click to edit master text styles planning for a second ... · • click to edit master text styles...
TRANSCRIPT
![Page 1: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/1.jpg)
• Click to edit Master text styles – Second level
Slide Title
1
Planning for a Repipe
What you need to know before you get started
![Page 2: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/2.jpg)
• Click to edit Master text styles – Second level
Slide Title
2
Did you know? From the time you decide to repipe, it usually takes 20-30 weeks for construction to actually begin!
![Page 3: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/3.jpg)
• Click to edit Master text styles – Second level
Slide Title
3 3
What takes so long?
Owner Makes Decision to
Repipe
Select an Engineer / Architect
Plans and Specs are Bid Ready /
RFP Out To Contractors
Bids Received from
Contractors / Engineer Analysis
Engineer Presents
Clarified Pricing
Select Contractor /
Begin Contract Negotiations
Submit for Permit
Contract Signed Issue General Notice
Issue 30 Day Notice
Permit Approved / Begin Work
1-2 weeks 6-8 weeks 3-4 weeks 1-2 weeks
1 week
2-4 weeks
1 week (Domestic) - 8 weeks (DWV & Hydronic)
2 weeks
1 week 3 weeks 4 weeks
![Page 4: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/4.jpg)
• Click to edit Master text styles – Second level
Slide Title
4 4
Selecting an Engineer/Architect
During this stage: • The owner will need to make decisions on scope (is anything
getting upgraded, what’s included, etc?) • Owner gets bids from 2-3 Engineers/Architects • Owner selects Engineer/Architect
Owner Makes Decision to
Repipe
Select an Engineer / Architect
1-2 weeks
![Page 5: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/5.jpg)
• Click to edit Master text styles – Second level
Slide Title
5 5
Getting Ready to Issue the RFP
During this stage: • The engineer/architect will need to draw
a permit set of plans • Engineer will create specification
documents (“specs”) clarifying scope for bidders
• Final Request For Proposal (RFP) is assembled
• Bidders list of potential contractors is assembled and vetted
• RFP is issued to bidders
Select an Engineer / Architect
Plans and Specs are Bid Ready /
RFP Out To Contractors
6-8 weeks
![Page 6: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/6.jpg)
• Click to edit Master text styles – Second level
Slide Title
6 6
Contractors Submit Proposals
During this stage: • Contractors perform bid walks • Requests for Information (RFIs) are
issued and answered • Contractors develop and submit
proposals
Plans and Specs are Bid Ready /
RFP Out To Contractors
Bids Received from
Contractors / Engineer Analysis
3-4 weeks
![Page 7: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/7.jpg)
• Click to edit Master text styles – Second level
Slide Title
7 7
Engineer Evaluates Contractors Bids
During this stage: • Engineer reviews bids and asks clarifying
questions of contractors • Engineer performs price breakdown and
Statement of Work (SOW) comparison • Engineer reformats bids into comparable
template for Owner review • Engineer presents bids and makes a
recommendation to Owner
Bids Received from
Contractors / Engineer Analysis
Engineer Presents
Clarified Pricing
1-2 weeks
![Page 8: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/8.jpg)
• Click to edit Master text styles – Second level
Slide Title
8 8
Contractor Is Selected
During this stage: • Reference checks are completed • Contractor is selected
Engineer Presents
Clarified Pricing
Select Contractor /
Begin Contract Negotiations
1 week
![Page 9: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/9.jpg)
• Click to edit Master text styles – Second level
Slide Title
9 9
Contract Negotiations
During this stage: • Contractor provides value
engineering (if required) • Scope is finalized • Allowances are finalized • Engineer edits plans (as needed) • Start date is finalized • Contract terms are negotiated
Select Contractor /
Begin Contract Negotiations
Submit for Permit
Contract Signed
2-4 weeks
4 weeks
![Page 10: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/10.jpg)
• Click to edit Master text styles – Second level
Slide Title
10 10
Communications Begin
During this stage: • Contractor works with Owner to
develop and issue building wide general notice about the upcoming project
• Town Hall Meetings are scheduled
Contract Signed Issue General Notice
1 week
![Page 11: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/11.jpg)
• Click to edit Master text styles – Second level
Slide Title
11 11
Scheduling Begins
During this stage: • Pre-construction meeting occurs with
– Owner – Property Manager – Contractor
• Schedule is finalized and 30-day notices are issued to residents in the first stack
Issue General Notice
Issue 30 Day Notice
3 weeks
![Page 12: Click to edit Master text styles Planning for a Second ... · • Click to edit Master text styles – Second level Slide Title 5 Getting Ready to Issue the RFP During this stage:](https://reader033.vdocument.in/reader033/viewer/2022052001/601327f5dc04556d1b2d1e7c/html5/thumbnails/12.jpg)
• Click to edit Master text styles – Second level
Slide Title
12 12
Construction Begins
During this stage: • Town Hall Meeting is conducted • Mobilization occurs
– Storage/build-outs are staged – Materials arrive onsite – Dumpsters are placed onsite
• First units are pre-walked by the project manager
Issue 30 Day Notice
Begin Work 4 weeks