![Page 1: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/1.jpg)
Continual Improvement Your Way!
Taking Your Team To New Heights With Kanban
For the Project Management Institute Heartland Chapter
![Page 2: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/2.jpg)
It’s Great To Meet You!
• @ Work
2 07/15/2014 Continual Improvement Your Way! - Kanban
![Page 3: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/3.jpg)
Continual Improvement Your Way! Taking Your Team To New Heights
• Kanban
– What?
– Why?
– How?
– Project Management
– Remaining Questions?
07/15/2014 3 Continual Improvement Your Way! - Kanban
![Page 4: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/4.jpg)
Kanban – What Is It?
07/15/2014 Continual Improvement Your Way! - Kanban 4
Let me tell you a story….
Tripadvisor.com
Imperialgardens.com.au
![Page 5: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/5.jpg)
What Is It?
07/15/2014 Continual Improvement Your Way! - Kanban 5
dallisonlee.com
No Focus
• Longer • More expensive • More errors • More stressful
![Page 6: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/6.jpg)
What Is It?
07/15/2014 Continual Improvement Your Way! - Kanban 6
Liveyourlegend.com
• Faster • Cheaper • Higher quality • Sense of
achievement • Happier
Amazing Focus
![Page 7: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/7.jpg)
What Is It?
Kanban Helps Us Focus And Finish
07/15/2014 Continual Improvement Your Way! - Kanban 7
![Page 8: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/8.jpg)
What Is It?
• A very visual value-delivery system:
– Workload management
– Project management
– All work
– Faster
– Better
– Happier
– Total respect
07/15/2014 Continual Improvement Your Way! - Kanban 8
![Page 9: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/9.jpg)
What Is It?
Kanban’s History In-Brief
07/15/2014 Continual Improvement Your Way! - Kanban 9
toyota.eu
agilistapm.com
Manufacturing
Knowledge-Work
![Page 10: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/10.jpg)
What Is It? What Does Kanban Look Like?
07/15/2014 Continual Improvement Your Way! - Kanban 10
Jeff Patton
![Page 11: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/11.jpg)
Kanban – What Is It?
• It’s Agile, But One Of Many!
07/15/2014 11 Continual Improvement Your Way! - Kanban
![Page 12: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/12.jpg)
Kanban – What Is It?
• It’s Very Adaptive!
07/15/2014 12 Continual Improvement Your Way! - Kanban
![Page 13: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/13.jpg)
Kanban – What Is It?
• It’s Lean In A Big Way!!
07/15/2014 13 Continual Improvement Your Way! - Kanban
![Page 14: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/14.jpg)
Kanban – What Is It?
• A Pull System!
• Pulling Work In
07/15/2014 14 Continual Improvement Your Way! - Kanban
Ozarksfirst.com
![Page 15: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/15.jpg)
Kanban – What Is It?
• It’s Culture!
•Cross-Functional Teams
•Versatilists, Flexibility
•Continual Improvement
•Servant Leadership
07/15/2014 15 Continual Improvement Your Way! - Kanban
![Page 16: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/16.jpg)
Kanban – What Is It?
An Agile, Lean, Adaptive Way To Managing Work And Delivering Value
(Focus & Finish)
07/15/2014 16 Continual Improvement Your Way! - Kanban
![Page 17: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/17.jpg)
Kanban – Why?
• Bottom Line:
– Increase through-put, optimal team performance
– Faster, better, cheaper
– Great team dynamics
– Appropriate self-direction
– Amazing quality – technical excellence
07/15/2014 17 Continual Improvement Your Way! - Kanban
![Page 18: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/18.jpg)
Kanban – Why?
• At The Team Level, I Can:
– Contribute wholly
– See bottlenecks before they reduce flow
– Minimize blockers
– Collaborate in real-time
– FOCUS!
07/15/2014 18 Continual Improvement Your Way! - Kanban
![Page 19: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/19.jpg)
Kanban – How?
• Three Must-Have Rules:
1. Visualize
2. Limit WIP
3. Manage flow
• Start By:
– Visualizing current work
• Progressively lean-out the process to:
– Limit WIP
– Manage flow (measure, continuously improve)
Maturity
07/15/2014 19 Continual Improvement Your Way! - Kanban
![Page 20: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/20.jpg)
Rule #1 - Visualize
Existing Process
Work In Progress Limits
Available capacity
Predictability
Work item
Notice Something
Cool?
07/15/2014 20 Continual Improvement Your Way! - Kanban
Jeff Patton
What About This?
![Page 21: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/21.jpg)
Rule #1 - Visualize
• All Work!
– Work-Item Types (Projects, Compliance, S/S)
– Routine rotations
– Anything that requires capacity
– Production issues
• Classify work appropriately
– Class of Service (special treatment)
• Expedite, Fixed-Date, Process Improvement
07/15/2014 21 Continual Improvement Your Way! - Kanban
![Page 22: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/22.jpg)
Rule #1 - Visualize
• The Work-Item ticket has it all!
07/15/2014 22 Continual Improvement Your Way! - Kanban
看板
Visual Card or Sign Board
![Page 23: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/23.jpg)
Time-Out
What is the biggest mistake many new Kanban teams make?
07/15/2014 Continual Improvement Your Way! - Kanban 23
![Page 24: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/24.jpg)
Rule #2 - Limit WIP
• Less Multi-Tasking
– Ideal
– Good target
• Limit each queue (WIP Limits)
– # of Work-Items (best)
– Story-Points (as a start only)
• Initially WIP Limits are _______!
• Requires execution, team practice
07/15/2014 24 Continual Improvement Your Way! - Kanban
![Page 25: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/25.jpg)
Rule #2 - Limit WIP
Capacity!
07/15/2014 25 Continual Improvement Your Way! - Kanban
![Page 26: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/26.jpg)
Rule #2 - Limit WIP
• Pull work in when your WIP Limit allows for it
• Pull work in, when you have:
– The capacity to work on it today
– All of the information you need to get started
– Confidence that you can maintain flow
07/15/2014 26 Continual Improvement Your Way! - Kanban
![Page 27: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/27.jpg)
Time-Out
• No capacity – Completely Stuck!
Can’t Pull! Solution?
07/15/2014 27 Continual Improvement Your Way! - Kanban
Beth Schmidt
![Page 28: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/28.jpg)
Rule #3 - Manage Flow
• Critical path, dates, & variances are important, but:
– Kanban teams focus on flow • “Do I have maximum flow today?”
– “Or am I stuck, blocked?”
• By focusing on flow, we often meet/exceed our target dates and increase our quality
07/15/2014 Continual Improvement Your Way! - Kanban 28
![Page 29: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/29.jpg)
Rule #3 - Manage Flow
• Flow is measured by managing:
– Lead Time (customer perspective)
– Cycle Times (any two points)
– Overall Through-Put
• And Adapting:
– Process improvements
– Lean-out eliminate waste
– WIP Limits (“finish” focus**)
07/15/2014 29 Continual Improvement Your Way! - Kanban
![Page 30: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/30.jpg)
Rule #3 - Manage Flow
07/15/2014 Continual Improvement Your Way! - Kanban 30
Lead Time Example
Cycle Time Example
![Page 31: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/31.jpg)
Rule #3 - Manage Flow
• Focus on
– Blockers: Obstacles, issues, low flow
– Bottlenecks: Queues that are stuck
• Throttle WIP Limits
– Increase through-put, flow
– Lower WIP Limits = More Focus
07/15/2014 31 Continual Improvement Your Way! - Kanban
![Page 32: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/32.jpg)
Rule #3 - Manage Flow Focus on Blockers
07/15/2014 Continual Improvement Your Way! - Kanban 32
Resource not available!
Knowledge gap!
Visualize Track Impact Eliminate
![Page 33: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/33.jpg)
Rule #3 - Manage Flow Focus on Blockers
• Eliminating the chance of a blocker recurring:
– Helps the team improve
– Increases flow
– Increases focus
07/15/2014 Continual Improvement Your Way! - Kanban 33
![Page 34: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/34.jpg)
Rule #3 - Manage Flow
• The Kanban Stand-Up
– Right-to-Left (don’t Scrum it)
– One question: ‘Any Blockers?’
– Meaningful Pull
07/15/2014 34 Continual Improvement Your Way! - Kanban
![Page 35: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/35.jpg)
Kanban & Project Management
• PM happens in a really neat way:
– Leadership at all levels
– C&C is out. Use only to:
• Ensure business objectives are met
• Maintain integrity of process
– Servant Leadership:
• “How can i help you today?”
• Active listening – really listen
– THE TEAM
07/15/2014 Continual Improvement Your Way! - Kanban 35
![Page 36: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/36.jpg)
Kanban & Project Management
• PM activities are best split: – (What, Scope, Why, & When) Product Ownership:
• PO owns leading work and the Input Queue • Manages stakeholder expectations
– (Process) Try a Scrum Master approach: • SM owns Kanban process integrity • Facilitates blocker elimination • Serves the team
– (How & When) Team Member: • All-in • Pulls work in, instead of being assigned work
– Honest (“I have capacity today”)
• Knows expected and current lead time, cycle times • Holds other team members accountable • Focuses on finish
07/15/2014 Continual Improvement Your Way! - Kanban 36
![Page 37: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/37.jpg)
Planned Improvement Cycles
• Frequent Retrospectives & Goal Setting
07/15/2014 Continual Improvement Your Way! - Kanban 37
Kanban Maturity
![Page 38: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/38.jpg)
Planned Improvement Cycles
07/15/2014 Continual Improvement Your Way! - Kanban 38
• Frequent Retrospectives & Goal Setting
![Page 39: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/39.jpg)
Make It Your Own!
• Team differences are great!
• Consider a multi-board system But stick to the 3
rules
07/15/2014 39 Continual Improvement Your Way! - Kanban
![Page 40: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/40.jpg)
To Sum It Up
• A tool….faster, better, cheaper, happier
• Easy to start….results are not immediate
• Try it
• Continuously improve over time
07/15/2014 Continual Improvement Your Way! - Kanban 40
![Page 41: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/41.jpg)
Other Questions? Thoughts?
07/15/2014 41 Continual Improvement Your Way! - Kanban
![Page 42: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/42.jpg)
Kanban Resources
• Leading Kanban Book:
– Kanban, Successful Evolutionary Change for Your Technology Business
– David J. Anderson
• Kanban Board Game:
– getkanban.com
• Limited WIP Society:
– limitedwipsociety.ning.com
07/15/2014 42 Continual Improvement Your Way! - Kanban
![Page 43: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/43.jpg)
One More Resource
PMI Heartland Advanced Education Series
Kanban Workshop – July 22nd
7 PDUs
Learn How To Get Started Kanban Planning Checklist
Kanban Setup Guide
Register on pmiheartland.org
07/15/2014 Continual Improvement Your Way! - Kanban 43
![Page 44: Continual Improvement Your Way! - pmiheartland.org · 2. Limit WIP 3. Manage flow •Start By: –Visualizing current work •Progressively lean-out the process to: –Limit WIP –Manage](https://reader035.vdocument.in/reader035/viewer/2022071218/6052e61afa22125bf4537c2f/html5/thumbnails/44.jpg)
Continual Improvement Your Way! Nikitas Kalantjakos
• I am honored that you have made the time and that you have given me this opportunity to share with you.
07/15/2014 44 Continual Improvement Your Way! - Kanban