colorado disaster recovery - aswm.org · •117 total flood recovery projects completed (68 ewp)...
TRANSCRIPT
![Page 1: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/1.jpg)
COLORADO DISASTER RECOVERYLESSONS LEARNED
A GUIDE TO PLAN, REACT, ADAPT, EVOLVE, AND ACHIEVE THE BEST POSSIBLE OUTCOMES FOR OUR COMMUNITIES AND STREAM CORRIDORS
NFFA Webinar: Disaster Recovery Lessons Learned. May 12, 2020
Authors: Jeff Sickles, Katie Jagt, Michael Blazewicz. Some rights reserved.
![Page 2: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/2.jpg)
A WATERSHED APPROACHBACKGROUND ON COLORADO’S RECOVERY PROGRAM
![Page 3: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/3.jpg)
THE FLOOD OF 2013
![Page 4: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/4.jpg)
WATERSHED BASED FLOOD RECOVERY
• Support watershed coalitions as a model for stakeholder engagement
• Execute projects with multiple objectives
• Incorporate resiliency into every project
• Protect life and property while restoring ecological processes that connect land and water
• Complete recovery work on a watershed scale
• Support early planning to identify root issues, develop holistic solutions, and allow time to secure appropriate funding
![Page 5: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/5.jpg)
• 117 total flood recovery projects completed (68 EWP)
• Total construction costs of over $70 million(~$50 million EWP)
• Over $270 million – value of infrastructure and private structures protected
• 65 miles of river and floodplain improvements implemented (40 miles EWP)
• 12 watershed master plans finalized
• 34 resiliency planning studies completed
• 23 comprehensive recovery planning studies completed
• Over 700 private property owners engaged
• $4.2 million across 10 coalitions for capacity building staffing grants. CWCB supplemented this with an additional $400,000.
*These are numbers for the CWCB and DOLA led recovery efforts for the 2013 flood.
RECOVERY: BY THE NUMBERS
![Page 6: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/6.jpg)
HOW AND WHY OF LESSONS LEARNED
• Recommendations that will allow state and federal disaster response programs to implement more resilient and holistic recovery actions (noted as Recommendations for Changes to State and Federal Disaster Response).
• Actions to implement immediately after a disaster has occurred (noted as Recommendations for Disaster Recovery Actions).
• Action items that can be completed by a community ahead of the next disaster (noted as Recommendations for Pre-Disaster Actions).
![Page 7: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/7.jpg)
![Page 8: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/8.jpg)
ORGANIZING FOR RECOVERYWITH ORGANIZATION COMES EMPOWERMENT
![Page 9: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/9.jpg)
DEVELOP A CENTRAILIZED RECOVERY PROGRAM THAT CAN SUPPORT A COMPREHENSIVE VISION
1Reduce Hazards and Protect Life Safety
and Property
2
3
4
5
Use Federal and State Funding Effectively
Enhance the Health and Resilience of
Watersheds and Stream Corridors
Build Capacity of Watershed Coalitions
Advance a Watershed Approach to Flood
Recovery
ORGANIZING FOR RECOVERY
![Page 10: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/10.jpg)
ORGANIZING FOR RECOVERY
![Page 11: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/11.jpg)
MAXIMIZE THE BENEFIT OF FEDERAL FUNDING THROUGH CENTRALIZED LEADERSHIP AND ORGANIZATION
RECOVERY
FUNDING
LOCAL
SPONSORS
ORGANIZING FOR RECOVERY
![Page 12: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/12.jpg)
MAXIMIZE THE BENEFIT OF FEDERAL FUNDING THROUGH CENTRALIZED LEADERSHIP AND ORGANIZATION
RECOVERY
FUNDING
LEAD
RECOVERY
AGENCY
LOCAL
SPONSORS
• Provides funding and program oversight,
• Addresses programmatic requirements
such as environmental compliance
• Sets the recovery vision
• Provides partial match funding
• Sets guidelines and standards
• Communication with local stakeholders
• Oversees project implementation
• Raises local match
• Commits to O&M
• Creates a program Technical
Assistance team to support
program management, design,
construction oversight, and QA.
• Set program expectations, e.g.
get away from overly restrictive
design requirements that are
inappropriate for stream
rehabilitation (e.g. 100% design)
RESPONSIBILITIES
OPPORTUNITIES
ORGANIZING FOR RECOVERY
![Page 13: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/13.jpg)
AUTHORIZE STATE AND LOCAL RECOVERY FUNDING
• Get people working
• Keep local disaster recovery money as flexible as possible
• Use local funding for recovery plans
• Leverage local dollars for construction match
ORGANIZING FOR RECOVERY
![Page 14: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/14.jpg)
PROJECT EXAMPLE: Colorado Recovery Planning
• Funding for master planning was made available via CWCB
• Move watershed coalitions and communities towards prioritization and implementation of recovery projects:
• Reduced flood and geomorphic hazards
• Improved ecological conditions
• The master plans defined each watershed’s vision for recovery and enhanced the community’s understanding of the river corridor and associated risks
ORGANIZING FOR RECOVERY
![Page 15: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/15.jpg)
A TALE OF TWO RECOVERY PROGRAMS
ORGANIZING FOR RECOVERY
![Page 16: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/16.jpg)
SHARED CORRIDORSRIVERS, ROADS, AND RESIDENCES
DISASTER RESPONSEGUIDING EMERGENCY EFFORTS TOWARDS RESILIENT LONG-TERM OUTCOMES
+
![Page 17: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/17.jpg)
Getting the foundation for a successful long-term design set immediately after the flood in the emergency response actions is imperative for recovery success.
DISASTER RESPONSE & SHARED CORRIDORS
![Page 18: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/18.jpg)
WHAT DO STREAMS LOOK LIKE IMMEDIATELY FOLLOWING A FLOOD?
Big Thompson River, Drake, ColoradoDISASTER RESPONSE & SHARED CORRIDORS
![Page 19: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/19.jpg)
AND WHY DO THEY LOOK SO DIFFERENT A FEW MONTHS LATER?
Big Thompson River, Drake, ColoradoDISASTER RESPONSE & SHARED CORRIDORS
![Page 20: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/20.jpg)
REFRAME THE FLOOD: From a “river problem” to a “human problem”
DISASTER RESPONSE & SHARED CORRIDORS
![Page 21: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/21.jpg)
THE 2013 FLOOD RESPONSE REFRAMED
Large Wood and
Small Wood Debris
Jam
Side Channel
Cutoff Chute
Tyranny of the Single
Thread
Depositional Area—Not
Erosional!Cutoff Chutes and
Side Channels
Destroyed
Riprap to halt erosion
Large Wood and
Small Wood Gone
DISASTER RESPONSE & SHARED CORRIDORS
![Page 22: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/22.jpg)
POST-FLOOD EMERGENCY REPAIRS
DISASTER RESPONSE & SHARED CORRIDORS
![Page 23: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/23.jpg)
Negative Ecosystem Impacts: CPW POST-FLOOD
Fish Survey Data
DISASTER RESPONSE & SHARED CORRIDORS
![Page 24: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/24.jpg)
Streams need space to accommodate their energy and sediment
DISASTER RESPONSE & SHARED CORRIDORS
![Page 25: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/25.jpg)
Conceptual Model of Energy Continuity
DISASTER RESPONSE & SHARED CORRIDORS
![Page 26: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/26.jpg)
Conceptual Model of Energy Continuity: Channelized
DISASTER RESPONSE & SHARED CORRIDORS
![Page 27: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/27.jpg)
Shared Corridors: Consider the difference between addressing a problem and
transferring a problemDISASTER RESPONSE & SHARED CORRIDORS
![Page 28: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/28.jpg)
DISASTER RESPONSE & SHARED CORRIDORS
![Page 29: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/29.jpg)
Colorado Disaster
Recovery: Lessons
Learned
County Road 43
Larimer County—FHWA project
DISASTER RESPONSE & SHARED CORRIDORS
![Page 30: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/30.jpg)
DISASTER RESPONSE & SHARED CORRIDORS
![Page 31: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/31.jpg)
Disaster Response and Shared Corridors
TEMPORARY BECOMES PERMANENT
DISASTER RESPONSE & SHARED CORRIDORS
![Page 32: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/32.jpg)
FLOOD RECOVERY PLANNINGVALUES, GOALS, AND OBJECTIVES
![Page 33: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/33.jpg)
FLOOD RECOVERY PLANNING
![Page 34: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/34.jpg)
FLOOD RECOVERY PLANNING
![Page 35: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/35.jpg)
FLOOD RECOVERY PLANNING
![Page 36: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/36.jpg)
FLOOD RECOVERY PLANNING
![Page 37: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/37.jpg)
FLOOD RECOVERY PLANNING
![Page 38: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/38.jpg)
PROJECT IDENTIFICATION AND SCOPINGLAYING THE FOUNDATION FOR SUCCESSFUL RECOVERY
![Page 39: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/39.jpg)
PROJECT IDENTIFICATION & SCOPING
![Page 40: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/40.jpg)
PROJECT IDENTIFICATION & SCOPING
![Page 41: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/41.jpg)
PROJECT IDENTIFICATION & SCOPING
![Page 42: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/42.jpg)
PROJECT IDENTIFICATION & SCOPING
![Page 43: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/43.jpg)
PROJECT IDENTIFICATION & SCOPING
![Page 44: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/44.jpg)
PROJECT IDENTIFICATION & SCOPING
![Page 45: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/45.jpg)
CONSTRUCTIONMAKING THIS OPPORTUNITY COUNT
![Page 46: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/46.jpg)
CONSTRUCTION
![Page 47: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/47.jpg)
CONSTRUCTION
![Page 48: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/48.jpg)
CONSTRUCTION
![Page 49: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/49.jpg)
CONSTRUCTION
![Page 50: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/50.jpg)
CONSTRUCTION
![Page 51: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/51.jpg)
CONSTRUCTION
![Page 52: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/52.jpg)
CONSTRUCTION
![Page 53: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/53.jpg)
MONITORING AND ADAPTIVE MANAGEMENT
![Page 54: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/54.jpg)
PRE-DISASTER PLANNINGPREPARING FOR THE FUTURE
![Page 55: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/55.jpg)
Pre-Disaster PlanningRoles and RelationshipsAdequately identify all hazards in the corridor.Pre-identify Project Areas (i.e., response zones)
![Page 57: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/57.jpg)
RECOVERY RESOURCESHIT THE GROUND RUNNING
![Page 59: COLORADO DISASTER RECOVERY - aswm.org · •117 total flood recovery projects completed (68 EWP) • Total construction costs of over $70 million (~$50 million EWP) • Over $270](https://reader034.vdocument.in/reader034/viewer/2022043001/5f7b38c93d6a3a6876101efa/html5/thumbnails/59.jpg)
THANK YOUQuestions?
Jeff Sickles, Enginuity [email protected]
Katie Jagt, Watershed Science & Design [email protected]
Michael Blazewicz, Round River Design [email protected]