EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANORHL ARCHITECTS I ADG OKLAHOMA STATE CAPITOL RESTORATION Exterior Rehabilitation Contents Summary Safety Progress Photos Attachments Roofing Replacement Update 1 2 3 JANUARY 2019 15039DB MONTHLY CONSTRUCTION PROGRESS REPORT 4 5 STATE CAPITOL RESTOR TATE CAPITOL RESTOR TATE CAPITOL RESTO

Upload: others

Post on 03-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

Summary

Contents

Key Activities

Scope Development

Schedule

Progress Photos

12345

EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANOR ARCHITECTS I ADG

JULY 2016

OKLAHOMA STATE CAPITOL RESTORATION

Exterior Rehabilitation

EXTERIOR DESIGN BUILD TEAM I JE DUNN I TREANORHL ARCHITECTS I ADG

OKLAHOMA STATE CAPITOL RESTORATION

Exterior Rehabilitation

ContentsSummary

Safety

Progress Photos

Attachments

Roofing Replacement Update

123

JANUARY 2019

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

45

STATE CAPITOL RESTORTATE CAPITOL RESTORTATE CAPITOL RESTO

Page 2: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

JANUARY 2019

Summary: During the month of January on the Oklahoma Capitol Exterior Restoration Project, exterior tunnel work was completed. Lincoln Boulevard was reopened in mid-January and will be re-striped in early February. The interior finishes in the tunnel will start in 2019, however, the tunnel will remain closed until the new Visitor’s Center is complete. The South Portico door installation was complete in early January ahead of the inauguration of the new Governor. The handrails for the lower South Plaza and the southwest ramp were installed in January. The temporary pedestrian protection was installed for the Southwest entry which allowed it to be re-opened at the end of January. Now that this entry is open, the Southeast entry has been closed while construction for the new Visitor’s Center is in progress. The West Wing South Elevation (Juliette) scaffolding was completely dismantled in January. The West Wing North Elevation (Lima) glass installation on phase 1 was also completed in January, along with the paint and sealant work. Interior storm window installation started at the end of the month and should be complete on phase 1 in early February. Phase 2 glass installation began in late January and will complete at the end of February. All exterior steel and cast iron frame repairs were completed in January. Paint and sealant work is on-going on phase 2 and will be complete at the end of February. The installation of the copper gutter lining is on-going and will be complete in mid-February in time for our final exterior skin punch list in March. The copper roofing replacement work has continued on the south wing. Over the last several weeks we have been working to repair the old and rotting substrate at the main sloped roof as well as the gutterways. New marine grade plywood framing is now complete in the gutterways and new roof drains and piping have been installed. The first sections of flat lock copper have been installed in the southeast (India) gutterway. At the main slope we are replacing all existing plywood. Once the existing plywood is removed, we review the existing substrate with our structural engineer to determine what 1x6 decking has to be replaced due to rotting. A large amount of rotting was found around the skylights of the south wing. This rotting included the 1x6 decking and the wood sleepers that are recessed into the concrete deck. Now that the substrate repairs are wrapping up on the sloped roof and around the skylights, we can begin framing the new skylights in February to receive copper. On the north wing, we expect to begin copper removal of the entire sloped roof at the beginning of February. This will allow us to analyze existing conditions and determine if extensive repairs need to be made to the substrate as we saw on the south wing. Please refer to the subsequent pages of this report to review photos of existing roofing conditions and re-roofing progress.

Page 3: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

KeyActivities:

- Echo new historical replica door installation complete - Tunnel phase two exterior work complete - Juliette scaffold demobilization complete - Kilo new historical replica door installation in progress - Lima copper gutter installation in progress - Lima stone restoration complete - South wing re-roofing gutterway framing complete - South wing gutterway flat-lock copper installation in progress - South wing re-roofing substrate repairs & plywood install in progress - West wing clerestory window installation complete - Lightwell excavation/concrete work for new sump pumps in progress - Northeast (Delta) phase 1 retaining wall replacement complete - Northeast phase (Delta) 1 mow strip installation complete - Delta balustrade stone restoration complete - Delta lightwell concrete wall repair prep work in progress - Alpha lightwell concrete wall repairs in progress

Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

JANUARY 2019

Page 4: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

Safety:The safety of our workforce and the general public during the course of construction is the most import-ant task that we must deliver. To that end, every craftsmen involved with the project receives a detailed project orientation, and prior to performing any task, the teams develop detailed task specific work plans. These work plans are often called Job Site Analysis (JSA) and assist project teams with analyzing different hazards associated with each work activity prior to beginning work.

Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

JANUARY 2019

Safety Data and Metrics

Orientations Performed through 01.31.19 665

First Aid Incidents for the month of January 0

Recordable Incidents for the month of January 0

Trade Partner Incidents for the month of January 1*

Total Man-Hours for the month of Jan. (hrs.) 6,111

Total Project Man-Hours (hrs.) 177,522

*During the month of January a trade partner had a worker that scraped his hand on a sharpening tool. The worker was wearing

his gloves at the time of the incident as well as his personal protective equipment.

Page 5: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

We recently completely another round of rigging training for our exterior restoration trade partners and our roofing crews. This rigging training included using virtual videos to learn proper hand signals as well as actual training on-site using the tower crane. Proper rigging training is important to ensure all materials that are being hoisted are secured properly before being lifted into the air.

Safety Spotlight

Page 6: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

Copper Re-roofing Update

Below Photo No. 1 shows a portion of the existing 1x6 wood decking that has had to be replaced on the south wing. This particular section is downslope from the southeast skylights. Photo No. 2 shows the installation of new 1x6 wood decking and plywood.

The following ZFI roof reports document the steps we are taking to make repairs of the existing substrate and also documents an unforeseen anchorage condition at the southeast and southwest gutterways.

Photo No. 1 Photo No. 2

Page 7: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

ZFI Engineering Co.

8411 S. Walker Ave.

OKC, OK 73139

Ph: 405.634.3393

Fx: 405.634.6414

www.zfiengr.com

RoofRepairWalk#1(11‐1‐2018)–PreliminaryInformation

Location: South End of Golf Elevation Gutterway (Backside of Parapet) GeneralComments: Existing Deformed Bar Anchors were discovered at the east end of the stone at the southern terminus of the gutterway. They occurred in immediate proximity to a pronounced crack in the limestone. Additional details and recommendations are forthcoming regarding how to treat the anchors and cracking. Mock‐upDiscussion Portions of the list of sleeper replacements/repairs and concrete fill patching below will serve as the mock-ups for their respective repair types. Additional comments in the list below.

Deformed Bar Anchors

Cramp Anchors

Cracked Stone

Page 8: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #1-Preliminary Memo ZFI Project #: 15071-01 November 1, 2018 Page 2 of 3

Location: Golf Elevation and India Elevation Gutterways RepairComments: Damaged or Rotted Sleepers in existing concrete fill. Replace sleepers from 2” to 3” above rotted area down the slope to the termination of the sleeper at the back of the parapet wall. Any concrete fill damaged as part of sleeper repair should be repaired per drawings. Repair list is as follows (sleepers numbered from the south end of the gutterway moving north): GolfElevation IndiaElevation1-4 1-46-10 7-1613-15 1820**, 21-27, 28* 2031-32 2134-36 25-2839 34-38*Mock-up for sleeper repair from damaged area down to parapet wall ** Mock-up for isolated sleeper repair (do NOT repair entire length to wall)

Page 9: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #1-Preliminary Memo ZFI Project #: 15071-01 November 1, 2018 Page 3 of 3

Location: Golf Elevation and India Elevation Gutterways RepairComments: Concrete fill repair (Type 6 per SS003). Perform mock-up repairs on the north side of sleeper #27 on Golf side and both sides as necessary next to sleeper #15 on Golf side.

Page 10: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

ZFI Engineering Co.

8411 S. Walker Ave.

OKC, OK 73139

Ph: 405.634.3393

Fx: 405.634.6414

www.zfiengr.com

RoofRepairWalk#2(12‐21‐2018)–DeckingEvaluation

India Slope of Repair Walk #2

Location: South End of South Wing (Gamma and India slopes) GeneralComments: The purpose of this walk was to evaluate the condition of the first expanse of exposed wood decking. At the time of the visit, a significant portion of the south half of the south wing had had the existing copper roofing and plywood underlayment removed. This exposed the 1x6 existing decking for evaluation. Removal of tar paper (between the decking and the plywood) was on-going. The walk consisted of marking (with orange paint) those specific decking boards that needed to be replaced and also general areas of decking that needed replacement. JEDunn was tasked with quantifying the total amount of replaced decking in this walk. Isolated locations requiring additional attachment using Aggre-gator concrete anchors were also noted. Existing nails that had popped up should be driven flush with the decking or supplemented with new nails per the repair documents.

Page 11: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 2 of 6

RepairDiscussion Portions of the decking had been removed in isolated locations and exposed the wood sleepers and concrete fill below. This was primarily at the ridge and at portions of the area that tied into the gutterway behind the east and west parapets. Demolished sleepers will be repaired prior to decking repairs.

Demo’d decking and sleepers @ ridge

Rotted decking at bottom of India Elevation Slope

Page 12: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 3 of 6

Decking appeared to be 1x6 material (~3/4” thick). In general, the decking was in good condition. Isolated areas of rot were encountered (the aforementioned ridge demo location and at the gutterways both pictured above). Split boards were observed in various locations and were typically required to be replaced between sleepers. Splits generally followed the length of the board and tended to originate at nail heads. Occasionally entire lengths of board were called for replacement due to extents of the splits.

Overcutting of the plywood also damaged some decking boards, requiring replacement or additional attachment. All efforts should be made during future demolition operations to avoid overcutting the plywood and damaging the existing decking. Based on this evaluation, there is a high likelihood that damaged decking will be in isolated locations only.

Split boards, typically thru nailhead

Overcut requiring additional attachment of decking to concrete below.

Page 13: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 4 of 6

Some small areas of rot/decay were noted along the limestone at the south edge of the roof. This appeared to be the result of the transition detail between the copper and the limestone at this location.

The following photos are representative examples of the decking repairs noted in the field.

Rotted decking along copper/limestone transition at south end of roof

Decking to be replaced (painted lines).

Additional attachment to sleepers or concrete fill below (painted dots)

Page 14: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 5 of 6

Repairs at south end of Gamma Elevation Slope

Repairs at south end of India Elevation Slope

Decking to be replaced, typ.

Additional attachment to sleepers or concrete fill below

Page 15: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Roof Repair Walk #2 ZFI Project #: 15071-01 December 21, 2018 Page 6 of 6

Extent of repairs on Gamma Slope

RepairComments: The following repair totals were determined by JEDunn personnel. GolfElevation IndiaElevation

121 linear feet of decking repair

168 linear feet of decking repair

24 anchor locations

4 anchor locations

Decking and sleeper repairs should be performed per the documents for ASI 016.

Page 16: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

Progress Photos & Field Reports

The photos and field reports attached in the subsequent pages represent progress photos taken during the month of January for the Oklahoma State Capitol Exterior Restoration project.

Page 17: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 1 of 8

FIELD OBSERVATION REPORT REPORT NO: 113 DATE: 1/2/2019

TIME: 1:15 - 2:00 PM DAY OF WEEK: Wednesday

OWNER: OMES TEMP. RANGE: Upper 20s

PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation

CAP PROJECT NO: 15039DB

JE DUNN PROJECT NO: 15025800

ADG PROJECT NO: 15-007

TREANORHL PROJECT NO: HP 15.007.00B

ZFI PROJECT NO: 15071-01

ALVINE PROJECT NO: 2014-4286

SRB PROJECT NO: 114801

WEATHER: Clear Overcast Rain Snow Cold

Warm Hot Foggy Windy Ice Other _________

SITE CONDITIONS: Clear Dusty Muddy Other ______________________

PERSONS CONTACTED: None

WORK OBSERVED:

Light fixture installation progressing on east elevation of east wing (Echo).

Door installation progressing on east elevation of east wing (Echo).

Concrete installation progressing at tunnel at circle drive.

Waterproofing installation progressing at tunnel at Lincoln Boulevard.

Roof work progressing on east elevation of south wing (Golf).

Handrail installation progressing at upper stairs at South Plaza.

Roof work progressing on west elevation of south wing (India).

Electrical equipment installation progressing adjacent to ramp at South Plaza.

Scaffold removal progressing on south elevation of west wing (Juliette).

Cast iron frame painting progressing on north elevation of west wing (Lima).

Window component installation progressing on north elevation of west wing (Lima).

Sealant installation progressing at windows on north elevation of west wing (Lima).

ITEMS DISCUSSED:

None

Page 18: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 2 of 8

ACTION REQUIRED:

Sand washed out at concrete sidewalk between ramp and Door 101 due to recent rains. (JE Dunn)

Trench drain grate rusted at north portion of West Plaza. (Streets)

ITEMS TO VERIFY:

None

REMARKS:

None

OBSERVED BY: Peter Breninger (ADG)

COPIES TO: Bobby Snyder (JE Dunn), Geoff Johnson (JE Dunn), Heath Glenn (JE Dunn), Lindsey Ross

(JE Dunn), Lynnsee Boyse (JE Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn),

JC Witcher (ADG), Robert Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz

(TreanorHL), Kelsey Liu (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley

(TreanorHL), Mike Thompson (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam

Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)

Page 19: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 3 of 8

Temporary guardrail in place at roof parapet on east elevation of north wing (Charlie)

Light fixtures in place on granite pedestals on east elevation of east wing (Echo)

Page 20: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 4 of 8

Door 104 installation progress on east elevation of east wing (Echo)

Concrete sidewalk and drive progress at tunnel at circle drive

Page 21: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 5 of 8

Waterproofing installation in progress at tunnel at Lincoln Boulevard

Handrail installation progress at upper stair at South Plaza

Page 22: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 6 of 8

Electrical equipment installation progress on north side of ramp at South Plaza

Scaffold removal in progress down to fourth floor on south elevation of west wing (Juliette)

Page 23: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 7 of 8

Cast iron frame painting progress at second floor window on north elevation of west wing (Lima)

Window component installation progress on north elevation of west wing (Lima)

Page 24: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 113 - 2018_01-02.docx

Page 8 of 8

Sand washed out at sidewalk on west elevation of south wing (India) due to recent rains.

Cast iron trench drain grate rusted at West Plaza.

Page 25: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 1 of 12

FIELD OBSERVATION REPORT REPORT NO: 114 DATE: 1/8/2019

TIME: 10:45 - 11:45 AM DAY OF WEEK: Tuesday

OWNER: OMES TEMP. RANGE: Upper 40s

PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation

CAP PROJECT NO: 15039DB

JE DUNN PROJECT NO: 15025800

ADG PROJECT NO: 15-007

TREANORHL PROJECT NO: HP 15.007.00B

ZFI PROJECT NO: 15071-01

ALVINE PROJECT NO: 2014-4286

SRB PROJECT NO: 114801

WEATHER: Clear Overcast Rain Snow Cold

Warm Hot Foggy Windy Ice Other _________

SITE CONDITIONS: Clear Dusty Muddy Other ______________________

PERSONS CONTACTED: None

WORK OBSERVED:

Retaining wall demolition progressing at northeast portion of site.

Backfill progressing at tunnel at Lincoln Boulevard.

Gutter way work progressing at roof on east elevation of south wing (Golf).

Roof drain piping installation progressing at south wing.

Door installation progressing on south elevation of south wing (Hotel).

Door restoration progressing on south elevation of south wing (Hotel).

Gutter way work progressing at roof on west elevation of south wing (India).

Door installation progressing on west elevation of south wing (India).

Scaffold removal progressing on south elevation of west wing (Juliette).

Handrail installation progressing at West Plaza.

Cast iron frame painting progressing on north elevation of west wing (Lima).

Window component installation progressing on north elevation of west wing (Lima).

Sealant installation progressing at windows on north elevation of west wing (Lima).

Copper installation progressing at gutter on north elevation of west wing (Lima).

Gutter installation progressing at backside of parapet on north elevation of west wing (Lima).

Page 26: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 2 of 12

ITEMS DISCUSSED:

Reviewed gasketing for double doors. Gasketing to be trimmed with straight edge so that doors do

not catch on each other.

Reviewed paint color and finish at interior side of doors and frames of Doors 201, 202, 203, and 204.

Interior side of Doors 202, 203, and 204 and hardware of Doors 202 and 204 to be painted Statuary

Bronze to match color of Door 203. Door 201 paint color and finish to remain.

ACTION REQUIRED:

None

ITEMS TO VERIFY:

None

REMARKS:

OAC Meeting occurred prior to the site visit in the jobsite trailers.

Interior/Exterior Coordination Meeting occurred prior to the site visit in Manhattan’s jobsite office.

OBSERVED BY: Peter Breninger (ADG)

COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Chris Savoie (JE Dunn), Geoff

Johnson (JE Dunn), Jon Whaley (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE

Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn), JC Witcher (ADG), Robert

Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Kelsey Liu

(TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI),

Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine),

Gary Noland (Smith Roberts Baldischwiler)

Page 27: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 3 of 12

Temporary guardrail installation progress at west and north elevations of north wing (Alpha and Bravo)

Retaining wall demolition in progress at northeast portion of site

Page 28: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 4 of 12

Backfill progress over tunnel at Lincoln Boulevard

Framing in progress at gutter at roof on east elevation of south wing (Golf)

Page 29: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 5 of 12

Roof drain piping progress on east elevation of south wing (Golf)

Protection in place under lower skylight to catch debris at south wing roof

Page 30: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 6 of 12

Door 203 installation progress on south elevation of south wing (Hotel)

Door 201 restoration progress on exterior side on south elevation of south wing (Hotel)

Page 31: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 7 of 12

Door 201 faux finish and hardware installation progress on interior side on south elevation of south wing

(Hotel)

Roof drain piping progress on west elevation of south wing (India)

Page 32: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 8 of 12

Plywood installation in progress at gutter way on west elevation of south wing (India). Deck repairs at

roof shown adjacent to gutter way.

Copper installation in progress at roof drain on west elevation of south wing (India)

Page 33: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 9 of 12

Door 101 installation in progress on west elevation of south wing (India)

Scaffold removal in progress down to third floor on south elevation of west wing (Juliette)

Page 34: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 10 of 12

Handrail installation in progress at south stair at West Plaza

Cast iron frame painting progress at window on north elevation of west wing (Lima)

Page 35: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 11 of 12

Window component installation progress at second floor on north elevation of west wing (Lima)

Sealant installation in progress at third floor window on north elevation of west wing (Lima)

Page 36: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 114 - 2019_01-08.docx

Page 12 of 12

Underlayment installation progress at backside of parapet at gutter on north elevation of west wing

(Lima).

Doors and hardware of Doors 202 and 204 to be painted Statuary Bronze to match color of Door 203.

Door 201 and 203 color and finish to remain as is.

Page 37: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 1 of 14

FIELD OBSERVATION REPORT REPORT NO: 115 DATE: 1/15/2019

TIME: 1:00 - 2:15 PM DAY OF WEEK: Tuesday

OWNER: OMES TEMP. RANGE: Lower 50s

PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation

CAP PROJECT NO: 15039DB

JE DUNN PROJECT NO: 15025800

ADG PROJECT NO: 15-007

TREANORHL PROJECT NO: HP 15.007.00B

ZFI PROJECT NO: 15071-01

ALVINE PROJECT NO: 2014-4286

SRB PROJECT NO: 114801

WEATHER: Clear Overcast Rain Snow Cold

Warm Hot Foggy Windy Ice Other _________

SITE CONDITIONS: Clear Dusty Muddy Other ______________________

PERSONS CONTACTED: Brad Slone, Chris Savoie, Geoff Johnson, James Shaw, Lindsey Ross, Lynnsee

Boyse, Mark Maska, Victor Mendoza - JE Dunn

Mike Thompson - ZFI

WORK OBSERVED:

Door installation progressing on west elevation of north wing (Alpha).

Retaining wall demolition progressing at northeast portion of site.

Mow strip installation progressing at northeast portion of site.

Door installation progressing on east elevation of east wing (Echo).

Concrete progressing at Lincoln Boulevard portion of tunnel.

Waterproofing installation progressing at east portion of tunnel.

Work progressing at roof on east elevation of south wing (Golf).

Deck demolition progressing at roof on west elevation of south wing (India).

Concrete fill demolition progressing at roof on west elevation of south wing (India).

Plywood installation progressing at roof on west elevation of south wing (India).

Door installation progressing on west elevation of south wing (India).

Electrical equipment installation progressing adjacent to ramp at South Plaza.

Scaffold removal progressing on south elevation of west wing (Juliette).

Handrail installation progressing at West Plaza.

Page 38: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 2 of 14

Cast iron frame painting progressing on north elevation of west wing (Lima).

Window component installation progressing on north elevation of west wing (Lima).

Sealant installation progressing at windows on north elevation of west wing (Lima).

Cast iron frame repairs progressing on north elevation of west wing (Lima).

Copper installation progressing at gutter on north elevation of west wing (Lima).

ITEMS DISCUSSED:

Meeting to review options for retaining wall over tunnel.

Reviewed options for sleeves in retaining walls for irrigation and lighting.

Reviewed location of retaining walls adjacent to the East Plaza. Retaining walls to line up with flat

portion of stone on battlement wall.

ACTION REQUIRED:

Spot elevations of area at tunnel to be provided to determine design of retaining wall. (JE Dunn)

Proposed locations of site lighting to be provided to determine locations of sleeves in retaining walls.

(ADG)

ITEMS TO VERIFY:

None

REMARKS:

None

OBSERVED BY: Peter Breninger (ADG)

COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Chris Savoie (JE Dunn), Geoff

Johnson (JE Dunn), Jon Whaley (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE

Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn), JC Witcher (ADG), Robert

Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Kelsey Liu

(TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI),

Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine),

Gary Noland (Smith Roberts Baldischwiler)

Page 39: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 3 of 14

Temporary guardrail installation progress at west and north elevations of north wing (Alpha and Bravo)

Door 001 installation progress on west elevation of north wing (Alpha)

Page 40: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 4 of 14

Retaining wall demolition progress at northeast portion of site

Retaining wall demolition progress at northeast portion of site

Page 41: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 5 of 14

Retaining wall demolition progress at northeast portion of site

Doors 103, 104, and 105 installation progress on east elevation of east wing (Echo)

Page 42: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 6 of 14

Concrete drive and road in place over tunnel at Lincoln Boulevard. Lincoln Boulevard open to all lanes of

traffic.

Waterproofing installation in progress at east portion of tunnel

Page 43: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 7 of 14

Temporary protection in place at gutter way, skylights, and south portion of roof on east elevation of

south wing (Golf)

Deck demolition in progress at roof on west elevation of south wing (India)

Page 44: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 8 of 14

Concrete fill demolition in progress at roof on west elevation of south wing (India)

Plywood installation in progress at roof on west elevation of south wing (India)

Page 45: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 9 of 14

Measuring for copper in progress on west elevation of south wing (India)

Temporary protection in place at skylights of roof on west elevation of south wing (India)

Page 46: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 10 of 14

Door 101 installation in progress on west elevation of south wing (India)

Sand bags placed adjacent to the sidewalk to prevent washout at the southwest portion of the site

Page 47: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 11 of 14

Wiring pulling and connection in progress at electrical equipment adjacent to ramp at South Plaza

Scaffold removal progress down to second floor window on south elevation of west wing (Juliette)

Page 48: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 12 of 14

Handrail installation progress at south stair at West Plaza

Handrail installation progress at north stair at West Plaza

Page 49: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 13 of 14

Cast iron frame painting progress at second floor window on north elevation of west wing (Lima)

Window component installation in progress at first floor window on north elevation of west wing (Lima)

Page 50: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 115 - 2019_01-15.docx

Page 14 of 14

Cast iron frame repair progress at fifth floor window on north elevation of west wing (Lima)

Copper installation in progress at gutter on north elevation of west wing (Lima)

Page 51: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 1 of 12

FIELD OBSERVATION REPORT REPORT NO: 116 DATE: 1/22/2019

TIME: 10:00 - 10:45 AM DAY OF WEEK: Tuesday

OWNER: OMES TEMP. RANGE: Lower 50s

PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation

CAP PROJECT NO: 15039DB

JE DUNN PROJECT NO: 15025800

ADG PROJECT NO: 15-007

TREANORHL PROJECT NO: HP 15.007.00B

ZFI PROJECT NO: 15071-01

ALVINE PROJECT NO: 2014-4286

SRB PROJECT NO: 114801

WEATHER: Clear Overcast Rain Snow Cold

Warm Hot Foggy Windy Ice Other _________

SITE CONDITIONS: Clear Dusty Muddy Other ______________________

PERSONS CONTACTED: Brandon Marriott, Chris Savoie, Jon Whaley, Lindsey Ross, Lynnsee Boyse, Mark

Maska, Victor Mendoza - JE Dunn

WORK OBSERVED:

Retaining wall work progressing at northeast portion of site.

Mow strip work progressing at northeast portion of site.

Retaining wall work progressing at southeast portion of site.

Concrete work progressing at east parking lot.

Waterproofing installation progressing at east portion of tunnel.

Roof drain piping installation progressing at south wing.

Door installation progressing on west elevation of south wing (India).

Railing installation progressing at ramp at South Plaza.

Electrical equipment installation progressing adjacent to ramp at South Plaza.

Scaffold removal progressing on south elevation of west wing (Juliette).

Handrail installation progressing at West Plaza.

Sealant installation progressing at windows on north elevation of west wing (Lima).

Window component installation progressing on north elevation of west wing (Lima).

Cast iron frame repairs progressing on north elevation of west wing (Lima).

Page 52: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 2 of 12

Copper installation progressing at gutter on north elevation of west wing (Lima).

ITEMS DISCUSSED:

None

ACTION REQUIRED:

None

ITEMS TO VERIFY:

None

REMARKS:

OAC Meeting occurred prior to the site visit in the jobsite trailers.

OBSERVED BY: Peter Breninger (ADG)

COPIES TO: Bobby Snyder (JE Dunn), Brandon Marriott (JE Dunn), Chris Savoie (JE Dunn), Geoff

Johnson (JE Dunn), Jon Whaley (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE

Dunn), Mark Maska (JE Dunn), Victor Mendoza (JE Dunn), JC Witcher (ADG), Robert

Meek (ADG), Amelia Hudspeth (TreanorHL), Julia Manglitz (TreanorHL), Kelsey Liu

(TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI),

Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine),

Gary Noland (Smith Roberts Baldischwiler)

Page 53: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 3 of 12

Platform demolished in light well on west elevation of north wing (Alpha)

Concrete demolished at base of stairs at North Plaza

Page 54: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 4 of 12

Retaining wall excavation and grading in progress at northeast portion of site

Mow strip formwork installation progress at northeast portion of site adjacent to balustrade

Page 55: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 5 of 12

Retaining wall excavation and grading progress at southeast portion of site

Concrete pour in progress for curb and gutter at east parking lot

Page 56: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 6 of 12

Formwork in place for concrete pour at east parking lot

Waterproofing covered over at east portion of tunnel

Page 57: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 7 of 12

Roof drain piping progress on east elevation of south wing (Golf)

Plywood up in place of Door 201 on south elevation of south wing (Hotel). Door was removed by OMES

and they attempted to reinstall it, then the door fell. The door is not meant to be operated. A to-be-

determined component will be added to the door so that people know it is not to be used.

Page 58: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 8 of 12

Door 101 installation in progress on west elevation of south wing (India). The historic light fixtures have

also been installed at the granite pedestals adjacent to Door 101.

Railing installation in progress at ramp at South Plaza.

Page 59: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 9 of 12

Railing installation in progress at ramp at South Plaza

Wiring connection in progress at electrical equipment adjacent to ramp at South Plaza

Page 60: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 10 of 12

Scaffold removal progress down to second floor windows on south elevation of west wing (Juliette)

Handrail installation progress at north stair at West Plaza

Page 61: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 11 of 12

Sealant installation in progress at fifth floor window on west portion on north elevation of west wing

(Lima)

Window component installation in progress at fifth floor window on east portion on north elevation of

west wing (Lima)

Page 62: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

P:\Oklahoma State Capitol\15-007 Capitol Renovation Exterior\Construction Administration\Field

Reports\ADG\OSCR FR 116 - 2019_01-22.docx

Page 12 of 12

Cast iron frame repair in progress at third floor window on east portion on north elevation of west wing

(Lima)

Copper installation progress at gutter on north elevation of west wing (Lima)

Page 63: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 1 of 5

FIELD OBSERVATION REPORT REPORT NO: 144 DATE: 01/09/2019 TIME: 11:00 am – 4:30 pm DAY OF WEEK: Wednesday OWNER: OMES TEMP. RANGE: Hi 40s – Lo 50s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other ___ SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:

Lynnsee Boyse, Mark Maska, Lindsey Ross, Geoffrey Johnson, Victor Mendoza, Jon Whaley, Brandon Marriott, Chris Savoie (JE Dunn) Eddie Pait, Jerry Barker (Baker Roofing) Lukasz Lesniak (Mark1) Trait Thompson, Doug Kellogg (OMES) Peter Breninger, JC Witcher (ADG) Mike Thompson (ZFI)

WORK OBSERVED:

Gutterway mockup in progress – sheet metal trial layout.

Gutterway framing is complete.

Removal and replacement of over decking has started on the west slope of the south wing.

ITEMS DISCUSSED:

Reglets and coordination with Mark1, particularly the at the pediment.

South wing skylight details and integration with panel installation: Reviewed on ground mockup created by Baker and Ornametals. Connections between top and sidewalls are all acceptable, corners that have blind rivets shall have closed end rivets. Continued discussion about the impact the upslope and downslope details have on the panel layout. (Baker)

Page 64: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 2 of 5

ACTION REQUIRED:

Discuss clip spacing with structural. (TreanorHL)

Trial panel layouts with the skylight upslope and downslope details (TreanorHL) and with proposed changes to those details (Baker). (Baker, TreanorHL)

ITEMS TO VERIFY:

REMARKS:

Appreciation luncheon.

OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson

(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE Dunn), Geoffrey Johnson (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)

Gutterway mockup coming out of the roof drain.

Page 65: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 3 of 5

Gap at slope change should be caulked with polyurethane sealant. Check compatibility with both

underlayment materials

Panel clips are specified for use with overdecking to keep transitions between panels spaced and edges

level. All fastners need to be countersunk.

Page 66: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 4 of 5

Side of lower skylight concrete curb exposed by removal of existing copper and substrate.

Location of gutterway cricket ridge is correct, however the blocking needs to extend and bevel cleanly

into the main slope.

Page 67: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_09.docx Page 5 of 5

Skylight downslope outside corner preliminary mockup.

Sklyight upslope corner preliminary mockup.

Skylight cricket preliminary mockup.

Page 68: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_10.docx Page 1 of 2

FIELD OBSERVATION REPORT REPORT NO: 145 DATE: 01/10/2019 TIME: 8:00 am – 10:00 am DAY OF WEEK: Thursday OWNER: OMES TEMP. RANGE: Lo 40s – Mid 40s PROJECT: Oklahoma Capitol Restoration - Exterior Rehabilitation CAP PROJECT NO: 15039DB JE DUNN PROJECT NO: 15025800 ADG PROJECT NO: 15-007 TREANOR PROJECT NO: HP 15.007.00B ZFI PROJECT NO: 15071-01 ALVINE PROJECT NO: 2014-4286 SRB PROJECT NO: 114801 WEATHER: Clear Overcast Rain Snow Cold Warm Hot Foggy Windy Ice Other ___ SITE CONDITIONS: Clear Dusty Muddy Other _________________ PERSONS CONTACTED:

Lynnsee Boyse, Bobby Snyder, Lindsey Ross, Jon Whaley, Brandon Marriott (JE Dunn) WORK OBSERVED:

ITEMS DISCUSSED:

Overview discussion of copper roofing scope and construction sequence considerations with Jon Whaley and Brandon Marriott, additional JE Dunn personnel for the roofing.

ACTION REQUIRED:

ITEMS TO VERIFY:

REMARKS:

Page 69: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

C:\Users\jmanglitz\Dropbox (Personal)\oklahoma - julia\CA\OSCR FR TA.144 - 2019_01_10.docx Page 2 of 2

OBSERVED BY: Julia Manglitz, Associate Principal (TreanorHL) COPIES TO: David Mihm (OMES), Doug Kellogg (OMES), Mike Jones (OMES), Trait Thompson

(OMES), Duane Mass (MAI), Jason Cady (MAI), Matthew Radcliffe (MAI), Mark Maska (JE Dunn), Bobby Snyder (JE Dunn), Lindsey Ross (JE Dunn), Lynnsee Boyse (JE Dunn), Geoffrey Johnson (JE Dunn), JC Witcher (ADG), Robert Meek (ADG), Julia Manglitz (TreanorHL), Todd Renyer (TreanorHL), Vance Kelley (TreanorHL), Mike Thompson (ZFI), Steve Ford (ZFI), Andy Wiese (Alvine), Ed Kongs (Alvine), Sam Haberman (Alvine), Steve Alvine (Alvine), Gary Noland (Smith Roberts Baldischwiler)

Page 70: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

Phasing & Schedule Attachments: The following documents are included in the subsequent pages:

- Site Phasing Plan - Site Utilization Plan - Six (6) Week Look Ahead Schedule

Page 71: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

Site Phasing Plan:

The site phasing plan is a broad representation of the work flow for the Capitol exterior rehabilitation. Beginning with Alpha (west elevation of the north wing), scaffolding was constructed continuing on to Bravo, Charlie, Delta and Echo. We construct a phase of scaffolding at a time, which is followed by hazardous material removal, window restoration, and stone and lighting repair. As each phase is complet-ed, the scaffolding will be disassembled and reassembled on similar elevations. This site phasing will occur for the duration of the rehabilitation until all work is complete, and the State Capitol is back to its original beauty and functionality.

Page 72: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Trailer Compound

TUNNEL (will continue across Lincoln)

DELTA

FOX TROT

ECHO

KILO

ALPHA

CHARLIE

GOLF

INDIA

HOTEL

JULIETTE

LIMA

BRAVOCOMPLETED

CO

MPLETED

CO

MPLE

TED

COMPLETED

CO

MPLETED

CO

MPLETED

ACTIVE ELEVATIONS

COMPLETED

CO

MPLE

TED

COMPLETED

CO

MPLE

TED

COMPLETED

Page 73: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

1503

9DB

MON

THLY

CON

STRU

CTIO

N PR

OGRE

SS R

EPOR

T

4 E SHERIDAN AVE SUITE 200 I OKLAHOMA CITY, OK 73104 I P 405.302.4500 I WWW.JEDUNN.COM

RETURNS TO TABLE OF CONTENTSCLICK HERE

JANUARY 2019 Exterior RehabilitationJE DUNN I TREANORHL ARCHITECTS I ADG

Site Utilization Plan:

Per our site utilization plan, the JE Dunn trailer compound is the designated area for our staff members,trade partners, and material storage areas. It currently houses four field offices.

Our site fencing is a revolving system that isolates our work area from the public as we move around the Capitol building, helping to ensure a safe work environment.

The gravel lay-down areas are designated paths where machinery, supplies, and equipment are stored and provide a roadway for machinery to move supplies to and from the job site. The gravel will also serve as a protective barrier of the subsurface. Fence gates mark all areas where access can be gained to the job site for material and/or equipmentdeliveries, emergency access, or personnel access. These gates remain closed and are locked every night to ensure a safe work environment.

Page 74: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

JED

JED

Page 75: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Activity ID Activity Name RemDur

Start Finish

Oklahoma Legislative SessionsOklahoma Legislative Sessions 85 04-Feb-19 03-Jun-19

.. 85 04-Feb-19 03-Jun-19

.. 85 04-Feb-19 03-Jun-19

CON-30300 2019 Session 85 04-Feb-19* 03-Jun-19

Construction SummaryConstruction Summary 81 26-Feb-18 A 04-Apr-19

.. 81 26-Feb-18 A 04-Apr-19

.. 81 26-Feb-18 A 04-Apr-19

CON-10980 Juliette Facade Repair Duration 17 26-Feb-18 A 30-Jan-19

CON-11000 Lima Facade Repair Duration 81 21-May-18 A 04-Apr-19

ElevationsElevations 59 22-Oct-18 A 04-Apr-19

Juliette- West Wing South FaceJuliette- West Wing South Face 13 12-Nov-18 A 30-Jan-19

ScaffoldScaffold 11 13-Dec-18 A 30-Jan-19

CON-19590 Juliette-Ph 2-Demobilize scaffold and tarp 11 13-Dec-18 A 30-Jan-19

CON-19600 Juliette-Patch scaffold anchor holes 11 13-Dec-18 A 30-Jan-19

InteriorInterior 7 12-Nov-18 A 22-Jan-19

CON-19630 Juliette-Interior Wall Finishes 7 12-Nov-18 A 22-Jan-19

Kilo- West Wing West FaceKilo- West Wing West Face 15 22-Oct-18 A 01-Feb-19

InteriorInterior 15 22-Oct-18 A 01-Feb-19

CON-17830 Kilo-Interior Wall Finishes 15 22-Oct-18 A 01-Feb-19

Lima- West Wing North FaceLima- West Wing North Face 59 30-Nov-18 A 04-Apr-19

ScaffoldScaffold 16 14-Mar-19 04-Apr-19

CON-20170 Lima-Ph 2-Remove temp HVAC in scaffold 1 14-Mar-19 14-Mar-19

CON-20180 Lima-Ph 2-Remove temp power in scaffold 2 14-Mar-19 15-Mar-19

CON-20190 Lima-Ph 2-Demobilize scaffold and tarp 12 18-Mar-19 04-Apr-19

CON-30820 Lima-Ph 2-Scaffold Demobilization Start 0 18-Mar-19

CON-20200 Lima-Patch scaffold anchor holes 1 04-Apr-19 04-Apr-19

InteriorInterior 30 14-Jan-19 A 22-Feb-19

CON-20250 Lima-Remove interior partitions 26 14-Jan-19 A 18-Feb-19

CON-20230 Lima-Interior Wall Finishes 30 14-Jan-19 22-Feb-19

CON-33690 Lima-Deliver Storm Windows 15 14-Jan-19 01-Feb-19

CON-20240 Lima-Interior storm windows 15 04-Feb-19 22-Feb-19

Window FinishesWindow Finishes 31 04-Dec-18 A 25-Feb-19

CON-20540 Lima-Ph 1-Re-install window sashes, panels, and trim 4 04-Dec-18 A 17-Jan-19

CON-32580 Lima-Ph 1-Final Paint Window Frame 7 10-Dec-18 A 22-Jan-19

CON-32590 Lima-Ph 1-Caulk window frames to stone 7 12-Dec-18 A 24-Jan-19

CON-24860 Lima-Ph 2-Re-install window sashes, panels, and trim 22 17-Jan-19 15-Feb-19

CON-20580 Lima-Ph 2-Final Paint Window Frame 20 23-Jan-19 19-Feb-19

CON-20600 Lima-Ph 2-Caulk window frames to stone 20 25-Jan-19 21-Feb-19

CON-20620 Lima-Ph 2-Re-install HVAC louvers 1 22-Feb-19 22-Feb-19

CON-20630 Lima-Window Spray Test 2 22-Feb-19 25-Feb-19

Stone Cleaning & SealantsStone Cleaning & Sealants 9 26-Feb-19 12-Mar-19

CON-20640 Lima-Ph 2-Wash down brick and stone 4 26-Feb-19 04-Mar-19

CON-33830 Lima-Ph 2-Dry Time 5 05-Mar-19 12-Mar-19

Gutter/ParapetGutter/Parapet 30 30-Nov-18 A 25-Feb-19

CON-30140 Lima-Install Metal Wall Panels 30 30-Nov-18 A 22-Feb-19

CON-30050 Lima-Install Underlayment 2 11-Dec-18 A 15-Jan-19

CON-30060 Lima-Install Gutter Liner 25 13-Dec-18 A 15-Feb-19

CON-30120 Lima-Install Hanging Gutter 10 11-Feb-19 22-Feb-19

CON-30150 Lima-Install Metal Wall Panel Trim 7 14-Feb-19 22-Feb-19

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

2019 2

2019 Session

Juliette Facade Repair Duration

Lima Facade Repair Duration

Juliette-Ph 2-Demobilize scaffold and tarp

Juliette-Patch scaffold anchor holes

Juliette-Interior Wall Finishes

Kilo-Interior Wall Finishes

Lima-Ph 2-Remove temp HVAC in scaffold

Lima-Ph 2-Remove temp power in scaffold

Lima-Ph 2-Demobilize scaffold and tarp

Lima-Ph 2-Scaffold Demobilization Start

Lima-Patch scaffold anchor holes

Lima-Remove interior partitions

Lima-Interior Wall Finishes

Lima-Deliver Storm Windows

Lima-Interior storm windows

Lima-Ph 1-Re-install window sashes, panels, and trim

Lima-Ph 1-Final Paint Window Frame

Lima-Ph 1-Caulk window frames to stone

Lima-Ph 2-Re-install window sashes, panels, and trim

Lima-Ph 2-Final Paint Window Frame

Lima-Ph 2-Caulk window frames to stone

Lima-Ph 2-Re-install HVAC louvers

Lima-Window Spray Test

Lima-Ph 2-Wash down brick and stone

Lima-Ph 2-Dry Time

Lima-Install Metal Wall Panels

Lima-Install Underlayment

Lima-Install Gutter Liner

Lima-Install Hanging Gutter

Lima-Install Metal Wall Panel Trim

Remaining Construction

Data Date: 14-Jan-19

Run Date: 22-Jan-19; 08:31

Oklahoma State Capitol Exterior Renovation

Page 1 of 4

 

Page 76: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Activity ID Activity Name RemDur

Start Finish

CON-30240 Lima-Flood-Test Gutter 1 18-Feb-19 18-Feb-19

CON-30200 Lima-Re-Install Lightning Protection 2 19-Feb-19 20-Feb-19

CON-30170 Lima-Install Lead Tees 1 21-Feb-19 25-Feb-19

Punch & CompletePunch & Complete 15 25-Feb-19 18-Mar-19

CON-30850 Lima-Window Restoration Complete 0 25-Feb-19

CON-22800 Lima Pre-punch 1 26-Feb-19 26-Feb-19

CON-22810 Lima Complete pre-punch list 1 27-Feb-19 27-Feb-19

CON-22820 Lima Punchlist 1 13-Mar-19 13-Mar-19

CON-22830 Lima - Complete punchlist 3 14-Mar-19 18-Mar-19

DoorsDoors 23 24-Jan-19 25-Feb-19

Bravo- North Wing North FaceBravo- North Wing North Face 5 19-Feb-19 25-Feb-19

New Door SequenceNew Door Sequence 5 19-Feb-19 25-Feb-19

CON-27490 Bravo.D106-Install New Frame 2 19-Feb-19 20-Feb-19

CON-27500 Bravo.D106-Install New Door/Hardware 3 21-Feb-19 25-Feb-19

Echo- East Wing East FaceEcho- East Wing East Face 4 24-Jan-19 29-Jan-19

New Door SequenceNew Door Sequence 4 24-Jan-19 29-Jan-19

CON-27730 Echo.D105-Remove Door/Hardware 1 24-Jan-19* 24-Jan-19

CON-27750 Echo.D105-Remove Frame 1 25-Jan-19 25-Jan-19

CON-27760 Echo.D105-Install New Frame 1 28-Jan-19 28-Jan-19

CON-27770 Echo.D105-Install New Door/Hardware 1 29-Jan-19 29-Jan-19

Golf- South Wing West FaceGolf- South Wing West Face 12 01-Feb-19 18-Feb-19

New Door SequenceNew Door Sequence 12 01-Feb-19 18-Feb-19

CON-27820 Golf.D102-Remove Door/Hardware 2 01-Feb-19* 04-Feb-19

CON-27840 Golf.D102-Remove Frame 2 05-Feb-19 06-Feb-19

CON-27850 Golf.D102-Install New Frame 2 07-Feb-19 08-Feb-19

CON-27860 Golf.D102-Install New Door/Hardware 3 11-Feb-19 13-Feb-19

CON-33700 Lightwell-HM Door Frames/Doors (X3) 6 11-Feb-19 18-Feb-19

Kilo- West Wing West FaceKilo- West Wing West Face 8 30-Jan-19 08-Feb-19

New Door SequenceNew Door Sequence 8 30-Jan-19 08-Feb-19

CON-27220 Kilo.D107-Install New Frame 1 30-Jan-19 30-Jan-19

CON-27130 Kilo.D108-Install New Frame 1 31-Jan-19 31-Jan-19

CON-27230 Kilo.D107-Install New Door/Hardware 1 31-Jan-19 31-Jan-19

CON-27140 Kilo.D108-Install New Door/Hardware 1 01-Feb-19 01-Feb-19

CON-27040 Kilo.D109-Install New Frame 1 04-Feb-19 04-Feb-19

CON-27050 Kilo.D109-Install New Door/Hardware 1 05-Feb-19 05-Feb-19

CON-27300 Kilo.D601 & 602 -Remove Frame 1 06-Feb-19 06-Feb-19

CON-27310 Kilo.D601 & 602 -Install New Frame 1 07-Feb-19 07-Feb-19

CON-27320 Kilo.D601 & 602 -Install New Door/Hardware 1 08-Feb-19 08-Feb-19

SiteSite 117 27-Nov-18 A 26-Jun-19

TunnelTunnel 96 17-Dec-18 A 28-May-19

Tunnel RepairsTunnel Repairs 17 15-Jan-19 06-Feb-19

CON-31530 Remove Barriers and Re-Open Lincoln 2 15-Jan-19 16-Jan-19

CON-33380 Remove Temp. Road 3 15-Jan-19 17-Jan-19

CON-31500 Concrete Prep for Sidewalks 2 21-Jan-19 22-Jan-19

CON-31510 Place & Finish Sidewalks 1 23-Jan-19 23-Jan-19

CON-31540 Phase 2 Complete 0 23-Jan-19

CON-31570 Replace Plants, Trees & Sod 7 29-Jan-19 06-Feb-19

CON-33390 Stripings & Markings 2 01-Feb-19 04-Feb-19

Tunnel FinishesTunnel Finishes 96 17-Dec-18 A 28-May-19

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

2019 2

Lima-Flood-Test Gutter

Lima-Re-Install Lightning Protection

Lima-Install Lead Tees

Lima-Window Restoration Complete

Lima Pre-punch

Lima Complete pre-punch list

Lima Punchlist

Lima - Complete punchlist

Bravo.D106-Install New Frame

Bravo.D106-Install New Door/Hardware

Echo.D105-Remove Door/Hardware

Echo.D105-Remove Frame

Echo.D105-Install New Frame

Echo.D105-Install New Door/Hardware

Golf.D102-Remove Door/Hardware

Golf.D102-Remove Frame

Golf.D102-Install New Frame

Golf.D102-Install New Door/Hardware

Lightwell-HM Door Frames/Doors (X3)

Kilo.D107-Install New Frame

Kilo.D108-Install New Frame

Kilo.D107-Install New Door/Hardware

Kilo.D108-Install New Door/Hardware

Kilo.D109-Install New Frame

Kilo.D109-Install New Door/Hardware

Kilo.D601 & 602 -Remove Frame

Kilo.D601 & 602 -Install New Frame

Kilo.D601 & 602 -Install New Door/Hardware

Remove Barriers and Re-Open Lincoln

Remove Temp. Road

Concrete Prep for Sidewalks

Place & Finish Sidewalks

Phase 2 Complete

Replace Plants, Trees & Sod

Stripings & Markings

Remaining Construction

Data Date: 14-Jan-19

Run Date: 22-Jan-19; 08:31

Oklahoma State Capitol Exterior Renovation

Page 2 of 4

 

Page 77: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Activity ID Activity Name RemDur

Start Finish

CON-32740 Waterproof Slab/Epoxy Coating 3 17-Dec-18 A 16-Jan-19

CON-32750 Frame Walls 15 17-Jan-19 06-Feb-19

CON-32770 OH Rough-In 10 17-Jan-19 30-Jan-19

CON-32780 Sump Pump 5 17-Jan-19 23-Jan-19

CON-32760 In-Wall Rough-In/Wood Bloc king 10 31-Jan-19 13-Feb-19

CON-32790 Frame Ceilings 15 07-Feb-19 27-Feb-19

CON-32820 Hang Walls 10 14-Feb-19 27-Feb-19

CON-32800 Light Fixtures 10 28-Feb-19 13-Mar-19

CON-32810 Hang Ceilings 5 14-Mar-19 20-Mar-19

CON-32830 Tape/Mud/Paint 15 14-Mar-19 03-Apr-19

CON-32840 Ceiling Grid 5 04-Apr-19 10-Apr-19

CON-32850 Handrails 5 04-Apr-19 10-Apr-19

CON-32860 Acoustical Panels 10 04-Apr-19 17-Apr-19

CON-32870 Millwork 20 04-Apr-19 01-May-19

CON-32920 Ceiling Grid Rough-In 5 11-Apr-19 17-Apr-19

CON-32930 Drop Tile 5 18-Apr-19 24-Apr-19

CON-32880 Rubber Stair Treads & Ris ers 3 25-Apr-19 29-Apr-19

CON-32890 Flooring Tile 15 25-Apr-19 15-May-19

CON-32900 Carpet 5 16-May-19 22-May-19

CON-32910 Final Clean 3 23-May-19 28-May-19

CON-32940 Tunnel Finishes Complete 0 28-May-19

Site-LightwellsSite-Lightwells 87 04-Feb-19 05-Jun-19

HardscapeHardscape 87 04-Feb-19 05-Jun-19

CON-33150 Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Demo Lightwells 15 04-Feb-19 22-Feb-19

CON-33180 Lightwells-(Golf, Foxtrot) -Pit Slab 1 25-Feb-19 25-Feb-19

CON-33170 Lightwells-(Golf, Foxtrot)-Install Sump Pumps 1 26-Feb-19 26-Feb-19

CON-33480 Lightwells-(Golf, Foxtrot)-Waterproofing 1 26-Feb-19 26-Feb-19

CON-33490 Lightwells-(Golf, Foxtrot)-Topping Slab 1 27-Feb-19 27-Feb-19

CON-33750 Lightwells-(Charlie, Delta) -Form/Pour Concrete Pits 7 19-Mar-19 27-Mar-19

CON-33760 Lightwells-(Charlie, Delta) -Topping Slab 1 28-Mar-19 28-Mar-19

CON-33500 Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Wall Coating 15 29-Mar-19 18-Apr-19

CON-33510 Lightwells-Ph 2 (Alpha, Lima, Juliette) -Demo Lightwells 15 05-Apr-19 25-Apr-19

CON-33520 Lightwells-(Juliette)-Form/Pour Concrete Pits 4 26-Apr-19 01-May-19

CON-33530 Lightwells-(Juliette)-Install Sump Pumps 1 02-May-19 02-May-19

CON-33540 Lightwells-(Juliette)-Waterproofing 1 02-May-19 02-May-19

CON-33550 Lightwells-(Juliette)-Topping Slab 1 03-May-19 03-May-19

CON-33770 Lightwells-(Alpha, Lima)-Form/Pour Concrete Pits 5 06-May-19 10-May-19

CON-33780 Lightwells-(Alpha, Lima)-Install Sump Pumps 1 13-May-19 13-May-19

CON-33790 Lightwells-(Alpha, Lima)-Waterproofing 1 13-May-19 13-May-19

CON-33800 Lightwells-(Alpha, Lima)-Topping Slab 1 14-May-19 14-May-19

CON-33560 Lightwells-Ph 2 (Alpha, Lima, Juliette)-Wall Coating 15 15-May-19 05-Jun-19

Site-South RampSite-South Ramp 14 27-Nov-18 A 31-Jan-19

HardscapeHardscape 14 27-Nov-18 A 31-Jan-19

CON-33680 Fabricate Handrails 6 27-Nov-18 A 21-Jan-19

CON-33670 Install Handrails & Guardrails 8 22-Jan-19 31-Jan-19

Site-Northeast Ret Wall/LandscapeSite-Northeast Ret Wall/Landscape 117 08-Jan-19 A 26-Jun-19

HardscapeHardscape 112 08-Jan-19 A 19-Jun-19

CON-23240 NE Wall-Demo Retaining Walls 0 08-Jan-19 A 14-Jan-19

CON-33590 NE Wall-Form/Place New Retaining Wall & Mow Strip 20 14-Jan-19 08-Feb-19

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

2019 2

Waterproof Slab/Epoxy Coating

Frame Walls

OH Rough-In

Sump Pump

In-Wall Rough-In/Wood Bloc king

Frame Ceilings

Hang Walls

Light Fixtures

Hang Ceilings

Tape/Mud/Paint

Ceiling Grid

Handrails

Acoustical Panels

Millwork

Ceiling Grid Rough-In

Drop Tile

Rubber Stair Treads & Ris ers

Flooring Tile

Carpet

Final Clean

Tunnel Finishes Complete

Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Demo Lightwells

Lightwells-(Golf, Foxtrot) -Pit Slab

Lightwells-(Golf, Foxtrot)-Install Sump Pumps

Lightwells-(Golf, Foxtrot)-Waterproofing

Lightwells-(Golf, Foxtrot)-Topping Slab

Lightwells-(Charlie, Delta) -Form/Pour Concrete Pits

Lightwells-(Charlie, Delta) -Topping Slab

Lightwells-Ph 1 (Charlie, Delta, Golf, Foxtrot) -Wall Coating

Lightwells-Ph 2 (Alpha, Lima, Juliette) -Demo Lightwells

Lightwells-(Juliette)-Form/Pour Concrete Pits

Lightwells-(Juliette)-Install Sump Pumps

Lightwells-(Juliette)-Waterproofing

Lightwells-(Juliette)-Topping Slab

Lightwells-(Alpha, Lima)-Form/Pour Concrete Pits

Lightwells-(Alpha, Lima)-Install Sump Pumps

Lightwells-(Alpha, Lima)-Waterproofing

Lightwells-(Alpha, Lima)-Topping Slab

Lightwells-Ph 2 (Alpha, Lima, Juliette)-Wall Coating

Fabricate Handrails

Install Handrails & Guardrails

NE Wall-Demo Retaining Walls

NE Wall-Form/Place New Retaining Wall & Mow Strip

Remaining Construction

Data Date: 14-Jan-19

Run Date: 22-Jan-19; 08:31

Oklahoma State Capitol Exterior Renovation

Page 3 of 4

 

Page 78: ContentsSummary MONTHLY CONSTRUCTION PROGRESS …capitolrestore.ok.gov/wp-content/uploads/2019/02/...OKC, OK 73139 Ph: 405.634.3393 Fx: 405.634.6414 Roof Repair Walk #1 (11‐1‐2018)

Activity ID Activity Name RemDur

Start Finish

CON-33810 NE Wall-Form/Place New Retaining Wall & Mow Strip (after crane demob) 5 12-Jun-19 19-Jun-19

LandscapeLandscape 97 11-Feb-19 26-Jun-19

CON-23250 NE Wall-Grading & Landscaping 15 11-Feb-19 01-Mar-19

CON-33190 NE Wall-Sump Pump Piping Daylighting 5 11-Feb-19 15-Feb-19

CON-33820 NE Wall-Grading & Landscaping (after crane demob) 5 19-Jun-19 26-Jun-19

Site-East PlazaSite-East Plaza 6 11-Feb-19 18-Feb-19

HardscapeHardscape 6 11-Feb-19 18-Feb-19

CON-33710 E Plaza. North Half-Slab on Grade 3 11-Feb-19 13-Feb-19

CON-33720 E Plaza. South Half-Slab on Grade 3 14-Feb-19 18-Feb-19

Site-North PlazaSite-North Plaza 4 19-Feb-19 22-Feb-19

HardscapeHardscape 4 19-Feb-19 22-Feb-19

CON-33730 N Plaza-Slab on Grade/Fill Exist Vent Shaft 4 19-Feb-19 22-Feb-19

Site-Southeast Ret Wall/LandscapeSite-Southeast Ret Wall/Landscape 13 28-Feb-19 18-Mar-19

HardscapeHardscape 13 28-Feb-19 18-Mar-19

CON-33740 SE Wall-Form/Place Ftgs/New Retaining Wall 13 28-Feb-19 18-Mar-19

Site-Southwest Ret Wall/LandscapeSite-Southwest Ret Wall/Landscape 40 22-Mar-19 16-May-19

HardscapeHardscape 25 22-Mar-19 25-Apr-19

CON-33200 SW Wall-Demo Retaining Walls 5 22-Mar-19 28-Mar-19

CON-33570 SW Wall-Form/Place New Retaining Wall & Mow Strip 20 29-Mar-19 25-Apr-19

LandscapeLandscape 15 26-Apr-19 16-May-19

CON-33220 SW Wall-Grading & Landscaping 15 26-Apr-19 16-May-19

CON-33210 SW Wall-Sump Pump Piping Daylighting 5 26-Apr-19 02-May-19

Site-Northwest Ret Wall/LandscapeSite-Northwest Ret Wall/Landscape 58 05-Apr-19 26-Jun-19

HardscapeHardscape 48 05-Apr-19 12-Jun-19

CON-33230 NW Wall-Demo Retaining Walls 5 05-Apr-19 11-Apr-19

CON-33580 NW Wall-Form/Place New Retaining Wall & Mow Strip 20 15-May-19 12-Jun-19

LandscapeLandscape 10 12-Jun-19 26-Jun-19

CON-33250 NW Wall-Grading & Landscaping 10 12-Jun-19 26-Jun-19

CON-33240 NW Wall-Sump Pump Piping Daylighting 5 12-Jun-19 19-Jun-19

Closeout & WarrantyCloseout & Warranty 317 02-Apr-19 29-Jun-20

.. 60 02-Apr-19 26-Jun-19

.. 60 02-Apr-19 26-Jun-19

CON-10760 Base Job Demobillization 60 02-Apr-19 26-Jun-19

JED-0600 Substantial Completion 0 26-Jun-19

Warranty Review sWarranty Review s 197 20-Sep-19 29-Jun-20

.. 197 20-Sep-19 29-Jun-20

CON-2840 Quarterly Warranty Review #1 2 20-Sep-19 24-Sep-19

CON-2850 Quarterly Warranty Review #2 2 16-Dec-19 18-Dec-19

CON-2860 Quarterly Warranty Review #3 2 11-Mar-20 13-Mar-20

CON-2870 1 Year Warranty Review 2 25-Jun-20 29-Jun-20

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

2019 2

NE Wall-Form/Place New Retaining Wall & Mow Strip (after crane demob)

NE Wall-Grading & Landscaping

NE Wall-Sump Pump Piping Daylighting

NE Wall-Grading & Landscaping (after crane demob)

E Plaza. North Half-Slab on Grade

E Plaza. South Half-Slab on Grade

N Plaza-Slab on Grade/Fill Exist Vent Shaft

SE Wall-Form/Place Ftgs/New Retaining Wall

SW Wall-Demo Retaining Walls

SW Wall-Form/Place New Retaining Wall & Mow Strip

SW Wall-Grading & Landscaping

SW Wall-Sump Pump Piping Daylighting

NW Wall-Demo Retaining Walls

NW Wall-Form/Place New Retaining Wall & Mow Strip

NW Wall-Grading & Landscaping

NW Wall-Sump Pump Piping Daylighting

Base Job Demobillization

Substantial Completion

Quarterly Warranty Review #1

Quarterly War

Remaining Construction

Data Date: 14-Jan-19

Run Date: 22-Jan-19; 08:31

Oklahoma State Capitol Exterior Renovation

Page 4 of 4