Construction Update Meeting

February 15, 2017

Oakland Children’s Hospital

3

• Doug Nelson – Executive Director of Development & Construction, UCSF Benioff Children’s Hospital Oakland

• Nick Chiu and Tony Solano – JLL

• Darrel Graef, Adam Della Monica – Project Superintendents, Turner Construction Company

• Andrew Pitts, Sr. PM– Turner Construction Company

Welcome

4

UCSF Benioff Children’s Hospital / Turner – General Discussion

Project Communication

Upcoming Construction Activities

Where is Waldo/ Superman?

Agenda

5

• Project Communication

• Project Communication– Darrel Graef (Turner Supt) 510-764-3059– Flyers and Project Website

• notifications of change to site conditions as it pertains to the neighborhood

• http://chonext100.org

• Concerns/Issue Reporting—Contact information are posted on Site Signage and Project Website

Communication & Reporting

6

• Exterior Glass Continuing • Exterior Lath and Stucco• Roofing OPC-2 (Weather Permitting)• Interior Gyp Board

• Upcoming Weekend Work. (Saturday 8:00 am – 5:00pm) February 25 ---- Crane Mechanical Equipment to OPC-2 Roof March 4 ---- Exterior Lath and Stucco (Rain Delayed) March 11 ---- Exterior Lath and Stucco (Rain Delayed) March 18 ---- Remove Material Hoist

Upcoming Major Construction Activities

7

Progress Photos

8

Progress Photos

9

Progress Photos

Oakland Children’s Hospital

12

Questions/Discussion?

Oakland Children’s Hospital