commissioning chart

21
CES Commissioning Guidelines Revision No. 0: 5/95 Test Plans 6-234 VERIFICATION and FUNCTIONAL PERFORMANCE TEST PLAN for PACKAGED AIR-COOLED CHILLER including PRE-STARTUP INSPECTION CHECKLIST, VERIFICATION TEST CHECKLIST, and FUNCTIONAL PERFORMANCE TEST CHECKLIST

Upload: sarif-islam

Post on 30-Sep-2015

16 views

Category:

Documents


2 download

DESCRIPTION

Flow chart

TRANSCRIPT

  • CES Commissioning Guidelines

    Revision No. 0: 5/95 Test Plans 6-234

    VERIFICATION

    and

    FUNCTIONAL PERFORMANCE TEST PLAN

    for

    PACKAGED AIR-COOLED CHILLER

    including

    PRE-STARTUP INSPECTION CHECKLIST,

    VERIFICATION TEST CHECKLIST,

    and

    FUNCTIONAL PERFORMANCE TEST

    CHECKLIST

  • CES Commissioning Guidelines

    Revision No. 0: 5/95 Test Plans 6-235

    6.10.1 High-Efficiency Packaged Air-Cooled

    Chiller

    Commissioning Process Summary

    The Commissioning Process for the high-efficiency packaged air-cooled chiller EEM

    includes pre-startup inspections of the installed equipment, systems, and subsystems,

    and the execution of the verification and functional performance testing of the chiller,

    pumps, and chiller control system. The fundamental operational and performance

    parameters to be verified through the testing include 1) drop in chilled water

    temperature across the evaporator (T, F), 2) chilled water flow rate (gpm), 3) electrical power consumption of the chiller and chilled water pump (kW), 4) chiller

    efficiency (kW/ton) under full-load and part-load operation, and 5) function of the

    system controls sequences.

    These performance parameters will vary depending on the systems operating conditions. Although manufacturers performance data can typically be obtained for most chillers, the actual in situ performance of a chiller may vary considerably. This

    performance, to be determined accurately, should be evaluated within the context of

    the entire chiller system. Therefore, actual field monitoring of a chiller system in

    accordance with an established monitoring protocol is often required.

    A protocol for monitoring chiller-system performance has been provided in Section

    3.6.2 of these Guidelines for use during the functional performance testing. The scope

    of the protocol is limited to electric chiller systems, and their associated pumps and

    heat-rejection equipment. The chiller-system monitoring protocol applicable to

    commissioning consists of three distinct stages Stage one: development of a chiller-system monitoring plan for submittal to and approval by PG&E; Stage two:

    implementation of procedures for actual field installation, placement and calibration of

    chiller-system operation during he monitoring period; and Stage three: collection,

    analysis and reporting of data and results. During a limited monitoring period, which

    will generally last two to eight weeks but can last longer, the chiller system should

    experience a wide range of operating conditions.

    The commissioning fieldwork for this dynamic EEM is conducted in accordance with

    the project-specific verification and functional performance test plan. This test plan

    must include a clear description of the design specifications and information which

    pertains to chiller controls sequence, manufacturer cut sheets and equipment

    performance specifications, installation instructions and O&M manuals in addition to

    the pre-startup inspection checklist, verification test checklist and the functional

    performance test checklist. This information will form the basis of the commissioning

    acceptance criteria and is necessary to evaluating the results of the inspections and

    tests. The final commissioning test plan must incorporate all the details required to

    describe the particular application and the operation of the high-efficiency packaged

    air-cooled chiller system being commissioned.

    In addition, a successful commissioning process will require coordination with all

    commissioning team members. The responsibilities of the team members are identified

    by the shaded boxes in the columns under each members title in the attached Team

  • CES Commissioning Guidelines

    Revision No. 0: 5/95 Test Plans 6-236

    Members Responsibilities chart as a means of facilitating this coordination. The attached EEM-specific Commissioning Process Flow Chart provides an overview of the

    commissioning process for this energy-efficiency measure.

    The pre-startup inspection of subsystems verifies, through visual examination, simple

    measurements and reference to contractors reports, that the components are installed in accordance with manufacturers specifications, meet design criteria and are ready for system start-up. The pre-startup checklist addresses verification of the physical

    installation, electrical system, system controls, test and balance for pumps, collection of

    equipment nameplate data and documentation. In addition, related pre-startup

    inspection checklists, non-compliance and corrections of components that do not meet

    the acceptance criteria and inspection checklists are addressed. The checklists provided

    are intended to serve as a guideline in the preparation of the project-specific pre-startup

    inspection checklists. The project-specific pre-startup inspection checklists must be

    finalized and approved by the CES Project Manager prior to performing any

    inspections.

    Following the completion of the pre-startup inspection, the verification checks and

    tests can commence. They should follow the order presented in the verification test

    checklist provided in this section, although the project-specific character of the testing

    must be considered. The checklist provided is not intended to replace the contractors normal and accepted procedures for installing and pre-testing equipment or relieve the

    contractor of the standard check-out and start-up responsibilities. The verification test

    checklists should be refined, as required, with the information gathered during the pre-

    startup inspections. This testing is intended to verify that all components, equipment,

    systems, and interfaces between systems operate in accordance with contract

    documents. The chiller, which includes the chiller soft start and restart sequences, chilled water pumping system and chiller system controls are all tested as part of this

    test procedure.

    Following the completion of the verification tests, the functional performance testing

    can commence. This testing should follow the order presented in the functional

    performance test checklist provided in this section, although the project-specific

    character of the testing must be considered. The functional performance test checklist

    should be refined, as required, with the information gathered during the pre-startup

    inspections and verification tests. The functional performance testing is intended to

    measure the energy-efficient performance of the packaged air-cooled chiller as defined

    in the final design-intent document.

    Prior to the verification and functional performance testing, the Prime Contractor may

    need to coordinate with the building operator to modify the system control setpoints to

    facilitate the operation of connected equipment for the duration of the testing. Once

    stable system operation has been established, the Prime Contractor can proceed to gather

    the required data. Any equipment found not to comply with the acceptance criteria must

    be repaired or corrected and then retested until satisfactory results are obtained.

    Following the on-site testing, the test results must be prepared, documentation compiled

    and the verification and functional performance test certified in accordance with these

    Guidelines. The testing procedures and results of all tests must be clearly documented in

    the final commissioning report.

  • CES Commissioning Guidelines

    Revision No. 0: 5/95 Test Plans 6-237

    Pre-Start up Inspections, Team Members Responsibilities Verification Checks and Tests and Functional Performance Testing Commissioning Team Members for Packaged Air-Cooled Chiller System EEM

    Action Item CE

    S P

    roje

    ct

    Ma

    nag

    er

    Qu

    ali

    ty A

    ssu

    ran

    ce E

    ng

    ine

    er

    Pri

    me C

    on

    tracto

    r

    Me

    ch

    an

    ical S

    ub

    co

    ntr

    acto

    r

    Ele

    ctr

    ical S

    ub

    co

    ntr

    acto

    r

    Bala

    nc

    ing

    Su

    bc

    on

    tracto

    r

    Co

    ntr

    ols

    Su

    bco

    ntr

    acto

    r

    Ow

    ne

    r's

    O&

    M S

    taff

    Verification Activities

    Prepare Inspection Checklists

    Approve Inspection Checklists

    Coordinate with Team Members

    Pre-Start up Inspection

    Conduct Pre-Start up Inspections

    On-site for Inspection Louvers, Controllers, Sensors, Connected Equipment & Wiring

    Luminaires, Sensors, Controls, Connected Equipment & Wiring

    Electrical Panels, Motors, Power Packs, etc.

    Power Available to Components

    System Controls

    Equipment Nameplate Data

    Documentation & Submittals

    Obtain Vendor Cut sheets and Performance Specs

    Obtain Manufacturer's Installation Instructions

    Obtain Manufacturer's O&M Manuals

    Prepare Related Checklists

    Non-Compliance & Corrections

    Determine Non-compliance components

    Corrections and Repairs

    Pre-Start up Inspection Follow-up

    Record Inspection Results

    Certify Pre-Startup Checklists

    Approve Pre-Startup Checklists

    Verification Testing

    Prepare Verification Test Checklists

    Initiate Start-up of System Components

    Verify Test and Balance Report

    Certify Readiness for Conducting Verification Testing

    Authorization to Proceed with Verification Testing

    Conduct Verification Testing

    Functional Performance Testing

    Prepare Functional Performance Checklists

    Authorization to Proceed with FPT

    Conduct Functional Performance Testing

    On-Site for Verification & Functional Performance Testing

    Documentation and Non-Compliance

    Record Results of Testing

    Determine Non-Compliance Components

    Corrections and Repairs

    Verify Results of Testing

    Approve Results

    Prepare Final Commissioning Report

    Prepare System Manual

  • Revision No. 0: 5/95 Test Plans 6-238

    BEGIN

    COMMISSIONING FIELD WORK

    COORDINATION WITH

    COMMISSIONING TEAM MEMBERS BY

    PRIME CONTRACTOR

    VERIFY TOOLS

    REQUIRED

    VERIFY DESIGN

    INFORMATION

    PREPARE EQUIPMENT

    SPECIFIC VERIFICATION INSPECTION CHECKLISTS

    PRE-INSPECTION

    ACTIVITIES

    APPROVAL OF PRE-START UP

    CHECKLISTS BY PG&E

    NO

    YES

    REVIEW MATERIAL

    DOCUMENTATION

    PHYSICAL INSPECTIONS OF

    INSTALLATIONS

    CONDUCT VERIFICATION

    INSPECTIONS OF MATERIALS AND COMPONENTS IN

    COMPLIANCE WITH

    CONSTRUCTION DOCUMENTS

    NON-COMPLIANCE AND CORRECTIONS

    DOCUMENTATION

    EQUIPMENT

    NAMEPLATE DATA

    VERIFICATION OF

    INSTALLATIONS IN ACCORDANCE WITH CONTRACT

    REQUIREMENTS BY

    QUALITY ASSURANCE ENGINEER

    SUBSYSTEMS START-UP

    NON-COMPLIANCE

    REPORT

    REPAIRS

    FAIL

    PASS

    COORDINATE TEST & BALANCE

    SUBCONTRACTOR ACTIVITIES

    INTEGRATE FACILITY

    AUTOMATION SYSTEM

    COMPLETE PRE-START UP

    INSPECTION FOR FULL SYSTEM

    START-UP

    NON-COMPLIANCE

    ISSUES

    MODIFICATIONS

    FAIL

    PASS

    CERTIFICATION OF

    PRE-START UP CHECKLISTS BY PRIME CONTRACTOR AND

    QUALITY ASSURANCE ENGINEER

    BEGIN SYSTEM

    START-UP

    COMPLETE START-UP

    TEST, ADJUST & BALANCE

    PREPARE VERIFICATION

    AND FUNCTIONAL PERFORMANCE

    TEST PLANS

    RECEIVE AUTHORIZATION

    FROM PG&E TO PROCEED

    REVISE

    NO

    YES

    BEGIN VERIFICATION

    TESTING

    COORDINATION WITH

    COMMISSIONING TEAM MEMBERS

    CONDUCT VERIFICATION OF

    OPERATION OF DYNAMIC SYSTEMS IN ACCORDANCE WITH

    CONTRACT REQUIREMENTS

    DOCUMENTATION OF OPERATION

    VERIFICATION OF OPERATION OF DYNAMIC

    SYSTEMS IN ACCORDANCE WITH CONTRACT REQUIREMENTS

    NON-COMPLIANCE

    CORRECTION

    AND REPAIRS

    BEGIN FUNCTIONAL

    PERFORMANCE TESTING

    COORDINATION WITH

    COMMISSIONING TEAM MEMBERS

    CALCULATE CHILLER

    EFFICIENCY AND COMPARE PERFORMANCE TO RATED EFFICIENCY

    CHECK & REPORT UNUSUAL VIBRATION

    ESTABLISH STABLE

    PART-LOAD OPERATION AND COLLECT DATA

    ESTABLISH STABLE

    FULL-LOAD OPERATION AND COLLECT DATA

    ACTIVATE SYSTEM

    CONTROLS FOR CHILLER START SEQUENCE

    PROVIDE SIMULATED

    COOLING LOAD IN BUILDING FUNCTIONAL PERFORMANCE

    TESTING

    DOCUMENTATION

    OF PERFORMANCE

    VERIFY COMPLIANCE WITH

    DESIGN INTENT AND MANUFACTURERS SPECIFICATIONS

    FAIL

    NON-

    COMPLIANCE REPORT

    CORRECTION

    AND REPAIRS

    CERTIFICATION OF VERIFICATION

    AND FUNCTIONAL PERFORMANCE TEST BY PRIME CONTRACTOR AND

    QUALITY ASSURANCE ENGINEER

    PASS

    PG&E APPROVAL OF

    PERFORMANCE

    FAIL

    EVALUATION

    & DIRECTED MODIFICATIONS

    PASS

    COMPLETE AS-BUILT

    DRAWINGS, SYSTEM MANUAL, AND CORRECTED

    O & M MANUALS

    PREPARE FINAL

    COMMISSIONING REPORT

    FINAL ACCEPTANCE

    OF FIELD VERIFICATION

    INSPECTIONS AND

    DYNAMIC TESTING BY PG&E

    END

    NO

    YES

    PACKAGED AIR-COOLED CHILLER EEM COMMISSIONING PROCESS FLOW CHART

    TEST & BALANCE

    FOR PUMPS

    CONTROLS

    ELECTRICAL

    PHYSICAL INSTALLATION

    PRE-START UP INSPECTION AND VERIFICATION OF

    EQUIPMENT AND SUBSYSTEMS

  • VERIFICATION AND FUNCTIONAL PERFORMANCE

    TEST PLAN

    FOR HIGH-EFFICIENCY PACKAGED

    AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-239

    PROJECT SPECIFIC INFORMATION

    Project Name: Project Number:

    Building Occupancy Type: Gross Floor Area:

    Prime Contractor:

    Required Operating Permits Obtained Prior to Commissioning: Yes No

    INSTALLATION ACCEPTANCE CRITERIA

    EEM Description:

    Required Specification:

    Construction Installation Drawing (Sheet #, Detail #):

    Manufacturer's Installation Requirement:

    Special Installation Considerations:

    (per Contract Documents)

    PERFORMANCE ACCEPTANCE CRITERIA

    Statement of Design Intent for EEM:

    (Definition of Performance Acceptance Criteria)

    System Description:

    Design Parameters (applicable to acceptance of performance):

    Global priorities established by design intent, which affect performance acceptance criteria

    (Refer to Guideline Section 2.2.2.3):

    Describe the expected results of each test procedure:

    Description of Design Day Conditions:

    Recommended Weather Conditions for Testing:

  • VERIFICATION AND FUNCTIONAL PERFORMANCE

    TEST PLAN

    FOR HIGH-EFFICIENCY PACKAGED

    AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-240

    Building Cooling System Description:

    Cooling coils capacity (tons):

    Total design air flow (cfm):

    Additional information:

    Description of System Controls and Sequence of Operation:

    Controls Operating Setpoints:

    Is Energy Management System (EMS) used? Yes No

    Are control valves connected to EMS? Yes No If yes, identify valves:

    EQUIPMENT DESCRIPTION

    Chiller:

    Manufacturer:

    Model Number:

    Type:

    Options Code:

    Rated Full-Load Capacity (tons):

    Rated Full-Load Efficiency (kW/ton):

    Motor Voltage/Phase/Hz:

    Motor Horsepower:

    Number of Chillers:

    Symbol/Designation from Drawings:

    Location:

    Additional Information:

  • VERIFICATION AND FUNCTIONAL PERFORMANCE

    TEST PLAN

    FOR HIGH-EFFICIENCY PACKAGED

    AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-241

    Chilled Water Pump:

    Manufacturer:

    Model Number:

    Design Parameters: gpm @ TDH

    Motor Voltage/Phase/Hz:

    Motor Horsepower:

    Number of Pumps:

    Symbol/Designation from Drawings:

    Pump Arrangement: Parallel Series Other

    Additional Information:

    Schedule Requirements:

    Start-up testing

    Pre-startup inspections

    Verification testing

    Functional performance testing

    Seasonal testing for design day conditions

    Required Tools and Instruments:

    Multimeter for electrical measurements

    Ammeter

    Power measurement transducer (PMT)

    Power factor meter

    Calibrated thermometer

    Pressure gauge for water

    Miscellaneous hand tools

    Description of Calibration Procedures:

    For all instruments that require calibration, provide the following information:

    Instrument description/identification

    Manufacturers calibration requirements

    Copy of most recent calibration certificates

    Date of most recent calibration

    Description of calibration procedure

  • VERIFICATION AND FUNCTIONAL PERFORMANCE

    TEST PLAN

    FOR HIGH-EFFICIENCY PACKAGED

    AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-242

    Field-Initiated Modifications to Approved Testing:

    Describe the conditions that invalidate the approved testing procedure.

    Identify the specific steps or tests in the approved procedures that are invalidated.

    Describe the modified steps to the procedures.

    Explain how these new steps address the unanticipated on-site conditions without altering the intent or the outcome of the testing.

    For responsible subcontractors, obtain the written agreement of the Prime Contractor.

    Obtain the written agreement of the Quality Assurance Engineer.

    Proceed with the modified testing procedure.

  • PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-243

    CHECKLIST ITEM YES NO

    1.0 Physical Installation of Chiller, Chilled Water Pump and Piping

    1.1 Chiller installed in accordance with manufacturers specifications

    1.2 Chiller refrigerant charge correct. Number of pounds:

    1.3 Refrigerant purging and charging connections installed

    and functional

    1.4 Chiller oil sump accessories and connections installed

    and functional

    1.5 Chilled water pump grouted in place

    1.6 Manufacturers recommended clearances provided for service access and air circulation around equipment

    1.7 Pump vibration isolation devices functional

    1.8 Pump alignment verified

    1.9 Piping installed in accordance with design drawings

    1.10 Piping flushed clean and leak tested

    1.11 Pumps not leaking

    1.12 Lubrication complete

    1.13 Piping properly labeled

    1.14 Valves properly labeled

    1.15 Temperature gauges installed

    1.16 Pressure gauges installed across chilled water circulation pump

    1.17 Air circulation fan(s) for air-cooled condenser installed

    and functional

    1.18 Airways and screens for air-cooled condenser installed and cleaned

    1.19 Condenser heat exchanger installed correctly in relation to airflow

    1.20 External surfaces of condenser heat exchanger clean

    1.21 Comments and Observations

    2.0 Electrical

    2.1 Disconnect panels installed and labeled

    2.2 Fuse ratings correct for connected equipment

    2.3 Switch gear installed and functional

    2.4 Power available to chiller starter

    2.5 Power available to chiller control panel

    2.6 Power available to chilled water disconnect

    2.7 Chiller motor rotation correct

  • PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-244

    CHECKLIST ITEM YES NO

    2.8 Chilled water pump motor rotation correct

    2.9 Motor protection devices installed and functional

    2.10 Control system contactors functional

    2.11 Control system interlocks functional

    2.12 Shielded wiring used on electronic controls

    2.13 Comments and observations:

    3.0 Controls

    3.1 Factory start-up and check-out complete

    3.2 Chiller safety/protection devices tested

    3.3 Chilled water flow switch installed

    3.4 Chilled water flow switch tested

    3.5 Chilled water pump interlock installed

    3.6 Chilled water pump interlock tested

    3.7 Control circuit logic for motors starting verified

    3.8 Outside air sensor calibrated

    3.9 Comments and observations:

    4.0 Test and Balance

    4.1 Water balance complete with design maximum flow verified

    4.2 Test and balance report submitted

    4.3 Chemical water treatment complete

    4.4 Comments and observations

    5.0 Equipment Nameplate Data

    5.1 Chiller

    Manufacturer:

    Model Number:

    Serial Number:

    Motor Voltage/Phase/Hz:

    Motor Horsepower:

    Location:

    Additional Information:

  • PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-245

    5.2 Water Temperature Controller:

    Manufacturer:

    Model Number:

    Serial Number:

    Electrical Data:

    Other:

    5.3 Chilled Water Pumps:

    Manufacturer:

    Model Number:

    Serial Number:

    Motor Voltage/Phase/Hz:

    Motor Horsepower:

    Number of Pumps:

    Location:

    Pump Arrangement:

    Additional Information:

    6.0 Documentation YES NO

    6.1 Vendor cut sheets, chiller part-load curves and pump curves

    6.2 Manufacturers product design data

    6.3 Operation and maintenance manuals

    6.4 Comments and Observations:

    7.0 Non-Compliance and Corrections

    The following items did not comply with manufacturers or contract specifications and require correction.

    7.1

    7.2

    7.3

    7.4

    7.5

  • PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-246

    8.0 Certification

    We the undersigned participated in this pre-startup inspection, acknowledge that the pre-startup

    process for the packaged air-cooled chiller EEM has been completed and that all corrections have

    been made.

    Date:

    8.1 Name:

    Company name:

    Role in inspection:

    Signature:

    8.2 Name:

    Company name:

    Role in inspection:

    Signature:

    8.3 Name:

    Company name:

    Role in inspection:

    Signature:

    8.4 Name:

    Company name:

    Role in inspection:

    Signature:

  • VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-247

    Verification Tests: The Prime Contractor shall demonstrate operation of the chilled water

    system in accordance with manufacturers and contract specifications. The building operators assistance will be required to change setpoints for the duration of the testing and restore them to

    their original settings after the tests have been completed. The tests will be conducted while the

    occupant and equipment loads are minimal.

    The following checklist shall serve as a general guideline for verification testing, although the

    project-specific character of the tests required must be considered. This checklist should be

    refined by the Prime Contractor to address project-specific details and the information gathered

    during the pre-startup inspections.

  • VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-248

    1.0 Provide simulated cooling load in building:

    1.1 Modify control system setpoints, as required, to facilitate chillers response to simulated building load.

    1.2 Switch system to warm-up mode in order to open all supply ducts, where VAV boxes may be present, and set fan powered box coils to full heat.

    1.3 Start the building air handling units in order to provide a cooling load for the chiller(s).

    1.4 Operate boilers or use outside air to provide cooling load in building depending upon the outside

    air temperature.

    2.0 Activate system controls for chiller start sequence as follows:

    2.1 Start chilled water pump and establish chilled water flow. Modulate the chilled water control

    valve to prevent a slug of hot water from entering the chiller. Verify operation of chillers chilled water flow switch.

    Result:

    2.2 Determine that chilled water temperature is above setpoint.

    Record water temperature:

    2.3 Verify that control system energizes chiller start sequence.

    Result:

    2.4 Verify that chiller senses chilled water temperature above setpoint and control system activates

    chiller start.

    Result:

    2.5 Verify functioning of soft start sequence. Result:

    2.6 Shut off air handling equipment to remove load on chilled water system. Monitor chilled water

    temperature to determine when temperature drops below setpoint. Verify that chiller shut-down

    sequence is initiated and accomplished after load is removed.

    Result:

    2.7 Restart air handling equipment one minute after chiller shut-down. Monitor chilled water

    temperature to determine when temperature rises above setpoint. Verify operation of chiller

    restart sequence.

    Result:

    3.0 Establish stable, full-load operation of the chiller, then measure and record the following data:

    3.1 Chilled water flow (gpm):

    Record chiller inlet/outlet pressure readings and compare to chiller design conditions, Test and

    Balance Report and chiller manufacturers performance data. DESIGN T&B F.P.T. ACTUAL

    Chiller Inlet Pressure (psig)

    Chiller Outlet Pressure (psig)

    3.2 Record chilled water supply and return temperature readings and compare to readout on chiller

    control panel.

    DISPLAYED ACTUAL

    Chilled Water Supply Temp (F)

    Chilled Water Return Temp (F)

  • VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-249

    3.3 Record for chiller: amperage each phase, voltage phase to phase, voltage phase to ground, and

    power factor.

    PHASE 1 PHASE 2 PHASE 3

    Amperage

    Voltage

    Voltage

    Voltage to Ground

    Power Factor

    KW (use PMT)

    3.4 Record for chilled water pump: amperage each phase, voltage phase to phase, voltage phase to

    ground, and power factor.

    PHASE 1 PHASE 2 PHASE 3

    Amperage

    Voltage

    Voltage

    Voltage to Ground

    Power Factor

    KW (use PMT)

    3.5 Record the following information:

    Ambient outside air DB temperature (F):

    Entering chilled water temperature (F):

    Leaving chilled water temperature (F):

    4.0 Establish stable, part-load operation at each of the following percentages of full-load operation

    (50%, 60%, 70%, 75%, 80%, 85%, 90%, and 95%), then measure and record the same data as

    requested in Section 3.0 above for all expected entering-condition air temperatures.

    5.0 Check and report unusual vibration, noise, etc.

    6.0 Use the following equation to calculate kW with the electrical data collected in Section 3 above:

    VA = 3 VI where V = voltage phase to phase

    I = amperage per phase

    PF = Sin where = phase angle between V & I KW = VA PF

  • VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-250

    7.0 Calculate chiller efficiency (kW/ton) at full-load operation and the part-load operation levels tested

    above and plot the results, as follows:

    7.1 Sort data into separate sets according to supply chilled water temperature ranges (for example,

    one set of data in the range of 50 to 52F, a second set for 53 to 55F, etc.). Select the smallest

    range that includes an adequate number of data points and proceed with plot preparation.

    7.2 Plot chiller kW versus chiller tons for each sorted data set. Where outside air temperatures

    differed by more than 5F (for example, 60 to 64F, 75 to 79F, etc.) during the test, identify

    the plotted points common to each range.

    7.3 Curve fit each group (designated by outside temperature range) of plotted points.

    8.0 Record Results

    8.1 Prime Contractor shall record and submit results of the verification testing to CES Project

    Manager.

    8.2 If specified equipment is not installed or operational, Prime Contractor shall report remedial

    action required and reschedule verification tests.

    9.0 Non-Compliance and Corrections

    The following items did not comply with manufacturers or contract specifications and require correction:

    9.1

    9.2

    9.3

    9.4

  • FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-251

    Functional Performance Tests: The Prime Contractor shall demonstrate performance of

    chilled water system in accordance with the final design-intent document and

    manufacturers and contract specifications. The building operators assistance will be required to change setpoints for the duration of the testing and restore them to their

    original settings after the tests have been competed. The tests will be conducted while

    the occupant and equipment loads are minimal.

    The following checklist shall serve as a general guideline for the functional perfor-

    mance testing, although the project-specific character of the tests required must be

    considered. This checklist should be refined by the Prime Contractor to address

    project-specific details and information gathered during the pre-startup inspections and

    verification testing.

  • FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-252

    1.0 Provide simulated cooling load in building:

    1.1 Modify control system setpoints, as required, to facilitate chillers response to simulated building load.

    1.2 Switch system to warm-up mode in order to open all supply ducts, where VAV boxes may be present, and set fan powered box coils to full heat.

    1.3 Start the building air handling units in order to provide a cooling load for the chiller(s).

    1.4 Operate boilers or use outside air to provide cooling load in building depending upon the outside

    air temperature and the design conditions to be simulated.

    2.0 Establish stable operation of the chiller in accordance with the final design-intent document, then

    measure and record the following data:

    2.1 Chilled water flow (gpm):

    Record chiller inlet/outlet pressure readings and compare to chiller design conditions, Test and

    Balance Report and chiller manufacturers performance data. DESIGN T&B F.P.T. ACTUAL

    Chiller Inlet Pressure (psig)

    Chiller Outlet Pressure (psig)

    2.2 Record chilled water supply and return temperature readings and compare to readout on chiller

    control panel.

    DISPLAYED ACTUAL

    Chilled Water Supply Temp (F)

    Chilled Water Return Temp (F)

    2.3 Record for chiller: amperage each phase, voltage phase to phase, voltage phase to ground, and

    power factor.

    PHASE 1 PHASE 2 PHASE 3

    Amperage

    Voltage

    Voltage

    Voltage to Ground

    Power Factor

    KW (use PMT)

    2.4 Record for chilled water pump: amperage each phase, voltage phase to phase, voltage phase to

    ground, and power factor.

    PHASE 1 PHASE 2 PHASE 3

    Amperage

    Voltage

    Voltage

    Voltage to Ground

    Power Factor

    KW (use PMT)

    2.5 Record the following information:

    Ambient outside air DB temperature (F):

    Entering chilled water temperature (F):

    Leaving chilled water temperature (F):

  • FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-253

    3.0 Use the following equation to calculate kW with the electrical data collected in Section 2 above:

    VA = 3 VI where V = voltage phase to phase

    I = amperage per phase

    PF = Sin where = phase angle between V & I KW = VA PF

    4.0 Calculate chiller efficiency (kW/ton) at the specified load-levels tested above and plot the results,

    as follows:

    4.1 Sort data into separate sets according to supply chilled water temperature ranges (for example,

    one set of data in the range of 50 to 52F, a second set for 53 to 55F, etc.). Select the smallest

    range that includes an adequate number of data points and proceed with plot preparation.

    4.2 Plot chiller kW versus chiller tons for each sorted data set. Where outside air temperatures

    differed by more than 5F (for example, 60 to 64F, 75 to 79F, etc.) during the test, identify

    the plotted points common to each range.

    4.3 Curve fit each group (designated by outside temperature range) of plotted points.

    5.0 Compare chiller calculated performance and plotted curves to manufacturers rated efficiency, performance specifications and part-load curves:

    6.0 Record Results

    6.1 Prime Contractor shall record and submit results of the functional performance testing to CES

    Project Manager.

    6.2 If specified equipment performance is not verified, Prime Contractor shall report remedial action

    required and reschedule functional performance tests.

    7.0 Non-Compliance and Corrections

    The following items did not comply with the final design-intent document or manufacturers or contract specifications and require correction:

    7.1

    7.2

    7.3

    7.4

    8.0 Documentation required in complete Final Commissioning Report

    9.1 Certified pre-startup checklists

    8.2 Certified verification and functional performance test checklists

    8.3 Test and Balance Report

    8.4 Vendor cut sheets and pump curves

    8.5 Manufacturers product design data 8.6 Operation and maintenance manuals

    8.7 Manufacturers installation specifications 8.8 Final as-built drawings

  • FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER

    Revision No. 0: 5/95 Test Plans 6-254

    9.0 Certification

    We the undersigned witnessed the verification and functional performance tests and certify that the

    testing procedures for the packaged air-cooled chiller EEM identified above have been completed,

    that the equipment tested has met the established operational and performance requirements and

    that all corrections required due to non-compliance with the contract documents, manufacturers specifications and final design-intent document have been made.

    Date:

    9.1 Name:

    Company name:

    Role in inspection:

    Signature:

    9.2 Name:

    Company name:

    Role in inspection:

    Signature:

    9.3 Name:

    Company name:

    Role in inspection:

    Signature:

    9.4 Name:

    Company name:

    Role in inspection:

    Signature: