commissioning generators and its auxiliary system
TRANSCRIPT
-
7/31/2019 Commissioning Generators and Its Auxiliary System
1/90
24 May 2012 PMI Revision 00 1
COMMISSIONING OF
GENERATOR AND
ITS AUXILIARY
SYSTEM
-
7/31/2019 Commissioning Generators and Its Auxiliary System
2/90
24 May 2012 PMI Revision 00 2
GENERATORS AND ITS AUXILIARYCAN BE BROADLY DIVIDED INTOTHREE SYSTEMS
A) Stator water system B) Seal oil system
C) Gas system
D) Generator
-
7/31/2019 Commissioning Generators and Its Auxiliary System
3/90
24 May 2012 PMI Revision 00 3
STATOR WATER SYSTEM
-
7/31/2019 Commissioning Generators and Its Auxiliary System
4/90
24 May 2012 PMI Revision 00 4
STATOR WINDINGWATER SYSTEM
DIFF PRESSSWITCH
VACUUMPUMPS
POLISH UNIT
FILTERS
COOLERS
PUMPS
GAS TRAP
FLOWMETERS
CONDUCTIVITY
EXPANSIONTANK
MAKEUP
FSI
IDIFF PRESS.
MAGNETFILTER
-
7/31/2019 Commissioning Generators and Its Auxiliary System
5/90
24 May 2012 PMI Revision 00 5
Stator water cooling is a closed loop system.
There are two full capacity single stagecentrifugal pumps with change over facility.
The pumps are driven by 3Ph. 415V A.C.
motors. The stator water cooler is shell and tube type
heat exchanger.
DM water flows through shell.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
6/90
24 May 2012 PMI Revision 00 6
There are two mechanical filters and one
magnetic filters. Mechanical filters are of wire mesh type.
Magnetic filter is having permanent magnet.
The expansion tank is a hermetically sealedcontainer made of S.S.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
7/90
24 May 2012 PMI Revision 00 7
Float valve in the expansion tank maintains
water level in the tank which act as suctionstorage tank for stator water pumps.
Polishing unit (mixed bed ion exchanger)
maintains conductivity of stator water to desiredlevel.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
8/90
24 May 2012 PMI Revision 00 8
For commissioning, first the system has to be
filled up.
Prerequisites for filling the cooling circuits:
a) complete circuit should be flushed,
b) hydraulic testing,
c) installation of pump and motors after O/H,
d) filters cleaned and boxed up,
-
7/31/2019 Commissioning Generators and Its Auxiliary System
9/90
24 May 2012 PMI Revision 00 9
e) coolers and all other components are boxed
up,f) ion exchanger is ready and is in service,
g) all instruments and measuring devices are in
position after calibration.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
10/90
24 May 2012 PMI Revision 00 10
System should be lined up for filling.
Complete stator water system should be filledwith DM water having required quality.
All air should be vented from the system before
starting of the pump.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
11/90
24 May 2012 PMI Revision 00 11
Trial run of the stator water pumps is
satisfactory. Check the stand by pump for automatic starting
on all interlocks and protections,
Adjust level regulator in the expansion tank, Check all the signaling, indicating, recording,
event logging, metering instruments, alarms and
annunciating devices for proper functioning.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
12/90
24 May 2012 PMI Revision 00 12
Adjust make up water pressure around
2.0Kg/cm2
Adjust small water flow through the gas trap
Check there is no leakage of water in the
system Take ejector into service
Take one cooler into service
-
7/31/2019 Commissioning Generators and Its Auxiliary System
13/90
24 May 2012 PMI Revision 00 13
Check emergency switching in circuit of the stand
by water pump Check high and low alarm of the expansion tank
Check high conductivity alarm and tripping
Check pump discharge pr., filter diff. pr.,conductivity, flow, inlet winding pr., winding diff. pr.,vacuum in expansion tank, motors current.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
14/90
24 May 2012 PMI Revision 00 14
SEAL OIL SYSTEM
-
7/31/2019 Commissioning Generators and Its Auxiliary System
15/90
24 May 2012 PMI Revision 00 15
SEAL OIL SYSTEM
OILCOOLER
FILTERS
DPRV
CONSTANT PRESS. REGULATORSWITH ORFICE PLATES
VACCUM
PUMP
BEARG
DRAINS
TG
1 2
EE
BEARING
TEBEARING
GASEXHAUST
FROM GAS
SYSTEM
IOT
VACUUM
TANK
SOST
SOPSOP-3
DC
DPSW
TS ES
FR
FLOW M.PS PG
-
7/31/2019 Commissioning Generators and Its Auxiliary System
16/90
24 May 2012 PMI Revision 00 16
Generator shaft seals are supplied with
pressuerised seal oil to prevent hydrogenescape at the shaft.
Oil pressure is kept higher than the gas
pressure. AC seal oil pump one number and DC seal
oil pump- one number are provided which
feed the oil to the seal through cooler andfilter.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
17/90
24 May 2012 PMI Revision 00 17
Both the AC seal oil pumps are 100%
capacity screw type pumps. A vacuum pump is provided to maintain
vacuum in seal oil tank.
There is a additional facility to supply seal oilfrom governing oil.
The seal oil pressure to the seal is controlled
by DPR which maintain specified DPbetween oil and hydrogen.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
18/90
24 May 2012 PMI Revision 00 18
Thrust oil holds the seal ring in position
against gas pressure. Two seal oil coolers each having 100%
capacity is provided to cool the oil.
Duplex filter is provided in the oil line.
Vacuum pump evacuates gases from SOT.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
19/90
24 May 2012 PMI Revision 00 19
Seal oil system will be commissioned when the
following system is ready1) Generator ready to be filled with hydrogen or air.
2) Machine (TG) ready to be put on barring gear.
Prior to commissioning make ensure properfunctioning of all the signaling, indicating, recording,event logging, metering instruments, alarms andannunciating devices.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
20/90
24 May 2012 PMI Revision 00 20
Seal oil system has to be filled with oil
Prerequisite for oil filling
1) set all level switches
2) close all stop and non-return shut offvalves
3) open all pressure gauge and pressureswitches isolating valves
-
7/31/2019 Commissioning Generators and Its Auxiliary System
21/90
24 May 2012 PMI Revision 00 21
4) open pressure transducer isolatingvalves
5) open isolating valves of impulse lines
of differential pressure regulator6) bearing lube oil system is in service
-
7/31/2019 Commissioning Generators and Its Auxiliary System
22/90
24 May 2012 PMI Revision 00 22
Open isolating valve of seal oil storage tank
to seal oil system. Oil will start filling the sealoil system
Open valves in oil flow path
Take coolers and filters into service
After oil is filled up into the system level willbe visible in the gauge glass of the SOT
-
7/31/2019 Commissioning Generators and Its Auxiliary System
23/90
24 May 2012 PMI Revision 00 23
Take governing oil system into service
Start AC seal oil pump
To clear air locking seal oil pump should be
switched on and off till its discharge pressuregauges shows a constant pressure
Vent DPRV-A and DPRV-B
-
7/31/2019 Commissioning Generators and Its Auxiliary System
24/90
24 May 2012 PMI Revision 00 24
Vent both the coolers one by one
Vent filters
Vent pressure gauges, pressure switches
and transmitters
Set seal oil pressure by DPRV-A
Stop AC seal oil pump and set DPRV-B
(
-
7/31/2019 Commissioning Generators and Its Auxiliary System
25/90
24 May 2012 PMI Revision 00 25
Set thrust oil pressure (0.5 Kg/cm2 more than
seal oil pressure) Take vacuum pump into service and adjust
SOT vacuum as recommended
Check all the meter readings are within limit
Check seal oil flow is as per systemrequirement
-
7/31/2019 Commissioning Generators and Its Auxiliary System
26/90
24 May 2012 PMI Revision 00 26
Check automatic starting of stand by DC seal oil
pump by different interlocks including alarm Check function of level switch of SOT, seal oil
storage tank and pre-chambers
After seal oil temperature reaches 30
0
C startcooling water flow to seal oil cooler and adjustthe flow in such a way so that the seal oiltemperature is maintained at 400C
-
7/31/2019 Commissioning Generators and Its Auxiliary System
27/90
24 May 2012 PMI Revision 00 27
HYDROGEN GAS SYSTEM
-
7/31/2019 Commissioning Generators and Its Auxiliary System
28/90
24 May 2012 PMI Revision 00 28
H2DISTRIB
HYDROGEN
CO2VAPOURIZER
TO
SEALOIL
DPT
H2 DRIER
HYDROGEN GAS SYSTEM
CO2
ANALYZER
DRAIN
AIR
FILTER
OP
DPI
-
7/31/2019 Commissioning Generators and Its Auxiliary System
29/90
24 May 2012 PMI Revision 00 29
Overhauling of gas drier has been carried
and the drier is boxed up Check all instruments are in position after
calibration
Functionally check the gas drier system Check the availability of adequate no of CO2
filling point and adequate no of CO2 cylinders
-
7/31/2019 Commissioning Generators and Its Auxiliary System
30/90
24 May 2012 PMI Revision 00 30
Check availability of adequate no of
Hydrogen filling points and cylinders
Functionally check the LLD system
Check whether the relief valves in the highpressure valves are alright
Check the generator is completely boxed up
Check the seal oil system is in service
-
7/31/2019 Commissioning Generators and Its Auxiliary System
31/90
24 May 2012 PMI Revision 00 31
Check generator air tightness test is
successfully completed.
Start purging air with CO2 till the purity ofCO2 inside casing reaches above 95%.
After CO2 purity reaches as desired startpurging CO2 with Hydrogen.
Continue purging till hydrogen purity reaches
above 98%.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
32/90
24 May 2012 PMI Revision 00 32
GAS SYSTEM
Pressurise generator casing with hydrogenup to its design value
Recheck hydrogen leakages by detector
Take drier into service
Take gas coolers into service
Vent the coolers and establish flow
-
7/31/2019 Commissioning Generators and Its Auxiliary System
33/90
24 May 2012 PMI Revision 00 33
TESTS ON GENERATOR
-
7/31/2019 Commissioning Generators and Its Auxiliary System
34/90
24 May 2012 PMI Revision 00 34
The field tests of the generator include theacceptance tests and periodic tests.The Acceptance tests are performed during
the erection and after completion of theerection.
The periodic tests are carried out duringoverhauls, routine repairs and during the time
between repairs.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
35/90
24 May 2012 PMI Revision 00 35
Measurement of Insulation ResistanceEach phase relative to
the earthed casing (frame) and other phasesearthed. Bus-duct shall be disconnected.IR measurement at 2500Volts
After
the water connections are mounted and before
the external parts of the cooling system isconnected.IR measurement at 2500Volts
-
7/31/2019 Commissioning Generators and Its Auxiliary System
36/90
24 May 2012 PMI Revision 00 36
a) The insulation resistance of the stator winding
shall be measured with distillate drained from thestator winding, the water headers being connectedto the ohmmeter screen and isolated from theexternal cooling systems.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
37/90
24 May 2012 PMI Revision 00 37
b) The value of the ratio R60/R15 shall be at
least 1.3 at a temperature of +10 C to +30
C. If the value of the resistance R60 or ratioR60/R15 is below the permissible value, the
stator winding shall be dried out accordingto the appropriate instructions, remove
moisture from the winding by blowing it out
with dry compressed air then recheck itsinsulation resistance.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
38/90
24 May 2012 PMI Revision 00 38
c) Prior to measuring the insulation resistance of
the stator windings make sure that there was noingress of water to it during storages transit and
erection of the stator (the condition of packagingwill show it.)
-
7/31/2019 Commissioning Generators and Its Auxiliary System
39/90
24 May 2012 PMI Revision 00 39
3. Rotor winding: IR measurement at 1000Volts.4. Bearing: Insulation resistance is measuredrelative to the base-plate, with oil pipingcompletely assembled, with no contactbetween the bearing and the rotor shaft
journal. IR measurement at 1000 Volts.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
40/90
24 May 2012 PMI Revision 00 40
5. Resistance temperature detectors:Insulation resistance of RTDs is
measured together with the wiring from,
the measuring instrument to the RTDS,including that running within thegenerator. IR measurement at 1000 Volts.
6. Insulation of oil catcher and the
outer end shields of at the exciter end. IRmeasurement at 1000 Volts.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
41/90
24 May 2012 PMI Revision 00 41
Shaft seal at the exciter end: Insulation
resistance as is measured between theshaft seal housing and the outer endshields, with oil piping completely
assembled. IR measurement at 1000
Volts.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
42/90
24 May 2012 PMI Revision 00 42
Measurement of A.C. Impedance ofRotor-winding This should be made with apower-frequency voltage of 220 V at differentrotor speeds varied in steps from 500 rpm to
3000 rpm and on the stationary rotor. Theresults shall be compared with those obtainedpreviously, the condition of the generator
during the compared measurements being thesame (the rotor is inside or outside thegenerator, the stator winding is open-circuitedor short-circuited, etc).
-
7/31/2019 Commissioning Generators and Its Auxiliary System
43/90
24 May 2012 PMI Revision 00 43
Leakage Test on Bearing and Shaft-Seal
Housings The leakage test should be
conducted with the use of white wash andkerosene, the leaks being detected by visualexamination. The shaft-seal housings shouldbe also tested for leakage with the use of
kerosene . No leaks are permitted, The testduration is 24 h.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
44/90
24 May 2012 PMI Revision 00 44
Leakage Test on Stator WindingTerminals and Water Connections Theleakage test on the stator winding terminals
should be done in several steps.First the terminal bars should be separatelytested for leakage and for strength. The test is
conducted with water at a pressure of 2450kPa (25 kgf/cm2) applied for 1 h. No waterleaks are permitted.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
45/90
24 May 2012 PMI Revision 00 45
Leakage Test on Stator WindingTerminals and Water Connections When
assembling, the terminal bushings, test themfor leakage in a special fixtures (tank) with airat a pressure of 490 kPa (5 kgf/cm2), gauge,applied for 1 h. The test shall be made on the
completely assembled terminal bushing, Noleaks are permitted.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
46/90
24 May 2012 PMI Revision 00 46
Hydraulic Pressure Test on Gas CoolersPrior to mounting the gas coolers in the statorcasing, rust-preventive coatings should be
remove from their surfaces and the tube finsblown with compressed air.The gas coolers are tested with a hydraulicpressure of 784 kPa (8.0 kgf/cm2) applied for60 min. No reduction of the test pressure andleaks should take place during the test.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
47/90
24 May 2012 PMI Revision 00 47
Hydraulic Pressure Test on Gas CoolersIn the gas coolers with installed protectors areliable contact between the protectors andprotected surface should be ensured. Theresistance shall not be greater than 0.1 ohm,
The protectors shall not have a joint coating.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
48/90
24 May 2012 PMI Revision 00 48
Hydraulic Pressure Test an StatorWindingThe hydraulic pressure test on the statorwinding is made with DM water at a pressure
of 764 kPa (8 kgf/cm ) applied for at least 24 h.Before the distillate pressure is increased, tothe required value, the air shall be fully
expelled from the system. No reduction of thetest pressure, no signs of moisture an thewinding, headers, flexible tubes and theirsections are permitted during the test.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
49/90
24 May 2012 PMI Revision 00 49
Gas Leakage Tests on Rotor, Stator andAssembled Generator
After the generator erection / overhauls /routine repairs wherever dismantling of theouter end shields or removal of the gascoolers is involved, the generator and its
separate parts should be subjected to a gasleakage test.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
50/90
24 May 2012 PMI Revision 00 50
Gas leakage Test on the current carryingbolts (Rotor)The test should be performed before the rotoris inserted into the stator. Air is applied in turn
to the gland seals of each current-carryingbolt through special radial holes in the rotorshaft, Gas leakage is determined from a dropof the test pressure.The detected leaks should be eliminated by re-packing or replacement of the gland seals bytheir.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
51/90
24 May 2012 PMI Revision 00 51
Gas Leakage Test on AssembledGeneratorThe leakage test is aimed at tracing and
stopping air leakage in the stator casingassembled with the terminals, gas coolers,shields, water connections. The air used forthe test shall be dry and clean. The leaks
should be located with the help of soapsolution applied to the welds and to all jointsof the parts and comments.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
52/90
24 May 2012 PMI Revision 00 52
After the traced leaks are stopped, the secondstep of testing determines the leakage rateand is per formed at an air-pressure equal tothe rated hydrogen pressure applied for 24 h.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
53/90
24 May 2012 PMI Revision 00 53
Note: It should be noted that a 1 Cchange in the air temperature inside thegenerator part under will result in a 1.6
kPa change in the air pressure, the testpressure being 392 kPa (4 kgf/cm2),gauge. Therefore, when the leakage tests
are conducted, special attention shouldbe paid to the variation of airtemperature inside the part under test.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
54/90
24 May 2012 PMI Revision 00 54
Testing of rotor vent ducts for freepassage of airMark out the rotor slots in a clockwise
direction (as viewed from the slip rings
end), starting from the big pole tooth
located in that part of the rotor where thefield current lead is connected to the
inner slip rings. Number the vent ducts
in the wedges of each slot, starting fromthe retaining ring located at the slip-ring
end.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
55/90
24 May 2012 PMI Revision 00 55
TESTING
(1) Using the stoppers, plug all the holesin the seat wedges(2) Take out the stoppers from the inlet
and outlet holes of the vent duct betested.(3) Fit the nipple of the inlet nozzle into
the inlet hole of the vent duct, and that ofthe outlet nozzle into the outlet hole, the
liquid-filled column micro-manometerbeing connected to the outlet nozzle.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
56/90
-
7/31/2019 Commissioning Generators and Its Auxiliary System
57/90
24 May 2012 PMI Revision 00 57
-
7/31/2019 Commissioning Generators and Its Auxiliary System
58/90
24 May 2012 PMI Revision 00 58
EXAMINATION OF ROTOR RETAINING
RINGS BY DYE-PENETRANT METHODThe dye-penetration method of surfaceexamination is used for detecting cracks
and other types of discontinuities on thesurface of the rotor retaining rings. Themethod is based on the ability of some
aniline dye solutions to penetrate intothe various types of discontinuities in
materials.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
59/90
24 May 2012 PMI Revision 00 59
Clean the surface to be examined to amirror-like condition. Polish out roughmarks or, otherwise, they may affect the
examination results directly beforeapplication of the dye-penetrant solution,de grease the examined surface area. Applya continuous coat of the dye penetrationsolution to the examined surface. As the
solution coat dries out, apply another coat.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
60/90
24 May 2012 PMI Revision 00 60
After 15-20 min, remove quickly and
thoroughly the dye-penetrant solutionwith soft clean cloth. Using a spraygun or a flat brush, apply a smooth
coat of whitewash. Examine thesurface 5 min after the white wash hasbeen applied. Appearance of red veins
on the surface is indicative of thepresence of cracks.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
61/90
24 May 2012 PMI Revision 00 61
The dry-penetrant solutions shall be
prepared and applied in the open air or in aproperly ventilated room as all the dry-penetrant solution components are fire-
hazardous. Therefore, no smoking, no openflame, no sparking and no switching on ofelectric device are allowed near the placewhere the solution is prepared orexamination is conducted. Rubber glovesare to be used when preparing for andconducting the examination.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
62/90
24 May 2012 PMI Revision 00 62
ELCID (Electrical Core ImperfectionDetection) test on Stator Core: This test is
conducted to assess the condition of thestator core by testing for location of anyinter-turn shorting in the stator corelamination. This test is repeated in everyoverhaul involving rotor thread out.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
63/90
24 May 2012 PMI Revision 00 63
-
7/31/2019 Commissioning Generators and Its Auxiliary System
64/90
24 May 2012 PMI Revision 00 64
-
7/31/2019 Commissioning Generators and Its Auxiliary System
65/90
24 May 2012 PMI Revision 00 65
-
7/31/2019 Commissioning Generators and Its Auxiliary System
66/90
24 May 2012 PMI Revision 00 66
-
7/31/2019 Commissioning Generators and Its Auxiliary System
67/90
24 May 2012 PMI Revision 00 67
-
7/31/2019 Commissioning Generators and Its Auxiliary System
68/90
24 May 2012 PMI Revision 00 68
-
7/31/2019 Commissioning Generators and Its Auxiliary System
69/90
24 May 2012 PMI Revision 00 69
Prior to the initial start of the generator, thefollowing shall be done:(1) All civil construction work according to thedesign documents shall be completed, the
general and local lighting systems shall beinstalled.(2) Erection of the generator, installation of theauxiliary equipment, primary and secondary
switching circuits and their associated equipmentshould be completed, the completion of the workrecorded.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
70/90
24 May 2012 PMI Revision 00 70
(3) All pre-operational electrical measurementsand tests included in the generatoracceptance test program shall be performed.
(4) Water-, gas- and oil-supply systems,thermal-control, delaying, alarm and indicationcircuit shall be adjusted and tested, non-electrical protections shall be put on guard.
(5) All safety and fire prevention measuresshall be taken.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
71/90
24 May 2012 PMI Revision 00 71
The initial start and initial operation of thegenerator shall be performed in accordance
with the test and commissioning program. Allwork on the initial start and operation shouldbe done in accordance with this instructionmanual, the relevant operating rules and the
directions of the generator manufacturer.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
72/90
24 May 2012 PMI Revision 00 72
Initial Start of GeneratorWith the rotor stationary, proceed as follows:(1) Supply oil to the generating unit bearingsand shaft seals and make sure that the oil isflowing to the drain pipes normally.(2) Fill the generator with hydrogen so that thehydrogen pressure reaches the rated value.
Use carbon dioxide or nitrogen to purge airfrom the generator before filling it withhydrogen.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
73/90
24 May 2012 PMI Revision 00 73
(3) Ensure that the differential pressurebetween the seal oil and gas inside thegenerator, as specified, is maintainedautomatically. During the initial start (while
accelerating the generator to the rated speed),measure the vibration on the bearings andensure that there is no unusual noise, rubbing,
etc. in the generator. Go rapidly through thecritical speeds at which the highest vibrationson the rotor are observed.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
74/90
24 May 2012 PMI Revision 00 74
With the rotor at the rated speed,check the following:(1) Temperature of oil at outlets of all thebearings, and temperature of the bearingliners and shaft-seal bushes, vibration on thegenerator supports,
(2) Operation of the generator and exciterbrush gear.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
75/90
24 May 2012 PMI Revision 00 75
(3) Generator phase sequence and phasing onthe power system, residual voltage, withoutapplication of field excitation of the rotor).4) Proper circulation of water in the cooling
circuits of, the stator, gas coolers, heatexchangers.Abnormalities revealed (if any) after the initial
start and mechanical run may be eliminated bystopping the generator and inspection of thebearings.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
76/90
24 May 2012 PMI Revision 00 76
The electrical tests on the generator
should be conducted in accordance withthe acceptance test program.
No limitation is imposed on the rate ofraising the generator terminal voltage for
starts form both cold and hot conditions.
There is no need to warm-up the
generator before raising the voltage.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
77/90
-
7/31/2019 Commissioning Generators and Its Auxiliary System
78/90
-
7/31/2019 Commissioning Generators and Its Auxiliary System
79/90
24 May 2012 PMI Revision 00 79
No specific limit is placed on the extent ofdeviation of the obtained characteristic fromthose determined earlier. The test should beconducted at the rated hydrogen pressure.
During this test, measure and record all the PToutput voltages. Also ensure, measure andrecord availability of PT voltages at all voltage
/ impedance operated relays.PT Voltages in the synchronising circuit to beverified.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
80/90
24 May 2012 PMI Revision 00 80
Three-Phase short-circuitCharacteristic of Generating Unit
This characteristic should be determined withthe stator current reaching the rated value.Prior to obtaining the characteristic, a shortinglink should be installed behind thetransformer. The hydrogen pressure should be
equal to the rated value.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
81/90
24 May 2012 PMI Revision 00 81
The deviation of the obtained short circuitcharacteristic from those determined earliershould be within the accuracy of
measurements.
During the SCC testing, measure and recordthe reflection of the CT secondary of all the
CTs. Ensure the CT juice is available at all therelevant relays.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
82/90
24 May 2012 PMI Revision 00 82
Safety precautions including fire fighting
equipments are available. Oil supply to generator bearing and seal
has been established and quality/flow of
oil is as per specification. Generator is filled with hydrogen of
desired purity and up to rated pressure.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
83/90
24 May 2012 PMI Revision 00 83
Generator stator winding is charged with
distillate of desired quality. The otherparameters of distillate is as per norms
Generator gas coolers are charged and the
parameters are normal Generator circuit breaker is in open
condition after testing
All switchyard equipments has been testedand normalised
-
7/31/2019 Commissioning Generators and Its Auxiliary System
84/90
24 May 2012 PMI Revision 00 84
All protection and control schemes are in
service after callibration and testing Excitation system has been tested,
normalised and field breaker has been kept
in open condition. Mode of excitation system has been
selected (auto/man)
-
7/31/2019 Commissioning Generators and Its Auxiliary System
85/90
24 May 2012 PMI Revision 00 85
When generator reaches rated speed check
the followinga) bearing and seal temperatures
b) performance of brush gear
c) vibrations
d) any gas, oil or water leakages
e) any abnormalities in generator
performance
-
7/31/2019 Commissioning Generators and Its Auxiliary System
86/90
24 May 2012 PMI Revision 00 86
Switch on excitation system and check forvarious parameters and functioning of excitation
system After ensuring all parameters are all right and
machine behavior is normal match thegenerators electrical parameters with the gridand synchronise the machine when permissivefor the same is available. The generator shall beswitched into the power system at precisesynchronizing.
Load the machine gradually. During loading alsomonitor all parameters.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
87/90
24 May 2012 PMI Revision 00 87
Inspection after Initial Operation Under
Load
The initial operation under load is considered tohave been accomplished if the generator hasshown normal performance during continuousoperation for 72 hours of switching thegenerator into the power system.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
88/90
24 May 2012 PMI Revision 00 88
After the 72-h operation, make inspection ofthe generator. During the inspection,disassemble the bearing and shaftirrespective whether any abnormalities have
been noted or in their performance duringadjustment and testing. The inspectioninvolves the visual examination of the shaft
journals, babbit-lined faces of the bearingliner an shaft-seal bushes.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
89/90
24 May 2012 PMI Revision 00 89
Clean the filters of the oil system and statorwinding cooling system. Remove scratches,marks, etc. on the shaft journals and babbit-lined faces by polishing or scraping. Stop theleaks detected in valves, flange joints, etc.
The generator is to be placed in commercialoperation after completion of the adjustmentand testing, and upon elimination of defectsand workmanship faults revealed during the
inspection.
-
7/31/2019 Commissioning Generators and Its Auxiliary System
90/90