![Page 1: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/1.jpg)
1,600 FT. SOUTH OF THE DAM
900 FT. ABOVE WATER
2000 FT. LONG
COMPLETION DATE: September 2010
OPEN TO TRAFFIC: November 2010
CONSTRUCTION OF THE
HOOVER DAM BYPASS
BRIDGE
THIS IS THE LAST
UPDATE: 05 August 2010
www.maximumreach.com
![Page 2: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/2.jpg)
Artists conception of
the bypass bridge in
the foreground
Pier
Pier
5 Pier
5
Pier
14
![Page 3: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/3.jpg)
BRIDGE DETAILS
LOOKING NORTH
Pier
5
Pier
14
![Page 4: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/4.jpg)
f
13' high x 20'
wide x 1' walls
![Page 5: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/5.jpg)
The construction of the bridge is completed. Only some
clean up remains which should be complete by 1 Sept.
Both cableways have been dismantled.
Note on slide number 12 the hand rail for the side walk
that runs on the north side of the bridge. It looks like the
vertical posts and the horizontal rail might be made out of
pipe. It doesn't appear that curved guard screen has been
install on the horizontal rail. Hopefully, it will not be
installed to block the view.
It looks like the bridge won't be open to traffic until
around 1 November 2010 after all the roadway is paved, ie,
in the areas under the towers for the cableways, etc.
This will be the last update on the progress of the bridge.
![Page 6: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/6.jpg)
Looking southwest at the bypass bridge
![Page 7: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/7.jpg)
![Page 8: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/8.jpg)
![Page 9: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/9.jpg)
![Page 10: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/10.jpg)
![Page 11: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/11.jpg)
![Page 12: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/12.jpg)
![Page 13: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/13.jpg)
![Page 14: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/14.jpg)
![Page 15: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/15.jpg)
![Page 16: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/16.jpg)
![Page 17: CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE THIS IS … of the Hoover Dam... · 2014. 2. 14. · 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: September](https://reader034.vdocument.in/reader034/viewer/2022051511/600ab8c92f215d2fbc00b5cf/html5/thumbnails/17.jpg)
FINÉ