CAPITAL PROJECTS COMPLETED - FY 2009 Fund #: 110 Fund Title: Refuse Disposal DPWES Project Manager: Riat, Amarjit DPWES Construction Manager: Knizner, Anthony Constructed By: Martin & Gass, Inc (contractor) Designed By: Solid Waste Services, LLC (consultant) Construction Completion Date: 6/16/2009 Contract Number: CN07110001 Task Order Number: N/A Tax Map #: 056-2 Land: $0 Design: $1,555,685 Permits/Fees: $92,843 Construction: $18,785,063 Utilities: $191,412 Magisterial District: Springfield Project Name: I-66 Citizens Disposal Facility Expansion Address: 4618 West Ox Rd Costs Total: $20,625,003 Dollar Amount SCOPE Construction of elevated unloading bays, new recycling center, truck scales & scale house, booths, major storm drainage & site improvements. Also, included was a new metal goods drop-off structure & brush processing area. 174002 Project #: Page 1

Upload: anna-carlen

Post on 13-Mar-2016

222 views

Category:

Documents


2 download

DESCRIPTION

Permits/Fees: $92,843 DPWES Project Manager: Riat, Amarjit DPWES Construction Manager: Knizner, Anthony Designed By: Solid Waste Services, LLC (consultant) Fund #: 110 Fund Title: Refuse Disposal 174002Project#: Constructed By: Martin & Gass, Inc (contractor) Project Name: I-66 Citizens Disposal Facility Expansion Address: 4618 West Ox Rd Dollar Amount Tax Map #: 056-2 Construction Completion Date: 6/16/2009 Costs Magisterial District: Springfield Page 1

TRANSCRIPT

Page 1: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 110Fund Title: Refuse Disposal

DPWES Project Manager: Riat, AmarjitDPWES Construction Manager: Knizner, Anthony

Constructed By: Martin & Gass, Inc (contractor)Designed By: Solid Waste Services, LLC (consultant)

Construction Completion Date: 6/16/2009

Contract Number: CN07110001Task Order Number: N/A

Tax Map #: 056-2

Land: $0

Design: $1,555,685Permits/Fees: $92,843

Construction: $18,785,063Utilities: $191,412

Magisterial District: Springfield

Project Name: I-66 Citizens Disposal Facility Expansion

Address: 4618 West Ox Rd

Costs

Total: $20,625,003

Dollar Amount

SCOPEConstruction of elevated unloading bays, new recycling center, truck scales & scale house, booths, major storm drainage & site improvements. Also, included was a new metal goods drop-off structure & brush processing area.

174002Project #:

Page 1

Page 2: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Buckley, Beth

Constructed By: Ashburn Contracting Corp (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 3/30/2009

Contract Number: CN09303357Task Order Number: 6

Tax Map #: 69-4

Land: $0

Design: $8,867Permits/Fees: $0

Construction: $22,567Utilities: $1,797

Magisterial District: Braddock

Project Name: Safety Improvements at Bus Shelters/Stops WB Braddock Rd and Red Fox Dr NB

Address: 9025 Orange Hunt Lane

Costs

Total: $33,231

Dollar Amount

SCOPEInstallation of a concrete pad, storm structures, and other related items.

Z00032 04024Project #:

Page 2

Page 3: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 10/10/2008

Contract Number: CN09303345Task Order Number: 99

Tax Map #: 058-4

Land: $0

Design: $11,934Permits/Fees: $0

Construction: $14,767Utilities: $1,022

Magisterial District: Braddock

Project Name: Safety Improvements at Bus Shelters/Stops WB Little River Trnpk. & Elizabeth Dr.

Address: 9005 Little River Turnpike

Costs

Total: $27,723

Dollar Amount

SCOPEInstallation of a pad, concrete walkway, and storm drainage improvements.

Z00032 03673Project #:

Page 3

Page 4: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Much, GaryDPWES Construction Manager: Glines, Dale

Constructed By: Finley Asphalt (contractor)Designed By: Much, Gary, Maintenance and Stormwater Management Div.

Construction Completion Date: 10/21/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #:

Land: $0

Design: $0Permits/Fees: $0

Construction: $150,299Utilities: $0

Magisterial District: Countywide

Project Name: Emergency Road Repairs/ Service Drive Paving

Address: Countywide

Costs

Total: $150,299

Dollar Amount

SCOPEApproximately 9,355 square feet of milling and paving were performed on service drives throughout the County.

V00002 9321Project #:

Page 4

Page 5: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Felix M. BermejoDPWES Construction Manager: N/A

Constructed By: Dominion Virginia Power & NOVEC (contractor)Designed By: Streetlight Section, Planning & Design Division, DPWES

Construction Completion Date: 6/30/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #:

Land: $0

Design: $0Permits/Fees: $0

Construction: $283,465Utilities: $0

Magisterial District: Countywide

Project Name: Countywide Streetlight Projects

Address: Countywide

Costs

Total: $283,465

Dollar Amount

SCOPEIn FY 2009, 129 new streetlights were installed/upgraded throughout the County. This total includes 16 LED streetlights installed at the Burke Centre Virginia Railway Express station parking lot as part of a LED pilot project.

Z00001Project #:

Page 5

Page 6: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES

Construction Completion Date: 11/13/2008

Contract Number: CN09303346Task Order Number: 100

Tax Map #: 19-4

Land: $0

Design: $2,468Permits/Fees: $0

Construction: $14,006Utilities: $0

Magisterial District: Dranesville

Project Name: Developer Default/ Kelly Estates

Address: 9038, 9040, 9042, & 9044 Leesburg Pike

Costs

Total: $16,474

Dollar Amount

SCOPECorrected developer default punch-list items. Relocated fire hydrant, installed water valves, corrected ponding water in pavement, and repaved work areas.

U00060 00812Project #:

Page 6

Page 7: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES

Construction Completion Date: 3/11/2009

Contract Number: CN09303354Task Order Number: 121

Tax Map #: 37-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $13,310Utilities: $0

Magisterial District: Dranesville

Project Name: Developer Default/ Brown's Mill Forest

Address: 1400 Block of Wynhurst Lane

Costs

Total: $13,310

Dollar Amount

SCOPERepair of storm lines, video storm lines, and asphalt patch/paving, in preparation for VDOT inspection and acceptance.

U00060 00810Project #:

Page 7

Page 8: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Huang, Ta-EnDPWES Construction Manager: Qureshi, Mannan

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker and Associates (consultant)

Construction Completion Date: 12/4/2008

Contract Number: N/ATask Order Number: 119

Tax Map #: 40-2, 40-4

Land: $0

Design: $27,000Permits/Fees: $0

Construction: $62,109Utilities: $0

Magisterial District: Dranesville

Project Name: Haycock Road Trail, Ph II

Address: 6904-6646 Haycock Road

Costs

Total: $89,109

Dollar Amount

SCOPEThe project included safety, accessibility, and rehabilitation of approximately 1,250 LF of asphalt trail along Haycock Road.

009406Project #:

Page 8

Page 9: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Barzingy, HavalDPWES Construction Manager: Vinluan, Rufino

Constructed By: Eastern Waterproofing & Restoration Co., Inc. (contractor)Designed By: Walker Parking Consultants/Walker Restoration (consultant)

Construction Completion Date: 12/29/2008

Contract Number: CN08303312Task Order Number: N/A

Tax Map #: 16-4

Land: $0

Design: $529,967Permits/Fees: $48,536

Construction: $2,103,410Utilities: $0

Magisterial District: Hunter Mill

Project Name: Herndon Monroe Parking Garage Remedial Work

Address: 12530 Sunrise Valley Drive

Costs

Total: $2,681,913

Dollar Amount

SCOPERemedial repairs to concrete floors and columns on each level of parking structure, installation of a new waterproofing membrane and new expansion joints on the top 3 levels, installation of new drains to improve surface drainage & other related items.

009527Project #:

Page 9

Page 10: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 6/15/2009

Contract Number: CN09303363Task Order Number: 18

Tax Map #: 17-3

Land: $0

Design: $5,351Permits/Fees: $0

Construction: $3,313Utilities: $2,229

Magisterial District: Hunter Mill

Project Name: Safety Improvements at Bus Shelters/Stops EB Sunrise Valley Dr and Glade Dr SB

Address: 2100 Westglade Court

Costs

Total: $10,893

Dollar Amount

SCOPEInstallation of a concrete pad, walkway, and other related items.

Z00032 05216Project #:

Page 10

Page 11: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 6/15/2009

Contract Number: CN09303364Task Order Number: 19

Tax Map #: 17-3

Land: $0

Design: $6,033Permits/Fees: $0

Construction: $3,466Utilities: $4,873

Magisterial District: Hunter Mill

Project Name: Safety Improvements at Bus Shelters/Stops NB Glade Dr & Cocquina Dr WB

Address: 2290 Cocquina Drive

Costs

Total: $14,372

Dollar Amount

SCOPEInstallation of a concrete pad, walkway curb ramp, and other related items.

Z00032 05072Project #:

Page 11

Page 12: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid

DPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 10/10/2008

Contract Number: CN09303342Task Order Number: 96

Tax Map #: 26-1

Land: $0

Design: $6,640Permits/Fees: $0

Construction: $8,726Utilities: $824

Magisterial District: Hunter Mill

Project Name: Safety Improvements at Bus Shelters/Stops EB Glade Dr near Breton Ct

Address: 11827 Breton Court

Costs

Total: $16,190

Dollar Amount

SCOPEConstruction of a concrete pad, sidewalk, curb ramp, and other related items.

Z00032 05082Project #:

Page 12

Page 13: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 6/15/2009

Contract Number: CN09303368Task Order Number: 23

Tax Map #: 26-1

Land: $1,269

Design: $6,286Permits/Fees: $0

Construction: $7,014Utilities: $551

Magisterial District: Hunter Mill

Project Name: Safety Improvements at Bus Shelters/Stops NB Colts Neck Rd & Steeplechase Dr

Address: 2401 Colts Neck Road

Costs

Total: $15,120

Dollar Amount

SCOPEInstallation of a concrete pad, walkway, and other related items.

Z00032 05148Project #:

Page 13

Page 14: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid

DPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 10/10/2008

Contract Number: CN09303341Task Order Number: 95

Tax Map #: 026-1

Land: $0

Design: $5,798Permits/Fees: $0

Construction: $7,334Utilities: $839

Magisterial District: Hunter Mill

Project Name: Safety Improvements at Bus Shelters/Stops NB Colts Neck Rd near Insha Ct EB

Address: 12001 Insha Court

Costs

Total: $13,971

Dollar Amount

SCOPEConstruction of a concrete pad, walkway, and other related items.

Z00032 05149Project #:

Page 14

Page 15: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Dewberry & Davis (consultant)

Construction Completion Date: 12/18/2008

Contract Number: CN09303348Task Order Number: 107

Tax Map #: 91-1

Land: $0

Design: $7,999Permits/Fees: $32

Construction: $8,301Utilities: $0

Magisterial District: Lee

Project Name: Developer Default/ Rite Aid Pharmacy at Silver Lake

Address: 7100 Silver Lake Blvd.

Costs

Total: $16,332

Dollar Amount

SCOPEInstalled a new fire lane, signage, repainting fire lane curbs, and related items.

U00060 00834Project #:

Page 15

Page 16: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Schmidt, NatashaDPWES Construction Manager: Pope, BillyDPWES Right-of-Way Agent: Zore, TasneemDPWES Surveyor: Strecker, Mathias

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Planning and Design Division, DPWES

Construction Completion Date: 9/20/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 081-3

Land: $36,494

Design: $6,687Permits/Fees: $0

Construction: $26,543Utilities: $0

Magisterial District: Lee

Project Name: Road Maintenance Program/ Tilbury Road

Address: 5942 Tilbury Road

Costs

Total: $69,724

Dollar Amount

SCOPEUpgraded approximately 1000 LF of existing alley to provide emergency access and installed two gates and associated signage.

V00004 RM101Project #:

Page 16

Page 17: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES

Construction Completion Date: 4/1/2009

Contract Number: CN09303355Task Order Number: 3

Tax Map #: 81-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $45,567Utilities: $0

Magisterial District: Lee

Project Name: Developer Default/ Skyline Homes

Address: Franconia Commons Dr. & Franconia Commons Ct.

Costs

Total: $45,567

Dollar Amount

SCOPEInstallation of new fire lane signage, replacing curb ramps, curb & gutter, sidewalks, asphalt patch work. Paving/overlaying intersection at entrance to neighborhood.

U00060 00802Project #:

Page 17

Page 18: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Huntley, Nyce & Associates (consultant)

Construction Completion Date: 8/22/2008

Contract Number: CN0830330Task Order Number: 76

Tax Map #: 81-3

Land: $0

Design: $3,105Permits/Fees: $0

Construction: $9,885Utilities: $0

Magisterial District: Lee

Project Name: Developer Default/ Meriwether Estates

Address: 6300 Block of Zekan Lane

Costs

Total: $12,990

Dollar Amount

SCOPERegrade stormwater pond to planned capacity and related restoration items.

U00060 00853Project #:

Page 18

Page 19: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 10/10/2008

Contract Number: CN09303344Task Order Number: 98

Tax Map #: 071-2

Land: $0

Design: $10,232Permits/Fees: $0

Construction: $15,047Utilities: $1,393

Magisterial District: Mason

Project Name: Safety Improvements at Bus Shelters/Stops WB Little River Tnpk & Roberts Ave

Address: 6800 Little River Turnpike

Costs

Total: $26,672

Dollar Amount

SCOPEConstruction of an asphalt pad, storm drainage improvements, and other related items.

Z00032 04080Project #:

Page 19

Page 20: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 6/19/2009

Contract Number: CN09303365Task Order Number: 20

Tax Map #: 071-2

Land: $0

Design: $7,131Permits/Fees: $0

Construction: $5,200Utilities: $2,378

Magisterial District: Mason

Project Name: Safety Improvements at Bus Shelters/Stops WB Little River Tnpk & Pinecrest Pwy

Address: 4548 Airlie Way

Costs

Total: $14,709

Dollar Amount

SCOPEInstallation of a concrete pad, curb ramp, walkway, and other related items.

Z00032 04079Project #:

Page 20

Page 21: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Guarino, MichaelDPWES Construction Manager: Farsad, Nahid

DPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 10/10/2008

Contract Number: CN09303343Task Order Number: 97

Tax Map #: 080-2

Land: $0

Design: $5,716Permits/Fees: $0

Construction: $10,076Utilities: $1,149

Magisterial District: Mason

Project Name: Safety Improvements at Bus Shelters/Stops WB Edsall Rd & Cherokee Ave

Address: 6540 Edsall Road

Costs

Total: $16,941

Dollar Amount

SCOPEConstruction of a concrete pad, sidewalk, and other related items.

Z00032 03266Project #:

Page 21

Page 22: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 6/19/2009

Contract Number: CN09303367Task Order Number: 22

Tax Map #: 71-2

Land: $0

Design: $6,734Permits/Fees: $0

Construction: $7,198Utilities: $870

Magisterial District: Mason

Project Name: Safety Improvements at Bus Shelters/Stops EB Little River Tnpk & Conwell Dr SB

Address: 6761 Little River Tpk.

Costs

Total: $14,802

Dollar Amount

SCOPEInstallation of a concrete pad, curb ramp, walkway, and other related items.

Z00032 03692Project #:

Page 22

Page 23: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 6/19/2009

Contract Number: CN09303366Task Order Number: 21

Tax Map #: 071-2

Land: $0

Design: $7,022Permits/Fees: $0

Construction: $7,045Utilities: $2,801

Magisterial District: Mason

Project Name: Safety Improvements @ Bus Shelters/Stops EB Little River Tnpk & Willow Run Dr

Address: 4600 Willow Run Drive

Costs

Total: $16,868

Dollar Amount

SCOPEInstallation of a concrete pad, curb ramp, walkway, and other related items.

Z00032 03694Project #:

Page 23

Page 24: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Dewberry & Davis, LLC (consultant)

Construction Completion Date: 4/1/2009

Contract Number: CN09303351Task Order Number: 109

Tax Map #: 71-2

Land: $0

Design: $6,800Permits/Fees: $0

Construction: $20,712Utilities: $0

Magisterial District: Mason

Project Name: Developer Default/ Hillbrook Springs

Address: 6900 Block of Winter Lane

Costs

Total: $27,512

Dollar Amount

SCOPERegrade stormwater pond to planned capacity and related restoration items.

U00060 00774Project #:

Page 24

Page 25: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Much, GaryDPWES Construction Manager: Glines, Dale

Constructed By: Finley Asphalt (contractor)Designed By: Much, Gary, Maintenance and Stormwater Management Div.

Construction Completion Date: 11/10/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 71-1-01

Land: $0

Design: $0Permits/Fees: $0

Construction: $10,035Utilities: $0

Magisterial District: Mason

Project Name: Road Maintenance Projects/ Tom Davis Drive

Address: Tom Davis Drive

Costs

Total: $10,035

Dollar Amount

SCOPEMilling and paving approximately 3,150 square feet of asphalt.

V00004 RM104Project #:

Page 25

Page 26: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Utterback, BrianDPWES Construction Manager: Farsad, Nahid

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 11/26/2008

Contract Number: CN09303350Task Order Number: 111

Tax Map #: 102-2

Land: $0

Design: $9,401Permits/Fees: $0

Construction: $9,856Utilities: $1,788

Magisterial District: Mount Vernon

Project Name: Safety Improvements at Bus Shelters/Stops NB Fort Hunt Rd & Gahant Rd WB

Address: 1305 Gahant Road

Costs

Total: $21,045

Dollar Amount

SCOPEConstruction of a bus pad, concrete sidewalk, storm drainage improvements, and other related items.

Z00032 01185Project #:

Page 26

Page 27: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Land Design Consultants, Inc. (consultant)

Construction Completion Date: 9/1/2008

Contract Number: CN09303337Task Order Number: 85

Tax Map #: 110-2

Land: $0

Design: $1,235Permits/Fees: $0

Construction: $9,135Utilities: $0

Magisterial District: Mount Vernon

Project Name: DeveloperDefault/ Mount Vernon Walk Pond

Address: 3700, 3800, & 3900 Block of Colonial Ave.

Costs

Total: $10,370

Dollar Amount

SCOPERegrade stormwater pond to planned capacity and related restoration items.

U00060 00823Project #:

Page 27

Page 28: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: William H. Gordon Assoc., Inc. (consultant)

Construction Completion Date: 3/1/2009

Contract Number: CN09303353Task Order Number: 115

Tax Map #: 48-2

Land: $0

Design: $27,393Permits/Fees: $490

Construction: $95,083Utilities: $0

Magisterial District: Providence

Project Name: Developer Default/ Oakton Retreat

Address: 2600 Block of Sledding Hill Road

Costs

Total: $122,966

Dollar Amount

SCOPERegrading stormwater pond to planned capacity, clearing & grubbing, and related restoration items.

U00060 00770Project #:

Page 28

Page 29: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Cutler, Tommy

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Patton, Harris, Rust & Assoc. (consultant)

Construction Completion Date: 3/24/2009

Contract Number: CN09303352Task Order Number: 113

Tax Map #: 56-2

Land: $0

Design: $0Permits/Fees: $128

Construction: $31,343Utilities: $0

Magisterial District: Springfield

Project Name: Developer Default/ Crown Ridge

Address: 4035 Ridge Top Road

Costs

Total: $31,471

Dollar Amount

SCOPERepair/replace portions of sidewalk, curb & gutter, asphalt patches, cleaning storm structures & piping, water line valve repairs/replacement, fire lane painting, and sign replacement.

U00060 00866Project #:

Page 29

Page 30: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Malayeri, HosseinDPWES Construction Manager: Reed, BobDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Harper, Greg

Constructed By: Manhattan Construction (contractor)Designed By: HOK (consultant)

Construction Completion Date: 7/30/2008

Contract Number: CN06312187Task Order Number: N/A

Tax Map #: 55-2

Land: $0

Design: $207,881Permits/Fees: $350

Construction: $11,290,326Utilities: $1,443

Magisterial District: Springfield

Project Name: Forensics Facility

Address: 4890 Alliance Drive

Costs

Total: $11,500,000

Dollar Amount

SCOPEState-of-the-art, 33,000 SF, facility to house FCPD Crime Scene Section, Electronic Surveillance, NOVARIS.

009438Project #:

Page 30

Page 31: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES

Construction Completion Date: 12/22/2008

Contract Number: CN08303323Task Order Number: 66

Tax Map #: 36-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $93,168Utilities: $0

Magisterial District: Sully

Project Name: Developer Default/ Shade Tree Estates, Section 2

Address: 12100 & 12101 Old Pine Way

Costs

Total: $93,168

Dollar Amount

SCOPERepair/replacement of driveways & curb ramps, drainage improvements, asphalt paving, and related items.

U00060 00764Project #:

Page 31

Page 32: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 303Fund Title: County Construction

DPWES Project Manager: Popoola, LarryDPWES Construction Manager: Conchar, Karen

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Popoola, Larry, Planning & Design Div., DPWES

Construction Completion Date: 12/22/2008

Contract Number: CN08303322Task Order Number: 67

Tax Map #: 36-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $8,085Utilities: $0

Magisterial District: Sully

Project Name: Developer Default/ Shade Tree Estates, Section 3

Address: 12191, 12195, 12196, & 12198 Goldenchain Ct.

Costs

Total: $8,085

Dollar Amount

SCOPERepair/replacement of driveways & curb ramps, drainage improvements, asphalt paving, and related items.

U00060 00775Project #:

Page 32

Page 33: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: El Kaissi, MohamadDPWES Construction Manager: Minnix, W. Todd

DPWES Surveyor: Housley, Gregg

Constructed By: Arthur Construction Company, Inc. (contractor)Designed By: Volkert & Associates, Inc. (consultant)

Construction Completion Date: 4/8/2009

Contract Number: CN09304371Task Order Number: N/A

Tax Map #: 091-2

Land: $1,524

Design: $121,976Permits/Fees: $0

Construction: $186,566Utilities: $2,372

Magisterial District: Lee

Project Name: South Van Dorn Street Walkway

Address: 6984 S. Van Dorn Street

Costs

Total: $312,438

Dollar Amount

SCOPEConstruction of 2,800 LF of concrete sidewalk, handrails and related items along southbound South Van Dorn Street from Kings Centre Drive to Telegraph Road.

064272Project #:

Page 33

Page 34: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: County Construction

DPWES Project Manager: Schmidt, NatashaDPWES Construction Manager: Minnix, W. ToddDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker Design Associates (consultant)

Construction Completion Date: 5/18/2009

Contract Number: CN07303289Task Order Number: N/A

Tax Map #: 061-3

Land: $5,657

Design: $58,772Permits/Fees: $125

Construction: $387,904Utilities: $6,810

Magisterial District: Mason

Project Name: Mason District Capital Projects Columbia Pike: Govnmnt Ctr to Downing St

Address: 6507 to 4000 Columbia Pike

Costs

Total: $459,268

Dollar Amount

SCOPEConstruction of approximately 480 feet of 5' concrete sidewalk along the south side of Columbia Pike from the Mason District Government Center to Downing Street, retaining wall, handrails, and other related items.

4YP201 PB026Project #:

Page 34

Page 35: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Ayers, RobertDPWES Construction Manager: Gharavi, MoDPWES Right-of-Way Agent: Zore, TasneemDPWES Surveyor: Harper, Greg

Constructed By: A&M Concrete Corp. (contractor)Designed By: Rinker Design Associates

Construction Completion Date: 1/25/2009

Contract Number: CN08304367Task Order Number: N/A

Tax Map #: 72-4

Land: $464,394

Design: $252,489Permits/Fees: $0

Construction: $831,859Utilities: $313,251

Magisterial District: Mason

Project Name: Route 236/Beauregard Street

Address: 6200 Little River Turnpike

Costs

Total: $1,861,993

Dollar Amount

SCOPEConstruction of an additional left-turn lane from eastbound Little River Turnpike to northbound Beauregard St., replacement of the existing traffic signal, new pedestrian crossings, drainage improvements, sidewalk, & other related items.

4YP013Project #:

Page 35

Page 36: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Roberson, JeanmarieDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Preston, ClintonDPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker Design Associates

Construction Completion Date: 9/30/2008

Contract Number: CN07304354Task Order Number: N/A

Tax Map #: 072-1

Land: $228,154

Design: $209,650Permits/Fees: $0

Construction: $709,990Utilities: $207,926

Magisterial District: Mason

Project Name: Braddock Road/Route 236

Address: Intersection of Braddock Road/Route 236

Costs

Total: $1,355,720

Dollar Amount

SCOPEThis project is part of the Four-Year Transportation Program and included the realignment of eastbound lanes through the intersection. The work included installation of traffic signals, sidewalks, concrete median, pavement marking, & storm structures.

4YP014Project #:

Page 36

Page 37: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, SamDPWES Right-of-Way Agent: Zore, TasneemDPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES

Construction Completion Date: 12/19/2008

Contract Number: CN09304372Task Order Number: 102

Tax Map #: 51-3

Land: $0

Design: $36,769Permits/Fees: $0

Construction: $125,372Utilities: $0

Magisterial District: Mason

Project Name: Pedestrian Improvements - VDOT Funded Arlington Blvd/Patrick Henry Dr

Address: Arlington Blvd. and Patrick Henry Dr.

Costs

Total: $162,141

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.

064267 PI001Project #:

Page 37

Page 38: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: El Kaissi, MohamadDPWES Construction Manager: Farsad, Nahid

DPWES Surveyor: Housley, Gregg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: El Kaissi, Mohamad, Planning & Design Div., DPWES

Construction Completion Date: 6/30/2009

Contract Number: CN09304377Task Order Number: 13

Tax Map #: 71-4

Land: $0

Design: $70,276Permits/Fees: $0

Construction: $101,848Utilities: $0

Magisterial District: Mason

Project Name: Spot Improvements - Braddock Rd/Randolph Dr

Address: Intersection of Braddock Rd at Randolph Dr

Costs

Total: $172,124

Dollar Amount

SCOPEThis project is part of the Four-Year Transportation Program and included the extension of the existing left turn lane on eastbound Braddock Road to the entrance of Thomas Jefferson High School and related items.

4YP207Project #:

Page 38

Page 39: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Division, DPWES

Construction Completion Date: 8/4/2008

Contract Number: CN08304360Task Order Number: 52

Tax Map #: 045-1

Land: $0

Design: $36,805Permits/Fees: $0

Construction: $113,459Utilities: $0

Magisterial District: Springfield

Project Name: Pedestrian Improvements - VDOT Funded Lee-Jackson Highway/Stringfellow Rd

Address: 4000 Stringfellow Road

Costs

Total: $150,264

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.

064267 PI006Project #:

Page 39

Page 40: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Roberson , JeanmarieDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Preston, ClintonDPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Rinker Design Associates (consultant)

Construction Completion Date: 6/8/2009

Contract Number: CN09304376Task Order Number: 120

Tax Map #: 068-1

Land: $0

Design: $76,547Permits/Fees: $0

Construction: $209,651Utilities: $5,910

Magisterial District: Springfield

Project Name: Braddock Rd/Rte 123 EB RTL

Address: Braddock Rd at Rt. 123 EB

Costs

Total: $292,108

Dollar Amount

SCOPEThis project provided a 450 LF extension of the existing right-turn lane from eastbound Braddock Road to Route 123.

064275Project #:

Page 40

Page 41: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Division, DPWES

Construction Completion Date: 8/4/2008

Contract Number: CN08304361Task Order Number: 53

Tax Map #: 045-2

Land: $0

Design: $37,477Permits/Fees: $0

Construction: $91,991Utilities: $0

Magisterial District: Springfield

Project Name: Pedestrian Improvements - VDOT Funded Lee-Jackson Highway/Majestic Lane

Address: Intersection of Lee-Jackson Hwy and Majestic Ln

Costs

Total: $129,468

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.

064267 PI008Project #:

Page 41

Page 42: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES

Construction Completion Date: 2/23/2009

Contract Number: CN09304373Task Order Number: 104

Tax Map #: 56-2

Land: $0

Design: $33,642Permits/Fees: $0

Construction: $74,824Utilities: $0

Magisterial District: Springfield

Project Name: Pedestrian Improvements - VDOT Funded Lee Highway/Monument Drive

Address: Monument Dr. and Lee Highway

Costs

Total: $108,466

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.

064267 PI012Project #:

Page 42

Page 43: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES

Construction Completion Date: 2/20/2009

Contract Number: CN09304375Task Order Number: 105

Tax Map #: 088-1

Land: $0

Design: $43,944Permits/Fees: $0

Construction: $67,788Utilities: $3,684

Magisterial District: Springfield

Project Name: Pedestrian Improvements - VDOT Funded Fairfax County Parkway/Old Keene Mill

Address: Fairfax Co. Pkwy at Old Keene Mill Road

Costs

Total: $115,416

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, asphalt walkway, pavement marking, and pedestrian signalization.

064267 PI023Project #:

Page 43

Page 44: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES

Construction Completion Date: 1/12/2009

Contract Number: CN09304374Task Order Number: 103

Tax Map #: 65-3

Land: $0

Design: $47,211Permits/Fees: $0

Construction: $125,738Utilities: $0

Magisterial District: Sully

Project Name: Pedestrian Improvements - VDOT Funded Centreville Road/Compton Road

Address: Centreville Road and Compton Road

Costs

Total: $172,949

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, concrete sidewalk, pavement marking, and pedestrian signalization.

064267 PI015Project #:

Page 44

Page 45: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 304Fund Title: Transportation Improvements

DPWES Project Manager: Hojatzadeh, MaxDPWES Construction Manager: Lim, Sam

Constructed By: Asburn Contracting Corporation (contractor)Designed By: Hojatzadeh, Max, Planning & Design Div., DPWES

Construction Completion Date: 8/4/2008

Contract Number: CN08304363Task Order Number: 55

Tax Map #: 065-3

Land: $0

Design: $47,368Permits/Fees: $0

Construction: $97,750Utilities: $0

Magisterial District: Sully

Project Name: Pedestrian Improvements - VDOT Funded Centreville Road/Green Trails Blvd.

Address: Centreville Rd and Green Trails Blvd

Costs

Total: $145,118

Dollar Amount

SCOPEPedestrian safety improvements including curb ramps, sidewalk, pavement marking, and pedestrian signalization.

064267 PI016Project #:

Page 45

Page 46: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 307Fund Title: Sidewalk Construction

DPWES Project Manager: Huang, Ta-EnDPWES Construction Manager: Rayyan, Yousef

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Huang, Ta-En, Maintenance and Stormwater Management Div.

Construction Completion Date: 7/30/2008

Contract Number: CN08004307Task Order Number: 78

Tax Map #: 082-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $44,950Utilities: $0

Magisterial District: Lee

Project Name: Clermont Subdivision Trail Project, Phase I

Address: 5623 Clermont Drive

Costs

Total: $44,950

Dollar Amount

SCOPEConstruction of approximately 1,700 LF of asphalt trail and 4 curb ramps.

X00407Project #:

Page 46

Page 47: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 311Fund Title: County Bond Construction

DPWES Project Manager: Ogurcak, ToniDPWES Construction Manager: Foelsch, RickDPWES Right-of-Way Agent: Buckley, Beth

Constructed By: Falls Church Construction Corp. (contractor)Designed By: Cole & Denny, Inc. (consultant)

Construction Completion Date: 10/23/2008

Contract Number: CN06311001Task Order Number: N/A

Tax Map #: 055-4

Land: $14,570

Design: $1,077,922Permits/Fees: $61,259

Construction: $3,519,832Utilities: $54,513

Magisterial District: Springfield

Project Name: Girls Probation House

Address: 12720 Lee Highway

Costs

Total: $4,728,096

Dollar Amount

SCOPEThis building is approximately 11,500 SF and includes offices, classrooms, meeting/multipurpose rooms, & recreation and housing facilities for a maximum of 12 residents. The project included approximately 34 parking spaces & outdoor recreation.

04A001Project #:

Page 47

Page 48: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 311Fund Title: County Bond Construction

DPWES Project Manager: Lepe, TeresaDPWES Construction Manager: Houde, HankDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Harper, Greg

Constructed By: Dustin Construction (contractor)Designed By: Baker and Associates (consultant)

Construction Completion Date: 10/15/2008

Contract Number: CN05311063Task Order Number: N/A

Tax Map #: 55-2

Land: $7,512,634

Design: $2,703,328Permits/Fees: $149,070

Construction: $37,447,284Utilities: $545,266

Magisterial District: Springfield

Project Name: West Ox Bus Operation Center

Address: 4950/4960 Alliance Drive

Costs

Total: $48,357,582

Dollar Amount

SCOPEThis facility is approximately 85,000 SF and consists of three major buildings: Admin/Operations, Maintenance Bldg. & Service/Fuel & Wash. The facility is shared by the Fairfax County Dept. of Transportation Connector and WMATA Metrobus operations.

88A002Project #:

Page 48

Page 49: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 312Fund Title: Public Safety Construction

DPWES Project Manager: Reed, Bob/Roberts. FrankDPWES Construction Manager: Fegan, Mike/Loomba, Krishna

Constructed By: Falls Church Construction Corp. (contractor)Designed By: Gauthier, Alvarado & Associates (consultant)

Construction Completion Date: 2/27/2009

Contract Number: CN07312190Task Order Number: N/A

Tax Map #: 55-2

Land: $0

Design: $909,337Permits/Fees: $56,326

Construction: $8,575,890Utilities: $28,320

Magisterial District: Springfield

Project Name: West Ox Road Complex - VDOT West Parcel Maintenance Facility

Address: 12700 Alliance Court

Costs

Total: $9,569,873

Dollar Amount

SCOPEThis project was funded by, and built for VDOT and consisted of administration & vehicle maintenance buildings, salt domes with conveyor system, & equipment structures for housing tailgate racks & spreader equipment.

009211 VDOTProject #:

Page 49

Page 50: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 312Fund Title: Public Safety Construction

DPWES Project Manager: Malayeri, HosseinDPWES Construction Manager: Reed, BobDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Harper, Greg

Constructed By: Manhattan Construction (contractor)Designed By: HOK (consultant)

Construction Completion Date: 7/30/2008

Contract Number: CN06312187Task Order Number: N/A

Tax Map #: 55-2

Land: $5,766,000

Design: $7,702,000Permits/Fees: $304,700

Construction: $80,466,330Utilities: $1,283,100

Magisterial District: Springfield

Project Name: McConnell Public Safety & Transportation Operations Center

Address: 4890 Alliance Drive

Costs

Total: $95,522,130

Dollar Amount

SCOPEState-of-the-art 114,000 SF facility to house Dept. of Public Safety Communications, Office of Emergency Management, Emergency Operations Center, Virginia State Police Div. 7 dispatchers, & VDOT Traffic Management Center.

009211Project #:

Page 50

Page 51: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 315Fund Title: Commercial Revitalization Program

DPWES Project Manager: Roberson, JeanmarieDPWES Construction Manager: Farsad, NahidDPWES Right-of-Way Agent: Barnes, DianneDPWES Surveyor: Harper, Greg

Constructed By: Tessa Construction & Tech Co., LLC (contractor)Designed By: Lewis Scully Gionet (consultant)

Construction Completion Date: 11/12/2008

Contract Number: CN07315040Task Order Number: N/A

Tax Map #: 30-2

Land: $29,957

Design: $95,950Permits/Fees: $0

Construction: $531,230Utilities: $3,398

Magisterial District: Dranesville

Project Name: Commercial Revitalization Prog./ McLean Streetscape Demonstration Project Ph. II

Address: Chain Bridge Road from Westmoreland to Cedar

Costs

Total: $660,535

Dollar Amount

SCOPEInstallation of 900 LF of paver sidewalk, raised median, drainage improvements, striping, landscaping, and other related items.

008912 00001Project #:

Page 51

Page 52: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, BillDPWES Construction Manager: Murray, Jonathan

Constructed By: Maintenance and Stormwater Management Division, DPWESDesigned By: GKY & Associates (consultant)

Construction Completion Date: 8/15/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 068-2

Land: $0

Design: $2,400Permits/Fees: $0

Construction: $13,654Utilities: $0

Magisterial District: Braddock

Project Name: Emergency Watershed Projects/ Tapestry Drive (4602)

Address: 4602 Tapestry Drive

Costs

Total: $16,054

Dollar Amount

SCOPEAn overland relief swale was constructed to direct surface flow away from the house to minimize the house flooding potential. A yard inlet was improved by adding a second throat opening increasing flow into the underground storm drain system.

FX8000 PC007Project #:

Page 52

Page 53: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Kumar, DipmaniDPWES Construction Manager: McCorkle, LisaDPWES Right-of-Way Agent: Coleman, MichaelDPWES Surveyor: Strecker, Matthias

Constructed By: Angler Environmental (contractor)Designed By: A. Morton Thomas & Associates (consultant)

Construction Completion Date: 4/11/2009

Contract Number: CN08318083Task Order Number: N/A

Tax Map #: 078-1

Land: $18,709

Design: $466,733Permits/Fees: $38,057

Construction: $1,694,364Utilities: $273,386

Magisterial District: Braddock

Project Name: Dam Safety Projects Dam Site 4 (Lake Royal)

Address: At the end of Starboard Drive - cul-de-sac

Costs

Total: $2,491,249

Dollar Amount

SCOPEThis project entailed a widening, realignment, and armoring of an existing earthen auxiliary spillway and raising the height of the training dikes.

FX4000 PC010Project #:

Page 53

Page 54: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rayyan, Yousef

DPWES Surveyor: Simpson, David

Constructed By: Environmental Quality Resource, Inc. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 6/5/2009

Contract Number: CN08318124Task Order Number: 5

Tax Map #: 070-1

Land: $0

Design: $28,206Permits/Fees: $0

Construction: $20,596Utilities: $3,210

Magisterial District: Braddock

Project Name: Accotink Creek Watershed Projects/ Duncan Drive Construction

Address: 4318 Duncan Drive

Costs

Total: $52,012

Dollar Amount

SCOPEProvide overland relief and structural improvements for residential flood mitigation.

AC8000 AC008Project #:

Page 54

Page 55: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 7/31/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 069-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $4,198Utilities: $0

Magisterial District: Braddock

Project Name: Major Storm Drainage Maintenance/ McFarland/Nash

Address: 4911 & 4930 McFarland Drive

Costs

Total: $4,198

Dollar Amount

SCOPETwo yard inlets were modified to increase inflow capacity. A berm was also constructed to direct surface water into the yard inlet minimizing house flooding potential.

FX6000 FX005Project #:

Page 55

Page 56: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management Program

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 2/1/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 077-2

Land: $0

Design: $0Permits/Fees: $0

Construction: $10,678Utilities: $0

Magisterial District: Braddock

Project Name: Major Storm Drainage Maintenance/ Wye Oak Commons Ci (12224)

Address: 12224 Wye Oak Commons Ci

Costs

Total: $10,678

Dollar Amount

SCOPEProject included lowering and replacing an existing one-throated yard inlet with a two-throated yard inlet to capture more surface drainage minimizing house flooding potential.

FX6000 FX005Project #:

Page 56

Page 57: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, Bill & Tucker, ValerieDPWES Construction Manager: Cameron, Tom & Kerns, Bobby

Constructed By: Video Pipe Services & E.E. Lyons (contractors)Designed By: Malcolm Pirnie (consultant)

Construction Completion Date: 6/30/2009

Contract Number: CN082903/CN0629002Task Order Number: 9,10,11,13,14,15,17,18,19

Tax Map #:

Land: $0

Design: $45,000Permits/Fees: $0

Construction: $655,143Utilities: $0

Magisterial District: Countywide

Project Name: Storm Sewer Pipe Rehabilitation and Lining

Address: Countywide

Costs

Total: $700,143

Dollar Amount

SCOPEApproximately 12,160 linear feet of the County's stormwater conveyance system was rehabilitated or lined. Liners were installed in deteriorated storm pipe and pipe joints were repaired and sealed.

FX6000-Project #:

Page 57

Page 58: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Lacquement, DonDPWES Construction Manager: Lacquement, Don

Constructed By: High Sierra (contractor)Designed By: Hagemeyer (consultant)

Construction Completion Date: 9/1/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: Countywide

Land: $0

Design: $19,200Permits/Fees: $0

Construction: $140,800Utilities: $0

Magisterial District: Countywide

Project Name: Dam Safety Projects/ Flood Response, Monitoring, and Signalization System

Address: Countywide

Costs

Total: $160,000

Dollar Amount

SCOPEThis project included the installation of automated water level gauges at 9 locations throughout the County including 7 high hazard dams, Huntington, & New Alexandria. The gauge readings improve flood potential forecasting & emerging response activity.

FX4000 FX001Project #:

Page 58

Page 59: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Qureshi, MannanDPWES Right-of-Way Agent: Knutsson, RobertDPWES Surveyor: Simpson, David

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Syed, Shahid, Stormwater Planning Division, DPWES

Construction Completion Date: 1/16/2009

Contract Number: CN09318126Task Order Number: 106

Tax Map #: 031-2

Land: $890,619

Design: $27,678Permits/Fees: $0

Construction: $49,140Utilities: $0

Magisterial District: Dranesville

Project Name: Pimmit Run Watershed Projects/ Woodacre Drive

Address: 1447 Woodacre Drive

Costs

Total: $967,437

Dollar Amount

SCOPEFlood mitigation of 1447 Woodacre Drive by acquiring the property, demolishing the house and raising the grades for future building pad to a 100-year elevation.

PM8000 PM003Project #:

Page 59

Page 60: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom

DPWES Surveyor: Harper, Greg

Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 5/31/2009

Contract Number: CN09318144Task Order Number: 7

Tax Map #: 019-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $49,694Utilities: $0

Magisterial District: Dranesville

Project Name: Infrastructure Replacement Program/ Atwood Road

Address: 9501 Atwood Road

Costs

Total: $49,694

Dollar Amount

SCOPEReplaced 180 feet of blocked dilapidated storm sewer pipe and added a drop structure to avoid repeated structure blockages.

FX6000 FX007Project #:

Page 60

Page 61: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, BillDPWES Construction Manager: Cameron, Tom

Constructed By: E.E. Lyons (contractor)Designed By: Schell, Bill, Maintenance & Stormwater Management Div.

Construction Completion Date: 5/26/2009

Contract Number: CN09318161Task Order Number: 15

Tax Map #: 030-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $18,164Utilities: $0

Magisterial District: Dranesville

Project Name: Infrastructure Replacement Program/ Laughlin Ave.

Address: 1514 Laughlin Avenue

Costs

Total: $18,164

Dollar Amount

SCOPEInadequate storm drainage pipes were removed and replaced with pipes which were larger in size. The additional capacity will help to minimize house and yard flooding.

FX6000 FX007Project #:

Page 61

Page 62: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, BillDPWES Construction Manager: Kolony, Drew

Constructed By: Apex (contractor)Designed By: GKY & Associates (consultant)

Construction Completion Date: 8/31/2008

Contract Number: N/ATask Order Number: 30

Tax Map #: 030-1

Land: $0

Design: $2,400Permits/Fees: $0

Construction: $27,773Utilities: $0

Magisterial District: Dranesville

Project Name: Emergency Watershed Projects/ Scotts Run Road

Address: 1310 Scotts Run Rd

Costs

Total: $30,173

Dollar Amount

SCOPEApproximately 200 feet of channel was dredged to get positive flow from a storm sewer system to the receiving stream. This project was constructed to minimize house and road flooding.

FX8000 SC001Project #:

Page 62

Page 63: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Murray, Jonathan

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 10/21/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 012-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $2,345Utilities: $0

Magisterial District: Hunter Mill

Project Name: Emergency Watershed Projects/ Westhills Lane (1324-1326)

Address: 1324 Westhills Lane

Costs

Total: $2,345

Dollar Amount

SCOPEAn 80 foot overland relief swale was constructed to direct surface water through the side yard to the street to minimize the risk of house flooding.

FX8000 DF008Project #:

Page 63

Page 64: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Snyder, Dave

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Snyder, Dave, Maintenance & Stormwater Management Div.

Construction Completion Date: 7/10/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 025-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $14,526Utilities: $0

Magisterial District: Hunter Mill

Project Name: Facility Major Maintenance/ Centreville/Old Centreville

Address: Centreville Road/Old Centreville Road

Costs

Total: $14,526

Dollar Amount

SCOPEThe project included sediment removal from the low flow control and ditches in order to improve pond performance. Wetland plant growth will further enhance water quality.

FX5000 FX006Project #:

Page 64

Page 65: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, BillDPWES Construction Manager: Pope, Billy

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Schell, Bill, Maintenance & Stormwater Management Div.

Construction Completion Date: 3/31/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 026-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $10,885Utilities: $0

Magisterial District: Hunter Mill

Project Name: Major Storm Drainage Maintenance/ Colts Neck Road

Address: Glade Drive/Colts Neck Road

Costs

Total: $10,885

Dollar Amount

SCOPEThe outfall drop structure was modified and a trash rack was installed to address safety issues.

FX6000 FX005Project #:

Page 65

Page 66: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Qamar, TabassumDPWES Construction Manager: Stewart, HeatherDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg

Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Wilbur Smith & Associates (consultant)

Construction Completion Date: 5/7/2009

Contract Number: CN09318129Task Order Number: 3

Tax Map #: 091-3

Land: $4,084

Design: $49,715Permits/Fees: $0

Construction: $79,304Utilities: $1,838

Magisterial District: Lee

Project Name: Dam Safety Projects/ Crestleigh PD1, 0765DP

Address: 7500 Block Beulah Street

Costs

Total: $134,941

Dollar Amount

SCOPEThe improvements included stabilizing the pond walls with gabion baskets and rip rap; increasing the pond volume; improving the outflow through the top of riser trash rack; and removal of trees from the embankment and restoration.

FX4000 LH001Project #:

Page 66

Page 67: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rayyan, Yousef

DPWES Surveyor: Simpson, David

Constructed By: Environmental Quality Resources,LLC (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 6/1/2009

Contract Number: CN08318085Task Order Number: 4

Tax Map #: 080-2

Land: $0

Design: $35,655Permits/Fees: $0

Construction: $37,153Utilities: $4,120

Magisterial District: Lee

Project Name: Cameron Run Watershed Projects/ Cabin John Road

Address: 6915 Cabin John Road

Costs

Total: $76,928

Dollar Amount

SCOPEProvide overland relief and structural improvements for residential flood mitigation.

CA8000 CA032Project #:

Page 67

Page 68: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rhame, Donna

DPWES Surveyor: Perry, Michael

Constructed By: Cephas Contracting Inc. (contractor)Designed By: Bawcombe, Nathanial & Rhame, Donna, SWPD, DPWES

Construction Completion Date: 12/12/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 091-4

Land: $0

Design: $574Permits/Fees: $344

Construction: $32,696Utilities: $0

Magisterial District: Lee

Project Name: Kingstowne Monitoring Telegraph Road (7137 Demolition)

Address: 7137 Telegraph Road

Costs

Total: $33,614

Dollar Amount

SCOPEDemolished blighted structure and re-vegetated the Resource Protection Area on newly acquired Board of Supervisors' property.

DC8000 DC008Project #:

Page 68

Page 69: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, BillDPWES Construction Manager: McCorkle, LisaDPWES Right-of-Way Agent: Ratliff, JamesDPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Malcolm Pirnie (consultant)

Construction Completion Date: 10/8/2008

Contract Number: CN08318121Task Order Number: 73

Tax Map #: 082-4

Land: $0

Design: $85,383Permits/Fees: $0

Construction: $400,000Utilities: $0

Magisterial District: Lee

Project Name: Infrastructure Replacement Program/ Pikes Branch Infrastructure Replacement

Address: Telegraph Rd/Florence Lane

Costs

Total: $485,383

Dollar Amount

SCOPERepair and replacement of the existing timber retaining wall and stabilization of 300 LF of stream bed; due to severe erosion along the Pikes Branch and undermining of the existing timber walls.

FX6000 CA010Project #:

Page 69

Page 70: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Gharavi, Mo

DPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting, Inc. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 1/14/2009

Contract Number: CN08318013Task Order Number: 86

Tax Map #: 082-3

Land: $3,891

Design: $56,048Permits/Fees: $0

Construction: $58,160Utilities: $3,083

Magisterial District: Lee

Project Name: Cameron Run Watershed Projects/ Thornwood Drive (6208)

Address: 6208 Thornwood Drive

Costs

Total: $121,182

Dollar Amount

SCOPEInstallation of drainage structures, pipes, grading for positive drainage, driveway replacement, and site restoration.

CA8000 CA028Project #:

Page 70

Page 71: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pistore, JustinDPWES Construction Manager: Murray, Jonathan

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Pistore, Justin, Stormwater Planning Division, DPWES

Construction Completion Date: 10/7/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 101-2

Land: $0

Design: $0Permits/Fees: $0

Construction: $3,245Utilities: $1,067

Magisterial District: Lee

Project Name: Little Hunting Creek Watershed Projects Seven Woods Dr Outfall Improvement

Address: 7950 Seven Woods Drive

Costs

Total: $4,312

Dollar Amount

SCOPEImprovement of an existing stormwater outfall, outfall channel, Resource Protection Area, water quality through the installation of energy dissipation structures, channel restoration, and native vegetation.

LH8000 LH021Project #:

Page 71

Page 72: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Chang, MartinDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Preston, ClintonDPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 2/23/2009

Contract Number: CN08318080Task Order Number: 116

Tax Map #: 072-1

Land: $6,093

Design: $62,788Permits/Fees: $0

Construction: $99,225Utilities: $1,528

Magisterial District: Mason

Project Name: Cameron Run Watershed Projects/ Pinecrest Golf Course

Address: 6600 Little River Turnpike

Costs

Total: $169,634

Dollar Amount

SCOPEConstruction of two bio-retention facilities. The new facilities will filter a portion of the runoff from the parking lot of the golf course and area adjacent to Little River Turnpike.

CA8000 CA009Project #:

Page 72

Page 73: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Barnes, DianneDPWES Surveyor: Simpson, David

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 2/20/2009

Contract Number: CN07318034Task Order Number: 118

Tax Map #: 061-1

Land: $314

Design: $46,871Permits/Fees: $0

Construction: $48,123Utilities: $4,425

Magisterial District: Mason

Project Name: Cameron Run Watershed Projects/ Valley Lane (3143) Construction

Address: 3143 Valley Lane

Costs

Total: $99,733

Dollar Amount

SCOPEProvide residential flood mitigation with structural improvements.

CA8000 CA024Project #:

Page 73

Page 74: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: Murray, JonathanDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Jensen, Chris

Constructed By: Maintenance & Stormwater Management Div., DPWESDesigned By: DPWES and Northern Virginia Soil & Water Conservation District

Construction Completion Date: 5/21/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 061-4

Land: $9,658

Design: $24,607Permits/Fees: $0

Construction: $41,284Utilities: $1,873

Magisterial District: Mason

Project Name: Cameron Run Watershed Projects Center Lane

Address: 5713 Center Lane

Costs

Total: $77,422

Dollar Amount

SCOPEProject included construction of bioretention facility, site grading, and reduction of impervious area to improve stormwater runoff and provide water quality.

CA8000 CA004Project #:

Page 74

Page 75: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Kumar, DipmaniDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Coleman, MichaelDPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Wilbur Smith & Associates (consultant)

Construction Completion Date: 8/25/2008

Contract Number: CN08318125Task Order Number: 77

Tax Map #: 080-2

Land: $4,857

Design: $37,654Permits/Fees: $0

Construction: $32,806Utilities: $3,312

Magisterial District: Mason

Project Name: Dam Safety Projects/ Fairfax Co Fire Station 26

Address: 5316 Carolina Place

Costs

Total: $78,629

Dollar Amount

SCOPEProvide a 510 square-foot bioretention filter retrofit to replace an infiltration trench. The filter will provide water quality treatment for a portion of the Fire Station #26 facility.

FX4000 CA003Project #:

Page 75

Page 76: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Chang, MartinDPWES Construction Manager: Qureshi, MannanDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Harper, Greg

Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Michael Baker Jr., Inc. (consultant)

Construction Completion Date: 5/22/2009

Contract Number: CN08318115Task Order Number: 7

Tax Map #: 060-4

Land: $0

Design: $32,724Permits/Fees: $0

Construction: $163,885Utilities: $0

Magisterial District: Mason

Project Name: Storm Drainage Improvements & Innovation/ Dearborn Dr Storm Drainage Project

Address: 6611 Dearborn Drive

Costs

Total: $196,609

Dollar Amount

SCOPEWork included restoring the species in Resource Protection Area by removing the invasive plants and replanting with native vegetation.

FX1000 CA002Project #:

Page 76

Page 77: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Murray, Jonathan

DPWES Surveyor: McEntire, Vickie

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 12/10/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 060-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $18,085Utilities: $2,352

Magisterial District: Mason

Project Name: Emergency Watershed Projects/ Woodland Road (4005) Phase I

Address: 4005 Woodland Road

Costs

Total: $20,437

Dollar Amount

SCOPEThe drainage channel was resized and realigned to convey the 100-yr storm away from the dwelling. This project was constructed to minimize house flooding potential.

FX8000 AC009Project #:

Page 77

Page 78: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom

Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 8/15/2008

Contract Number: CN09318131Task Order Number: 2

Tax Map #: 050-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $83,137Utilities: $0

Magisterial District: Mason

Project Name: Infrastructure Replacement Program/ Wayne Road

Address: 3034 Wayne Road

Costs

Total: $83,137

Dollar Amount

SCOPE136 feet of deteriorated corrugated metal pipe was replaced with a 42" diameter reinforced concrete pipe and associated drainage structures were installed and replaced.

FX6000 FX007Project #:

Page 78

Page 79: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Rhame, DonnaDPWES Construction Manager: Gharavi, Mo

DPWES Surveyor: Harper, Greg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 4/16/2009

Contract Number: CN08318104Task Order Number: 112

Tax Map #: 060-3

Land: $0

Design: $40,539Permits/Fees: $0

Construction: $53,601Utilities: $2,966

Magisterial District: Mason

Project Name: Cameron Run Watershed Projects/ Kendale Road Construction

Address: 3816 Kendale Road

Costs

Total: $97,106

Dollar Amount

SCOPEProvide overland relief and structural improvements for residential flood mitigation.

CA8000 CA030Project #:

Page 79

Page 80: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Housley, Gregg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 10/6/2008

Contract Number: CN08318120Task Order Number: 84

Tax Map #: 102-1

Land: $0

Design: $22,600Permits/Fees: $0

Construction: $108,140Utilities: $0

Magisterial District: Mount Vernon

Project Name: Little Hunting Creek Watershed Projects/ Walt Whitman School Retrofit

Address: 2500 Parker's Lane

Costs

Total: $130,740

Dollar Amount

SCOPEConstruction of rain gardens, pervious pavement, and manufactured BMPs for improved water quality.

LH8000 LH006Project #:

Page 80

Page 81: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Perry, Michael

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 10/28/2008

Contract Number: CN08318119Task Order Number: 88

Tax Map #: 111-1

Land: $0

Design: $23,064Permits/Fees: $0

Construction: $41,217Utilities: $0

Magisterial District: Mount Vernon

Project Name: Little Hunting Creek Watershed Projects/ Fort Hunt Elementary School

Address: 8801 Linton Lane

Costs

Total: $64,281

Dollar Amount

SCOPEConstruction of two bio-filtration ponds and manufactured BMPs for improved water quality.

LH8000 LH006Project #:

Page 81

Page 82: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Housley, Gregg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 12/15/2008

Contract Number: CN08318118Task Order Number: 101

Tax Map #: 092-4

Land: $0

Design: $36,118Permits/Fees: $0

Construction: $88,096Utilities: $0

Magisterial District: Mount Vernon

Project Name: Little Hunting Creek Watershed Projects/ Hybla Valley Elementary School

Address: 3415 Lockheed Boulevard

Costs

Total: $124,214

Dollar Amount

SCOPEConstruction of rain gardens, pervious pavement, and manufactured BMPs for improved water quality.

LH8000 LH006Project #:

Page 82

Page 83: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Hatterick, JeffDPWES Construction Manager: Pope, Billy

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: St. Clair, Scott, Maintenance & Stormwater Management Div.

Construction Completion Date: 3/15/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 098-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $7,555Utilities: $0

Magisterial District: Mount Vernon

Project Name: Emergency Watershed Projects/ Newington Commons Road (8749)

Address: 8749 Newington Commons Road

Costs

Total: $7,555

Dollar Amount

SCOPEThis project included adding a throat and lowering an existing yard inlet to minimize the risk of house flooding.

FX8000 PC006Project #:

Page 83

Page 84: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Strecker, Mathias

Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 3/11/2009

Contract Number: CN08318085Task Order Number: 1

Tax Map #: 093-1

Land: $287

Design: $31,633Permits/Fees: $0

Construction: $55,132Utilities: $0

Magisterial District: Mount Vernon

Project Name: Little Hunting Creek Watershed Projects/ Bucknell Manor Park Retrofit

Address: 2236 Mary Baldwin Drive

Costs

Total: $87,052

Dollar Amount

SCOPERemoval of an existing concrete ditch and construction of two vegetated swales incorporating new low impact development measures for improved water quality.

LH8000 LH012Project #:

Page 84

Page 85: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pokharel, SajanDPWES Construction Manager: Rayyan, YousefDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: McEntire, Vickie

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 5/10/2009

Contract Number: CN08318084Task Order Number: 5

Tax Map #: 102-4

Land: $3,270

Design: $23,062Permits/Fees: $0

Construction: $65,265Utilities: $736

Magisterial District: Mount Vernon

Project Name: Little Hunting Creek Watershed Projects/ Collingwood Park Retrofit

Address: 8200 W. Boulevard Drive

Costs

Total: $92,333

Dollar Amount

SCOPEConstruction of one bio-retention filter, one soil amendment area and several strips of no-mow areas in slopes near the entrance to improve water quality as well as attenuate flows before discharging to an existing outfall.

LH8000 LH013Project #:

Page 85

Page 86: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Moffatt & Nichol/RKK (consultant)

Construction Completion Date: 6/29/2009

Contract Number: CN08318087Task Order Number: 1

Tax Map #: 098-3

Land: $3,709

Design: $94,204Permits/Fees: $0

Construction: $106,368Utilities: $4,079

Magisterial District: Mount Vernon

Project Name: Dam Safety Projects/ Southern Oaks

Address: 8300 Block Southern Oaks Court

Costs

Total: $208,360

Dollar Amount

SCOPEThe project provided for the retrofit of a stormwater detention pond and included the repair of the principal spillway, installation of new storm pipes & riser structure and establishment of permanent access for maintenance.

FX4000 PC007Project #:

Page 86

Page 87: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 3/16/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 098-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $9,499Utilities: $0

Magisterial District: Mount Vernon

Project Name: Emergency Watershed Projects/ Moline Place (8307, 8309, 8311, 8313)

Address: 8307 - 8313 Moline Place

Costs

Total: $9,499

Dollar Amount

SCOPEAdditional throat openings were constructed on two yard inlets to allow for extra capacity of stormwater into the existing storm drain system to minimize the potential of clogging and house flooding.

FX8000 PC003Project #:

Page 87

Page 88: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Schell, BillDPWES Construction Manager: Cameron, Tom

Constructed By: E.E. Lyons (contractor)Designed By: Malcolm Pirnie (consultant)

Construction Completion Date: 3/1/2009

Contract Number: CN09318130Task Order Number: 1 & 8

Tax Map #: 102-1

Land: $0

Design: $5,000Permits/Fees: $0

Construction: $10,024Utilities: $0

Magisterial District: Mount Vernon

Project Name: Infrastructure Replacement Program Paul Springs Pwky

Address: Intersection of Paul Spring Pkwy/New Orleans Dr.

Costs

Total: $15,024

Dollar Amount

SCOPERepaired and replaced two deteriorating outfall structures and associated pipe segments.

FX6000 FX007Project #:

Page 88

Page 89: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management Program

DPWES Project Manager: Schell, BillDPWES Construction Manager: Cook, Steve

Constructed By: American Contracting & Environmental Services (contractor)Designed By: Malcolm Pirnie (consultant)

Construction Completion Date: 12/1/2008

Contract Number: CN03402777Task Order Number: N/A

Tax Map #: 093-1

Land: $0

Design: $65,500Permits/Fees: $0

Construction: $132,000Utilities: $0

Magisterial District: Mount Vernon

Project Name: Watershed Projects New Alexandria Pump Station Upgrades

Address: 6500 Thirteenth St.

Costs

Total: $197,500

Dollar Amount

SCOPETo minimize the flooding potential of the New Alexandria Pump Station and to safeguard its electrical equipment, automated, and mechanical components were installed to protect the station and to control inflow/outflow gates.

BH8000 BH001Project #:

Page 89

Page 90: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Perry, Michael

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Moffatt & Nichol/RKK (consultant)

Construction Completion Date: 5/8/2009

Contract Number: CN08318088Task Order Number: 117

Tax Map #: 46-2

Land: $3,382

Design: $84,124Permits/Fees: $0

Construction: $109,714Utilities: $12,990

Magisterial District: Providence

Project Name: Dam Safety Projects/ Mill Run Crossing

Address: 3300 Block Cranbrook Court

Costs

Total: $210,210

Dollar Amount

SCOPEThis project provided for the retrofit of a stormwater detention pond, repair of a failed principal spillway, installation of a new storm pipe, & riser structure and establishment of permanent access for maintenance.

FX4000 DF007Project #:

Page 90

Page 91: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Bajere, PaulDPWES Construction Manager: Qureshi, Mannan

Constructed By: Ashburn Contracting Corp. (contractor)Designed By: Bajere, Paul, Stormwater Planning Division, DPWES

Construction Completion Date: 2/3/2009

Contract Number: CN09126001Task Order Number: 4

Tax Map #: 040-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $17,459Utilities: $7,614

Magisterial District: Providence

Project Name: Cameron Run Watershed Projects/ Falls Hill Retrofits

Address: 7315 Gordons Road

Costs

Total: $25,073

Dollar Amount

SCOPEThis project provided flood mitigation measures at 7135 Gordons Road by replacing an existing 9 foot long curb inlet top with a 18 foot curb drop inlet drop. The work also included replacing existing curb & gutter to match new curb inlet top.

CA8000 CA014Project #:

Page 91

Page 92: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Murray, Jonathan

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 6/15/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 048-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $5,602Utilities: $0

Magisterial District: Providence

Project Name: Major Storm Drainage Maintenance/ Ellenwood

Address: 2915 Everleigh Way

Costs

Total: $5,602

Dollar Amount

SCOPEWork included modifying a yard inlet by adding two throat openings and constructing a berm around the back of the structure. This work was completed to minimize house flooding potential.

FX6000 FX005Project #:

Page 92

Page 93: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Kolony, Drew

Constructed By: Apex (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 9/1/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 039-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $11,200Utilities: $0

Magisterial District: Providence

Project Name: Emergency Watershed Projects/ Bell Lane (8232)

Address: 8232 Bell Lane

Costs

Total: $11,200

Dollar Amount

SCOPERetrofit of two window wells and installation of appropriate drainage facilities to minimize house flooding potential.

FX8000 DF001Project #:

Page 93

Page 94: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tuttle, RonDPWES Construction Manager: N/A

Constructed By: Fairfax Releaf, Inc. & Virginia Deparment of Forestry (contractor)Designed By: Tuttle, Ron, Stormwater Planning Division, DPWES

Construction Completion Date: 5/9/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 050-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $0Utilities: $0

Magisterial District: Providence

Project Name: Cameron Run Watershed Projects Shrevewood ES- Phase I & II SW Retrofit

Address: 7525 Shreve Road

Costs

Total: $0

Dollar Amount

SCOPEConversion of approximately 1.5 acres of turf to native forest and meadow. Work completed by volunteers.

CA8000 CA033Project #:

Page 94

Page 95: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tuttle, RonDPWES Construction Manager: N/A

Constructed By: Waples Mill Elementary School, FCPSDesigned By: Tuttle, Ron, Stormwater Planning Division, DPWES

Construction Completion Date: 5/1/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 046-2

Land: $0

Design: $0Permits/Fees: $0

Construction: $0Utilities: $0

Magisterial District: Providence

Project Name: Difficult Run Watershed Projects Waples Mill Elementary School - Phase I & II SW

Address: 11509 Waples Mill Road

Costs

Total: $0

Dollar Amount

SCOPEAmend soil and convert approximately 1/2 acre of turf to native meadow and install bioretention basin for improved stormwater detention and water quality. Work completed by school ground operations.

DF8000 DF010Project #:

Page 95

Page 96: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Maguire, JoanDPWES Construction Manager: Weaver, John

DPWES Surveyor: Harper, Greg

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: St. Clair, Scott, Maintenance & Stormwater Management Div.

Construction Completion Date: 11/15/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 088-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $8,647Utilities: $0

Magisterial District: Springfield

Project Name: Emergency Watershed Projects/ Gavelwood Ct/9000 Block/Flood Mitigation

Address: 9010. 9012, 9014 Gavelwood Court

Costs

Total: $8,647

Dollar Amount

SCOPEA one-throated yard inlet was installed along the existing pipe system to minimize house flooding.

FX8000 PC005Project #:

Page 96

Page 97: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: Bashir, QaisDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg

Constructed By: Environmental Quality Resources, LLC (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 8/15/2008

Contract Number: CN07318042Task Order Number: 9

Tax Map #: 078-3

Land: $6,457

Design: $46,782Permits/Fees: $0

Construction: $121,002Utilities: $2,427

Magisterial District: Springfield

Project Name: Dam Safety Projects/ Cardinal Glen Sec. 2 - Phase 1

Address: 6000 Block Heathwick Court

Costs

Total: $176,668

Dollar Amount

SCOPEThis project provided for construction of an emergency spillway and establishment of a permanent access road. The Phase 1 of this project was completed in 2008 and provided for dam repairs and construction of stormwater structures.

FX4000 PC005Project #:

Page 97

Page 98: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: Gharavi, MoDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Harper, Greg

Constructed By: APEX Companies, LLC (contractor)Designed By: Moffatt & Nichol/RKK (consultant)

Construction Completion Date: 2/24/2009

Contract Number: CN08318086Task Order Number: 14

Tax Map #: 76-1

Land: $172

Design: $59,159Permits/Fees: $0

Construction: $70,505Utilities: $1,177

Magisterial District: Springfield

Project Name: Dam Safety Projects/ Colchester Hills

Address: 12131 Brantleigh Place

Costs

Total: $131,013

Dollar Amount

SCOPEThis project provided for the repair of the failed dam embankment, replacement of the principal spillway and outfall pipes, removal of debris and sediment, and planting of trees and shrubs.

FX4000 PH001Project #:

Page 98

Page 99: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Sprow, Pete

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.

Construction Completion Date: 9/24/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 065-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $18,241Utilities: $0

Magisterial District: Springfield

Project Name: Dam Safety Projects/ Little Rocky Run Sediment Removal & Wetland Retrofit

Address: 13821 South Springs Drive

Costs

Total: $18,241

Dollar Amount

SCOPEThe project included sediment removal in order to improve pond performance and a wetland plant seed mix to enhance water quality.

FX4000 LR003Project #:

Page 99

Page 100: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Sprow, Pete

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.

Construction Completion Date: 4/1/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 098-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $52,649Utilities: $0

Magisterial District: Springfield

Project Name: Dam Safety Projects/ Whisperwood Pond 2 Sediment Removal and Retrofit

Address: 8929 Mountain Ash Drive

Costs

Total: $52,649

Dollar Amount

SCOPEWork included removal of sediment and debris, as well as retrofitting a trash rack, wing walls, and apron which will improve pond performance.

FX4000 PC015Project #:

Page 100

Page 101: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: McCorkle, LisaDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg

Constructed By: APEX Companies, LLC (contractor)Designed By: Bowman Consulting Group (consultant)

Construction Completion Date: 5/8/2009

Contract Number: CN07318042Task Order Number: 9

Tax Map #: 078-3

Land: $3,229

Design: $46,782Permits/Fees: $0

Construction: $147,299Utilities: $2,427

Magisterial District: Springfield

Project Name: Dam Safety Projects/ Cardinal Glen Sec. 2 - Phase II

Address: 6000 Block Heathwick Court

Costs

Total: $199,736

Dollar Amount

SCOPEThis project provided for dam repair and included the construction of a stormwater riser structure, outfall pipe, open water channel, grading, and site restoration.

FX4000 PC005Project #:

Page 101

Page 102: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom

DPWES Surveyor: Harper, Greg

Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 10/25/2008

Contract Number: N/ATask Order Number: 3

Tax Map #: 089-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $52,394Utilities: $0

Magisterial District: Springfield

Project Name: Infrastructure Replacement Program/ Holford Lane

Address: 6700 Holford Lane

Costs

Total: $52,394

Dollar Amount

SCOPEThis project included removing and replacing approximately 152 linear feet of storm pipe, replacing the end wall, installing a drop structure, and stabilizing and restoring the adjacent easement area.

FX6000 FX007Project #:

Page 102

Page 103: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Pistore, JustinDPWES Construction Manager: Bashir, Qais

DPWES Surveyor: Harper, Greg

Constructed By: Angler Environmental (contractor)Designed By: Michael Baker Jr., Inc. (consultant)

Construction Completion Date: 4/30/2009

Contract Number: CN08318107Task Order Number: N/A

Tax Map #: 078-4

Land: $172

Design: $100,283Permits/Fees: $0

Construction: $197,728Utilities: $0

Magisterial District: Springfield

Project Name: Pohick Creek Watershed Projects/ Poplar Spring Court

Address: 9300 Block Poplar Spring Court

Costs

Total: $298,183

Dollar Amount

SCOPEProvide 600 LF of stream restoration by establishing a stable stream morphology through stabilizing bank grades, installing natural channel design with varying rock structures, and restoring the riparian area through establishment of native plantings.

PC8000 PC004Project #:

Page 103

Page 104: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Markey, Richard

Constructed By: APEX (contractor)Designed By: Markey, Richard, Maintenance & Stormwater Management Div.

Construction Completion Date: 12/23/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 065-4

Land: $0

Design: $2,399Permits/Fees: $0

Construction: $110,113Utilities: $0

Magisterial District: Springfield

Project Name: Dam Safety Projects/ Compton Heights Sediment Removal and Retrofit

Address: 6848 Compton Heights Circle

Costs

Total: $112,512

Dollar Amount

SCOPERemoval of 300 cubic yards of sediment from the pond floor and adjacent micropools restoring the pond to its original capacity. A gabion weir sediment forebay was also installed to improve sediment management.

FX4000 LR002Project #:

Page 104

Page 105: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Weaver, John

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 7/25/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 078-04

Land: $0

Design: $0Permits/Fees: $0

Construction: $3,431Utilities: $0

Magisterial District: Springfield

Project Name: Major Storm Drainage Maintenance/ 6244 Garretson St

Address: 6244 Garretson Street

Costs

Total: $3,431

Dollar Amount

SCOPEA manhole structure was modified to a two-throated yard inlet to minimize house and yard flooding.

FX6000 FX005Project #:

Page 105

Page 106: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Rossi, Dennis

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.

Construction Completion Date: 8/6/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 045-3

Land: $0

Design: $0Permits/Fees: $0

Construction: $3,306Utilities: $0

Magisterial District: Sully

Project Name: Facility Major Maintenance/ Poplar Tree Estates Sec 2 Trash Rack Retrofit

Address: Poplar Tree Rd

Costs

Total: $3,306

Dollar Amount

SCOPEFabrication and construction of a new trash rack to minimize future blockages and potential house flooding. The redesign was so successful that the pond did not block during Tropical Storm Hanna in September 2008.

FX5000 FX006Project #:

Page 106

Page 107: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Meyers, MattDPWES Construction Manager: Lim, VannakDPWES Right-of-Way Agent: Finnell, RichardDPWES Surveyor: Housley, Gregg

Constructed By: APEX Companies, LLC (contractor)Designed By: Moffatt & Nichol/RKK (consultant)

Construction Completion Date: 2/10/2009

Contract Number: CN08318089Task Order Number: 15

Tax Map #: 046-1

Land: $4,804

Design: $97,293Permits/Fees: $0

Construction: $119,010Utilities: $1,132

Magisterial District: Sully

Project Name: Dam Safety Projects/ Fox Vale Sec 6

Address: 11900 Block Vale Road

Costs

Total: $222,239

Dollar Amount

SCOPEThis project increased the pond capacity and included the construction of a riser structure, storm drain pipes, rip rap, landscaping, and other related items.

FX4000 DF008Project #:

Page 107

Page 108: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Snyder, Dave

Constructed By: Maintenance and Stormwater Management Division, DPWESDesigned By: Markey, Richard, Maintenance & Stormwater Management Div.

Construction Completion Date: 1/5/2009

Contract Number: N/ATask Order Number: N/A

Tax Map #: 053-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $16,796Utilities: $0

Magisterial District: Sully

Project Name: Facility Major Maintenance/ Pleasant Hill Sediment Removal and Retrofit

Address: 15389 Martins Hundred Drive

Costs

Total: $16,796

Dollar Amount

SCOPEThe project included the retrofit of a new headwall and trash rack improving the performance of the facility.

FX5000 FX005Project #:

Page 108

Page 109: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Markey, RichardDPWES Construction Manager: Snyder, Dave

Constructed By: Maintenance & Stormwater Management Division, DPWESDesigned By: Markey. Richard, Maintenance & Stormwater Management Div.

Construction Completion Date: 8/8/2008

Contract Number: N/ATask Order Number: N/A

Tax Map #: 045-1

Land: $0

Design: $0Permits/Fees: $0

Construction: $30,250Utilities: $0

Magisterial District: Sully

Project Name: Dam Safety Projs/ Chantilly Library Sediment Removal & Wetland Retrofit

Address: 4000 Stringfellow Road

Costs

Total: $30,250

Dollar Amount

SCOPEThe project included sediment removal in order to improve pond performance and a wetland plant seed mix to enhance water quality.

FX4000 CU001Project #:

Page 109

Page 110: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 318Fund Title: Stormwater Management

DPWES Project Manager: Tucker, ValerieDPWES Construction Manager: Cameron, Tom

Constructed By: E.E. Lyons (contractor)Designed By: Tucker, Valerie, Maintenance & Stormwater Management Div.

Construction Completion Date: 6/12/2009

Contract Number: CN09318163Task Order Number: 16

Tax Map #: 053-4

Land: $0

Design: $0Permits/Fees: $0

Construction: $34,111Utilities: $0

Magisterial District: Sully

Project Name: Infrastructure Maintenance Program/ Ampstead Court

Address: 14932 Ampstead Court

Costs

Total: $34,111

Dollar Amount

SCOPEA curb inlet was added and an overland relief channel was constructed to minimize house flooding.

FX6000 FX007Project #:

Page 110

Page 111: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 340Fund Title: Housing Assistance Program

DPWES Project Manager: Ayers, RobertDPWES Construction Manager: Minnix, W. ToddDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: McMillen, Barry

Constructed By: Tessa Construction & Tech Co. (contractor)Designed By: Rinker Design Associates (consultant)

Construction Completion Date: 8/29/2008

Contract Number: CP06380011Task Order Number: N/A

Tax Map #: 083-3

Land: $99,756

Design: $143,054Permits/Fees: $0

Construction: $1,697,915Utilities: $0

Magisterial District: Lee

Project Name: Jefferson Manor IIB

Address: 2800 Fort Drive

Costs

Total: $1,940,725

Dollar Amount

SCOPEReconstruction of approx. 1500' of Fort Drive, from Edgehill Drive to North Kings Highway. It included a new 12" watermain, storm drainage system, curb & gutter, sidewalks, concrete driveway entrances, driveways, retaining walls, & stairways.

013918Project #:

Page 111

Page 112: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 370Fund Title: Park Authority Bond Construction

DPWES Project Manager: Ogurcak, ToniDPWES Construction Manager: Foelsch, Rick

Constructed By: Falls Church Construction Corp. (contractor)Designed By: Bowie Gridley Architects (consultant)

Construction Completion Date: 8/7/2008

Contract Number: CN0651035-01Task Order Number: N/A

Tax Map #: 97-1

Land: $261,424

Design: $130,484Permits/Fees: $0

Construction: $2,419,489Utilities: $36,455

Magisterial District: Springfield

Project Name: South Run RECenter - Fitness Addition

Address: 7550 Reservation Drive

Costs

Total: $2,847,852

Dollar Amount

SCOPEThis project consisted of a two story, 7,000 SF addition to the existing South Run District Park RECenter, a 65 space parking lot with lighting and a new stormwater detention pond. The addition provides a program room and fitness center.

476204Project #:

Page 112

Page 113: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 402Fund Title: Wastewater Treatment Revenue Fund

DPWES Project Manager: Flowers, RandallDPWES Construction Manager: Knizner, AnthonyDPWES Right-of-Way Agent: Buckley, BethDPWES Surveyor: Murdoch, Guy

Constructed By: Anchor Construction Corp. (contractor)Designed By: Dewberry & Davis (consultant)

Construction Completion Date: 8/28/2008

Contract Number: CN03402780Task Order Number: N/A

Tax Map #: 21-4

Land: $0

Design: $492,719Permits/Fees: $300

Construction: $5,092,405Utilities: $0

Magisterial District: Dranesville

Project Name: River Oaks Sanitary Sewer Extension & Improvement

Address: River Oaks Subdivision

Costs

Total: $5,585,424

Dollar Amount

SCOPEInstallation of approximately 3,200 LF of gravity sewer pipe, 19,500 LF of force main sanitary pipe, grinder pumps, water line relocation, extensive pavement, and site restoration.

X00826 E004Project #:

Page 113

Page 114: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 402Fund Title: Wastewater Treatment Revenue Fund

DPWES Project Manager: Adams, ShannaDPWES Construction Manager: Knizner, AnthonyDPWES Right-of-Way Agent: Kresge, CarolDPWES Surveyor: Housley, Gregg

Constructed By: William B. Hopke Company, Inc. (contractor)Designed By: Dewberry & Davis (consultant)

Construction Completion Date: 5/18/2009

Contract Number: CN06402007Task Order Number: N/A

Tax Map #: 037-4

Land: $0

Design: $42,665Permits/Fees: $300

Construction: $976,232Utilities: $0

Magisterial District: Hunter Mill

Project Name: Extension Project/ Stryker Avenue

Address: Stryker Avenue

Costs

Total: $1,019,197

Dollar Amount

SCOPEInstallation of 1,650 LF of gravity sanitary sewer pipe, 1,270 LF of sanitary sewer force main pipe, manholes, grinder pumps and renovations to the Little Vienna Sewage Pump Station to accommodate the additional flow resulting from this expansion.

X00826 EI02Project #:

Page 114

Page 115: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 402Fund Title: Wastewater Treatment Revenue Fund

DPWES Project Manager: Flowers, RandallDPWES Construction Manager: Nolan, Bill

Constructed By: ALPHA Construction Company (contractor)Designed By: Whitman, Requardt & Associates (consultant)

Construction Completion Date: 9/5/2008

Contract Number: CN08402002Task Order Number: N/A

Tax Map #: 102-2

Land: $0

Design: $39,637Permits/Fees: $300

Construction: $216,496Utilities: $0

Magisterial District: Mount Vernon

Project Name: Pump Station Renovation Gunston Commons & Wellington I Pump Stations

Address: 7835 Southdown Road

Costs

Total: $256,433

Dollar Amount

SCOPEInstallation of the generator and the fuel tank relocated from Gunston Commons Sewage Pumping Station on a new concrete pad with a new weatherproof enclosure, and installation of a flood gate system.

I00351 0002Project #:

Page 115

Page 116: Completed Projects FY2009

CAPITAL PROJECTS COMPLETED - FY 2009

Fund #: 402Fund Title: Wastewater Treatment Revenue Fund

DPWES Project Manager: N/ADPWES Construction Manager: Steele, TerrenceDPWES Right-of-Way Agent: Kresge, Carol

Constructed By: Flippo Construction Company Inc. (contractor)Designed By: Camp Dresser & McKee (consultant)

Construction Completion Date: 1/28/2009

Contract Number: CN08402005Task Order Number: N/A

Tax Map #: 093-2

Land: $0

Design: $351,301Permits/Fees: $300

Construction: $4,406,345Utilities: $0

Magisterial District: Mount Vernon

Project Name: Belle View Gravity Sewer Relocation

Address: Belle View Blvd/Wakefield Street

Costs

Total: $4,757,946

Dollar Amount

SCOPEConstruction of 550 LF of 12-inch sanitary sewer pipe through a 36-inch casing pipe installed with micro-tunneling and multiple new manholes. Due to high groundwater & running sand soil, a "secant pile wall" was utilitized for excavation support.

X00905Project #: