commissioning issues and solutions - fieldbus · commissioning issues and solutions arasu thanigai...

53
1 1 Successful Implementation & Improved Operation Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung 10th April 2013

Upload: others

Post on 23-Mar-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

1 1 Successful Implementation & Improved Operation

Commissioning issues and

solutions

Arasu Thanigai

Pepperl+Fuchs Pte Ltd

Singapore

Fieldbus Foundation Seminar Kaohsiung – 10th April 2013

Page 2: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

2 2 Successful Implementation & Improved Operation

Install the Cables

Check out the cable installation

Install the Devices

Check the device installation

Install the DCS

Assigning the I/O

Calibration the Sensor

Ranging

Calibration the 4~20mA

System Ranging

System Calibration 4~20mA

Commissioning Process

Page 3: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

3 3 Successful Implementation & Improved Operation

4~20mA Install the Cables

Check out the cable installation

Install the Devices

Check the device installation

Install the DCS

Assigning the I/O

Calibration the Sensor

Ranging

Calibration the 4~20mA

System Ranging

System Calibration 4~20mA

Foundation Fieldbus • Install the Cables

• Check out the cable installation

• Install the Devices

• Check the device installation

• Install the DCS

• Assigning the I/O

• Calibration the Sensor

• Ranging

• Calibration the 4~20mA

• System Ranging

• System Calibration 4~20mA

Commissioning Process Comparison.

Page 4: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

4 4 Successful Implementation & Improved Operation

4~20mA

Foundation Fieldbus

4-20mA

P.S.

fieldbus

P.S.

Distance and relevant issue

Artificial hours and relevant cost

Cable connection Quantity

Hidden trouble points

Cable installation

Page 5: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

5 5 Successful Implementation & Improved Operation

4~20mA Install the Cables

Check out the cable installation

Install the Devices

Check the device installation

Install the DCS

Assigning the I/O

Calibration the Sensor

Ranging

Calibration the 4~20mA

System Ranging

System Calibration 4~20mA

Foundation Fieldbus • Install the Cables

• Check out the cable installation

• Install the Devices

• Check the device installation

• Install the DCS

• Assigning the I/O

• Calibration the Sensor

• Ranging

• Calibration the 4~20mA

• System Ranging

• System Calibration 4~20mA

Commissioning Process Comparison.

Page 6: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

6 6 Successful Implementation & Improved Operation

4~20mA

Foundation Fieldbus

4-20mA

P.S.

fieldbus

P.S.

Test

Report

Distance and connection Quantity

Tools

Checking of cable installation.

Page 7: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

7 7 Successful Implementation & Improved Operation

4~20mA Install the Cables

Check out the cable installation

Install the Devices

Check the device installation

Install the DCS

Assigning the I/O

Calibration the Sensor

Ranging

Calibration the 4~20mA

System Ranging

System Calibration 4~20mA

Foundation Fieldbus • Install the Cables

• Check out the cable installation

• Install the Devices

• Check the device installation

• Install the DCS

• Assigning the I/O

• Calibration the Sensor

• Ranging

• Calibration the 4~20mA

• System Ranging

• System Calibration 4~20mA

Commissioning Process Comparison.

Page 8: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

8 8 Successful Implementation & Improved Operation

Install the Device

Distribution

Block

Cable

Power supply

/ Conditioner

Foundation Fieldbus

Host

FF field

devices

Page 9: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

9 9 Successful Implementation & Improved Operation

4~20mA Install the Cables

Check out the cable installation

Install the Devices

Check the device installation

Install the DCS

Assigning the I/O

Calibration the Sensor

Ranging

Calibration the 4~20mA

System Ranging

System Calibration 4~20mA

Foundation Fieldbus • Install the Cables

• Check out the cable installation

• Install the Devices

• Check the device installation

• Install the DCS

• Assigning the I/O

• Calibration the Sensor

• Ranging

• Calibration the 4~20mA

• System Ranging

• System Calibration 4~20mA

Commissioning Process Comparison.

Page 10: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

10 10 Successful Implementation & Improved Operation

Assigning the I/O

Foundation fieldbus devices are recognized by three

mechanisms: a traditional node address for communication, a

human readable device tag corresponding to the project P&I

diagram, and a unique identifier allowing the system to

automatically resolve any tag or address conflicts.

The system automatically assigns the address to all devices,

avoiding human errors such as address duplication associated

with manually managed protocols, and saving time.

Therefore technicians work based on tag and need not be

concerned with address.

Thanks to the unique identifier, multiple devices can be

connected and commissioned at the same time.

It is plug-'n'-play.

Page 11: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

11 11 Successful Implementation & Improved Operation

4~20mA Install the Cables

Check out the cable installation

Install the Devices

Check the device installation

Install the DCS

Assigning the I/O

Calibration the Sensor

Ranging

Calibration the 4~20mA

System Ranging

System Calibration 4~20mA

Foundation Fieldbus • Install the Cables

• Check out the cable installation

• Install the Devices

• Check the device installation

• Install the DCS

• Assigning the I/O

• Calibration the Sensor

• N/A

• N/A

• N/A

• N/A

Commissioning Process Comparison.

Page 12: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

12 12 Successful Implementation & Improved Operation

No range mismatch

Unit downloaded when device is replaced

Transmitter Positioner

FF FF

BUS

FF

CTRL

CPU

CPU

CPU

Digital Digital Digital

Transmitter

Range

0-800 kPa

System

Range

0-400 kPa

8 mA Process

200 kPa

Reading

100 kPa

...alarms and trips

not working

AI

Unit

Unit

AO

Unit

Unit

Commissioning Process Comparison.

4~20mA

Foundation Fieldbus

Page 13: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

13 13 Successful Implementation & Improved Operation

Why Foundation Fieldbus

The global process industry loses $20

billion, or five percent of annual production,

due to unscheduled downtime and poor

quality.

ARC estimates that almost 80 percent of

these losses are preventable, with 40 percent

largely due to operator error.

Source ARC Insight June 10 2010

Page 14: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

14 14 Successful Implementation & Improved Operation

Common issues

Check DD file

Check ITK version

Check if HIST done

Check if the device listed at www.fieldbus.org

Page 15: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

15 15 Successful Implementation & Improved Operation

How to Check

Page 16: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

16 16 Successful Implementation & Improved Operation

Collaboration with NAMUR

Using the power of FOUNDATION Fieldbus, and considering NAMUR requirements, the new standard diagnostic profile aim to: – Standardize the integration of diagnostic information – Guarantee valuable information to the user

Page 17: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

17 17 Successful Implementation & Improved Operation

Diagnosis results must be reliable

Diagnosis results must always be viewed in the context of the application.

Internal diagnosis must be categorized into 4 standard “status signals”

Configuration must be free, as reactions will depend on the user's requirements

Detailed information can be read out by the device specialist

NAMUR NE107: Self-Monitoring and Diagnosis

of Field Devices

Page 18: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

18 18 Successful Implementation & Improved Operation

Namur - Diagnostic categories

Maintenance Required The output from the device is

valid but the wear reserve is nearly exhausted or function

will be restricted due to operational conditions

Out of Specification Measurement uncertainty, or

output position deviation, is greater than expected due to

deviations in ambient or process conditions.

Function Check Output invalid due to ongoing work on the device

Failure Output is invalid due to a malfunction in the field device

Page 19: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

19 19 Successful Implementation & Improved Operation

Distribution of information

Maintenance

Required

Out of

Specification

Function

Check

Failure

Output is valid

Measurement is

uncertain

Ongoing work on the

device, output invalid

Wear reserve is

exhausted

due to deviations in

ambient conditions.

Output is invalid malfunction in the field

device

OPERATOR

INSTRUMENT

TECH

Page 20: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

20 20 Successful Implementation & Improved Operation

Mapping to FF Quality Status & Block Error bits

Maintenance

Required

Out of

Specification

Function

Check

Failure

Output is valid

Measurement is

uncertain

Ongoing work on the

device, output invalid

Wear reserve is

exhausted

due to deviations in

ambient conditions.

Output is invalid

malfunction in the field

device

INSTRUMENT TECH

GOOD

UNCERTAIN

OUT OF SERVICE

BAD

NEEDS MAINT SOON

NEEDS MAINT SOON

NEEDS MAINT NOW

QUALITY STATUS BLOCK ERROR

OPERATOR

Page 21: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

21 21 Successful Implementation & Improved Operation

Commissioning Issues

Physical Layer commissioning.

Page 22: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

22 22 Successful Implementation & Improved Operation

AG 181

Page 23: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

23 23 Successful Implementation & Improved Operation

Typical problems

Improperly closed housing

Loose wire

Internally modified

Error log showing

intermittent faults

Interoperability testing

by end user

Electro-magnetic interference

Faulty field device Cable degradation Wrong termination

Page 24: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

24 24 Successful Implementation & Improved Operation

Need for diagnostics

• Field study by installation and commissioning

Engineers around the world shows that more

than 80% of the plant disturbances come from

the physical layer level be it conventional

4-20mA applications or Fieldbus applications.

• Unless the engineers sufficiently trained for

Fieldbus applications the most common

mistakes are made at the physical layer level

such as wiring faults, wrong termination etc.

Page 25: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

25 25 Successful Implementation & Improved Operation

Asset/Resource System Influencers

• Maintenance Cost Reduction Drives End Users

• 40% of Mfg. Cost is Maintenance

• 50% of Maintenance Is Corrective

– 10 times More Costly Than Preventative Maintenance

• Preventative Maintenance is Done 25% of Time

– 5 Times More costly Than Predictive Maintenance

• 60% of Preventative Maintenance is Unnecessary

• What has been largely missing up to now is timely,

relevant, and accurate information

From ARC Independent Research

Page 26: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

26 26 Successful Implementation & Improved Operation

Segment

Protectors FieldBarrier

Fie

ld D

evic

es

Fie

ld D

evic

es

Fie

ld D

evic

es

Junction Boxes Terminator Surge

Protec.

Surge

Protect.

Fie

ld D

evic

es

Fieldbus

Process

Interfaces

Complete Interface

Power

Supplies

Surge

protection

Page 27: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

27 27 Successful Implementation & Improved Operation

Hazardous safety rules not followed

– Ground faults

– Fieldbus and power

cables tied together

Page 28: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

28 28 Successful Implementation & Improved Operation

Poor cable installation

Page 29: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

29 29 Successful Implementation & Improved Operation

ANSI recommendation

Communication

Cables

(Fieldbus)

Shielded/Unshielded

Cables Carrying

>60 VDC or

>25 VAC but

<= 400 V

Shielded/Unshielded

Cables Carrying

> 400 V

Any Cables at

risk of

Lighting

Communication

Cables

(Fieldbus)

10 cm

20 cm

50 cm

Shielded/Unshielded

Cables Carrying

>60 VDC or

>25 VAC but

<= 400 V

10 cm

10 cm

50 cm

Shielded/Unshielded

Cables Carrying

> 400 V

20 cm

10 cm

50 cm

Any Cables at

risk of Lighting

50 cm

50 cm

50 cm

Page 30: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

30 30 Successful Implementation & Improved Operation

Poor cable installations

– Cable gland not tight

– Seal missing

Page 31: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

31 31 Successful Implementation & Improved Operation

And corrosion as a consequence

– Water ingress or worse:

– Aggressive media

Page 32: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

32 32 Successful Implementation & Improved Operation

Poor Device Instalation

Page 33: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

33 33 Successful Implementation & Improved Operation

Poor maintenance

Page 34: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

34 34 Successful Implementation & Improved Operation

Typical locations and Fieldbus issues

Page 35: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

35 35 Successful Implementation & Improved Operation

– Always on the critical path

– Manual, step-by-step procedure

– Labor intensive

– Requires

• Screw driver

• Check sheet

• Pencil

• Multimeter

• Oscilloscope

– Connect one device at a time

– Disconnect after testing

Test Report

Commissioning in the Past.

Page 36: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

36 36 Successful Implementation & Improved Operation

A portable tool for commissioning, monitoring,

troubleshooting and printout.

Portable Commissioning Tool

Page 37: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

37 37 Successful Implementation & Improved Operation

Online Commissioning Tools

Page 38: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

38 38 Successful Implementation & Improved Operation

What parameters to look for

– External power

– Fieldbus Output Power

– Fieldbus Segmetn current

– Grounding and shielding

– Communicaiton quality ( jitter) of segment and

devices

– Signal amplitude

– Noise of segment and deivces

– Waveform of the semgent

– Terminators

Page 39: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

39 39 Successful Implementation & Improved Operation

Commissioning in the past

– Always on the critical path

– Manual, step-by-step procedure

– Labor intensive

– Requires

• Screw driver

• Check sheet

• Pencil

• Multimeter

• Oscilloscope

– Connect one device at a time

– Disconnect after testing

Test Report

Page 40: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

40 40 Successful Implementation & Improved Operation

Simple Commissioning Steps with ADM

– Verify address setting

– Wire up devices in the right location

– Check shielding

– Activate communication

– Use automated work procedures

• Testing

• Documentation

– All devices at once

– Wiring remains undisturbed! Commissioning Wizard

Test

Report

x

Page 41: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

41 41 Successful Implementation & Improved Operation

One Plant Asset Management – Includes fieldbus now as asset

– Customary look and feel

– Reduces required training

– Reduces potential for errors

Open Architecture Integration: – AMS Suite

– PRM

– FieldCare

– FieldMate

– PACTware

– OPC Interface

Commissioning now via DCS

Page 42: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

42 42 Successful Implementation & Improved Operation

Example - ADM and DCS integration

Diagnostics at

DCS Station

Rela

y c

on

tac

t

op

tio

na

l)

RS485

Industrial Switch

Ethernet

or

FF H1

Address switches

Page 43: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

43 43 Successful Implementation & Improved Operation

Example Commissioning via DCS Asset management

PRM Alarm window view

PRM Network view

Segment-specific status of the physical layer

ADM status view with PRM TAG

FF-Segment

FF-Host

Page 44: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

44 44 Successful Implementation & Improved Operation

Commissioning Wizard

With Expert System Support – Takes snapshot

– Identifies wiring erros

– Ensures compliance with

AG181 and IEC 61158-2

– Recommends limits for ADM

messages

– Stores limits in non-volatile memory

Automatic Tag Readout

Creates baseline report: – Snapshot of all measurements

– Complete documentation

Saves 80% of pre-commissioning

time

Page 45: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

45 45 Successful Implementation & Improved Operation

Online monitoring

Clean layout shows boundaries – Displays measurement values

– Highlights violations with color coding:

– Issues diagnostic messages

Good value

Maintenance required

Out of specification

Page 46: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

46 46 Successful Implementation & Improved Operation

Diagnostic Menu

Expert System delivers

clear text information for

fast fault finding 1 Active messages

2 Actionable information

with solution guideance

based on expert system

3 History with timestamps

When the failure… … occured

… disappeared

– Export function for

external analysis and

storage

1

2 2

3

Page 47: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

47 47 Successful Implementation & Improved Operation

Built-in fieldbus oscilloscope

ADM provides expert tools

for fast fault finding – For diagnosing complex scenarios

– For the fieldbus expert

– With fieldbus specific triggers

– Captures up to 10 shots in a row

Page 48: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

48 48 Successful Implementation & Improved Operation

Bad Wiring

Page 49: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

49 49 Successful Implementation & Improved Operation

49

Bad wiring technique

Welding, variable frequency drives (VFD),

Motors, machinery:

Increase of HF noise

Increasing number of retransmissions

Can be a combination of both

Page 50: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

50 50 Successful Implementation & Improved Operation

Practical Example

In this example the frequency of noise was

approx. 150Hz

7 ms

Page 51: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

51 51 Successful Implementation & Improved Operation

Practical Example

“Make” Disturbance

"Break" disturbance

Vibration

frequency

Trunk signal

Failed telegram

Telegram

Page 52: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

52 52 Successful Implementation & Improved Operation

Surge Protection

FIELDBUS

TERMINATOR

SEGMENT

PROTECTORS

HOST

FIELDBARRIERS

PROCESS

INTERFACE

POWER

SUPPLY

CONVENTIONAL

FIELD DEVICES

FIELDBUS

DEVICES

JUNCTION

BOX

But Practically this setup is not

possible due to cost reasons.

Protection at both trunk ends is

more feasible

Page 53: Commissioning issues and solutions - Fieldbus · Commissioning issues and solutions Arasu Thanigai Pepperl+Fuchs Pte Ltd Singapore Fieldbus Foundation Seminar Kaohsiung – 10th April

53 53 Successful Implementation & Improved Operation

Conclusion

– Advanced Diagnostics tools for for physical layer

reduced physical layer commissiong time and

provided online monitoring and reporting system that

saves CAPEX and OPEX – Most problems at early bus installations were due to poor installation.

However, simple, user-friendly, Fieldbus testers are now available,

allowing the installation crew to easily check the wiring, and the device

commissioning crew to check network operation, spotting any problems

early

– Many contractors and Technicians are trained and are skilled in Fieldbus

installation and commissioning, and have the test equipment and in-

house procedures to ensure reliable operation