How we plan to maintain stable pig iron production at EVRAZ NTMK CONSTRUCTION OF THE BLAST FURNACE No. 7 To be launched in Q1 2018 EVRAZ NTMK EVRAZ NTMK’s blast furnaces no. 5 and no. 6 each currently have an effective operating volume of 2,200 m 3 . They are known as the most productive and efficient blast furnaces in Russia and Europe. Building the new blast furnace no. 7 provides alternative capacity while the blast furnace no. 6 is taken off-line for a major overhaul. PIG IRON PRODUCTION, kt No.5 BF No.6 BF 2017 2–3 year plan 4,714 kt Newly built No.7 BF Idled No.5 BF Repaired No.6 BF 52 www.evraz.com

Upload: others

Post on 10-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION OF THE BLAST FURNACE No. 7...CONSTRUCTION OF THE BLAST FURNACE No. 7 To be launched in Q1 2018 EVRAZ NTMK EVRAZ NTMK’s blast furnaces no. 35 and no. 6 each currently

How we plan to maintain stable pig iron production at EVRAZ NTMK

CONSTRUCTION OF THE BLAST FURNACE No. 7

To be launched in Q1 2018

EVRAZ NTMK

EVRAZ NTMK’s blast furnaces no. 5 and no. 6 each currently have an effective operating volume of 2,200 m3. They are known as the most productive and efficient blast furnaces in Russia and Europe. Building the new blast furnace no. 7 provides alternative capacity while the blast furnace no. 6 is taken off-line for a major overhaul.

PIG IRON PRODUCTION, kt

No.5BF

No.6BF

2017 2–3 year plan

4,714 kt >5,000 kt

Newly built

No.7BF

Idled

No.5BF

Repaired

No.6BF

52

ww

w.ev

raz.

com

Page 2: CONSTRUCTION OF THE BLAST FURNACE No. 7...CONSTRUCTION OF THE BLAST FURNACE No. 7 To be launched in Q1 2018 EVRAZ NTMK EVRAZ NTMK’s blast furnaces no. 35 and no. 6 each currently

CONSTRUCTION OF THE BLAST FURNACE No. 7 The new technology will allow to reduce the environmental effect significantly and will improve working conditions in the blast furnace shop.

Technology

• two fully enclosed casting yards• automated furnace filling and external cooling systems • high-capacity aspiration systems and stoves• every tap spout near tap holes is equipped with over-head exhaust hoods and efficient

bag filters, which improve air filtration by 2.5 times • the main slag discharge runner’s upgraded design prevents closed-circuit water leaks

Characteristics of the blast furnace no. 7

Production capacity 2.5 mtpa of pig iron

Volume

2,200 m3

53