construction option josue fernandez › ae › thesis › portfolios › 2014 › jif5105 ›...

24
JOSUE FERNANDEZ CONSTRUCTION OPTION

Upload: others

Post on 29-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

JOSUE FERNANDEZCONSTRUCTION OPTION

Page 2: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Josue FernandezConstruction Option

Page 3: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Location: _Rockville, MD

Size: _285,000 Square Feet _4 Total Floors and 2 Sublevels

Function: _Retail & Residential Apts.

Schedule: _October 2012 - May 2014 _20 Months

Cost: _$36 Million

Delivery Method: _Design-Bid-Build

Owner: _Federal Realty Investment Trust

Project OverviewProject Overview

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Courtesy of : Design Collective

Page 4: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

3 Lane Highway

4 Lane Highw

ay

2 Lane Road

3 La

ne S

tree

t

Stores/ GymBuildings

2 Stories

Stores1 Story

ROCKVILLE, MD

BLOCK 12

Josue Fernandez9.31.2013

LEGEND:1. Parking2. Contractor Staging Area3. Material Storage Area4. Dumpsters

5. CM Trailer

6. Owner's Rep. Trailer7. Electrical Trailer8. Mechanical Trailer9. Concrete Trailer10. Plumbing Trailer 11. Temporary Power12. Concrete Wash Down Area

13. Construction Fence14. Gate/ Construction15. Tire Wash Racks16. Portable Toilets17. Concrete Pump/ Pipe18. Concrete Truck19. Delivery Truck

Scale:1"= 100'Site Logistics: Substructure

1 La

ne R

oad

BLOCK 12Building Footprint

BLOCK 11Building Footprint

BLOCK 10Building Footprint

Construction Conditions

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Courtesy of : Google Earth

Page 5: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

AN

ALY

SIS

MA

P

Budget Overruns

Challenges

Quick Turnover

Tight Profit Margins

Apartment Complex Concerns

Alternate Delivery Method

Building Energy Efficiency

Info./ Doc. Management HUB

Prefabrication of Brick Veneer

Analysis 1

Analysis 2

Analysis 3

Analysis 4

Analysis Topics

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 6: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Current: DBB Delivery Method Proposed: DB Delivery Method

Advantages:

Disadvantages:

_Familiar delivery method_Construction price before construction starts_Opportunity for competitive bidding

_No subcontractor input_Design must be complete prior to construction_Designer and contractor develop work autonomously_Prices & schedules based on construction documents

Advantages:

Disadvantages:

_Construction input in the design phase_Good communication & relationships_Eliminates responsability and finger-pointing when conflict occurs_Iterative cost estimating from early collaboration by constrcution team

_Difficult to provide firm, fixed price before project begins_Owner may perceive less design control_No independent oversight of work performed

Goal of Analysis #1

Analysis Topic 1: Alternate Delivery Method

To validate the advatages and disadvantages of a contractor led Design-Build Delivery

Method

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 7: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Design

NTP with Construction

10/1

51/01

Hurricane Sandy

11/2

2/26

Close- out 5/28

Project Complete

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2012 2013 2014

tnemerucorP

Construction

5/28

8/20

DESIGN-BID-BUILD

DESIGN-BUILD

2011

Design

NTP with Construction

5/1

Hurricane Sandy 11/2

11/4

Close- out 12/26

Project Complete

tnemerucorP

Construction

12/26

8/4

5/17

Delivery Method Difference Project Delivery Method Selection System Schedule Comparison

DBB  w/  CM  @  Risk Design-­‐BuildDesign  complete  before  contractor  involved

No No

Advesarial  relationship  between  designer  &  contractor

Possible No

Can  fast  track? Likely Yes

Contractor  feedback  on  design? No Yes

#  of  parties  responsible  for  construction?

1 1

List  parties  contracted  with  owner 2 1

Owner  has  design  control Yes Some

Organizational  Structure  Difference

#20- CMGC, D/B

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Organizational structural difference (Messner, 2012)

The PDSS Model- Tabulated Solutions (Vesay, 1991)

Page 8: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Current: DBB Delivery Method Proposed: DB Delivery Method

Federal Realty Investment Trust Owner

Mark Hendrickson Owners Representative

Whiting-Turner

Construction Manager

DCI

Architect

SCA Structural Engineers

Summit Engineer

MEP Engineers

Dixie

Excavation

Schuster Concrete Concrete

Caretti

Masonry

Misc. Metals Structural/ Metals

Prospect Waterproofing/ Roofing

Power Design Electric

Madison Plumbing

Contract Types

GMP Lump Sum Cost Plus Fee Communication

Federal Realty Investment Trust Owner

Whiting-Turner

Construction Manager

SCA Structural Engineers

Summit Engineer

MEP Engineers

Dixie Excavation

Schuster Concrete Concrete

Caretti

Masonry

Misc. Metals Structural/ Metals

Prospect Waterproofing/ Roofing

Power Design Electric

Madison Plumbing

Contract Types

GMP

Lump Sum Cost Plus Fee Communication

Mark Hendrickson Owners Representative

DCI

Architect

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 9: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Conclusion:South Hall Project:

Contractor led Design-Build Delivery Method is recommended

Block  12  Problems South  Halls  Benefits  from  Design-­‐Build  Delivery  Method

 Barton  Malow  assumes  more  risk  for  design  mistakes,  but  is  able  to  charge  a  higher  fee.  

 Delivery  method  allowed  early  subcontractor  input  before  drawings  were  complete,  which  enabled  real  time  cost  tracking  

during  design    Early  input  from  subcontractors  helped  in  owner  decision  making  

process  

Project  Turnover  Harnessed  a  more  collaborative  enironment,  leading  to  a  much  more  effective  communication  

Profit  Margins  Project  is  on  budget  

Complex  Concerns  Early  identification  of  desired  energy  efficient  materials  and  equipement  were  identified  early  in  design  

Design-­‐Build:  South  Halls  Project

Budget  Overruns

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 10: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Thin Brick By Owensboro Panel Information Section Cut

Goal of Analysis #2

Analysis Topic 2: Premanufactured Brick Veneer Panels

To reduce the brick veneer installation time in order to accelerate the overall schedule

16” x 48” Panels

EXTERIOR WALL TYPE #1

EXT WALL TYPE #1 - 6" WD STUD, MASONRY VENEER (SHOWN)

NOMINAL 4" THICKNESS MASONRY VENEER (REF.ELEVATION FOR COLOR INDICATION)AIR CAVITY

FELT PAPER (BOND BREAK)

1/2" WALL SHEATHING W/TAPED JOINTS

NOMINAL 2 X6 WD FRAMING MEMBER

5/8" MIN. FIN. GYPSUM BOARD

1' - 2"

SECTION

PLAN

R-13 MIN. FRICTION FIT BATTINSULATION

WD/MTL STUD - MASONRY VENEER

2" RIGID INSULATION

EXT WALL TYPE #1A - 6" MTL STUD, MASONRY VENEER (SIM)

EXT WALL TYPE #1S - 6" WD STUD (PARTITION TYPE P30, UL 210), MASONRY VENEER

PART'N TYPE P30@ TYPE # 1S

7-1/4” 6-3/4”

Current: 6-3/4”

Proposed:6-3/4”

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Util-A-Crete Panel System + 6” Polystyrene 3CI Panel

Courtesy of : Owensboro Courtesy of : Owensboro Courtesy of : WT Courtesy of : The Best Panel Co.

Page 11: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Transportation Logistics ScheduleThermal Performance

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

Thermal Performance

20.2

R-Va

lue

Thin Brick By Owensboro Panels w/ 6" 3CI Insulation Panel

Modular Brick Veneer

39.1

_5 Deliveries_One 48” Flatbed & Four 45” Flatbeds_176 total Pallets (18 panels per pallet)

3 Lane Highway

4 Lane Highw

ay

2 Lane Road

3 La

ne S

tree

t

Stores/ GymBuildings

2 Stories

Stores1 Story

ROCKVILLE, MD

BLOCK 12

Josue Fernandez9.31.2013

LEGEND:1. Parking2. Contractor Staging Area3. Material Storage Area4. Dumpsters

5. CM Trailer

6. Owner's Rep. Trailer7. Electrical Trailer8. Mechanical Trailer9. Concrete Trailer10. Plumbing Trailer 11. Temporary Power12. Construction Hoist

13. Construction Fence14. Gate/ Construction15. Tire Wash Racks16. Portable Toilets17.Mobile Crane18. Flatbed Delivery Trucks19. Delivery Trucks

Scale:1"= 100'Site Logistics: Enclosure

1 La

ne R

oad

01

05

BLOCK 12Building Footprint

06

0703

10

09

08

BLOCK 11Building Footprint

BLOCK 10Building Footprint

04

11

02 04

Swing Rad

ius 14

6'-1"

Jib Elev

ation

505.0

'

12

Modular Brick= 177 days

Premanufactured Panels= 119 days

Assumption: 75% time saving on schedule

Time Saving= 43 Days

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 12: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Cost Recommendation

Modular Brick= $89,313.68

Premanufactured Panels= $206,287.94

Difference= $116,974.26

General Conditions= $135,248.00

SAVINGS= $18,274.10

Premanufactured panels accelerate the schedule and yield savings. The premanu-

factured panels are recommended.

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 13: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Building Automation Components (Residential Level)

Components Layout Plan

Goal of Analysis #3

Analysis Topic 3: Building Energy Efficiency

To reduce the building’s energy consumption to help maintain the building’s

energy efficiency.

UNIT 1A

UD

NOTE 2(13,15)

(17,19)30/2/*WSHP-3

(1)

UB

(1) c

UIa

(2)

(4) (3)

EF-1F

UF(3)

F

HR

e

(4)(4)

(4)(4)

(2)

(12)

MICRO+60"AFF

(24) (22)

(14)

DISP

(20)

a

b

D

(1)

Dd

(18)

(21,23)(11)

(16)

HR

(10)HR

(2)

DISP

(2)

HR

TECH PNL+80"AFF

UJ30/2WH-AUNIT PNL '1A'

UA

(1)b

UA

(1)b

UA

(1)

bUB

(1)

c

(26,28)

(1)

(12)

c

D

(2)

(10)

d

(4)UH

(1) UJ

(3)

e(4)

33

3

HR

HR

(4)

(2)

(4)

(2) (2)

(16)

NOTE 1

J

J

1(9)

1(9)

UNIT 1A - Automation Components Floor PlanSCALE: NOT TO SCALE

1E2.99

Key:

WeMo Insight Switch

Nest Thermosat 2nd Gen.

Belkin Wemo Nest Thermostat

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Courtesy of : Belkin Courtesy of : Nest

Page 14: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Phantom Load Analysis (Typical Residential Unit)

Simple PaybackPlug Load Analysis (Typical Residential Unit)

WeMo  Insight  Switch  #

Electronics Wattage Phantom  Load

Alarm  Clock 4 YESCell  Phone  Charger 10 YESLaptop 60 YESPortable  Electric  Heater 1200 NOFans 100 NODesk  &  Table  Lamps 100 NOPrinter/  Scanner 100 YES

Hair  Dryer 920 YESHair  Curler 320 YESShaver 20 YESElectric  Tooth  Brush 10 YES

Television 100 YESDVD/VCR  Player 40 YESGame  Console 250 NOStereo  System 30 YESAquarium 1210 NO

Coffee  Maker 900 YESToaster  Oven 630 NOBlender NO

5 Microwave 1050 YES*information  provided  by  http://energy.maryland.gov/

Plug  Load  Analysis  for  a  Typical  Unit  in  Block  12

1

2

3

4

0.11629$           per  kWh

1 2 3 4 5 6 7 8

WeMo  Insight  Switch  #

ElectronicsQuantity  In  Use

Typical  Hours  "off"  or  Standby,  

Daily

Wattage  off/Stand-­‐by  Mode

Days  per  Month  in  Operation

Monthly  kWh

Monthly  Cost

Alarm  Clock 1 24 1.5 30 1.1 0.13$                        Cell  Phone  Charger 1 21 2.5 20 1.1 0.12$                        Laptop 1 16 4.4 20 1.4 0.16$                        Printer/  Scanner 1 23 7.6 20 3.5 0.41$                        

Hair  Dryer 1 22 2.3 30 1.5 0.18$                        Hair  Curler 1 22 2.6 20 1.1 0.13$                        Shaver 1 23 0.6 20 0.3 0.03$                        Electric  Tooth  Brush 1 23 1.6 30 1.1 0.13$                        

Television 1 23 3.5 20 1.6 0.19$                        DVD/VCR  Player 1 23 5.2 20 2.4 0.28$                        Stereo  System 1 23 3.5 20 1.6 0.19$                        

4 Coffee  Maker 1 21 1.5 20 0.6 0.07$                        

5 Microwave 1 23.5 2.5 20 1.2 0.14$                        

18.5 2.16$                        

*information  based  from  "Phantom  Load  Spreadsheet"  from    www.NEED.org

Phantom  Load  Spreadsheet:  Typical  Unit  in  Block  12

1

2

3

TOTAL

Phantom Load= $2.16 /month*12 months = $25.92 /yearPayback Period= 17 years

5 Belkin WeMo ComponentsOUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 15: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Nest Thermostat- Energy Savings(Typical Residential Unit)

Simple Payback

Yearly Savings= $173 /yearPayback Period= 2 years

1 Nest ThermostatComponent

Nest  Learning  Thermostat  2nd  Generation $173  per  year  19.5%  per  device  

Energy  Savings:  Nest  Learning  Thermostat  2nd  GenerationEnergy  Savings  on  Heating  and  Cooling  Costs

*  Results  obtained  from  the  "Nest  Learning  Thermostat  Efficiency  Simulation:  Update  Using  Data  from  First  Three  Months”  report  done  by  Nest  Labs  on  April  2012

Recommendation

_Belkin WeMo is not recommended for this project

_Nest Thermostat is recommended

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 16: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Sensible Wheel in RTU Unit Energy Model- TRANE TRACE

_Wheels are compact and can achieve high heat transfer effectiveness_Low air pressure drop (0.4-0.7 in. of water)_Potential for cooling or heating equipment size reduction

Advantages

Disadvantages

Goal of Mechanical Breadth

Mechanical Beadth: Sensible Wheel (Retail Level)

To reduce the building’s energy consumption to help maintain the building’s

energy efficiency.

_Initial first cost of equipment and fan power requirement to overcome resistance_Requires periodical maintenance of rotating mechanism and cleaning of fill medium_Some cross-contamination of two air streams, due to carryover and leakage

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Courtesy of : http://cipco.apogee.net/ces/

Page 17: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Energy Use (Retail Level)

Use Cost Use Cost Use Cost

Electricity  (kWh) 313,122                       36,413$                 339,366                             39,465$             (26,244)             (3,052)$               Electricity  ($/kWh) 0.11629$          Gas  (therms) 22,363                             21,021$                 11,338                                 10,658$             11,025               10,364$             Gas  ($/therms) 0.94000$          

Building  (Btu/ft^2-­‐yr) 69,065                             -­‐$                             65,671                                 -­‐$                           3,394                   -­‐$                          Source  (Btu/ft^2-­‐yr) 168,651                       -­‐$                             177,481                             -­‐$                           (8,830)                 -­‐$                          

Floor  Area  (ft^2)

Baseline RedesignIncrease  in  Emissions

Use Use Use

CO2  (lbm/year) 4,534,850                 5,121,007         13%SO2  (gm/year) 16,212                             18,307                     13%NOX  (gm/year) 6,920                                 7,815                         13%

Unit  Cost  of  Energy

Yearly  Environmental  Impact

Yearly  Energy  Usage  and  CostEnergy  Cost  for  ChangeBaseline Redesign

112940

MonthBaseline  (kWh)

Redesign  (kWh)Difference  

(kWh)Baseline  (therms)

Redesign  (therms)

Difference  (therms)

January 19,845                 24,875                                     (5,030)                   4,525                       1,677                                         2,848                      February 18,018                 22,478                                     (4,460)                   4,011                       1,515                                         2,496                      March 24,413                 27,737                                     (3,324)                   2,928                       1,652                                         1,276                      April 23,296                 25,038                                     (1,742)                   1,846                       1,305                                         541                            May 30,175                 31,163                                     (988)                           433                             403                                                 30                                June 32,467                 33,198                                     (731)                           36                                 24                                                     12                                July 31,982                 32,507                                     (525)                           -­‐                               -­‐                                                 -­‐                              

August 35,153                 35,950                                     (797)                           23                                 13                                                     10                                September 28,204                 29,093                                     (889)                           311                             286                                                 25                                October 26,313                 27,563                                     (1,250)                   1,864                       1,308                                         556                            

November 23,692                 25,726                                     (2,034)                   2,397                       1,479                                         918                            December 19,565                 24,037                                     (4,472)                   3,989                       1,677                                         2,312                      

Largest  Differnce (5,030)                   Largest  Differnce 2,848                      

Average  Value (2,186.83)         Average  Value 918.67                

Energy Gas

Monthly  Energy  Usage

 -­‐        

 5,000    

 10,000    

 15,000    

 20,000    

 25,000    

 30,000    

 35,000    

 40,000    

Energy  Use  (k

Wh)  

Monthly  Electricity  Use  

Baseline  (kWh)  

Redesign  (kWh)  

 -­‐          500    

 1,000      1,500      2,000      2,500      3,000      3,500      4,000      4,500      5,000    

Energy  Use  (the

rms)  

Monthly  Gas  Use  

Baseline  (therms)  

Redesign  (therms)  

Yearly  Energy  SavingsCost

Electricity  (kWh) (3,052)$                                                                                                                                                Gas  (kBtu) 10,364$                                                                                                                                              

Savings  for  Building  with  Enthalpy  wheel

7,312$                                                                                                                                                  

MonthBaseline  (kWh)

Redesign  (kWh)Difference  

(kWh)Baseline  (therms)

Redesign  (therms)

Difference  (therms)

January 19,845                 24,875                                     (5,030)                   4,525                       1,677                                         2,848                      February 18,018                 22,478                                     (4,460)                   4,011                       1,515                                         2,496                      March 24,413                 27,737                                     (3,324)                   2,928                       1,652                                         1,276                      April 23,296                 25,038                                     (1,742)                   1,846                       1,305                                         541                            May 30,175                 31,163                                     (988)                           433                             403                                                 30                                June 32,467                 33,198                                     (731)                           36                                 24                                                     12                                July 31,982                 32,507                                     (525)                           -­‐                               -­‐                                                 -­‐                              

August 35,153                 35,950                                     (797)                           23                                 13                                                     10                                September 28,204                 29,093                                     (889)                           311                             286                                                 25                                October 26,313                 27,563                                     (1,250)                   1,864                       1,308                                         556                            

November 23,692                 25,726                                     (2,034)                   2,397                       1,479                                         918                            December 19,565                 24,037                                     (4,472)                   3,989                       1,677                                         2,312                      

Largest  Differnce (5,030)                   Largest  Differnce 2,848                      

Average  Value (2,186.83)         Average  Value 918.67                

Energy Gas

Monthly  Energy  Usage

 -­‐        

 5,000    

 10,000    

 15,000    

 20,000    

 25,000    

 30,000    

 35,000    

 40,000    

Energy  Use  (k

Wh)  

Monthly  Electricity  Use  

Baseline  (kWh)  

Redesign  (kWh)  

 -­‐          500    

 1,000      1,500      2,000      2,500      3,000      3,500      4,000      4,500      5,000    

Energy  Use  (the

rms)  

Monthly  Gas  Use  

Baseline  (therms)  

Redesign  (therms)  

MonthBaseline  (kWh)

Redesign  (kWh)Difference  

(kWh)Baseline  (therms)

Redesign  (therms)

Difference  (therms)

January 19,845                 24,875                                     (5,030)                   4,525                       1,677                                         2,848                      February 18,018                 22,478                                     (4,460)                   4,011                       1,515                                         2,496                      March 24,413                 27,737                                     (3,324)                   2,928                       1,652                                         1,276                      April 23,296                 25,038                                     (1,742)                   1,846                       1,305                                         541                            May 30,175                 31,163                                     (988)                           433                             403                                                 30                                June 32,467                 33,198                                     (731)                           36                                 24                                                     12                                July 31,982                 32,507                                     (525)                           -­‐                               -­‐                                                 -­‐                              

August 35,153                 35,950                                     (797)                           23                                 13                                                     10                                September 28,204                 29,093                                     (889)                           311                             286                                                 25                                October 26,313                 27,563                                     (1,250)                   1,864                       1,308                                         556                            

November 23,692                 25,726                                     (2,034)                   2,397                       1,479                                         918                            December 19,565                 24,037                                     (4,472)                   3,989                       1,677                                         2,312                      

Largest  Differnce (5,030)                   Largest  Differnce 2,848                      

Average  Value (2,186.83)         Average  Value 918.67                

Energy Gas

Monthly  Energy  Usage

 -­‐        

 5,000    

 10,000    

 15,000    

 20,000    

 25,000    

 30,000    

 35,000    

 40,000    

Energy  Use  (k

Wh)  

Monthly  Electricity  Use  

Baseline  (kWh)  

Redesign  (kWh)  

 -­‐          500    

 1,000      1,500      2,000      2,500      3,000      3,500      4,000      4,500      5,000    

Energy  Use  (the

rms)  

Monthly  Gas  Use  

Baseline  (therms)  

Redesign  (therms)  

Use Cost Use Cost Use Cost

Electricity  (kWh) 313,122                       36,413$                 339,366                             39,465$             (26,244)             (3,052)$               Electricity  ($/kWh) 0.11629$          Gas  (therms) 22,363                             21,021$                 11,338                                 10,658$             11,025               10,364$             Gas  ($/therms) 0.94000$          

Building  (Btu/ft^2-­‐yr) 69,065                             -­‐$                             65,671                                 -­‐$                           3,394                   -­‐$                          Source  (Btu/ft^2-­‐yr) 168,651                       -­‐$                             177,481                             -­‐$                           (8,830)                 -­‐$                          

Floor  Area  (ft^2)

Baseline RedesignIncrease  in  Emissions

Use Use Use

CO2  (lbm/year) 4,534,850                 5,121,007         13%SO2  (gm/year) 16,212                             18,307                     13%NOX  (gm/year) 6,920                                 7,815                         13%

Unit  Cost  of  Energy

Yearly  Environmental  Impact

Yearly  Energy  Usage  and  CostEnergy  Cost  for  ChangeBaseline Redesign

112940

_Increase electricity_Decrease gas

_$7,312 yearly energy savings

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 18: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Coil Selection Recommendation

Capacity  (Mbh)

Coil  Airflow  (CFM)

Ent.  (°F) Lvg.  (°F)Capacity  (Mbh)

Coil  Airflow  (CFM)

Ent.  (°F) Lvg.  (°F)

Baseline (812.8)                   14,297                                     17.0                                             68.0                           545.7                       14,297                                     90.6                           69.8                          

Redesign (187.7)                   14,297                                     56.2                                             68.0                           354.2                       14,297                                     79.1                           69.8                          

Change77%  

reduction35%  

reduction

Heating  Coil  Selection Cooling  Coil  Selection

Coil  Selection

39.2  °F  higher  entering  temp11.2  °F  higher  entering  

temp

_35% Cooling coil reduction_77% Heating coil reduction

The sensible wheel is recommended for yearly energy savings and further savings in

reduction of coils

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 19: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Final Conclusions Recommendation

Alternate Delivery Method:_More collaborative_Early contractor input_Maintain project on budget

Prefab. of Brick Veneer:_Higher R-Value_Higher cost, but GC savings - $18k_Schedule accelerated 43 days

Building Energy Efficiency:_Belkin WeMo Component _17 yr. payback period_Nest Thermostat Component _2 yr. payback period

Sensible Wheel:_$7,312 yearly energy savings_35% cooling coil reduction_77% heating coil reduction

Alternate Delivery Method:_Contractor led Design-Build delivery method is recommended, and could have helped in hindsight

Prefab. of Brick Veneer:_Recommended for cost savings and schedule acceleration

Building Energy Efficiency:_ Belkin WeMo component is not recommended, long payback period_Nest Thermostat component is recommended, short payback period

Sensible Wheel:_Implement sensible wheel for energy savings and cooling/ heating coil reduction

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 20: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Acknowledgements

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Academic Acknowledgements

Steven RogersPatrick Laninger

Gabe PowersFamily & Friends

Special Thanks!

Penn State Architectural Engineering Faculty & StaffDr. Craig Dubler

Page 21: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Questions?

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 22: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Appendix: Analysis 2

Component Thickness R-­‐Value  per  Inch R-­‐Value  per  Unit R-­‐Value(in.) (hr*ft^2*°F/BTU*in.) (hr*ft^2*°F/BTU) (hr*ft^2*°F/BTU)

Outside -­‐ -­‐ 0.17 0.171/2"  Thin  Brick,  1/4"  Util-­‐A-­‐Crete,  and  6"  Polystyrene   6-­‐3/4" -­‐ 30.00 30.00Zip  Wall  (Taped) 1/2 -­‐ 0.62 0.62Mtl  Stud  Fram.  with  R-­‐19  Batt  Ins. 6 -­‐ 7.10 7.10G.W.B. 5/8 -­‐ 0.56 0.56Inside -­‐ -­‐ 0.68

39.13

Component Thickness R-­‐Value  per  Inch R-­‐Value  per  Unit R-­‐Value(in.) (hr*ft^2*°F/BTU*in.) (hr*ft^2*°F/BTU) (hr*ft^2*°F/BTU)

Outside -­‐ -­‐ 0.17 0.17Brick 4 -­‐ 0.44 0.44Air  Gap 3/4 -­‐ 1.00 1.00Rigid  Insulation 2 4.80 -­‐ 9.60Zip  Wall  (Taped) 1/2 -­‐ 0.62 0.62Mtl  Stud  Fram.  with  R-­‐19  Batt  Ins. 6 -­‐ 7.10 7.10G.W.B. 5/8 -­‐ 0.56 0.56Inside -­‐ -­‐ 0.68

20.17R-­‐Value  of  Modular  Brick  Assembly

R-­‐Value  of  Thin  Brick  Assembly

Thin  Brick  By  Owensboro  Panels  w/  6"  3CI  Insulation  Panel  (1'-­‐2")

Modular  Brick  Veneer  (1'-­‐2")

0.00  

5.00  

10.00  

15.00  

20.00  

25.00  

30.00  

35.00  

40.00  

45.00  

1  

Chart  Title  

Series1   Series2  

Component Thickness R-­‐Value  per  Inch R-­‐Value  per  Unit R-­‐Value(in.) (hr*ft^2*°F/BTU*in.) (hr*ft^2*°F/BTU) (hr*ft^2*°F/BTU)

Outside -­‐ -­‐ 0.17 0.171/2"  Thin  Brick,  1/4"  Util-­‐A-­‐Crete,  and  6"  Polystyrene   6-­‐3/4" -­‐ 30.00 30.00Zip  Wall  (Taped) 1/2 -­‐ 0.62 0.62Mtl  Stud  Fram.  with  R-­‐19  Batt  Ins. 6 -­‐ 7.10 7.10G.W.B. 5/8 -­‐ 0.56 0.56Inside -­‐ -­‐ 0.68

39.13

Component Thickness R-­‐Value  per  Inch R-­‐Value  per  Unit R-­‐Value(in.) (hr*ft^2*°F/BTU*in.) (hr*ft^2*°F/BTU) (hr*ft^2*°F/BTU)

Outside -­‐ -­‐ 0.17 0.17Brick 4 -­‐ 0.44 0.44Air  Gap 3/4 -­‐ 1.00 1.00Rigid  Insulation 2 4.80 -­‐ 9.60Zip  Wall  (Taped) 1/2 -­‐ 0.62 0.62Mtl  Stud  Fram.  with  R-­‐19  Batt  Ins. 6 -­‐ 7.10 7.10G.W.B. 5/8 -­‐ 0.56 0.56Inside -­‐ -­‐ 0.68

20.17R-­‐Value  of  Modular  Brick  Assembly

R-­‐Value  of  Thin  Brick  Assembly

Thin  Brick  By  Owensboro  Panels  w/  6"  3CI  Insulation  Panel  (1'-­‐2")

Modular  Brick  Veneer  (1'-­‐2")

0.00  

5.00  

10.00  

15.00  

20.00  

25.00  

30.00  

35.00  

40.00  

45.00  

1  

Chart  Title  

Series1   Series2  

R-value

#  of  Pallets #  of  Panels #  of  Pallets #  of  Brickettes Material  Load  (lbs) Max  Load  (lbs)

1 48"  Flatbed 38   684   2   250   39,120   45,000  2 45"  Flatbed 35   630   2   250   36,300   45,000  3 45"  Flatbed 35   630   2   250   36,300   45,000  4 45"  Flatbed 35   630   2   250   36,300   45,000  5 45"  Flatbed 33   594   1   250   32,720   45,000  

176   3,168   9   1,250  

Thin  Brick  Panel  Truck  Delivery  Schedule

Total:

Panels Brickettes Truck  CapacityDelivery  # Truck  Type

Transportation Logistics

Elevation Size Productivity DurationSF SF/Day Days

North  Elevation 2,582   78 33South  Elevation 4,117   94 44West  Elevation 4,597   96 48East  Elevation 2,976   80 37

Courtyard  Elevation 2,391   159 15

177

Elevation Size Productivity DurationSF SF/Day Days

North  Elevation 2,582   140 18South  Elevation 4,117   140 29West  Elevation 4,597   140 33East  Elevation 2,976   140 21

Courtyard  Elevation 2,391   140 17

119

Scheduled  Modular  Brick  Construction  Durations

Projected  Thin  Brick  Construction  Durations

Total  Duration

Total  Duration

Elevation Size Productivity DurationSF SF/Day Days

North  Elevation 2,582   78 33South  Elevation 4,117   94 44West  Elevation 4,597   96 48East  Elevation 2,976   80 37

Courtyard  Elevation 2,391   159 15

177

Elevation Size Productivity DurationSF SF/Day Days

North  Elevation 2,582   140 18South  Elevation 4,117   140 29West  Elevation 4,597   140 33East  Elevation 2,976   140 21

Courtyard  Elevation 2,391   140 17

119

Scheduled  Modular  Brick  Construction  Durations

Projected  Thin  Brick  Construction  Durations

Total  Duration

Total  Duration

Schedule

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 23: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Appendix: Analysis 2

Material Area Cost  per  Unit Total  Cost(SF) ($/  SF) ($)

Modular  Brick 16,663               5.36$   89,313.68$  Thin  Brick  Panels 16,663               12.38$   206,287.94$  

116,974.26$                  

Brick  Construction  Cost  Comparison

Cost  Difference

Cost

43  𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊  𝐷𝐷𝐷𝐷𝐷𝐷𝐷𝐷  𝑜𝑜𝑜𝑜  𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇  𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆6  𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊  𝐷𝐷𝐷𝐷𝐷𝐷𝐷𝐷 ∗

$1,509,749.46  𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺  𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶  𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶20  𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀ℎ𝑠𝑠 ∗ 4   !""#$

!"#$!!

= $𝟏𝟏𝟏𝟏𝟏𝟏,𝟐𝟐𝟐𝟐𝟐𝟐

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix

Page 24: CONSTRUCTION OPTION JOSUE FERNANDEZ › ae › thesis › portfolios › 2014 › jif5105 › ... · Josue Fernandez 9.31.2013 LEGEND: 1. Parking 2. Contractor Staging Area 3. Material

Appendix: Analysis 3

Payback- Belkin WeMo

Payback- Nest Thermostat

5  𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆ℎ𝑒𝑒𝑒𝑒 ∗ 24  ℎ𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜  𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 ∗ 1.5  𝑊𝑊 ∗ 30  𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑  𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎1000 !"

!"!

∗ 0.11629  $  𝑝𝑝𝑝𝑝𝑝𝑝  𝑘𝑘𝑘𝑘ℎ = $0.63

63.60  $  𝑝𝑝𝑝𝑝𝑝𝑝  𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 ∗ 5  𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢$25.92  /𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 − $7.54  /  𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 = 17  𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦

265  $  𝑝𝑝𝑝𝑝𝑝𝑝  𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 ∗ 1  𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢$173  /𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 = 2  𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦

OUTLINE

_Project Overview_Delivery Method_Brick Veneer Panels_BA Components_Sensible Wheel_Final Conclusions_Acknowledgements_Appendix