Construction Activity Notification COS Main Terminal Apron Pavement Rehabilitation CAN #01 Issue Date: 03/08/2016 Project Information Project Title COS Main Terminal Apron Pavement Rehabilitation Contractor Interstate Highway Construction (IHC) Work Location Main Terminal Apron and Secured SIDA Activity Title Concrete pavement rehabilitation of the main terminal apron Activity Description Pavement and trench drain repair, select concrete panel removal and replacement at the terminal apron. Temporary airline gate relocation. The entire project duration has multiple construction phases starting 03/14/2016 through 08/01/2016, construction activity notifications will be issued identifying affected closed areas and timelines for each phase. Facility/System Impacts Construction activity consists of pavement and trench drain repair, select concrete panel removal and replacement at the terminal apron. The West Terminal Apron and Taxiway-P will be closed to all aircraft traffic from 03/14/2016 – 03/29/2016. Construction activity will occur primarily from 0600 to 1900 hours local time, TSA/COS-Airport security and safety measures will be in effect at all times. Refer to the construction plan (page-2 below) for apron vehicle/equipment traffic, to use established vehicle service routes. Start Date / Time March 14, 2016 / 0600 hours (construction activity) End Date / Time March 29, 2016 / 0600 hours (construction activity) Activity Contact List Role Name Contact Airport Project Manager Sam Schneiter 719-550-1907 or [email protected] Contractor Project Manager Jim Klemperer Engineer Project Manager Alex McKean (RS&H) 303-409-7915 Airport Operations Airport Communications Center 719-550-1918 or -1919 For apron vehicle/equipment traffic see Page-2, Construction Access and Safety Plan (Sheet C007). For aircraft deicing operations during this west apron closure, see Page-3 Deice Plan (Exhibit I). COS.2016_Ramp.Rehab-PH.IA.docx, Page 1 of 3

Upload: others

Post on 04-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction Activity Notification - Colorado Springs...through 08/01/2016, construction activity notifications will be issued identifying affected closed areas and timelines for each

Construction Activity Notification

COS Main Terminal Apron Pavement Rehabilitation

CAN #01 Issue Date: 03/08/2016 Project Information

Project Title COS Main Terminal Apron Pavement Rehabilitation Contractor Interstate Highway Construction (IHC) Work Location Main Terminal Apron and Secured SIDA Activity Title Concrete pavement rehabilitation of the main terminal apron Activity Description Pavement and trench drain repair, select concrete panel removal and replacement

at the terminal apron. Temporary airline gate relocation. The entire project duration has multiple construction phases starting 03/14/2016 through 08/01/2016, construction activity notifications will be issued identifying affected closed areas and timelines for each phase.

Facility/System Impacts Construction activity consists of pavement and trench drain repair, select concrete panel removal and replacement at the terminal apron. The West Terminal Apron and Taxiway-P will be closed to all aircraft traffic from 03/14/2016 – 03/29/2016. Construction activity will occur primarily from 0600 to 1900 hours local time, TSA/COS-Airport security and safety measures will be in effect at all times. Refer to the construction plan (page-2 below) for apron vehicle/equipment traffic, to use established vehicle service routes.

Start Date / Time March 14, 2016 / 0600 hours (construction activity) End Date / Time March 29, 2016 / 0600 hours (construction activity) Activity Contact List

Role Name Contact Airport Project Manager Sam Schneiter 719-550-1907 or [email protected]

Contractor Project Manager Jim Klemperer Engineer Project Manager Alex McKean (RS&H) 303-409-7915

Airport Operations Airport Communications Center 719-550-1918 or -1919 For apron vehicle/equipment traffic see Page-2, Construction Access and Safety Plan (Sheet C007). For aircraft deicing operations during this west apron closure, see Page-3 Deice Plan (Exhibit I).

COS.2016_Ramp.Rehab-PH.IA.docx, Page 1 of 3