collaborative value-engineering management

38
Collaborative Value-engineering Management in Happy Valley Underground Stormwater Storage Scheme Drainage Services Department LUK Wai-hung

Upload: others

Post on 16-Oct-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Collaborative Value-engineering Management

Collaborative Value-engineering Management

in

Happy Valley Underground Stormwater Storage Scheme

Drainage Services Department

LUK Wai-hung

Page 2: Collaborative Value-engineering Management

Contents Project Background

Collaborative Value-engineering Management (CVM)

- Team Building

- Value Engineering

- Risk and Programme Management

Trust and Morale – Ups and Downs

Conclusion

2

Page 3: Collaborative Value-engineering Management

Project Background

3

Page 4: Collaborative Value-engineering Management

THE PROBLEM - FLOODING

4

Flood Depth (m) >0.45

0.15-0.45 <0.15

Causeway Bay

Happy Valley

Percival Street

Lap Tak Lane

Queen’s Road East

Happy Valley Recreation Ground and Race Course

Wong Nai Chung Rd

Over 26 ha of land was

flooded in 2000,2006,

2008 in Happy Valley and

Causeway Bay

4

Page 5: Collaborative Value-engineering Management

5

THE CONCERN

Happy Valley is a highly

congested urban area with

Horse Racings.

Open excavation would

induce significant

Environmental,

Traffic and Public

impacts to the Built

Environment.

5

Page 6: Collaborative Value-engineering Management

6

THE PROJECT- HVUSSS

HVUSSS Happy Valley

Underground

Stormwater Storage

Scheme

6

Page 7: Collaborative Value-engineering Management

Contract No. DC/2012/03 Contract Name Happy Valley Underground Stormwater Storage Scheme Employer Drainage Services Department PM/Supervisor Chief Engineer/DPD, DSD Scope of Works Construction of storage tank, box culvert, pump house Original Target Cost HK$ 678M

Duration Sep 2012 – April 2018 (64 months)

NEC3 Option Option C – Target contract with activity schedule

Contractor Chun Wo Construction & Engineering Co. Ltd.

QS Consultant Mott MacDonald Hong Kong Limited

NEC Advisor Arcadis / JCP

7

THE CONTRACT

Page 8: Collaborative Value-engineering Management

NEC3 Cl. 10.1:

among Employer, Project Manager, Supervisor, Contractor,…….

8

Mutual Trust and

Cooperation

Page 9: Collaborative Value-engineering Management

Collaboration

Employer Project Manager Supervisor Contractor Sub-contractor Stakeholders Consultants …..

9

Page 10: Collaborative Value-engineering Management

Collaboration

NEC3 : Risk Management Programme Management Compensation Events Open Book Account

Collaborative Value-engineering Management

10

360o Communication Active Subcontractor Management

Page 11: Collaborative Value-engineering Management

Collaborative Value-engineering Management (CVM) in HVUSSS

Click to show Video…

11

Page 12: Collaborative Value-engineering Management

In CVM, we develop mutual trust and cooperation by 360o communication network

12

Page 13: Collaborative Value-engineering Management

Stakeholders Workshop

District Council members, HKJC, LCSD, Contractor,

Subcontractors…

360o Communication Network

Team Building

36 WhatsApp

Groups in different categories

13

Page 14: Collaborative Value-engineering Management

Project Manager’s Staff

Cost consultants’ Staff

Team Building

Joint Office

Contractor’s Staff

Morning Briefing

14

360o Communication Network

Page 15: Collaborative Value-engineering Management

Team Building

15

360o Communication Network

Joint Organization Chart

Page 16: Collaborative Value-engineering Management

In CVM, we promote value-engineering by utilizing tools in NEC Contract

16

Page 17: Collaborative Value-engineering Management

Highest G.W.L. +5mPD G.L. +5mPD

+0.0mPD

Alluvial silt and clay

Fill

CDG / HDG

Bedrock

Original Foundation Design : 533 Pre-Bored H-Piles

Value-engineering

Pain/ Gain Share by Open Book Account

Initiative for Contractor to propose Cost-saving Design

17

Storage Tank

Page 18: Collaborative Value-engineering Management

Highest G.W.L. +5mPD G.L. +5mPD

+0.0mPD

Fill

Subsurface drainage Maintain water table below base slab

Subsurface drainage

Cut-off wall

Alluvial silt and clay

CDG / HDG

Bedrock

Subsoil Drain and Pumping

Water Harvesting System

Cost Saving Design: Cut-off Wall / Sub-surface Drainage System

Value-engineering

18

Pain/ Gain Share by Open Book Account

HKD $72M Saving HKD $ 678M Contract Sum

Storage Tank

Page 19: Collaborative Value-engineering Management

Sub-soil Drainage System

Treatment

Plant

Sub-soil Drainage System Treated Water

Storage

Chamber

Sports Pitches

Untreated

Water

Storage

Chamber Underground Stormwater Storage Tank

Ground Water

Rain

Water

Irrigation

Water

Toilet

Flushing

Value-engineering

CE about Water Harvesting System was issued within one month with no abortive works

19

Timely Assessment of Compensation Event

Page 20: Collaborative Value-engineering Management

Active Subcontractor Management

20

Value-engineering

Control Measures on Subcontract Package Selection Payment Finalisation

Concerns on Target Contract: ? Cost of work by subcontractor is reimbursable ? Contractor may have no incentive to selective most competitive offer

Page 21: Collaborative Value-engineering Management

Active Subcontractor Management

Tender Interview

Tender Briefing

21

Value-engineering

No. of finalized Subcontracts = 28 out of 126

49 no.

12 no. 42 no.

23 no.

39%

10% 33%

18%

Sum of awarded subcontracts

<=$50,000

>$50,000 &<=$200,000

>$200,000 &<=$4,000,000

>$4,000,000

Page 22: Collaborative Value-engineering Management

Active Subcontractor Management

Capture Innovative Proposal by Subcontractor

Alternative Turf Proposal

22

Save $3M out of $16M

Advance Progress by

1 month

Value-engineering

Page 23: Collaborative Value-engineering Management

In CVM, we manage risk and programme by utilizing tools in NEC Contract

23

Page 24: Collaborative Value-engineering Management

Early Warning and Risk Register

Risk and Programme Management

24

Pre contract : 9 Ground Condition Excessive Settlement Congested Working Environment Flood Risk

Construction : 44 Interfacing works with HKJC Delay in Access Date of Pitch No. 4 Lack of engineering and site resources Slow progress of different work fronts Missing details Defects

Page 25: Collaborative Value-engineering Management

Early Warning and Risk Register

Risk and Programme Management

25

PM Contractor

27 26

Open Closed

9 44

Pre –Contract Construction

9 44

Time to Close No.

1 – 60 days 11

61-120 days 18

>120 days 15

By PM (27)

By Contractor

(26)

Number of Early Warnings

Pre-Contract Stage (9)

Construction Stage (44)

Open (9)

Closed (44)

1 - 60 days 25%

61 - 120 days 41%

>120 days 34%

Time required for closing the Early Warnings

Page 26: Collaborative Value-engineering Management

Collaboration in Risk and Programme Management

Risk and Programme Management

Tight Schedule, High Project Risk

Interface construction works of HKJC and DSD during summer break of 2014

26

Page 27: Collaborative Value-engineering Management

Collaboration in Risk and Programme Management

Risk and Programme Management

27

27.05.2014

Page 28: Collaborative Value-engineering Management

Haul road over Box Culvert to be used by both DSD and HKJC

In/ out

Southern Connection

Construction Vehicles in the loop Construction Vehicles in/out via subway

HKJC proposed haul road in DSD works area

Storage area

Box Culvert by DSD

Stage 1 Tank by DSD

Box Culvert need early completion

Risk and Programme Management

Collaboration in Risk and Programme Management

28

Western Connection

Page 29: Collaborative Value-engineering Management

Construction of Pipe Pile Wall at Crescent Garden

Stilling Basin & Box Culvert (DSD-Chun Wo)

Mar 2014 – Jan 2015

Box Culvert (HKJC - Gammon)

Jun – Jul 2014

29

Risk and Programme Management

Collaboration in Risk and Programme Management

29

Shared Access

Page 30: Collaborative Value-engineering Management

Race Track

Shoring Layout Plan

Sectional Plan

Race Track

DSD’s Works Area

DSD’s Works Area

Risk and Programme Management

Collaboration in Risk and Programme Management

Shared ELS system

30

30

Page 31: Collaborative Value-engineering Management

Collaboration in Risk and Programme Management

Risk and Programme Management

Shared Access

Gammon Chun Wo

31

Gammon Chun wo

Shared ELS System

Page 32: Collaborative Value-engineering Management

Collaboration in Risk and Programme Management

Risk and Programme Management

Management Involvement from both sides 32

29.09.2014

Page 33: Collaborative Value-engineering Management

Trust and Morale – Ups and Downs

33

Page 34: Collaborative Value-engineering Management

Trust: Ups and Down

34

Page 35: Collaborative Value-engineering Management

Morale

35

Page 36: Collaborative Value-engineering Management

Achievement

36

Awards

(photo taken at the prize presentation ceremony held in London, UK, April 2015)

Highly Commended New Engineering Contract (NEC) Large Project of the Year 2015 Award by NEC Users’ Group in UK

Page 37: Collaborative Value-engineering Management

ACHIEVEMENTS in progress, cost, quality and safety

CERTAINITY of risks about time and cost for all parties

TRUST has to be earned

EFFORT has to be paid for the achievements

37

Conclusion

37

Page 38: Collaborative Value-engineering Management

38

Thank You