commissioning chart
DESCRIPTION
Flow chartTRANSCRIPT
-
CES Commissioning Guidelines
Revision No. 0: 5/95 Test Plans 6-234
VERIFICATION
and
FUNCTIONAL PERFORMANCE TEST PLAN
for
PACKAGED AIR-COOLED CHILLER
including
PRE-STARTUP INSPECTION CHECKLIST,
VERIFICATION TEST CHECKLIST,
and
FUNCTIONAL PERFORMANCE TEST
CHECKLIST
-
CES Commissioning Guidelines
Revision No. 0: 5/95 Test Plans 6-235
6.10.1 High-Efficiency Packaged Air-Cooled
Chiller
Commissioning Process Summary
The Commissioning Process for the high-efficiency packaged air-cooled chiller EEM
includes pre-startup inspections of the installed equipment, systems, and subsystems,
and the execution of the verification and functional performance testing of the chiller,
pumps, and chiller control system. The fundamental operational and performance
parameters to be verified through the testing include 1) drop in chilled water
temperature across the evaporator (T, F), 2) chilled water flow rate (gpm), 3) electrical power consumption of the chiller and chilled water pump (kW), 4) chiller
efficiency (kW/ton) under full-load and part-load operation, and 5) function of the
system controls sequences.
These performance parameters will vary depending on the systems operating conditions. Although manufacturers performance data can typically be obtained for most chillers, the actual in situ performance of a chiller may vary considerably. This
performance, to be determined accurately, should be evaluated within the context of
the entire chiller system. Therefore, actual field monitoring of a chiller system in
accordance with an established monitoring protocol is often required.
A protocol for monitoring chiller-system performance has been provided in Section
3.6.2 of these Guidelines for use during the functional performance testing. The scope
of the protocol is limited to electric chiller systems, and their associated pumps and
heat-rejection equipment. The chiller-system monitoring protocol applicable to
commissioning consists of three distinct stages Stage one: development of a chiller-system monitoring plan for submittal to and approval by PG&E; Stage two:
implementation of procedures for actual field installation, placement and calibration of
chiller-system operation during he monitoring period; and Stage three: collection,
analysis and reporting of data and results. During a limited monitoring period, which
will generally last two to eight weeks but can last longer, the chiller system should
experience a wide range of operating conditions.
The commissioning fieldwork for this dynamic EEM is conducted in accordance with
the project-specific verification and functional performance test plan. This test plan
must include a clear description of the design specifications and information which
pertains to chiller controls sequence, manufacturer cut sheets and equipment
performance specifications, installation instructions and O&M manuals in addition to
the pre-startup inspection checklist, verification test checklist and the functional
performance test checklist. This information will form the basis of the commissioning
acceptance criteria and is necessary to evaluating the results of the inspections and
tests. The final commissioning test plan must incorporate all the details required to
describe the particular application and the operation of the high-efficiency packaged
air-cooled chiller system being commissioned.
In addition, a successful commissioning process will require coordination with all
commissioning team members. The responsibilities of the team members are identified
by the shaded boxes in the columns under each members title in the attached Team
-
CES Commissioning Guidelines
Revision No. 0: 5/95 Test Plans 6-236
Members Responsibilities chart as a means of facilitating this coordination. The attached EEM-specific Commissioning Process Flow Chart provides an overview of the
commissioning process for this energy-efficiency measure.
The pre-startup inspection of subsystems verifies, through visual examination, simple
measurements and reference to contractors reports, that the components are installed in accordance with manufacturers specifications, meet design criteria and are ready for system start-up. The pre-startup checklist addresses verification of the physical
installation, electrical system, system controls, test and balance for pumps, collection of
equipment nameplate data and documentation. In addition, related pre-startup
inspection checklists, non-compliance and corrections of components that do not meet
the acceptance criteria and inspection checklists are addressed. The checklists provided
are intended to serve as a guideline in the preparation of the project-specific pre-startup
inspection checklists. The project-specific pre-startup inspection checklists must be
finalized and approved by the CES Project Manager prior to performing any
inspections.
Following the completion of the pre-startup inspection, the verification checks and
tests can commence. They should follow the order presented in the verification test
checklist provided in this section, although the project-specific character of the testing
must be considered. The checklist provided is not intended to replace the contractors normal and accepted procedures for installing and pre-testing equipment or relieve the
contractor of the standard check-out and start-up responsibilities. The verification test
checklists should be refined, as required, with the information gathered during the pre-
startup inspections. This testing is intended to verify that all components, equipment,
systems, and interfaces between systems operate in accordance with contract
documents. The chiller, which includes the chiller soft start and restart sequences, chilled water pumping system and chiller system controls are all tested as part of this
test procedure.
Following the completion of the verification tests, the functional performance testing
can commence. This testing should follow the order presented in the functional
performance test checklist provided in this section, although the project-specific
character of the testing must be considered. The functional performance test checklist
should be refined, as required, with the information gathered during the pre-startup
inspections and verification tests. The functional performance testing is intended to
measure the energy-efficient performance of the packaged air-cooled chiller as defined
in the final design-intent document.
Prior to the verification and functional performance testing, the Prime Contractor may
need to coordinate with the building operator to modify the system control setpoints to
facilitate the operation of connected equipment for the duration of the testing. Once
stable system operation has been established, the Prime Contractor can proceed to gather
the required data. Any equipment found not to comply with the acceptance criteria must
be repaired or corrected and then retested until satisfactory results are obtained.
Following the on-site testing, the test results must be prepared, documentation compiled
and the verification and functional performance test certified in accordance with these
Guidelines. The testing procedures and results of all tests must be clearly documented in
the final commissioning report.
-
CES Commissioning Guidelines
Revision No. 0: 5/95 Test Plans 6-237
Pre-Start up Inspections, Team Members Responsibilities Verification Checks and Tests and Functional Performance Testing Commissioning Team Members for Packaged Air-Cooled Chiller System EEM
Action Item CE
S P
roje
ct
Ma
nag
er
Qu
ali
ty A
ssu
ran
ce E
ng
ine
er
Pri
me C
on
tracto
r
Me
ch
an
ical S
ub
co
ntr
acto
r
Ele
ctr
ical S
ub
co
ntr
acto
r
Bala
nc
ing
Su
bc
on
tracto
r
Co
ntr
ols
Su
bco
ntr
acto
r
Ow
ne
r's
O&
M S
taff
Verification Activities
Prepare Inspection Checklists
Approve Inspection Checklists
Coordinate with Team Members
Pre-Start up Inspection
Conduct Pre-Start up Inspections
On-site for Inspection Louvers, Controllers, Sensors, Connected Equipment & Wiring
Luminaires, Sensors, Controls, Connected Equipment & Wiring
Electrical Panels, Motors, Power Packs, etc.
Power Available to Components
System Controls
Equipment Nameplate Data
Documentation & Submittals
Obtain Vendor Cut sheets and Performance Specs
Obtain Manufacturer's Installation Instructions
Obtain Manufacturer's O&M Manuals
Prepare Related Checklists
Non-Compliance & Corrections
Determine Non-compliance components
Corrections and Repairs
Pre-Start up Inspection Follow-up
Record Inspection Results
Certify Pre-Startup Checklists
Approve Pre-Startup Checklists
Verification Testing
Prepare Verification Test Checklists
Initiate Start-up of System Components
Verify Test and Balance Report
Certify Readiness for Conducting Verification Testing
Authorization to Proceed with Verification Testing
Conduct Verification Testing
Functional Performance Testing
Prepare Functional Performance Checklists
Authorization to Proceed with FPT
Conduct Functional Performance Testing
On-Site for Verification & Functional Performance Testing
Documentation and Non-Compliance
Record Results of Testing
Determine Non-Compliance Components
Corrections and Repairs
Verify Results of Testing
Approve Results
Prepare Final Commissioning Report
Prepare System Manual
-
Revision No. 0: 5/95 Test Plans 6-238
BEGIN
COMMISSIONING FIELD WORK
COORDINATION WITH
COMMISSIONING TEAM MEMBERS BY
PRIME CONTRACTOR
VERIFY TOOLS
REQUIRED
VERIFY DESIGN
INFORMATION
PREPARE EQUIPMENT
SPECIFIC VERIFICATION INSPECTION CHECKLISTS
PRE-INSPECTION
ACTIVITIES
APPROVAL OF PRE-START UP
CHECKLISTS BY PG&E
NO
YES
REVIEW MATERIAL
DOCUMENTATION
PHYSICAL INSPECTIONS OF
INSTALLATIONS
CONDUCT VERIFICATION
INSPECTIONS OF MATERIALS AND COMPONENTS IN
COMPLIANCE WITH
CONSTRUCTION DOCUMENTS
NON-COMPLIANCE AND CORRECTIONS
DOCUMENTATION
EQUIPMENT
NAMEPLATE DATA
VERIFICATION OF
INSTALLATIONS IN ACCORDANCE WITH CONTRACT
REQUIREMENTS BY
QUALITY ASSURANCE ENGINEER
SUBSYSTEMS START-UP
NON-COMPLIANCE
REPORT
REPAIRS
FAIL
PASS
COORDINATE TEST & BALANCE
SUBCONTRACTOR ACTIVITIES
INTEGRATE FACILITY
AUTOMATION SYSTEM
COMPLETE PRE-START UP
INSPECTION FOR FULL SYSTEM
START-UP
NON-COMPLIANCE
ISSUES
MODIFICATIONS
FAIL
PASS
CERTIFICATION OF
PRE-START UP CHECKLISTS BY PRIME CONTRACTOR AND
QUALITY ASSURANCE ENGINEER
BEGIN SYSTEM
START-UP
COMPLETE START-UP
TEST, ADJUST & BALANCE
PREPARE VERIFICATION
AND FUNCTIONAL PERFORMANCE
TEST PLANS
RECEIVE AUTHORIZATION
FROM PG&E TO PROCEED
REVISE
NO
YES
BEGIN VERIFICATION
TESTING
COORDINATION WITH
COMMISSIONING TEAM MEMBERS
CONDUCT VERIFICATION OF
OPERATION OF DYNAMIC SYSTEMS IN ACCORDANCE WITH
CONTRACT REQUIREMENTS
DOCUMENTATION OF OPERATION
VERIFICATION OF OPERATION OF DYNAMIC
SYSTEMS IN ACCORDANCE WITH CONTRACT REQUIREMENTS
NON-COMPLIANCE
CORRECTION
AND REPAIRS
BEGIN FUNCTIONAL
PERFORMANCE TESTING
COORDINATION WITH
COMMISSIONING TEAM MEMBERS
CALCULATE CHILLER
EFFICIENCY AND COMPARE PERFORMANCE TO RATED EFFICIENCY
CHECK & REPORT UNUSUAL VIBRATION
ESTABLISH STABLE
PART-LOAD OPERATION AND COLLECT DATA
ESTABLISH STABLE
FULL-LOAD OPERATION AND COLLECT DATA
ACTIVATE SYSTEM
CONTROLS FOR CHILLER START SEQUENCE
PROVIDE SIMULATED
COOLING LOAD IN BUILDING FUNCTIONAL PERFORMANCE
TESTING
DOCUMENTATION
OF PERFORMANCE
VERIFY COMPLIANCE WITH
DESIGN INTENT AND MANUFACTURERS SPECIFICATIONS
FAIL
NON-
COMPLIANCE REPORT
CORRECTION
AND REPAIRS
CERTIFICATION OF VERIFICATION
AND FUNCTIONAL PERFORMANCE TEST BY PRIME CONTRACTOR AND
QUALITY ASSURANCE ENGINEER
PASS
PG&E APPROVAL OF
PERFORMANCE
FAIL
EVALUATION
& DIRECTED MODIFICATIONS
PASS
COMPLETE AS-BUILT
DRAWINGS, SYSTEM MANUAL, AND CORRECTED
O & M MANUALS
PREPARE FINAL
COMMISSIONING REPORT
FINAL ACCEPTANCE
OF FIELD VERIFICATION
INSPECTIONS AND
DYNAMIC TESTING BY PG&E
END
NO
YES
PACKAGED AIR-COOLED CHILLER EEM COMMISSIONING PROCESS FLOW CHART
TEST & BALANCE
FOR PUMPS
CONTROLS
ELECTRICAL
PHYSICAL INSTALLATION
PRE-START UP INSPECTION AND VERIFICATION OF
EQUIPMENT AND SUBSYSTEMS
-
VERIFICATION AND FUNCTIONAL PERFORMANCE
TEST PLAN
FOR HIGH-EFFICIENCY PACKAGED
AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-239
PROJECT SPECIFIC INFORMATION
Project Name: Project Number:
Building Occupancy Type: Gross Floor Area:
Prime Contractor:
Required Operating Permits Obtained Prior to Commissioning: Yes No
INSTALLATION ACCEPTANCE CRITERIA
EEM Description:
Required Specification:
Construction Installation Drawing (Sheet #, Detail #):
Manufacturer's Installation Requirement:
Special Installation Considerations:
(per Contract Documents)
PERFORMANCE ACCEPTANCE CRITERIA
Statement of Design Intent for EEM:
(Definition of Performance Acceptance Criteria)
System Description:
Design Parameters (applicable to acceptance of performance):
Global priorities established by design intent, which affect performance acceptance criteria
(Refer to Guideline Section 2.2.2.3):
Describe the expected results of each test procedure:
Description of Design Day Conditions:
Recommended Weather Conditions for Testing:
-
VERIFICATION AND FUNCTIONAL PERFORMANCE
TEST PLAN
FOR HIGH-EFFICIENCY PACKAGED
AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-240
Building Cooling System Description:
Cooling coils capacity (tons):
Total design air flow (cfm):
Additional information:
Description of System Controls and Sequence of Operation:
Controls Operating Setpoints:
Is Energy Management System (EMS) used? Yes No
Are control valves connected to EMS? Yes No If yes, identify valves:
EQUIPMENT DESCRIPTION
Chiller:
Manufacturer:
Model Number:
Type:
Options Code:
Rated Full-Load Capacity (tons):
Rated Full-Load Efficiency (kW/ton):
Motor Voltage/Phase/Hz:
Motor Horsepower:
Number of Chillers:
Symbol/Designation from Drawings:
Location:
Additional Information:
-
VERIFICATION AND FUNCTIONAL PERFORMANCE
TEST PLAN
FOR HIGH-EFFICIENCY PACKAGED
AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-241
Chilled Water Pump:
Manufacturer:
Model Number:
Design Parameters: gpm @ TDH
Motor Voltage/Phase/Hz:
Motor Horsepower:
Number of Pumps:
Symbol/Designation from Drawings:
Pump Arrangement: Parallel Series Other
Additional Information:
Schedule Requirements:
Start-up testing
Pre-startup inspections
Verification testing
Functional performance testing
Seasonal testing for design day conditions
Required Tools and Instruments:
Multimeter for electrical measurements
Ammeter
Power measurement transducer (PMT)
Power factor meter
Calibrated thermometer
Pressure gauge for water
Miscellaneous hand tools
Description of Calibration Procedures:
For all instruments that require calibration, provide the following information:
Instrument description/identification
Manufacturers calibration requirements
Copy of most recent calibration certificates
Date of most recent calibration
Description of calibration procedure
-
VERIFICATION AND FUNCTIONAL PERFORMANCE
TEST PLAN
FOR HIGH-EFFICIENCY PACKAGED
AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-242
Field-Initiated Modifications to Approved Testing:
Describe the conditions that invalidate the approved testing procedure.
Identify the specific steps or tests in the approved procedures that are invalidated.
Describe the modified steps to the procedures.
Explain how these new steps address the unanticipated on-site conditions without altering the intent or the outcome of the testing.
For responsible subcontractors, obtain the written agreement of the Prime Contractor.
Obtain the written agreement of the Quality Assurance Engineer.
Proceed with the modified testing procedure.
-
PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-243
CHECKLIST ITEM YES NO
1.0 Physical Installation of Chiller, Chilled Water Pump and Piping
1.1 Chiller installed in accordance with manufacturers specifications
1.2 Chiller refrigerant charge correct. Number of pounds:
1.3 Refrigerant purging and charging connections installed
and functional
1.4 Chiller oil sump accessories and connections installed
and functional
1.5 Chilled water pump grouted in place
1.6 Manufacturers recommended clearances provided for service access and air circulation around equipment
1.7 Pump vibration isolation devices functional
1.8 Pump alignment verified
1.9 Piping installed in accordance with design drawings
1.10 Piping flushed clean and leak tested
1.11 Pumps not leaking
1.12 Lubrication complete
1.13 Piping properly labeled
1.14 Valves properly labeled
1.15 Temperature gauges installed
1.16 Pressure gauges installed across chilled water circulation pump
1.17 Air circulation fan(s) for air-cooled condenser installed
and functional
1.18 Airways and screens for air-cooled condenser installed and cleaned
1.19 Condenser heat exchanger installed correctly in relation to airflow
1.20 External surfaces of condenser heat exchanger clean
1.21 Comments and Observations
2.0 Electrical
2.1 Disconnect panels installed and labeled
2.2 Fuse ratings correct for connected equipment
2.3 Switch gear installed and functional
2.4 Power available to chiller starter
2.5 Power available to chiller control panel
2.6 Power available to chilled water disconnect
2.7 Chiller motor rotation correct
-
PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-244
CHECKLIST ITEM YES NO
2.8 Chilled water pump motor rotation correct
2.9 Motor protection devices installed and functional
2.10 Control system contactors functional
2.11 Control system interlocks functional
2.12 Shielded wiring used on electronic controls
2.13 Comments and observations:
3.0 Controls
3.1 Factory start-up and check-out complete
3.2 Chiller safety/protection devices tested
3.3 Chilled water flow switch installed
3.4 Chilled water flow switch tested
3.5 Chilled water pump interlock installed
3.6 Chilled water pump interlock tested
3.7 Control circuit logic for motors starting verified
3.8 Outside air sensor calibrated
3.9 Comments and observations:
4.0 Test and Balance
4.1 Water balance complete with design maximum flow verified
4.2 Test and balance report submitted
4.3 Chemical water treatment complete
4.4 Comments and observations
5.0 Equipment Nameplate Data
5.1 Chiller
Manufacturer:
Model Number:
Serial Number:
Motor Voltage/Phase/Hz:
Motor Horsepower:
Location:
Additional Information:
-
PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-245
5.2 Water Temperature Controller:
Manufacturer:
Model Number:
Serial Number:
Electrical Data:
Other:
5.3 Chilled Water Pumps:
Manufacturer:
Model Number:
Serial Number:
Motor Voltage/Phase/Hz:
Motor Horsepower:
Number of Pumps:
Location:
Pump Arrangement:
Additional Information:
6.0 Documentation YES NO
6.1 Vendor cut sheets, chiller part-load curves and pump curves
6.2 Manufacturers product design data
6.3 Operation and maintenance manuals
6.4 Comments and Observations:
7.0 Non-Compliance and Corrections
The following items did not comply with manufacturers or contract specifications and require correction.
7.1
7.2
7.3
7.4
7.5
-
PRE-COMMISSIONING INSPECTION CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-246
8.0 Certification
We the undersigned participated in this pre-startup inspection, acknowledge that the pre-startup
process for the packaged air-cooled chiller EEM has been completed and that all corrections have
been made.
Date:
8.1 Name:
Company name:
Role in inspection:
Signature:
8.2 Name:
Company name:
Role in inspection:
Signature:
8.3 Name:
Company name:
Role in inspection:
Signature:
8.4 Name:
Company name:
Role in inspection:
Signature:
-
VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-247
Verification Tests: The Prime Contractor shall demonstrate operation of the chilled water
system in accordance with manufacturers and contract specifications. The building operators assistance will be required to change setpoints for the duration of the testing and restore them to
their original settings after the tests have been completed. The tests will be conducted while the
occupant and equipment loads are minimal.
The following checklist shall serve as a general guideline for verification testing, although the
project-specific character of the tests required must be considered. This checklist should be
refined by the Prime Contractor to address project-specific details and the information gathered
during the pre-startup inspections.
-
VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-248
1.0 Provide simulated cooling load in building:
1.1 Modify control system setpoints, as required, to facilitate chillers response to simulated building load.
1.2 Switch system to warm-up mode in order to open all supply ducts, where VAV boxes may be present, and set fan powered box coils to full heat.
1.3 Start the building air handling units in order to provide a cooling load for the chiller(s).
1.4 Operate boilers or use outside air to provide cooling load in building depending upon the outside
air temperature.
2.0 Activate system controls for chiller start sequence as follows:
2.1 Start chilled water pump and establish chilled water flow. Modulate the chilled water control
valve to prevent a slug of hot water from entering the chiller. Verify operation of chillers chilled water flow switch.
Result:
2.2 Determine that chilled water temperature is above setpoint.
Record water temperature:
2.3 Verify that control system energizes chiller start sequence.
Result:
2.4 Verify that chiller senses chilled water temperature above setpoint and control system activates
chiller start.
Result:
2.5 Verify functioning of soft start sequence. Result:
2.6 Shut off air handling equipment to remove load on chilled water system. Monitor chilled water
temperature to determine when temperature drops below setpoint. Verify that chiller shut-down
sequence is initiated and accomplished after load is removed.
Result:
2.7 Restart air handling equipment one minute after chiller shut-down. Monitor chilled water
temperature to determine when temperature rises above setpoint. Verify operation of chiller
restart sequence.
Result:
3.0 Establish stable, full-load operation of the chiller, then measure and record the following data:
3.1 Chilled water flow (gpm):
Record chiller inlet/outlet pressure readings and compare to chiller design conditions, Test and
Balance Report and chiller manufacturers performance data. DESIGN T&B F.P.T. ACTUAL
Chiller Inlet Pressure (psig)
Chiller Outlet Pressure (psig)
3.2 Record chilled water supply and return temperature readings and compare to readout on chiller
control panel.
DISPLAYED ACTUAL
Chilled Water Supply Temp (F)
Chilled Water Return Temp (F)
-
VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-249
3.3 Record for chiller: amperage each phase, voltage phase to phase, voltage phase to ground, and
power factor.
PHASE 1 PHASE 2 PHASE 3
Amperage
Voltage
Voltage
Voltage to Ground
Power Factor
KW (use PMT)
3.4 Record for chilled water pump: amperage each phase, voltage phase to phase, voltage phase to
ground, and power factor.
PHASE 1 PHASE 2 PHASE 3
Amperage
Voltage
Voltage
Voltage to Ground
Power Factor
KW (use PMT)
3.5 Record the following information:
Ambient outside air DB temperature (F):
Entering chilled water temperature (F):
Leaving chilled water temperature (F):
4.0 Establish stable, part-load operation at each of the following percentages of full-load operation
(50%, 60%, 70%, 75%, 80%, 85%, 90%, and 95%), then measure and record the same data as
requested in Section 3.0 above for all expected entering-condition air temperatures.
5.0 Check and report unusual vibration, noise, etc.
6.0 Use the following equation to calculate kW with the electrical data collected in Section 3 above:
VA = 3 VI where V = voltage phase to phase
I = amperage per phase
PF = Sin where = phase angle between V & I KW = VA PF
-
VERIFICATION TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-250
7.0 Calculate chiller efficiency (kW/ton) at full-load operation and the part-load operation levels tested
above and plot the results, as follows:
7.1 Sort data into separate sets according to supply chilled water temperature ranges (for example,
one set of data in the range of 50 to 52F, a second set for 53 to 55F, etc.). Select the smallest
range that includes an adequate number of data points and proceed with plot preparation.
7.2 Plot chiller kW versus chiller tons for each sorted data set. Where outside air temperatures
differed by more than 5F (for example, 60 to 64F, 75 to 79F, etc.) during the test, identify
the plotted points common to each range.
7.3 Curve fit each group (designated by outside temperature range) of plotted points.
8.0 Record Results
8.1 Prime Contractor shall record and submit results of the verification testing to CES Project
Manager.
8.2 If specified equipment is not installed or operational, Prime Contractor shall report remedial
action required and reschedule verification tests.
9.0 Non-Compliance and Corrections
The following items did not comply with manufacturers or contract specifications and require correction:
9.1
9.2
9.3
9.4
-
FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-251
Functional Performance Tests: The Prime Contractor shall demonstrate performance of
chilled water system in accordance with the final design-intent document and
manufacturers and contract specifications. The building operators assistance will be required to change setpoints for the duration of the testing and restore them to their
original settings after the tests have been competed. The tests will be conducted while
the occupant and equipment loads are minimal.
The following checklist shall serve as a general guideline for the functional perfor-
mance testing, although the project-specific character of the tests required must be
considered. This checklist should be refined by the Prime Contractor to address
project-specific details and information gathered during the pre-startup inspections and
verification testing.
-
FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-252
1.0 Provide simulated cooling load in building:
1.1 Modify control system setpoints, as required, to facilitate chillers response to simulated building load.
1.2 Switch system to warm-up mode in order to open all supply ducts, where VAV boxes may be present, and set fan powered box coils to full heat.
1.3 Start the building air handling units in order to provide a cooling load for the chiller(s).
1.4 Operate boilers or use outside air to provide cooling load in building depending upon the outside
air temperature and the design conditions to be simulated.
2.0 Establish stable operation of the chiller in accordance with the final design-intent document, then
measure and record the following data:
2.1 Chilled water flow (gpm):
Record chiller inlet/outlet pressure readings and compare to chiller design conditions, Test and
Balance Report and chiller manufacturers performance data. DESIGN T&B F.P.T. ACTUAL
Chiller Inlet Pressure (psig)
Chiller Outlet Pressure (psig)
2.2 Record chilled water supply and return temperature readings and compare to readout on chiller
control panel.
DISPLAYED ACTUAL
Chilled Water Supply Temp (F)
Chilled Water Return Temp (F)
2.3 Record for chiller: amperage each phase, voltage phase to phase, voltage phase to ground, and
power factor.
PHASE 1 PHASE 2 PHASE 3
Amperage
Voltage
Voltage
Voltage to Ground
Power Factor
KW (use PMT)
2.4 Record for chilled water pump: amperage each phase, voltage phase to phase, voltage phase to
ground, and power factor.
PHASE 1 PHASE 2 PHASE 3
Amperage
Voltage
Voltage
Voltage to Ground
Power Factor
KW (use PMT)
2.5 Record the following information:
Ambient outside air DB temperature (F):
Entering chilled water temperature (F):
Leaving chilled water temperature (F):
-
FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-253
3.0 Use the following equation to calculate kW with the electrical data collected in Section 2 above:
VA = 3 VI where V = voltage phase to phase
I = amperage per phase
PF = Sin where = phase angle between V & I KW = VA PF
4.0 Calculate chiller efficiency (kW/ton) at the specified load-levels tested above and plot the results,
as follows:
4.1 Sort data into separate sets according to supply chilled water temperature ranges (for example,
one set of data in the range of 50 to 52F, a second set for 53 to 55F, etc.). Select the smallest
range that includes an adequate number of data points and proceed with plot preparation.
4.2 Plot chiller kW versus chiller tons for each sorted data set. Where outside air temperatures
differed by more than 5F (for example, 60 to 64F, 75 to 79F, etc.) during the test, identify
the plotted points common to each range.
4.3 Curve fit each group (designated by outside temperature range) of plotted points.
5.0 Compare chiller calculated performance and plotted curves to manufacturers rated efficiency, performance specifications and part-load curves:
6.0 Record Results
6.1 Prime Contractor shall record and submit results of the functional performance testing to CES
Project Manager.
6.2 If specified equipment performance is not verified, Prime Contractor shall report remedial action
required and reschedule functional performance tests.
7.0 Non-Compliance and Corrections
The following items did not comply with the final design-intent document or manufacturers or contract specifications and require correction:
7.1
7.2
7.3
7.4
8.0 Documentation required in complete Final Commissioning Report
9.1 Certified pre-startup checklists
8.2 Certified verification and functional performance test checklists
8.3 Test and Balance Report
8.4 Vendor cut sheets and pump curves
8.5 Manufacturers product design data 8.6 Operation and maintenance manuals
8.7 Manufacturers installation specifications 8.8 Final as-built drawings
-
FUNCTIONAL PERFORMANCE TEST CHECKLIST PACKAGED AIR-COOLED CHILLER
Revision No. 0: 5/95 Test Plans 6-254
9.0 Certification
We the undersigned witnessed the verification and functional performance tests and certify that the
testing procedures for the packaged air-cooled chiller EEM identified above have been completed,
that the equipment tested has met the established operational and performance requirements and
that all corrections required due to non-compliance with the contract documents, manufacturers specifications and final design-intent document have been made.
Date:
9.1 Name:
Company name:
Role in inspection:
Signature:
9.2 Name:
Company name:
Role in inspection:
Signature:
9.3 Name:
Company name:
Role in inspection:
Signature:
9.4 Name:
Company name:
Role in inspection:
Signature: