    Construction Update Week o December 7, 2009Men o Gamma,

    Greetings men! I realize it has been a month and a hal since the last newsletter but believe me,there has been no shortage o progress. Since my last newsletter, we have nally received ourbuilding permit and have begun reconstruction in earnest. You will see by the photos throughout,we have not only started rising rom the ground but the historic chapter house is also beginning to

    take shape.

    Te majority o the action has occurred in three key areas; the oundation o the new addition, theinterior raming o the new suites in the chapter house, and utility work. Right now you can standin our uture multi-purpose basement and start to envision uture gatherings where alumni andactives join together and celebrate our common bonds. You can walk the ramed corridors o ourhistoric house and envision the great common space that has been created to bring our memberscloser in riendship. You can stand in the area o our uture Alumni errace and realize our housewill be the envy o all other raternities on campus.

    With those words I will show you the progress through photos but remind you that our work as Alumni is not complete. We are still short o our undraising goals and we are looking oryour help. We have various options or your involvement including tax ree donations to the

    oundation, simple gi s o any value, pledges spread out over months or years, or thepurchase o notes to support our immediate needs.

    Our bank nancing is in place, our contractor is hard at work and now we need you tohelp at whatever level possible! Please think about being a part o our campaign and giveback to the house that has hope ully given you memories and bonds or li e.

    All the Best,

    T.J. Blakeman, Construction Chair Pledge Class of 1999(217) 414-0630 or [email protected]

  • 8/14/2019 Construction Update December 7, 2009

    2/4View all of the construction photos (updated weekly) at www.aklgamma.com .

  • 8/14/2019 Construction Update December 7, 2009

    3/4

    If you plan to be in the Champaign-Urbana area and would like to tour the house, please

    contact T.J. Blakeman at (217) 403-8800 and we will schedule a visit.

    Entrance to Second HouseSuite

    Common study space in third foor SeniorsSuite

    Second House Suite

    Third house stair landing

  • 8/14/2019 Construction Update December 7, 2009

    4/4

    We Still Need Your Help!Although work is underway we have met 90% o our unding goals we must continue our

    undraising eforts to complete the project. We are hoping that as you see work underway, thatyou will eel con dent in our progress to continue or begin making generous contributions.

    o complete this project we need

    YOUR HELP!!! Visit www.aklgamma.com to contribute any amount

    Connect with Alpha Kappa LambdaAKL Gamma has create a number o ways or you to stay in touch with us. Please take time to

    connect with us so we can keep you up to date with all o the changes at gamma.

    www.aklgamma.com - Chapter website and Alumni DatabaseNew website coming soon!

    Alpha Kappa Lambda - Gamma Chapter - on facebook @AKL_Gamma on TwitterKlaxon - Newsletter

    www.akl.org - National Fraternity Website

    Alpha Kappa LambdaGamma Chapter 401 East Daniel Street Champaign, Illinois 6182