contech systems finalstrand

Upload: turoy

Post on 08-Mar-2016

224 views

Category:

Documents


0 download

DESCRIPTION

Contech Systems FINALStrand

TRANSCRIPT

  • S t r a n d A n c h o r s

  • Con-Tech Systems Ltd. was founded in 1985 and is a family owned company. Since incep-tion our primary focus in the initial stages was manufacturing post-tensioned Strand Anchors for geo-technical construction. Since that time, not only have we remained close to our roots with our innovative Strand prod-ucts, but we have also devel-oped and promoted many other unique and innovative products to allow our customers to com-plete many difficult projects.

    Con-Tech has completed strand projects as small as one anchor to projects containing thousands of anchors. We have completed projects with anchors as small as one strand, to ninety-two strands; still the largest anchor ever manufactured in the world. With these wide selections of products still available to our customers today we are abe to service not only large interna-

    tional contractors but also small owner operators. We have the ability to produce anchors with standard corrosion protection systems and are also able to adapt to special project corro-sion requirements as needed. Through our several production plants and offices located across Canada and the USA; from B.C. to Ontario, from Washington State, to North Carolina and Florida, we are able to service any of your project needs.

    ... page 2 ... page 3

    S t r a n d A n c h o r s S t r a n d A n c h o r s

    Contents: CTS Strand Anchors:

    Company Introduction:

    Advantages of CTS Strand Anchors:

    CoverCompany Profile...................................... Page 2Strand Anchor Introduction..................... Page 3Our Committment................................... Page 4Corrosion Protection Tree....................... Page 5Corrosion Protection Classification.... ..... Page 6Anchor Details......................................... Page 7Technical Data......................................... Page 8Technical Data......................................... Page 9Anchor Head Technical Data................... Page 10Hollow Ram Jacks................................... Page 11Accessories............................................. Page 12Accessories............................................. Page 13Strand Anchor Off-Coilers....................... Page 14Applications............................................ Page 15Back Cover: Contact Information

    Recognised as one of the strongest, most flexible and cost effective anchor systems in the industry, Strand Anchors are in use throughout North America. Our unique encapsulation process ensures that the Strands bond length is not contaminated with the grease from the free length. Strand Anchors are typically used for either permanent or temporary tie down and tie back anchors in either rock or soil. Examples include hydroelectric dams, wind tower foundations, slope stabilization and excavation shoring.

    Transportation of anchor tendons on reels coiled or looped. Therefore only small stor-age and assembly area are required.

    Cutting of length of anchors on job site pos-sible to suit local ground conditions.

    Installation of flexible anchor tendons un-der extremely tight space conditions.

    Less danger of contact with overhead pow-er lines, because anchors are not as rigid as bars.

    High yield point (1570 N/mm2 = 227 KSI) and low E-modulus of 20000 N/mm2 = 29000 KSI indicates that the strain of strand is greater than that for 150 KSI bars.

    With our strand anchors more than one tension element in each anchor guarantees higher safety versus single bar anchors.

    Our slim line strand coupler allows for easy splicing of even multiple strand anchors.

    Pacific Coastal Highway Retaining Wall, Gorda, CA

    The Dalles Dam, WA/OR

    The Dalles Dam, WA/OR

    92 Strand Anchors, Seven Mile Dam. To date worlds largest anchors! Greenwich Wind Farm, Ontario, Canada

  • S t r a n d A n c h o r s S t r a n d A n c h o r s

    ... page 4 ... page 5

    Our Committment: Corrosion Protection Tree:

    Con-Tech Systems Ltd. is committed to providing our customers with the best quality products and service. From the time an order is placed we have strict processes to ensure the customer gets not only what they need but also what they want. We have highly trained, professional staff who ensure that our anchors conform to the latest edition of the Post-Tensioning Institute Manual for Rock and Soil Anchors.

    Temporary(less than 2 years)

    Service Life

    Extended Temporary(2 to 5 years)

    Permanent

    Class I ProtectionAggressivityAggressivity

    AggressiveAggressive Non-Aggressive Non-Aggressive

    No ProtectionClass II Protection Class II ProtectionClass I Protection

  • PTI - Class IDouble Corrosion Protection

    PTI - Class II Single Corrosion Protection

    Temporary AnchorNo Corrosion Protection

    Cover Cap

    Wedge

    Wedge Plate

    Bearing Plate

    Trumpet

    Greased & Sheathed Strand in Unbonded Length

    Organizers along Bond Length

    Bare Strand in Bond Length

    Centralizer

    Unbonded Length

    Bond Length

    Wedge

    Wedge Plate

    Bearing Plate

    Greased & Sheathed Strand in Unbonded Length

    Organizers along Bond Length

    Bare Strand in Bond Length

    Centralizer

    Cover Cap

    Trumpet

    Corrugated Sheathing

    End Cap

    Bond Length

    Unbonded Length

    Bond Length

    Unbonded Length

    Wedge

    Wedge Plate

    Bearing Plate

    Organizers along Bond Length

    Bare Strand in Bond Length

    Centralizer

    Seal Seal Seal

    2-0

    Sh

    op

    Gro

    uted

    Internal Grout Tube

    PROTECTION REQUIREMENTS Class Anchorage Unbonded Tendon Bond Length Length

    PTI Class IEncapsulatedTendon

    Trumpet Grout or corrosion

    inhibiting com-pound filled, cover if exposed.

    Corrosion inhibiting compound filled sheath encased in grout, or

    Grout filled sheath, or Grout encased epoxy-coat-

    ed strand in a successfully water-pressure tested drill hole.

    No trumpet. Grease-filled sheath.

    Grout-filled encapsula-tion, or

    Epoxy coated strand tendon in a successfully water-pressure tested drill hole.

    No extra protection

    required.

    PTI Class II

    Temporary - up to 24 months

    Grout encasement. Corrosion inhibiting compound filled sheath encased in grout, or

    Grout filled sheath, or Grout encased fully or

    partially bonded tendon in sound rock or concrete.

    Trumpet Grout or corrosion

    inhibiting com-pound filled, cover if exposed.

    Optional-Greased & Sheathed Strand in Unbonded Length

    S t r a n d A n c h o r s S t r a n d A n c h o r s

    ... page 6 ... page 7

    Corrosion Protection Classification: Anchor Details:In the 2014 Recommendations for Prestressed Rock and Soil Anchors (this is the Fifth Edition and is endorsed by the ADSC Anchored Earth Retention Committee) the Post-Tensioning Institute defines three classes of Cor-rosion Protection:PTI Class I: Encapsulated Tendons (often referred to as double corrosion protected, DCP)PTI Class II: Grout Protected Tendons (often referred to as single corrosion protected, SCP)Temporary: Grout Protected (often referred to as single corrosion protected, SCP)

    PTI Class I PTI Class II Temporary

    TyPICAL APPLICATIONS:

  • NominalDiameter

    inch mm kips kN kips kN kips kN inch inch mm1 0.217 140 58.6 260.7 46.9 208.6 35.2 156.42 0.434 280 117.2 521.3 93.8 417.1 70.4 312.83 0.651 420 175.8 782.0 140.6 625.6 105.6 469.34 0.868 560 234.4 1042.7 187.5 834.1 140.8 625.75 1.085 700 293.0 1303.3 234.4 1042.7 176.0 782.16 1.302 840 351.6 1564.0 281.3 1251.2 211.2 938.57 1.519 980 410.2 1824.7 328.2 1459.7 246.4 1094.98 1.736 1120 468.8 2085.3 375.0 1668.3 281.6 1251.49 1.953 1260 527.4 2346.0 421.9 1876.8 316.8 1407.810 2.17 1400 586.0 2606.7 468.8 2085.3 352.0 1564.211 2.387 1540 644.6 2867.3 515.7 2293.9 387.2 1720.612 2.604 1680 703.2 3128.0 562.6 2502.4 422.4 1877.013 2.821 1820 761.8 3388.7 609.4 2710.9 457.6 2033.514 3.038 1960 820.4 3649.3 656.3 2919.5 492.8 2189.915 3.255 2100 879.0 3910.0 703.2 3128.0 528.0 2346.316 3.472 2240 937.6 4170.7 750.1 3336.5 563.2 2502.717 3.689 2380 996.2 4431.3 797.0 3545.1 598.4 2659.118 3.906 2520 1054.8 4692.0 843.8 3753.6 633.6 2815.619 4.123 2660 1113.4 4952.7 890.7 3962.1 668.8 2972.020 4.34 2800 1172.0 5213.3 937.6 4170.7 703.2 3128.021 4.557 2940 1230.6 5474.0 984.5 4379.2 738.4 3284.422 4.774 3080 1289.2 5735.4 1031.4 4588.3 773.5 3441.227 5.859 3780 1582.2 7038.9 1265.8 5631.1 949.3 4223.330 6.51 4200 1758.0 7821.0 1406.4 6256.8 1054.8 4692.631 6.727 4340 1816.6 8081.7 1453.3 6465.4 1090.0 4849.037 8.029 5180 2168.2 9645.9 1734.6 7716.7 1300.9 5787.547 10.199 6580 2754.2 12251.3 2203.4 9801.0 1654.4 7351.760 13.02 8400 3516.0 15640.0 2812.8 12512.0 2112.0 9385.2 10" 11.6 29592 19.964 12880 5391.2 23981.3 4313.0 19185.0 3238.4 14390.6 N/A N/A N/A

    2" 2.4 61

    Max Jacking Load (80% of GUTS)

    3" 3.6

    8" 9.5

    91

    241

    6" 7.1 180

    Strands

    5" 5.7 145

    4" 4.7 119

    HDPE Corrugated Sheathing

    Outside DiameterMax Design Load

    (60% of GUTS)Ulimate Load

    (fpu x APS) = GUTSX-Section Area

    (Aps)

    The drill hole size chosen should allow for a minimum grout cover over the corrugated sheath of 0.5 (12.7 mm).If our post-grout pressure lines are used, allow for a minimum of 1 (25.4 mm) grout cover on the side where the grout pipe is assembled.

    Our centralizers are made to allow for a minimum of 0.5 (12.7 mm) grout cover or to a specified size.They are available as single wing parts (a minimum of 3 wings is required per location) or as multiple wing elements.Our strand organizers are fabricated to provide the minimum strand spacing recommended in the PTI manual.

    CTS Rock and Soil Anchors meet the ASTM A-416 or ASTM A-488 (epoxy coated strand) specifications for 0.6, 7 wire strand.Ultimate stress (fpu) 270 ksi 1861.65 N/mm2

    Weight per strand 0.74 lbc./lf 1.10 kg/m

    They are in accordance to:Recommendations for Prestressed Rock and Soil Anchors, Post Tensioning Institute (PTI), latest edition.Ground Anchors and Anchored Systems, Geotechnical Engineering Circular No. 4, Federal Highway Administration, Washington DC, FHWA-IF-99-015, 1999

    S t r a n d A n c h o r s S t r a n d A n c h o r s

    ... page 8 ... page 9

    Strand Technical Data:

  • Stressing Jacks table: CTS offers a variety of Hollow-Ram Jacks for stressing Strand Anchors. Sizes range from 100 Ton to 2200 Ton+. Calibrated Kits for rent include Jacks, Hydraulic Power Packs, Guages and Hoses Please call us and allow us to assist you with your specific requirements.

    Hollow Ram Jacks:

    ModelNumber

    Usage(No. of Strands) Stroke

    Ram Area(inch2)

    Maximum Load

    @ 10,000 PSI

    CenterHole I.D.

    CylinderO.D.

    HeightCollapsed Material

    Weight(lbs.)

    CTS-CBJ-3 1 3.0 " 5.0 " 25 TONS 0.70 " 4.25 " 8.00 " ALUM 10CTS-25-8 1 8.0 " 5.0 " 25 TONS 0.70 " 4.50 " 13.00 " ALUM 20CTS-50 Titan 4.0 " 10.3 " 50 TONS 2.12 " 7.50 " 9.50 " ALUM 40

    CTS-100 4 6.0 " 21.0 " 100 TONS 2.00 " 7.00 " 12.50 " STEEL 90CTS-100 4 8.0 " 21.0 " 100 TONS 3.50 " 10.00 " 16.00 " ALUM 120CTS-120 5 6.5 " 24.3 " 120 TONS 3.50 " 9.50 " 14.00 " ALUM 80CTS-150 6 8.0 " 30.0 " 150 TONS 3.50 " 10.00 " 15.00 " ALUM 125CTS-150 6 10.0 " 29.5 " 150 TONS 3.50 " 12.00 " 19.00 " ALUM 225CTS-200 7 7.0 " 40.0 " 200 TONS 3.50 " 11.00 " 17.00 " STEEL 335CTS-200 7 9.5 " 40.0 " 200 TONS 3.50 " 12.00 " 19.00 " ALUM 200CTS-200 9 9.5 " 40.0 " 200 TONS 4.50 " 11.50 " 21.00 " STEEL 450CTS-300 12 18.0 " 60.0 " 300 TONS 5.25 " 14.00 " 27.50 " STEEL 875CTS-300 12 18.0 " 60.0 " 300 TONS 5.25 " 14.00 " 34.00 " STEEL 1,350CTS-500 15 14.0 " 110.0 " 500 TONS 8.00 " 20.00 " 27.50 " STEEL 1,830CTS-800 27 14.0 " 160.0 " 800 TONS 9.50 " 26.50 " 32.50 " STEEL 3,600

    CTS-2200 92 35.0 " 440.0 " 2,200 TONS 16.00 " 38.50 " 55.00 " STEEL 13,000

    Strands Diameter Thickness Bearing PlateThru HoleTrumpet Size

    Required (Min.)4 5" 2" 3-1/2" 3-1/2" SCH407 5-1/2" 2" 4" 4" SCH409 6-1/4" 2-5/8" 4-3/4" 5" SCH40

    12 7-1/2" 2-3/4" 5" 5" SCH4015 8-1/2" 3-1/2" 6" 6" SCH40

    Or HSS Equivalent

    Anchor Head Dimensions

    Any variation of custom sizes or machining such as external threading available upon request

    2200 Ton Hollow Ram Jack500 Ton Hollow Ram Jack

    Monostrand Jack

    Carbon Fiber light weight Jack

    S t r a n d A n c h o r s S t r a n d A n c h o r s

    ... page 10 ... page 11

    Anchor Head Technical Data: Hollow Ram Jack Details:

    9 Strand Anchor Head

    Anchor Head Side View

  • Grippers - Designed to be used with standard .600 7 wire strand anchor tendon. Variety of sizes are available.

    Cover Caps - Standard sizes stocked for 4, 7, 9, 12, and 15 strand anchor heads. Custom sizes are available.

    Post Grout Tubes - any required length can be accommodated thanks to our modular system.

    Couplers - designed to be used with standard 0.600 diameter, 7 wire anchor tendon.

    Bearing Plates - any size or configuration can be ac-commodated including addition of trumpets if needed.

    Centralizers - Various sizes and styles including balloon, snap ring, banana peel style, and heavy duty.

    Restrainer Plates - Standard restraining plates are kept in stock in the 4, 7, 9, 12, and 15 strand sizes however, any other size can be fabricated to match the required anchor.

    Adjustable Stressing Chairs - available in 4, 7, 9, 12 and 15 Strand sizes.

    Anchor Heads - Many standard sizes available as well as any custom anchor head if required.

    Organizers - Can be made to accommodate any size of anchor.

    S t r a n d A n c h o r s S t r a n d A n c h o r s

    ... page 12 ... page 13

    Accessories:Accessories:

  • ... page 14 ... page 15

    Strand Anchor Off-Coilers:

    Manually operated Horizontal Off-Coiler

    Con-Tech Systems Ltd. offers uncoiling equipment to facilitate the safe installation of our Strand Anchors. Manual Horizontal and Motorized Vertical Off-Coilers are available for a variety of applications.

    Motorized Vertical Off-Coiler

    Manually operated Horizontal Off-Coiler

    S t r a n d A n c h o r s S t r a n d A n c h o r s

    ... page 14 ... page 15

    Applications:

    Dam Retrofits Tom Miller Dam, Austin TX

    Excavation Shoring The Cosmopolitan, Las Vegas NV

    Bridges Bixby Creek Bridge, CA

    Retaining Walls US 27/SR 29 Hwy, Chatanooga, TN

    Foundations Greenwich Wind Farm, Ontario

    Landslide Mitigation The Point, San Diego, CA

  • Version: 2014

    Memberships:Partnerships:

    Website: www.contechsystems.com

    Head Office: Sales & Production: 8150 River Road, Delta, B.C. Canada V4G 1B5

    Tel: 604-946-5571Toll Free: 1-888-818-4826Email: [email protected]

    Eastern Locations:Sales & Production: Brockville, ON, Canada

    Tel: 613-342-0041 Charlotte, NC, USA

    Tel: 704-494-3989Sales: East Stroudsburg, PA, USA

    Tel: 613-342-0041 New Port Richey, FL, USA

    Tel: 727-842-5760Email: [email protected]

    Western Locations:Production Plant: Blaine, WA USA

    Toll Free: 1-888-818-4826Email: [email protected]

    Magnolia Point, Seattle WATie Back Anchors for mud slide repair. (In progress/completion)

    Seven Mile Dam, B.C.Seismic upgrade of the hydro power dam.

    CTS Tie Down Anchors with 92 Strands.