construction methods of embankments on soft soils - … · material, considering the ... the...

13
Chapter 1 Construction methods of embankments on soft soils The most appropriate construction method to be used in a given project is associated with factors such as geotechnical characteristics of deposits, use of the area, construc- tion deadlines and costs involved. Figure 1.1 presents some construction methods of embankments on soft soils. Some methods contemplate settlement control and oth- ers stability control, but most methods contemplate both issues. In the case of very soft soils, it is common to use geosynthetic reinforcement associated with most of the alternatives presented in Figure 1.1. Time constraints may render inadequate techniques such as conventional embank- ments (Figure 1.1A,B,C,D,M) or embankments over vertical drains (Figure 1.1K,L), favoring embankments on pile-like elements (Figure 1.1F,G,H) or lightweight fills (Figure 1.1E), which, however, may have higher costs. Removal of soft soil can be used when the layer is not very thick (Figure 1.1I,J) and the transport distances are not considerable. In urban areas, it is difficult to find areas for the disposal of excavated material, considering the environmental issue associated with this disposal. Space constraints can also prevent the use of berms (Figure 1.1B), particularly in the case of urban areas. The geometry of the embankments and the geotechnical characteristics are highly variable factors and the construction methodology must be analyzed case by case. 1.1 REPLACEMENT OF SOFT SOILS AND DISPLACEMENT FILLS 1.1.1 Replacement of soft soils Replacement of soft soils is the partial or total removal (Figure 1.1I,J) of these soils using draglines or excavators or the direct placement of landfill to replace the soft soil. This construction method, generally used in deposits with compressible soil thicknesses of up to 4 m, has the advantage of reducing or eliminating settlements and increasing the safety factor against failure. Initially, a working platform is set up to level the terrain, just to allow the access of equipment (Figure 1.2A,B), right after the dredger starts excavating the soft soil, followed by the filling of the excavated space with fill material (Figure 1.2C,D). Due to the very low support capacity of the top clay layers, these steps must be performed very carefully, and the equipment should be light. For very soft soils, it is noted that service roads suffer continuous settlements, as a result of the overload of Copyrighted C most approp most approp tors such as tors such as nes and cos nes and cos on soft so on soft so trol, but m trol, but m mon to use mon to use in Figure in Figure y re y re Material 1 1 nder ina nder ina ) or emba ) or emba like elem like elem ay have h ay have h Figure 1.1 Figure 1.1 lt to fin lt to fin ue ue - as as se se Tay ocia ocia e of berm e of berm aylor he embankm he embankm constructio constructio & AC AC Francis EMEN EMEN of these s of these s s e soft so e soft so kn kn

Upload: vothuan

Post on 22-May-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Chapter 1

Construction methods of embankmentson soft soils

The most appropriate construction method to be used in a given project is associatedwith factors such as geotechnical characteristics of deposits, use of the area, construc-tion deadlines and costs involved. Figure 1.1 presents some construction methods ofembankments on soft soils. Some methods contemplate settlement control and oth-ers stability control, but most methods contemplate both issues. In the case of verysoft soils, it is common to use geosynthetic reinforcement associated with most of thealternatives presented in Figure 1.1.

Time constraints may render inadequate techniques such as conventional embank-ments (Figure 1.1A,B,C,D,M) or embankments over vertical drains (Figure 1.1K,L),favoring embankments on pile-like elements (Figure 1.1F,G,H) or lightweight fills(Figure 1.1E), which, however, may have higher costs. Removal of soft soil can beused when the layer is not very thick (Figure 1.1I,J) and the transport distances are notconsiderable. In urban areas, it is difficult to find areas for the disposal of excavatedmaterial, considering the environmental issue associated with this disposal.

Space constraints can also prevent the use of berms (Figure 1.1B), particularlyin the case of urban areas. The geometry of the embankments and the geotechnicalcharacteristics are highly variable factors and the construction methodology must beanalyzed case by case.

1.1 REPLACEMENT OF SOFT SOILS AND DISPLACEMENT FILLS

1.1.1 Replacement of soft soils

Replacement of soft soils is the partial or total removal (Figure 1.1I,J) of these soilsusing draglines or excavators or the direct placement of landfill to replace the soft soil.This construction method, generally used in deposits with compressible soil thicknessesof up to 4 m, has the advantage of reducing or eliminating settlements and increasingthe safety factor against failure. Initially, a working platform is set up to level theterrain, just to allow the access of equipment (Figure 1.2A,B), right after the dredgerstarts excavating the soft soil, followed by the filling of the excavated space with fillmaterial (Figure 1.2C,D).

Due to the very low support capacity of the top clay layers, these steps must beperformed very carefully, and the equipment should be light. For very soft soils, it isnoted that service roads suffer continuous settlements, as a result of the overload of

Copyrighted

Copyrighted

The most appropriate construction method to be used in a given project is associated

Copyrighted

The most appropriate construction method to be used in a given project is associatedwith factors such as geotechnical characteristics of deposits, use of the area, construc-

Copyrighted

with factors such as geotechnical characteristics of deposits, use of the area, construc-tion deadlines and costs involved. Figure 1.1 presents some construction methods of

Copyrighted

tion deadlines and costs involved. Figure 1.1 presents some construction methods ofembankments on soft soils. Some methods contemplate settlement control and oth-

Copyrighted embankments on soft soils. Some methods contemplate settlement control and oth-ers stability control, but most methods contemplate both issues. In the case of very

Copyrighted ers stability control, but most methods contemplate both issues. In the case of verysoft soils, it is common to use geosynthetic reinforcement associated with most of the

Copyrighted soft soils, it is common to use geosynthetic reinforcement associated with most of thealternatives presented in Figure 1.1.

Copyrighted alternatives presented in Figure 1.1.Time constraints may render inadequate techniques such as conventional embank-

Copyrighted Time constraints may render inadequate techniques such as conventional embank-Material

alternatives presented in Figure 1.1.Material

alternatives presented in Figure 1.1.Time constraints may render inadequate techniques such as conventional embank-Material

Time constraints may render inadequate techniques such as conventional embank-ments (Figure 1.1A,B,C,D,M) or embankments over vertical drains (Figure 1.1K,L),

Material

ments (Figure 1.1A,B,C,D,M) or embankments over vertical drains (Figure 1.1K,L),favoring embankments on pile-like elements (Figure 1.1F,G,H) or lightweight fills

Material favoring embankments on pile-like elements (Figure 1.1F,G,H) or lightweight fills(Figure 1.1E), which, however, may have higher costs. Removal of soft soil can be

Material (Figure 1.1E), which, however, may have higher costs. Removal of soft soil can beused when the layer is not very thick (Figure 1.1I,J) and the transport distances are not

Material used when the layer is not very thick (Figure 1.1I,J) and the transport distances are notconsiderable. In urban areas, it is difficult to find areas for the disposal of excavated

Material considerable. In urban areas, it is difficult to find areas for the disposal of excavatedmaterial, considering the environmental issue associated with this disposal.

Material material, considering the environmental issue associated with this disposal.- material, considering the environmental issue associated with this disposal.- material, considering the environmental issue associated with this disposal.

Space constraints can also prevent the use of berms (Figure 1.1B), particularly-

Space constraints can also prevent the use of berms (Figure 1.1B), particularlyTaylor

material, considering the environmental issue associated with this disposal.Taylor

material, considering the environmental issue associated with this disposal.Space constraints can also prevent the use of berms (Figure 1.1B), particularlyTaylor

Space constraints can also prevent the use of berms (Figure 1.1B), particularlyTaylor in the case of urban areas. The geometry of the embankments and the geotechnical

Taylor in the case of urban areas. The geometry of the embankments and the geotechnicalcharacteristics are highly variable factors and the construction methodology must be

Taylor characteristics are highly variable factors and the construction methodology must be

& 1.1 REPLACEMENT OF SOFT SOILS AND DISPLACEMENT FILLS

& 1.1 REPLACEMENT OF SOFT SOILS AND DISPLACEMENT FILLSFrancis

1.1 REPLACEMENT OF SOFT SOILS AND DISPLACEMENT FILLSFrancis

1.1 REPLACEMENT OF SOFT SOILS AND DISPLACEMENT FILLS

Replacement of soft soils is the partial or total removal (Figure 1.1I,J) of these soils

FrancisReplacement of soft soils is the partial or total removal (Figure 1.1I,J) of these soils

Francisusing draglines or excavators or the direct placement of landfill to replace the soft soil.

Francisusing draglines or excavators or the direct placement of landfill to replace the soft soil.This construction method, generally used in deposits with compressible soil thicknesses

FrancisThis construction method, generally used in deposits with compressible soil thicknesses

Page 2: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Figu

re1.

1C

onst

ruct

ion

met

hods

ofem

bank

men

tson

soft

soils

(ada

pted

from

Lero

ueil,

1997

).

Copyrighted

Copyrighted Material - Taylor & Francis

FrancisFigure1.

1

FrancisFigure1.

1

Page 3: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Construction methods of embankments on soft soils 3

Figure 1.2 Execution schedule for soft soil replacement: (A) and (B) excavation and removal of softsoil; (C) and (D) filling of the hole; (E) replaced soil (final condition).

equipment traffic. Shortly after, the hole is completely filled with fill material (Figure1.2E), then, it is necessary to verify the thicknesses of the remaining soft clay throughboreholes.

1.1.2 Displacement fills

The displacement of soft soils can be accomplished with the embankment’s own weight.This technique is called displacement fill, which is the advancement of the frontal partof the embankment, which should be higher than the designed embankment. Thiswill push and expel part of the soft soil layer, causing its rupture and leaving theembedded fill in its place (Zayen et al., 2003). The expulsion is facilitated by thelateral and frontal release of the tip fill, as shown schematically in Figure 1.3. Thisconstruction method can be used on the periphery of the area of interest by confiningthe internal area, allowing the embankment in this area to be constructed with a greaterthicknesses.

The thickness of the remaining soft soil must be evaluated through boreholescarried out after the excavation. If there is any remaining soft soil with thicknessgreater than the desirable, a temporary surcharge shall be applied to eliminate postconstruction settlements.

One disadvantage of the replacement and displacement methods is the difficulty inquality control, because there is no guarantee that soft material will be removed evenly,

Copyrighted

Copyrighted Material

Material Execution schedule for soft soil replacement: (A) and (B) excavation and removal of soft

Material Execution schedule for soft soil replacement: (A) and (B) excavation and removal of softsoil; (C) and (D) filling of the hole; (E) replaced soil (final condition).

Material soil; (C) and (D) filling of the hole; (E) replaced soil (final condition).

- equipment traffic. Shortly after, the hole is completely filled with fill material (Figure- equipment traffic. Shortly after, the hole is completely filled with fill material (FigureTaylor

equipment traffic. Shortly after, the hole is completely filled with fill material (FigureTaylor

equipment traffic. Shortly after, the hole is completely filled with fill material (Figure1.2E), then, it is necessary to verify the thicknesses of the remaining soft clay through

Taylor 1.2E), then, it is necessary to verify the thicknesses of the remaining soft clay through

& The displacement of soft soils can be accomplished with the embankment’s own weight.& The displacement of soft soils can be accomplished with the embankment’s own weight.Francis

The displacement of soft soils can be accomplished with the embankment’s own weight.Francis

The displacement of soft soils can be accomplished with the embankment’s own weight.This technique is called displacement fill, which is the advancement of the frontal part

FrancisThis technique is called displacement fill, which is the advancement of the frontal partof the embankment, which should be higher than the designed embankment. This

Francisof the embankment, which should be higher than the designed embankment. This

Franciswill push and expel part of the soft soil layer, causing its rupture and leaving the

Franciswill push and expel part of the soft soil layer, causing its rupture and leaving theembedded fill in its place (Zayen et al., 2003). The expulsion is facilitated by the

Francisembedded fill in its place (Zayen et al., 2003). The expulsion is facilitated by the

Francislateral and frontal release of the tip fill, as shown schematically in Figure 1.3. This

Francislateral and frontal release of the tip fill, as shown schematically in Figure 1.3. This

Page 4: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

4 Design and Performance of Embankments on Very Soft Soils

Figure 1.3 Execution methodology of displacement fill at periphery: (A) plan; (B) cross section (Zayenet al., 2003).

which may cause differential settlements. Another disadvantage is associated with highvolumes of disposed material and the difficulty of disposal, mainly in urban areas, asit is a material that cannot be reused and in certain cases may even be contaminated.

Working platform

Working platforms, shown in Figure 1.4, are constructed to allow the access of heavyequipment in general for vertical drains installation and pile driving in case of piledembankments for instance. In some cases, the strength of the upper layer is so lowthat it is necessary to use constructive geotextiles reinforcement, with tensile strength

Copyrighted

Copyrighted Material - Taylor & Francis

FrancisExecution methodology of displacement fill at periphery: (A) plan; (B) cross section (Zayen

FrancisExecution methodology of displacement fill at periphery: (A) plan; (B) cross section (Zayen

which may cause differential settlements. Another disadvantage is associated with high

Franciswhich may cause differential settlements. Another disadvantage is associated with high

Page 5: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Construction methods of embankments on soft soils 5

Figure 1.4 Construction of a working platform and vertical drain installation.

between 30 kN/m and 80 kN/m to minimize the loss of fill material (Almeida et al.,2008c).

1.2 CONVENTIONAL EMBANKMENT WITHTEMPORARY SURCHARGE

A conventional embankment is one constructed without any specific settlement orstability control devices. The conventional embankment may be constructed withtemporary surcharge (Figure 1.1M), whose function is to speed up the primary settle-ments and offset all or part of the secondary settlements caused by viscous phenomenanot related to the dissipation of pore pressures. The temporary surcharge method isdiscussed in Chapter 5.

One disadvantage of this construction method is the long time necessary for settle-ment stabilization in low permeability very soft deposits. Therefore, one must assessthe evolution of post construction settlements so that the necessary maintenance isplaned.

Another disadvantage of using surcharge is the large amount of related earthworksassociated. When the estimated settlements are reached, the temporary surcharge isremoved and the removed material can be used as fill in another location, as describedin detail in Chapter 5.

Copyrighted Material

Material Construction of a working platform and vertical drain installation.

Material Construction of a working platform and vertical drain installation.- between 30 kN/m and 80 kN/m to minimize the loss of fill material (Almeida et al.,

- between 30 kN/m and 80 kN/m to minimize the loss of fill material (Almeida et al.,Taylor

between 30 kN/m and 80 kN/m to minimize the loss of fill material (Almeida et al.,Taylor

between 30 kN/m and 80 kN/m to minimize the loss of fill material (Almeida et al.,

& FrancisA conventional embankment is one constructed without any specific settlement or

FrancisA conventional embankment is one constructed without any specific settlement orstability control devices. The conventional embankment may be constructed with

Francisstability control devices. The conventional embankment may be constructed withtemporary surcharge (Figure 1.1M), whose function is to speed up the primary settle-

Francistemporary surcharge (Figure 1.1M), whose function is to speed up the primary settle-ments and offset all or part of the secondary settlements caused by viscous phenomena

Francisments and offset all or part of the secondary settlements caused by viscous phenomenanot related to the dissipation of pore pressures. The temporary surcharge method is

Francisnot related to the dissipation of pore pressures. The temporary surcharge method is

Page 6: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

6 Design and Performance of Embankments on Very Soft Soils

1.3 EMBANKMENTS BUILT IN STAGES, EMBANKMENTS WITHLATERAL BERMS AND REINFORCED EMBANKMENTS

When the undrained strength of the upper layers of soft deposit is very low, one shouldconsider the reduction of the embankment height (Figure 1.1D). However, this reduc-tion may not be feasible, due to requirements regarding either regional flood levels, orthe geometric project of the road. In such cases, due to the low safety factor againstfailure, the construction of the embankment (with surcharge) may not be possible ina single stage.

The construction of the embankment in stages (Figure 1.1C), which allows thegradual gain of clay strength over time, is then a construction alternative. Stabilitymust be verified for each stage, and for this evaluation, it is necessary to monitor theoverall performance by means of geotechnical instrumentation and in situ tests for thenecessary adjustments to the project. The increase of the clay undrained strength pre-viously estimated in the design phase should then be verified through vane tests carriedout before performing each construction stage. Construction in stages is discussed inChapters 4 and 6.

The use of equilibrium berms (Figure 1.1B) is another solution that can be adoptedto increase the safety factor (Fs) regarding failure. When there are restrictions as tothe length of berms, or to reduce the amount of earthworks, a basal reinforcement(e.g., Magnani et al., 2009, 2010) may be installed (Figure 1.1A) with the goal ofincreasing the Fs and better distributing stresses. These two solutions to increase the Fs

are addressed in the Chapter 6. The geosynthetic reinforcement must be installed afterthe installation of the vertical drains to avoid mechanical damage to the reinforcement.

1.4 EMBANKMENT ON VERTICAL DRAINS

The early vertical drains used were sand drains, which were subsequently replaced byPrefabricated vertical drains, (PVDs). The PVDs consist of a plastic core with channel-shaped grooves, encased in a low weight nonwoven geosynthetic filter, as shown inFigure 1.5A.

The drainage blanket of embankments over PVDs, is initially constructed, whichalso functions as a working platform (Figure 1.4), followed by the PVD installationand the construction of the embankment. In the driving process, the PVD is attachedto a driving footing, which ensures that the end of the PVD is well fixed at the bottomof the layer, when the mandrel is removed (Figure 1.5B). In general, PVDs are usedin association with temporary surcharge. The installation of the PVDs is carried outusing driving equipment with great productivity – about 2km per day, depending onthe stratigraphy – if compared to the necessary operations to install sand drains, withimportant financial impacts. The experience in the west part of Rio de Janeiro has anaverage productivity of 1km to 2km long of PVDs installed per day, for local conditions(Sandroni, 2006b).

Vacuum preloading (Figure 1.1 K) consists of the concomitant use of surchargetechniques (Figure 1.1 M) and drains (Figure 1.1L), i.e. a system of vertical (andhorizontal) drains is installed and vacuum is applied, which has a preloading effect(hydrostatic). The use of PVDs and vacuum preloading are addressed in Chapter 5.

Copyrighted

gradual gain of clay strength over time, is then a construction alternative. StabilityCopyrighted

gradual gain of clay strength over time, is then a construction alternative. Stabilitymust be verified for each stage, and for this evaluation, it is necessary to monitor theCopyrighted

must be verified for each stage, and for this evaluation, it is necessary to monitor theoverall performance by means of geotechnical instrumentation and

Copyrighted

overall performance by means of geotechnical instrumentation andnecessary adjustments to the project. The increase of the clay undrained strength pre-

Copyrighted

necessary adjustments to the project. The increase of the clay undrained strength pre-viously estimated in the design phase should then be verified through vane tests carried

Copyrighted

viously estimated in the design phase should then be verified through vane tests carriedout before performing each construction stage. Construction in stages is discussed in

Copyrighted

out before performing each construction stage. Construction in stages is discussed inChapters 4 and 6.

Copyrighted Chapters 4 and 6.

The use of equilibrium berms (Figure 1.1B) is another solution that can be adopted

Copyrighted The use of equilibrium berms (Figure 1.1B) is another solution that can be adopted

to increase the safety factor (F

Copyrighted to increase the safety factor (Fthe length of berms, or to reduce the amount of earthworks, a basal reinforcement

Copyrighted the length of berms, or to reduce the amount of earthworks, a basal reinforcementMaterial

to increase the safety factor (FMaterial

to increase the safety factor (Fthe length of berms, or to reduce the amount of earthworks, a basal reinforcementMaterial

the length of berms, or to reduce the amount of earthworks, a basal reinforcement(e.g., Magnani et al., 2009, 2010) may be installed (Figure 1.1A) with the goal of

Material

(e.g., Magnani et al., 2009, 2010) may be installed (Figure 1.1A) with the goal ofand better distributing stresses. These two solutions to increase the F

Material

and better distributing stresses. These two solutions to increase the Fare addressed in the Chapter 6. The geosynthetic reinforcement must be installed after

Material are addressed in the Chapter 6. The geosynthetic reinforcement must be installed afterthe installation of the vertical drains to avoid mechanical damage to the reinforcement.

Material the installation of the vertical drains to avoid mechanical damage to the reinforcement.

- 1.4 EMBANKMENT ON VERTICAL DRAINS- 1.4 EMBANKMENT ON VERTICAL DRAINSTaylor

1.4 EMBANKMENT ON VERTICAL DRAINSTaylor

1.4 EMBANKMENT ON VERTICAL DRAINS

The early vertical drains used were sand drains, which were subsequently replaced by

Taylor The early vertical drains used were sand drains, which were subsequently replaced by

Taylor Prefabricated vertical drains, (PVDs). The PVDs consist of a plastic core with channel-

Taylor Prefabricated vertical drains, (PVDs). The PVDs consist of a plastic core with channel-shaped grooves, encased in a low weight nonwoven geosynthetic filter, as shown in

Taylor shaped grooves, encased in a low weight nonwoven geosynthetic filter, as shown in& shaped grooves, encased in a low weight nonwoven geosynthetic filter, as shown in& shaped grooves, encased in a low weight nonwoven geosynthetic filter, as shown in

The drainage blanket of embankments over PVDs, is initially constructed, which& The drainage blanket of embankments over PVDs, is initially constructed, whichFrancis

The drainage blanket of embankments over PVDs, is initially constructed, whichFrancis

The drainage blanket of embankments over PVDs, is initially constructed, whichalso functions as a working platform (Figure 1.4), followed by the PVD installation

Francisalso functions as a working platform (Figure 1.4), followed by the PVD installationand the construction of the embankment. In the driving process, the PVD is attached

Francisand the construction of the embankment. In the driving process, the PVD is attachedto a driving footing, which ensures that the end of the PVD is well fixed at the bottom

Francisto a driving footing, which ensures that the end of the PVD is well fixed at the bottomof the layer, when the mandrel is removed (Figure 1.5B). In general, PVDs are used

Francisof the layer, when the mandrel is removed (Figure 1.5B). In general, PVDs are usedin association with temporary surcharge. The installation of the PVDs is carried out

Francisin association with temporary surcharge. The installation of the PVDs is carried out

Page 7: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Construction methods of embankments on soft soils 7

Figure 1.5 Scheme of an embankment on PVDs: (A) schematic cross section with equilibrium berms;(B) detail of the anchoring mandrel and footing of PVD; (C) detail of the driving mandreland anchoring tube of PVDs.

1.5 LIGHTWEIGHT FILLS

The magnitude of primary settlements of the embankments on layers of soft soils isa function of increased vertical stress caused by the embankment built on the softsoil layer. Therefore, the use of lightweight materials in the embankment reduces themagnitude of these settlements. This technique, known as lightweight fill (Fig 1.1E),has the additional advantage of improving stability conditions of these embankments,also allowing for faster execution of the work and lessening differential settlements.

In Table 1.1 specific weights of certain materials are presented. These materialsintroduce voids into the embankments and are considered lightweight materials, suchas, for example, expanded polystyrene (EPS), concrete pipes/galleries, etc.

Among the listed materials, EPS has been the most used (van Dorp, 1996), becausewhen compared to other materials, it has a smaller specific weight (0.15 to 0.30 kN/m3)and combines high resistance (70 to 250 kPa) with low compressibility (elastic modulusof 1 to 11 MPa). There are EPS with different weights and, strength, and when choos-ing an EPS, one must take into account the use of the embankment and the mobile

Copyrighted Material - - Taylor

Taylor Scheme of an embankment on PVDs: (A) schematic cross section with equilibrium berms;

Taylor Scheme of an embankment on PVDs: (A) schematic cross section with equilibrium berms;(B) detail of the anchoring mandrel and footing of PVD; (C) detail of the driving mandrel

Taylor (B) detail of the anchoring mandrel and footing of PVD; (C) detail of the driving mandrel

& FrancisThe magnitude of primary settlements of the embankments on layers of soft soils is

FrancisThe magnitude of primary settlements of the embankments on layers of soft soils isa function of increased vertical stress caused by the embankment built on the soft

Francisa function of increased vertical stress caused by the embankment built on the softsoil layer. Therefore, the use of lightweight materials in the embankment reduces the

Francissoil layer. Therefore, the use of lightweight materials in the embankment reduces themagnitude of these settlements. This technique, known as lightweight fill (Fig 1.1E),

Francismagnitude of these settlements. This technique, known as lightweight fill (Fig 1.1E),has the additional advantage of improving stability conditions of these embankments,

Francishas the additional advantage of improving stability conditions of these embankments,

Page 8: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

8 Design and Performance of Embankments on Very Soft Soils

Table 1.1 Specific weights of lightweight materials for embankments.

Specific weightMaterial (kN/m3)

Expanded polystyrene – EPS 0.15 to 0.30(foam or similar)

Concrete pipes (diameter: 1 m to 1.5 m; 2 to 4wall thickness: 6 to 10 cm)

Shredded tires 4 to 6Expanded clay 5 to 10Sawdust 8 to 10

Figure 1.6 Use of EPS on embankments on soft soils: (A) cross section of an embankment built withEPS; (B) detail of the construction of an EPS embankment (Lima and Almeida, 2009).

loads. Figure 1.6 gives an example of lightweight fill, where the EPS core is surroundedwith actual fill material with greater weight. In addition to the embankment, a pro-tective concrete layer may be built, i.e. a slab approximately 10 cm to 15 cm thick onthe lightweight fill, to redistribute stresses on the EPS, avoiding the punching of thismaterial, caused mainly by vehicular traffic. Considering the load of the surroundingembankment and slab, preloading of the soft soil shall be done, with the use of verti-cal drains (usually partially penetrating) during the necessary period. The EPS may besensitive to the action of organic solvents, thus it must be protected by a waterproofingcover insensitive to these liquids, as indicated in Figure 1.6A.

The thickness hemb indicated in Figure 1.6 depends on the applied loads, i.e. theuse of the area. On low traffic and low load sites, this thickness will be smaller thanin high traffic areas.

If the area of the embankment with EPS is subject to flooding, the EPS may float,compromising the stability and overall behavior of the embankment. In this case, theEPS base should be installed above the maximum predicted water level.

The lightweight embankment with EPS may have several formats, depending on itsusage, with typical block dimensions of 4.00 × 1.25 × 1.00 m, but it is possible to useblocks with different dimensions according to the demands of each project, or it is even

Copyrighted

Copyrighted Material

Material - Use of EPS on embankments on soft soils: (A) cross section of an embankment built with- Use of EPS on embankments on soft soils: (A) cross section of an embankment built withTaylor

Use of EPS on embankments on soft soils: (A) cross section of an embankment built withTaylor

Use of EPS on embankments on soft soils: (A) cross section of an embankment built withEPS; (B) detail of the construction of an EPS embankment (Lima and Almeida, 2009).

Taylor EPS; (B) detail of the construction of an EPS embankment (Lima and Almeida, 2009).

loads. Figure 1.6 gives an example of lightweight fill, where the EPS core is surrounded

Taylor loads. Figure 1.6 gives an example of lightweight fill, where the EPS core is surroundedwith actual fill material with greater weight. In addition to the embankment, a pro-

Taylor with actual fill material with greater weight. In addition to the embankment, a pro-tective concrete layer may be built, i.e. a slab approximately 10 cm to 15 cm thick on

Taylor tective concrete layer may be built, i.e. a slab approximately 10 cm to 15 cm thick on& with actual fill material with greater weight. In addition to the embankment, a pro-& with actual fill material with greater weight. In addition to the embankment, a pro-tective concrete layer may be built, i.e. a slab approximately 10 cm to 15 cm thick on& tective concrete layer may be built, i.e. a slab approximately 10 cm to 15 cm thick onthe lightweight fill, to redistribute stresses on the EPS, avoiding the punching of this

& the lightweight fill, to redistribute stresses on the EPS, avoiding the punching of thisFrancis

the lightweight fill, to redistribute stresses on the EPS, avoiding the punching of thisFrancis

the lightweight fill, to redistribute stresses on the EPS, avoiding the punching of thismaterial, caused mainly by vehicular traffic. Considering the load of the surrounding

Francismaterial, caused mainly by vehicular traffic. Considering the load of the surrounding

Francisembankment and slab, preloading of the soft soil shall be done, with the use of verti-

Francisembankment and slab, preloading of the soft soil shall be done, with the use of verti-cal drains (usually partially penetrating) during the necessary period. The EPS may be

Franciscal drains (usually partially penetrating) during the necessary period. The EPS may be

Francissensitive to the action of organic solvents, thus it must be protected by a waterproofing

Francissensitive to the action of organic solvents, thus it must be protected by a waterproofing

Page 9: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Construction methods of embankments on soft soils 9

possible to specifically cut the blocks on the worksite (Figure 1.6B). The high cost ofEPS may render their implementation unsuitable in areas distant from the EPS factory,due to the cost of transporting large volumes of EPS required for the embankments.

1.6 EMBANKMENTS ON PILE-LIKE ELEMENTS

Embankments on pile-like elements (Figure 1.1F,G,H) are those in which all or partof the load of the embankment is transmitted to the more competent foundation soil,underlying the soft deposit and will be addressed in Chapter 7.

Embankments can be supported on piles or columns made of different materials.The stress distribution from the embankment to the piles or columns is done by meansof a platform with caps, geogrids or slabs. Embankments on pile-like elements mini-mizes or even – depending on the adopted solution – eliminates settlements, in additionto improving the stability of embankment. One advantage of this construction methodis reducing the construction schedule of the embankment, since its construction maybe done in one stage, in a relatively short period.

The treatment of soft soil with granular columns (Figure 1.1F), in addition toproducing less horizontal and vertical displacements when compared to conventionalembankments or embankments on drains, also dissipates pore pressures through radialdrainage, which speeds up the settlements and increases shear resistance of the foun-dation soil mass. The encasement of these columns using tubular geosynthetics withhigh modulus maximizes their performance.

Piled embankment (Figure 1.1H) uses the arching effect (Terzaghi, 1943), thereforeallowing the stresses of the embankment to be distributed to the piles. The efficiencyof the arching increases as the height of the embankment increases, consequently dis-tributing the load to the caps and the piles (Hewlett and Randolph, 1988). Currently,geogrids are used on the caps to increase the spacing between piles.

1.7 CONSTRUCTION METHODOLOGIES FOR HARBOR WORKS

Soft soil deposits are common in harbor works, which are usually located in coastalareas, because of the amount of sediments that occur over thousands of years, oreven recent sediment deposits, due to anthropogenic activities. In Brazil, examples ofsuch areas are, among others, ports of Santos (Ramos and Niyama, 1994), Sepetiba(Almeida et al., 1999), Itaguaí (Marques et al., 2008), Suape (Oliveira, 2006), Itajaí-Navegantes (Marques and Lacerda, 2004), Natal (Mello, Schnaid and Gaspari, 2002),Rio Grande (Dias, 2001), and also in port areas in the Amazon region (Alencar Jr. et al.,2001; Marques, Oliveira and Souza, 2008).

Harbor works (Mason, 1982) consist essentially of an anchoring dock with a yardfor holding containers in general. Figure 1.7 shows possible construction schemes forport works (Mason, 1982; Tschebotarioff, 1973). The quay is usually a structuresupported by piles, which can either have an associated retaining structure or not.Examples of quays with frontal retaining structures are indicated in Figure 1.7A,B,C.The case shown in Figure 1.7A includes a relief platform. This procedure has theadvantage of decreasing the active pressures on the retaining structure. In the case

Copyrighted

Embankments can be supported on piles or columns made of different materials.Copyrighted

Embankments can be supported on piles or columns made of different materials.The stress distribution from the embankment to the piles or columns is done by means

Copyrighted

The stress distribution from the embankment to the piles or columns is done by meansof a platform with caps, geogrids or slabs. Embankments on pile-like elements mini-

Copyrighted

of a platform with caps, geogrids or slabs. Embankments on pile-like elements mini-mizes or even – depending on the adopted solution – eliminates settlements, in addition

Copyrighted

mizes or even – depending on the adopted solution – eliminates settlements, in additionto improving the stability of embankment. One advantage of this construction method

Copyrighted

to improving the stability of embankment. One advantage of this construction methodis reducing the construction schedule of the embankment, since its construction may

Copyrighted

is reducing the construction schedule of the embankment, since its construction maybe done in one stage, in a relatively short period.

Copyrighted be done in one stage, in a relatively short period.

The treatment of soft soil with granular columns (Figure 1.1F), in addition to

Copyrighted The treatment of soft soil with granular columns (Figure 1.1F), in addition to

producing less horizontal and vertical displacements when compared to conventional

Copyrighted producing less horizontal and vertical displacements when compared to conventionalembankments or embankments on drains, also dissipates pore pressures through radial

Copyrighted embankments or embankments on drains, also dissipates pore pressures through radialMaterial

producing less horizontal and vertical displacements when compared to conventionalMaterial

producing less horizontal and vertical displacements when compared to conventionalembankments or embankments on drains, also dissipates pore pressures through radialMaterial

embankments or embankments on drains, also dissipates pore pressures through radialdrainage, which speeds up the settlements and increases shear resistance of the foun-

Material

drainage, which speeds up the settlements and increases shear resistance of the foun-dation soil mass. The encasement of these columns using tubular geosynthetics with

Material

dation soil mass. The encasement of these columns using tubular geosynthetics withhigh modulus maximizes their performance.

Material high modulus maximizes their performance.

Piled embankment (Figure 1.1H) uses the arching effect (Terzaghi, 1943), therefore

Material Piled embankment (Figure 1.1H) uses the arching effect (Terzaghi, 1943), therefore

allowing the stresses of the embankment to be distributed to the piles. The efficiency

Material allowing the stresses of the embankment to be distributed to the piles. The efficiencyof the arching increases as the height of the embankment increases, consequently dis-

Material of the arching increases as the height of the embankment increases, consequently dis-- of the arching increases as the height of the embankment increases, consequently dis-- of the arching increases as the height of the embankment increases, consequently dis-tributing the load to the caps and the piles (Hewlett and Randolph, 1988). Currently,

- tributing the load to the caps and the piles (Hewlett and Randolph, 1988). Currently,Taylor

of the arching increases as the height of the embankment increases, consequently dis-Taylor

of the arching increases as the height of the embankment increases, consequently dis-Taylor

tributing the load to the caps and the piles (Hewlett and Randolph, 1988). Currently,Taylor

tributing the load to the caps and the piles (Hewlett and Randolph, 1988). Currently,geogrids are used on the caps to increase the spacing between piles.

Taylor geogrids are used on the caps to increase the spacing between piles.

1.7 CONSTRUCTION METHODOLOGIES FOR HARBOR WORKS

Taylor 1.7 CONSTRUCTION METHODOLOGIES FOR HARBOR WORKS& 1.7 CONSTRUCTION METHODOLOGIES FOR HARBOR WORKS& 1.7 CONSTRUCTION METHODOLOGIES FOR HARBOR WORKS

Soft soil deposits are common in harbor works, which are usually located in coastal& Soft soil deposits are common in harbor works, which are usually located in coastalFrancis

Soft soil deposits are common in harbor works, which are usually located in coastalFrancis

Soft soil deposits are common in harbor works, which are usually located in coastalareas, because of the amount of sediments that occur over thousands of years, or

Francisareas, because of the amount of sediments that occur over thousands of years, oreven recent sediment deposits, due to anthropogenic activities. In Brazil, examples of

Franciseven recent sediment deposits, due to anthropogenic activities. In Brazil, examples ofsuch areas are, among others, ports of Santos (Ramos and Niyama, 1994), Sepetiba

Francissuch areas are, among others, ports of Santos (Ramos and Niyama, 1994), Sepetiba(Almeida et al., 1999), Itaguaí (Marques et al., 2008), Suape (Oliveira, 2006), Itajaí-

Francis(Almeida et al., 1999), Itaguaí (Marques et al., 2008), Suape (Oliveira, 2006), Itajaí-

FrancisNavegantes (Marques and Lacerda, 2004), Natal (Mello, Schnaid and Gaspari, 2002),

FrancisNavegantes (Marques and Lacerda, 2004), Natal (Mello, Schnaid and Gaspari, 2002),

Page 10: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

10 Design and Performance of Embankments on Very Soft Soils

Figure 1.7 Details of geotechnical solutions in port areas.

shown in Figure 1.7 B, the retaining structure is supported by a system of two inclinedpiles, one being compressed and the other being tensioned. In Figure 1.7C, the retainingstructure is supported by inclined piles working in tension. The compression stressesare then transmitted to the retaining structure.

In modern harbor works, which handle large vessels (the current dredging require-ments reach depths of about 20 m), the retaining structures must reach great depths,so as to have the appropriate depth of embedment, in particular in the case of verythick compressible layers. Consequently, the previously described retaining structureshave high costs, and alternatives have been proposed as indicated in Figure 1.7D,E.In the case shown in Figure 1.7D, the quay was expanded, and in the case ofFigure 1.7E, a relief platform was used.

Figure 1.7F is a variant of Figure 1.7E and consists of an embankment, traditionallyconstructed with rock-fill, on the interface with the yard. An alternative to the rock-fillis the use of geotextile tubes filled with granular material or with soil cement.

Stability and settlement analysis should be carried out, regardless of the optionadopted among the cases described here, and potential critical failure surfaces areshown in Figure 1.7A,D,E. In harbor works, the typical container surcharge is in the

Copyrighted Material - Taylor

Taylor Details of geotechnical solutions in port areas.

Taylor Details of geotechnical solutions in port areas.

shown in Figure 1.7 B, the retaining structure is supported by a system of two inclined

Taylor shown in Figure 1.7 B, the retaining structure is supported by a system of two inclinedpiles, one being compressed and the other being tensioned. In Figure 1.7C, the retaining

Taylor piles, one being compressed and the other being tensioned. In Figure 1.7C, the retaining& shown in Figure 1.7 B, the retaining structure is supported by a system of two inclined& shown in Figure 1.7 B, the retaining structure is supported by a system of two inclinedpiles, one being compressed and the other being tensioned. In Figure 1.7C, the retaining& piles, one being compressed and the other being tensioned. In Figure 1.7C, the retainingstructure is supported by inclined piles working in tension. The compression stresses

& structure is supported by inclined piles working in tension. The compression stressesFrancis

structure is supported by inclined piles working in tension. The compression stressesFrancis

structure is supported by inclined piles working in tension. The compression stresses

In modern harbor works, which handle large vessels (the current dredging require-

FrancisIn modern harbor works, which handle large vessels (the current dredging require-

ments reach depths of about 20 m), the retaining structures must reach great depths,

Francisments reach depths of about 20 m), the retaining structures must reach great depths,so as to have the appropriate depth of embedment, in particular in the case of very

Francisso as to have the appropriate depth of embedment, in particular in the case of very

Francisthick compressible layers. Consequently, the previously described retaining structures

Francisthick compressible layers. Consequently, the previously described retaining structures

Page 11: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Figure 1.8 Detail of the methodology for disposal of confined sediment.

Copyrighted

Copyrighted Material - Taylor & Francis

Francis

Page 12: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

12 Design and Performance of Embankments on Very Soft Soils

order of 50 to 80 kPa, and the magnitude of the allowed post construction settlementswill depend on technical and operational factors.

In general, harbor works require dredging thick layers of sediment. In these cases,it is common that the superficial layers present such a contamination level, that envi-ronmental agencies will not allow the disposal into water bodies. The alternative hasbeen to dispose the sediments on land and on the harbor work site or offshore. Onesolution is the disposal of these dredged sediments in geotextile tubes (Leshchinskyet al., 1996; Pilarczyk, 2000), which allow the dehydration of the sediment. Also, bymeans of physical-chemical processes, the contaminant gets attached to the sedimentand the dried fluid is then disposed of under environmentally controlled conditions.

Figure 1.8 presents a constructive scheme adopted for the disposal of such contam-inated sediments in confined areas on land, which has 4 phases with 12 constructivesteps explained in the figure. In some cases, the geosynthetic tubes are stacked in twoor three layers. Once the landfill is completed, it can then be used as a storage area.

1.8 FINAL REMARKS

The planned use of the area has an important influence on the most appropriate con-structive technique of embankment on soft clay. For example, on embankments of portyards, the owner may accept post construction settlements and prefer to make periodic

Chart 1.1 Summary of construction methodologies and their characteristics.

Construction methodologies Characteristics

Total or partial removal ofsoft layer

Effective, fast, high environmental impact; boreholes are necessaryfor measuring the quantity of removed/remaining soil

Soil expulsion with controlledrupture (displacement fill)

Used for deposits of small thickness and very dependent on localexperience; boreholes are necessary to gauge the thickness of theremoved/remaining soil

Conventional embankment Stabilization of settlements is slow

Construction in stages Used, in most cases, with vertical drains; it is necessary tomonitor the clay strength gain; it is not favorable forshort deadlines

Vertical drains and surcharge Used to accelerate settlements, large accumulated experience.Temporary surcharge may minimize or surpress secondarysettlements

Berms and/or reinforcement Frequently adopted; it is necessary to assess whether the tensilestrength of the reinforcement is actually mobilized in situ

Use of lightweight materials Ideal for tight deadlines; relatively high costs; its use has increased

Embankments on piles withgeogrid platform

Ideal for tight deadlines; various layouts and materials canbe used

Granular columns(granular piles)

Granular columns that may or may not be encased with geotextile;settlements are accelerated due to the draining nature ofgranular columns; geogrids are sometimes installed above thegranular columns

Vacuum preloading Can partially substitute the need for surcharge with fill material;horizontal strains are much smaller than those of conventionalsurcharge

Copyrighted

Figure 1.8 presents a constructive scheme adopted for the disposal of such contam-Copyrighted

Figure 1.8 presents a constructive scheme adopted for the disposal of such contam-inated sediments in confined areas on land, which has 4 phases with 12 constructiveCopyrighted

inated sediments in confined areas on land, which has 4 phases with 12 constructivesteps explained in the figure. In some cases, the geosynthetic tubes are stacked in two

Copyrighted

steps explained in the figure. In some cases, the geosynthetic tubes are stacked in twoor three layers. Once the landfill is completed, it can then be used as a storage area.

Copyrighted

or three layers. Once the landfill is completed, it can then be used as a storage area.

1.8 FINAL REMARKS

Copyrighted 1.8 FINAL REMARKS

The planned use of the area has an important influence on the most appropriate con-

Copyrighted The planned use of the area has an important influence on the most appropriate con-structive technique of embankment on soft clay. For example, on embankments of port

Copyrighted structive technique of embankment on soft clay. For example, on embankments of portMaterial

structive technique of embankment on soft clay. For example, on embankments of portMaterial

structive technique of embankment on soft clay. For example, on embankments of portyards, the owner may accept post construction settlements and prefer to make periodic

Material

yards, the owner may accept post construction settlements and prefer to make periodic

Summary of construction methodologies and their characteristics.

Material Summary of construction methodologies and their characteristics.

Material Characteristics

Material Characteristics

Material Effective, fast, high environmental impact; boreholes are necessary

Material Effective, fast, high environmental impact; boreholes are necessary- Effective, fast, high environmental impact; boreholes are necessary- Effective, fast, high environmental impact; boreholes are necessaryfor measuring the quantity of removed/remaining soil- for measuring the quantity of removed/remaining soilTaylor

for measuring the quantity of removed/remaining soilTaylor

for measuring the quantity of removed/remaining soilTaylor

Used for deposits of small thickness and very dependent on localTaylor

Used for deposits of small thickness and very dependent on localexperience; boreholes are necessary to gauge the thickness of the

Taylor experience; boreholes are necessary to gauge the thickness of the

Taylor Stabilization of settlements is slow

Taylor Stabilization of settlements is slow

Taylor Used, in most cases, with vertical drains; it is necessary to

Taylor Used, in most cases, with vertical drains; it is necessary to& & Used, in most cases, with vertical drains; it is necessary to& Used, in most cases, with vertical drains; it is necessary tomonitor the clay strength gain; it is not favorable for

& monitor the clay strength gain; it is not favorable forFrancis

monitor the clay strength gain; it is not favorable forFrancis

monitor the clay strength gain; it is not favorable forFrancis

FrancisUsed to accelerate settlements, large accumulated experience.

FrancisUsed to accelerate settlements, large accumulated experience.Temporary surcharge may minimize or surpress secondary

FrancisTemporary surcharge may minimize or surpress secondary

FrancisFrequently adopted; it is necessary to assess whether the tensile

FrancisFrequently adopted; it is necessary to assess whether the tensilein situ

Francisin situ

Francis

Page 13: Construction methods of embankments on soft soils - … · material, considering the ... The drainage blanket of embankments over PVDs, is initially constructed, which ... Construction

Construction methods of embankments on soft soils 13

maintenance on the embankment, rather than investing initially on the stabilization ofthe settlements. However, for real estate, post construction settlements are inaccept-able, since the constructor will not return to the site. On highways, settlements onbridge approaches reduce the comfort and safety of users, and on railroads, the postconstruction settlements should be small to minimize high maintenance costs, mainlyrelated to the disruption of traffic. In the case of high-speed trains, for example, postconstruction settlements should be null.

Chart 1.1 summarizes the constructive methodologies presented in this chapterand their main features. For very soft soils it is common to use several constructiontechniques in parallel. For example, in the southeastern region of Brazil, particularlyin the port of Santos area and in the West zone of Rio de Janeiro, in some cases, thechoice has been to adopt reinforced embankments constructed in stages on verticaldrains with berms and surcharge (Almeida et al., 2008c).

The decision for one executive methodology in detriment to another is a functionof the geotechnical characteristics of the deposits, the use of the area (including theneighborhood), construction deadlines and the costs involved.

Copyrighted

in the port of Santos area and in the West zone of Rio de Janeiro, in some cases, theCopyrighted

in the port of Santos area and in the West zone of Rio de Janeiro, in some cases, thechoice has been to adopt reinforced embankments constructed in stages on vertical

Copyrighted

choice has been to adopt reinforced embankments constructed in stages on verticaldrains with berms and surcharge (Almeida et al., 2008c).

Copyrighted

drains with berms and surcharge (Almeida et al., 2008c).The decision for one executive methodology in detriment to another is a function

Copyrighted

The decision for one executive methodology in detriment to another is a function

Copyrighted

of the geotechnical characteristics of the deposits, the use of the area (including the

Copyrighted

of the geotechnical characteristics of the deposits, the use of the area (including theneighborhood), construction deadlines and the costs involved.

Copyrighted

neighborhood), construction deadlines and the costs involved.

Material - Taylor & Francis