Construction Traffic Analysis: To be or Not to be
A Case Study for NC-107 Widening, Sylva NC
Presented by
Taruna Tayal,
Donald A. Bryson, PE November 16, 2016
Project Background and Concerns
Major north/south
transportation corridor in
Jackson County
Northern Loop around Sylva
and Dillsboro
27,000-39,000 AADT in 2035
Congestion
Safety
Prioritize improvements
Implement traffic calming
devises
Minimize impacts to
surrounding businesses
NC-107 Corridor
Mostly commercial development
Few educational facilities
Approximately 95 driveways intersect this corridor
Sparse residential and commercial development
Fourteen signalized intersections along US 23 Business and NC 107
Modeling and Analysis
Design – Synchronized
Street
TransModeler Micro-
Simulation analysis
Scenarios studied
– 2015: Build and No-Build
– 2025: No-Build and
Construction
– 2035: Build and No-Build
Attributes Compared
– Level of Service
– Travel Time
– Delay (sec/veh)
– Queues
Design and Analysis
Courtesy: NC 107 Corridor Study Report
Jackson County Regional Model for
Growth and Base network
Network disaggregated in
TransModeler for finer geography
ODME in TransModeler for 2013 trip
table
Fratar for FY trip table
Modeling
Design and Analysis
2025 Under Construction
2035 Build
Findings
Travel Time Savings and LOSSkyland Drive to Fairview Road
Performance
MeasureTime of Day Direction
Construction Year (2025) Future Year (2035)
No Build
Under
Construction No Build Build
Travel Time
(minutes
(AM Peak
Hour)
Northbound 6.3 6.6 13.3 5.5
Southbound 12.6 9.4 18.7 14.4
(PM Peak
Hour)
Northbound 13.4 22.3 28.3 7.9
Southbound 12.5 12.7 19.2 14.3
Average
Speed (Miles
per hour)
(AM Peak
Hour)
Northbound 28.8 27.5 10.1 23.6
Southbound 14.4 19.3 7.0 9.2
(PM Peak
Hour)
Northbound 13.5 8.1 5.1 16.8
Southbound 14.5 14.3 6.9 9.6
LOS
(AM Peak
Hour)
Northbound B B F C
Southbound E D F F
(PM Peak
Hour)
Northbound E F F D
Southbound E E F F
Delay Savings (Seconds/Vehicle)
-500.0
-400.0
-300.0
-200.0
-100.0
0.0
100.0
200.0
300.0
US 23 Business/ Skyland Drive
NC 107 /Chipper Curve
Road
NC 107 / US 23Business
NC 107 /Cherry Street
NC 107 / CopeCreek Road
NC 107 / Wal-Mart Entrance
NC 107 / JonesStreet
NC 107 /Lowes
Entrance
NC 107 / NC116
NC 107/Fairview Road
Construction Year (2025) AM Peak Hour Construction Year (2025) PM Peak Hour
Design Year (2035) AM Peak Hour Design Year (2035) PM Peak Hour
AM Peak Hour Southbound Queue Length(Feet)
0
200
400
600
800
1000
1200
NC 107 / US 23Business (Asheville
Highway)
NC 107 / CherryStreet
NC 107 / CopeCreek Road /
Walter Ashe Road
NC 107 / Wal-MartEntrance
NC 107 / JonesStreet / Brysons
Farm Road
NC 107 / LowesEntrance
NC 107 / NC 116(Webster Road)
NC 107/ FairviewRoad
Constrution Year (2025) No-Build Constrution Year (2025) Build Design Year (2035) No-Build Design Year (2035) Build
PM Peak Hour Northbound Queue Length(Feet)
0
200
400
600
800
1000
1200
1400
1600
NC 107 / US 23Business (Asheville
Highway)
NC 107 / CherryStreet
NC 107 / CopeCreek Road /
Walter Ashe Road
NC 107 / Wal-MartEntrance
NC 107 / JonesStreet / Brysons
Farm Road
NC 107 / LowesEntrance
NC 107 / NC 116(Webster Road)
NC 107/ FairviewRoad
Constrution Year (2025) No-Build Constrution Year (2025) Build
Design Year (2035) No-Build Design Year (2035) Build
Conclusion and
Lessons Learned
Work zone implementation strategies such as lane closures and
time restrictions,
Phase construction
– Construction of U-turn bulb-outs
– Southbound outside widening
– Northbound outside widening
– Median widening
Left turns may be considered from NC 107 to northbound US 23
Business (Asheville Highway)
Add roundabout at the intersection of Caldwell Street and Cherry
Street
Recommendations
Pros and Cons
Better Construction
Revise interim and final design
Help the businesses understand
the impacts
Costly Analysis
Only Peak Hour impacts
No Construction safety
Performance Measures
& Construction Impacts
Travel time savings =
critical performance measure
Should construction
impacts be considered?
Excellent case study– No feasible alternate routes
– No practical transit / TDM options
– Simple but realistic assumptions
Considers only travel delay benefits
Reducing Travel Delay
Chart
CONSTRUCTION
OPEN
Chart
Cost Benefit AnalysisCONSTRUCTION
OPEN
Chart
Cis
0%
2%
4%
8%
($5,000)
($2,500)
$0
$2,500
$5,000
$7,500
$10,000
$12,500
$15,000
$17,500
2 0 2 4 2 0 2 5 2 0 2 6 2 0 2 7 2 0 2 8 2 0 2 9 2 0 3 0 2 0 3 1 2 0 3 2 2 0 3 3 2 0 3 4 2 0 3 5
AN
NU
AL
SAV
ING
S IN
20
14
DO
LLA
RS
(10
00
'S)
EFFECT OF DISCOUNT RATE ON CUMULATIVE DELAY SAVINGSANNUAL TRAVEL T IME SAVINGS IN $1000S
0%
2%
4%
8%
CONSTRUCTION
OPEN
http://tcsidewalks.blogspot.com/2013/03/what-does-peak-vmt-mean-for-twin-cities.html
US VMT (12-Month Moving Total)
1990 2000 2010 20202015 202520051995
Other construction impacts…CONSTRUCTION
OPEN
Fuel consumption?
Economic impacts?
Air quality?
Safety?
Construction impacts can be significant– New alignment vs widen existing
– Evaluate:
• Operational improvements
• Demand management
• Alternate modes
– Is rigorous construction planning justified?
Beware of “end-state” planning– Interim matters
– Immediate vs long-range impacts
Benefit/Cost: Simple Complicated
What about uncertainty?
Things to ponder:
23 offices throughout the east coast
www.vhb.com
Taruna Tayal| [email protected] | 919.741.5525
Donald A. Bryson | [email protected] | 919.334.5615
Questions / Comments