construction (design and management) regulations 2015...

18
Copyright of RSK 03 December 2015 1 Construction (Design and Management) Regulations 2015 (CDM) Nicola Rose Senior EHS Consultant

Upload: lynhan

Post on 29-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Copyright of RSK 03 December 2015 1

Construction (Design and Management) Regulations 2015 (CDM)

Nicola Rose Senior EHS Consultant

Copyright of RSK

Construction safety statistics

How safe is construction?

In 2013/14,

Construction industry accounts for 5% of all UK employees, but 31% of fatalities

76,000 cases of work-related ill health

2.3 million working days lost (of which 1.7 million due to ill health and remainder to injury)

03 December 2015 2

Copyright of RSK

Occupational ill health

03 December 2015 3

Type of ill health Notes

Work-related ill health Construction 30% higher than national average

Musculoskeletal disorders Almost double national average

Self-reported mental ill health (stress, depression, anxiety) Half national average

Respiratory diseases

12,000 deaths per year across all industries, of which 2/3 attributable to asbestos and COPD Over 40% of all occupational cancers were in construction. Of these, nearly 70% attributable to asbestos.

Copyright of RSK

Background

HSE review of CDM 2007 conducted in 2011:

CDM well-embedded at more organised level of construction industry, but

Poorly embedded at smaller end

Non-alignment of CDM 2007 with the European Directive 92/57/EEC - Temporary or Mobile Construction Sites, in relation to

Application to domestic clients

Threshold for notification

Threshold for appointment of coordinators

2014 consultation on changes to CDM 2007

03 December 2015 4

Copyright of RSK 03 December 2015 5

Timeline

CDM 2015 came into force for new projects on 6 April 2015

Transitional arrangements for existing projects between 6 April and 6 October 2015 – now finished

The end of the CDM-C?

Review of the Temporary or Mobile Construction Sites Directive

Copyright of RSK

Key changes

Creation of new duty holder – principal designer

End of CDM-C role, allocation of duties to clients and principal designers

Decrease in threshold for appointment of coordinators (PD and PC)

Increase in threshold for notification

Requirement for construction phase plan for all construction projects

Replacement of the ACoP with guidance

Removal of detailed guidelines on competence

Application (limited) to domestic clients

03 December 2015 6

Copyright of RSK

CDM coordinators/ principal designers

2014 consultation document:

“There is a widely held view … that the current approach [i.e. CDM-C] is often bureaucratic and adds costs with little added value. [CDM-Cs] are often not well embedded into the pre-construction project team.

[ HSE] therefore aim[s] to replace the role with one called the ‘principal designer’ (PD). The responsibility for discharging the function will rest with an individual or business in control of the preconstruction phase. It is this element of control and influence over the design which are the fundamental differences between the CDM-C role and the PD role. The default position will be that the responsibility for discharging of the function is within the existing project team...”

03 December 2015 7

Copyright of RSK

Principal designers

Must be appointed on any project where two or more contractors expected

Appointed in writing

Designer with control of the project design phase

Must be a designer or project manager (somebody who appoints designers)

Coordination of H&S design review

Ensure that designers comply with CDM, give due consideration to H&S and cooperate with other parties

If the client does not appoint a PD, the client must discharge the PD duties

03 December 2015 8

Copyright of RSK

New client duties

Client duties under CDM2015 have increased, with some of the previous CDM-C duties allocated to the client.

New client duties:

Provide preconstruction information

File F10 notification to HSE;

Appoint a principal designer and a principal contractor if there will be more than one contractor working on the project

03 December 2015 9

Copyright of RSK

Notification of project: F10

Client’s duty to file F10 as soon as practicable before construction begins

Notification applies where project

likely to last more than 30 days AND more than 20 workers simultaneously on site, OR

likely to last more than 500 person days

03 December 2015 10

Copyright of RSK

CDM 2015: Notifiable and non-notifiable projects

Significant change!

Under CDM 2007, there was a two-tier system: “notifiable” and “non-notifiable” projects. The threshold for notification and the threshold for appointment of CDM-C and principal contractor were the same, i.e. projects over 30 days or 500 person days.

Under CDM 2015, the threshold for appointment of principal designer and principal contractor and for notification to HSE have both changed and are no longer linked.

03 December 2015 11

Copyright of RSK

Construction health and safety plan

The client must ensure that construction does not commence until the principal contractor (or contractor if there is only one) has developed a construction-phase health and safety plan (CPHSP).

Under CDM 2007, the CDM coordinator reviewed the CPHSP on behalf of the client. Under CDM 2015, there is no express requirement for the client or principal designer to review the CPHSP.

03 December 2015 12

Copyright of RSK

Health and safety file

Initially prepared by the principal designer during the preconstruction phase

If the principal designer’s appointment finishes before construction is complete, the principal contractor becomes responsible for the health and safety file.

03 December 2015 13

Copyright of RSK

Implications for developers

Client duties have increased. Therefore…

Principal designer: in-house, lead designer or independent?

Construction-phase plan: who will review?

Preconstruction information: agree who will collate

F10 notification: agree who will complete

03 December 2015 14

Copyright of RSK

CDM prosecutions: CDM Regulations

As of early 2014, there had been at least 368 prosecutions since CDM started in 1994. Principal issues:

Asbestos

Services

Falls from height/roofs

Structural erection

Excavation

Work near public

Fines range from £1 to £125,000

Note also: fee for intervention

03 December 2015 15

Copyright of RSK

CDM prosecutions 1995–2011 by duty holder: 368 total cases

03 December 2015 16

Client, 48%

Principal contractor, 28%

CDM-C, 7%

Designer, 6%

Contractor, 5%CDM Part 4, 6%

ClientPrincipal contractorCDM-CDesignerContractorCDM Part 4

Copyright of RSK 03 December 2015 17

Q & A

Copyright of RSK 03 December 2015 18