construction tips & tricks stacy hagenbucher. common mistakes on finals source document –need...
TRANSCRIPT
Construction Tips & TricksStacy Hagenbucher
Common Mistakes on Finals
• Source Document– Need to reference back to the
source document – including tickets• HMA Density Incentive
– Tonnages need to broke out for shoulders along mainline
• Maintenance and Repair of Haul Roads– This needs to be paid on all projects
Common Mistakes on Finals
• Signs, Type II – Make sure the spreadsheet is
calculating the correct area – not all signs are rectangular
• No Passing Zone Logs– A copy need to be added to Finals for
Mike Worzella• Scale Checks
– Portable• DT1931
– Permanent
DT1931
Contract Modification Justification• Tool – Force Account Sheet
– In Pantry 2014-NC Region Folder– Generalized numbers only –
numbers will change based on project and location.
– Quick go by – useful to determine if modification justifiable
Contract Modification Justification• Bid Express
– www.bidx.com• Wisconsin Department of
Transportation
– Useful with a few exceptions• Keep it to our region• Maintain reasonable search criteria• Realize these are bid prices – contract
modification prices may run higher
Contract Modification Justification
Contract Modification Justification
Contract Modification Justification
Pantry 2014
• Updated the Electrical Spreadsheet to include tab for both types of side pulls.
• Added MGAL spreadsheet• Added spreadsheet for comments
– Please pass this on to me at end of construction year
– Will be used to modify any changes required for Pantry 2015.