Conceptual rendering

Citizens Advisory CommitteeMarch 16, 2010

2

Genesis of the ARTIC Project

Need for the ARTIC Project

CA High-Speed Train

Demand for Metrolink & Amtrak

Anaheim centrally located

Anaheim southern terminus for the first phase of California High-Speed Rail

3

Regionally Located

4

Regional Connectivity

Transportation Modes

The ARTIC Project Site

5

ARTIC Transportation Services

Transportation ServicesMetrolinkAmtrakOCTA BusAnaheim Resort TransitLAWA Flyaway ShuttlesTaxi ServicesIntercity BusesInternational BusesTour and Charter BusesPrivate Vehicles/Parking

OCTA Bravo BRT

6

ARTIC Transportation Services

Future Transportation ServiceAnaheim Rapid Connection (ARC)

7

Site Development

Approximately 16 Acre Site

Transit center and supportive facilities

Bus / shuttle / taxi / kiss and ride

Access and street improvements

Trackwork and platforms

Parking

Public art

Conceptual site plan

8

Conceptual Site Layout

1

2

3

4

5

6

7

7

Santa Ana

River

Kate

lla

Avenue

Douglass Road

1. Intermodal Center2. Stadium Pavilion3. Plaza4. Santa Ana River Park

5. Surface Parking/Future Development6. Anaheim Stadium7. Existing Uses (separate land owner)8. Rail Platforms

Plan is subject to revision

8

SR-57

9

Conceptual Design

A Soaring Open SpaceWorld Class Transportation Hub - functional, adaptable, and

flexibleAn Iconic Design - skyline, presence, and visibilityVibrant Urban Center - pedestrian, sustainable, civic, and public

10

The ARTIC Project Interior

Progressive Design

Light-filled

Timeless

Energy efficient

LEED Platinum

Goal

11

Funding

Significant Local Funding Commitment

Conceptual site plan

Funding Source Amount (in millions)

Renewed Measure M – Project T Bond Proceeds $ 99.2

Measure M – Transit Revenue $ 44.6

2008 State Transportation Improvement Program $ 29.2

Federal Earmark $ 3.2

Federal Transit Administration $ 2.6

Total $178.8

12

Recent Activity and Upcoming Milestones

Major Project Milestones

Environmental Clearance Begins….....…………………………..............

April 2009

City of Anaheim Retained Architecture and Engineering Consultant

(A&E) and Program Management Consultant (PMC)

(Parsons Brinckerhoff/HOK, Architecture & Final

Design)…..……......Spring/Summer 2009

Environmental Clearance……………….…..…………………..................Late

2010

Architecture & Engineering Complete……..…….

…………….................Early 2011

General Contractor Procurement and Construction

Start......................Early 2011

Construction Complete – Station Operational…….…………………….......

….2013

13

Project Questions

For Project Questionswww.articinfo.com