consultation report
DESCRIPTION
TDP Consultation ReportTRANSCRIPT
iv
Table of Contents
1. INTRODUCTION .................................................................................................................................. 1
2. CONSULTATION PROCESS .................................................................................................................. 1
2.1 Public Consultation ....................................................................................................................... 1
2.2 Other Consultation Meetings ....................................................................................................... 1
3. FOCUS OF THE CONSULTATION ......................................................................................................... 3
3.1 Volume I: Major Network Development....................................................................................... 3
3.2 Volume II (Part 1): Operations and Maintenance ......................................................................... 3
3.3 Volume II (Part 2): Metering ......................................................................................................... 3
3.4 Volume III: System Operations ..................................................................................................... 3
4. RESPONSE ........................................................................................................................................... 4
5. SUMMARY OF COMMENTS ................................................................................................................ 5
Tables
Table 1 Distribution of Participants ..................................................................................................... 4
Table 2 General Issues ......................................................................................................................... 6
Table 3 Luzon Grid Issues .................................................................................................................. 30
Table 4 Mindanao Grid Issues ........................................................................................................... 34
Table 5 Visayas Grid Issues ................................................................................................................ 36
Annexes
Annex A Pro-forma Invitation
Annex B Broadsheet Publications
Annex C DoE Meeting Highlights
Annex D List of Participants
1
1. INTRODUCTION
In response to the changes in the electrical transmission system and to the needs of its
customers across the country, NGCP undertakes the annual updating of the Transmission
Development Plan (TDP). Republic Act No. 9136 or the “Electric Power Industry Reform Act
of 2001 (EPIRA)” mandates NGCP to consult the Electric Power Industry Participants in the
preparation of the TDP.
This report contains the proceedings of the public consultations for the 2011 TDP. It explains
NGCP’s position and response to the questions, comments and inquiries raised during the
various consultation meetings.
2. CONSULTATION PROCESS
The consultation process started even prior to the conduct of simulation studies when NGCP
met with district offices together with major customers nationwide, to validate the
substation forecast and discuss any significant development that may require expansion of
transmission facilities.
Upon completion of the TDP Consultation Draft and meeting with DOE and TRANSCO, NGCP
formally started with the consultation process with the posting of the Consultation Draft
(Volumes 1 to 3) on NGCP’s corporate website (www.ngcp.ph) starting 13 December 2011.
The pro-forma invitation (please see Annex A), which was signed by the NGCP President,
were distributed nationwide to the grid customers.
To reach to a greater audience, NGCP published the announcement for the Public
Consultation on two major broadsheets (see Annex B), The Philippine Star and Philippine
Daily Inquirer on 11 December 2011 and 10 December 2012, respectively.
2.1 Public Consultation
NGCP conducted the consultation meetings with the stakeholders by region:
Luzon – 05 January 2012 at Sulu Hotel, Diliman, Quezon City
Mindanao – 10 January 2012 at Marco Polo Hotel, Davao City
Visayas – 13 January 2012 at Parklane Hotel, Cebu City
2.2 Other Consultation Meetings
NGCP also conducted separate presentation meetings with major stakeholders:
Philippine Electricity Market Corporation (PEMC) – 22 November 2011 at PEMC Office,
Robinsons-Equitable Tower, Ortigas Center, Pasig City;
2
Grid Management Committee (GMC) and Distribution Management Committee (DMC) –
13 December 2011 at the NGCP Office;
Manila Electric Company (MERALCO) – 15 December 2011 at Lopez Building, Meralco
Compound, Ortigas Avenue, Pasig City;
Department of Energy (DOE) –The first consultation meeting was held on 20 September
2011 at the NGCP Building, Quezon Avenue Corner BIR Road, Diliman, Quezon City. Present
in the meeting were the department undersecretaries and directors of the different
bureaus.
The second meeting with DOE was held at the PEMC Office Robinsons-Equitable Tower,
Ortigas Center, Pasig City, on 05 December 2011 with no less than DOE Secretary Jose Rene
D. Almendras presiding. The highlights of this meeting are listed in Annex C; and
National Transmission Corporation (TransCo) – NGCP met with the National Transmission
Corporation on two occasions to discuss the TDP Consultation Draft. The first was on 12
September 2011 at NGCP Office while the second meeting was on 04 January 2012 at the
TransCo Office.
3
3. FOCUS OF THE CONSULTATION
The public consultation is a venue and opportunity for the stakeholders to provide feedback
and comment on the content and scope of the TDP. The three-volume TDP consists of:
Major Network Development (Volume I), Operation and Maintenance Programs (Volume II,
Part 1), Metering Services (Volume II, Part 2) and System Operations (Volume III, Part 1).
3.1 Volume I: Major Network Development
This report focuses on the proposed network expansion and upgrades which are based on
the system simulations studies conducted by NGCP.
3.2 Volume II (Part 1): Operations and Maintenance
This report covers the plans to ensure the network’s reliability and capability to
continuously provide the level of power quality required by the industry. Included herein
are the proposed plans for the rehabilitation, replacement, repair and/or maintenance of
transmission and sub-transmission lines and substation equipment covering each grid.
3.3 Volume II (Part 2): Metering
This report covers the proposed capital projects for expansion, upgrade, rehabilitation and
replacement programs of NGCP for Transmission Revenue Metering Facilities. It also covers
the acquisition of capital equipment and common-use infrastructure for revenue metering
service.
3.4 Volume III: System Operations
This report covers the proposed upgrading, restoration, replacement, repair and/or
maintenance projects for the telecommunication systems and infrastructures, protection,
SCADA/MBSC and other supervision-related applications and equipment necessary for the
effective management of the national power grid and the system’s stability, and in
dispatching generation, including but not limited to market operations and arrangement for
ancillary services.
4
4. RESPONSE
A total of 187 stakeholders across the archipelago representing 56 electric cooperatives, 16
private distribution utilities, 40 generation companies, 60 non-utility customers, 6
government agencies and 9 non-governmental organizations participated in the public
consultation meetings. Shown below is the breakdown of the attendees from each grid.
Table 1 Distribution of Participants
Category Luzon Visayas Mindanao Philippines
Cooperative 22 16 18 56
Private DU 10 3 3 16
Government 3 2 1 6
Generators 21 14 5 40
Industry 35 14 11 60
Others (Academe, NGO’s, etc.) 6 1 2 9
TOTAL 97 50 40 187
5
5. SUMMARY OF COMMENTS
The comments, issues and questions raised during the public consultation meetings and
sent to [email protected], and NGCP’s response to each of them, are summarized in
the following pages.
2011 Transmission Development Plan Public Consultation Report
6
Table 2 General Issues
Issues Concerned
Party
Comments NGCP Response Issues Concerned
Party
Comments NGCP Response
1 TDP Preparation
TransCo TransCo expressed its desire not only to be
consulted but to be actively involved in the TDP
preparation.
TransCo admits that presently, they do not
have yet the technical capabilities in using the
special application software for system
simulation studies.
NGCP has invited TransCo to participate in an
in-house training on power system studies and
transmission planning. This is part of NGCP’s
efforts to extend assistance to TransCo in terms
of capacity building for the latter’s technical
team.
CEPALCO There seems to be some lapses in the
transmission development planning if it is not
based on an integrated resource planning
approach. We understand that this is not solely
the responsibility of NGCP. However, we
suggest NGCP to initiate discussions with DOE,
with generators and distributors as well, in the
preparation of the PDP and TDP under an
integrated resource planning framework..
With the enactment of EPIRA, generation
planning becomes DOE’s responsibility and
transmission by NGCP. NGCP assures that
before the conduct of the simulation studies for
the TDP, there has been good coordination
between NGCP and DOE. NGCP will also take up
the issue with DOE.
2 Proposed Projects
TransCo Are those projects being declared by DOE in the
list include indicative projects?
Both committed and indicative are included in
DOE’s plan.
Per agreement with DOE, NGCP will follow the
generation line up listed in the DOE Power
Development Program (PDP). It should be
noted that the PDP and TDP are updated on an
annual basis.
TransCo TransCo is aware of the November 2010
application of NGCP. Our observation was there
were notable changes from the said application
Some other projects were already identified
but were not filed yet because of prioritization
and transmission tariff impact consideration.
2011 Transmission Development Plan Public Consultation Report
7
compared to the 2011 TDP when the draft
came out some time mid 2011. How come
there were major additional projects in such a
short time?
NGCP needs to implement the projects this
early, thus the decision to file them, to meet
the target completion of these new projects.
ANECO Assuming the years written on the TDP are the
indicative years that the plants will be online,
have you validated if the proposed power
projects will really be online on the indicated
years therein? There are instances that we
cannot implement the power projects on the
year it is expected to come in.
There are two planning inputs. The first is the
planning forecast and the other one is the
generation capacity addition. Between the two,
the forecast is pretty straight forward while
capacity addition is difficult to follow. NGCP’s
problem is on the generation capacity addition.
Our agreement with the DOE is that the PDP,
which contains both the load forecast and
capacity addition, will be the official reference
line. So basically, NGCP just follow what is in
the PDP.
3
Generation
Capacity Addition
TransCo According to NGCP. 4,188 MW is the total
conventional and renewable energy for Luzon
for the next 20 years based on DOE’s list, but
during the hearing at the ERC with the
presentation of NREB, what was initially
proposed was about 760 MW. How will you
explain this discrepancy?
NGCP follows the generation line up listed in
the PDP. DOE may have come up with different
figures on the installation target for certain
years, the reason for any discrepancy in the
figures.
The 4,188 MW is the total of conventional and
renewable energy. The renewable energy for
Luzon is 432.3MW. In terms of installation
target for RE, NGCP will follow DOE which
among the power plants will be included in the
installation target. According to DOE,
whichever comes first will get the slot for the
allocation target.
GMC Do all these generation capacity addition No, not all of these projects have GIS. Some of
2011 Transmission Development Plan Public Consultation Report
8
projects already have completed the grid
impact studies?
them have not yet contacted NGCP for the
conduct of their respective GIS. As long as a
project is included in DOE’s list, NGCP will also
include those projects in the assumptions.
GMC Are these projects committed? Considering
indicative generation projects may impact to
higher wheeling charges.
From a transmission planning perspective, it is
better that these indicative generation projects
be included in the assumptions. However, the
ERC would have to evaluate the level of
commitment of these projects before it
approves any associated transmission
expansion investment. It is important to note
that since the TDP is updated on an annual
basis, should there be changes in the status of
the generation projects, NGCP can easily reflect
them in the transmission plan.
GMC At what point do you change the generation
capacity addition projects from indicative to
committed?
NGCP relies on DOE being the agency
responsible for generation planning.
Global Business
Power Corporation
Is there already a budgetary allocation based
on the time frame you have mentioned for your
demand and transmission capacity projects?
NGCP is committed to implement and complete
all ERC-approved projects, in which the
corresponding capital expenditure (CAPEX)
program (where the annual budget for each
project is indicated) is already part of the ERC’s
Final Determination (FD). For the new projects
not included in the FD, they will be filed with
the ERC for provisional approval.
4 System
Operations
TransCo What is NGCP’s data center standard? It is consistent with IEC standard. (NGCP will
provide a copy of this policy at the NGCP-
TransCo Data Center).
TransCo
Will SO still procure any protective relay or will
not anymore?
There is a delineation of responsibilities
between O&M and SO groups of NGCP
regarding this.
MERALCO What is the standard of SO for substations? NGCP follows that of the IEC, but plans to adopt
2011 Transmission Development Plan Public Consultation Report
9
other standards once the Smart Grid is
implemented.
MERALCO Any concrete plan on how to implement Smart
Grid technology?
In all new projects, NGCP is already
implementing Smart Grid technology based on
IEC standard.
TransCo NGCP intends to use OPGW fibers for both M1
and M2 line protections. How can redundancy
be addressed under this scheme?
Only stations within fiber loops—e.g., with
OPGW routes in different directions—shall use
fiber for both M1 and M2. Otherwise,
microwave radio shall be used to provide the
redundant path for the required differential
protection.
Aboitiz Power
Hedcor
What are SO’s requirements for the RE systems
that may be coming in? What are the
equipment needed on our side?
NGCP is working closely with DOE on how to
establish these requirements for RE sources or
embedded generation. NGCP is revising the
specifications that will enable them to integrate
these RE sources to the system. For REs, NGCP
would want them to be connected through
fiber links.
Currently, we only have one market for Luzon
and Visayas.
The objective is to make the system operation
as a single entity. That is complementary to the
market objective which is to make one open
market. The hierarchical design is for efficient
dispatching.
5 Telecoms and
SCADA
TransCo To support the proposed replacements due to
limited bandwidth, a summary of channel
loading or utilization must be included in
NGCP’s TDP.
Do we have some system to monitor whether
all these equipment have been fully utilized?
NGCP can provide the SCADA/EMS reports,
bandwidth demand per typical node and
bandwidth allocation in backbone.
For SCADA applications, NGCP can produce the
report they submit on a day to day basis, e.g.,
2011 Transmission Development Plan Public Consultation Report
10
Do we have that assessment?
the EMS applications.
For the bandwidth utilization of telecom, NGCP
can provide based on the breakdown of the
traffic. NGCP can describe which part of the
bandwidth is used by which application and
which network element manages this particular
traffic.
NGCP can provide the following:
• SCADA/EMS reports
• Bandwidth demand per typical node
• Bandwidth allocation in backbone
TransCo What are those EMS applications in the new
SCADA that you are proposing?
Higher version of the RTU data storage,
advance estimator and contingency analysis in
order to consider the market operation.
TransCo Can the IT equipment/facilities needed by SO
be provided by corporate IS/IT?
All IT equipment specs and acquisitions
(outside SCADA equipment), including those
needed by S.O., are supervised by our IT
Department.
TransCo Is DOST or DOTC coordinating with NGCP
regarding the required NDN knowing that they
are trying to revive the telecommunication
stockroom of the Government?
What is the commercial agreement for such? Is
there a rebate to the transmission charge (PDS)
in as much as there is an extra income for that?
Yes, DOTC already approached NGCP. Also,
PAGASA is utilizing NGCP’s backbone. However,
there is no existing commercial agreement with
DOST nor with DOTC yet with regard to the
PAGASA use of NGCP channels inasmuch as the
channels are used for public service. NGCP
does not derive any extra income on PAGASA’s
use of the these facilities
TransCo Why is split type highly recommended in TDP?
This type is more difficult to maintain as the
transceiver is installed on top of antenna
tower.
As stated in the TDP, the energy-efficient (and
cheaper) split-type radio technology shall be
adopted where feasible (e.g., for up-to-STM1
radio links) to optimize radio transmitter
power, eliminate waveguide-caused problems
2011 Transmission Development Plan Public Consultation Report
11
and minimize dependence on air-conditioning
requirements (and reduce failure rates caused
by overheating).
TransCo Can we use lease channels as back up in some
areas to reduce CAPEX? A study shall be
conducted in the aspects and be included in
TDP.
Leased channels are indeed being used as (less-
secure) backups where feasible. They are also
used to provide short-term communication
facilities. Incorporating in the TDP the
economic selection study for each permanent
telecom link would be rather cumbersome (and
may not be necessary given the knowledge of
existing public infra and prevailing lease
rates)—perhaps we can address this issue in a
more specific manner?
TransCo Is it possible to have a 100% physical
redundancy (1+1) via OPGW? Existing
transmission lines, in some areas, may not
allow such configuration. Is this not very
expensive?
Not all stations can be provided with 1+1
physical redundancy via existing OPGW.
Microwave radio provides an alternate route in
some cases to attain the 1+1 mode.
TransCo Are the installations of IP ready S/S
automations synchronized with the
installations of IP connectivity?
NGCP already has IP connectivity and their
applications are migrating towards the use of
this method of transport. The new S/S
automation systems are thus specified to
operate using IP-mode standards upon
commissioning.
6 Right-of-Way DOE The DOE recognized the difficulty of acquiring
right-of-way for transmission projects and, at
times, local government units intervene in
locating the transmission routes. In response,
DOE is working with different government
agencies in identifying Projects of National
2011 Transmission Development Plan Public Consultation Report
12
Significance (PNS) to ensure their timely
completion. NGCP’s transmission projects may
well qualified as PNS.
GMC Nowadays, it is difficult to secure right-of-way.
It is critical that NGCP should identify which
generation projects are committed for planning
purposes. How are the indicative plants taken
up in your TDP?
NGCP still considers the indicative power plants
because there are cases wherein they require
transmission reinforcements. However, once a
project was identified, we consider it as a
generation-associated project and identify
which power plant triggers the need for that
project.
7 Command Center MERALCO Will the command center of NGCP be manned? Yes it will be manned 24/7. We will be in close
coordination with NDCC (NDRRMC).
8 Legal Issue
TransCo On Hanjin reimbursement issue, would NGCP
be paying for it since it will be reclassified as
transmission?
It was clarified by TransCo that based on EO
701, TransCo has to pay but since it will be
reclassified as Transmission, NGCP has to pay
for that line.
In its latest letter, Transco would like to
transfer to NGCP the facilities so that the latter
can operate and maintain them.
San Miguel Power
Corporation
Suggests NGCP to advise the electric utilities
that what should be covered by our
Distribution Service Agreement are distribution
wheeling services agreement. The transmission
services agreement are still being signed by
NGCP and utilities should only sign the
distribution wheeling services agreement.
NGCP will follow ERC’s rules on the commercial
relationship between the customers and its
service providers.
9 Congestion
Aboitiz Power Is the Lumban-Bay Upgrading scheduled in
2013 similar to the MakBan-Calauan-Kalayaan
line project which is expected to solve the
congestion problem in that area?
NGCP confirms that the Lumban-Bay Upgrading
Project is the same with the Kalayaan-MakBan
line which is now being upgraded to four
bundle 795 MCM.
10 Tudaya I (6 MW)
and Tudaya II (7
GMC How come these projects are not included in
your list when they are in the pipeline of GIS?
NGCP based its study assumptions on the
generation line up contained in DOE’s PDP. If
2011 Transmission Development Plan Public Consultation Report
13
MW) the proposed generation project is not included
in the PDP, it is likely that it is not also included
in NGCP’s list.
11 N-1 and N-2
TransCo Had there been a decision on the issue
regarding the N-1 and N-2 consideration during
the planning and operation perspective? Has
there been a resolution?
NGCP is looking at N-1 from two different
perspectives - from a planning perspective and
from an operation perspective. From a planning
perspective the system is intact; all the
elements are complete when you apply the N-
1. From an operation perspective, the system
is already altered when N-1 is applied.
NGCP maintains its position that the application
of N-1 should be taken in planning and
operations perspective.
TransCo How will you consider NGCP’s planning
methodology, deterministic or probabilistic?
Woudn’t probabilistic approach be more
appropriate?
NGCP’s planning methodology, at the moment,
is based on deterministic approach. NGCP is
still waiting for ERC’s recommended approach.
12
Renewable
Energy
AES Masinloc We have noticed that RE is already considered
in the 2011 TDP. Have you considered REs that
will be connected through the distribution
system or just those that will be connected in
the transmission? In the event that the RE is
not suitable to connect to distribution system,
how will it be considered in the succeeding
TDPs?
NGCP will propose a guideline that will govern
RE’s connection to the grid.
MERALCO Any updates on RE penetration limit of NGCP? NGCP has not finalized yet the penetration limit
study.
2011 Transmission Development Plan Public Consultation Report
14
Aboitiz How will these RE projects going to be
integrated? Is that part of the challenges that
NGCP is seeing in the next years?
One of NGCP’s mandates under RA 9513 is to
provide priority connection to RE sources.
Given the intermittent nature of some RE,
there should be a different set of technical
requirements to govern them which are not yet
included in the Grid Code. NGCP is currently
developing these requirements which will be
the basis in integrating RE to the grid.
Aboitiz To date, we only have one wind power project
and that is located in North Luzon.
Operationally, can NGCP provide us an insight
as to the integration of that plant to the
transmission system?
We already have informed the DOE with the
need to conduct a study called Renewable
Energy Integration Study (REIS) that will
complement the standard Grid Impact Studies
(GIS). The main purpose of the REIS is to take
into consideration the intermittent nature of
the RE sources (wind and solar PV). NGCP is still
developing the methodology of the REIS.
CEPALCO Did NGCP recommend to DOE the 50 MW
maximum limit of solar PV to be installed to
avoid introducing problems of intermittency
and interruption in the grid?
First, it is the DOE and not NGCP that sets the
installation targets for RE. Based on NGCP’s
recent study which was submitted to the DOE,
Mindanao does not have adequate regulating
reserves to support intermittent RE. That could
be one of the reasons of DOE for reducing the
installation target.
CEPALCO The objectives of system operations should be
attached with the corporate objectives to
accelerate access to RE sources. It is observed
that NGCP is somehow trying to obstruct or
delay the entry RE sources and to limit the
amount of embedded generation in our
system. What is the intent of NGCP in regards
to these RE sources?
NGCP’s mandates under RA 9513 is clear – to
provide priority connection to RE and to
establish the penetration limit for intermittent
RE. Any recommendation on the integration
capacity will be based on the results of the
study.
For embedded generation, NGCP is not
obstructing their entry. According to OATS
Rules, it should be GMC that will be setting the
2011 Transmission Development Plan Public Consultation Report
15
limit of the embedded generation.
Conal Holdings
Corporation
Is the system ready for RE? This will depend on the location, capacity and
timing of RE projects. We have completed the
initial study that will determine the capacity of
the grid to integrate RE. To make the system
more robust, NGCP has ongoing projects
associated with RE in northern Luzon (San
Esteban-Laoag Transmission Upgrading Project)
which includes the expansion of the Laoag
substation for the incoming wind power plant.
13 Embedded
Generation
MERALCO What is the status of NGCP’s proposal to limit
Embedded Generation?
NGCP is still in consultation with other
stakeholders.
14 O&M
TransCo How do NGCP consider SPS? What is your
reliability level for SPS?
SPS was revised to address simultaneous
trippings. N-1-1 cases do not require SPS.
However, N-2 cases require SPS.
TransCo In the multiple tripping of Tayabas substation,
the MBSC display was not updating due to UPS
being affected by said trippings. What is the
plan of NGCP to resolve this problem?
The UPS has already been replaced.
TransCo Some equipment which is due for replacement
does not meet the economic service life set by
ERC. Is NGCP inclined to provide good products
and good maintenance services to extend said
equipment economic life span?
The economic service life is not the only driver
in replacing the equipment but the actual
condition whether it is still good or is already
deteriorating. However, our experience shows
that as the equipment age, more and more
problems are already manifesting. Therefore
for planning purposes we need to already plan
for replacement of equipment that shows a
pattern of failures.
2011 Transmission Development Plan Public Consultation Report
16
There is really a need for O&M to have a good
maintenance strategy to extend the life of this
equipment since ERC has put a cap on O&M’s
expenditures.
TransCo Why do we need to monitor water elevations
for hydro plants when it is the obligation of the
generators to inform the customers of the
availability of supply?
In order to monitor reserves especially for
Mindanao in ensuring the stability of the grid.
TransCo For O&M expenditures, may we be clarified on
2 issues: On the secondary devices - start from
where to where?
What about in the substation?
Starts from the control system, line protection
even up to the battery system because these
are fault clearance system. Every device in the
system is somehow connected to the function
of the whole system. For example, if the
battery is not working, the system cannot
supply the control and the protection system.
TransCo You have said that a lot of the equipment
reached the useful economic life, what if those
equipment still passes the test of Material
Testing Division (MTD), what is your plan? Do
you intend to replace everything?
NGCP needs to establish a trend. If there is a
significant change in the trend, it will be
analyzed and decided if there is a need for
replacement. There must be other
consideration. Take for example, if the power
factor tests of the insulation of equipment
show signs of deterioration we need to plan the
replacement as part of the pro-active measure.
TransCo Have you come up with the policy regarding
spare parts?
NGCP has a policy on spares. But even for
spares, we cannot acquire the desired level of
spares. NGCP’s strategy is to acquire the spares
from major engineering projects that involve
replacement of equipment. Some of the
replaced equipment which are in good
condition will be refurbished and will serve as
spares. The approved budget is a constraint to
establish the desired level of spares.
2011 Transmission Development Plan Public Consultation Report
17
TransCo Is equipment restoration time considered in the
determination of appropriate connectivity for
teleprotection system? There are links with
higher speed/capacity but need longer time to
restore.
Yes, NGCP is taking into consideration the
equipment restoration time in determining the
appropriate connectivity for teleprotection
system.
TransCo To support replacements of operational but
obsolete equipment, a summary of channel
loading or utilization must be included in
NGCP’s TDP.
Operational equipment that need to be
replaced because of obsolescence refer to (a)
those with no available spare-parts support,
and therefore risk run-to-failure outage, or (b)
those that no longer work with existing
standards. This consideration has little to do
with channel loading or utilization.
The respective descriptions of the aging of
specific network elements are described in
System Profile (Section 2) of each discipline. For
example, in the case of Telecoms, Table 2.1.1
lists the significant network components (e.g.,
M/W Radio, OPGW, OLTE, PLC/PSE) and
provides respective overviews—per network
element and per region—in relation to the ERC-
defined economic lives. (Detailed accounts for
each unique equipment installed at a particular
station are as recorded in the Fixed Assets
Register.)
TransCo Why do we have to phase out PLC? PLC is the
most reliable link in power system
teleprotection.
Differential protection is preferred over
distance protection—PLC cannot carry
differential signals because of its limited
bandwidth. And even for distance protection,
we do not agree that PLC is the most reliable
link in all cases because of the less predictable
2011 Transmission Development Plan Public Consultation Report
18
effect of noise on its analog signals.
TransCo Why do you have to implement projects in-
house? This has no warranty, supplied
equipment can be used in other areas and it
affects maintenance works.
As stated in the TDP, in-house implementation
optimizes in-house engineering resources,
minimizes implementation time and
synchronizes construction with operational
priorities. This results in lower overall cost,
efficient design (e.g., no need to replace
serviceable components), and less interruption
to operations (i.e., no special shutdowns). Of
course, all new equipment has warranty.
DOE DOE Secretary inquires about the inventory of
Polychlorinated Biphenyl (PCB)
NGCP confirms that all equipment with PCB has
been identified (first phase) and there is an
ongoing program to replace/manage them in
compliance with environmental regulations.
SN Aboitiz Power
Benguet
What are the measures that NGCP is
undertaking in relation to the hazards in
landslide prone areas?
NGCP embarks on mitigating measures such as
building massive concrete structures or
relocating structures to more stable sites. NGCP
also undertakes pilot testing of vetiver grass
that prevents soil erosion.
MERALCO What is the plan of NGCP on transformer which
exceeded its economic life?
NGCP has a replacement plan for these old
transformers.
MERALCO Does NGCP have an upgrading/replacement
program so MERALCO can align to the
program?
NGCP regularly submits to DOE its Grid
Operating Maintenance Program (GOMP)
which covers a 3-year planning period.
SOVECO Do you have a record on the percentage of the
economic life of equipment to determine how
much it contributes to failure and if it is due for
replacement?
The suggestion is duly noted. The statistics is
more applicable to major equipment of the
transmission system such as transformers,
circuit breakers and the like. For the statistics
of the percentages, NGCP has the details of
these incidents before it arrived at the
conclusion to replace these components.
2011 Transmission Development Plan Public Consultation Report
19
GMC Have you considered the costs that sabotaged
lines will incur in the O&M CAPEX budget?
It is difficult to anticipate when and where a
sabotage will take place. At any rate, budget
will be allocated to repair any damaged facility.
15 Metering
San Miguel
Corporation
Who checks your meters’ accuracy and
calibration? Suggested annual audit of the
meters by third party.
Meters and instrument transformers are
checked by NGCP and by ERC.
TransCo Do we still have manual downloading?
Yes, if there is a problem in communication.
TransCo In the event that there is no problem in
communication, is everything automated?
Yes, the only limitation is the availability of
networks to support data communication
requirements.
MERALCO For AMR metering, what technology is NGCP
looking at? MV90?
A newer version of MV90 which is capable of
using IP-based telephony and GPRS to connect
to the meters is being acquired to replace the
existing system.
MERALCO In regards to PT/CT testing or metering, who
should shoulder the testing of metering
equipment?
Based on the Grid Code, the asset owner
should shoulder the cost of testing.
MERALCO MERALCO requested NGCP to consider the
timing of meter testing for alternate meters.
NGCP notes this request and will closely
coordinate the timing of the work with the
concerned Customer or Generator.
MERALCO What is the regulator’s economic life for meters
of NGCP? It is 15 years for MERALCO.
For NGCP, it is 10 years.
Do the installations of alternate meters mean
additional charges to the customers’ present
metering service charges?
The installation of alternate meters will add to
the Regulatory Asset Base for revenue
metering, which will be recovered through the
MSP charge. However, the cost of meters is not
really that substantial, and is outweighed by
the benefits of having these installed as we
2011 Transmission Development Plan Public Consultation Report
20
have experienced in Luzon and Visayas.
In regards to the relocation and consolidation
of the metering points, there are customers
with many metering points, will this result to a
substantial increase in the metering charges
even for the existing individual metering
points?
If the only development will be the
consolidation of metering facilities then the
total number of metering facilities will really
decrease. However, through the years, while
there are metering points that are
consolidated, there are also new connections.
This is true not only with the generators but
also with load customers and distributors. Thus,
NGCP does not foresee any significant
reduction in the metering facilities.
Inquired for clarification on the installation of
revenue meters to substation metering
facilities. Does this mean replacement of all the
statistical meters to revenue class meters?
What is the primary purpose of replacing the
statistical meters? Revenue meters are more
expensive.
The cost of the new statistical meters and those
of the revenue meters, which we have
installed, does not have much difference. The
primary purpose is to satisfy the management
directive that we have to meter our own
consumption. Eventually, that will be used as
basis for our payment of our substation energy
consumption.
Is it part of the direction for this upgrade of the
metering system in the grid to be able to
aggregate the demands of your customers?
NGCP upgrade their meters to load profile
capable meters for aggregation of demand for
coincident addition. It allows more flexibility in
terms of computing the total demand of the
customers.
SOCOTECO I What does NGCP consider in their CAPEX
budget, the cost of the relocation or the cost of
new facility?
The cost of relocation/totalization is
approximately the same as the cost of new
metering facility since New metering assets will
have to be installed at the new connection
point. The metering assets installed at existing
Metering Point/s will be retired and will be
included in the spares inventory.
We will not be transferring the metering assets
2011 Transmission Development Plan Public Consultation Report
21
installed at the existing Metering Points to the
new connection point, instead we will be
installing new metering assets.
Mactan Electric
Company
With regard to the rates passed on to the
consumers, we are asking NGCP to observe
prudency in doing its capital expenditure
programming. Are the meters, you are
installing to measure your own consumption,
the same with your load customers?
NGCP is required to pay for its own substation
usage that is why it installs its own meters.
These meters satisfy the basic requirement for
accuracy, functionality and basic costing and
are much less than the main meters. On
prudency, NGCP is a regulated entity and only
implements ERC approved projects that have
gone through prudency test. The age and the
condition of the assets are considered in the
capital expenditure planning.
Mactan Electric
Company
During testing of our equipment like our
metering services, we should not be paying for
the rental of NGCP equipments because we are
charged for its acquisition on your CAPEX.
These technical services are not considered in
the normal operation of NGCP, they are add-on
service provision. When NGCP projects its
operation and maintenance cost it only
considers the regular manpower cost for the
transmission services. However, these charges
are currently under review. NGCP understands
and recognizes your concern.
TransCo Does NGCP report the income from these
technical services?
Yes.
NPC has this customer within our service area
that has an expired TSC that is currently
applying to us. How will this affect our
metering arrangement? Can we assume the
metering of TSC?
At this stage, NGCP does not have plans of
selling the metering assets as yet. NGCP
suggests that the DU install their own meter for
the customer that they will assume or continue
paying NGCP for the metering services
provided.
San Roque Power Does NGCP still do the metering for IPPs which NGCP will take care only of its WESM meters.
2011 Transmission Development Plan Public Consultation Report
22
Corp. have ECA and PPA meters with NPC? There is currently an ongoing discussion
between NGCP and NPC for the former to
divest itself of that task. NGCP, however, can
offer that service if there will be a commercial
agreement binding them and NPC, the IPP and
IPPA.
16 3rd Regulatory
Period
TransCo Why is it that there were modified new projects
that are not included during the 3rd regulatory
application? What are the factors that have
resulted in such?
NGCP took into consideration the following
factors/challenges during the planning period:
a) change of the timeline of the incoming
generators; b) change on new technology; and,
c) changes in system conditions, thus, it is
difficult to foresee which projects should be
filed at once.
TransCo We believe that this planning criterion were
also NGCP’s consideration during the third
regulatory application, how come they were
not considered in the application.
The criteria are the same. However, the
projects that were filed in the 3rd Regulatory
Period had to be prioritized taking into
consideration, among other factors, the impact
on transmission tariff. Thus, not all projects
that were identified following the criteria were
included in the ERC filing.
TransCo Does it mean there will be reprioritization of
projects in the third regulatory?
No, NGCP is committed to implement all the
ERC-approved projects and file new projects
that need to be implemented within the 3rd
Regulatory Period.
TransCo Are the infrastructure projects that you are
mentioning already part of the approved CAPEX
for the 3rd Regulatory Period?
Yes. Actually the infrastructures are part of the
3rd Regulatory, but the issue is NGCP has to
prioritize based on the budget.
It should be noted that relative to the 3rd
Regulatory budget cap, issues such as the need
to address RE connections and Smart Grid
standards, although part of the TDP, may not
be fully addressed.
2011 Transmission Development Plan Public Consultation Report
23
TransCo Do RE-associated projects already part of the
3rd Reg projects?
For the Third Regulatory period, there is no
transmission line reinforcement project that
can be directly associated with RE.
17 Reliability MERALCO There were complaints to GMC regarding
reliability of 69 kv lines, what are the actions of
NGCP on these?
Those reverted to NGCP’s RAB are being
maintained and rehabilitated by NGCP.
18 Leyte-Mindanao
Interconnection
Project
DOE The Secretary noted that the forecast drought
in Mindanao will further highlight the need for
LMIP. Based on the report of Manila
Observatory on the model used to predict the
rainfall pattern, Mindanao will continue to
experience drought in the coming years. To
worsen the problem, siltation is also being
encountered in Pulangi Hydro Plant. For this
reason, DOE has been encouraging investors to
put up non-hydro power plants in Mindanao.
19 Batangas-
Mindoro
Interconnection
Project (BMIP)
DOE DOE is looking forward to this project as it will
support the plan of NPC to fully interconnect
the 69 kV Mindoro Grid.
NGCP clarified that the BMIP does not include
the reinforcement/expansion of the existing
Mindoro transmission backbone.
Palawan, being a potential growth area, can
also be considered in future interconnection
projects.
20
Planning
considerations
DOE The Secretary agreed that generators should be
located, as much as possible, near the load
center (within the island grid) to avoid the
uprating/expansion of existing submarine
interconnection between the islands.
DOE The Secretary inquired on heavily-loaded
corridors and substations in Metro Manila and
Among the substations that continue to exhibit
significant growth are Dasmarinas and Las
2011 Transmission Development Plan Public Consultation Report
24
if the necessary expansions are included in the
plan.
Piñas, both of which have been allocated with
additional transformers.
DOE Adequate transmission facilities must be
ensured for new growth areas such as Clark
Economic Zone, where the newly-developed
international airport will be expanded, the
former U.S Naval Station in Sangley Point
(Cavite), and Panay.
NGCP will consider in the next TDP the demand
forecast in these areas. The Secretary assured
NGCP that DOE will provide updates and
information on potential economic growth
areas.
San Miguel
Corporation
Suggested NGCP to review the 2011 TDP. NGCP
should retain investments in the major loop or
to what are necessary for the improvement of
the grid.
NGCP, guided by the Grid Code, wants to invest
where the need arises. There is already a
resolution where assets are discussed and the
boundaries are defined.
TransCo NGCP needs to come up with a cut-off date for
the receiving of data from DOE. Preferred
timeline is end of first quarter. What level of
forecast do NGCP obtains from DOE?
DOE releases a grid level forecast. This is
validated by NGCP from submission of
application of new generators. NGCP’s forecast
is on the substation level.
GMC Define ideal location for power plants. When we say ideal, it implies that these
locations require minimal transmission
reinforcements only. Further, these refer to the
ideal connection points to proponents, where
they can readily connect without waiting for
any grid expansion or reinforcement.
Conal Holdings
Corporation
There may be some capacities coming in that
could overkill the Mindanao capacities. In your
presentation of the Vol. I (Major Network
Development) for Mindanao, I didn’t see the
100 MW San Ramon coal power project which
will come in by 2016.
The main reason why some capacities that are
coming in may not be included in NGCP’s
assumptions is because they are not included in
the PDP of the DOE.
Aboitiz Power
Hedcor
We want to ask for NGCP’s inputs on how our
on line projects, the expansion of the Sibulan
project and the Sitasimon project, can connect
For the Sibulan, since it is only an expansion,
we can look at the existing connection points.
For the Sitasimon, on the other hand, kindly
2011 Transmission Development Plan Public Consultation Report
25
to your lines. These are already in our
engineering board.
approach one of NGCP’s account officers.
NGCP has not received any formal application
from Hedcor in regards to the proposed
project. NGCP needs to evaluate the proposed
connection schemes to identify the nearest
connection points for the proposed power
plant before conducting the grid impact
studies.
Davao Light and
Power Company
Projects are stemmed from forecasts. What do
NGCP consider the actual or the reliable
capacity of the generating plants?
From a planning perspective, it would be better
for NGCP to consider the maximum capacity of
the power plants rather than the derated
capacity.
21 Request for
Information
DOE The Secretary instructed NGCP to identify its
transmission facilities that are located along
major waterways and report them immediately
to the DOE. The government is clearing all
major waterways of obstructions as part of its
flood control measures.
NGCP will identify the said transmission
facilities and will provide the list to DOE.
TransCo Requested NGCP to provide TransCo with the
list of transmission lines which are beyond 50
years and the NGCP’s assessment and plans on
the said old transmission lines and the list of
other equipment’s age in comparison to the
approved ERC life span on a per substation
basis?
NGCP will provide the list requested.
It is notable that NGCP has an ongoing program
to replace parts of the lines which had been the
cause of many forced outages. For example,
per statistics, the major cause of tripping of
many of these lines is due to insulator failures.
NGCP has programmed the replacement of
substantial number of insulators, with the lines
that have more number of trippings and most
critical ones given priority. This is premised on
2011 Transmission Development Plan Public Consultation Report
26
the condition that shutdown of the lines can be
allowed by the System Operator on an
extended period. During the implementation of
the replacement program, other line hardwares
which are found to be defective will also be
replaced.
Furthermore, wood poles are gradually being
replaced with steel poles or with more reliable
structures such as steel towers, wherever more
suitable or appropriate.
TransCo Requested NGCP to provide them the present
list of transmission lines for the 3200+ MW of
indicative projects.
NGCP can provide the said list.
TransCo Requested NGCP to provide the list of new and
old names of substations.
NGCP can provide the said list.
TransCo Requested NGCP to provide the inter-island
power flow in different scenarios from 2014
onwards for the Negros-Panay-Cebu project.
NGCP to provide the info needed.
TransCo Do you have a periodic asset condition report
that includes what are the conditions of the
asset from commissioning, the supplier, the
basic specifications, significant events that
occurred with these assets to support your
CAPEX programs? Are they available as
reference to NGCP’s observance of CAPEX?
NGCP has this information on various internal
memoranda. NGCP will have to establish this
data so that they can be requested to produce
the report. Every commissioning,
troubleshooting, repair and replacement
should be recorded as to reflect the history of
the equipment. Aside from economic life, NGCP
also considers the condition of the equipment,
the obsolescence and the availability of spares
in replacing the said equipments. Presently the
condition of every asset is being monitored and
the historical records are kept by the
Maintenance and Test Division (MTD) and
district offices that are in-charge of these
2011 Transmission Development Plan Public Consultation Report
27
assets.
Recently NGCP has launched the Enterprise
Resource Planning (ERP) and one of the system
that could collate and summarize asset
condition is the Enterprise Asset Management
System.
Aboitiz Power
Hedcor
There are two drivers for your CAPEX budget
for O&M: the frequency of outages and aging
of equipment. Requested for historical data of
outages of equipment and NGCP’s driver for
aging equipment.
NGCP is more concerned of aging facilities
because most of the outages stemmed from
old transmission facilities. NGCP will provide
the data requested.
MERALCO Any update on the ICCP data requested by
MERALCO?
NGCP already replied to the request of
MERALCO, although, there were some data
that were not provided due to their
confidentiality.
Cebu Energy May we ask for a timeline for the Calung-
Calung-Naga reinforcement and the Naga-Quiot
project?
The Calung-Calung-Toledo-Colon project has
been awarded to the winning bidder in August
2012 with an estimated completion date of July
2013. The Colon-Cebu project started last
December and expected to be finished in the
1st quarter of 2013.
CEPALCO Suggested early weekly advisory from NGCP to
customers so they can also disseminate info
before interruption or outages occur.
There is already a proposal to harness the local
media. The said proposal, which is still subject
to the approval, suggests a 2-3 minute airing of
the affected areas during outages or
interruptions.
22 Asset
Management
San Miguel
Corporation
Assets are found to be poor in quality because
of selection of poor brands and absence of a
program that defines the assets’ standards.
NGCP has already started a standardization
program for purchasing of equipment. There is
a process that defines the list of accredited
2011 Transmission Development Plan Public Consultation Report
28
suppliers.
23 Duties and
Responsibilities
Identification
TransCo How do we divide SO responsibility when it
comes to protection and when it comes to
O&M?
SO is the one preparing the philosophy and also
the technical requirement and it is the O&M
that will implement the replacement.
TransCo The entire hardwires relay, corresponding CT
PT and others will be thru whom?
It will now be the responsibility of O&M.
TransCo The calculation and the setting will be done by
whom?
It will now be the responsibility of SO.
TransCo Are you going towards the direction wherein
the SO will calculate and prepare the setting
and O&M to buy all the relays and set the
relay?
From now on, the responsibility of the
equipment will be transferred to O&M. The
owner of the substation will be O&M.
24 Submarine Cable
TransCo Was there an ERC policy on submarine cable? To date, ERC has not issued a policy yet. In the
December 5 meeting with Sec. Almendras, the
Secretary agreed that generators should be
located, as much as possible, near the load
center (within the island grid) to avoid the
uprating of existing submarine interconnection
between the islands.
TransCo We need policy on treatment of submarine
cable.
Either ERC or DOE will issue such policy.
25 Substation
Naming
Convention
TransCo What is the reason for renaming some of the
substations? Do we really need to do that?
We are basing it on the standard equipment
identification as provided in the Grid Code.
26 Market Operation TransCo For interfacing in the market, shouldn’t it be
the market operator to spend for the interface?
Any expense related to market operation
should be shouldered by the market operator
because they are collecting market fees from
the participants.
Yes, but the system is designed more on data
collection/data forwarding concern. It is more
on the data interface, not on the hardware
itself.
27 Ancillary Services TransCo In as much as ancillary services are part of pass Ancillary Services compliance is monitored
2011 Transmission Development Plan Public Consultation Report
29
thru billing to consumers, is NGCP monitoring
compliance of providers to such. Why is it not
included in your submission? What is submitted
is just the nomination.
through Dispatch Instruction response and
through RTU. Monitoring device (RTU) is a pre-
requisite of AS scheduling to ensure
compliance. Upon non-compliance of AS
provider at a certain interval, scheduled
capacity is not paid. This can be verified every
billing period.
28 Sub transmission
Assets
DECORP When the RSTAs were reverted back to
transmission lines that means they will fall part
of the mark. Does this mean even those utilities
who bought their 69 kV sub transmission lines
will be paying the revenue requirements for
these RSTAs?
Based on the recent resolutions of ERC, RSTAs
are now part of the transmission system. NGCP,
being the agency in-charge of the maintenance
and operation of the grid, will have to treat
these RSTAs as transmission assets.
29 Tariff CEPALCO Does NGCP plan on instituting a point-to-point
determination of tariff than the postage stamp
system for the transmission grid? It’s going to
be unfair if NGCP will grant preferential tariff to
CASURECO.
NGCP only provides network service, so it is still
a postage stamp methodology. We have
received CASURECO’s request for the cost of a
specific transmission service for a point
connected to the plant of Agus. NGCP is not
encouraging any design of special rates.
2011 Transmission Development Plan Public Consultation Report
30
Table 3 Luzon Grid Issues
Issues Concerned
Party
Comments NGCP Response
1 New Growth Areas DOE The Secretary inquired on heavily-loaded
corridors and substations in Metro Manila
and if the necessary expansions are included
in the plan.
Among the substations that continue to exhibit
significant growth are Dasmarinas and Las Piñas, both
of which have been allocated with additional
transformers.
DOE Adequate transmission facilities must be
ensured for new growth areas such as Clark
Economic Zone, where the newly-developed
international airport will be expanded, the
former U.S Naval Station in Sangley Point
(Cavite), and Panay.
NGCP will consider in the next TDP the demand
forecast in these areas. The Secretary assured NGCP
that DOE will provide updates and information on
potential economic growth areas.
It is challenging to develop new 69kV
substation in South Mexico because there’s a
difficulty in locating a feasible space for the
proposed plant. Can NGCP perhaps consider
another substation between Concepcion and
Mexico to take care of growth in Clark for us
to be able to tap in 230kV line in the next 10
years?
It is a good thing that the TDP is updated annually.
NGCP recognizes the needs in Mexico and already had
internal discussions to address these needs. NGCP will
make sure that in the 2012 TDP, the needs of Clark
will be considered in the expansion plans.
2 San Gabriel 500 MV
Project
TransCo So San Gabriel 500MW is a confirmed
project. When is the target initial
synchronization? Do you have a timeline for
their activities?
NGCP refers to the year when the power plant is
expected to be online as its reference in pursuing any
associated transmission project.
3 Ambuklao Substation
TransCo Is there still a need to uprate in as much as
the existing 795 conductor could still
accommodate the 105 projected generation
of Ambuklao? Is the line that very old?
Yes. One of the circuits is constructed in 1950s and
the main consideration is Magat Hydro expansion.
2011 Transmission Development Plan Public Consultation Report
31
TransCo What is the relationship of Magat expansion
project to this one?
Project was developed for the Ambuklao repowering
and Magat expansion.
4 San Jose S/S’s
TransCo On the NGCP’s plan to put up a fifth (5th)
bank transformer in San Jose SS, may we be
clarified why there is a need for N-2 in this
SS? Is this really necessary? Won’t the 5th
bank purpose would just be for aesthetic in
as much as the four banks in existence can
accommodate the N-1 requirement?
If you intend to transfer that later to the new
Antipolo cut in why the need to procure it in
advance? We will just spending additional for
the hauling, dismantling, hauling and
assembling plus all the tests in the new
Antipolo cut in?
Would it not be more practical to have the
supposed “5th” bank at San Jose be part of
the new Antipolo cut in at the 4th regulatory
as NGCP had envisioned?
This has been substantially discussed before in the
meeting/s with DOE and TRANSCO. A report on this is
being finalized to reflect NGCP’s final position on the
issue and which will form part of NGCP’s submissions
to the ERC when it files the project for Provisional
Approval.
MERALCO Recommended to convert from ring bus to
breaker and a half scheme.
NGCP is considering the recommendation, however, a
shutdown is difficult to schedule. Upon the
development of Antipolo Substation the
reconfiguration can be implemented.
5 Antipolo S/S
TransCo On the proposed Antipolo SS, can you
enlighten us on the reasons/logic of the
proposal and what are benefits of this?
This is discussed in Section 5.2.1.6 of the 2011 TDP
Consultation Draft.
6 C-6 Circumferential
Road Development
DOE Kindly consider the C-6 route for the
development of the 500 kV transmission
backbone.
As suggested, NGCP will consider the C-6 route in
developing the 500 KV transmission backbone to
strengthen the network serving Metro Manila and the
2011 Transmission Development Plan Public Consultation Report
32
suburbs. NGCP will coordinate with DPWH/MMDA
and will also study a proposed third option for the
backbone, i.e., along the Laguna De Bay.
7 GNPower Associated
Lines
DOE DOE asked for any updates regarding the
project.
NGCP is encountering delays in the implementation of
associated transmission lines for Mariveles Coal-fired
Power Plant (GNPower). As a measure, the
contingency line will be in place before the end of
2011.
8 Araneta-Sucat 230
kV Line
TransCo There is a SC decision to decommission
Araneta-Sucat 230kV line. How did you
address this in your TDP?
No capex was proposed for the Third Regulatory
Period for the re-routing of the Sucat-Araneta line
because it is unfair for the consumers to be paying in
advance the cost of the project when there is no final
decision yet on the issue.
9 System operations
Aboitiz Power There’s a limitation in the Makban- Kalayaan
line every time it runs out of supply during
summer season.
NGCP will look into this.
10 San Jose-Angat Line
MERALCO There are 3 directly-connected customers
(DCC) in the area, upon acquisition of
TransCo facilities by MERALCO only the 3
DCC will not become customers of
MERALCO. Would NGCP allow MERALCO to
build lines in the area to supply the 3 DCC?
The capacity of the ERC-approved San Jose-Angat Line
Project of NGCP is designed to replace the three
existing old circuits. Thus, building additional lines is
no longer necessary but a switching station only to be
constructed along the new San Jose-Angat Line and
this will serve as the connection point of the 3 DCC.
11 Transmission loop
project in northern
Luzon
Hedcor Aboitiz Are there new plans in Mt. Province, from La
Trinidad to MOPRECO? We are planning to
connect on the 69 kV single circuit line in
there.
NGCP already included this on its 2012 activities.
12 La Trinidad-Calot 69
kV transmission line
Hedcor Aboitiz There are seven power plants connected in
the said line. This is a single circuit line which
makes it unreliable and declared as a
transmission asset by the ERC.
ERC clarified this line as transmission asset.NGCP
needs ERC approval prior to implement the
rehabilitation/expansion of the said line.
2011 Transmission Development Plan Public Consultation Report
33
13 New Ambuklao and
Binga transmission
lines
SN Aboitiz
Power Benguet
What is the timeline in upgrading these
lines?
NGCP concentrates on area where there is a lot of
trippings. We conduct refurbishment of the whole line
(comprehensive maintenance).
14 Calamba S/S MERALCO What is the connection scheme being
planned by NGCP?
Initially cut-in, eventually bus-in scheme. Although the
approved budget is only for radial connection.
MERALCO What is the timeline of the project? Earliest is January 2012.
MERALCO If radially connected, will NGCP charge
MERALCO or divest the line?
As per Resolution 16, it’s a connection asset.
15 RP Energy Project
MERALCO Clarification why the line in the presentation
is only 49 Km.
The total length of the line is 57 Km, 49 Km + 8Km line
to Hanjin.
MERALCO Will the NGCP Mancom already decide on
the connection scheme for Hanjin
Substation?
We hope it can be decided soon.
2011 Transmission Development Plan Public Consultation Report
34
Table 4 Mindanao Grid Issues
Issues Concerned
Party
Comments NGCP Response
1 N-1 Issues
FIBECO Main concern is the power outage we
experience every time power outage or
interruption occurs in Maramag or Kibawe
lines. In planning, have you considered a
substation project along Tagoloan and
Maramag?
NGCP has not received any information yet with regard
to the proposed substation between Tagoloan and
Maramag. The proponent is advised to submit a
proposal to NGCP for evaluation.
2 Agus-Kibawe Line 2
Project
TransCo What is your long term plan for the Agus-
Kibawe Line 2? With the new 230kV, does
NGCP intend to continue repairing it?
NGCP will continue to repair it. But once we have the
backbone which is located in a safe area, it is easy to
secure the new backbone system.
TransCo What is the status of the project? The Agus-Kibawe Line 2 project is already energized.
3 Growth Rate GMC We’re surprised with the growth rate of
Mindanao (5,320 MW) against that of Visayas.
Is this 5,320 MW an annual average growth?
Yes, that is the annual average growth rate.
4 Bunawan Project Davao Light
and Power
Company
Inquired for any updates on DLPC’s Bunawan
project application.
NGCP to check the status of the said application.
5 Rizal S/S Conal
Holdings
Corporation
The basis of this project is to support
Tampakan, what if Tampakan won’t push
through?
The project may not also push through. It will be up to
ERC to approve the proposed project. The regulator is
adopting a wait-and-see approach when it comes to
transmission projects that are associated with new
power plants.
6 Transmission Loss Is NGCP considering recomputing the
transmission loss of Mindanao?
NGCP on a monthly basis does compute the
transmission losses. Nothing bars NGCP from filing with
or informing ERC. NGCP provides regular updates on
this to GMC. NGCP is still waiting on what will ERC say
on the information that we’re giving to GMC every
month.
7 Transmission Line Aboitiz Is the scheme for the associated transmission NGCP has an ongoing GIS for this and NGCP has
2011 Transmission Development Plan Public Consultation Report
35
line for the coal power project in Davao
already finalized?
requested additional information to proceed with the
grid impact study.
2011 Transmission Development Plan Public Consultation Report
36
Table 5 Visayas Grid Issues
Issues Concerned
Party
Comments NGCP Response
1 Generation Capacity
Addition
TransCo May we know the load of Panay-Negros-Cebu
and the incoming of plant in Panay? So that
we can fully appreciate the recommended
projects.
Actually, it is already included in the 2011 TDP report.
Based on NGCP’s assessment, the load in Panay is lower
as compared to the total capacity additions in Panay.
Eventually, there will be an excess power that will be
exported to Negros and then to Cebu.
Will there be a third line for the Panay-Negros
submarine connection to accommodate the
proposed 420 MW power plant in Panay?
NGCP has two options to accommodate the proposed
420 MW power plant in Panay. First is 230 kV
transmission line backbone which can accommodate
the full capacity, and the second option is the second
circuit of the 138 kV line. NGCP recognizes that the
second 138 kV line cannot accommodate the full
capacity but due to the high cost of 230 kV line, NGCP is
leaning towards the second 138 kV line. NGCP then will
monitor the status of the incoming power plants and
propose a third line to accommodate the other
incoming power plants should it be needed. Ideally
power plants should be constructed near load centers
to minimize the reinforcement of the transmission
lines.
TransAsia
Renewable
Guimaras
Is 54 MW Wind Farm project in Guimaras
included in your transmission plans?
During the Third Regulatory reset application with the
ERC, there is no complete information yet on the 54
MW wind capacity, the reason why the transmission
reinforcement is not included in the 3rd Regulatory
application.
2 Bohol Backbone
Transmission Project
DOE DOE inquired for any updates on the project. The project is expected to be completed in July 2012.
The new 138 KV Substation located near Tagbilaran
City, a component of the project, will improve the
reliability of power supply in Panglao Island - a major
2011 Transmission Development Plan Public Consultation Report
37
tourist destination.
3 Transmission Line
San Miguel
Corporation
Raised their concern regarding the
proliferation of 138 kV transmission voltages
in Visayas because accordingly 138 kV is just
for short lines. Suggests pursuing plans of
stringing 230 kV lines in Cebu-Negros-Panay
for a more stable interconnection.
NGCP is technically in favor of a 230 kV backbone to
increase reliability, security and accommodate the
sharing of generation in Cebu-Negros-Panay. But
looking at the cost of building 230 kV transmission
lines, it is very expensive and NGCP has to balance
technical and economic considerations including
optimization of the transmission assets for a period of
10 to 15 years.
San Miguel
Corporation
Suggests to extend 230 kV lines further down
Cebu and then transform it directly to 69 kV
for the use of utilities and other directly
connected consumers rather than
transforming to 138 kV and then to 69 kV, to
avoid double transformation losses.
For voltage problems, there is the option of using
reactive compensation which may be cheaper than
outright implementation of higher transmission
voltage. Upgrading to higher voltage level needs
extensive study.
4 Negros-Panay
Interconnection
Project
TransCo What’s the justification of the Negros-Panay
interconnection project. The reasoning stated
in the TDP 2011, which is voltage regulation, is
quite misleading.
Project is developed to accommodate increased power
flow to Panay because of the entry of new power
plants. Voltage regulation is the secondary reason.
Aklan Electric
Cooperative
According to your presentation, the uprating
of the Negros-Panay interconnection is based
on the entry of new power plants. Did you also
consider the present congestion affecting the
distribution utilities in Panay, because when a
power plant shutdowns we are forced to
implement Manual Load Dropping? Can you
implement the uprating project earlier?
NGCP reiterates the main reason for the project is the
entry of the new power plants as it affects the
proposed capacity of the Negros-Panay interconnection
and the worst case scenario in terms of determining
the need to uprate the Negros-Panay link. NGCP also
recognizes that this project is also very critical to the
DUs in Panay. NGCP has been receiving request to
implement the project as early as last year.
NOCECO Regarding the proposed PhP 36 Billion, 230 kV
line from Cebu to Negros to export the excess
NGCP recognizes that sometimes the transmission
solution may not be the cheapest one and a generation
2011 Transmission Development Plan Public Consultation Report
38
capacity in Panay. What if a 200MW power
plant in Negros is constructed, what will be its
significant effect on that line? Would it not be
cheaper just to construct a power plant in
Negros?
solution will be better. The key here is to coordinate
with DOE which oversees the generation projects. For
NGCP, if there will be no other solution it will be forced
to implement the project.
5 Colon-Cebu 138 kV
T/L
Global
Business
Power
Corporation
We are monitoring the progress of the on-
going projects, like the Cebu-Colon
transmission line. Can we have an updated
timeline of these projects?
NGCP provided the status of these on-going projects
during the meeting.
6 Reliability
Orica Nitrates Aside from the 50 MVA additional
transformers on the Amlan Substation, Do you
have any developments on the 69 kV
transmission line from Amlan to Dumaguete?
We are patronizing the 69 kV line but we are
having some problems on the voltage input in
our plant, it seems that the 69 kV line is
overloaded. Can we ask for a timeline on
when the developments are going to be
implemented?
NGCP proposed an additional transformer in Amlan
Substation because the existing 50 MVA transformer
may not be sufficient. The 69 kV transmission line has
the same capacity so it follows that it may not be
sufficient in the near future. But as to the 69 kV
transmission line, a subtransmission asset undergoing
divestment, NGCP will have to coordinate with the
concerned distribution utility (DU) because they have
the responsibility and the first say on upgrading the
line. NGCP can also upgrade the line but will have to
recover the investments through subtransmission
charges. It’s better to set a meeting with the concerned
DU to determine what the recommended action plan is,
on whether or not NGCP will implement the project.
7 Cebu-Mandaue-
Lapu-lapu T/L
VECO In the Cebu-Mandaue-LapuLapu transmission
line and substation project your estimated
time of completion is 2015. Can you
reconsider the timeframe because LapuLapu is
now at 125 MVA with 7% increase per annum?
By 2015, the current transformers will be
loaded at 95%.
As much as NGCP wants to accelerate the project, it is
aware of the difficulty in implementation because the
area is heavily populated and the proposed project is
an underground cable which can cause obstruction
during construction. NGCP will be coordinating with the
concerned agencies like the DPWH and investigate the
capacity of the bridge if it can carry the additional
cables or if it needs to consider another option. NGCP is
also implementing other projects in order to address
the additional load in Mandaue and Mactan.
2011 Transmission Development Plan Public Consultation Report
39
8 O&M
Southern
Leyte Electric
Cooperative
Your immediate answer on how to resolve the
issue on implementing maintenance works on
the Ormoc-Maasin 138kV line and Maasin-
Bontoc 69 kV line without getting the whole of
our coverage area (Maasin-Bontoc-
Himayangan 69 kV substations) interrupted.
Can you give us a timeline for the upgrading of
the Babatngon substation because it is our
alternative line aside from our main supply in
Maasin substation?
NGCP has two proposed projects that will address your
concerns: First, on the maintenance works on Ormoc-
Maasin, is the second circuit stringing of the 138 kV line
from Ormoc to Maasin substations and the second is
the additional transformer in Babatngon which is your
alternative supply. However, the single circuit 69 kV
line in Babatngon is already divested to Leyeco II which
has the same capacity as the existing 1-50 MVA
Babatngon substation. So if you shift your load to
Babatngon the constraint on your load will be on the 69
kV transmission line even though NGCP has already
upgraded the transformers in Babatngon. You may
have to coordinate with Leyeco II.
9 138 kV Looping of
Panay
When do you expect to finish the loop
transmission line of Panay?
The project in Panay that will loop the island is the
Southern Panay 138 kV Backbone Transmission and the
Culasi-San Jose 69 kV Transmission line. The Southern
Panay (Sta. Barbara-San Jose) is an on-going project
with a target date of completion on the 4th quarter of
2012. Culasi-San Jose is in its pre-construction stage
and the contract will be awarded in July 2012 and
target date of completion is October 2013.
10 2nd Cebu-Negros 138
kV Line
May we ask for a clarification regarding the
submarine cable that is supposed to connect
additional capacity to Panay? Why is it that
230 kV is presented to ERC when the existing
submarine cable is only 138 kV? Is it possible
to construct it at 138 kV rather than 230 kV?
What was proposed to ERC in 2005 for the Negros-
Panay second circuit is a 138 kV line. What NGCP is
presenting in the public consultations is an option for a
230 kV backbone and another option for the 2nd circuit
138 kV line. A 230 kV line is proposed to significantly
reduce the length of the backbone, from north Cebu to
cross directly to Negros and because there is a plan to
construct a 200 MW power plant in Panay. However,
the cost estimate is about PhP 36 billion. The 230 kV
Cebu-Negros is just an option. At this point, NGCP is
2011 Transmission Development Plan Public Consultation Report
40
leaning towards the 138 kV option.
11 Ancillary Services
NOCECO The provision and acquisition of ancillary
services in the Visayas to prevent manual load
dropping during day peak and night peak and
once a plant or a line is out.
NGCP is currently looking for ancillary service provider
in Visayas. Right now the remaining power plants of
NAPOCOR and the geothermal power plant in
Palinpinon are the only ancillary service providers.
NGCP is asking the power plants to provide ancillary
services, but according to them they don’t have enough
capacity. Last March 2011 NGCP went out and publish
in the newspaper to ask for ancillary services provider
in the Visayas and Mindanao and it is going to publish
again.
12 Catbalogan-Calbayog
69 kV T/L
SAMELCO II Is the Catbalogan-Calbayog 69 kV line being
decommissioned after the energization of the
Calbayog 138 kV line?
That was the original plan, to decommission the 69 kV
Catbalogan-Calbayog, but we are not pushing through
with it.