commissioning generators and its auxiliary system

Upload: sam

Post on 05-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    1/90

    24 May 2012 PMI Revision 00 1

    COMMISSIONING OF

    GENERATOR AND

    ITS AUXILIARY

    SYSTEM

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    2/90

    24 May 2012 PMI Revision 00 2

    GENERATORS AND ITS AUXILIARYCAN BE BROADLY DIVIDED INTOTHREE SYSTEMS

    A) Stator water system B) Seal oil system

    C) Gas system

    D) Generator

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    3/90

    24 May 2012 PMI Revision 00 3

    STATOR WATER SYSTEM

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    4/90

    24 May 2012 PMI Revision 00 4

    STATOR WINDINGWATER SYSTEM

    DIFF PRESSSWITCH

    VACUUMPUMPS

    POLISH UNIT

    FILTERS

    COOLERS

    PUMPS

    GAS TRAP

    FLOWMETERS

    CONDUCTIVITY

    EXPANSIONTANK

    MAKEUP

    FSI

    IDIFF PRESS.

    MAGNETFILTER

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    5/90

    24 May 2012 PMI Revision 00 5

    Stator water cooling is a closed loop system.

    There are two full capacity single stagecentrifugal pumps with change over facility.

    The pumps are driven by 3Ph. 415V A.C.

    motors. The stator water cooler is shell and tube type

    heat exchanger.

    DM water flows through shell.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    6/90

    24 May 2012 PMI Revision 00 6

    There are two mechanical filters and one

    magnetic filters. Mechanical filters are of wire mesh type.

    Magnetic filter is having permanent magnet.

    The expansion tank is a hermetically sealedcontainer made of S.S.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    7/90

    24 May 2012 PMI Revision 00 7

    Float valve in the expansion tank maintains

    water level in the tank which act as suctionstorage tank for stator water pumps.

    Polishing unit (mixed bed ion exchanger)

    maintains conductivity of stator water to desiredlevel.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    8/90

    24 May 2012 PMI Revision 00 8

    For commissioning, first the system has to be

    filled up.

    Prerequisites for filling the cooling circuits:

    a) complete circuit should be flushed,

    b) hydraulic testing,

    c) installation of pump and motors after O/H,

    d) filters cleaned and boxed up,

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    9/90

    24 May 2012 PMI Revision 00 9

    e) coolers and all other components are boxed

    up,f) ion exchanger is ready and is in service,

    g) all instruments and measuring devices are in

    position after calibration.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    10/90

    24 May 2012 PMI Revision 00 10

    System should be lined up for filling.

    Complete stator water system should be filledwith DM water having required quality.

    All air should be vented from the system before

    starting of the pump.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    11/90

    24 May 2012 PMI Revision 00 11

    Trial run of the stator water pumps is

    satisfactory. Check the stand by pump for automatic starting

    on all interlocks and protections,

    Adjust level regulator in the expansion tank, Check all the signaling, indicating, recording,

    event logging, metering instruments, alarms and

    annunciating devices for proper functioning.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    12/90

    24 May 2012 PMI Revision 00 12

    Adjust make up water pressure around

    2.0Kg/cm2

    Adjust small water flow through the gas trap

    Check there is no leakage of water in the

    system Take ejector into service

    Take one cooler into service

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    13/90

    24 May 2012 PMI Revision 00 13

    Check emergency switching in circuit of the stand

    by water pump Check high and low alarm of the expansion tank

    Check high conductivity alarm and tripping

    Check pump discharge pr., filter diff. pr.,conductivity, flow, inlet winding pr., winding diff. pr.,vacuum in expansion tank, motors current.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    14/90

    24 May 2012 PMI Revision 00 14

    SEAL OIL SYSTEM

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    15/90

    24 May 2012 PMI Revision 00 15

    SEAL OIL SYSTEM

    OILCOOLER

    FILTERS

    DPRV

    CONSTANT PRESS. REGULATORSWITH ORFICE PLATES

    VACCUM

    PUMP

    BEARG

    DRAINS

    TG

    1 2

    EE

    BEARING

    TEBEARING

    GASEXHAUST

    FROM GAS

    SYSTEM

    IOT

    VACUUM

    TANK

    SOST

    SOPSOP-3

    DC

    DPSW

    TS ES

    FR

    FLOW M.PS PG

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    16/90

    24 May 2012 PMI Revision 00 16

    Generator shaft seals are supplied with

    pressuerised seal oil to prevent hydrogenescape at the shaft.

    Oil pressure is kept higher than the gas

    pressure. AC seal oil pump one number and DC seal

    oil pump- one number are provided which

    feed the oil to the seal through cooler andfilter.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    17/90

    24 May 2012 PMI Revision 00 17

    Both the AC seal oil pumps are 100%

    capacity screw type pumps. A vacuum pump is provided to maintain

    vacuum in seal oil tank.

    There is a additional facility to supply seal oilfrom governing oil.

    The seal oil pressure to the seal is controlled

    by DPR which maintain specified DPbetween oil and hydrogen.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    18/90

    24 May 2012 PMI Revision 00 18

    Thrust oil holds the seal ring in position

    against gas pressure. Two seal oil coolers each having 100%

    capacity is provided to cool the oil.

    Duplex filter is provided in the oil line.

    Vacuum pump evacuates gases from SOT.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    19/90

    24 May 2012 PMI Revision 00 19

    Seal oil system will be commissioned when the

    following system is ready1) Generator ready to be filled with hydrogen or air.

    2) Machine (TG) ready to be put on barring gear.

    Prior to commissioning make ensure properfunctioning of all the signaling, indicating, recording,event logging, metering instruments, alarms andannunciating devices.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    20/90

    24 May 2012 PMI Revision 00 20

    Seal oil system has to be filled with oil

    Prerequisite for oil filling

    1) set all level switches

    2) close all stop and non-return shut offvalves

    3) open all pressure gauge and pressureswitches isolating valves

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    21/90

    24 May 2012 PMI Revision 00 21

    4) open pressure transducer isolatingvalves

    5) open isolating valves of impulse lines

    of differential pressure regulator6) bearing lube oil system is in service

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    22/90

    24 May 2012 PMI Revision 00 22

    Open isolating valve of seal oil storage tank

    to seal oil system. Oil will start filling the sealoil system

    Open valves in oil flow path

    Take coolers and filters into service

    After oil is filled up into the system level willbe visible in the gauge glass of the SOT

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    23/90

    24 May 2012 PMI Revision 00 23

    Take governing oil system into service

    Start AC seal oil pump

    To clear air locking seal oil pump should be

    switched on and off till its discharge pressuregauges shows a constant pressure

    Vent DPRV-A and DPRV-B

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    24/90

    24 May 2012 PMI Revision 00 24

    Vent both the coolers one by one

    Vent filters

    Vent pressure gauges, pressure switches

    and transmitters

    Set seal oil pressure by DPRV-A

    Stop AC seal oil pump and set DPRV-B

    (

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    25/90

    24 May 2012 PMI Revision 00 25

    Set thrust oil pressure (0.5 Kg/cm2 more than

    seal oil pressure) Take vacuum pump into service and adjust

    SOT vacuum as recommended

    Check all the meter readings are within limit

    Check seal oil flow is as per systemrequirement

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    26/90

    24 May 2012 PMI Revision 00 26

    Check automatic starting of stand by DC seal oil

    pump by different interlocks including alarm Check function of level switch of SOT, seal oil

    storage tank and pre-chambers

    After seal oil temperature reaches 30

    0

    C startcooling water flow to seal oil cooler and adjustthe flow in such a way so that the seal oiltemperature is maintained at 400C

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    27/90

    24 May 2012 PMI Revision 00 27

    HYDROGEN GAS SYSTEM

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    28/90

    24 May 2012 PMI Revision 00 28

    H2DISTRIB

    HYDROGEN

    CO2VAPOURIZER

    TO

    SEALOIL

    DPT

    H2 DRIER

    HYDROGEN GAS SYSTEM

    CO2

    ANALYZER

    DRAIN

    AIR

    FILTER

    OP

    DPI

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    29/90

    24 May 2012 PMI Revision 00 29

    Overhauling of gas drier has been carried

    and the drier is boxed up Check all instruments are in position after

    calibration

    Functionally check the gas drier system Check the availability of adequate no of CO2

    filling point and adequate no of CO2 cylinders

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    30/90

    24 May 2012 PMI Revision 00 30

    Check availability of adequate no of

    Hydrogen filling points and cylinders

    Functionally check the LLD system

    Check whether the relief valves in the highpressure valves are alright

    Check the generator is completely boxed up

    Check the seal oil system is in service

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    31/90

    24 May 2012 PMI Revision 00 31

    Check generator air tightness test is

    successfully completed.

    Start purging air with CO2 till the purity ofCO2 inside casing reaches above 95%.

    After CO2 purity reaches as desired startpurging CO2 with Hydrogen.

    Continue purging till hydrogen purity reaches

    above 98%.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    32/90

    24 May 2012 PMI Revision 00 32

    GAS SYSTEM

    Pressurise generator casing with hydrogenup to its design value

    Recheck hydrogen leakages by detector

    Take drier into service

    Take gas coolers into service

    Vent the coolers and establish flow

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    33/90

    24 May 2012 PMI Revision 00 33

    TESTS ON GENERATOR

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    34/90

    24 May 2012 PMI Revision 00 34

    The field tests of the generator include theacceptance tests and periodic tests.The Acceptance tests are performed during

    the erection and after completion of theerection.

    The periodic tests are carried out duringoverhauls, routine repairs and during the time

    between repairs.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    35/90

    24 May 2012 PMI Revision 00 35

    Measurement of Insulation ResistanceEach phase relative to

    the earthed casing (frame) and other phasesearthed. Bus-duct shall be disconnected.IR measurement at 2500Volts

    After

    the water connections are mounted and before

    the external parts of the cooling system isconnected.IR measurement at 2500Volts

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    36/90

    24 May 2012 PMI Revision 00 36

    a) The insulation resistance of the stator winding

    shall be measured with distillate drained from thestator winding, the water headers being connectedto the ohmmeter screen and isolated from theexternal cooling systems.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    37/90

    24 May 2012 PMI Revision 00 37

    b) The value of the ratio R60/R15 shall be at

    least 1.3 at a temperature of +10 C to +30

    C. If the value of the resistance R60 or ratioR60/R15 is below the permissible value, the

    stator winding shall be dried out accordingto the appropriate instructions, remove

    moisture from the winding by blowing it out

    with dry compressed air then recheck itsinsulation resistance.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    38/90

    24 May 2012 PMI Revision 00 38

    c) Prior to measuring the insulation resistance of

    the stator windings make sure that there was noingress of water to it during storages transit and

    erection of the stator (the condition of packagingwill show it.)

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    39/90

    24 May 2012 PMI Revision 00 39

    3. Rotor winding: IR measurement at 1000Volts.4. Bearing: Insulation resistance is measuredrelative to the base-plate, with oil pipingcompletely assembled, with no contactbetween the bearing and the rotor shaft

    journal. IR measurement at 1000 Volts.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    40/90

    24 May 2012 PMI Revision 00 40

    5. Resistance temperature detectors:Insulation resistance of RTDs is

    measured together with the wiring from,

    the measuring instrument to the RTDS,including that running within thegenerator. IR measurement at 1000 Volts.

    6. Insulation of oil catcher and the

    outer end shields of at the exciter end. IRmeasurement at 1000 Volts.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    41/90

    24 May 2012 PMI Revision 00 41

    Shaft seal at the exciter end: Insulation

    resistance as is measured between theshaft seal housing and the outer endshields, with oil piping completely

    assembled. IR measurement at 1000

    Volts.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    42/90

    24 May 2012 PMI Revision 00 42

    Measurement of A.C. Impedance ofRotor-winding This should be made with apower-frequency voltage of 220 V at differentrotor speeds varied in steps from 500 rpm to

    3000 rpm and on the stationary rotor. Theresults shall be compared with those obtainedpreviously, the condition of the generator

    during the compared measurements being thesame (the rotor is inside or outside thegenerator, the stator winding is open-circuitedor short-circuited, etc).

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    43/90

    24 May 2012 PMI Revision 00 43

    Leakage Test on Bearing and Shaft-Seal

    Housings The leakage test should be

    conducted with the use of white wash andkerosene, the leaks being detected by visualexamination. The shaft-seal housings shouldbe also tested for leakage with the use of

    kerosene . No leaks are permitted, The testduration is 24 h.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    44/90

    24 May 2012 PMI Revision 00 44

    Leakage Test on Stator WindingTerminals and Water Connections Theleakage test on the stator winding terminals

    should be done in several steps.First the terminal bars should be separatelytested for leakage and for strength. The test is

    conducted with water at a pressure of 2450kPa (25 kgf/cm2) applied for 1 h. No waterleaks are permitted.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    45/90

    24 May 2012 PMI Revision 00 45

    Leakage Test on Stator WindingTerminals and Water Connections When

    assembling, the terminal bushings, test themfor leakage in a special fixtures (tank) with airat a pressure of 490 kPa (5 kgf/cm2), gauge,applied for 1 h. The test shall be made on the

    completely assembled terminal bushing, Noleaks are permitted.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    46/90

    24 May 2012 PMI Revision 00 46

    Hydraulic Pressure Test on Gas CoolersPrior to mounting the gas coolers in the statorcasing, rust-preventive coatings should be

    remove from their surfaces and the tube finsblown with compressed air.The gas coolers are tested with a hydraulicpressure of 784 kPa (8.0 kgf/cm2) applied for60 min. No reduction of the test pressure andleaks should take place during the test.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    47/90

    24 May 2012 PMI Revision 00 47

    Hydraulic Pressure Test on Gas CoolersIn the gas coolers with installed protectors areliable contact between the protectors andprotected surface should be ensured. Theresistance shall not be greater than 0.1 ohm,

    The protectors shall not have a joint coating.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    48/90

    24 May 2012 PMI Revision 00 48

    Hydraulic Pressure Test an StatorWindingThe hydraulic pressure test on the statorwinding is made with DM water at a pressure

    of 764 kPa (8 kgf/cm ) applied for at least 24 h.Before the distillate pressure is increased, tothe required value, the air shall be fully

    expelled from the system. No reduction of thetest pressure, no signs of moisture an thewinding, headers, flexible tubes and theirsections are permitted during the test.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    49/90

    24 May 2012 PMI Revision 00 49

    Gas Leakage Tests on Rotor, Stator andAssembled Generator

    After the generator erection / overhauls /routine repairs wherever dismantling of theouter end shields or removal of the gascoolers is involved, the generator and its

    separate parts should be subjected to a gasleakage test.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    50/90

    24 May 2012 PMI Revision 00 50

    Gas leakage Test on the current carryingbolts (Rotor)The test should be performed before the rotoris inserted into the stator. Air is applied in turn

    to the gland seals of each current-carryingbolt through special radial holes in the rotorshaft, Gas leakage is determined from a dropof the test pressure.The detected leaks should be eliminated by re-packing or replacement of the gland seals bytheir.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    51/90

    24 May 2012 PMI Revision 00 51

    Gas Leakage Test on AssembledGeneratorThe leakage test is aimed at tracing and

    stopping air leakage in the stator casingassembled with the terminals, gas coolers,shields, water connections. The air used forthe test shall be dry and clean. The leaks

    should be located with the help of soapsolution applied to the welds and to all jointsof the parts and comments.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    52/90

    24 May 2012 PMI Revision 00 52

    After the traced leaks are stopped, the secondstep of testing determines the leakage rateand is per formed at an air-pressure equal tothe rated hydrogen pressure applied for 24 h.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    53/90

    24 May 2012 PMI Revision 00 53

    Note: It should be noted that a 1 Cchange in the air temperature inside thegenerator part under will result in a 1.6

    kPa change in the air pressure, the testpressure being 392 kPa (4 kgf/cm2),gauge. Therefore, when the leakage tests

    are conducted, special attention shouldbe paid to the variation of airtemperature inside the part under test.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    54/90

    24 May 2012 PMI Revision 00 54

    Testing of rotor vent ducts for freepassage of airMark out the rotor slots in a clockwise

    direction (as viewed from the slip rings

    end), starting from the big pole tooth

    located in that part of the rotor where thefield current lead is connected to the

    inner slip rings. Number the vent ducts

    in the wedges of each slot, starting fromthe retaining ring located at the slip-ring

    end.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    55/90

    24 May 2012 PMI Revision 00 55

    TESTING

    (1) Using the stoppers, plug all the holesin the seat wedges(2) Take out the stoppers from the inlet

    and outlet holes of the vent duct betested.(3) Fit the nipple of the inlet nozzle into

    the inlet hole of the vent duct, and that ofthe outlet nozzle into the outlet hole, the

    liquid-filled column micro-manometerbeing connected to the outlet nozzle.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    56/90

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    57/90

    24 May 2012 PMI Revision 00 57

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    58/90

    24 May 2012 PMI Revision 00 58

    EXAMINATION OF ROTOR RETAINING

    RINGS BY DYE-PENETRANT METHODThe dye-penetration method of surfaceexamination is used for detecting cracks

    and other types of discontinuities on thesurface of the rotor retaining rings. Themethod is based on the ability of some

    aniline dye solutions to penetrate intothe various types of discontinuities in

    materials.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    59/90

    24 May 2012 PMI Revision 00 59

    Clean the surface to be examined to amirror-like condition. Polish out roughmarks or, otherwise, they may affect the

    examination results directly beforeapplication of the dye-penetrant solution,de grease the examined surface area. Applya continuous coat of the dye penetrationsolution to the examined surface. As the

    solution coat dries out, apply another coat.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    60/90

    24 May 2012 PMI Revision 00 60

    After 15-20 min, remove quickly and

    thoroughly the dye-penetrant solutionwith soft clean cloth. Using a spraygun or a flat brush, apply a smooth

    coat of whitewash. Examine thesurface 5 min after the white wash hasbeen applied. Appearance of red veins

    on the surface is indicative of thepresence of cracks.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    61/90

    24 May 2012 PMI Revision 00 61

    The dry-penetrant solutions shall be

    prepared and applied in the open air or in aproperly ventilated room as all the dry-penetrant solution components are fire-

    hazardous. Therefore, no smoking, no openflame, no sparking and no switching on ofelectric device are allowed near the placewhere the solution is prepared orexamination is conducted. Rubber glovesare to be used when preparing for andconducting the examination.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    62/90

    24 May 2012 PMI Revision 00 62

    ELCID (Electrical Core ImperfectionDetection) test on Stator Core: This test is

    conducted to assess the condition of thestator core by testing for location of anyinter-turn shorting in the stator corelamination. This test is repeated in everyoverhaul involving rotor thread out.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    63/90

    24 May 2012 PMI Revision 00 63

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    64/90

    24 May 2012 PMI Revision 00 64

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    65/90

    24 May 2012 PMI Revision 00 65

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    66/90

    24 May 2012 PMI Revision 00 66

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    67/90

    24 May 2012 PMI Revision 00 67

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    68/90

    24 May 2012 PMI Revision 00 68

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    69/90

    24 May 2012 PMI Revision 00 69

    Prior to the initial start of the generator, thefollowing shall be done:(1) All civil construction work according to thedesign documents shall be completed, the

    general and local lighting systems shall beinstalled.(2) Erection of the generator, installation of theauxiliary equipment, primary and secondary

    switching circuits and their associated equipmentshould be completed, the completion of the workrecorded.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    70/90

    24 May 2012 PMI Revision 00 70

    (3) All pre-operational electrical measurementsand tests included in the generatoracceptance test program shall be performed.

    (4) Water-, gas- and oil-supply systems,thermal-control, delaying, alarm and indicationcircuit shall be adjusted and tested, non-electrical protections shall be put on guard.

    (5) All safety and fire prevention measuresshall be taken.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    71/90

    24 May 2012 PMI Revision 00 71

    The initial start and initial operation of thegenerator shall be performed in accordance

    with the test and commissioning program. Allwork on the initial start and operation shouldbe done in accordance with this instructionmanual, the relevant operating rules and the

    directions of the generator manufacturer.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    72/90

    24 May 2012 PMI Revision 00 72

    Initial Start of GeneratorWith the rotor stationary, proceed as follows:(1) Supply oil to the generating unit bearingsand shaft seals and make sure that the oil isflowing to the drain pipes normally.(2) Fill the generator with hydrogen so that thehydrogen pressure reaches the rated value.

    Use carbon dioxide or nitrogen to purge airfrom the generator before filling it withhydrogen.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    73/90

    24 May 2012 PMI Revision 00 73

    (3) Ensure that the differential pressurebetween the seal oil and gas inside thegenerator, as specified, is maintainedautomatically. During the initial start (while

    accelerating the generator to the rated speed),measure the vibration on the bearings andensure that there is no unusual noise, rubbing,

    etc. in the generator. Go rapidly through thecritical speeds at which the highest vibrationson the rotor are observed.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    74/90

    24 May 2012 PMI Revision 00 74

    With the rotor at the rated speed,check the following:(1) Temperature of oil at outlets of all thebearings, and temperature of the bearingliners and shaft-seal bushes, vibration on thegenerator supports,

    (2) Operation of the generator and exciterbrush gear.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    75/90

    24 May 2012 PMI Revision 00 75

    (3) Generator phase sequence and phasing onthe power system, residual voltage, withoutapplication of field excitation of the rotor).4) Proper circulation of water in the cooling

    circuits of, the stator, gas coolers, heatexchangers.Abnormalities revealed (if any) after the initial

    start and mechanical run may be eliminated bystopping the generator and inspection of thebearings.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    76/90

    24 May 2012 PMI Revision 00 76

    The electrical tests on the generator

    should be conducted in accordance withthe acceptance test program.

    No limitation is imposed on the rate ofraising the generator terminal voltage for

    starts form both cold and hot conditions.

    There is no need to warm-up the

    generator before raising the voltage.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    77/90

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    78/90

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    79/90

    24 May 2012 PMI Revision 00 79

    No specific limit is placed on the extent ofdeviation of the obtained characteristic fromthose determined earlier. The test should beconducted at the rated hydrogen pressure.

    During this test, measure and record all the PToutput voltages. Also ensure, measure andrecord availability of PT voltages at all voltage

    / impedance operated relays.PT Voltages in the synchronising circuit to beverified.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    80/90

    24 May 2012 PMI Revision 00 80

    Three-Phase short-circuitCharacteristic of Generating Unit

    This characteristic should be determined withthe stator current reaching the rated value.Prior to obtaining the characteristic, a shortinglink should be installed behind thetransformer. The hydrogen pressure should be

    equal to the rated value.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    81/90

    24 May 2012 PMI Revision 00 81

    The deviation of the obtained short circuitcharacteristic from those determined earliershould be within the accuracy of

    measurements.

    During the SCC testing, measure and recordthe reflection of the CT secondary of all the

    CTs. Ensure the CT juice is available at all therelevant relays.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    82/90

    24 May 2012 PMI Revision 00 82

    Safety precautions including fire fighting

    equipments are available. Oil supply to generator bearing and seal

    has been established and quality/flow of

    oil is as per specification. Generator is filled with hydrogen of

    desired purity and up to rated pressure.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    83/90

    24 May 2012 PMI Revision 00 83

    Generator stator winding is charged with

    distillate of desired quality. The otherparameters of distillate is as per norms

    Generator gas coolers are charged and the

    parameters are normal Generator circuit breaker is in open

    condition after testing

    All switchyard equipments has been testedand normalised

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    84/90

    24 May 2012 PMI Revision 00 84

    All protection and control schemes are in

    service after callibration and testing Excitation system has been tested,

    normalised and field breaker has been kept

    in open condition. Mode of excitation system has been

    selected (auto/man)

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    85/90

    24 May 2012 PMI Revision 00 85

    When generator reaches rated speed check

    the followinga) bearing and seal temperatures

    b) performance of brush gear

    c) vibrations

    d) any gas, oil or water leakages

    e) any abnormalities in generator

    performance

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    86/90

    24 May 2012 PMI Revision 00 86

    Switch on excitation system and check forvarious parameters and functioning of excitation

    system After ensuring all parameters are all right and

    machine behavior is normal match thegenerators electrical parameters with the gridand synchronise the machine when permissivefor the same is available. The generator shall beswitched into the power system at precisesynchronizing.

    Load the machine gradually. During loading alsomonitor all parameters.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    87/90

    24 May 2012 PMI Revision 00 87

    Inspection after Initial Operation Under

    Load

    The initial operation under load is considered tohave been accomplished if the generator hasshown normal performance during continuousoperation for 72 hours of switching thegenerator into the power system.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    88/90

    24 May 2012 PMI Revision 00 88

    After the 72-h operation, make inspection ofthe generator. During the inspection,disassemble the bearing and shaftirrespective whether any abnormalities have

    been noted or in their performance duringadjustment and testing. The inspectioninvolves the visual examination of the shaft

    journals, babbit-lined faces of the bearingliner an shaft-seal bushes.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    89/90

    24 May 2012 PMI Revision 00 89

    Clean the filters of the oil system and statorwinding cooling system. Remove scratches,marks, etc. on the shaft journals and babbit-lined faces by polishing or scraping. Stop theleaks detected in valves, flange joints, etc.

    The generator is to be placed in commercialoperation after completion of the adjustmentand testing, and upon elimination of defectsand workmanship faults revealed during the

    inspection.

  • 7/31/2019 Commissioning Generators and Its Auxiliary System

    90/90