 / Beginning of operation: Apr 2009Investment: R$ 121 million (US$ 53 million)International funding (IDB): 60% / Counterpart City of Curitiba (PMC): 40%

Page 8: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

THE PROJECT: STREET NETWORK

Urban Integration

Page 9: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

THE PROJECT: STREET NETWORK

DEDICATED BUS LANE

THREE LANES

THREE LANES

LOCAL LANE + PARKING

LOCAL LANE + PARKING

Page 10: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

THE PROJECT: PUBLIC TRANSPORT

North Sector - 8 stations (+1 future)South Sector - 5 stations

Line 2 - Atuba/ Central Station

Line 3 - Atuba/ Pinheirinho

Line 1 - Pinheirinho/ Central Station

Page 11: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

2 lanes (3.5m each)

3 lanes (3.5m each)

3 lanes (3.5m each)

Local lane (6m)

Local lane (6m)

Bus Stations: 1km apart

THE PROJECT: PUBLIC TRANSPORT

Page 12: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

BusStations

THE PROJECT: PUBLIC TRANSPORT

Page 13: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

THE PROJECT: LAND USE AND ZONING

Building incentives

Mixed use

Development poles

Page 14: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

(FUTURA)

Atuba ParkAtuba Park

Portugal WoodsPortugal Woods

Municipal Garden/ Orchard Municipal Garden/ Orchard

BoulevardBoulevard

THE PROJECT: ENVIRONMENT

• Park: 21,000m2

• 5,200 trees, of 22 native species

• 18 Km of bikeways (6km in phase 1)

• Other works

Page 15: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

THE PROJECT: ENVIRONMENT

WATER

•Stations are provided with mechanisms to collect, store and reuse the rain water

ENERGY

•Use of energy efficient system for Public lighting

CONSTRUCTION WORKS WASTE MANAGEMENT PLAN

•Plan to warranty the correct final disposal of the construction works waste

Page 16: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

THE PROJECT: ENVIRONMENT

Buses running on Bio Fuel

Page 17: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

GREEN LINE EXPECTED OUTCOMES

• Improvement of the public transport system regarding quality and travel time;

• Enhancement of urban mobility and integration;

• Socioeconomic development for the project site and sourroudings;

• Improvement of environmental aspects.

Page 18: Clever de Almeida: Energy Efficiency in Cities - Curitiba's Green Line

www.curitiba.pr.gov.br

www.ippuc.org.br

Cléver Ubiratan Teixeira de Almeida

[email protected]