Competence mapping and workforceplanning for decommissioning

Autor

Page 2: Competence mapping and workforce planning for decommissioning

Background

• Service provider

• Knowledge centred company

• SME

• Counterparts often large companies, utilities

• Services comprise– Radiation protection services

– Activation and shielding calculations

– Waste management, package optimization

– Project support and documentation

– KM tools and implementation

– R&D for decommissioning

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 142

Page 3: Competence mapping and workforce planning for decommissioning

Knowledge Mapping

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 143

Page 4: Competence mapping and workforce planning for decommissioning

Knowledge Mapping

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 144

Page 5: Competence mapping and workforce planning for decommissioning

Gap Analysis

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 145

Page 6: Competence mapping and workforce planning for decommissioning

Requirement drives process

defines

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 146

Page 7: Competence mapping and workforce planning for decommissioning

Process defines roles and duties

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 147

Page 8: Competence mapping and workforce planning for decommissioning

Role requires skills & competences

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 148

Page 9: Competence mapping and workforce planning for decommissioning

Personal knowledge model

Ability• Physical

possibility, fitness

Skill

• Mental possibility, after training

Competence• ability &

skill & experience

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 149

Page 10: Competence mapping and workforce planning for decommissioning

Certificates and Qualifications

• Certificates and Qualifications are important to showfitness for job

• Often, these expire after several years and need a re-training

• Management system can inform the user on expiring certificates and qualifications

• As all certificates are in the system, employees canshow their egligibility quickly

• Reverse determination of competences from rolespossible

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1410

Page 11: Competence mapping and workforce planning for decommissioning

Ability/Skill/Competence based search

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1411

Page 12: Competence mapping and workforce planning for decommissioning

Bring it to the attention of personnel

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1412

Page 13: Competence mapping and workforce planning for decommissioning

Decommissioning phase model

Planning&

Preparation

Transition from

Operations

Decontaminating& Dismantling

within the controlled area

Conventionaldemolition & site

release

Deferral PeriodNG-T-2.3 (REVISION)

Work in progress

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1413

Page 14: Competence mapping and workforce planning for decommissioning

Phase 1 - Planning

• Decommissioning planning; (including decommissioning scenarios)

• Facility initial characterization;

• Safety, security and environmental studies;

• Waste management planning (treatment, waste routes identification);

• Authorization from the regulator;

• Preparing management group and contracting strategies and preparation.

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1414

Page 15: Competence mapping and workforce planning for decommissioning

Phase 1 qualifications needed

• project managers

• project engineering staff,

• radiation and safety specialists,

• procurement personnel,

• licensing specialists,

• dismantling specialists,

• waste management specialists

• operational personnel

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1415

Page 16: Competence mapping and workforce planning for decommissioning

Phase 2 - Transition

• Drainage and drying of systems;

• Decontamination of closed systems if planned in the decommissioning scenario (for dose reduction, decommissioning optimization, waste management, etc.);

• Radiological inventory characterization to support detailed planning;

• Removal of system fluids, operational waste and redundant material;

• Reduction of all fire hazard materials;

• New construction (e.g. interim storage, waste treatment facilities, new ventilation etc.)

• Anticipated dismantling (if planned in the decommissioning scenario and authorized by the applicable license)

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1416

Page 17: Competence mapping and workforce planning for decommissioning

Phase 3a – Preparation for deferral

• Maintaining all plant systems required to support the stabilization configuration of the plant systems;

• Decontamination of external surfaces of system, structures and components (SSCs);

• Ensuring all radioactive materials that will remain on site are properly stored and removal of any materials that can be permanently disposed;

• Reconfiguration of the site security boundary, landscaping, to address the reduced plant configuration where possible;

• Any required modifications to establish the physical security of site structures.

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1417

Page 18: Competence mapping and workforce planning for decommissioning

Phase 3a – qualifications needed

• management and administrative support,

• engineering,

• maintenance and work control,

• operations,

• oversight and nuclear safety,

• radiation protection,

• chemistry,

• regulatory/licensing,

• health and safety,

• security,

• craft labour.

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1418

Page 19: Competence mapping and workforce planning for decommissioning

Phase 3b – Dismantling controlled area

• Completion of the defined end state, final planning for dismantling activities and procurement of any required specialized equipment;

• Modification of SSCs as dismantling progresses • Completion of contracting for specialty services• Removal of radiologically contaminated components and piping from the reactor

systems;• Removal of general commodities from site• Decontamination of site structures for final removal or redeployment;• Removal of hazardous materials from plant SSCs;• Remediation according to the agreed end state of any contaminated

environmental media• Characterization, packaging, conditioning and storage or disposal of all

radioactive and hazardous wastes;• Removal of conventional waste from site according to the agreed end state; • Declassification of materials/buildings from the “controlled area” to conventional

site;• Finalization of the approach to license termination with the regulator and

stakeholders and preparation of associated documentation.

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1419

Page 20: Competence mapping and workforce planning for decommissioning

Phase 4 – release of site & demolition

• Procurement of contracts for conventional dismantling and demolition;

• Conventional dismantling of systems and buildings outside the controlled area;

• Demolition of the buildings from the formerly controlled area;

• Final clean-up and landscaping of the site;

• Final survey of the site;

• Perpetuity funding/surveillance for limited or restricted release of property.

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1420

Page 21: Competence mapping and workforce planning for decommissioning

Phase 4 – qualifications needed

• radiation protection,

• engineering personnel,

• contractors,

• project management staff

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1421

Page 22: Competence mapping and workforce planning for decommissioning

Specialized workforce

• Decommissioning requires very specificknowledge

– Cutting

– Dismantling, demolition

– Measurement

– Waste management

• The workforce is rather limited

• Interdependencies on the market need to be takeninto account at early stage – example German phase out

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1422

Page 23: Competence mapping and workforce planning for decommissioning

Work safety vs radiation protection

risk level

Decommissioning progress

radiation risks

work safety risks

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1423

Page 24: Competence mapping and workforce planning for decommissioning

IT based technologies

• VR and AR can not only be helpful for engineers but also for blue-collar workers.

• Adequate trainings are praktically unavailable in themoment

• Training of engineers and workers needs alignment

Workshop on Optimization of Technology Selection for Decommissioning Miami, FIU Campus, 2019-09-09 - 1424