1.0 INTRODUCTION Setting out is the process of using the surveying inst described in preceding chapters to transfer information from a such it is the opposite of surveying and the task most com engineers supervising the construction of new works. There are three distinct elements to the task horizontal co new works are in the correct place, vertical control to ensure level and vertical alignment to ensure that multi-storey or und plumb. nformation on the drawing concerning the proposed works mu the ground in a format that can be understood by all levels of 2.0 OBJECTIVE - To make a laying out at the corners of a proposed building ac taken from building site plan. - To e!pose student to setting out works and prepare before bu 3.0 EQUIPMENT i"Total Station ii" #rism iii" #ole and mini prism iv" $ails and hammer v" Tape vi" %ooden pegs vii" Tripod

Upload: muhammad-riezhuan-rabani

Post on 04-Nov-2015

213 views

Category:

Documents


0 download

DESCRIPTION

setting out

TRANSCRIPT

1.0 INTRODUCTION

Setting out is the process of using the surveying instruments and techniques described in preceding chapters to transfer information from a plan to the ground. As such it is the opposite of surveying and the task most commonly performed by site engineers supervising the construction of new works.

There are three distinct elements to the task horizontal control to ensure that the new works are in the correct place, vertical control to ensure that they are at the correct level and vertical alignment to ensure that multi-storey or underground construction is plumb.

Information on the drawing concerning the proposed works must be transferred to the ground in a format that can be understood by all levels of the workforce on site.

2.0 OBJECTIVE

- To make a laying out at the corners of a proposed building according to the dimension taken from building site plan.

- To expose student to setting out works and prepare before build a building.

3.0 EQUIPMENT

i) Total Station

ii) Prism

iii) Pole and mini prism

iv) Nails and hammer

v) Tape

vi) Wooden pegs

vii) Tripod 4.0PROCEDURE1.The traverse and tachymetry plan were used which is from previous project.

2.A suitable area was selected for suggestion of a building construction in the traverse area.

3.A line of traverse and a station were taken as observation station.

4.Station 5 was chose as control point and line station 5 to 1 as a reference line.

5.Bearing and distance of every point of the building area were determined by using AutoCAD.

6.Setting up work was started.

7.The total station were set at station 5 and observed at station 1. Bearing 5 to 1 were set as reference bearing.

8.Observations were done at every point of the building area based on the bearing that obtained from the AutoCAD. The pole and mini prism were moved to get exact distance.

9.Observations were done on point A,B,C,D,E and F. Every point was marked with set out.

10.To checked, a method using theorem Pythagoras were used:

Total station was set at the other station from station 5.

The bearing was set which is from station 1 to station 5.

Distance and bearing were observed at every point of the building for.

11.The shape of the building was produced.

12.The plotting building points were done in Traverse plan by using AutoCAD and report was done.

5.0RESULT

6.0DATA ANALYSIS

To find the Latitude :

Distace x Cos (Bearing)

To find the Departure :

Distance x Sin (Bearing)

To find the coordinate :

(Coordinate from Station or Point) (each of latitude for N/S coordinate or departure for E/W coordinate)

For example :

To get the value of latitude and departure for point A from Point 1.Data :

Bearing : 319(1720

Distance : 29.112 m

Coordinate :

Point 1

N/S = -15237.945

E/W = -45361.800 Therefore ,

Latitude = 29.112 x cos 319(1720

= 22.067

Departure = 29.112 x sin 319(1720

= -18.988

Finally after got the latitude and departure, the coordinate should be defined.The coordinate :

For N/S,

-15237.945+22.067

= -15215.878

For E/W.

-45361.800+(-18.988)

= -45380.788

The calculation to get the different coordinate between point 5 and point 1 at every pointFor example :

Coordinate at point A for N/S = -15265.482 ( - 15215.878 ) = -49.604

Coordinate at point A for E/W= -45342.045 ( - 45380.788 ) = 38.743

The calculation to get the error of at every point

For example :

Data :

Different value at point A for N/S = -49.604

Different value at point A for E/W= 38.743

Therefore,

e

-49.604

38.743

So the error ,e = (38.743)+ (-49.604)

= 62.9417.0DISCUSSION

The calculation should be done to determine the bearing and the distance from the surveying software, for each point of the building that we want to build. The field work is just to mark the point which has been plot in the purpose building plan.

From our traverse area, we plan a building inside the boundary of the traverse. First each corner point of the building that we want to build is set out using pegs.

From what we have done, there are a few errors that occurred. The error that we can see is that our allowable error is bigger than it should be. Because of the error that is too big, the building will not be at the exact location as set up on our purpose building plan.

The factors that contribute to the errors are:

Human factor

-Communication between the observer and the pole holder wasnt good.

-Pole holder adjusted the pole before the point was marked, so, the point was not marked at an accurate point.

-While installing the pegs at the point, maybe it was moved a little bit off from its exact location.

Instrument factor

-The total station was set up at a location that was not levelled.

Ways to overcome the factors of errors:

-By providing walkie-talkie for observer and pole holder.

-The observer and pole holder should discuss by using hand signals before the work starts.

8.0CONCLUSION

For the conclusion, we found that the setting out surveying works was done to determine the point at the building that we want to build. From the purpose building plan, we designed the building location and transfer it to the ground surface. If the setting out was not accurate, the building that we want to build would not be at the correct location and size.

This will contribute a lot of problems while and after the construction work. Hence, the accuracy of the setting out is very important to guarantee the comfort and safety to the people.

This setting out was done, based on previous three surveying work, which is levelling, traverse, and tacheometry. The most important thing while doing this setting our work is that we should know how to efficiently conduct all these three surveying work because, from the levelling work, we can determine the reduce level at out point while from the traverse work, we can know the boundary and the coordinate for our point. Lastly, from tacheometry works, we can produce the topographic and detail plan to continue this setting out work.

From all these data that we have, we have set the exact location for the building by using pegs. Since, there are some errors in our setting out work; we cannot proceed for the continuous work. So, we need to overcome these errors first.