concrete masonry site practice and workmanship guide...concrete masonry: site practice and...

28
c CONCRETE NZ - CONCRETE MASONRY - SITE PRACTICE AND WORKMANSHIP GUIIDE Concrete Masonry Site Practice and Workmanship Guide Concrete NZ www.concretenz.org.nz Concrete New Zealand July 2020

Upload: others

Post on 05-Sep-2020

11 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

c

CONCRETE NZ - CONCRETE MASONRY - SITE PRACTICE AND WORKMANSHIP GUIIDE

Concrete Masonry

Site Practice and Workmanship Guide

Concrete NZ www.concretenz.org.nz

Concrete New Zealand

July 2020

Page 2: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Concrete Masonry: Site Practice and Workmanship Guide p2

Acknowledgements

[inside cover – intentionally left blank]

Page 3: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Concrete Masonry: Site Practice and Workmanship Guide p3

Acknowledgements

This Guide was prepared by:

Ralf Kessel, Architect (NZRAB), Concrete NZ

With review assistance of:

Bowers Brothers Concrete

Mitchell Concrete

Firth Industries

The Block Shop

Viblock

Disclaimer

All information provided in this document is guidance only and in no way replaces the services

of professional consultants. No liability can be accepted by Concrete NZ for its use.

Copyright

© July 2020 Concrete NZ

PO Box 448, Wellington 6140, New Zealand

Phone 644 499 8820, email [email protected], website www.concretenz.org.nz

Extracts from NZS 4210:2001 and NZS 4229:2013 have been provided by

Standards New Zealand under licence LN001372.

Except where the Copyright Act allows, no part of this publication may

be reproduced, stored in any retrieval system in any form, or transmitted

by any means, without the prior permission in writing of Concrete NZ.

ISBN: 978-0-908956-73-9

ISBN (online): 978-0-908956-74-6

Images:

with kind permission of Bowers Brothers Concrete and Firth Industries

Page 4: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Concrete Masonry: Site Practice and Workmanship Guide p4

About this guide

This is a guide to good site practice and workmanship for concrete masonry. It is intended for

use by all members of the building team, including site supervisors and brick and block layers.

This guide:

• covers the key points for preparing and carrying out masonry work onsite

• includes extracts from relevant Standards and Codes of Practice for easy reference

• provides a handy action checklist.

High levels of workmanship and site practice should result in durable brick and blockwork that

has a consistent appearance and needs little or no maintenance during its design life.

Units, mortar, grout, rebar and other ancillary components such as beams and columns must

also be designed and specified in accordance with the New Zealand Building Code and relevant

Standards.

If you need more advice, concrete masonry manufacturers have a vested interest in the

achievement of successful masonry work and can help with all aspects of workmanship and site

practice.

Page 5: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Concrete Masonry: Site Practice and Workmanship Guide p5

Quick checklist for concrete masonry construction

This checklist summarises the key points discussed in this guide. You can copy and print it for

easy reference.

Before you start ✓

Order early from the manufacturer; check site access to a suitable storage area

Check risks are eliminated/minimised (Refer to Worksafe New Zealand’s website at www.worksafe.govt.nz for more information)

Check relevant Standards and Codes of Practice

Obtain agreement by all parties if a reference panel is required

Getting ready ✓

Check the delivery – make sure units are the correct type, number and quality

Site storage – provide adequate protection for materials onsite

Take suitable precautions if air temperature is likely to be below 5° C or above 25° C

Set to work ✓

Make sure mortar is made to specifications

Are the units laid correctly and onto a clean substrate, and are the joints tooled to the manufacturer’s requirements?

Are rebars installed to specifications and tolerances?

Does the grout have the correct properties, strength, admixtures and workability?

Are control joints placed at required locations?

Are the walls sealed for weathertightness and to mitigate against efflorescence?

Keep checking ✓

Are the walls within tolerances of NZS 4210, Table 2.2?

Is the blockwork protected when work is not proceeding?

Are the walls propped during construction against wind and earthquake loads?

Page 6: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Concrete Masonry: Site Practice and Workmanship Guide p6

Contents of this guide

Before you start p7

Check your supplies and the site

Health and safety precautions

Relevant Standards and Codes of Practice

Construct a reference panel if required

Getting ready p10

Check the delivery

Site storage

What’s the weather?

Set to work p12

Making the mortar

Laying the units and tooling

Installing rebars

Grouting

Placing control joints in the grout

Final weather seals

Keep checking p23

Check wall tolerances

Protect blockwork while not working

Temporary propping

Resources p26

Page 7: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Before you start

Concrete Masonry: Site Practice and Workmanship Guide p7

Before you start

Check your supplies and the site

One of your first tasks when starting a new

masonry project should be to consult with the

manufacturer, involving them as appropriate in

pre-contract meetings and discussions. You will

need an accurate delivery schedule for bulk

orders to help suppliers plan availability and

delivery. In particular, any specially shaped units

may be subject to lead times – early consultation

with the manufacturer is vital to avoid any

programme delays.

Another early planning step should be to earmark a suitable storage area onsite. This area

should be firm, level and well drained. It should be large enough to store the amount of

material being delivered and also have some contingency space.

Your proposed storage area should be easy to access for the expected size of delivery vehicle.

Also consider whether the material stored there will be an obstacle and/or obstruct site works

and other vehicle movements. Avoiding this also means the material is less likely to be at risk of

soiling from passing vehicles or adjacent site operations.

Health and safety precautions

Before starting work, make sure you are clear what

health and safety precautions need to be taken. You

can use a risk matrix to identify the risks and also

what precautions can be taken to eliminate or

reduce these.

Once work starts, you will need to review work on an

ongoing basis to identify any new risks that need to

be managed.

Always ensure your health and safety! Protect

yourself by use of a harness or suitable rope system

when working at height.

Page 8: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Before you start

Concrete Masonry: Site Practice and Workmanship Guide p8

Dust control measures when cutting or grinding blocks

Protect yourself and your co-workers from potential harm from dust and micro silica released

when cutting or grinding concrete blocks. Use tools which provide water to the blade system

and an on-tool extraction collector. To remove dust use H-class HEPA-filtered vacuum cleaners

in accordance with Standard AS/NZS 60335-2-691. Seal dust waste bags and place them in the

correct waste container.

Alert:

Worksafe New Zealand now enforces dust control in the immediate area when cutting blocks.

Fines are being imposed if appropriate steps are not taken to protect others working onsite. Go

to www.worksafe.govt.nz for more information and guidance on what is required.

Relevant Standards and Codes of Practice

It is important for brick and block layers to be familiar with the performance requirements of

the New Zealand Building Code (refer to www.building.govt.nz for more about Building Code

compliance) and the content of current New Zealand Standards and guidance related to

masonry work, which provide ways to meet these requirements. Key documents include:

• CCANZ CP 01 - Code of Practice for weathertight concrete and concrete masonry

construction

• NZS 4210:2001 Masonry construction: Materials and workmanship

• NZS 4229:2013 Concrete masonry buildings not requiring specific engineering design

• NZS 4230:2004 Design of reinforced concrete masonry structures (used by engineers)

• NZS 3104:2003 Specification for concrete production (provides an understanding of the

properties of mortar, grout and concrete in general).

These documents are available at Building CodeHub (https://codehub.building.govt.nz) or from

Standards New Zealand (www.standards.govt.nz).

Also see:

• NZS 3101.1&2:2006, Amendment No. 3, 2017 - Concrete structures standard

• NZS 3103:1991 Specification for sands for mortars and plasters

• NZS 3109:1997 Concrete construction

• NZS 3121:2015 Water and aggregate for concrete

• NZS 3124:1987 Specification for concrete construction for minor works

• AS/NZS 4671:2019 Steel for the reinforcement of concrete

1 AS/NZS 60335-2-69:2017 – Household and similar electrical appliances – Safety. Part 2.69: Particular

requirements for wet and dry vacuum cleaners, including power brush, for commercial use (IEC 60335-2-69 Ed

5:2016, MOD)

Page 9: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Before you start

Concrete Masonry: Site Practice and Workmanship Guide p9

Construct a reference panel if required

Constructing a reference panel of brick or blockwork onsite is a good idea before work starts,

as it provides a benchmark if any issues arise. This should be agreed by the client and all other

relevant parties (e.g. the engineer and architect). In general terms, it’s also best to sort out any

uncertainties with the parties before starting/ continuing the job.

Site reference panels are especially important for concrete brick veneer. They provide the

opportunity to identify the inherent characteristics of the concrete brick such as colour

variance, shape, size, texture, and any chips. They also illustrate the mortar joint colour and

shape. These panels are also important if architectural masonry has been requested and design

requirements for the appearance have been specified. On masonry end blocks there could also

be “core bar” cracks. A reference panel sets the general standard of workmanship and level of

expectation that can be reasonably achieved by the block layer given the specified material.

The reference panel shall show at least 1 m2 of block/ veneer face. Choose a stable and

suitable site for constructing the panel which does not obstruct any works or storage areas.

Also consider the access arrangements and ensure that the delivery vehicle can be safely

manoeuvred to the desired delivery point.

A reference or sample panel should be

agreed by the client and all other relevant

parties.

Page 10: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Getting ready

Concrete Masonry: Site Practice and Workmanship Guide p10

Getting ready

Check the delivery

Check the type and quantity

of material that is delivered

onsite against the design,

drawings, specifications and

agreements.

It’s a good idea to select a

number of concrete blocks at

random from the delivery.

Check their appearance is

reasonably consistent with

the site reference panel.

If you are not sure whether they are acceptable, ask the relevant parties as soon as possible.

Site storage

As concrete blocks and bricks can be susceptible to chipping, always take care to place packs

carefully with the forklift and avoid allowing any distortion of the pack shape to occur.

Bricks and blocks must be stored with a cover and protected from bad weather. Excessively wet

or saturated blocks are difficult to lay and may risk causing efflorescence, lime leaching and

mortar colour variation.

What’s the weather?

If the air temperature is below 5° C or above 25° C you will need to take some extra steps if you

want to start work.

Generally, masonry construction should not be carried out when it is below about 5° C without

taking precautions such as:

• heating the water used for mixing mortar

• not using any frozen materials or materials containing ice

• protecting masonry for at least 24 hours after it has been laid – you can use covers,

blankets, heated enclosures or similar to make sure the mortar can gain strength

without freezing or suffering any harmful effects from cold winds.

Page 11: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Getting ready

Concrete Masonry: Site Practice and Workmanship Guide p11

If the air temperature is more than 25° C you will also need to take precautions, such as:

• lightly dampening masonry units before laying

• keeping the mortar moist – mortar must not be spread on the wall more than two unit

lengths ahead of the units being placed

• preventing the mortar from drying so rapidly that it cannot cure properly – you can do

this by applying a very light fog spray several times during the first 24 hours after the

blocks are laid, or by taking other protective measures over the same period.

Page 12: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p12

Set to work

Making the mortar

Make sure your mortar is

made to the specifications

for the project and that its

constituents are clean and

accurately gauged. Mortar

mixes are typically specified

by volume ratios –

ingredients differ, so be sure

to use the correct mix for

the application.

Mortar generally requires a

compressive strength of 12.5

MPa unless otherwise

specified.

Table 2.1 of NZS 4210 Masonry construction: Materials and workmanship shows the mixtures

for durability classes M2 – M4.

NZS 4210 Table 2.1 – Mortar mix composition using parts by volume using hydrated lime

Durability Cement Hydrated lime Sand

M4 [Exposed/Coastal] 1 0 - 0.25 3

M3 [Exterior/Inland] 1 0.5 4.5

M2 [Interior] 1 1 6

Comment from NZS 4210:

C2.2.2.1 The workability of mortars is significantly affected by sand grading and particle

shape. For the majority of mortars it is likely that the use of an admixture or hydrated lime will

be necessary to produce the desired workability. Admixture dosage should strictly follow the

manufacturer's instructions since significant loss of strength and bond can occur through over

dosage.

Page 13: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p13

The following table gives tips for mixing mortar.

Mortar mixing tips

Safety first • Always wear eye protection and waterproof gloves when mixing mortar.

Preparing the ingredients

• Use a dry bucket to measure out the materials.

• Use cement from unopened bags – opened cement bags tend to absorb environmental humidity, which changes the water percentage of the mortar mix and can reduce its strength.

• If you are mixing by hand, prepare a mixing container with a flat, solid surface base and tall sides.

• Pre-wet the mixing container before filling it with fresh mortar.

Mixing the mortar

• Add the masonry cement, additives and sand in the appropriate amounts to your mixing container, then add water on top of the dry ingredients.

• If you are mixing by hand, fold the mortar mix from the bottom into the water and keep mixing until the water is mixed in. Next, add more water and keep mixing. Keep adding water until the mortar attains a smooth consistency.

• Stop mixing when the mortar is wet enough to slip easily off the shovel but holds its shape if you make a hollow in the mix. Mortar has attained the correct viscosity when you can make a few ledges in the mortar mix and these ledges stand up.

• Mix mortar for not less than three minutes and not more than five minutes after the last materials have been introduced into the mixer or tub.

What to watch for

• It is important to understand that once the mix starts to set it cannot be re-mixed because this will reduce the mortar's strength. Also, if too much water is added to the mix this will affect the mortar’s chemical composition, reducing its strength and potentially causing problems in the future.

• Mortar, like concrete, is only good for 90 minutes. After that time you will need to discard it because it starts to lose some of its characteristics and workability.

More mortar tips:

Also see The Brick and Blocklayers Federation ‘Veneer best practice guide’ at

www.bbfnz.co.nz/bricks-and-blocks/masonry-brick-veneer-best-practice-guide

Page 14: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p14

Preventing mortar colour variation

Prevent variations in mortar colour by controlling the exposure of mortar to any additional

water until it has set. Ways to achieve this include, but are not limited to, the following:

• Consider humidity levels when laying. Aim to lay the areas of the build that will get the

afternoon sun in the afternoon.

• Make sure that masonry units are not carrying any additional water by protecting them

from exposure to the elements or to water on or in the ground.

• Ensure the sand and cement ratios are consistent. This is more easily achieved if you are

using bagged mortar. If batch mixing, ensure that you are using a consistent measuring

device for the sand and cement (i.e. use buckets not shovels).

• Cover any unfinished work when you stop for the day or for any extended period.

• Check that the mortar joint is “thumbprint” hard before tooling.

• Ensure that the jointers you are using are made of a consistent material. For example,

steel jointers can cause mortar to dry darker than plastic coated jointers.

• Avoid over-tooling (aggressive or elongated).

• Avoid retempering coloured mortar, especially when using dark colours.

• When the work is complete, ensure that it is covered for at least six to eight hours to

allow the mortar joints to harden and completely seal.

Laying the units and tooling

Concrete blocks should not be

laid when they are saturated

as their subsequent drying out

will result in a considerable

amount of shrinkage

movement. This will cause

cracks in joints and, possibly,

in the units themselves.

Before laying masonry units,

the concrete substrate shall be

clean and free from

contaminants, loose aggregate

and any other material that could reduce the bond between the units and the base.

Laying of masonry units shall be in accordance with NZS 4210. All masonry units shall be laid in

mortar in courses, true to line, plumb, and level to the tolerances of NZS 4210, unless

otherwise specified.

Page 15: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p15

Mortar must cover the entire face shell width of the blocks. The mortar joints shall be

compressed by tooling in accordance with NZS 4210 and Detail 70 of CCANZ CP 01. The mortar

joint shall be tooled after the initial water loss, once the mortar is thumbnail hard.

Installing rebars

Reinforcement requirements for concrete masonry walls are given in NZS 4210 paragraph 2.6.

Reinforcement shall be detailed, bent and placed in accordance with NZS 3109, NZS 3124 or

NZS 4229, except where subject to specific engineering design.

Details of standard bends are given in NZS 4210, Appendix 2.D. Table 2.E1 of NZS 4210

(reproduced on the next page) provides the minimum steel coverage for the various exposure

zones to meet the requirements of Building Code Clause B2 Durability.

• Vertical bars shall be securely held in position at the top of the wall, and placed at

intervals not exceeding 1.2 m for 10 mm bars; 2.4 m for 12 mm bars; or 3.6 m for 16

mm or larger bars.

• Horizontal bars are required to be in grouted cells and shall be at least 25 mm above or

below a mortar joint and fully embedded in grout. Horizontal bars shall be positively

held in position by tying the bar to the vertical reinforcement or by the use of specially

designed units, steel spacers or links.

Page 16: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p16

NZS 4210 Table 2.E1 – Masonry durability requirements

Exposure categories Durability requirements

NZS 36042 zones

NZS 3101 zones (Note 1)

Masonry units (Note 2)

Mortar (Note 3)

Classification built in components (Note 4)

Minimum cover to reinforcement (Note 5)

Seaspray B2 Exposed M4 R4 30 (60)

1 & 4 B1 General purpose

M4 R3 20 (50)

2 & 3 A2 Protected M3 R3 15 (45)

Closed

interior

A1 Protected M2 R1 5 (35)

Geothermal

hotspot

U Exposed M4 R5 Specific engineering design consideration

NOTE – (1) The NZS 3101 zones shall be as defined in section 5 of that Standard. (2) These classifications are defined in AS/NZS 4456.103 for resistance to salt attack. The

requirement is not needed for concrete masonry products. (3) The requirements of the mortar to meet the classifications nominated in the table

are given in 2.2.2.1 of this Standard. (4) The classifications are defined in AS/NZS 2699: Part 1 Wall Ties, Part 2 Connectors

and Accessories, Part 3 Lintel and shelf angles. A protection specification is given for the component which a manufacturer must meet and label the component to identify the level of corrosion protection.

(5) The cover is measured from the inside of the cell face of the unit. The figures in brackets are the approximate total cover to the outside face of the wall assuming a face shell thickness of 30 mm. Reinforcements shall be restrained so that the minimum covers are maintained during construction. Retaining walls shall be classed as B2 as specified in NZS 3101.

(6) When weatherproofed to the requirements of 2.21.2.2 – 2.21.2.5, Exposure Categories 1, 2, 3 & 4 (NZS 3604) or B1 & A2 (NZS 3103) can be reduced to “Closed interior” or “A1”. When waterproofed to the requirements of 2.21.2.1 all exposure categories can be reduced to “Closed interior” or “A1”.

2 NZS 3604:2011 Timber-framed buildings 3 AS/NZS 4456.10:2003 Masonry units and segmental pavers and flags - Methods of test Determining resistance to

salt attack

Page 17: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p17

Typical rebar layout around windows is shown in NZS 4229 Figure. 8.1 (reproduced below).

However, this is indicative only: layout may vary, depending on structural requirements.

NZS 4229 Figure 8.1 – Reinforcement above and below openings

Page 18: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p18

Grouting

Before grouting, check that the works comply with the drawings and specifications. Also check:

• the cells are clean for grouting

• reinforcement is correctly positioned and tied

• all clean out holes and positions that would cause the loss of grout have been sealed.

Masonry grout generally requires a compressive strength of 17.5 MPa (unless otherwise

specified). The grout must fill the cells, provide the specified compressive strength, and bond

the reinforcing steel to the masonry units.

To meet these criteria the flowability, aggregate size and proportions of a grout mix must be

compatible with the application. Fine and coarse aggregates for concrete grout shall comply

with NZS 3121. An expansive admixture is generally used to make sure the grout reaches into

every corner of the cell.

Key steps for applying this grout are as follows:

Applying high lift grouting

Step 1 Clean out the grout space and remove all debris and loose material from the construction joint.

Step 2 Grout the wall in a semi-continuous operation to the top.

Step 3 Consolidate with a vibrator or by rodding (see note below) as filling work proceeds to the top.

Step 4 After waiting for expansion, trowel down and re-compact the top surface of the expanded grout. An alternative method is to place a weighted board on top of the wall to contain the expansion.

What NZS 4210 says:

2.14.2.2 Consolidation shall be carried out by mechanical immersion vibration or rodding with

a solid bar or rod of minimum dimension 16 mm until no settlement of top surface occurs.

More grouting tips:

Also refer to section 4.3 of the ‘New Zealand Concrete Masonry Manual’, available at

https://concretenz.org.nz/page/masonry_manual

Page 19: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p19

Placing control joints in the grout

While grout cures, water escapes and reduces the grout's volume so cracks occur. These cracks

cannot be prevented, but their location can be determined through the placement of control

joints.

Control joints are continuous vertical joints at places where stresses due to grout shrinkage

might concentrate. Control joints are also required at:

• major changes in wall height

• changes in wall thickness

• chases or recesses for services

• wall intersections

• return angles in L, T and U shaped footprints

• one or both sides of any openings.

The following figures show typical examples of a wall control joint and a bond beam control

joint.

Control joint example, wall area

Page 20: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p20

Control joint example, at bond beam level

The spacing of control joints shall not exceed 6 m and they shall be constructed in every

respect to the details and requirements of NZS 4229 and NZS 4210, unless otherwise specified

on the drawings. Ideally, no reinforcement should pass through the control joint but this is

often impractical in New Zealand because of seismic requirements. It is usual to debond any

reinforcement passing through the control joint for at least 400 mm on one side of this joint

(see NZS 4229 Figure 12.2, reproduced below). However, this is not the case for bond beam

and lintel reinforcement, where the reinforcement continues uninterrupted and is bonded to

both sides.

NZS 4229 Figure 12.2 – Control joint detail for solid-filled walls and partially filled walls where

horizontal bars are placed between floors but not bond beams

Page 21: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p21

The Concrete Masonry Manual (CCM) Figure 3 below shows both control joints: the hatched

area shows bond beam reinforcement passing through, whereas the joint within the lower

course shows the reinforcement lapping and debonding to one side.

CMM, Figure 3 – Control joint elevation

Page 22: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Set to work

Concrete Masonry: Site Practice and Workmanship Guide p22

Final weather seals

Masonry walls exposed to the weather will require some form of protection so they are

sufficiently weathertight to meet the requirements of Building Code Clause E2 External

moisture. This can be done in accordance with CCANZ CP 01 section 4: this Code of Practice is

cited in Acceptable Solution E2/AS3 (a means of compliance with Clause E2). The walls can be

sealed with clear or pigmented coatings, plastered, or receive an exterior insulation and finish

system (EIFS).

This requirement does not apply to brick veneer installed in front of a ventilated cavity, as brick

veneer is deemed to be weathertight protection for masonry structures when installed as per

CCANZ CP 01, section 4.6.

If efflorescence is a concern, applying a clear sealer or pigmented coating is recommended: this

will absorb water across a masonry surface and also prevent efflorescence from recurring.

A clear coating weather seal provides a matt finish to this wall and helps prevent efflorescence.

More tips:

See Firth’s publication ‘Architectural Masonry – Best practice guide for specifiers + installers’, at

www.firth.co.nz/assets/Uploads/TechnicalDocuments/AM-Best-Practice-Guide-June-2018.pdf

For more about Acceptable Solutions and other ways to comply with the Building Code go to

www.building.govt.nz

Page 23: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Keep checking

Concrete Masonry: Site Practice and Workmanship Guide p23

Keep checking

Check wall tolerances

Wall straightness should be checked throughout construction. NZS 4210 Table 2.2 (reproduced

below) provides acceptable tolerances.

NZS 4210 Table 2.2 – Maximum tolerances

Item Tolerances

Deviation from the position shown on plan for a building more than one storey in height

15mm

Deviation from vertical within a storey 10 mm per 3 m of height

Deviation from vertical in total height of building 20 mm

Relative vertical displacement between masonry courses (a) Nominated fair face (one side only) (b) Structural face

3mm 5mm

Relative displacement between loadbearing walls in adjacent storeys intended to be in vertical alignment

5 mm

Deviation from line in plan (a) In any length up to 10 m (b) In any length over 10 m

5 mm 10 mm total

Deviation of bed joint from horizontal (a) In any length up to 10 m (b) In any length over 10 m

5 mm 10 mm total

Average thickness of bed joint, cross joint, or perpend

+ 3 mm on thickness specified

NOTE – Tolerances shall not breach minimum cavity widths.

Page 24: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Keep checking

Concrete Masonry: Site Practice and Workmanship Guide p24

Protect blockwork while not working

Brickwork must be kept clean and

protected from rainfall,

contamination and snow. During

breaks in construction, take

particular care to cover the top

course of block and brickwork with

waterproof sheeting so it is

adequately protected from bad

weather.

Make sure that no mortar smearing

or splashing occurs as the work

proceeds. Staining of brickwork

often comes from excessive wetting or saturation of recently built brickwork.

If overnight frost is expected before the mortar has fully set, it shall be protected with an

insulating layer underneath the waterproof sheet.

Temporary propping

Masonry work requires temporary propping to resist wind, earthquake and other lateral loads

until it can support itself without any distress to the components. Typically, a wall over one

metre in height is at significant risk. An ungrouted wall is very susceptible to failure from strong

winds.

Page 25: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Keep checking

Concrete Masonry: Site Practice and Workmanship Guide p25

What NZS 4210 says:

2.17 Bracing during construction Temporary bracing shall be provided to masonry where necessary to resist lateral loads during construction. C2.17 Unfilled blockwork 190mm thick, 1m high becomes unstable when subjected to a wind gust of velocity above about 90 km/h, while a similar wall 2.4 m high becomes unstable at a gust velocity above about 60 km/h. Thinner walls become unstable at lower gust velocities.

Propping of walls during construction is needed at 3 m centres for at least five to seven days

after erection.

Page 26: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Resources

Concrete Masonry: Site Practice and Workmanship Guide p26

Resources

The following publications provide further guidance:

New Zealand Concrete Masonry Association ‘New Zealand Concrete Masonry Manual’

https://concretenz.org.nz/page/masonry_manual

Brick and Blocklayers Federation of New Zealand (BBFNZ) ‘Masonry (Brick) Veneer Best Practice

Guide’

www.bbfnz.co.nz/bricks-and-blocks/masonry-brick-veneer-best-practice-guide

NZS 4210:2001 Masonry construction: Materials and workmanship

https://www.standards.govt.nz/sponsored-standards/building-standards/nzs4210/

NZS 4229:2013 Concrete masonry buildings not requiring specific engineering design

https://www.standards.govt.nz/assets/Publication-files/BSP/NZS4229-2013.pdf

Firth ‘Architectural Masonry – Best practice guide for specifiers + installers’

www.firth.co.nz/assets/Uploads/TechnicalDocuments/AM-Best-Practice-Guide-June-2018.pdf

Firth ‘RapidstakTM Mortarless Masonry’

www.firth.co.nz/assets/Uploads/TechnicalDocuments/FIR0745-Rapidstak-bro-16pg.pdf

New Zealand Masonry Trades Association (NZMTA), Trade Support Documents

https://nzmta.com (members only)

Page 27: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

Concrete Masonry: Site Practice and Workmanship Guide p27

[inside cover – intentionally left blank]

Page 28: Concrete Masonry Site Practice and Workmanship Guide...Concrete Masonry: Site Practice and Workmanship Guide p4 About this guide This is a guide to good site practice and workmanship

CONCRETE NZ - CONCRETE MASONRY - SITE PRACTICE AND WORKMANSHIP GUIDE -

PRELIMINARY DRAFT

CONCRETE MASONRY – SITE PRACTICE AN WORKMANSHIP GUIDE

CONCRETE NZ - CONCRETE MASONRY - SITE PRACTICE AND WORKMANSHIP GUIIDE

Concrete NZ www.concretenz.org.nz

Concrete NZ www.concretenz.org.nz