Amendment Record CONFIGURATION MANAGEMENT PROCESS Version 2.1 FT/CMMI/SUP/MAP Private and Confidential No part of this publication may be reproduced or distributed in any form or by any means, or stored in a database or retrieval

Upload: others

Post on 25-Mar-2020

19 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Amendment Record

CONFIGURATION MANAGEMENT PROCESS

Version 2.1

FT/CMMI/SUP/MAP

Private and Confidential

No part of this publication may be reproduced or distributed in any form or by any means, or stored in a database or retrieval

Page 2: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 2/19

Version No Changes / Remarks Prepared By Approved By Release Date

2 Update Process Ho Kian Ping Daryl Choo 18/11/2015

2.1 Update process to align with ISMS

Ti Hooi Suan Daryl Choo 01/08/2017

Page 3: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 3/19

TABLE OF CONTENTS

Page no

CONFIGURATION MANAGEMENT PROCESS ............................................................................................ 4

1.0 PURPOSE AND SCOPE .............................................................................................................................. 4

2.0 GLOSSARY ............................................................................................................................................... 4

3.0 ROLES AND RESPONSIBILITY ...................................................................................................................... 4

4.0 PROCESS FLOW DIAGRAM ....................................................................................................................... 6

5.0 LIST OF PROCEDURES.............................................................................................................................. 11

6.0 PROCEDURE DESCRIPTION ..................................................................................................................... 12

6.1. Prepare CM Plan ......................................................................................................................... 12

6.2. Setup CM Environment .............................................................................................................. 13

7.0 MEASUREMENT ....................................................................................................................................... 18

8.0 TAILORING OPTIONS .............................................................................................................................. 18

9.0 QUALITY RECORDS................................................................................................................................. 18

Page 4: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 4/19

Configuration Management Process

1.0 Purpose and Scope The purpose of this Configuration Management (CM) process is to establish and maintain integrity of work products using configuration identification, configuration control, configuration status accounting, and configuration audits. CM activities include: • Preparing CM Plan • Placing identified configuration items (CI) into repositories • Tracking and controlling changes of CI(s) • Maintaining configuration records • Performing configuration audits

2.0 Glossary

Abbreviation Description CC Configuration Controller CCB Change Control Board CI Configuration Item CM Configuration Management CR Change Request DAR Decision Analysis & Resolution PAL Process Asset Library PD Project Director PDM Product Manager PM Project Manager SA System Analyst

SEPG Software Engineering Process Group SQA Software Quality Assurance

3.0 Roles and Responsibility

CC

• Setup repositories to store CIs and non-CIs. • Controlling changes to baseline configuration

items. • Making changes to version control of CI according

to the defined procedure. • Ensuring backup of CIs and non-CIs. • Accounting for status of identified CIs and non-CIs.

Page 5: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 5/19

• Publish periodic reports related to CM for the PM SA • Ensure developers support CM processes

PM

• Responsible for planning, directing, controlling, structuring and motivating the project.

• Ensure adequate CM resources, including CM tools, are made available.

• Ensure CM requirements, processes, and practices are conveyed to all project members.

CCB • Review all proposed CRs. • Assess change impacts. • Review modifications to all documentation.

Head of CCB • Chair the CCB meeting • Approved/reject CR

SQA • Ensure quality of the process

Page 6: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 6/19

4.0 Process Flow Diagram SUPPORT

Prepared Configuration Management Plan

START

Project Manager identifies the Configuration Controller.

CC prepares the draft CM plan

PM approves the CM planBaselined CM

plan

CC briefs/train the project team members on the CM related process workflow and

repositories.

END

SQA reviews the draft CM plan. CM Checklist

Draft CM plan

Page 7: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 7/19

SUPPORT

Setup Configuration Management Environment

START

CC sets up the CM Environment as per CM plan.

CM environment setup by CC at project level, reviewed by PM, SQA or SA of the project.

CC briefs/train the project team members on the CM

environment.

END

CM plan

Page 8: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 8/19

SUPPORT

Acquire CI and Non-CI

START

Project team member notifies CC that the CI is ready to be

baselined.

CC confirms the submitted work product is configured as

per CM plan.

CC checks into the CI/Non-CI into appropriate repository

END

PAL Repository

CC update the CI List CI List

Page 9: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 9/19

SUPPORT

Change Request Procedure

START

The PDM fills the CR Form (Part A)

PM allocates the project team member to perform the impact analysis and update in CR Form

(Part B)

CCB reviews and approved/reject the CR based on Impact

Analysis performed.

END

PM will inform project team member to proceed with the change implementation.

Change Request Form (Part A)

Change Request Form (Part B)

Change Request Form (Part C)

Approved?

Yes

No

PM updates the implementation status.

Change Request Form (Part D)

Page 10: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 10/19

SUPPORT

Repositories Backup

START

PM or CC ensure the backup is performed per policy

Perform the backup as per CM plan

Label/tag the backup files accordingly

END

PAL

Backup External Hard Disk / Cloud

Page 11: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 11/19

SUPPORT

CM Audits and CM Reporting

START

Identify the types of audit to perform in the project (Baseline

Audit or CM Audit)

Baseline Audit perform by the Reviewer. CM Audit perform by

SQA.

SQA conducts the Phase End CM Audit base on CM Checklist and send QA report to PM.

END

CM Checklist QA Report

5.0 List of Procedures 1. Prepare CM Plan 2. Setup CM environment 3. Acquire CI and Non CI 4. Change request procedure 5. Repositories backup 6. CM audits and CM reporting

Page 12: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 12/19

6.0 Procedure Description 6.1. Prepare CM Plan Entry Criteria 1. Project Initiation Note is issued.

2. Project Manager is assigned to the project. 3. Project members are identified.

Inputs 1. Project Initiation Note

2. CM Plan template Steps 1. PM identifies CC.

In small project, PM can handle role of CC. In medium to large projects, CC role may be distributed to multiple project team members.

2. PM confirms CC has necessary skills to perform the CC role. PM arranges CC-role based training, if required by SEPG.

3. CC prepares CM Plan. This involves: � Identifying Configuration Items & repositories (refer to CI Master List)

� CM related roles & responsibilities � Configuration management strategies � Backup policy � Identifying the composition of CCB. CCB typically consists of Project Manager, Project Configuration Controller, SA, PDM, and other relevant stakeholders.

� Change management procedure � Naming & version numbering convention � CM Report � CM Audit frequency

Guidelines: CI Master List CM Templates :CM Plan 4. CM Plan is reviewed by SQA using a checklist as per Review Process and will be baselined. Review comments are incorporated and verified as per Review Process CM Checklist :Checklist for CM Plan Review

Page 13: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 13/19

5. CC baselines CM Plan. Subsequent changes to CM Plan are handled using ‘Control Changes to Configuration Items’ procedure of this process.

6. CC briefs project team members on: • CM related processes & workflow • CM repositories

Outputs 1. CM Plan Exit Criteria 1. CM Plan is baselined after closure of review comments

6.2. Setup CM Environment Entry Criteria 1. Baselined CM Plan

2. File server for CM. Inputs 1. Baselined CM Plan

2. CI Master List Steps 1. CC sets up the following CM environment as required to

implement CM Plan: • Controlled repository structures • Security (read/write) access • Release options

2. CM environment set up by CC at project level is reviewed by PM, SQA or SA of the project. Issues raised are tracked to closure.

3. CC briefs project team members on CM environment. Output 1. CM environment Exit Criteria 1. CM environment is reviewed and ready for use

Page 14: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 14/19 6.3. Acquire CI and Non-CI. Entry Criteria 1. CI Master List updated with new CI or Non-CI Inputs 1. Newly submitted CI or Non-CI

2. CM Plan Steps 1. Project member notifies CC that the CI is ready to be

baselined. Baseline means a set of specifications or work products that: - � Has been formally reviewed and agreed on. � Which thereafter serves as the basis for further development

� Which can be changed only through change control procedures

2. CC confirms the following: • Submitted work product is a configuration item as

per CM Plan • Work product has a unique identifier • Work product has been reviewed or tested • Work product follows a defined CI Master List

Guideline : CI Master List

3. Work product shall be baselined when there is no defect found.

4. CC checks in the CI/Non-CI into appropriate repository (depending on development phase) with the correct name, unique identifier and version number.

5. CC updates CI List. CC also conducts configuration status accounting on periodic basis. CM Template :CI List, CM Plan

6. CC confirms the submitting project member that the CI/Non-CI has been checked in to the repository.

Outputs 1. New CI/Non-CI in the Baselined Repository

Page 15: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 15/19

2. CI List Exit Criteria 1. CI/Non-CI is checked in the Baselined Repository

2. Updated CI List

6.4. Control Changes to CI / Change Request Procedure Entry Criteria 1. When a Change Request is initiated Inputs 1. Change Request Steps 1. CR Part A: Initiation

The PDM fills the CR Form when there is a request that is varied from the baselined user requirement. A copy of the CR form is sent to CC and CC makes an entry in CR Tracking Register. CM Forms :CR Form CM Templates: CR Tracking Register

2. CR Part B: Impact Analysis Once the CR form is registered into the CR Tracking Register the following steps are performed: • PM allocates the project team member to perform

the impact analysis who will then update the analysis content to the CR form (Part B).

• Impact analysis is performed to analyze the impact on schedules, resources and plans and estimate is made on the total effort and size required for the change

3. When a CR is in progress and another CR comes up and it is interdependent to the earlier CR then this “Change on a Change” situation will be handled by creating the new change received as a separate CR and would be executed likewise based on priority as per the defined CR process.

4. CR Part C: Change Request Disposition CCB reviews and approves/rejects the CR based on Impact Analysis performed. If the CR is approved, the CCB shall determine whether the CR is chargeable or not. DAR may be used to determine the decision making.

Page 16: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 16/19

5. CR Part D: Implementation Status • PM will inform project team member to proceed with

the change implementation. • Project team member then makes the necessary

changes. • The modified CI together with the CR form will undergo

formal review process. • Project team member informs CC of completed

change request. 6. CC checks in the CI into Baselined Repository with the

correct name, unique identifier and version number. 7. CC updates CR Tracking Register. 8. CC updates CI List

Outputs 1. Chargeable or free CR

2. CR Tracking Register 3. CR Form 4. CI List

Exit Criteria 1. CR is closed

2. CR Tracking Register status is set to “Closed” or “Rejected”

6.5. Repositories Backup Entry Criteria 1. Source code backup daily

2. Project related documents backup weekly Inputs 1. Project’s repositories

2. External Hard Disk Steps 1. PM or CC ensure the backup is performed by System

Engineer

2. Frequency and naming convention of backup is as defined in CM Plan.

3. The backup external hard disk are labeled with: � Type (Source Code, Documents) � Date of backup

Outputs 1. Backup External Hard Disk Exit Criteria 1. Successful backup carried out and verified by PM.

Page 17: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 17/19 6.6. CM Audits and CM Reporting Entry Criteria 1 Successful review of CM Plan

2 Project is in execution phase

Inputs 1 CM Plan

2 CI List

Steps 1 CC identifies types of audit to perform in the project. Audits performed are: • Baseline audit which focuses on the product and

work product and is done before an item is base lined

• Configuration management audit which is typically performed and focuses on conformance to the configuration management process and conforms to the physical characteristics expected in terms of location, etc.

2 CC determines frequency of each audit to be performed and documents the frequency in the Configuration Management plan. CC also determines the stakeholder responsible to perform the audits. • Baseline audit is performed by reviewer • Configuration management audit is performed by

SQA 3 CC assists SQA in performing audits. Audits are performed

using a defined checklist. Audit results are documented in QA Audit Report as per Process and Product Quality Assurance Process. SQA reports any non-conformances to the Project Manager. CC closes any non-conformances found during audit. Checklist: CM Checklist Forms: QA Report Forms: Non-compliance Form

Page 18: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 18/19

4 CC maintains the latest CM Plan and all configuration management related records such as CI List and CR Tracking Register

5 System Engineer performs backup activities. PM or CC perform random retrieval to check integrity of the backups.

6 Brief new members of the project on configuration management and CM tool.

7 SQA conducts Phase End CM audit and sends QA Audit Report to PM. Forms: CI List Forms: QA Audit Report

Output 1 CI List

2 QA Audit Report

Exit Criteria 1 Project is complete

7.0 Measurement None identified

8.0 Tailoring Options Refer to the Process Tailoring Document

9.0 Quality Records Output / Record Retention Responsibility

CM Plan ,CR Form, CR Tracking Register, CI List

Retained by CC until project completion Retained by PAL for 7 years thereafter

Defect Tracking Logs of CM Plan Retained by CC until project completion

Page 19: Configuration Management Process v2 1 · handled using ‘Control Changes to Configuration Items’ procedure of this process. 6. CC briefs project team members on: • CM related

Configuration Management Process Reference No Version Page No

FT/CMMI/SUP/CMP 2.1 19/19

NAS / Cloud storage Retained by CC until project completion Retained by PAL for 7 years thereafter

~ End of Document ~