connectivity and lta minutes rev4 - powergrid minutes/nr/9... · minutes for 8 th connectivity...
TRANSCRIPT
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 1 of 20
Minutes for 8th Connectivity & Long Term Access Meeting with Northern Region Constituents held on 20/01/2016 at NRPC Office, Delhi.
A. CTU welcomed the participants and informed that Minutes of the 7th Connectivity & Long Term Access Meeting with Northern Region Constituents were issued vide letter ref. no. C/CTU-Plg/N/C<A/ dated 10/08/2015. As no observations/comments were received on the minutes, the minutes of 8th Connectivity & Long Term Access Meeting with Northern Region Constituents are confirmed.
B. It was informed that following new Connectivity/ LTA applications need to be
discussed. In addition to new applications, certain modifications of already granted
Connectivity/LTA was also deliberated.
Table-1.0
Sl. No Applicant Time frame Location IC (MW)
Connectivity Sought (MW)
LTA Sought (MW)
1 Nuclear power Corporation of India Ltd.
Aug’2020 Fatehabad (Haryana)
1400 1400 1400
2 Noida Power Company Ltd. April’2014 Greater Noida,
U.P - 500 500
3 Jaiprakash Power Ventures Ltd. Aug’2015 Himachal Pradesh
1000 - 264
4 Lucknow Solar Power Development Corporation Ltd.
Mar’2017 Lucknow 270 270 270
5
Essel Saurya Urja Company of Rajasthan Ltd.
July’2017 Rajasthan 750 750 750
Adani Renewable Energy Park Rajasthan Ltd.
Mar’2017 Rajasthan 250 250 250
Adani Green Energy Ltd. Mar’2016 Rajasthan 250 250 250
Saurya Urja Company of Rajasthan Ltd. (Two Applications)
Jan’2017 Rajasthan - 500 250+250
Saurya Urja Company of Rajasthan Ltd.
Dec’2016 Jaisalmer, Rajasthan
1000 1000 -
Saurya Urja Company of Rajasthan Ltd.
Dec’2016 Jodhpur,
Rajasthan 1000 1000 -
6 NSL Tidong Power Generation Pvt. Ltd.
Jun’2016 Himachal Pradesh
- - 88
7 NHPC Ltd.(Kishenganga HEP) Sep’2016 J&K 330 330 330
8 Aditya Birla Nuvo Ltd. Oct’2016 Sikar, Rajasthan 150 150 -
9 Indian Oil Corporation Ltd. (Mathura Refinery)
July’2018 Mathura, U.P - 100 -
10 NTPC Ltd. (Bilhaur STPP) Dec’2017 Bilhaur, U.P 1320 1320 -
11 SJVNL Ltd. (Dhaulasidh HEP) Jan’2018 Hamirpur, H.P 66 66 -
12 Connectivity & Long Term Applications held up seeking directions from CERC
13 Uttrakhand Connectivity/LTA Applications
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 2 of 20
Details of the applications are given below:
1.0 Connectivity & LTA to GHAVP Nuclear power plant (2X700MW) of M/s NPCIL in Haryana
CTU informed that the Connectivity & LTA application from NPCIL was also
discussed during the 7th Connectivity/Long Term Meeting of Northern Region
Constituents held on 14/07/2015. According to the application, the connectivity as
well as Long Term Access for 1400 MW is sought from upcoming Nuclear power
generator (2X700MW) of M/s NPCIL for Gorakhpur Haryana Anu Vidyut Pariyojna
(GHAVP) located at Fatehabad, Haryana w.e.f. Aug’2020 & Sep.’2020 respectively
with target Beneficiaries as Northern region.
Following Transmission System for Connectivity & LTA was proposed during the 7th
meeting of Connectivity & LTA applications in NR:
Proposal for Connectivity:
� Fatehbad - NPCIL generation 400 kV D/c line
Proposal for Long Term Access:
� LILO of second circuit of Moga-Hisar 400 kV D/c line at Fatehbad
� LILO of both circuits of Moga-Hisar 400 kV D/c line at NPCIL generation switchyard
During the last meeting, HVPNL had observed that NPCIL have acquired land for
4*700 MW therefore they should seek LTA & Connectivity corresponding to the
same. HVPNL were of the view that the proposed scheme may need changes
considering the final capacity of 4*700 MW. CEA had advised NPCIL and HVPNL to
resolve the matter and confirm the capacity for which the evacuation scheme should
be planned by CEA/CTU.
During the meeting, representative from NPCIL stated that considering the present
financial sanction of 2*700 MW, Connectivity and LTA applications have been made
and it prefers to retain the same applications, rather than making new applications
(4*700MW) for which no financial sanction is available. Therefore, it was proposed
by NPCIL that power evacuation scheme for GHAVP may be considered based on
the application (2*700MW).
Accordingly, it was decided that there being no change in the Connectivity and LTA
quantum, the transmission system proposed in the 36th Standing Committee meeting
of Northern region Constituents and 7th meeting of Connectivity and LTA application in
NR may be considered for grant of Connectivity & LTA. The same was agreed in 37th
Standing Committee Meeting of NR held on the same day before the present
meeting. Further, as per decision in the 37th Standing Committee meeting of
Northern region Constituents a 125 MVAR bus reactor may also be provided by
14 Inter – Regional LTA Applications to NR
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 3 of 20
applicant at generation switchyard and switchgear equipment may be designed with
50 kA fault level.
CTU enquired from NPCIL about the status of allocation of power to different constituents. In response NPCIL informed that allocation of power is yet to be made by the competent authority. In this regard, CTU informed that as per the detailed procedure of CERC in absence of allocation of power, NPCIL shall be required to sign LTA agreement and submit construction phase BG @ Rs. 5 Lakhs/MW corresponding to the LTA quantum, so that implementation of the transmission can be recommended to the Empowered Committee. Further, they were also advised to indicate the auxiliary consumption so as to account for the same while issuing LTA intimation.
Members agreed for the above proposal.
2.0 Connectivity & Long Term Access to M/s Noida Power Company Ltd. for drawl
of 500 MW as a bulk consumer in Greater Noida area, Uttar Pradesh.
CTU informed that the issue of grant of Connectivity and LTA to Noida Power Company Ltd. (NPCL) had been discussed in various Standing Committee/LTA & connectivity meetings, however, the same could not be resolved.
Pursuant to CERC order dated 16/09/2015, NOC was issued by UPPTCL vide letter dated 28-10-2015. UPPTCL has indicated that 500MW load of NPCL can be catered to from existing and upcoming system of STU. Based on the above NOC, agenda for grant of LTA to M/s NPCL was circulated to all Northern region Constituents, wherein it was proposed that LTA may be granted for drawl of 500MW power at G. Noida 765/400kV S/s of UPPTCL w.e.f. 1/10/2017 to 30/9/2042:
UPPTCL informed that their network would be adequate to deliver 500MW LTA to NPCL from Oct, 2017 from existing STU network & upcoming 765/400/220 kV, 400/220 kV, 400/132 kV, 220/33 kV, 132 kV substations in the area, therefore CTU need not develop any system for proposed LTA. It was also informed that some of 765kV, 400kV substations will be available by the end of 2015 and others by 2016 along with following connecting line:
� LILO of Agra-Meerut 765 kV ISTS existing line at G. Noida (765 kV) � G. Noida (765 kV)- G. Noida (Pali) 400 kV D/c line � G. Noida (765 kV)- Sikandrabad 400 kV D/c (Quad) line
In view of the above, it was agreed to cancel the already granted connectivity at 400/220 kV G. Noida (new) proposed under ISTS. Further, LTA may be granted subject to the condition mentioned in the NOC furnished by UPPTCL.
M/s NPCL requested that as some part of the U.P Transmission system associated
with grant of Connectivity as bulk consumer to them is getting commissioned shortly,
therefore, part LTA may be granted to them. CTU stated that, as per CERC
regulations, grant of part LTA is not permitted, therefore, LTA shall be granted for
total quantum ie. 500 MW from the time period as requested in the LTA application
ie. October’17. Representative from M/s NPCL also agreed to the same.
Members agreed to the above.
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 4 of 20
3.0 Long Term Access for 264 MW to M/s Jaiprakash Power Ventures Ltd. for
Karcham Wangtoo Hydro Electric Plant in Himachal Pradesh.
CTU informed that earlier LTA was granted for 704 MW for Karcham Wangtoo
generation project with target regions as NR which was subsequently revised as NR
(440 MW), WR (176 MW) and SR (88 MW).
However, JPVL requested POWERGRID to reinstate the earlier granted LTA to
Northern Region beneficiaries for 704 MW instead of NR, WR and SR.
The matter was also discussed during the 7th NR LTA/Connectivity meeting wherein
CEA had suggested that Jaiprakash Power Ventures Ltd. may apply with a new LTA
application as the change in LTA Quantum is more than 100 MW.
Subsequently, as suggested by CEA, a fresh LTA application was submitted by
Jaiprakash Power Ventures Ltd. in Aug’2015 for change of target region from WR-
176MW & SR-88MW to NR.
It was discussed & agreed that as the Karcham Wangtoo HEP is located in Northern
part of Northern Region, therefore, change of target region from WR & SR shall not
require any augmentation in transmission system. Hence, change of target region
sought by the applicant was agreed to subject to the fulfillment of regulatory
provisions. It was also informed to the applicant that the grant of LTA and treatment
of relinquishment charges shall be applicable as per the directions/guidelines of the
Hon’ble Commission, for which representative of Jai Prakash Power Ventures Ltd.
gave their consent.
Members agreed for the same.
4.0 Connectivity & Long Term Access to M/s Lucknow Solar Power Development
Corporation Ltd. for 270 MW from Jalaun Solar Park in Uttar Pradesh.
In the 36th Meeting of Standing Committee on Power System Planning in Northern
Region held on 13/07/2015, transmission system for Solar Power Parks in Jalaun,
UP (370 MW) comprising establishment of 400/132kV, 3x200 MVA S/s at Jalaun &
400kV D/c line between Jalaun PS & Kanpur (New) was discussed and in-principally
agreed. In the meeting, it was also decided that implementation of above
transmission scheme shall be taken up only after receipt of application from Solar
park developer for LTA of at least 25% of their installed capacity.
Subsequently, M/s Lucknow Solar Power Development Corp. Ltd. (LSPDCL), the
Solar Power park developer, submitted the application for Connectivity and LTA in
ISTS for revised capacity (270 MW) (Further modified to 260 MW) of Jalaun Solar
Power Park with NR as target beneficiary. As per the application, LTA is sought from
Dec’2016 for 25 years, which was further revised as Mar’17.
Subsequently, the above proposal of LSPDCL was discussed in the 37th Standing
Committee Meeting of Northern region Constituents wherein it was agreed that
transmission scheme for evacuation of power from different location of Jalaun Solar
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 5 of 20
Power park will be evolved & developed by UPPTCL as an Intra State transmission
scheme. Therefore, the implementation of above identified Interstate transmission
system for Jalaun Solar power park by POWER GRID is not required.
Hence, it was agreed to close the Connectivity & LTA application of M/s Lucknow
Solar Power Development Corp. Ltd. (LSPDCL).
Members agreed for the same
5.0 Connectivity & Long Term Access applications M/s Saurya Urja Company of
Rajasthan Ltd., M/s Essel Saurya Urja Company of Rajasthan Ltd. & Adani
Renewable Energy park Rajasthan Ltd. for Ultra Mega Solar Parks in Bhadla,
Distt. Rajasthan.
CTU informed that in the 36th Meeting of Standing Committee on Power System
Planning in Northern Region held on 13/07/2015, inter-state transmission scheme for
evacuation of 3000MW of solar power in Jodhpur (Bhadla :1000MW) and Jaisalmer
(Parewar and Fatehgarh : 2000MW) was in-principally agreed. In the meeting, it was
also agreed that implementation of above system shall be taken up by POWERGRID
only after receipt of LTA of at least 25% of their installed capacity from respective
Solar park developers.
It was informed that subsequently, following three Solar Power park Developers
(SPPDs) have applied for Connectivity /LTA at Bhadla (Jodhpur) in Rajasthan
Applicant LTA
(MW)
Solar Park Schedule Target Region
Saurya Urja Company of Rajasthan Ltd. 500 Bhadla Ph.-III Jan’17 NR
Adani Renewable Energy Park
Rajasthan Ltd.
250 Bhadla Ph-IV Mar’17 NR
Essel Saurya Urja Company of
Rajasthan Ltd.
750 Phalodi-
Pokaran
Jul’17 NR-400 MW and
WR-350 MW
It was informed that based on the joint visit for site selection for 765/400/220kV
Bhadla Pooling station by RRECL, RVPN, POWERGRID, Solar Power park
developers etc., Govt land (about 130 acres) in Tehsil Bap, Jodhpur district was
identified and applied to Govt of Rajasthan for land allotment. The above site for
Bhadla Pooling Station is at about 20 km from M/s Saurya Urja & Adani Solar Power
Park whereas M/s Essel’s Park is about 60 km.
The connectivity to M/s Adani (250 MW) and M/s Saurya Urja Co. (500 MW) was
proposed at 220kV voltage level, whereas connectivity of M/s Essel (750 MW) was
proposed at 400kV. It was decided that 220kV & 400kV D/c Interconnecting
Transmission line from Solar Park Pooling station upto 220/400/765kV Bhadla
Pooling station shall be developed by the respective applicants/SPPD as part of its
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 6 of 20
internal transmission infrastructure. M/s Adani & M/s Saurya Urja Co. Ltd agreed for
the development of 220kV D/c interconnection upto Bhadla PS as part of their
internal infrastructure. M/s Essel Saurya (750 MW) expressed their concerns
regarding laying 60 km long 400kV D/c interconnecting line upto Bhadla PS due to
ROW concerns, cost economics as well as their limited technical expertise. Members
decided that in view of the short gestation period of the project, it is advisable that
interconnecting line may be developed by M/s Essel as its being done by other
SPPD’s also.
However, scope of 4 nos. 220kV line bays (2 nos. 220kV each for M/s Saurya Urja &
Adani Renewable) and 2 nos. 400kV line bays (for M/s Essel) at 220/400/765kV
Bhadla Pooling station for termination of SPPD’s interconnecting transmission lines
is kept under the scope of the proposed ISTS scheme for expediting implementation.
Further, to address reactive power management aspects including during low/no
solar generation periods, 1x240MVAr bus reactor at 765kV & 1x125 MVAr at 400kV
at Bhadla S/s is proposed. For 765kV Bhadla- Bikaner D/c line also, 1x240 MVar
Switchable line reactor at each end of each Ckt. is proposed.
Considering above three (3) LTA applications for 1500 MW Solar Power transfer
requirement through Bhadla pooling station, following transmission scheme was
agreed to be taken up for implementation as ISTS by POWERGRID:
i. 765kV Bhadla (PG) – Bikaner(PG) D/c
ii. 400kV Bhadla (PG)- Bhadla (RVPN) D/c (Quad)
iii. Establishment of Pooling Station at Bhadla (PG) (765/400kV : 3x1500MVA
400/220kV : 3x500MVA,)
iv. 2 nos. 400kV & 4 nos. 220kV line bays at Bhadla (PG) for interconnection of
solar park interconnection
v. 1x240 MVAr switchable line reactor at each end (each ckt) of 765kV
Bhadla(PG)- Bikaner(PG) D/c line
vi. 1x240 MVAr (765kV ) & 1x125 MVAr (400kV) Bus reactors at Bhadla Pooling
Station
It was agreed that Long Term Access shall be granted to the above applicants with
the above mentioned transmission system.
Further, grant of Connectivity for all three applicants was agreed through following
Transmission system:
1) M/s Saurya Urja Company of Rajasthan Ltd.
� M/s Saurya generation switchyard - Bhadla (PG) Pooling Station 220 kV D/c
(Twin Zebra) line (to be implemented by the applicant)
2) M/s Adani Renewable Energy Park Rajasthan Ltd.
� M/s Adani generation switchyard - Bhadla (PG) Pooling Station 220 kV D/c line
(to be implemented by the applicant)
3) M/s Essel Saurya Urja Company of Rajasthan Ltd.
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 7 of 20
� M/s Essel Saurya generation switchyard - Bhadla (PG) Pooling Station 400 kV
D/c line (to be implemented by the applicant)
The above Tr. system was agreed during 38th standing Committee meeting of NR.
M/s Saurya Urja Co. of Rajasthan Ltd., M/s Adani Renewable Energy Park
Rajasthan Ltd, and M/s Essel Saurya Co. of Rajasthan Ltd, in their LTA applications
indicated schedule for Jan’17, Mar’17 and Jul’17 respectively. It was deliberated that
considering the scope involvement in above transmission system, target
commissioning schedule may be taken as progressively from Dec’17.
Applicants/SPPD agreed to review and align their target commissioning schedule in
line with the above.
I. Earlier Connectivity Applications of Saurya Urja Company of Rajasthan Ltd. for
1000MW each at Bhadla & Parewar:
It was informed that in the 7th Connectivity / LTA Meeting of Northern Region
Constituents held on 14.07.2015, Connectivity applications from M/s Saurya Urja
Company of Rajasthan Ltd. for Solar power projects of 1000MW capacity each at
Bhadla & Parewar (Jaisalmer) in Rajasthan were discussed. However confirmation
of RVPN regarding Connectivity points, space availability for 220 kV & 400 kV bays
etc. could not be discussed as representative from RVPN was not present.
It was deliberated that following has been observed while processing the
Connectivity applications of M/s Saurya Urja Company of Rajasthan Ltd.:
− M/s Saurya applied for Connectivity of 1000 MW capacity each at Bhadla &
Jaisalmer (Parewar)
− M/s Saurya vide letter dated. 23.06.15 informed that they have received
authorization from MNRE to apply for Connectivity/LTA in ISTS for both Bhadla
Phase-III (1000 MW) as well as Jaisalmer Phase-I solar projects (1000 MW)
therefore their applicant category may be considered as Solar Power Park
Developer (SPPD).
− Subsequently, M/s Saurya also applied for Connectivity & Long Term Access in
ISTS for 500 MW at Bhadla (Jodhpur). However authorization from MNRE to
above developer is given under Bhadla Phase-III (1000 MW) capacity only.
− Further, as per the discussion with RVPN, it was informed that M/s Saurya is
already given connectivity/LTA for its Bhadla Solar project (1000 MW) by RVPN
for 500 MW
− In effect, M/s Saurya Urja applied for Connectivity of 1500 MW from its Bhadla
Solar Project and SPPD authorization from MNRE is available for 1000 MW at
Bhadla out of which 500 MW is granted by RRVPN, as informed
− In addition, MNRE vide letter dated 17.12.15 intimated about cancellation of
Jaisalmer Ph-I solar Park (1000 MW) to be set up by M/s Saurya Urja at Parewar,
Joga & Kachuri villages of Jaisalmer.
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 8 of 20
As the earlier Connectivity applications at Bhadla (1000 MW) & Parewar, Jaisalmer
(1000 MW) are pending with CTU, M/s Saurya was requested to clarify about the
present status of 1000MW project each at Bhadla & Parewar (Jaisalmer) and their
connectivity applications in above context.
On the above representative of M/s Saurya Urja stated that the earlier Connectivity
application for 1000 MW at Bhadla & Jaisailmer by M/s Saurya Urja Company of
Rajasthan Ltd. may be closed and the same was agreed.
II. Earlier Connectivity Application of Adani Green Energy Ltd. for 250MW:
It was informed that M/s Adani Green Energy Ltd. had earlier applied for grant of
Connectivity for 250 MW in the “Generator” category at Bhadla, Rajasthan. Also, M/s
Adani Renewable Energy Park Raj Ltd. has applied for Connectivity of 250 MW at
Bhadla as “SPPD”. All other application details including location of the project are
same as given in the application by M/s Adani Green Energy Ltd.
Representative of M/s Adani Green Energy Ltd. clarified that the earlier Connectivity
application of 250 MW as a “Generator” may be closed.
Members agreed to above.
6.0 Long Term Access to NSL Tidong Power Generation Pvt. Ltd. for 88 MW of
Tidong HEP in Himachal Pradesh.
CTU informed that Long Term Application from M/s NSL Tidong Power Generation
Pvt. Ltd. for 88 MW from Tidong HEP located in Himachal Pradesh for transfer of
power to Southern region was discussed during the 7th Meeting of Northern Region
Constituents regarding Connectivity/Long Term applications held on 14/07/2015. The
transmission system discussed & agreed in the 30th NR SCM for Interim as well as
final arrangement for evacuation of power through Tidong-I HEP is as below:
Interim Arrangement:
� LILO of one circuit of 220 kV D/C Kashang- Bhaba line at Tidong-I HEP
Final Arrangement:
� 2x315 MVA (7x105 MVA units) 220/400 kV GIS Pooling Station at Jangi (with
4000 Amps. switchgear) (with space provision for 3rd ICT)
� Tidong – Jangi Pooling Station 220 kV D/c line
Further, during the meeting held on 14/07/’2015 it was informed that the processing
of pending LTA applications since Nov’2013 for power transfer to Southern region
were held up on litigation and they are gradually being processed as per the priority
and availability of ATC. It was informed that after the CERC order the pending
applications for power transfer to Southern Region have already been processed.
Subsequently, the above proposal for grant of LTA was discussed in
Connectivity/LTA meeting of Southern region constituents held on 29/12/2015 for
their concurrence and after deliberations, following was agreed:
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 9 of 20
LTA to M/s NSL Tidong Power generation Private Limited may be granted subject to
commissioning of following:
� Angul-Srikakulam-Vemagiri 765kV D/c line along with “Constraints in 400kV bay extensions at Vemagiri” (Including rearrangement of Vemagiri(PG)-Vemagiri(AP) line). (Note- To enhance the ATC from NEW grid to SR grid, certain realignment works had been proposed, the same are being discussed with AP. Accordingly this grant would be subject to the agreement of AP for the proposed realignment)..
� Wardha - Maheshwaram 765kV D/c link with anchoring at Nizamabad along with “Connectivity lines associated with Maheshwaram substation”.
It was agreed that LTA to M/s NSL Tidong Power generation Pvt. Ltd. may be granted subject to above mentioned conditions & Transmission system. The start date of LTA may be considered as 1st July, 2017 or the availability of corridor as mentioned above whichever is later.
Members agreed for the same.
7.0 Connectivity & LTA to NHPC Ltd. for Kishenganga HEP for transfer of 330 MW
of power
CTU informed that the Connectivity & LTA application was discussed & agreed
during the 7th Connectivity/Long Term Meeting of Northern Region Constituents with
the following Transmission system:
o Kishenganga – Amargarh 220 kV D/c
o Kishenganga – Wagoora 220 kV D/c
CTU stated that allocation from Ministry of Power for the generation project has not
been submitted by NHPC who has applied for Connectivity as well LTA as per CERC
regulations, 2009 to fulfill the regulatory requirements. In this regard NHPC need to
submit the power allocation from Govt of India so as the intimation of Connectivity &
LTA can be issued. As NHPC was not present in the meeting, therefore, the same
could not be confirmed.
Members noted.
8.0 Connectivity to M/s Aditya Birla Nuvo Ltd. for 150 MW for Solar generating
plant in Rajasthan.
CTU informed that Connectivity application was received from M/s Aditya Birla Nuvo
Ltd. in September’2015 for 150 MW quantum of power from Solar generating plant
Project located in Sikar, Rajasthan. As per the application, Connectivity has been
sought at Sikar (POWERGRID) 400/220 kV S/s from Oct’2016.
It was also informed that space is not available for 220 kV bays at Sikar 400/200 kV
(PG) substation, therefore, connectivity cannot be provided at this substation.
However, connectivity can be considered through LILO of one circuit of Sikar (PG) -
Sikar (RVPNL) 220 kV D/c line at Solar Generation plant. It was stated that this
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 10 of 20
requires consent from RVPNL, however, the consent of RVPNL could not be
obtained as no representative was present in the meeting.
The matter was deliberated and looking into the tight commissioning schedule of
Solar Project, i.e. Oct’2016 as indicated by applicant, it was decided that CEA would
convene a meeting with RVPNL and CTU on an early date to resolve the matter.
Accordingly, it was decided that connectivity may be granted to M/s Aditya Birla
Nuvo Ltd. for 150 MW quantum of power from Solar generating plant after resolution
of issue as mentioned above.
It was also agreed that as the project capacity is 150 MW, the construction of
connectivity line shall have to be taken up by the applicant in-line with CERC
regulations.
CTU informed to the applicant that mere connectivity does not fulfill the condition of
adequacy of transmission system for transfer of power to target beneficiaries and the
grant of connectivity shall not entitle to interchange any power with the grid.
Transmission beyond immediate evacuation system shall be evolved once the
applicant applies for the LTA. Hence, M/s Aditya Birla Nuvo Ltd. was advised to
apply for LTA.
Members agreed to the above
9.0 Connectivity to M/s Indian Oil Corporation Limited for 100 MW as bulk
Consumer for their Mathura refinery.
CTU informed that Indian Oil Corporation Limited had applied for Connectivity as a
bulk consumer for 100 MW quantum of power for their Mathura refinery, Uttar
Pradesh, which was discussed during the 7th Connectivity/Long Term meeting of
Northern Region Constituents. However, grant of Connectivity could not be finalized
due to certain issues regarding grant of Connectivity as a bulk consumer to a
generator, construction of dedicated line etc.
Subsequently, a meeting was held between CTU and M/s IOCL on 27/08/2015
wherein M/s IOCL has expressed its desire to connect to STU network for which
STU consent is required.
Accordingly, the matter was discussed in the meeting, wherein UPPTCL informed
that in the vicinity of IOCL Mathura refinery, their new Math 220/132/33 kV
substation has been approved and is expected to be completed by 2018.
After deliberations, it was agreed that applicant shall approach UPPTCL for their
concurrence and communicate the same to CTU. Thereafter, connectivity may be
granted to M/s IOCL through STU network.
Members agreed to the above.
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 11 of 20
10.0 Connectivity to Bilhaur STPP (2X660MW) of M/s NTPC Limited in Uttar Pradesh
CTU informed that Connectivity application for 1320 MW from coal based Bilhaur
STPP (2X660MW) generation of M/s NTPC Limited was discussed in 7th
Connectivity/Long Term Meeting of Northern Region Constituents held on
14/07/2015 and it was agreed that Connectivity may be granted to M/s NTPC for
Bilhaur STPP w.e.f. Dec. 2017 with the following Transmission system:
• Bilhaur- Kanpur(New) 400 kV (Quad) D/c line
Subsequently, the above system has also been agreed during the 37th Standing
Committee Meeting of Northern region Constituents.
Further, during the meeting, it was agreed that a 125 MVAR bus reactor may be
provided by applicant at generation switchyard and switchgear equipment may be
designed with 50 kA fault level.
NTPC was enquired about the status allocation of power to different constituents to
which it was informed that allocation of power is yet to be made by the competent
authority. In this regard, CTU informed that as per the detailed procedure in absence
of allocation of power, NTPC shall be required sign LTA agreement and submit
construction phase BG @ Rs. 5 Lakhs/MW corresponding to the LTA quantum, so
that implementation of the transmission can be recommended to the Empowered
Committee.
CTU reiterated that mere connectivity does not full fill the condition of adequacy of
transmission system for transfer of power to beneficiaries and the grant of
connectivity shall not entitle to interchange any power with the grid. It was informed
that NTPC has not yet applied for LTA and Transmission system beyond immediate
evacuation system shall be evolved once the NTPC applies for the LTA. Accordingly,
NTPC was suggested to apply for LTA.
Members agreed to the above.
11.0 Connectivity to Dhaulasidh Hydro Electric Power Project (66MW) of M/s SJVN
Limited in Himachal Pradesh.
CTU informed that connectivity to Dhaulasidh was included in the agenda of 7th NR
LTA/ Connectivity Meeting, however, the same could not be discussed due to
absence of HPPTCL representative. Subsequently, a meeting for Connectivity to
Dhaulasidh HEP was held among CEA, HPSEBL/HPPTCL & SJVNL on 09/09/15.
Thereafter, SJVNL vide letter dated 08/10/2015 requested that considering techno-
economic reasons, the Connectivity of Dhaulasidh generation plant may be granted
through 220 kV D/c line from Dhaulasidh HEP to 400/220 kV S/s at Hamirpur
(POWERGRID).
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 12 of 20
The same was discussed during the meeting and it was agreed to grant Connectivity
to M/s SJVNL for Dhaulasidh HEP for 66 MW with the following Transmission
system:
� Dhaulasidh HEP- Hamirpur (PG) 220 kV D/c line
It was deliberated that the connectivity line shall be constructed by SJVNL including
bays at both ends, in line with CERC regulations. Representative from M/s SJVNL
informed the revised commissioning schedule of the project as December’ 2022,
therefore, connectivity was agreed to be granted from Dec’2022.
CTU re-iterated that mere connectivity does not fulfill the condition of adequacy of
transmission system for transfer of power to target beneficiaries and the grant of
connectivity shall not entitle to interchange any power with the grid. Transmission
beyond immediate evacuation system shall be evolved once the applicant applies for
the LTA. Hence, M/s SJVNL was advised to apply for LTA.
Members agreed for the same.
12.0 Pending Connectivity & Long Term Applications pertaining to Northern region
CTU informed that there are many Long Term Access applications where LTA could
not be granted as the LTA applicants have sought repeated extensions in grant of
Long Term access by requesting to keep their applications ‘in abeyance’. Similarly,
some applications could not be granted LTA as the regional constituents opined and
informed about the lack of progress of generation plant. CERC has been approached
for suitable directions in this regard and the list of such LTA/Connectivity applications
is as below:
It was further informed that following LTA applications are pending for
directions/guidelines from CERC due to non-signing of LTA agreement:
Sl. No Applicant Time frame Location IC (MW)
Connectivity Sought (MW)
LTA Sought (MW)
1 Jaiprakash Associates Ltd. (Roorkee Unit)
April’2017 Uttrakhand 120 - 10
2 Jaiprakash Associates Ltd. (Panipat Unit)
April’2017 Uttrakhand 120 - 10
3 Gama Infraprop (P) Ltd. Oct’2011 Uttrakhand 225 - 50
4 NTPC Ltd. (Gidderbaha STPP) Deferred Punjab 2640 2640 2617.74
5 Miyar HEP Company Ltd. July’2017 Himachal Pradesh
120 120 120
6 SELI HEP Company Ltd. Oct’2017 Himachal Pradesh
400 400 400
7 M/s NHPC Ltd. (Kotlibehl HEP) 2016-17 Uttrakhand 215 215 (10% overload capacity)
215 (10% overload capacity)
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 13 of 20
Sl.
No
Applicant Time frame Location IC Connectivity Sought (MW)
LTA Sought (MW)
1 Himachal Pradesh Power Corporation Limited (Sainj HEP)
April’2014 Himachal Pradesh
100 100 100
2 Himachal Pradesh Power Corporation Limited (Sawra Kuddu)
Dec’2012 Himachal Pradesh
111 111 111
3 Sravanthi Energy Pvt. Ltd. Mar’2011 Uttrakhand 450 450
(Two Phases) 450
(Two Phases)
CTU informed that based on the directions/guidelines of CERC, suitable actions shall
be taken.
Members noted the above.
13.0 LTA/Connectivity to hydro projects in Uttarakhand
LTA/Connectivity for various hydro projects being developed in Uttarakhand was
discussed, the details of which are given below:
A) Projects for which LTA was granted beyond Kashipur: Tapovan Vishnugarh
HEP(520MW), Alaknanda HEP (300 MW) & Phatabyung HEP (76 MW)
CTU informed that for above projects, earlier Connectivity was granted by PTCUL
and LTA was granted by CTU beyond Kashipur. Subsequently, vide order dated
31/1/2013 in Petition no. 133/MP/2012, the comprehensive transmission system
identified by PTCUL in association with CEA for evacuation of power from these
generation projects have been declared as deemed ISTS system. Accordingly,
during the 7th LTA/Connectivity meeting of NR constituents, these generators were
asked to apply afresh for connectivity to CTU.
It was further informed that Phatabyung HEP & Alaknanda HEP had signed LTA
Agreements, however based on revised connectivity application the injection point
for LTA would get changed to deemed ISTS network and the already signed LTA
agreement shall be revised by CTU. It was also agreed that after grant of
connectivity, PTCUL would sign Implementation Agreement with the generators in
line with CERC Regulations.
i. Connectivity to Tapovan Vishnugarh Hydro project (520 MW) of M/s NTPC Ltd.
in Uttarakhand.
CTU informed that connectivity application was received in October’2015 from NTPC
Ltd. for 520 MW Tapovan Vishnugarh Hydro Project located in Uttarakhand. As per
application, the Connectivity has been sought from 1st Sep’2018 (commissioning of
first unit).
CTU informed that the associated composite transmission system for various hydro
projects in Uttarakhand including Tapovan Vishnugarh HEP was revised in the 35th
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 14 of 20
Standing Committee meeting of transmission planning of NR held on 03/11/14. The
final agreed composite transmission is given below:
� Establishment of 400/220 kV, 2X315MVA Pipalkoti (GIS) substation
� Tapovan Vishnugad HEP– Pipalkoti (THDC) S/s 400 kV D/c (Twin Moose) line
� LILO of one circuit of Vishnu Prayag-Muzaffarnagar 400 kV line at Pipalkoti
(THDC) 400/220 kV substation
� Pipalkoti HEP - Pipalkoti (THDC) S/s 400kV D/C (Twin Moose) line.
� Pipalkoti (THDC) S/s -Srinagar 400 kV D/c (Quad)
� Srinagar-Kashipur 400 kV D/c (Quad)
It was informed that the integrated transmission system has been evolved for
Tapovan Vishnugarh, Akalnanda & Pipalkoti hydro projects, the Connectivity system
needs to be segregated based on the commissioning schedule. The integrated
transmission system is to be developed in a phased manner.
CTU further informed that the transmission system for Tapovan Vishnugadh and
Pipalkoti HEPs need to be finalised on priority as these project are expected in 2018-
19 time frame and delay in finalisation may result into bottling up of power. It was
proposed that PTCUL may take up the implementation of 400 kV D/c line with twin
conductor from Tapovan Vishnugah to proposed site of Pipalkoti substation and join
with 400 kV Quad line from proposed site of Pipalkoti to Srinagar. Further, the
power from Pipalkoti HEP may be injected at Pipalkoti switching station. It was
further stated that in the time frame of Pipalkoti HEP, only 400 kV switching station
would be required and transformers are to be provided later with other generation
projects like Alaknanda HEP.
Note : Subsequently to discuss the evacuation of power from Tapovan Vishnugadh
and Pipalkoti HEPs a meeting was held in CEA on 18/02/2016 wherein it was
informed that Tapovan Vishnugadh is expected by September 2018 and Pipalkoti
HEP is expected by end of 2019.
Accordingly, following is proposed for grant of connectivity:
a) Tapopvan Vishnugarh HEP:
Transmission system for grant of connectivity to Tapovan Vishnugarh HEP shall be as below: � Tapovan Vishnugad HEP– Proposed site of Pipalkoti 400 kV S/s 400kV D/c (Twin
Moose) line � Proposed site of Pipalkoti 400 kV S/s-Srinagar 400kV D/c (Quad Moose) line
b) Pipalkoti HEP:
Transmission system for grant of connectivity to Pipalkoti HEP shall be as below:
� Pipalkoti HEP– 400 kV Pipalkoti switching station 400kV D/c (Twin Moose) line
� Establishment of 400 kV Pipalkoti switching station
� Diversion of Tapovan Vishnugad HEP– Proposed site of Pipalkoti 400 kV S/s
400kV D/c (Twin Moose) line at Pipalkoti switching station
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 15 of 20
� Diversion of Proposed site of Pipalkoti 400 kV S/s– Srinagar 400kV D/c (Quad)
line at Pipalkoti switching station
It was deliberated that for evacuation of power beyond Srinagar 400/220 kV S/s
(PTCUL), Srinagar (PTCUL)-Kashipur 400 kV (Quad) D/c line shall be required.
Further, it was discussed that implementation of the above system is to be carried
out by PTCUL, however their concurrence could not be obtained as no
representative from PTCUL was present in the meeting. It was agreed that CEA
would convene a meeting among PTCUL, NTPC, THDC & CTU for concurrence of
PTCUL on above system. Thereafter, Connectivity may be granted to M/s NTPC Ltd.
from Sep’2018. (Subsequently to discuss the evacuation of power from Tapovan
Vishnugadh and Pipalkoti HEPs a meeting was held in CEA on 18/02/2016 wherein
the above proposal was agreed.)
CTU informed that PTCUL need to sign the implementation agreement with the
generator as per the CERC guidelines.
Members agreed for the same
ii. Connectivity for 259MW to Alaknanda HEP (300MW) of M/s GMR (Badrinath)
Hydro Power Generation Pvt. Ltd in Uttarakhand.
CTU informed that M/s GMR (Badrinath) Hydro Power Generation Pvt. Ltd had been
granted Long Term Access beyond Kashipur for transfer of 259 MW power from
Alaknanda HEP (300MW) in Uttarakhand. Connectivity was granted by PTCUL for
the same.
Also, vide order dated 31/1/2013 in Petition no. 133/MP/2012, the comprehensive
transmission system identified by PTCUL in association with CEA have been
declared as deemed ISTS system. Accordingly, during the 7th LTA/Connectivity
meeting of NR constituents, the applicant was asked to apply afresh for connectivity
to CTU.
In the last few LTA/Connectivity meetings, M/s GMR (Badrinath) Hydro Power
Generation Pvt. Ltd had informed that their generation activities are on hold for want
of requisite clearances and the case is pending in Hon’ble Supreme Court.
It was further informed that M/s GMR (Badrinath) Hydro Power Generation Pvt. Ltd.
had already signed LTA Agreement, however based on revised connectivity
application the injection point for LTA would get changed to deemed ISTS network
and the already signed LTA agreement shall be revised by CTU.
Therefore, it was reiterated that without Connectivity, LTA is infructuous and they
need to apply for ISTS connectivity to CTU. After deliberations it was agreed that
agreed that the matter of M/s GMR (Badrinath) Hydro Power Generation Pvt. Ltd.
shall be discussed after receipt of Connectivity application.
Members agreed for the same
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 16 of 20
iii. Connectivity to Phata Byung Hydro project (76 MW) of M/s Lanco Mandakini Hydro Energy Pvt. Ltd. in Uttarakhand.
CTU informed that Connectivity application has been received in Aug’2015 from M/s
Lanco Mandakini Hydro Energy Pvt. Ltd. for transfer of 76 MW power from Phata
Byung Hydro Project. As per the application, Connectivity has been sought from
Sep’2017. However, the applicant subsequently informed the revised commissioning
schedule as Sep’2018.
It was informed that the composite associated transmission system for various hydro
projects in Uttarakhand including Phata Byung HEP has been developed by PTCUL
under which, Phata Byung HEP is connected through:
� LILO of one circuit of Rambara- Baramwari 220kV line at the generation
switchyard
It was discussed that as Rambara generation project is uncertain, 220 kV D/c line
from Phata Byung generation switchyard to Barmwari (PTCUL) S/s can be
implemented by the applicant. However, the transmission system beyond Baramwari
S/s upto Srinagar 400/220 kV S/s shall be implemented by PTCUL.
After deliberations, it was agreed that Connectivity can be granted to M/s Lanco
Mandakini Hydro Energy Pvt. Ltd. for Phata Byung HEP with the following
transmission system from Sep’2018:
� Phata Byung generation switchyard - Barmwari (PTCUL) S/s 220 kV D/c line
It was discussed that for evacuation of power beyond Srinagar 400/220 kV S/s
(PTCUL), Srinagar (PTCUL)-Kashipur 400 kV (Quad) D/c line shall be required,
which is to be Implemented by PTCUL. In this regard, concurrence from PTCUL is
required, however, the same could not be obtained as representative from PTCUL
was not present in the meeting. It was agreed that the applicant shall approach
PTCUL and communicate the same to CTU, based on which connectivity shall be
granted.
CTU informed that Long Term Open Access has already been granted beyond
Kashipur and PTCUL shall sign the implementation agreement with the generator as
per the CERC guidelines.
Members agreed.
B) Projects for which Connectivity applied to CTU
iv. Connectivity to Pipalkoti Hydro project (444 MW) of M/s THDC India Ltd. in Uttarakhand
Discussed above at para 15. A) i
Members agreed for the same
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 17 of 20
C) Other Projects: It was deliberated that there are certain other projects who had
applied connectivity to PTCUL, however they had not applied LTA to CTU. In
addition some of the generation developers have neither applied for connectivity nor
LTA. PTCUL may impress upon those generators to apply for connectivity and LTA
to CTU.
Members noted the same.
14.0 Inter – Regional LTA Applications to NR
CTU informed that based on LTA applications and Central Sector allocations, total
power transfer requirement towards NR comes out to about 26000MW. If certain
uncertain/abandoned/closed applications are not considered, power transfer
requirement reduces to about 23500 MW. In addition to the import requirement of
NR assessed above, additional requirement of about 2500 MW power transfer to NR
is envisaged from following generation projects in WR (& SR):
Sl No.
Generation Projects Region Additional Allocation to NR (MW)
1 KSK Mahanadi Power Company Ltd WR 1000 (Firm)
2 MB Power (MP) Ltd. WR 200 (169MW Firm)
3 MB Power (MP) Ltd. WR 144
4 Suzlon Power Infrastructure Ltd. (3 applications, location of project in SR)
SR 120
5 SEI Sunshine Power Pvt. Ltd. WR 180
6 Rewa Ultra Mega Solar Ltd. WR 300
7 DB Power Chhattisgarh Ltd. WR 75 (Firm)
8 Maruti Clean Coal & Power Ltd * WR 205 (Firm)
9 TRN Energy Ltd * WR 240 (Firm)
Grand Total 2464
* TRN Energy and Maruti Clean Coal & Power Ltd. had submitted LTA applications against firm PPAs signed with beneficiaries in NR; however same were closed on account of incomplete applications.
CTU further stated that the above mentioned quantum of WR – NR power transfer, power transfer requirement of TRN, DBPCL and MCCPL has also been included in studies considering that they have firm PPA as they may apply afresh. In addition to above applications, LTA application of Barethi STPS indicates about 871MW power allocation to Northern Region. Hence, the total power transfer requirement to NR after considering above applications is likely to be about 26500-27000 MW.
CEA informed that the above was discussed during the 37th SCMPSPNR wherein UP raised the issue of lightly loaded ER-NR links. It was deliberated that since generation projects in WR (particularly in Chhattisgarh) and in Odisha, which have strong connectivity with WR (via Chhattisgarh), have materialized in time, the WR – NR corridor gets stressed.
Director, CEA further informed that during the 22nd meeting of WR constituents regarding Connectivity/Open Access held on 30.11.2015 following new inter-regional transmission corridor was agreed:
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 18 of 20
• Establishment of New 2x1500MVA, 765/400kV Substation at Allahabad
• Vindhyachal Pool – Allahabad (New) 765kV D/c line
• Allahabad (New) – Lucknow 765kV D/c line
• LILO of Sasaram – Fatehpur 765kV S/c line at Allahabad (New)
• LILO of Meja – Allahabad 400kV D/c line at Allahabad (New)*
* On the above CTU representative stated that while carrying out the above studies it was observed that Allahabad – Allahabad 400 kV D/c line becomes critically loaded. Accordingly in this case LILO of Allahabad – Kanpur 400 kV D/c line at Allahabad (New) has been considered and with this problem of critical loading of Allahabad – Allahabad (New) gets alleviated.
CEA further informed that constituents of WR had agreed that strengthening
between WR & NR is required to process the pending LTA applications, however,
considering the reservations expressed by UPPTCL, it was decided that a Sub-
committee comprising of CEA, UPPTCL & CTU shall be formed to discuss and
finalize the transmission strengthening scheme between WR & NR. It was also
decided that UPPTCL would submit their concern while finalizing the scheme.
It was agreed that based on the recommendations of above Sub-Committee, LTA to
the applicants may be granted in order of their priority in-line with CERC regulations.
Members agreed for the same
Meeting ended with a vote of Thanks
----x-------x------x----
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 19 of 20
Annexure-I
List of participants for the 8th
Connectivity/Long Term Access of Northern region
Constituents on 20.01.2016 at NRPC, Delhi.
Name Designation
NRPC 1. Sh. P. S. Mhaske Member Secretary
CEA 1. Sh. K.K. Arya Chief Engineer I/c (SP&PA)
2. Sh. Chandra Prakash Director
3. Ms. Manjari Chaturvedi Dy. Director
4. Sh. Priyam Srivastava Asstt. Director
5. Sh. Vikas Sahu Engineer
POWERGRID
1. Smt. Seema Gupta COO (CTU-Planning & CE)
2. Sh. Subir Sen ED(Smart Grid)
3. Sh. Mukesh Khanna AGM(CTU-Planning)
4. Sh. V. Thiagarajan DGM(CTU-Planning)
5. Sh. Kashish Bhambhani Chief Manager (Smart Grid)
6. Ms. Rashmi Pant Joshi Dy. Manager (CTU-Planning)
7. Ms. Ankita Singh Sr. Engineer (CTU-Planning)
8. Sh. Sandeep Kumawat Sr. Engineer (Smart Grid)
NRLDC, POSOCO 1. Sh. K.V.S Baba ED
2. Sh. Rajiv Porwal DGM
3. Ms Suruchi Jain Dy. Manager
4. Sh. Pradeep Reddy Sr. Engineer
NTPC 1. Sh. Vivek Kumar Dy. Manager (Commercial)
HPPTCL 1. Sh. Keshav Singh Director(Projects)
2. Sh. Sandeep Sharma DGM(Plg)
3. Sh. Kushal Chandel Dy. Manager
HVPNL 1. Sh. J.K Juneja Director (Technical)
2. Sh. Rakesh Garg XEN/Comml.
Seli Hydro Power Ltd. 1. Sh. Rajan Saklani AVP
2. Sh. Abhishek Gupta AGM
3. Sh. Ashish Gupta AM
Minutes for 8th Connectivity & Long Term Access Meeting with NR Constituents held on 20/01/2016
Page 20 of 20
NSL Tidong Power Generation (P) Ltd. 1. Srinivasulu Dy. Manager
2. B. Sakshi Dev AVP
Saurya Urja Company of Rajasthan Ltd. 1. Sh. S. C. Misra Adviser (Transmission)
Essel Saurya Urja comapny of Rajasthan Ltd.
1. Sh. Jagjeet Singh Sr. Manager
GMR Badrinath 1. Sh. G. Saraswat AVP- Transmission
2. Sh. Rishu Garg AM- Transmission
3. Sh. Rajbir Singh Manger-Transmission
SJVN Ltd. 1. Sh. Balwant Negi Manager
2. Sh. Rajeev Agarwal Manager
Jayprakash Power Ventures Ltd. 1. Sh. Sanjeev Goel General Manager
2. Sh. Sanjiv K. Goel Addl. General Manager
Adani Green Energy Ltd. 1. Sh. M.B Krishna Rao General Manager
Aditya Birla Nuvo Ltd. 1. Sh. Surajit Chanda DGM
Lanco Mandakini Hydro Energy Pvt. Ltd. 1. Sh. Jitendra Verma Manager
Indian Oil Corporation Ltd. 1. Sh. Pawan Rawat Sr. Manager