completed projects fy2009
DESCRIPTION
Permits/Fees: $92,843 DPWES Project Manager: Riat, Amarjit DPWES Construction Manager: Knizner, Anthony Designed By: Solid Waste Services, LLC (consultant) Fund #: 110 Fund Title: Refuse Disposal 174002Project#: Constructed By: Martin & Gass, Inc (contractor) Project Name: I-66 Citizens Disposal Facility Expansion Address: 4618 West Ox Rd Dollar Amount Tax Map #: 056-2 Construction Completion Date: 6/16/2009 Costs Magisterial District: Springfield Page 1TRANSCRIPT
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 110Fund Title: Refuse Disposal
DPWES Project Manager: Riat, AmarjitDPWES Construction Manager: Knizner, Anthony
Constructed By: Martin & Gass, Inc (contractor)Designed By: Solid Waste Services, LLC (consultant)
Construction Completion Date: 6/16/2009
Contract Number: CN07110001Task Order Number: N/A
Tax Map #: 056-2
Land: $0
Design: $1,555,685Permits/Fees: $92,843
Construction: $18,785,063Utilities: $191,412
Magisterial District: Springfield
Project Name: I-66 Citizens Disposal Facility Expansion
Address: 4618 West Ox Rd
Costs
Total: $20,625,003
Dollar Amount
SCOPEConstruction of elevated unloading bays, new recycling center, truck scales & scale house, booths, major storm drainage & site improvements. Also, included was a new metal goods drop-off structure & brush processing area.
174002Project #:
Page 1
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Buckley, Beth
Constructed By: Ashburn Contracting Corp (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 3/30/2009
Contract Number: CN09303357Task Order Number: 6
Tax Map #: 69-4
Land: $0
Design: $8,867Permits/Fees: $0
Construction: $22,567Utilities: $1,797
Magisterial District: Braddock
Project Name: Safety Improvements at Bus Shelters/Stops WB Braddock Rd and Red Fox Dr NB
Address: 9025 Orange Hunt Lane
Costs
Total: $33,231
Dollar Amount
SCOPEInstallation of a concrete pad, storm structures, and other related items.
Z00032 04024Project #:
Page 2
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 10/10/2008
Contract Number: CN09303345Task Order Number: 99
Tax Map #: 058-4
Land: $0
Design: $11,934Permits/Fees: $0
Construction: $14,767Utilities: $1,022
Magisterial District: Braddock
Project Name: Safety Improvements at Bus Shelters/Stops WB Little River Trnpk. & Elizabeth Dr.
Address: 9005 Little River Turnpike
Costs
Total: $27,723
Dollar Amount
SCOPEInstallation of a pad, concrete walkway, and storm drainage improvements.
Z00032 03673Project #:
Page 3
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Much, GaryDPWES Construction Manager: Glines, Dale
Constructed By: Finley Asphalt (contractor)Designed By: Much, Gary, Maintenance and Stormwater Management Div.
Construction Completion Date: 10/21/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #:
Land: $0
Design: $0Permits/Fees: $0
Construction: $150,299Utilities: $0
Magisterial District: Countywide
Project Name: Emergency Road Repairs/ Service Drive Paving
Address: Countywide
Costs
Total: $150,299
Dollar Amount
SCOPEApproximately 9,355 square feet of milling and paving were performed on service drives throughout the County.
V00002 9321Project #:
Page 4
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Felix M. BermejoDPWES Construction Manager: N/A
Constructed By: Dominion Virginia Power & NOVEC (contractor)Designed By: Streetlight Section, Planning & Design Division, DPWES
Construction Completion Date: 6/30/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #:
Land: $0
Design: $0Permits/Fees: $0
Construction: $283,465Utilities: $0
Magisterial District: Countywide
Project Name: Countywide Streetlight Projects
Address: Countywide
Costs
Total: $283,465
Dollar Amount
SCOPEIn FY 2009, 129 new streetlights were installed/upgraded throughout the County. This total includes 16 LED streetlights installed at the Burke Centre Virginia Railway Express station parking lot as part of a LED pilot project.
Z00001Project #:
Page 5
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES
Construction Completion Date: 11/13/2008
Contract Number: CN09303346Task Order Number: 100
Tax Map #: 19-4
Land: $0
Design: $2,468Permits/Fees: $0
Construction: $14,006Utilities: $0
Magisterial District: Dranesville
Project Name: Developer Default/ Kelly Estates
Address: 9038, 9040, 9042, & 9044 Leesburg Pike
Costs
Total: $16,474
Dollar Amount
SCOPECorrected developer default punch-list items. Relocated fire hydrant, installed water valves, corrected ponding water in pavement, and repaved work areas.
U00060 00812Project #:
Page 6
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES
Construction Completion Date: 3/11/2009
Contract Number: CN09303354Task Order Number: 121
Tax Map #: 37-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $13,310Utilities: $0
Magisterial District: Dranesville
Project Name: Developer Default/ Brown's Mill Forest
Address: 1400 Block of Wynhurst Lane
Costs
Total: $13,310
Dollar Amount
SCOPERepair of storm lines, video storm lines, and asphalt patch/paving, in preparation for VDOT inspection and acceptance.
U00060 00810Project #:
Page 7
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Huang, Ta-EnDPWES Construction Manager: Qureshi, Mannan
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker and Associates (consultant)
Construction Completion Date: 12/4/2008
Contract Number: N/ATask Order Number: 119
Tax Map #: 40-2, 40-4
Land: $0
Design: $27,000Permits/Fees: $0
Construction: $62,109Utilities: $0
Magisterial District: Dranesville
Project Name: Haycock Road Trail, Ph II
Address: 6904-6646 Haycock Road
Costs
Total: $89,109
Dollar Amount
SCOPEThe project included safety, accessibility, and rehabilitation of approximately 1,250 LF of asphalt trail along Haycock Road.
009406Project #:
Page 8
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Barzingy, HavalDPWES Construction Manager: Vinluan, Rufino
Constructed By: Eastern Waterproofing & Restoration Co., Inc. (contractor)Designed By: Walker Parking Consultants/Walker Restoration (consultant)
Construction Completion Date: 12/29/2008
Contract Number: CN08303312Task Order Number: N/A
Tax Map #: 16-4
Land: $0
Design: $529,967Permits/Fees: $48,536
Construction: $2,103,410Utilities: $0
Magisterial District: Hunter Mill
Project Name: Herndon Monroe Parking Garage Remedial Work
Address: 12530 Sunrise Valley Drive
Costs
Total: $2,681,913
Dollar Amount
SCOPERemedial repairs to concrete floors and columns on each level of parking structure, installation of a new waterproofing membrane and new expansion joints on the top 3 levels, installation of new drains to improve surface drainage & other related items.
009527Project #:
Page 9
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 6/15/2009
Contract Number: CN09303363Task Order Number: 18
Tax Map #: 17-3
Land: $0
Design: $5,351Permits/Fees: $0
Construction: $3,313Utilities: $2,229
Magisterial District: Hunter Mill
Project Name: Safety Improvements at Bus Shelters/Stops EB Sunrise Valley Dr and Glade Dr SB
Address: 2100 Westglade Court
Costs
Total: $10,893
Dollar Amount
SCOPEInstallation of a concrete pad, walkway, and other related items.
Z00032 05216Project #:
Page 10
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 6/15/2009
Contract Number: CN09303364Task Order Number: 19
Tax Map #: 17-3
Land: $0
Design: $6,033Permits/Fees: $0
Construction: $3,466Utilities: $4,873
Magisterial District: Hunter Mill
Project Name: Safety Improvements at Bus Shelters/Stops NB Glade Dr & Cocquina Dr WB
Address: 2290 Cocquina Drive
Costs
Total: $14,372
Dollar Amount
SCOPEInstallation of a concrete pad, walkway curb ramp, and other related items.
Z00032 05072Project #:
Page 11
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid
DPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 10/10/2008
Contract Number: CN09303342Task Order Number: 96
Tax Map #: 26-1
Land: $0
Design: $6,640Permits/Fees: $0
Construction: $8,726Utilities: $824
Magisterial District: Hunter Mill
Project Name: Safety Improvements at Bus Shelters/Stops EB Glade Dr near Breton Ct
Address: 11827 Breton Court
Costs
Total: $16,190
Dollar Amount
SCOPEConstruction of a concrete pad, sidewalk, curb ramp, and other related items.
Z00032 05082Project #:
Page 12
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 6/15/2009
Contract Number: CN09303368Task Order Number: 23
Tax Map #: 26-1
Land: $1,269
Design: $6,286Permits/Fees: $0
Construction: $7,014Utilities: $551
Magisterial District: Hunter Mill
Project Name: Safety Improvements at Bus Shelters/Stops NB Colts Neck Rd & Steeplechase Dr
Address: 2401 Colts Neck Road
Costs
Total: $15,120
Dollar Amount
SCOPEInstallation of a concrete pad, walkway, and other related items.
Z00032 05148Project #:
Page 13
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid
DPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 10/10/2008
Contract Number: CN09303341Task Order Number: 95
Tax Map #: 026-1
Land: $0
Design: $5,798Permits/Fees: $0
Construction: $7,334Utilities: $839
Magisterial District: Hunter Mill
Project Name: Safety Improvements at Bus Shelters/Stops NB Colts Neck Rd near Insha Ct EB
Address: 12001 Insha Court
Costs
Total: $13,971
Dollar Amount
SCOPEConstruction of a concrete pad, walkway, and other related items.
Z00032 05149Project #:
Page 14
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Dewberry & Davis (consultant)
Construction Completion Date: 12/18/2008
Contract Number: CN09303348Task Order Number: 107
Tax Map #: 91-1
Land: $0
Design: $7,999Permits/Fees: $32
Construction: $8,301Utilities: $0
Magisterial District: Lee
Project Name: Developer Default/ Rite Aid Pharmacy at Silver Lake
Address: 7100 Silver Lake Blvd.
Costs
Total: $16,332
Dollar Amount
SCOPEInstalled a new fire lane, signage, repainting fire lane curbs, and related items.
U00060 00834Project #:
Page 15
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Schmidt, NatashaDPWES Construction Manager: Pope, BillyDPWES Right-of-Way Agent: Zore, TasneemDPWES Surveyor: Strecker, Mathias
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Planning and Design Division, DPWES
Construction Completion Date: 9/20/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 081-3
Land: $36,494
Design: $6,687Permits/Fees: $0
Construction: $26,543Utilities: $0
Magisterial District: Lee
Project Name: Road Maintenance Program/ Tilbury Road
Address: 5942 Tilbury Road
Costs
Total: $69,724
Dollar Amount
SCOPEUpgraded approximately 1000 LF of existing alley to provide emergency access and installed two gates and associated signage.
V00004 RM101Project #:
Page 16
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES
Construction Completion Date: 4/1/2009
Contract Number: CN09303355Task Order Number: 3
Tax Map #: 81-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $45,567Utilities: $0
Magisterial District: Lee
Project Name: Developer Default/ Skyline Homes
Address: Franconia Commons Dr. & Franconia Commons Ct.
Costs
Total: $45,567
Dollar Amount
SCOPEInstallation of new fire lane signage, replacing curb ramps, curb & gutter, sidewalks, asphalt patch work. Paving/overlaying intersection at entrance to neighborhood.
U00060 00802Project #:
Page 17
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Huntley, Nyce & Associates (consultant)
Construction Completion Date: 8/22/2008
Contract Number: CN0830330Task Order Number: 76
Tax Map #: 81-3
Land: $0
Design: $3,105Permits/Fees: $0
Construction: $9,885Utilities: $0
Magisterial District: Lee
Project Name: Developer Default/ Meriwether Estates
Address: 6300 Block of Zekan Lane
Costs
Total: $12,990
Dollar Amount
SCOPERegrade stormwater pond to planned capacity and related restoration items.
U00060 00853Project #:
Page 18
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 10/10/2008
Contract Number: CN09303344Task Order Number: 98
Tax Map #: 071-2
Land: $0
Design: $10,232Permits/Fees: $0
Construction: $15,047Utilities: $1,393
Magisterial District: Mason
Project Name: Safety Improvements at Bus Shelters/Stops WB Little River Tnpk & Roberts Ave
Address: 6800 Little River Turnpike
Costs
Total: $26,672
Dollar Amount
SCOPEConstruction of an asphalt pad, storm drainage improvements, and other related items.
Z00032 04080Project #:
Page 19
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 6/19/2009
Contract Number: CN09303365Task Order Number: 20
Tax Map #: 071-2
Land: $0
Design: $7,131Permits/Fees: $0
Construction: $5,200Utilities: $2,378
Magisterial District: Mason
Project Name: Safety Improvements at Bus Shelters/Stops WB Little River Tnpk & Pinecrest Pwy
Address: 4548 Airlie Way
Costs
Total: $14,709
Dollar Amount
SCOPEInstallation of a concrete pad, curb ramp, walkway, and other related items.
Z00032 04079Project #:
Page 20
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid
DPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 10/10/2008
Contract Number: CN09303343Task Order Number: 97
Tax Map #: 080-2
Land: $0
Design: $5,716Permits/Fees: $0
Construction: $10,076Utilities: $1,149
Magisterial District: Mason
Project Name: Safety Improvements at Bus Shelters/Stops WB Edsall Rd & Cherokee Ave
Address: 6540 Edsall Road
Costs
Total: $16,941
Dollar Amount
SCOPEConstruction of a concrete pad, sidewalk, and other related items.
Z00032 03266Project #:
Page 21
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 6/19/2009
Contract Number: CN09303367Task Order Number: 22
Tax Map #: 71-2
Land: $0
Design: $6,734Permits/Fees: $0
Construction: $7,198Utilities: $870
Magisterial District: Mason
Project Name: Safety Improvements at Bus Shelters/Stops EB Little River Tnpk & Conwell Dr SB
Address: 6761 Little River Tpk.
Costs
Total: $14,802
Dollar Amount
SCOPEInstallation of a concrete pad, curb ramp, walkway, and other related items.
Z00032 03692Project #:
Page 22
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 6/19/2009
Contract Number: CN09303366Task Order Number: 21
Tax Map #: 071-2
Land: $0
Design: $7,022Permits/Fees: $0
Construction: $7,045Utilities: $2,801
Magisterial District: Mason
Project Name: Safety Improvements @ Bus Shelters/Stops EB Little River Tnpk & Willow Run Dr
Address: 4600 Willow Run Drive
Costs
Total: $16,868
Dollar Amount
SCOPEInstallation of a concrete pad, curb ramp, walkway, and other related items.
Z00032 03694Project #:
Page 23
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Dewberry & Davis, LLC (consultant)
Construction Completion Date: 4/1/2009
Contract Number: CN09303351Task Order Number: 109
Tax Map #: 71-2
Land: $0
Design: $6,800Permits/Fees: $0
Construction: $20,712Utilities: $0
Magisterial District: Mason
Project Name: Developer Default/ Hillbrook Springs
Address: 6900 Block of Winter Lane
Costs
Total: $27,512
Dollar Amount
SCOPERegrade stormwater pond to planned capacity and related restoration items.
U00060 00774Project #:
Page 24
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Much, GaryDPWES Construction Manager: Glines, Dale
Constructed By: Finley Asphalt (contractor)Designed By: Much, Gary, Maintenance and Stormwater Management Div.
Construction Completion Date: 11/10/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 71-1-01
Land: $0
Design: $0Permits/Fees: $0
Construction: $10,035Utilities: $0
Magisterial District: Mason
Project Name: Road Maintenance Projects/ Tom Davis Drive
Address: Tom Davis Drive
Costs
Total: $10,035
Dollar Amount
SCOPEMilling and paving approximately 3,150 square feet of asphalt.
V00004 RM104Project #:
Page 25
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 11/26/2008
Contract Number: CN09303350Task Order Number: 111
Tax Map #: 102-2
Land: $0
Design: $9,401Permits/Fees: $0
Construction: $9,856Utilities: $1,788
Magisterial District: Mount Vernon
Project Name: Safety Improvements at Bus Shelters/Stops NB Fort Hunt Rd & Gahant Rd WB
Address: 1305 Gahant Road
Costs
Total: $21,045
Dollar Amount
SCOPEConstruction of a bus pad, concrete sidewalk, storm drainage improvements, and other related items.
Z00032 01185Project #:
Page 26
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Land Design Consultants, Inc. (consultant)
Construction Completion Date: 9/1/2008
Contract Number: CN09303337Task Order Number: 85
Tax Map #: 110-2
Land: $0
Design: $1,235Permits/Fees: $0
Construction: $9,135Utilities: $0
Magisterial District: Mount Vernon
Project Name: DeveloperDefault/ Mount Vernon Walk Pond
Address: 3700, 3800, & 3900 Block of Colonial Ave.
Costs
Total: $10,370
Dollar Amount
SCOPERegrade stormwater pond to planned capacity and related restoration items.
U00060 00823Project #:
Page 27
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: William H. Gordon Assoc., Inc. (consultant)
Construction Completion Date: 3/1/2009
Contract Number: CN09303353Task Order Number: 115
Tax Map #: 48-2
Land: $0
Design: $27,393Permits/Fees: $490
Construction: $95,083Utilities: $0
Magisterial District: Providence
Project Name: Developer Default/ Oakton Retreat
Address: 2600 Block of Sledding Hill Road
Costs
Total: $122,966
Dollar Amount
SCOPERegrading stormwater pond to planned capacity, clearing & grubbing, and related restoration items.
U00060 00770Project #:
Page 28
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Patton, Harris, Rust & Assoc. (consultant)
Construction Completion Date: 3/24/2009
Contract Number: CN09303352Task Order Number: 113
Tax Map #: 56-2
Land: $0
Design: $0Permits/Fees: $128
Construction: $31,343Utilities: $0
Magisterial District: Springfield
Project Name: Developer Default/ Crown Ridge
Address: 4035 Ridge Top Road
Costs
Total: $31,471
Dollar Amount
SCOPERepair/replace portions of sidewalk, curb & gutter, asphalt patches, cleaning storm structures & piping, water line valve repairs/replacement, fire lane painting, and sign replacement.
U00060 00866Project #:
Page 29
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Malayeri, HosseinDPWES Construction Manager: Reed, BobDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Harper, Greg
Constructed By: Manhattan Construction (contractor)Designed By: HOK (consultant)
Construction Completion Date: 7/30/2008
Contract Number: CN06312187Task Order Number: N/A
Tax Map #: 55-2
Land: $0
Design: $207,881Permits/Fees: $350
Construction: $11,290,326Utilities: $1,443
Magisterial District: Springfield
Project Name: Forensics Facility
Address: 4890 Alliance Drive
Costs
Total: $11,500,000
Dollar Amount
SCOPEState-of-the-art, 33,000 SF, facility to house FCPD Crime Scene Section, Electronic Surveillance, NOVARIS.
009438Project #:
Page 30
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES
Construction Completion Date: 12/22/2008
Contract Number: CN08303323Task Order Number: 66
Tax Map #: 36-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $93,168Utilities: $0
Magisterial District: Sully
Project Name: Developer Default/ Shade Tree Estates, Section 2
Address: 12100 & 12101 Old Pine Way
Costs
Total: $93,168
Dollar Amount
SCOPERepair/replacement of driveways & curb ramps, drainage improvements, asphalt paving, and related items.
U00060 00764Project #:
Page 31
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 303Fund Title: County Construction
DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES
Construction Completion Date: 12/22/2008
Contract Number: CN08303322Task Order Number: 67
Tax Map #: 36-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $8,085Utilities: $0
Magisterial District: Sully
Project Name: Developer Default/ Shade Tree Estates, Section 3
Address: 12191, 12195, 12196, & 12198 Goldenchain Ct.
Costs
Total: $8,085
Dollar Amount
SCOPERepair/replacement of driveways & curb ramps, drainage improvements, asphalt paving, and related items.
U00060 00775Project #:
Page 32
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: El Kaissi, MohamadDPWES Construction Manager: Minnix, W. Todd
DPWES Surveyor: Housley, Gregg
Constructed By: Arthur Construction Company, Inc. (contractor)Designed By: Volkert & Associates, Inc. (consultant)
Construction Completion Date: 4/8/2009
Contract Number: CN09304371Task Order Number: N/A
Tax Map #: 091-2
Land: $1,524
Design: $121,976Permits/Fees: $0
Construction: $186,566Utilities: $2,372
Magisterial District: Lee
Project Name: South Van Dorn Street Walkway
Address: 6984 S. Van Dorn Street
Costs
Total: $312,438
Dollar Amount
SCOPEConstruction of 2,800 LF of concrete sidewalk, handrails and related items along southbound South Van Dorn Street from Kings Centre Drive to Telegraph Road.
064272Project #:
Page 33
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: County Construction
DPWES Project Manager: Schmidt, NatashaDPWES Construction Manager: Minnix, W. ToddDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker Design Associates (consultant)
Construction Completion Date: 5/18/2009
Contract Number: CN07303289Task Order Number: N/A
Tax Map #: 061-3
Land: $5,657
Design: $58,772Permits/Fees: $125
Construction: $387,904Utilities: $6,810
Magisterial District: Mason
Project Name: Mason District Capital Projects Columbia Pike: Govnmnt Ctr to Downing St
Address: 6507 to 4000 Columbia Pike
Costs
Total: $459,268
Dollar Amount
SCOPEConstruction of approximately 480 feet of 5' concrete sidewalk along the south side of Columbia Pike from the Mason District Government Center to Downing Street, retaining wall, handrails, and other related items.
4YP201 PB026Project #:
Page 34
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Ayers, RobertDPWES Construction Manager: Gharavi, MoDPWES Right-of-Way Agent: Zore, TasneemDPWES Surveyor: Harper, Greg
Constructed By: A&M Concrete Corp. (contractor)Designed By: Rinker Design Associates
Construction Completion Date: 1/25/2009
Contract Number: CN08304367Task Order Number: N/A
Tax Map #: 72-4
Land: $464,394
Design: $252,489Permits/Fees: $0
Construction: $831,859Utilities: $313,251
Magisterial District: Mason
Project Name: Route 236/Beauregard Street
Address: 6200 Little River Turnpike
Costs
Total: $1,861,993
Dollar Amount
SCOPEConstruction of an additional left-turn lane from eastbound Little River Turnpike to northbound Beauregard St., replacement of the existing traffic signal, new pedestrian crossings, drainage improvements, sidewalk, & other related items.
4YP013Project #:
Page 35
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Roberson, JeanmarieDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Preston, ClintonDPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker Design Associates
Construction Completion Date: 9/30/2008
Contract Number: CN07304354Task Order Number: N/A
Tax Map #: 072-1
Land: $228,154
Design: $209,650Permits/Fees: $0
Construction: $709,990Utilities: $207,926
Magisterial District: Mason
Project Name: Braddock Road/Route 236
Address: Intersection of Braddock Road/Route 236
Costs
Total: $1,355,720
Dollar Amount
SCOPEThis project is part of the Four-Year Transportation Program and included the realignment of eastbound lanes through the intersection. The work included installation of traffic signals, sidewalks, concrete median, pavement marking, & storm structures.
4YP014Project #:
Page 36
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, SamDPWES Right-of-Way Agent: Zore, TasneemDPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES
Construction Completion Date: 12/19/2008
Contract Number: CN09304372Task Order Number: 102
Tax Map #: 51-3
Land: $0
Design: $36,769Permits/Fees: $0
Construction: $125,372Utilities: $0
Magisterial District: Mason
Project Name: Pedestrian Improvements - VDOT Funded Arlington Blvd/Patrick Henry Dr
Address: Arlington Blvd. and Patrick Henry Dr.
Costs
Total: $162,141
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.
064267 PI001Project #:
Page 37
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: El Kaissi, MohamadDPWES Construction Manager: Farsad, Nahid
DPWES Surveyor: Housley, Gregg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: El Kaissi, Mohamad, Planning & Design Div., DPWES
Construction Completion Date: 6/30/2009
Contract Number: CN09304377Task Order Number: 13
Tax Map #: 71-4
Land: $0
Design: $70,276Permits/Fees: $0
Construction: $101,848Utilities: $0
Magisterial District: Mason
Project Name: Spot Improvements - Braddock Rd/Randolph Dr
Address: Intersection of Braddock Rd at Randolph Dr
Costs
Total: $172,124
Dollar Amount
SCOPEThis project is part of the Four-Year Transportation Program and included the extension of the existing left turn lane on eastbound Braddock Road to the entrance of Thomas Jefferson High School and related items.
4YP207Project #:
Page 38
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Division, DPWES
Construction Completion Date: 8/4/2008
Contract Number: CN08304360Task Order Number: 52
Tax Map #: 045-1
Land: $0
Design: $36,805Permits/Fees: $0
Construction: $113,459Utilities: $0
Magisterial District: Springfield
Project Name: Pedestrian Improvements - VDOT Funded Lee-Jackson Highway/Stringfellow Rd
Address: 4000 Stringfellow Road
Costs
Total: $150,264
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.
064267 PI006Project #:
Page 39
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Roberson , JeanmarieDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Preston, ClintonDPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker Design Associates (consultant)
Construction Completion Date: 6/8/2009
Contract Number: CN09304376Task Order Number: 120
Tax Map #: 068-1
Land: $0
Design: $76,547Permits/Fees: $0
Construction: $209,651Utilities: $5,910
Magisterial District: Springfield
Project Name: Braddock Rd/Rte 123 EB RTL
Address: Braddock Rd at Rt. 123 EB
Costs
Total: $292,108
Dollar Amount
SCOPEThis project provided a 450 LF extension of the existing right-turn lane from eastbound Braddock Road to Route 123.
064275Project #:
Page 40
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Division, DPWES
Construction Completion Date: 8/4/2008
Contract Number: CN08304361Task Order Number: 53
Tax Map #: 045-2
Land: $0
Design: $37,477Permits/Fees: $0
Construction: $91,991Utilities: $0
Magisterial District: Springfield
Project Name: Pedestrian Improvements - VDOT Funded Lee-Jackson Highway/Majestic Lane
Address: Intersection of Lee-Jackson Hwy and Majestic Ln
Costs
Total: $129,468
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.
064267 PI008Project #:
Page 41
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES
Construction Completion Date: 2/23/2009
Contract Number: CN09304373Task Order Number: 104
Tax Map #: 56-2
Land: $0
Design: $33,642Permits/Fees: $0
Construction: $74,824Utilities: $0
Magisterial District: Springfield
Project Name: Pedestrian Improvements - VDOT Funded Lee Highway/Monument Drive
Address: Monument Dr. and Lee Highway
Costs
Total: $108,466
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.
064267 PI012Project #:
Page 42
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES
Construction Completion Date: 2/20/2009
Contract Number: CN09304375Task Order Number: 105
Tax Map #: 088-1
Land: $0
Design: $43,944Permits/Fees: $0
Construction: $67,788Utilities: $3,684
Magisterial District: Springfield
Project Name: Pedestrian Improvements - VDOT Funded Fairfax County Parkway/Old Keene Mill
Address: Fairfax Co. Pkwy at Old Keene Mill Road
Costs
Total: $115,416
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, asphalt walkway, pavement marking, and pedestrian signalization.
064267 PI023Project #:
Page 43
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES
Construction Completion Date: 1/12/2009
Contract Number: CN09304374Task Order Number: 103
Tax Map #: 65-3
Land: $0
Design: $47,211Permits/Fees: $0
Construction: $125,738Utilities: $0
Magisterial District: Sully
Project Name: Pedestrian Improvements - VDOT Funded Centreville Road/Compton Road
Address: Centreville Road and Compton Road
Costs
Total: $172,949
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.
064267 PI015Project #:
Page 44
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 304Fund Title: Transportation Improvements
DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam
Constructed By: Asburn Contracting Corporation (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES
Construction Completion Date: 8/4/2008
Contract Number: CN08304363Task Order Number: 55
Tax Map #: 065-3
Land: $0
Design: $47,368Permits/Fees: $0
Construction: $97,750Utilities: $0
Magisterial District: Sully
Project Name: Pedestrian Improvements - VDOT Funded Centreville Road/Green Trails Blvd.
Address: Centreville Rd and Green Trails Blvd
Costs
Total: $145,118
Dollar Amount
SCOPEPedestrian safety improvements including curb ramps, sidewalk, pavement marking, and pedestrian signalization.
064267 PI016Project #:
Page 45
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 307Fund Title: Sidewalk Construction
DPWES Project Manager: Huang, Ta-EnDPWES Construction Manager: Rayyan, Yousef
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Huang, Ta-En, Maintenance and Stormwater Management Div.
Construction Completion Date: 7/30/2008
Contract Number: CN08004307Task Order Number: 78
Tax Map #: 082-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $44,950Utilities: $0
Magisterial District: Lee
Project Name: Clermont Subdivision Trail Project, Phase I
Address: 5623 Clermont Drive
Costs
Total: $44,950
Dollar Amount
SCOPEConstruction of approximately 1,700 LF of asphalt trail and 4 curb ramps.
X00407Project #:
Page 46
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 311Fund Title: County Bond Construction
DPWES Project Manager: Ogurcak, ToniDPWES Construction Manager: Foelsch, RickDPWES Right-of-Way Agent: Buckley, Beth
Constructed By: Falls Church Construction Corp. (contractor)Designed By: Cole & Denny, Inc. (consultant)
Construction Completion Date: 10/23/2008
Contract Number: CN06311001Task Order Number: N/A
Tax Map #: 055-4
Land: $14,570
Design: $1,077,922Permits/Fees: $61,259
Construction: $3,519,832Utilities: $54,513
Magisterial District: Springfield
Project Name: Girls Probation House
Address: 12720 Lee Highway
Costs
Total: $4,728,096
Dollar Amount
SCOPEThis building is approximately 11,500 SF and includes offices, classrooms, meeting/multipurpose rooms, & recreation and housing facilities for a maximum of 12 residents. The project included approximately 34 parking spaces & outdoor recreation.
04A001Project #:
Page 47
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 311Fund Title: County Bond Construction
DPWES Project Manager: Lepe, TeresaDPWES Construction Manager: Houde, HankDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Harper, Greg
Constructed By: Dustin Construction (contractor)Designed By: Baker and Associates (consultant)
Construction Completion Date: 10/15/2008
Contract Number: CN05311063Task Order Number: N/A
Tax Map #: 55-2
Land: $7,512,634
Design: $2,703,328Permits/Fees: $149,070
Construction: $37,447,284Utilities: $545,266
Magisterial District: Springfield
Project Name: West Ox Bus Operation Center
Address: 4950/4960 Alliance Drive
Costs
Total: $48,357,582
Dollar Amount
SCOPEThis facility is approximately 85,000 SF and consists of three major buildings: Admin/Operations, Maintenance Bldg. & Service/Fuel & Wash. The facility is shared by the Fairfax County Dept. of Transportation Connector and WMATA Metrobus operations.
88A002Project #:
Page 48
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 312Fund Title: Public Safety Construction
DPWES Project Manager: Reed, Bob/Roberts. FrankDPWES Construction Manager: Fegan, Mike/Loomba, Krishna
Constructed By: Falls Church Construction Corp. (contractor)Designed By: Gauthier, Alvarado & Associates (consultant)
Construction Completion Date: 2/27/2009
Contract Number: CN07312190Task Order Number: N/A
Tax Map #: 55-2
Land: $0
Design: $909,337Permits/Fees: $56,326
Construction: $8,575,890Utilities: $28,320
Magisterial District: Springfield
Project Name: West Ox Road Complex - VDOT West Parcel Maintenance Facility
Address: 12700 Alliance Court
Costs
Total: $9,569,873
Dollar Amount
SCOPEThis project was funded by, and built for VDOT and consisted of administration & vehicle maintenance buildings, salt domes with conveyor system, & equipment structures for housing tailgate racks & spreader equipment.
009211 VDOTProject #:
Page 49
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 312Fund Title: Public Safety Construction
DPWES Project Manager: Malayeri, HosseinDPWES Construction Manager: Reed, BobDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Harper, Greg
Constructed By: Manhattan Construction (contractor)Designed By: HOK (consultant)
Construction Completion Date: 7/30/2008
Contract Number: CN06312187Task Order Number: N/A
Tax Map #: 55-2
Land: $5,766,000
Design: $7,702,000Permits/Fees: $304,700
Construction: $80,466,330Utilities: $1,283,100
Magisterial District: Springfield
Project Name: McConnell Public Safety & Transportation Operations Center
Address: 4890 Alliance Drive
Costs
Total: $95,522,130
Dollar Amount
SCOPEState-of-the-art 114,000 SF facility to house Dept. of Public Safety Communications, Office of Emergency Management, Emergency Operations Center, Virginia State Police Div. 7 dispatchers, & VDOT Traffic Management Center.
009211Project #:
Page 50
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 315Fund Title: Commercial Revitalization Program
DPWES Project Manager: Roberson, JeanmarieDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Barnes, DianneDPWES Surveyor: Harper, Greg
Constructed By: Tessa Construction & Tech Co., LLC (contractor)Designed By: Lewis Scully Gionet (consultant)
Construction Completion Date: 11/12/2008
Contract Number: CN07315040Task Order Number: N/A
Tax Map #: 30-2
Land: $29,957
Design: $95,950Permits/Fees: $0
Construction: $531,230Utilities: $3,398
Magisterial District: Dranesville
Project Name: Commercial Revitalization Prog./ McLean Streetscape Demonstration Project Ph. II
Address: Chain Bridge Road from Westmoreland to Cedar
Costs
Total: $660,535
Dollar Amount
SCOPEInstallation of 900 LF of paver sidewalk, raised median, drainage improvements, striping, landscaping, and other related items.
008912 00001Project #:
Page 51
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, BillDPWES Construction Manager: Murray, Jonathan
Constructed By: Maintenance and Stormwater Management Division, DPWESDesigned By: GKY & Associates (consultant)
Construction Completion Date: 8/15/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 068-2
Land: $0
Design: $2,400Permits/Fees: $0
Construction: $13,654Utilities: $0
Magisterial District: Braddock
Project Name: Emergency Watershed Projects/ Tapestry Drive (4602)
Address: 4602 Tapestry Drive
Costs
Total: $16,054
Dollar Amount
SCOPEAn overland relief swale was constructed to direct surface flow away from the house to minimize the house flooding potential. A yard inlet was improved by adding a second throat opening increasing flow into the underground storm drain system.
FX8000 PC007Project #:
Page 52
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Kumar, DipmaniDPWES Construction Manager: McCorkle, LisaDPWES Right-of-Way Agent: Coleman, MichaelDPWES Surveyor: Strecker, Matthias
Constructed By: Angler Environmental (contractor)Designed By: A. Morton Thomas & Associates (consultant)
Construction Completion Date: 4/11/2009
Contract Number: CN08318083Task Order Number: N/A
Tax Map #: 078-1
Land: $18,709
Design: $466,733Permits/Fees: $38,057
Construction: $1,694,364Utilities: $273,386
Magisterial District: Braddock
Project Name: Dam Safety Projects Dam Site 4 (Lake Royal)
Address: At the end of Starboard Drive - cul-de-sac
Costs
Total: $2,491,249
Dollar Amount
SCOPEThis project entailed a widening, realignment, and armoring of an existing earthen auxiliary spillway and raising the height of the training dikes.
FX4000 PC010Project #:
Page 53
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rayyan, Yousef
DPWES Surveyor: Simpson, David
Constructed By: Environmental Quality Resource, Inc. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 6/5/2009
Contract Number: CN08318124Task Order Number: 5
Tax Map #: 070-1
Land: $0
Design: $28,206Permits/Fees: $0
Construction: $20,596Utilities: $3,210
Magisterial District: Braddock
Project Name: Accotink Creek Watershed Projects/ Duncan Drive Construction
Address: 4318 Duncan Drive
Costs
Total: $52,012
Dollar Amount
SCOPEProvide overland relief and structural improvements for residential flood mitigation.
AC8000 AC008Project #:
Page 54
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 7/31/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 069-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $4,198Utilities: $0
Magisterial District: Braddock
Project Name: Major Storm Drainage Maintenance/ McFarland/Nash
Address: 4911 & 4930 McFarland Drive
Costs
Total: $4,198
Dollar Amount
SCOPETwo yard inlets were modified to increase inflow capacity. A berm was also constructed to direct surface water into the yard inlet minimizing house flooding potential.
FX6000 FX005Project #:
Page 55
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management Program
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 2/1/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 077-2
Land: $0
Design: $0Permits/Fees: $0
Construction: $10,678Utilities: $0
Magisterial District: Braddock
Project Name: Major Storm Drainage Maintenance/ Wye Oak Commons Ci (12224)
Address: 12224 Wye Oak Commons Ci
Costs
Total: $10,678
Dollar Amount
SCOPEProject included lowering and replacing an existing one-throated yard inlet with a two-throated yard inlet to capture more surface drainage minimizing house flooding potential.
FX6000 FX005Project #:
Page 56
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, Bill & Tucker, ValerieDPWES Construction Manager: Cameron, Tom & Kerns, Bobby
Constructed By: Video Pipe Services & E.E. Lyons (contractors)Designed By: Malcolm Pirnie (consultant)
Construction Completion Date: 6/30/2009
Contract Number: CN082903/CN0629002Task Order Number: 9,10,11,13,14,15,17,18,19
Tax Map #:
Land: $0
Design: $45,000Permits/Fees: $0
Construction: $655,143Utilities: $0
Magisterial District: Countywide
Project Name: Storm Sewer Pipe Rehabilitation and Lining
Address: Countywide
Costs
Total: $700,143
Dollar Amount
SCOPEApproximately 12,160 linear feet of the County's stormwater conveyance system was rehabilitated or lined. Liners were installed in deteriorated storm pipe and pipe joints were repaired and sealed.
FX6000-Project #:
Page 57
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Lacquement, DonDPWES Construction Manager: Lacquement, Don
Constructed By: High Sierra (contractor)Designed By: Hagemeyer (consultant)
Construction Completion Date: 9/1/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: Countywide
Land: $0
Design: $19,200Permits/Fees: $0
Construction: $140,800Utilities: $0
Magisterial District: Countywide
Project Name: Dam Safety Projects/ Flood Response, Monitoring, and Signalization System
Address: Countywide
Costs
Total: $160,000
Dollar Amount
SCOPEThis project included the installation of automated water level gauges at 9 locations throughout the County including 7 high hazard dams, Huntington, & New Alexandria. The gauge readings improve flood potential forecasting & emerging response activity.
FX4000 FX001Project #:
Page 58
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Qureshi, MannanDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Simpson, David
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Syed, Shahid, Stormwater Planning Division, DPWES
Construction Completion Date: 1/16/2009
Contract Number: CN09318126Task Order Number: 106
Tax Map #: 031-2
Land: $890,619
Design: $27,678Permits/Fees: $0
Construction: $49,140Utilities: $0
Magisterial District: Dranesville
Project Name: Pimmit Run Watershed Projects/ Woodacre Drive
Address: 1447 Woodacre Drive
Costs
Total: $967,437
Dollar Amount
SCOPEFlood mitigation of 1447 Woodacre Drive by acquiring the property, demolishing the house and raising the grades for future building pad to a 100-year elevation.
PM8000 PM003Project #:
Page 59
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom
DPWES Surveyor: Harper, Greg
Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 5/31/2009
Contract Number: CN09318144Task Order Number: 7
Tax Map #: 019-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $49,694Utilities: $0
Magisterial District: Dranesville
Project Name: Infrastructure Replacement Program/ Atwood Road
Address: 9501 Atwood Road
Costs
Total: $49,694
Dollar Amount
SCOPEReplaced 180 feet of blocked dilapidated storm sewer pipe and added a drop structure to avoid repeated structure blockages.
FX6000 FX007Project #:
Page 60
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, BillDPWES Construction Manager: Cameron, Tom
Constructed By: E.E. Lyons (contractor)Designed By: Schell, Bill, Maintenance & Stormwater Management Div.
Construction Completion Date: 5/26/2009
Contract Number: CN09318161Task Order Number: 15
Tax Map #: 030-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $18,164Utilities: $0
Magisterial District: Dranesville
Project Name: Infrastructure Replacement Program/ Laughlin Ave.
Address: 1514 Laughlin Avenue
Costs
Total: $18,164
Dollar Amount
SCOPEInadequate storm drainage pipes were removed and replaced with pipes which were larger in size. The additional capacity will help to minimize house and yard flooding.
FX6000 FX007Project #:
Page 61
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, BillDPWES Construction Manager: Kolony, Drew
Constructed By: Apex (contractor)Designed By: GKY & Associates (consultant)
Construction Completion Date: 8/31/2008
Contract Number: N/ATask Order Number: 30
Tax Map #: 030-1
Land: $0
Design: $2,400Permits/Fees: $0
Construction: $27,773Utilities: $0
Magisterial District: Dranesville
Project Name: Emergency Watershed Projects/ Scotts Run Road
Address: 1310 Scotts Run Rd
Costs
Total: $30,173
Dollar Amount
SCOPEApproximately 200 feet of channel was dredged to get positive flow from a storm sewer system to the receiving stream. This project was constructed to minimize house and road flooding.
FX8000 SC001Project #:
Page 62
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Murray, Jonathan
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 10/21/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 012-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $2,345Utilities: $0
Magisterial District: Hunter Mill
Project Name: Emergency Watershed Projects/ Westhills Lane (1324-1326)
Address: 1324 Westhills Lane
Costs
Total: $2,345
Dollar Amount
SCOPEAn 80 foot overland relief swale was constructed to direct surface water through the side yard to the street to minimize the risk of house flooding.
FX8000 DF008Project #:
Page 63
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Snyder, Dave
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Snyder, Dave, Maintenance & Stormwater Management Div.
Construction Completion Date: 7/10/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 025-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $14,526Utilities: $0
Magisterial District: Hunter Mill
Project Name: Facility Major Maintenance/ Centreville/Old Centreville
Address: Centreville Road/Old Centreville Road
Costs
Total: $14,526
Dollar Amount
SCOPEThe project included sediment removal from the low flow control and ditches in order to improve pond performance. Wetland plant growth will further enhance water quality.
FX5000 FX006Project #:
Page 64
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, BillDPWES Construction Manager: Pope, Billy
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Schell, Bill, Maintenance & Stormwater Management Div.
Construction Completion Date: 3/31/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 026-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $10,885Utilities: $0
Magisterial District: Hunter Mill
Project Name: Major Storm Drainage Maintenance/ Colts Neck Road
Address: Glade Drive/Colts Neck Road
Costs
Total: $10,885
Dollar Amount
SCOPEThe outfall drop structure was modified and a trash rack was installed to address safety issues.
FX6000 FX005Project #:
Page 65
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Qamar, TabassumDPWES Construction Manager: Stewart, HeatherDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg
Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Wilbur Smith & Associates (consultant)
Construction Completion Date: 5/7/2009
Contract Number: CN09318129Task Order Number: 3
Tax Map #: 091-3
Land: $4,084
Design: $49,715Permits/Fees: $0
Construction: $79,304Utilities: $1,838
Magisterial District: Lee
Project Name: Dam Safety Projects/ Crestleigh PD1, 0765DP
Address: 7500 Block Beulah Street
Costs
Total: $134,941
Dollar Amount
SCOPEThe improvements included stabilizing the pond walls with gabion baskets and rip rap; increasing the pond volume; improving the outflow through the top of riser trash rack; and removal of trees from the embankment and restoration.
FX4000 LH001Project #:
Page 66
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rayyan, Yousef
DPWES Surveyor: Simpson, David
Constructed By: Environmental Quality Resources,LLC (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 6/1/2009
Contract Number: CN08318085Task Order Number: 4
Tax Map #: 080-2
Land: $0
Design: $35,655Permits/Fees: $0
Construction: $37,153Utilities: $4,120
Magisterial District: Lee
Project Name: Cameron Run Watershed Projects/ Cabin John Road
Address: 6915 Cabin John Road
Costs
Total: $76,928
Dollar Amount
SCOPEProvide overland relief and structural improvements for residential flood mitigation.
CA8000 CA032Project #:
Page 67
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rhame, Donna
DPWES Surveyor: Perry, Michael
Constructed By: Cephas Contracting Inc. (contractor)Designed By: Bawcombe, Nathanial & Rhame, Donna, SWPD, DPWES
Construction Completion Date: 12/12/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 091-4
Land: $0
Design: $574Permits/Fees: $344
Construction: $32,696Utilities: $0
Magisterial District: Lee
Project Name: Kingstowne Monitoring Telegraph Road (7137 Demolition)
Address: 7137 Telegraph Road
Costs
Total: $33,614
Dollar Amount
SCOPEDemolished blighted structure and re-vegetated the Resource Protection Area on newly acquired Board of Supervisors' property.
DC8000 DC008Project #:
Page 68
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, BillDPWES Construction Manager: McCorkle, LisaDPWES Right-of-Way Agent: Ratliff, JamesDPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Malcolm Pirnie (consultant)
Construction Completion Date: 10/8/2008
Contract Number: CN08318121Task Order Number: 73
Tax Map #: 082-4
Land: $0
Design: $85,383Permits/Fees: $0
Construction: $400,000Utilities: $0
Magisterial District: Lee
Project Name: Infrastructure Replacement Program/ Pikes Branch Infrastructure Replacement
Address: Telegraph Rd/Florence Lane
Costs
Total: $485,383
Dollar Amount
SCOPERepair and replacement of the existing timber retaining wall and stabilization of 300 LF of stream bed; due to severe erosion along the Pikes Branch and undermining of the existing timber walls.
FX6000 CA010Project #:
Page 69
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Gharavi, Mo
DPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting, Inc. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 1/14/2009
Contract Number: CN08318013Task Order Number: 86
Tax Map #: 082-3
Land: $3,891
Design: $56,048Permits/Fees: $0
Construction: $58,160Utilities: $3,083
Magisterial District: Lee
Project Name: Cameron Run Watershed Projects/ Thornwood Drive (6208)
Address: 6208 Thornwood Drive
Costs
Total: $121,182
Dollar Amount
SCOPEInstallation of drainage structures, pipes, grading for positive drainage, driveway replacement, and site restoration.
CA8000 CA028Project #:
Page 70
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pistore, JustinDPWES Construction Manager: Murray, Jonathan
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Pistore, Justin, Stormwater Planning Division, DPWES
Construction Completion Date: 10/7/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 101-2
Land: $0
Design: $0Permits/Fees: $0
Construction: $3,245Utilities: $1,067
Magisterial District: Lee
Project Name: Little Hunting Creek Watershed Projects Seven Woods Dr Outfall Improvement
Address: 7950 Seven Woods Drive
Costs
Total: $4,312
Dollar Amount
SCOPEImprovement of an existing stormwater outfall, outfall channel, Resource Protection Area, water quality through the installation of energy dissipation structures, channel restoration, and native vegetation.
LH8000 LH021Project #:
Page 71
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Chang, MartinDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Preston, ClintonDPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 2/23/2009
Contract Number: CN08318080Task Order Number: 116
Tax Map #: 072-1
Land: $6,093
Design: $62,788Permits/Fees: $0
Construction: $99,225Utilities: $1,528
Magisterial District: Mason
Project Name: Cameron Run Watershed Projects/ Pinecrest Golf Course
Address: 6600 Little River Turnpike
Costs
Total: $169,634
Dollar Amount
SCOPEConstruction of two bio-retention facilities. The new facilities will filter a portion of the runoff from the parking lot of the golf course and area adjacent to Little River Turnpike.
CA8000 CA009Project #:
Page 72
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Barnes, DianneDPWES Surveyor: Simpson, David
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 2/20/2009
Contract Number: CN07318034Task Order Number: 118
Tax Map #: 061-1
Land: $314
Design: $46,871Permits/Fees: $0
Construction: $48,123Utilities: $4,425
Magisterial District: Mason
Project Name: Cameron Run Watershed Projects/ Valley Lane (3143) Construction
Address: 3143 Valley Lane
Costs
Total: $99,733
Dollar Amount
SCOPEProvide residential flood mitigation with structural improvements.
CA8000 CA024Project #:
Page 73
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: Murray, JonathanDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Jensen, Chris
Constructed By: Maintenance & Stormwater Management Div., DPWESDesigned By: DPWES and Northern Virginia Soil & Water Conservation District
Construction Completion Date: 5/21/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 061-4
Land: $9,658
Design: $24,607Permits/Fees: $0
Construction: $41,284Utilities: $1,873
Magisterial District: Mason
Project Name: Cameron Run Watershed Projects Center Lane
Address: 5713 Center Lane
Costs
Total: $77,422
Dollar Amount
SCOPEProject included construction of bioretention facility, site grading, and reduction of impervious area to improve stormwater runoff and provide water quality.
CA8000 CA004Project #:
Page 74
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Kumar, DipmaniDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Coleman, MichaelDPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Wilbur Smith & Associates (consultant)
Construction Completion Date: 8/25/2008
Contract Number: CN08318125Task Order Number: 77
Tax Map #: 080-2
Land: $4,857
Design: $37,654Permits/Fees: $0
Construction: $32,806Utilities: $3,312
Magisterial District: Mason
Project Name: Dam Safety Projects/ Fairfax Co Fire Station 26
Address: 5316 Carolina Place
Costs
Total: $78,629
Dollar Amount
SCOPEProvide a 510 square-foot bioretention filter retrofit to replace an infiltration trench. The filter will provide water quality treatment for a portion of the Fire Station #26 facility.
FX4000 CA003Project #:
Page 75
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Chang, MartinDPWES Construction Manager: Qureshi, MannanDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Harper, Greg
Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Michael Baker Jr., Inc. (consultant)
Construction Completion Date: 5/22/2009
Contract Number: CN08318115Task Order Number: 7
Tax Map #: 060-4
Land: $0
Design: $32,724Permits/Fees: $0
Construction: $163,885Utilities: $0
Magisterial District: Mason
Project Name: Storm Drainage Improvements & Innovation/ Dearborn Dr Storm Drainage Project
Address: 6611 Dearborn Drive
Costs
Total: $196,609
Dollar Amount
SCOPEWork included restoring the species in Resource Protection Area by removing the invasive plants and replanting with native vegetation.
FX1000 CA002Project #:
Page 76
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Murray, Jonathan
DPWES Surveyor: McEntire, Vickie
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 12/10/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 060-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $18,085Utilities: $2,352
Magisterial District: Mason
Project Name: Emergency Watershed Projects/ Woodland Road (4005) Phase I
Address: 4005 Woodland Road
Costs
Total: $20,437
Dollar Amount
SCOPEThe drainage channel was resized and realigned to convey the 100-yr storm away from the dwelling. This project was constructed to minimize house flooding potential.
FX8000 AC009Project #:
Page 77
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom
Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 8/15/2008
Contract Number: CN09318131Task Order Number: 2
Tax Map #: 050-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $83,137Utilities: $0
Magisterial District: Mason
Project Name: Infrastructure Replacement Program/ Wayne Road
Address: 3034 Wayne Road
Costs
Total: $83,137
Dollar Amount
SCOPE136 feet of deteriorated corrugated metal pipe was replaced with a 42" diameter reinforced concrete pipe and associated drainage structures were installed and replaced.
FX6000 FX007Project #:
Page 78
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Gharavi, Mo
DPWES Surveyor: Harper, Greg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 4/16/2009
Contract Number: CN08318104Task Order Number: 112
Tax Map #: 060-3
Land: $0
Design: $40,539Permits/Fees: $0
Construction: $53,601Utilities: $2,966
Magisterial District: Mason
Project Name: Cameron Run Watershed Projects/ Kendale Road Construction
Address: 3816 Kendale Road
Costs
Total: $97,106
Dollar Amount
SCOPEProvide overland relief and structural improvements for residential flood mitigation.
CA8000 CA030Project #:
Page 79
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Housley, Gregg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 10/6/2008
Contract Number: CN08318120Task Order Number: 84
Tax Map #: 102-1
Land: $0
Design: $22,600Permits/Fees: $0
Construction: $108,140Utilities: $0
Magisterial District: Mount Vernon
Project Name: Little Hunting Creek Watershed Projects/ Walt Whitman School Retrofit
Address: 2500 Parker's Lane
Costs
Total: $130,740
Dollar Amount
SCOPEConstruction of rain gardens, pervious pavement, and manufactured BMPs for improved water quality.
LH8000 LH006Project #:
Page 80
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Perry, Michael
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 10/28/2008
Contract Number: CN08318119Task Order Number: 88
Tax Map #: 111-1
Land: $0
Design: $23,064Permits/Fees: $0
Construction: $41,217Utilities: $0
Magisterial District: Mount Vernon
Project Name: Little Hunting Creek Watershed Projects/ Fort Hunt Elementary School
Address: 8801 Linton Lane
Costs
Total: $64,281
Dollar Amount
SCOPEConstruction of two bio-filtration ponds and manufactured BMPs for improved water quality.
LH8000 LH006Project #:
Page 81
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Housley, Gregg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 12/15/2008
Contract Number: CN08318118Task Order Number: 101
Tax Map #: 092-4
Land: $0
Design: $36,118Permits/Fees: $0
Construction: $88,096Utilities: $0
Magisterial District: Mount Vernon
Project Name: Little Hunting Creek Watershed Projects/ Hybla Valley Elementary School
Address: 3415 Lockheed Boulevard
Costs
Total: $124,214
Dollar Amount
SCOPEConstruction of rain gardens, pervious pavement, and manufactured BMPs for improved water quality.
LH8000 LH006Project #:
Page 82
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Hatterick, JeffDPWES Construction Manager: Pope, Billy
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: St. Clair, Scott, Maintenance & Stormwater Management Div.
Construction Completion Date: 3/15/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 098-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $7,555Utilities: $0
Magisterial District: Mount Vernon
Project Name: Emergency Watershed Projects/ Newington Commons Road (8749)
Address: 8749 Newington Commons Road
Costs
Total: $7,555
Dollar Amount
SCOPEThis project included adding a throat and lowering an existing yard inlet to minimize the risk of house flooding.
FX8000 PC006Project #:
Page 83
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Strecker, Mathias
Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 3/11/2009
Contract Number: CN08318085Task Order Number: 1
Tax Map #: 093-1
Land: $287
Design: $31,633Permits/Fees: $0
Construction: $55,132Utilities: $0
Magisterial District: Mount Vernon
Project Name: Little Hunting Creek Watershed Projects/ Bucknell Manor Park Retrofit
Address: 2236 Mary Baldwin Drive
Costs
Total: $87,052
Dollar Amount
SCOPERemoval of an existing concrete ditch and construction of two vegetated swales incorporating new low impact development measures for improved water quality.
LH8000 LH012Project #:
Page 84
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: McEntire, Vickie
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 5/10/2009
Contract Number: CN08318084Task Order Number: 5
Tax Map #: 102-4
Land: $3,270
Design: $23,062Permits/Fees: $0
Construction: $65,265Utilities: $736
Magisterial District: Mount Vernon
Project Name: Little Hunting Creek Watershed Projects/ Collingwood Park Retrofit
Address: 8200 W. Boulevard Drive
Costs
Total: $92,333
Dollar Amount
SCOPEConstruction of one bio-retention filter, one soil amendment area and several strips of no-mow areas in slopes near the entrance to improve water quality as well as attenuate flows before discharging to an existing outfall.
LH8000 LH013Project #:
Page 85
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Moffatt & Nichol/RKK (consultant)
Construction Completion Date: 6/29/2009
Contract Number: CN08318087Task Order Number: 1
Tax Map #: 098-3
Land: $3,709
Design: $94,204Permits/Fees: $0
Construction: $106,368Utilities: $4,079
Magisterial District: Mount Vernon
Project Name: Dam Safety Projects/ Southern Oaks
Address: 8300 Block Southern Oaks Court
Costs
Total: $208,360
Dollar Amount
SCOPEThe project provided for the retrofit of a stormwater detention pond and included the repair of the principal spillway, installation of new storm pipes & riser structure and establishment of permanent access for maintenance.
FX4000 PC007Project #:
Page 86
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 3/16/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 098-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $9,499Utilities: $0
Magisterial District: Mount Vernon
Project Name: Emergency Watershed Projects/ Moline Place (8307, 8309, 8311, 8313)
Address: 8307 - 8313 Moline Place
Costs
Total: $9,499
Dollar Amount
SCOPEAdditional throat openings were constructed on two yard inlets to allow for extra capacity of stormwater into the existing storm drain system to minimize the potential of clogging and house flooding.
FX8000 PC003Project #:
Page 87
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Schell, BillDPWES Construction Manager: Cameron, Tom
Constructed By: E.E. Lyons (contractor)Designed By: Malcolm Pirnie (consultant)
Construction Completion Date: 3/1/2009
Contract Number: CN09318130Task Order Number: 1 & 8
Tax Map #: 102-1
Land: $0
Design: $5,000Permits/Fees: $0
Construction: $10,024Utilities: $0
Magisterial District: Mount Vernon
Project Name: Infrastructure Replacement Program Paul Springs Pwky
Address: Intersection of Paul Spring Pkwy/New Orleans Dr.
Costs
Total: $15,024
Dollar Amount
SCOPERepaired and replaced two deteriorating outfall structures and associated pipe segments.
FX6000 FX007Project #:
Page 88
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management Program
DPWES Project Manager: Schell, BillDPWES Construction Manager: Cook, Steve
Constructed By: American Contracting & Environmental Services (contractor)Designed By: Malcolm Pirnie (consultant)
Construction Completion Date: 12/1/2008
Contract Number: CN03402777Task Order Number: N/A
Tax Map #: 093-1
Land: $0
Design: $65,500Permits/Fees: $0
Construction: $132,000Utilities: $0
Magisterial District: Mount Vernon
Project Name: Watershed Projects New Alexandria Pump Station Upgrades
Address: 6500 Thirteenth St.
Costs
Total: $197,500
Dollar Amount
SCOPETo minimize the flooding potential of the New Alexandria Pump Station and to safeguard its electrical equipment, automated, and mechanical components were installed to protect the station and to control inflow/outflow gates.
BH8000 BH001Project #:
Page 89
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Perry, Michael
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Moffatt & Nichol/RKK (consultant)
Construction Completion Date: 5/8/2009
Contract Number: CN08318088Task Order Number: 117
Tax Map #: 46-2
Land: $3,382
Design: $84,124Permits/Fees: $0
Construction: $109,714Utilities: $12,990
Magisterial District: Providence
Project Name: Dam Safety Projects/ Mill Run Crossing
Address: 3300 Block Cranbrook Court
Costs
Total: $210,210
Dollar Amount
SCOPEThis project provided for the retrofit of a stormwater detention pond, repair of a failed principal spillway, installation of a new storm pipe, & riser structure and establishment of permanent access for maintenance.
FX4000 DF007Project #:
Page 90
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Bajere, PaulDPWES Construction Manager: Qureshi, Mannan
Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bajere, Paul, Stormwater Planning Division, DPWES
Construction Completion Date: 2/3/2009
Contract Number: CN09126001Task Order Number: 4
Tax Map #: 040-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $17,459Utilities: $7,614
Magisterial District: Providence
Project Name: Cameron Run Watershed Projects/ Falls Hill Retrofits
Address: 7315 Gordons Road
Costs
Total: $25,073
Dollar Amount
SCOPEThis project provided flood mitigation measures at 7135 Gordons Road by replacing an existing 9 foot long curb inlet top with a 18 foot curb drop inlet drop. The work also included replacing existing curb & gutter to match new curb inlet top.
CA8000 CA014Project #:
Page 91
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Murray, Jonathan
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 6/15/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 048-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $5,602Utilities: $0
Magisterial District: Providence
Project Name: Major Storm Drainage Maintenance/ Ellenwood
Address: 2915 Everleigh Way
Costs
Total: $5,602
Dollar Amount
SCOPEWork included modifying a yard inlet by adding two throat openings and constructing a berm around the back of the structure. This work was completed to minimize house flooding potential.
FX6000 FX005Project #:
Page 92
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Kolony, Drew
Constructed By: Apex (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 9/1/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 039-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $11,200Utilities: $0
Magisterial District: Providence
Project Name: Emergency Watershed Projects/ Bell Lane (8232)
Address: 8232 Bell Lane
Costs
Total: $11,200
Dollar Amount
SCOPERetrofit of two window wells and installation of appropriate drainage facilities to minimize house flooding potential.
FX8000 DF001Project #:
Page 93
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tuttle, RonDPWES Construction Manager: N/A
Constructed By: Fairfax Releaf, Inc. & Virginia Deparment of Forestry (contractor)Designed By: Tuttle, Ron, Stormwater Planning Division, DPWES
Construction Completion Date: 5/9/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 050-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $0Utilities: $0
Magisterial District: Providence
Project Name: Cameron Run Watershed Projects Shrevewood ES- Phase I & II SW Retrofit
Address: 7525 Shreve Road
Costs
Total: $0
Dollar Amount
SCOPEConversion of approximately 1.5 acres of turf to native forest and meadow. Work completed by volunteers.
CA8000 CA033Project #:
Page 94
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tuttle, RonDPWES Construction Manager: N/A
Constructed By: Waples Mill Elementary School, FCPSDesigned By: Tuttle, Ron, Stormwater Planning Division, DPWES
Construction Completion Date: 5/1/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 046-2
Land: $0
Design: $0Permits/Fees: $0
Construction: $0Utilities: $0
Magisterial District: Providence
Project Name: Difficult Run Watershed Projects Waples Mill Elementary School - Phase I & II SW
Address: 11509 Waples Mill Road
Costs
Total: $0
Dollar Amount
SCOPEAmend soil and convert approximately 1/2 acre of turf to native meadow and install bioretention basin for improved stormwater detention and water quality. Work completed by school ground operations.
DF8000 DF010Project #:
Page 95
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Maguire, JoanDPWES Construction Manager: Weaver, John
DPWES Surveyor: Harper, Greg
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: St. Clair, Scott, Maintenance & Stormwater Management Div.
Construction Completion Date: 11/15/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 088-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $8,647Utilities: $0
Magisterial District: Springfield
Project Name: Emergency Watershed Projects/ Gavelwood Ct/9000 Block/Flood Mitigation
Address: 9010. 9012, 9014 Gavelwood Court
Costs
Total: $8,647
Dollar Amount
SCOPEA one-throated yard inlet was installed along the existing pipe system to minimize house flooding.
FX8000 PC005Project #:
Page 96
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg
Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 8/15/2008
Contract Number: CN07318042Task Order Number: 9
Tax Map #: 078-3
Land: $6,457
Design: $46,782Permits/Fees: $0
Construction: $121,002Utilities: $2,427
Magisterial District: Springfield
Project Name: Dam Safety Projects/ Cardinal Glen Sec. 2 - Phase 1
Address: 6000 Block Heathwick Court
Costs
Total: $176,668
Dollar Amount
SCOPEThis project provided for construction of an emergency spillway and establishment of a permanent access road. The Phase 1 of this project was completed in 2008 and provided for dam repairs and construction of stormwater structures.
FX4000 PC005Project #:
Page 97
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: Gharavi, MoDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Harper, Greg
Constructed By: APEX Companies, LLC (contractor)Designed By: Moffatt & Nichol/RKK (consultant)
Construction Completion Date: 2/24/2009
Contract Number: CN08318086Task Order Number: 14
Tax Map #: 76-1
Land: $172
Design: $59,159Permits/Fees: $0
Construction: $70,505Utilities: $1,177
Magisterial District: Springfield
Project Name: Dam Safety Projects/ Colchester Hills
Address: 12131 Brantleigh Place
Costs
Total: $131,013
Dollar Amount
SCOPEThis project provided for the repair of the failed dam embankment, replacement of the principal spillway and outfall pipes, removal of debris and sediment, and planting of trees and shrubs.
FX4000 PH001Project #:
Page 98
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Sprow, Pete
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.
Construction Completion Date: 9/24/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 065-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $18,241Utilities: $0
Magisterial District: Springfield
Project Name: Dam Safety Projects/ Little Rocky Run Sediment Removal & Wetland Retrofit
Address: 13821 South Springs Drive
Costs
Total: $18,241
Dollar Amount
SCOPEThe project included sediment removal in order to improve pond performance and a wetland plant seed mix to enhance water quality.
FX4000 LR003Project #:
Page 99
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Sprow, Pete
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.
Construction Completion Date: 4/1/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 098-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $52,649Utilities: $0
Magisterial District: Springfield
Project Name: Dam Safety Projects/ Whisperwood Pond 2 Sediment Removal and Retrofit
Address: 8929 Mountain Ash Drive
Costs
Total: $52,649
Dollar Amount
SCOPEWork included removal of sediment and debris, as well as retrofitting a trash rack, wing walls, and apron which will improve pond performance.
FX4000 PC015Project #:
Page 100
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: McCorkle, LisaDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg
Constructed By: APEX Companies, LLC (contractor)Designed By: Bowman Consulting Group (consultant)
Construction Completion Date: 5/8/2009
Contract Number: CN07318042Task Order Number: 9
Tax Map #: 078-3
Land: $3,229
Design: $46,782Permits/Fees: $0
Construction: $147,299Utilities: $2,427
Magisterial District: Springfield
Project Name: Dam Safety Projects/ Cardinal Glen Sec. 2 - Phase II
Address: 6000 Block Heathwick Court
Costs
Total: $199,736
Dollar Amount
SCOPEThis project provided for dam repair and included the construction of a stormwater riser structure, outfall pipe, open water channel, grading, and site restoration.
FX4000 PC005Project #:
Page 101
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom
DPWES Surveyor: Harper, Greg
Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 10/25/2008
Contract Number: N/ATask Order Number: 3
Tax Map #: 089-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $52,394Utilities: $0
Magisterial District: Springfield
Project Name: Infrastructure Replacement Program/ Holford Lane
Address: 6700 Holford Lane
Costs
Total: $52,394
Dollar Amount
SCOPEThis project included removing and replacing approximately 152 linear feet of storm pipe, replacing the end wall, installing a drop structure, and stabilizing and restoring the adjacent easement area.
FX6000 FX007Project #:
Page 102
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Pistore, JustinDPWES Construction Manager: Bashir, Qais
DPWES Surveyor: Harper, Greg
Constructed By: Angler Environmental (contractor)Designed By: Michael Baker Jr., Inc. (consultant)
Construction Completion Date: 4/30/2009
Contract Number: CN08318107Task Order Number: N/A
Tax Map #: 078-4
Land: $172
Design: $100,283Permits/Fees: $0
Construction: $197,728Utilities: $0
Magisterial District: Springfield
Project Name: Pohick Creek Watershed Projects/ Poplar Spring Court
Address: 9300 Block Poplar Spring Court
Costs
Total: $298,183
Dollar Amount
SCOPEProvide 600 LF of stream restoration by establishing a stable stream morphology through stabilizing bank grades, installing natural channel design with varying rock structures, and restoring the riparian area through establishment of native plantings.
PC8000 PC004Project #:
Page 103
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Markey, Richard
Constructed By: APEX (contractor)Designed By: Markey, Richard, Maintenance & Stormwater Management Div.
Construction Completion Date: 12/23/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 065-4
Land: $0
Design: $2,399Permits/Fees: $0
Construction: $110,113Utilities: $0
Magisterial District: Springfield
Project Name: Dam Safety Projects/ Compton Heights Sediment Removal and Retrofit
Address: 6848 Compton Heights Circle
Costs
Total: $112,512
Dollar Amount
SCOPERemoval of 300 cubic yards of sediment from the pond floor and adjacent micropools restoring the pond to its original capacity. A gabion weir sediment forebay was also installed to improve sediment management.
FX4000 LR002Project #:
Page 104
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 7/25/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 078-04
Land: $0
Design: $0Permits/Fees: $0
Construction: $3,431Utilities: $0
Magisterial District: Springfield
Project Name: Major Storm Drainage Maintenance/ 6244 Garretson St
Address: 6244 Garretson Street
Costs
Total: $3,431
Dollar Amount
SCOPEA manhole structure was modified to a two-throated yard inlet to minimize house and yard flooding.
FX6000 FX005Project #:
Page 105
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Rossi, Dennis
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.
Construction Completion Date: 8/6/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 045-3
Land: $0
Design: $0Permits/Fees: $0
Construction: $3,306Utilities: $0
Magisterial District: Sully
Project Name: Facility Major Maintenance/ Poplar Tree Estates Sec 2 Trash Rack Retrofit
Address: Poplar Tree Rd
Costs
Total: $3,306
Dollar Amount
SCOPEFabrication and construction of a new trash rack to minimize future blockages and potential house flooding. The redesign was so successful that the pond did not block during Tropical Storm Hanna in September 2008.
FX5000 FX006Project #:
Page 106
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Meyers, MattDPWES Construction Manager: Lim, VannakDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Housley, Gregg
Constructed By: APEX Companies, LLC (contractor)Designed By: Moffatt & Nichol/RKK (consultant)
Construction Completion Date: 2/10/2009
Contract Number: CN08318089Task Order Number: 15
Tax Map #: 046-1
Land: $4,804
Design: $97,293Permits/Fees: $0
Construction: $119,010Utilities: $1,132
Magisterial District: Sully
Project Name: Dam Safety Projects/ Fox Vale Sec 6
Address: 11900 Block Vale Road
Costs
Total: $222,239
Dollar Amount
SCOPEThis project increased the pond capacity and included the construction of a riser structure, storm drain pipes, rip rap, landscaping, and other related items.
FX4000 DF008Project #:
Page 107
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Snyder, Dave
Constructed By: Maintenance and Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.
Construction Completion Date: 1/5/2009
Contract Number: N/ATask Order Number: N/A
Tax Map #: 053-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $16,796Utilities: $0
Magisterial District: Sully
Project Name: Facility Major Maintenance/ Pleasant Hill Sediment Removal and Retrofit
Address: 15389 Martins Hundred Drive
Costs
Total: $16,796
Dollar Amount
SCOPEThe project included the retrofit of a new headwall and trash rack improving the performance of the facility.
FX5000 FX005Project #:
Page 108
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Markey, RichardDPWES Construction Manager: Snyder, Dave
Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey. Richard, Maintenance & Stormwater Management Div.
Construction Completion Date: 8/8/2008
Contract Number: N/ATask Order Number: N/A
Tax Map #: 045-1
Land: $0
Design: $0Permits/Fees: $0
Construction: $30,250Utilities: $0
Magisterial District: Sully
Project Name: Dam Safety Projs/ Chantilly Library Sediment Removal & Wetland Retrofit
Address: 4000 Stringfellow Road
Costs
Total: $30,250
Dollar Amount
SCOPEThe project included sediment removal in order to improve pond performance and a wetland plant seed mix to enhance water quality.
FX4000 CU001Project #:
Page 109
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 318Fund Title: Stormwater Management
DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom
Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.
Construction Completion Date: 6/12/2009
Contract Number: CN09318163Task Order Number: 16
Tax Map #: 053-4
Land: $0
Design: $0Permits/Fees: $0
Construction: $34,111Utilities: $0
Magisterial District: Sully
Project Name: Infrastructure Maintenance Program/ Ampstead Court
Address: 14932 Ampstead Court
Costs
Total: $34,111
Dollar Amount
SCOPEA curb inlet was added and an overland relief channel was constructed to minimize house flooding.
FX6000 FX007Project #:
Page 110
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 340Fund Title: Housing Assistance Program
DPWES Project Manager: Ayers, RobertDPWES Construction Manager: Minnix, W. ToddDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: McMillen, Barry
Constructed By: Tessa Construction & Tech Co. (contractor)Designed By: Rinker Design Associates (consultant)
Construction Completion Date: 8/29/2008
Contract Number: CP06380011Task Order Number: N/A
Tax Map #: 083-3
Land: $99,756
Design: $143,054Permits/Fees: $0
Construction: $1,697,915Utilities: $0
Magisterial District: Lee
Project Name: Jefferson Manor IIB
Address: 2800 Fort Drive
Costs
Total: $1,940,725
Dollar Amount
SCOPEReconstruction of approx. 1500' of Fort Drive, from Edgehill Drive to North Kings Highway. It included a new 12" watermain, storm drainage system, curb & gutter, sidewalks, concrete driveway entrances, driveways, retaining walls, & stairways.
013918Project #:
Page 111
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 370Fund Title: Park Authority Bond Construction
DPWES Project Manager: Ogurcak, ToniDPWES Construction Manager: Foelsch, Rick
Constructed By: Falls Church Construction Corp. (contractor)Designed By: Bowie Gridley Architects (consultant)
Construction Completion Date: 8/7/2008
Contract Number: CN0651035-01Task Order Number: N/A
Tax Map #: 97-1
Land: $261,424
Design: $130,484Permits/Fees: $0
Construction: $2,419,489Utilities: $36,455
Magisterial District: Springfield
Project Name: South Run RECenter - Fitness Addition
Address: 7550 Reservation Drive
Costs
Total: $2,847,852
Dollar Amount
SCOPEThis project consisted of a two story, 7,000 SF addition to the existing South Run District Park RECenter, a 65 space parking lot with lighting and a new stormwater detention pond. The addition provides a program room and fitness center.
476204Project #:
Page 112
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 402Fund Title: Wastewater Treatment Revenue Fund
DPWES Project Manager: Flowers, RandallDPWES Construction Manager: Knizner, AnthonyDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Murdoch, Guy
Constructed By: Anchor Construction Corp. (contractor)Designed By: Dewberry & Davis (consultant)
Construction Completion Date: 8/28/2008
Contract Number: CN03402780Task Order Number: N/A
Tax Map #: 21-4
Land: $0
Design: $492,719Permits/Fees: $300
Construction: $5,092,405Utilities: $0
Magisterial District: Dranesville
Project Name: River Oaks Sanitary Sewer Extension & Improvement
Address: River Oaks Subdivision
Costs
Total: $5,585,424
Dollar Amount
SCOPEInstallation of approximately 3,200 LF of gravity sewer pipe, 19,500 LF of force main sanitary pipe, grinder pumps, water line relocation, extensive pavement, and site restoration.
X00826 E004Project #:
Page 113
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 402Fund Title: Wastewater Treatment Revenue Fund
DPWES Project Manager: Adams, ShannaDPWES Construction Manager: Knizner, AnthonyDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg
Constructed By: William B. Hopke Company, Inc. (contractor)Designed By: Dewberry & Davis (consultant)
Construction Completion Date: 5/18/2009
Contract Number: CN06402007Task Order Number: N/A
Tax Map #: 037-4
Land: $0
Design: $42,665Permits/Fees: $300
Construction: $976,232Utilities: $0
Magisterial District: Hunter Mill
Project Name: Extension Project/ Stryker Avenue
Address: Stryker Avenue
Costs
Total: $1,019,197
Dollar Amount
SCOPEInstallation of 1,650 LF of gravity sanitary sewer pipe, 1,270 LF of sanitary sewer force main pipe, manholes, grinder pumps and renovations to the Little Vienna Sewage Pump Station to accommodate the additional flow resulting from this expansion.
X00826 EI02Project #:
Page 114
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 402Fund Title: Wastewater Treatment Revenue Fund
DPWES Project Manager: Flowers, RandallDPWES Construction Manager: Nolan, Bill
Constructed By: ALPHA Construction Company (contractor)Designed By: Whitman, Requardt & Associates (consultant)
Construction Completion Date: 9/5/2008
Contract Number: CN08402002Task Order Number: N/A
Tax Map #: 102-2
Land: $0
Design: $39,637Permits/Fees: $300
Construction: $216,496Utilities: $0
Magisterial District: Mount Vernon
Project Name: Pump Station Renovation Gunston Commons & Wellington I Pump Stations
Address: 7835 Southdown Road
Costs
Total: $256,433
Dollar Amount
SCOPEInstallation of the generator and the fuel tank relocated from Gunston Commons Sewage Pumping Station on a new concrete pad with a new weatherproof enclosure, and installation of a flood gate system.
I00351 0002Project #:
Page 115
CAPITAL PROJECTS COMPLETED - FY 2009
Fund #: 402Fund Title: Wastewater Treatment Revenue Fund
DPWES Project Manager: N/ADPWES Construction Manager: Steele, TerrenceDPWES Right-of-Way Agent: Kresge, Carol
Constructed By: Flippo Construction Company Inc. (contractor)Designed By: Camp Dresser & McKee (consultant)
Construction Completion Date: 1/28/2009
Contract Number: CN08402005Task Order Number: N/A
Tax Map #: 093-2
Land: $0
Design: $351,301Permits/Fees: $300
Construction: $4,406,345Utilities: $0
Magisterial District: Mount Vernon
Project Name: Belle View Gravity Sewer Relocation
Address: Belle View Blvd/Wakefield Street
Costs
Total: $4,757,946
Dollar Amount
SCOPEConstruction of 550 LF of 12-inch sanitary sewer pipe through a 36-inch casing pipe installed with micro-tunneling and multiple new manholes. Due to high groundwater & running sand soil, a "secant pile wall" was utilitized for excavation support.
X00905Project #:
Page 116