consolidation needs for the electrical distribution, control cables and optical fibres equipment f....

16
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

Upload: ralf-barnett

Post on 18-Jan-2018

216 views

Category:

Documents


0 download

DESCRIPTION

Why consolidation ? 3  Non compliance to present safety and technical norms  Ageing equipment everywhere  Well beyond manufacturer recommended lifetime (reliability)  Impossibility to find spares  Unsafe to manoeuver  Layered installation of equipment  Evolution through the addition of strata instead of an integrated approach  Radiation damage  Mostly cables and fibers but also emergency stops  Overcrowded passages and tray  Needs beyond the EL 2025 program (including major HV Upgrade & Consolidation projects) 12 September 2013Consolidation Day - François Duval EN-EL

TRANSCRIPT

Page 1: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

Consolidation needs for the Electrical Distribution, Control

Cables and Optical Fibres Equipment

F. Duval

Page 2: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

2 Consolidation Day - François Duval EN-EL

Outline

1. Boundary Conditions2. Methodology3. Domains of

Consolidation Cables Fibres High Voltage Network Low Voltage Network Controls General

4. Conclusion

12 September 2013

Page 3: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

3 Consolidation Day - François Duval EN-EL

Why consolidation ?

Non compliance to present safety and technical norms Ageing equipment everywhere

Well beyond manufacturer recommended lifetime (reliability) Impossibility to find spares Unsafe to manoeuver

Layered installation of equipment Evolution through the addition of strata instead of an

integrated approach Radiation damage

Mostly cables and fibers but also emergency stops Overcrowded passages and tray Needs beyond the EL 2025 program (including major

HV Upgrade & Consolidation projects)

12 September 2013

Page 4: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

4 Consolidation Day - François Duval EN-EL

Methodology

Study the different domains Risk analysis for each to

determine priority done or in preparation

The costs quoted are based on supply contracts and experience (e.g. cabling)

Systems thinking rather than replacing like with like

Every consolidation item is documented in detail in EDMS

12 September 2013

Page 5: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

5 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

SPS machineCritical state 1: Point 5 surface, shafts and

underground Point 4 surface, shafts and

underground Point 3 surface, shafts and

underground

Critical state 3: Point 6 surface, shafts and

underground Point 1 surface, shafts and

underground Point 2 surface, shafts and

underground Point 7 surface, shafts and

underground

Critical state 5: TT60, TT70

Shafts are the most critical areas for all points.

PS-Complex and Meyrin site Critical state 2: Bld.360-361 (under the Booster),

rooms BCER, BOR, BAT Bld.354, room CCR et MNR, gallery

815 Gallery TP9 between Bld.354 and

Bld.361 Bld.353 (ring centre) and tunnel of PS

Bld.350 accelerator TT2 entire tunnel (from Build. 269 to

TT2A towards nTOF)

Critical state 4: Bld.2001 (upstairs), cable

connections from Build.2008

Priorities for Cable Clean Up

Page 6: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

6 Consolidation Day - François Duval EN-EL

Domains of Consolidation

▶ Taking into account the LIU project and the priorities for overcrowded areas, we propose to clean up during LS2:▶ the booster complex ▶ the SPS-P5 during LS2

Concerns ~10’000 cables Total estimated cable length: 1500 km 14 MCHF 8 FTE

12 September 2013

Cable Clean UpCleanup cables on overcrowded areasCannot pull cables in the proper technical wayThis situation is general for SPSIn some cases, cables cannot be installed anymore

EDMS 1309198 & 1309230

Page 7: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

7 Consolidation Day - François Duval EN-EL

Domains of Consolidation

In order to exchange the cables in the irradiated areas of the SPS to ensure operation, two cable replacement campaigns similar to the one which is taking place in SPS TS1+ will have to be organized during LS2

These two areas will be selected after the conclusions of the RIAC and other constraints

The procurement of new cables for these campaigns will start already in 2016-2017.

The studies to prepare these campaigns as well as the procurement of cables will take place in advance of LS2 (2015-2017). The budget for these is included in this request.

Number of cables to be replaced: ~1200Total estimated cable length: 600 km 4 MCHF (1.1 MCHF already funded) 5 FTE

12 September 2013

Irradiated Cables

EDMS 1309192

Page 8: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

8 Consolidation Day - François Duval EN-EL

Domains of Consolidation

Consolidation of the network the dimensioning of the existing, CERN-wide, infrastructure to cope

with new users needs. This was until now mainly paid by the IT/CS Group.

the replacement of radiation sensitive fibres in all radiation areas

Total estimated cable length: 600 km 6 MCHF 10 FTE

12 September 2013

Fibres

EDMS 1309213

Page 9: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

9 Consolidation Day - François Duval EN-EL

Domains of Consolidation

Tools for management and monitoring

Creation and population of of an optical fibre database “Fibrothèque” based on the existing Cablothèque.

Implementation of an on-line transmission quality monitoring system based.

Total estimated 0.9 MCHF for the Fibrothèque 0.23 MCHF for the Online Monitoring ToolsBoth including manpower

12 September 2013

Fibres

EDMS 1311049

EDMS 1309232

Page 10: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

10 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

High Voltage Network Consolidation of old protection

relays Necessary upgrade on functionalities after

the consolidation of the 66 kV protection system (communication, differential..)

Poor reliability due to ageing of electronic components (e.g. drift of time constants)

200 relays to be replaced, 4 MCHF

Consolidation of the 400 kV protection system

RTE now requires an additional breaker (incomer) in order to comply with the French regulations

Consolidation of the protection system: Necessary upgrade on functionalities after the

consolidation of the 66 kV protection system (communication, differential..)

Separation from 18 kV pulsed system (room, 48Vdc, etc.)

1,5 MCHF

CERN

RTE

EDMS 1309170

EDMS 1309158

Page 11: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

11 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

High Voltage Network Consolidation of the PS and administrative areas in Meyrin:Necessary to withstand increasing short circuit current and necessary to extend switchboards not anymore available on the market.

Consolidation of two substations (ME16 & ME49) Operation problems Old cubicles will be reused as spares

Consolidation of HV power cables Larger section External insulation in very bad shape

Consolidation of distribution transformers Cope with present power demand Continuous effort to eliminate non compliant transformers Switch from oil transformers to dry type Oil transformer pits not compliant with CERN safety rules

2 MCHF EDMS 1312515

Page 12: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

12 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

High Voltage Network Consolidation of Meyrin Diesel

Generators No more spares for the generator sets The cooling system and various mechanical

components are at the end of their lifetime 3MCHF

Consolidation LHC Diesel control Diesel system reliability decreasing (see monthly

test reports) Control system needs upgrade (com, safe

connection, etc.) 0.5 MCHF

SPS and Meyrin Safety network Following the upgrades and consolidations in the

SPS and in Prevessin, install power cables, reorganize the BKs, modify control system accordingly

1 MCHF

EDMS 1310817

EDMS 1312490

EDMS 1312490

Page 13: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

13 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

Low Voltage Network Consolidation of the Distribution

networks Consolidation based on risk analysis and fleet

assessment Consolidation of the whole distribution system

according to present and future needs 208 switchboards to be replaced until 2020 30 MCHF

Consolidation of the 48 Vdc distribution systems

Consolidation based on risk analysis and fleet assessment

Redesign of the complete system (redundancy, LED based safety lighting)

Upgrade of functionalities (double supply, separate battery pack, by-pass functionalities, etc.)

27 systems will be replaced 4.5 MCHF

EDMS 1306444, 1306452 & 1306435

EDMS 1311131

Page 14: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

14 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

Controls Consolidation of the PLC

system The evolution of the network requires

modifications of some of the PLC functionalities

No spares for ageing PLC systems 5 PLC systems will be consolidated

(ATLAS Diesels, Autotransfert, Normal/Secours at LHC1)

0.42 MCHF

Consolidation of the local SCADA infrastructure

Replacement of the RTUs by a local SCADA,

33 substations (or group of substation) will be consolidated

2 MCHF EDMS 1310618

EDMS 1306576

Page 15: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

15 Consolidation Day - François Duval EN-EL

Domains of Consolidation

12 September 2013

General North area consolidation

Inside the global North Area Consolidation project

23 switchboards and 9 UPSs will be replaced and adapted to the new power, space, etc. requirements

5.9 MCHF

Consolidation of the AUG chains Replacement of 20 racks and 1800

buttons, Redesign of AUG chains (1’500 buttons) Suppression of 400 superfluous buttons

mainly in LHC surface buildings. Replacement of ~400 membranes 1.6 MCHF

EDMS 1309894

EDMS 1312090

Page 16: Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval

16 Consolidation Day - François Duval EN-EL

… in summary

Domain Budget [MCHF]Cables 18Fibres 7.13High Voltage Network

12

Low Voltage Network

34.5

Controls 2.42General 7.5

12 September 2013

The Consolidation Programme addresses the items which are urgent to ensure safe and reliable operation of the Electrical Distribution Network as well as the control cable and optical fibre infrastructures

Resources for LS2 is an issue…..