construction disputes and their settlement

Upload: abhinav-kalathiparambil

Post on 04-Apr-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Construction Disputes and Their Settlement

    1/19

    Construction Disputes and

    their SettlementBUILDING TECHNOLOGY AND

    MANAGEMENT

  • 7/31/2019 Construction Disputes and Their Settlement

    2/19

    Development of Disputes

    Natural phenomenon!

    Interpretation of contract clauses

    Difference in opinion regarding the execution of

    the work

    Unforeseen problems

    2

  • 7/31/2019 Construction Disputes and Their Settlement

    3/19

    Types of Construction Disputes

    Claims of Contractor against Owner/Client

    Claims of Owner/Client against Contractor

    Sub-contractors claims

    3

    Claim: Demand for something considered ones due

  • 7/31/2019 Construction Disputes and Their Settlement

    4/19

    Claims of Contractor against Owner/Client

    Claims to recover damages caused by breach of

    conditions by the owner

    Claims to recover loss or damage caused by an

    unjust termination of the contract by the owner

    Claims to recover damages upon rescinding of the

    contract due to frustration

    4

  • 7/31/2019 Construction Disputes and Their Settlement

    5/19

    Claim Generating Circumstances

    1. Delay in the supply of drawings and clarifications

    2. Defects in the specifications furnished

    3. Delay/manufacturing defects inmaterials/equipment supplied by the owner

    4. Changes in law, regulations or codes subsequentto the award of the contract

    5. Changed or differing site conditions

    6. Delay due to other contractors work

    7. Acceleration in work demanded by the owner8. Defects in the contract agreement

    9. Inordinate delay in the release of payments

    10.Unjustified termination of the contractor by the

    owner 5

  • 7/31/2019 Construction Disputes and Their Settlement

    6/19

    11. Substantial delay in handing over the site

    12. Owners failure in his implied duties

    13. Unreasonable rejection of acceptable work

    14. Delay in clearances

    15. Suspension of work by the owner for his ownconvenience

    16. Rescheduling/prolonging work for financial andother reasons

    17. Work arising during maintenance period, which isnot covered by the contractors obligations

    18. Owners delay in decision overamendments/change orders

    19. Quantity variations, for which provision is notmade in the contract

    6

  • 7/31/2019 Construction Disputes and Their Settlement

    7/19

    20. Failure by sub-contractors nominated by the

    owner

    21. Stipulations of near-impossibilities for compliance

    or incorporation into the contract work

    22. Natural calamities

    23. Force Majeure

    7

  • 7/31/2019 Construction Disputes and Their Settlement

    8/19

    Claims of Owner/Client against Contractor

    Claims for defective work done by the contractor

    Claims for delay caused by the contractor

    Counter-claim as a defense

    Claim against professionals

    Claims following termination and breach

    Claims for expenditure incurred in completing the

    work left incomplete or abandoned by the

    contractor

    Claims for liquidated damages8

  • 7/31/2019 Construction Disputes and Their Settlement

    9/19

    Owners Claim Procedure

    Engineers Comments Consultants Comments

    Claims Committees Recommendation

    Top Managements Approval

    Claim Initiation by the Client/Owner

    Excusable Delays

    9

  • 7/31/2019 Construction Disputes and Their Settlement

    10/19

    Modes of Settlement of Disputes

    By direct negotiations between the client and the

    contractor

    Settlement by arbitration

    Through civil courts

    10

  • 7/31/2019 Construction Disputes and Their Settlement

    11/19

    Direct Negotiations

    Easiest and least expensive

    Majority of the disputes are settled through

    negotiations

    Arbitration is sought after, only if direct

    negotiations fail

    11

  • 7/31/2019 Construction Disputes and Their Settlement

    12/19

    Settlement Through Courts

    Last resort

    Attempted only if direct negotiation and

    arbitration fails

    Time consuming, to the tune of several years

    Expensive

    12

  • 7/31/2019 Construction Disputes and Their Settlement

    13/19

    Settlement Through Arbitration

    Arbitrationis the hearing and determination of

    a dispute by an impartial referee selected by theparties concerned.

    Arbitratoris a person chosen by the concernedparties to pronounce judgment on the dispute.

    Sole Arbitrator

    Joint Arbitrators

    13

  • 7/31/2019 Construction Disputes and Their Settlement

    14/19

    Advantages of Arbitration over Litigation

    1. Cost

    2. Speed

    3. Convenience

    4. Technical knowledge

    5. Informality

    6. Proceedings in private premises

    7. Finality of award

    14

  • 7/31/2019 Construction Disputes and Their Settlement

    15/19

    Indian Arbitration Act 1940

    Arbitration without intervention of a court

    Arbitration with intervention of a court

    Arbitration in lawsuits

    15

    Provides for arbitration in the following three cases:

  • 7/31/2019 Construction Disputes and Their Settlement

    16/19

    The Act:

    does not dictate the form of arbitration to be

    adopted

    does not prescribe the procedure for arbitration

    does not interfere with the award given by the

    arbitrator

    does not require the arbitrator to state reasons in

    support of his ruling

    16

  • 7/31/2019 Construction Disputes and Their Settlement

    17/19

    Arbitration Clause

    1. All disputes will be settled through arbitration in

    accordance with the Indian Arbitration Act, 1940

    2. The parties may appoint a single arbitrator or

    each party may nominate an arbitrator and thetwo nominated arbitrators may mutually select an

    umpire

    3. The parties will mutually agree regarding the

    sharing of arbitration fees and expenses

    17

  • 7/31/2019 Construction Disputes and Their Settlement

    18/19

    4 The arbitration proceedings will be conducted by

    the arbitrator(s) in accordance with laid down

    procedures, at mutually convenient places and

    dates

    5 If difference in opinion arises between the twoarbitrators, the decision of the umpire will be

    final

    6 The arbitration award will be final and bindingupon both parties

    18

  • 7/31/2019 Construction Disputes and Their Settlement

    19/19

    Reference

    o

    Joy, PK, Handbook of Construction Management,MacMillan India

    o Patil, BS, Civil Engineering Contracts and

    Estimates, Universities Press

    o Gahlot, PS and BM Dhir, Construction Planning and

    Management, New Age International

    o Gupta, BL and A Gupta, Construction Management

    and Machinery, Standard Publishers

    19