Appendix A
City of Lincoln Council
Combined Assurance Status Report
February 2017
Combined Assurance Status Report
Introduction 1
Key Messages 3
Critical Systems 5
Key Projects 10
Key Partnerships 12
Key Risks 13
The contacts at Assurance Lincolnshire for this review are:
John Scott
Audit Manager (Head of Internal Audit)
Paul Berry
Principal Auditor
Combined Assurance Status Report
1
Introduction
This is the fifth combined assurance report for the Council.
By grouping the different sources of assurance in a single model we provide the basis for Senior Management and the Audit Committee to gain a better understanding of their organisations assurance status and needs. We do this by coordinating assurance arrangements – providing some structure – this is the Assurance Map. We have well established Assurance Maps that help us to focus our work plans on the make or break risks that affect the successful delivery of services and strategic objectives. The Map also recognises the importance of critical business systems that support successful delivery and ‘protect the business’ – the due diligence activities. The Map gives an overview of assurance provided across the whole organisation – not just those from Internal Audit – making it possible to identify where assurances are present, their source, and where there are potential assurance ‘unknowns or gaps’. The Map is an invaluable tool for senior managers, providing a
snapshot of assurance at any point of time. This report
explores those assurances in more detail.
We gathered and analysed assurance information in a control
environment that:
takes what we have been told on trust, and
encourages accountability with those responsible for managing the service.
Scope
We gathered information on:
Critical systems – those areas identified by senior
management as having a significant impact on the
successful delivery of our priorities or whose failure could
result in significant damage to our reputation, financial loss
or impact on people.
Due diligence activities – those that support the running
of the Council and ensure compliance with policies.
Key risks – found on our strategic risk register,
operational risk registers or associated with major new
business strategy / change.
Key projects –supporting corporate priorities / activities.
Key partnerships – partnerships that play a key role in
successful delivery of services
Combined Assurance Status Report
2
Methodology
To ensure our combined assurance model shows assurances
across the entire Council, not just those from Internal Audit,
we leverage assurance information from your ‘business as
usual’ operations. Using the ‘3 lines of assurance’ concept:
Our approach includes a critical review or assessment on the
level of confidence the Council can have on its service
delivery arrangements, management of risks, operation of
controls and performance.
We did this by:
Speaking to senior and operational managers who have the day to day responsibility for managing and controlling their service activities.
Working with corporate functions and using other third party inspections to provide information on performance, successful delivery and organisational learning.
Using the outcome of Internal Audit work to provide independent insight and assurance opinions.
Considering other information and business intelligence that feed into and has potential to impact on assurance.
We used a Red (low), Amber (medium) and Green (high) rating to help us assess the level of assurance confidence in place.
The overall assurance opinion is based on the assessment and judgement of senior management. Internal audit has helped co-ordinate these and provided some challenge but as accountability rests with the Senior Manager we used their overall assurance opinion.
• Accountable for Delivery Management
• External Inspections & Internal Assurance
Functions
Corporate and Third Party
• Independent Assurance Internal Audit
Combined Assurance Status Report
3
Key Messages
We identified 78 critical services/systems, 27 projects (8 current SPIT projects and 19 strategic plan projects) and 7 strategic risks. Out of the total of 112 areas;
84 have Green assurance (76%)
24 have Amber assurance (22%)
3 have Red assurance (2%) All assurance ratings have improved compared to 2015/16. Critical services/systems; 60 Green (77%), 15 Amber (19%) & 3 Red (4%) – see pages 5-9 for further details and graphs. Strategic / SPIT Projects; 19 Green (69%) & 8 Amber (31%) – see pages 10-11 for further details and graphs. Strategic Risks; 6 Green (86%) and 1 Amber (14%) – see pages 13-14 for further details and graphs.
Red Amber Green
2%
22%
76%
Overall Assurance Status 2016/17
Red Amber Green
7%
28%
65%
Overall Assurance Status 2015/16
Combined Assurance Status Report
4
Suggested next steps……
This is a positive report and shows an improving assurance
position. Plans are in place to manage any mitigate any
Amber or Red assurances.
Combined Assurance Status Report
5
Critical Systems
78 critical services/systems were identified and of these
management considered 60 (77%) to be Green and 15 (19%)
to be Amber and 3 Red. (4%)
Internal Audit provided assurance on 53% of areas (within the
last 3 years plus current year) 16% of areas not recorded as
previously reviewed.
4%
19%
77%
Red
Amber
Green
Unknown
Management
Corporate & 3rd Party
Internal Audit
100%
27%
51%
Who Provides Your Assurance
Combined Assurance Status Report
6
Chief Executives Directorate
Within the Chief Executives Directorate, the following key
services / critical systems operate
• CX Business Management, Legal, Electoral Services,
Democratic Services, Procurement, HR (and payroll),
Workbased Learning, Civic and Twinning
• Finance, Insurance, Creditors, Debtors, Risk
Management, Audit, Commercialism, Revenues, Benefits,
Property Services
• Communications, Business Strategy, Performance,
Strategic Information Provision, Social Policy (Anti-Poverty /
Community Cohesion), Partnership management, Business
Development and ICT, Customer Services
The following services received a green assurance:
CX Business Management
Democratic Services,
Civic and Twinning
Finance,
Creditors,
Debtors,
Risk Management,
Audit,
TOFS
Revenues; NNDR, CTS, Recovery, Council tax, Benefits
Property Services
Managed Workspaces
Small Business Support
Business Strategy,
Performance management
Equality and diversity
Corporate governance
Strategic Information Provision,
Social Policy (Anti-Poverty / Community Cohesion), Partnership management
Business Development and ICT,
Customer Services
Project management (frameworks)
Corporate Governance
Equality and Diversity
Partnership governance
Business Continuity The Amber and Red assurance areas are; Legal – The information governance project is making good progress; there is further work to complete and resources have been secured for 2017/18. Addressing the forthcoming EU data protection regulation will be part of this work. Vision 2020 project support around growth will be significant and legal work complex and resources will be carefully managed. Ongoing work around Transport Hub, Boultham Park and
Combined Assurance Status Report
7
Housing (including Housing Company) remains Amber until completion. Further Member Code of Conduct training will be provided. Elections-Further training on elections is required internally in the short term; appropriate external support will be obtained. Procurement-Good compliance but there are some resource pressures. Procurement Lincolnshire involvement will cease as of 1.4.18 and preparations for that are underway. Updated Contract Procedure roll out for 2017/18. HR/payroll The new People strategy is on track; there are several linked projects including appraisal, recruitment, managing attendance, and training to be completed. There could be changes to the job evaluation scheme. There is also a new OH provider and new agency worker contract transition to manage. Payroll responsibilities in some areas need to be clarified and the overtime/enhancement project has not progressed as expected. Work based learning-current changes and risks to apprenticeship funding is being project managed. The Government is introducing a new apprenticeship levy and the impacts are being assessed. Insurance-With the loss of the insurance officer arrangements are in place for further external support and more input from service areas. Communications-delivery is good; there are risks in achieving the commercial financial target set Counter Fraud – The counter fraud partnership continues; there is a refreshed CF strategy, action plan and fraud risk register. However there are a lack of resources generally to take on much pro-active work outside of fraud partnership and NFI and SFIS engagement. This includes CTS fraud, tenancy fraud.
Property Services-Facilities Management - new asset management plan required and scheduled for 2017/18. Asset review programme has been taking place. Still an area where there is insufficient resource and the AMP would Assist. Business Continuity (RED) - IT Disaster recovery project well underway; still to complete IT DR plan. Updating BCP's currently to tie in with IT DR; remains Amber until this work is completed Other areas (green assurance): benefits subsidy claim still qualified; but this will take time to reverse. Finance is overall green assurance but TOFS remains Amber due to 18/19 target achievement. There are new Financial Regulations due out in early 2017/18; there are some compliance concerns. Customer service is overall green but telephony remains Amber – a new system will be in place shortly. A new Customer experience strategy will be completed shortly. Further work to complete on “channel shift” projects to maximize outcomes. Work has commenced on the reshaping local government agenda – which is also a strategic risk.
Combined Assurance Status Report
8
Communities and Environment Directorate
The following services received a green assurance: Planning (Development Management) Planning policy (Joint Strategic Planning) Planning (Heritage) Public Protection and anti-social behaviour CCTV Parks & Open Spaces & Allotments Street Cleansing Grounds Maintenance Waste Public Conveniences Car Parks Bus Station Environmental Protection Pollution Control Food safety Licensing Community Centres Crematorium and Cemeteries Events, Culture and Tourism The Amber and Red assurance areas are; Strategic waste management – Recycling rates have not continued to improve, and contamination of recycling streams has become more of an issue. Ultimately these could pose operational and financial challenges if service changes are
required to address these issues. The district Councils have submitted a proposal to the County Council on how to address contamination, but this has been rejected on grounds of cost. The County Council are now seeking to link both the contamination issue and their new contract for handling recycling material through the development of a new Joint Municipal Waste Management Strategy, which is being developed currently. Health & Safety Expectation that following audit of CHS (Health and Safety development plan) in quarter 4 that will become green; incident reporting and risk assessment gone live - monitoring implementation. Responsible Officer roles to complete. Private Sector Housing – looking to improve the rate of DFG grant delivery; options for the delivery of a future emergency grant scheme. The trusted landlord scheme needs implementing 2017/18 and plan being developed. Empty Homes strategy to be refreshed. Applied for further rogue landlord funding. HMO are key focus; more structured plan being developed. Mandatory HMO licensing will increase significantly 17/18. Sport and Leisure (RED) - Still trying to resolve tri-partite agreement and identify/assess mitigation options. Market income down. Neighbourhood working (RED)- Consultation commenced on refocus of NW for the City. Building Control - income level is still a risk Other areas (green assurance): a new public health strategic partnership is being developed. The Greater Lincs local plan – anticipating inspectors report mid- March 2017.
Combined Assurance Status Report
9
A review of health and safety processes and procedures
associated with open space management is identifying some
benefits from updating certain elements. This is expected to
place an additional burden on existing staff resources,
impacting other street scene services.
Housing and Regeneration Directorate The following services received a green assurance: Housing Business Support HRA/Landlord Services (Tenancy Services) Supported Housing Void Properties Lincare / Control Centre Housing Repairs Service Housing Investment Safety Assurance Choice based lettings/housing allocations Growth and Regeneration Environmental Strategy Economic Development Housing Strategy and Enabling The Amber and Red assurance areas are;
Property Shop/Choice based Letting and Registration-There are current issues with the CBL software which are being addressed and revising procedures. Homelessness- Legislative changes are coming forward which will mean the Council is responsible for more people. We need to focus on prevention and this work is being started now. There is an increase in applications, it is increasingly harder to place in private accommodation, less affordable rents and LHA caps; private landlord and rent deposit schemes are being reviewed; Other areas (green assurance): A new rechargeable repairs policy has been introduced which requires full implementation; there is a new stores contract for City maintenance services and the location of new stores. The Council will be seeking accreditation of the Housing tenant ASB charter – Respect - in 17-18. The Directorate continues with its new build housing investments including establishing a new Housing company. The housing strategy will be completed and approved. Major Developments Directorate The following services received a green assurance: Growth (Regeneration strategy & delivery) Supporting strategic infrastructure projects Investments (large business enquiries, local business support, promotion of the city)
Combined Assurance Status Report
10
Other areas(green assurance): Growth challenges outlined
in the Vision 2020 plan – attracting investment, housing, skills,
renewal areas. Reviewing WGC and costings.
Combined Assurance Status Report
11
Projects
Overall Comments
The Council has a range of strategic projects linked to the
previous strategic plan, transformation and capital schemes.
There are currently 18 Strategic Plan and 8 current SPIT
(Strategic Plan Implementation Team) projects.
Once a new monitoring process is agreed these strategic
projects will be replaced by the new projects from Vision 2020.
18 are rated as Green
8 are rated as Amber
Amber or Red assurance projects are:
SPIT:
Compulsory Acquisition - 13 Albany Terrace
Data Recovery and Back Up
Strategic Plan (2015-17):
There are 35 Strategic Plan projects currently under
consideration. As of 31st January 2017 of the 35 monitored
projects there are 14 completed projects (3 of these
completed in this period); 1 is classified as off track, 6 have
0%
31%
69%
0%
Red
Amber
Green
Unknown
Combined Assurance Status Report
12
some slippage and 12 that are on track. There are a further 2
projects that are classed as deferred or merged.
Of the 19 remaining live projects – 6 are almost complete; 10
are continued in the Vision 2020 and just 3 have been
dropped (Devolution; the specific combined heat and power
for WGC project and the idea for an energy service company
(ESCO))
Amber projects (some slippage – not causing significant
issues):
There are six amber projects, none of which are causing
serious concerns.
These are:
Development of Central Lincolnshire local plan
Development of a Business prospectus
Increase opportunities for locals people to access training and then employment
Implementation of landlord accreditation scheme
Deliver empty homes strategy
Seek accreditation of the Housing tenant ASB Charter Management of Risk
Each project is assigned a project manager and suitable
corporate support is identified. Project performance is
managed through SPIT (Strategic Plan Implementation Team)
or a separate Board. TOFS (Towards Financial Sustainably
Board) projects are managed through a TOFS Board.
Mega projects have their own project governance and Board
frameworks. There are 4 Mega projects; Boultham Park,
Transport HUB and Western Growth Corridor plus Housing
new Build/Delivery Group.
Another area of focus is the Lincoln Anti-Poverty Action Plan
which has a range of projects and actions. Some key areas
have been included within Vision 2020.
The Executive receive information on all projects.
We are conscious of the need to ensure that all projects are
properly resourced whilst maintaining the ability to deliver day
to day services.
As well as the key corporate projects identified in this section,
there are also smaller projects delivered across the Council.
We are satisfied that appropriate mechanisms and processes
are in place to manage the Council’s major projects.
Combined Assurance Status Report
13
Partnerships
Overall Comments
Significant work has been completed reviewing partnerships
over the last 12-18 months ensuring that governance
arrangements are in place and that the right officers and
members are representing the City Council. There is a key
partnership register covering both member and officer
involvement. The Chief Executive has been pro-active in
connecting with key partners - this is ongoing and includes
The Chamber of Commerce, Universities, Police, Greater
Lincolnshire LEP and others. There is currently a piece of
work around Growth and engagement with stakeholders and
key partners.
Management of Risk
• Governance arrangements are in place for all significant
partnerships, working to agreed terms of reference and
incorporating performance management aspects. Partnership
guidance document rolled out during 2013/14 is currently
being updated.
• We interact with the voluntary sector and have built strong
relations with those bodies supporting the council’s strategic
priorities- in particular the Third Sector Infrastructure Body for
Lincoln – Voluntary Centre Services, which is now located in
City Hall.
Management have not identified any non-compliance with the
Council’s partnership / joint working corporate guidance.
Internal Audit will carry out a partnerships internal audit in
2017/18 to obtain independent assurance on partnership /
joint working governance.
Combined Assurance Status Report
14
Risks
Strategic Risks
The Council has 7 Strategic Risks – 3 are assessed as Red
and 4 as Amber. The Red risks are;
All risks are being actively managed in accordance with the
Risk Management Framework.
Amber strategic risks are:
To deliver a sustainable Medium term Financial
Strategy
Deliver the Towards Financial Sustainability
Programme whilst ensuring the resilience of the
Council
Meet the emerging changes required in the Council’s
culture, behaviour and skills to support the delivery of
the council’s Vision 2020 and the transformational
journey to a “performance culture”.
Ensure sufficient levels of resilience and capacity exist
in order to deliver key strategic projects within the
Council
The Council has an active approach to risk management and
has reviewed the key strategic risks facing the Council.
As well as the risks identified in this section, Managers identify
operational risks and these are managed through similar
processes.
• Engaging with the Council’s strategic partners
and stakeholders to deliver against the Council’s
Vision 2020.
• • To ensure compliance with statutory duties
and appropriate governance arrangements are in
place, including: Health & Safety, Information
Management/IT Security, ICT Disaster
Recovery
• Develop an appropriate strategic response to the
changing structures in Local Government
Combined Assurance Status Report
15
Strategic risks are managed through CMT and are reported
through the Performance Scrutiny Committee / Executive.
Each risk is managed through a member of the Corporate
Management Team.
Overall, risks are clearly identified and well managed by the
Council.
All Strategic Risks have a management assurance which
reflects how well the risk is being managed rather than the risk
score;
All strategic risks have Green management assurance, with
the exception of the strategic response to the changing
structures in Local Government.
Operational Risks
There are three operational (Directorate) risk registers. There
are four Red risks linked to:
Recycling rates - Proposal made by Districts to County
to address recycling rates- response awaited
Failure to meet the Affordable Homes target – a key
target of the Housing Strategy – various
initiatives/projects to mitigate risk
Management of financial pressures (DCE) (TFS
programme; Income targets; Tripartite Agreement; Unfunded
budget pressures; Managing growth; Car parking income levels
during Hub construction
Failure to maintain properties/facilities safely, in
accordance with Council’s tree of responsibility - Individuals who haven’t accepted responsibilities to be targeted for
resolution
All risks are being actively managed in accordance with the
Risk Management Framework
Emerging Risks
No red emerging risks have been identified that are not
already identified within existing risk registers and service
plans.
Combined Assurance Status Report
16