contract 3713p design-build for the works yard dispersal ... · contract 3713p design-build for the...

70
2714939 City of Richmond Business & Financial Services Department Request for Proposal Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction The City of Richmond is soliciting design-build proposals for the expansion to the Works Yard Dispersal building (the “Expansion”). The Expansion shall utilize modular building units. The objective of this Request for Proposal (RFP) is to provide the City with qualified proponents capable of carrying out the work herein defined. The subsequent proponent submissions will form the basis for evaluation and selection. 2. Submission Details Four (4) copies of proposals marked “3709P Design-build for the Works Yard Dispersal Expansion” addressed to the Purchasing Section, will be received at the Information Counter, Main Floor, Richmond City Hall, 6911 No. 3 Road, Richmond BC V6Y 2C1, until 2:00 PM, Local Time on Thursday, September 24, 2009. Submissions received after this time will be returned to the sender. The City reserves the right to cancel this Request for Proposal for any reason without any liability to any proponent or to waive irregularities at their own discretion. Proposals may be withdrawn by written notice only provided such notice is received at the office of the City’s Purchasing Section prior to the date/time set as the closing time for receiving proposals. Proposals shall be open for acceptance for 90 days following the submission closing date. All proposals will remain confidential, subject to the Freedom of Information and Privacy Act (BC). Except as expressly and specifically permitted in these instructions, no Proponent shall have any claim for any compensation of any kind whatsoever, as a result of participating in the RFP, and by submitting a proposal each proponent shall be deemed to have agreed that it has no claim.

Upload: others

Post on 28-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

2714939

City of Richmond Business & Financial Services Department Request for Proposal

Contract 3713P

Design-Build for the Works Yard Dispersal Expansion 1. Introduction

The City of Richmond is soliciting design-build proposals for the expansion to the Works Yard Dispersal building (the “Expansion”). The Expansion shall utilize modular building units.

The objective of this Request for Proposal (RFP) is to provide the City with qualified proponents capable of carrying out the work herein defined. The subsequent proponent submissions will form the basis for evaluation and selection.

2. Submission Details

Four (4) copies of proposals marked “3709P Design-build for the Works Yard Dispersal Expansion” addressed to the Purchasing Section, will be received at the Information Counter, Main Floor, Richmond City Hall, 6911 No. 3 Road, Richmond BC V6Y 2C1, until 2:00 PM, Local Time on Thursday, September 24, 2009. Submissions received after this time will be returned to the sender.

The City reserves the right to cancel this Request for Proposal for any reason without any liability to any proponent or to waive irregularities at their own discretion.

Proposals may be withdrawn by written notice only provided such notice is received at the office of the City’s Purchasing Section prior to the date/time set as the closing time for receiving proposals.

Proposals shall be open for acceptance for 90 days following the submission closing date.

All proposals will remain confidential, subject to the Freedom of Information and Privacy Act (BC).

Except as expressly and specifically permitted in these instructions, no Proponent shall have any claim for any compensation of any kind whatsoever, as a result of participating in the RFP, and by submitting a proposal each proponent shall be deemed to have agreed that it has no claim.

Page 2: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond 2 Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

3. Enquiries

3.1 Clarification of terms and conditions of the proposal process shall be directed to:

Purchasing Sumita Dosanjh Telephone: 604-276-4097 Buyer II, Contracting Specialist E-mail: [email protected] Purchasing Department City of Richmond 3.2 Technical clarification shall be directed to:

Technical Anthony Fu, EIT Telephone: 604-247-4905 Project Manager E-mail: [email protected] Engineering Design and Construction Any interpretation of, additions to, deletions from, amendments or any other corrections to the Request for Proposal document, will be issued as written addenda by the City of Richmond. It is the sole responsibility of the potential Bidders to check with the City of Richmond’s Website, and / or BC Bid to ensure that all available information has been received prior to submitting a proposal.

The City, its agents and employees shall not be responsible for any information given by way of oral communication.

4. Site Meeting

A site visit is scheduled for Friday, September 11, 2009 at 10:00 am with sign-in attendance forms. Potential Bidders are asked to meet at the Richmond Operations Works Yard, at 5599 Lynas Lane, Richmond, BC. The City strongly encourages all potential Bidders to attend this session. No other sessions will be organised or arranged for this project.

5. Negotiations

5.1 The award of the contract is subject to negotiations with the lead proponent including, but not limited to, the following:

a) Changes or work refinements in the service requirements or proposed scope of work.

b) Price – if directly related to a change or refinement in the proposed scope of work.

5.3 If , in the City’s sole opinion, the agreement cannot be executed by the lead proponent, the City may, at its sole discretion and without liability, immediately terminate all further negotiations and attempts to finalize the agreement with the lead proponent and enter into negotiations with the next qualified proponent or cancel the RFP.

Page 3: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond 3 Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

6. Project Scope

The Expansion consists of:

Base Work (Storm and Sewer Crews Building Units) – Fabrication, delivery and assembly of two (2) modular building units replacing the existing temporary trailer located at the north end of the main dispersal building at the Richmond Operations Works Yard.

Optional Work 1 (Office) – Fabrication, delivery and assembly of an additional modular building unit; quantity (1).

Optional Work 2 (Pumps Crew Building Unit) – Fabrication, delivery and assembly of an additional modular building unit; quantity (1).

Additional Work 1 - Removal of the existing dispersal trailer from the site; quantity (1).

The successful Proponent will design, build, deliver to and install the modular buildings at the site. The approximate location of the site is shown on drawing attached as Appendix I.

Technical Design Criteria

Technical Design Criteria dated August 10, 2009 has been prepared by Stantec Consulting Engineers on behalf of the City and is attached as Appendix II. The Expansion must comply with BC Building Code 2006.

7. Deliverables

The Successful Proponent will provide to the City:

Base Work (Storm and Sewer Crews Building Units) Professionally sealed drawings for building permit application, along with associated

Letters of Assurance. Two (2) modular buildings, designed, delivered and installed as defined by the

Technical Design Criteria. As-built record drawings in AutoCad and Operations and Maintenance Manuals in

digital format.

Optional Work 1 (Office) Professionally sealed drawings for building permit application, along with associated

Letters of Assurance. One (1) modular buildings, designed, delivered and installed as defined by the

Technical Design Criteria. As-built record drawings in AutoCad and Operations and Maintenance Manuals in

digital format.

Page 4: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond 4 Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

Optional Work 2 (Pumps Crew Building Unit) Professionally sealed drawings for building permit application, along with associated

Letters of Assurance. One (1) modular buildings, designed, delivered and installed as defined by the

Technical Design Criteria. As-built record drawings in AutoCad and Operations and Maintenance Manuals in

digital format.

8. Project Schedule

The project is to commence ten (10) working days after Award of Contract. The City requires that the Expansion be completed, delivered and installed without delay. The proponent is required to submit a detailed anticipated project schedule as part of their submission.

9. Permits and Bylaws

The Successful Proponent shall comply with all laws, regulations and building codes relating to the work, whether Federal, Provincial, or municipal, and all established standards and engineering practices. The Successful Proponent shall pay for all permits, licenses and certificates required in respect of the work, with the exception of the Building Permit, which will be paid by the City. Design must conform to the Occupational Environment Regulations of the WorkSafeBC and meet the operational requirements of the City.

10. Indemnification and Insurance

The Successful Proponent will indemnify, hold and save harmless the City from and against all claims, losses, damages, costs, actions and other proceedings, made, sustained, brought or prosecuted in manner, based upon, occasioned by attributable to any injury, including death, property damage, infringement or damage arising from any act or omission of the Successful Proponent, his employees, officers, volunteers, servants or agents or persons from whom the Successful Proponent has assumed responsibility in the performance or purported performance of this agreement.

11. Warranty

Unless otherwise specified, the Successful Proponent warrants that in the manufacture of the supplies only the best workmanship and materials have been employed and if, within a period of one (1) year from the date of acceptance of the supplies by the City, such supplies or any portion thereof are found by the City to be defective or faulty due to imperfect or bad workmanship or material, the Successful Proponent agrees, to replace such defective supplies forthwith without expense to the City.

Page 5: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond 5 Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

12. Patent Fees

The Successful Proponent shall pay all royalties and licence fees and shall save the City harmless from loss on account of suits or claims of infringement of patents in the doing of the work.

13. Proposal Submissions

All proponents are required to provide the following information with their submissions, and in the order that follows:

A Corporate profile of their firm outlining its history, philosophy and target market.

A detailed listing of modular building design and construction experience.

A description of the Proponent’s understanding of the project objectives/outcomes and vision, and how these achieve the Technical Design Criteria.

Team Composition – a complete listing of all key personnel who will be assigned to this project. This will include their relevant experience, qualifications for this project, roles and responsibilities, leadership, etc., in addition to their availability for this project.

A detailed project methodology explaining each project task including what will be expected of both the consultant and the City with respect to each task.

An overall layout of their proposed design including:

rough elevation drawings; dimensions, and materials to be used.

A detailed project schedule of all activities, including milestones, project meetings, any interim reports and progress reports required for this project. This schedule must indicate the time required for producing final design drawings for building permit application, and the time required for fabrication off-site, removal of existing temporary trailer, and assembly and installation of the new modular building units on site. Building permit application reviews for this type of project typically take approximately two (2) weeks depending upon any issues indicated by the review.

A detailed proposal of what will be delivered, including the expected outcome and benefits to the City of Richmond.

Provision of a priced methodology complete with a time allotment for each identified task you propose to employ to carry out the work, this shall form the basis for payments to the successful proponent. Supplement this with a schedule of fees for staff to be assigned to the project. These rates shall be the basis for adjustments to the value of the contract in the event the scope of work varies from that proposed.

Page 6: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond 6 Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

Final summary of prices for base work, optional works, etc. should be presented as follows:

ITEM DESCRIPTION AMOUNT

PRICE A Base Work - Storm and Sanitary Crew Modular Building Units

$__________

PRICE B Optional Work 1 - Office Modular Building Unit $__________

PRICE C Optional Work 2 - Pumps Crew Modular Building Unit $__________

CREDIT Additional Work 1 - Credit for the removal of existing temporary trailer

$__________

TOTAL $__________ A minimum of three (3) client references from projects of a similar size and scope.

14. Working Agreement

The successful proponent will enter into a contract for services with the City based upon the information contained in this request for proposal and the successful proponents submission and any modifications thereto. The Form of Contract will be CCDC2. City of Richmond Supplemental Conditions are attached as Appendix III.

15. Evaluation Criteria

Proposals shall be evaluated to determine the best value offered to the City against conformance to the following criteria:

Understanding of project objectives/outcomes and methodology. Project Schedule. Team Composition – Experience and Qualifications of those staff to be assigned

to the project. Project Deliverables. Value for Money. References.

Page 7: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

2714939

City of Richmond

Business & Financial Services Department Notice of No Bid

Note: Receipt of this completed form will assist us in calling for future bids. Please complete

and submit this form prior to the closing date and time as shown on the Request for Quotation/Proposal/Tender form. Please remember to include Quotation/Proposal/Tender No. at right.

Quotation/Proposal/Tender No.

3713P A Quotation/Proposal/Tender is not being submitted for the following reason(s):

We do not manufacture/supply the required goods/services

Cannot obtain raw materials/goods in time to meet delivery requirements

We do not manufacture/supply to stated specifications Cannot meet delivery requirements

Specifications are not sufficiently defined Cannot quote/tender a firm price at this time

Insufficient information to prepare quote/proposal/tender Insufficient time to prepare quote/tender.

Quantity too small We are unable to competitively quote/tender at this time.

Quantity too large We do not have facilities to handle this requirement

Quantity beyond our production capacity Licensing restrictions (please explain)

Cannot meet packaging requirements Agreements with distributors/dealers do not permit us to sell directly.

Cannot handle due to present plant loading Other reasons or additional comments (please explain below)

I / We wish to quote / tender on similar goods / services in future

Yes No

Authorized Company Official – Signature and Title Date

Firm Name

Address

City

Province Postal Code

This space for City of Richmond Comments

Telephone Number

Page 8: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

Appendix I – Drawing

Page 9: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract
Page 10: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

Appendix II – Technical Design Criteria

Page 11: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond Public Works Yard Dispersal Expansion Request For Proposals Technical Design Criteria

City of Richmond Public Works Yard 5599 Lynas Lane Richmond, British Columbia 114501313

August 10, 2009

Page 12: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA

i

Table of Contents

1.0 FUNCTIONAL REQUIREMENTS..........................................................................................1 1.1 GENERAL BUILDING PLANNING PRINCIPLES ..................................................................1

1.1.1 Summary of Requirements .....................................................................................1 1.1.2 Relationships / Functionality ...................................................................................2 1.1.3 Site Related Relationships......................................................................................2 1.1.4 Construction Related Issues and Relationships .....................................................2 1.1.5 Conceptual Relationships .......................................................................................3 1.1.6 Millwork in contract .................................................................................................4 1.1.7 Not in contract.........................................................................................................4

2.0 ARCHITECTURAL DESIGN CRITERIA ...............................................................................5 2.1 BUILDING CODE SUMMARY ...............................................................................................5

2.1.1 Standards................................................................................................................5 2.1.2 Building data ...........................................................................................................5 2.1.3 Major Occupancy ....................................................................................................5 2.1.4 Construction............................................................................................................5

2.2 EXTERIOR WALLS ...............................................................................................................5 2.3 EXTERIOR WINDOWS .........................................................................................................5 2.4 PLATFORM / RAMPS / STAIRS............................................................................................6 2.5 ROOF SYSTEM.....................................................................................................................6 2.6 DOORS 6 2.7 FLOOR FINISHES.................................................................................................................6 2.8 INTERIOR PARTITIONS .......................................................................................................6 2.9 CEILINGS ..............................................................................................................................7 2.10 MILLWORK............................................................................................................................7 2.11 RODENT CONTROL .............................................................................................................7

3.0 STRUCTURAL DESIGN CRITERIA......................................................................................8 3.1 GENERAL DESIGN REQUIREMENTS .................................................................................8 3.2 DESIGN LOADS AND SERVICEABILITY REQUIREMENTS ...............................................8 3.3 FOUNDATIONS.....................................................................................................................9

4.0 MECHANICAL DESIGN CRITERIA ....................................................................................10 4.1 GENERAL DESIGN REQUIREMENTS ...............................................................................10 4.2 REGULATIONS AND STANDARDS ...................................................................................10 4.3 BUILDING DESCRIPTION ..................................................................................................10 4.4 CLIMATIC DESIGN CONDITIONS AND DESIGN CRITERIA.............................................10 4.5 HEATING (TYPICAL FOR ALL SPACES) ...........................................................................11 4.6 COOLING (OFFICE MODULE ONLY).................................................................................11 4.7 VENTILATION .....................................................................................................................11 4.8 PLUMBING ..........................................................................................................................12

Page 13: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Table of Contents

ii

4.8.1 Plumbing Systems ................................................................................................12 4.8.2 Plumbing Systems ................................................................................................12

4.9 DOMESTIC COLD WATER.................................................................................................12 4.10 DOMESTIC HOT WATER SYSTEM....................................................................................13 4.11 SANITARY WASTE SYSTEM .............................................................................................13 4.12 STORM DRAINAGE SYSTEM ............................................................................................13 4.13 FIRE SUPPRESSION..........................................................................................................14

5.0 ELECTRICAL DESIGN CRITERIA .....................................................................................15 5.1 GENERAL DESIGN REQUIREMENTS ...............................................................................15 5.2 REGULATIONS AND STANDARDS ...................................................................................15 5.3 UTILITY SERVICES ............................................................................................................15 5.4 POWER DISTRIBUTION.....................................................................................................15 5.5 RECEPTACLES AND POWER OUTLETS..........................................................................16 5.6 LIGHTING AND LIGHTING CONTROLS ............................................................................16 5.7 EMERGENCY LIGHTING AND EXIT SIGNS ......................................................................17 5.8 FIRE ALARM .......................................................................................................................17 5.9 TELECOMMUNICATION SYSTEM .....................................................................................17 5.10 GENERAL INSTALLATION REQUIREMENTS ...................................................................17 5.11 DATA / NETWORK SYSTEM ..............................................................................................17

6.0 SITE DEVELOPMENT, SITE WORKS AND SITE SERVICING .........................................18 6.1 EXISTING ASHPHALT ........................................................................................................18 6.2 WORK BY OTHERS............................................................................................................18 APPENDIX A – FLOOR PLAN DRAWING

Page 14: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 1

1.0 Functional Requirements

At the City of Richmond Public Works Yard, located at 5599 Lynas Lane, Richmond British Columbia, the Storm, Sanitary and Pumps crews are dispersed from a temporary trailer. A larger modular dispersal building is required to accommodate these three crews. Functional spaces required include offices and dispersal/lunch areas for each 18-25 person crew. The temporary trailer will then removed and credited by the contractor.

As a result of these requirements, the following is required:

Dispersal Building Expansion (the “Work”):

• Modular dispersal building comprised of 4 units (total approximate area 250 m2)

• Removal of the temporary trailer currently located adjacent to the existing main dispersal building.

1.1 GENERAL BUILDING PLANNING PRINCIPLES

1.1.1 Summary of Requirements

Program areas that satisfy Richmond Public Works Yard (RPWY) requirements to disperse the Storm, Sanitary and Pump crews from a new building located in the City of Richmond Public Works yard is summarized in Table 1-1

Seria

l

Description

Sum

mer

O

ccup

ancy

Win

ter

Occ

upan

cy

Proposed Area (m²)

1 Office 6 6 61.5 2 Pumps Crews 25 20 61.5 3 Storm Crew 25 18 61.5 4 Sanitary Crew 25 18 61.5 Subtotal Net Area 246 Approximate Gross Up

Factor (15%) 36.9

Total Gross Building Area 282.9

Table 1-1

• Net area requirements for the building, excluding Design and Mechanical/Service space, shall be considered a minimum requirement for each space, and for the building as a whole.

Page 15: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Functional Requirements August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 2

• Staff will use shower rooms in the existing main dispersal building

o Women’s locker room / showers are located in the Existing Female Dispersal Washroom Building

o Men’s showers are located in the Existing Main Dispersal building

• Crews occasionally eat lunch in trailers

1.1.2 Relationships / Functionality

• Three crew areas are to be adjacent to each other

• Office area to be adjacent to crew area, and closest to existing main dispersal building.

• Crews will arrive, dress and disperse before shift start. Occasionally crew members will return to eat lunch mid-shift. At the end of shift, crew members prepare paper work and leave at 4PM

1.1.3 Site Related Relationships

• Provide direct exterior man door access from each crew area

• No internal access between functional spaces required

• No additional parking stalls required

• No landscaping required

• No fencing required

• Pedestrian access path from expansion to existing main dispersal building

• Adjacent to existing main dispersal building (lockers area and dispersal for Park, Roads, Water and Fleet crews)

1.1.4 Construction Related Issues and Relationships

• Maintain existing main dispersal building operations throughout construction

• Minimize Storm, Sanitary and Pumps dispersal crew operations disruption

• Lay down area to be confirmed with City of Richmond Public Works prior to construction start (including access, extents of lay down area)

Page 16: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Functional Requirements August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 3

1.1.5 Conceptual Relationships

Conceptual relationships that satisfy RPWY requirements to disperse the Storm, Sanitary and Pump crews from a new building located in the City of Richmond Public Works Yard are shown in Figure 1-1

Pumps Crew Dispersal

Sanitary Crews Dispersal

Storm Crew Dispersal

Offices

Existing Main Dispersal Building

Figure 1-1

Page 17: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Functional Requirements August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 4

1.1.6 Millwork in contract

Wash sink cabinet

Microwave stand

Stationery / Forms boards

Bulletin boards

1.1.7 Not in contract

Work stations

Computer stations

Microwaves

Chairs

Lockers

Tables

Benches

Building signage

Page 18: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Architectural Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 5

2.0 Architectural Design Criteria

2.1 BUILDING CODE SUMMARY

2.1.1 Standards

British Columbia Building Code of Canada (BCBC) 2006, division B, part 9

2.1.2 Building data

Building Area: 246 m2

Building Height: 1 storey

2.1.3 Major Occupancy

Group D, Business and personal services

2.1.4 Construction

Article 3.2.2.55. Group 2 up to 2 storeys

Combustible or non-combustible construction used singly or in combination. Load bearing walls and columns supporting an assembly required to have a fire-resistance rating not less than 45 minute.

2.2 EXTERIOR WALLS

The building envelope will consist of exterior pre-finished metal cladding (rain screen wall system) supported by wood frame construction or other structural system with R-15 average insulation value for the wall. Interior finish of exterior walls in the office and lockers area will be either painted gypsum wall board on a 25mm cavity with a minimum of 75mm semi-rigid or foam insulation applied over a waterproof membrane.

2.3 EXTERIOR WINDOWS

Exterior windows are to be operable, energy efficient type with double-glazing and low-e coating installed in thermally broken aluminum frames. Glazing will be provided in functional spaces that benefit from natural lighting for both operational and user requirements. Clerestory may be used near lockers.

Page 19: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Architectural Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 6

2.4 PLATFORM / RAMPS / STAIRS

Platform and ramps to be of treated tongue and groove wood construction supported on treated wood posts maximum spacing 2500mm on centres and treated wood beams and joists as required.

Ramps to have a minimum slope of 1:10 and minimum clear distance of 915mm as per sentence 3.4.6.6 (5) and table 3.4.6.A of British Columbia Building Code 2006.

Stairs to be treated wood stringers attached to beams on the upper end and concrete footings. Treads and risers to be built of treated wood lumber.

A 38mm diameter painted steel guardrail at 1070mm above finished floor, a 38mm diameter painted steel handrail at 960mm above finished floor or edge of nosing supported on 38mm diameter painted steel posts at maximum 1500mm on centres, with 16mm X 16mm balustrades at 100mm OC welded to upper handrail and guardrail and a 38 mm painted steel lower rail placed 100mm above finished floor or edge of nosing.

All platform, ramps and stairs to be painted

2.5 ROOF SYSTEM

Roofing for the facility will be EPDM membrane type on flat roofs. Roofing membrane will be installed over rigid insulation with an insulation value of minimum R-30 on an air/vapour barrier on deck sheathing over structural deck. Overflow drains or roof scuppers are to be provided for all flat roofs.

2.6 DOORS

Exterior doors will be insulated hollow metal in pressed steel and thermally broken frames. Interior doors are to be painted hollow metal type with honeycomb cores in metal frames. All doors to have kick plates. Door hardware is to be medium duty. Lock specification by City of Richmond.

2.7 FLOOR FINISHES

Flooring will be industrial grade sheet vinyl with rubber cove base.

2.8 INTERIOR PARTITIONS

Interior walls are painted gypsum wall board (Latex G3 finish).

Page 20: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Architectural Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 7

2.9 CEILINGS

Ceiling will be suspended acoustic tile and in washroom areas will be epoxy or alkyd painted suspended gypsum board ceilings. Ceiling height will be 2750mm.

2.10 MILLWORK

Kitchenette millwork is to be provided to standard AWMACC grade with plastic laminate.

2.11 RODENT CONTROL

A 200mm wide 600mm deep skirting / curb embedded 300mm in the ground to be built all around the perimeter of the building to deter rodents.

Page 21: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Structural Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 8

3.0 Structural Design Criteria

3.1 GENERAL DESIGN REQUIREMENTS

Structural design and documentation shall conform to the requirements of the 2006 British Columbia building code (2006 BCBC), applicable CSA material standards and municipal bylaws.

The structural design, documentation and contract administration shall be carried out under the direct supervision of the Structural Engineer of Record in accordance with the requirements of the BCBC 2006 and “Guidelines for Structural Engineering Services for Building Projects” by the Association of Professional Engineers and Geoscientists of British Columbia (APEGBC)

The Structural Engineer of Record (SER) shall be a professional engineer registered in the Province of British Columbia.

The SER shall ensure that an independent concept review has been completed prior to the submission for building permit.

A geotechnical investigation shall be carried out under the direct supervision of a professional engineer registered in the province of British Columbia.

Modular Structure to be portable and able to be relocated in future.

3.2 DESIGN LOADS AND SERVICEABILITY REQUIREMENTS

The structure shall be designed for the loads appropriate for the occupancy and climatic conditions. The loads shall satisfy the minimum loading and serviceability requirements for the 2006 BCBC. The Importance Category of the building is “Normal”.

The following minimum floor and roof loads shall apply:

Floor: 4.8 kPa

Roof: 1.0 kPa or snow load (whichever is greater)

The following deflection limits shall apply:

Floor: L/360 for live load

L/240 for long-term dead plus live load

Roof: L/360 for live load

Page 22: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Structural Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 9

The following storey drift limitations shall apply:

Wind: L/500

Seismic: L/50

3.3 FOUNDATIONS

A geotechnical investigation carried out under the direct supervision of a professional engineer registered in the province of British Columbia is required.

Post construction differential settlements shall be limited to ¾ inch over a distance of 25 feet and overall total settlement shall be limited to 2 inches.

Previous soils investigation close to the proposed site indicates the soils to be liquefiable (site class F) and a Dynamic Site Response Analysis is required to provide Site Coefficients (Fa and Fv). A raft foundation is recommended to meet the code requirements and settlement limitations. Preloading may be required if modular building structure can not accommodate these settlements.

Page 23: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 10

4.0 Mechanical Design Criteria

4.1 GENERAL DESIGN REQUIREMENTS

The intent of this section is to outline the design criteria for the mechanical systems of the proposed building modules. These systems include the heating, ventilating and air conditioning (HVAC), plumbing and fire protection systems and will be further developed into final design through the “design-build” process. This section should be read in conjunction with the Architectural, Civil, Structural and Electrical sections of this document.

4.2 REGULATIONS AND STANDARDS

The mechanical systems will be designed and installed by following principles of good engineering practice and by meeting or exceeding requirements of applicable codes and standards currently in effect, including but not limited to the following:

British Columbia Building Code – 2006 (BCBC)

Division B - Part 3 – Section 3.7. Health Requirements

Division B - Part 6 – Heating, Ventilating and Air-conditioning

Division B - Part 9 – Section 9.10. Fire Protection

British Columbia Fire Code – 2006 (BCFC)

City of Richmond Bylaw No. 8306, Fire Protection and Life Safety – 2008-07-14

American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE)

ASHRAE 62.1-2007, Ventilation for Acceptable Indoor Air Quality

ASHRAE 90.1-2007, Energy Standard for Buildings Except Low-Rise Residential Buildings

4.3 BUILDING DESCRIPTION

Refer to Part 1 of this RFP Technical Design Criteria.

4.4 CLIMATIC DESIGN CONDITIONS AND DESIGN CRITERIA

The climatic design data and the design indoor conditions for the building are summarized below:

Page 24: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 11

Outdoor Design Conditions:

Winter Design Temperature (occurs 1% of the time):

Dry Bulb -9°C

Summer Design Temperature (occurs 2.5% of the time):

Dry Bulb 27°C (DB)

Wet Bulb 19°C (WB)

Indoor Design Conditions:

Office Module (summer): 24°C

Sanitary, Storm and Pumps (summer): Not controlled

All areas (winter): 22°C

4.5 HEATING (TYPICAL FOR ALL SPACES)

Provide the following:

Electric heaters to maintain space temperature, based on the maximum ventilation load in winter.

Individual wall mounted thermostats with local adjustment.

4.6 COOLING (OFFICE MODULE ONLY)

Provide an electric air-source heat pump for all-seasons air conditioning (heating/cooling) of the office module only. Control will be by means of a wall-mounted electronic user programmable thermostat. Equipment and controls to be fully compatible one with the other and from a single manufacturer. Where baseboard electric heater(s) are provided for space heating in the same space as the heat pump, provide an automatic lock-out provision within the thermostat to prevent simultaneous heating and cooling. Energy efficiency of the heat pump unit shall meet or exceed the latest requirements of ASHRAE 90.1-2007.

4.7 VENTILATION

Provide mechanical ventilation in accordance with BCBC Section 6.2.2. for each (room) module. Minimum fresh air volumetric flow rate shall be maintained during all occupied periods in conformance with the requirements ASHRAE 62.1-2007. Mechanical exhaust shall be provided in the following areas:

Page 25: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 12

Locker/dressing room area within each (room) module (continuous)

Provide energy recovery ventilators as appropriate.

4.8 PLUMBING

Provide plumbing and drainage conforming to the requirements of BCBC Section 3.7.2. - Plumbing Facilities.

4.8.1 Plumbing Systems

The plumbing systems include:

Sanitary Waste system

Plumbing Fixtures and Trim

Domestic Cold Water System

Domestic Hot Water Supply

4.8.2 Plumbing Systems

Provide the following fixtures:

Shallow, single compartment stainless steel sinks

Low flow single lever sink faucets.

Hose bib on the outside of the Office module

4.9 DOMESTIC COLD WATER

Domestic cold water will be provided by a common connection to the existing Main Dispersal Building. Provide a mains connection point; protect from freezing. Provide shut -off valves at the mains connection point and at every branch line from the primary piped supply and at each plumbing fixture. The domestic cold water mains connection shall be located near the South-west corner of the structure (see Architectural plan) and shall extend 610 mm beyond the face of the structure. Owner will connect the cold water mains supply to the common domestic cold water inlet connection at the point of termination (see 6.2 below). The domestic cold connection water connection shall have a maintained clear space of not less than 910 mm (1200 mm preferred) between it and the common sanitary sewer mains connection (see 4.11 below).

Insulate domestic cold water piping to prevent condensation and winter freeze-up.

Page 26: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 13

Domestic cold water is required for the sinks and outdoor hose bibb.

4.10 DOMESTIC HOT WATER SYSTEM

Domestic hot water will be provided by a common connection to the existing Main Dispersal Building. Provide a mains connection point; protect from freezing. Provide shut -off valves at the mains connection and at every branch line from the primary piped supply and at each plumbing fixture. The domestic hot water mains connection shall be located near the South-west corner of the structure (see Architectural plan) and shall extend 610 mm beyond the face of the structure. Owner will connect the hot water mains supply to the common domestic hot water inlet connection at the point of termination (see 6.2 below). The domestic hot connection water connection shall have a maintained clear space of not less than 910 mm (1200 mm preferred) between it and the common sanitary sewer mains connection (see 4.11 below).

Insulate domestic hot water piping to prevent heat loss and winter freeze-up.

Domestic hot water is required for the sinks

4.11 SANITARY WASTE SYSTEM

Provide sanitary waste and vent piping to all plumbing fixtures. The sanitary system connects by gravity to the site main sanitary sewer. Provide a common sanitary sewer outlet mains connection at the South-west corner of the structure; extend the connection 610 mm beyond the face of the structure (see Architectural plan). Owner will provide for connection of the common sanitary sewer outlet to the site main sanitary sewer (see 6.2 below). The common sanitary sewer outlet shall be separated from the common domestic hot and cold water supply connections of not less than 914 mm clear distance (1200 mm preferred).

Gravity sanitary waste piping will be non-combustible cast iron or copper for above slab interior services.

Readily accessible cleanouts will extend to floor level or will be extended to a wall location in suitable locations for ease of long term maintenance.

4.12 STORM DRAINAGE SYSTEM

Provide storm drain system for the following:

Roof areas of all building (room) modules

Foundations and walkways abutting the buildings.

Conform to the requirements of BCBC Part 9.

Page 27: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 14

Storm runoff shall be diverted to the facility storm drain system or an approved dry well. Direct surface runoff away from foundations and walkways.

4.13 FIRE SUPPRESSION

Provide fire protection in accordance with BCBC and BCFC. Provide an approved fire extinguisher in each building (room) module in accordance with BCBC § 9.10.20.4. – Portable Fire Extinguishers. Mount on a wall near the location of the microwave oven, accessible to the exit.

Page 28: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Electrical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 15

5.0 Electrical Design Criteria

5.1 GENERAL DESIGN REQUIREMENTS

The intent of this section is to outline the proposed electrical systems criteria at the concept stage of the project. These systems include power distribution, power outlets, lighting layout and telecommunication voice/data outlets and will be further developed into final design through the “design-build” process. This section should be read in conjunction with the Architectural, Civil, Structural and Mechanical sections of this document.

5.2 REGULATIONS AND STANDARDS

The electrical systems will conform to the current application of the Canadian Electrical Code and local standards and regulations. This will be achieved by meeting or exceeding, but not limited, to the following:

1. British Columbia Building Code.

2. CSA C22.1-06, Canadian Electrical Code Part 1 (20th Edition).

3. Canadian Standard Association (CSA International).

4. TIA/EIA-568 Commercial Building Telecommunications Cabling Standard.

5.3 UTILITY SERVICES

No addition electrical service from local utility provider is required for the expansion.

5.4 POWER DISTRIBUTION

The electric power for the expansion will be connected to/supplied from the existing main dispersal building.

• Two new 3P breakers shall be installed at the 347/600V, 3 Phase, 4 Wire panel board in the electrical closet of existing main dispersal building.

• 600-120/208V Δ-Y transformer shall be installed in the electrical closet of existing main dispersal building.

• A 100A, 347/600V, 3 phase, 4 wire lighting panel board and a 100A, 120/208V, 3 phase, 4 wire power panel board shall be installed at corridor or office of the expansion space.

• Spare breakers for each panel board shall be at least 30% of connected circuit numbers and all bussing shall be tinned copper.

• Feeder cable from existing main dispersal building to new panel boards shall be marked as suitable for exposed wiring where exposed to the weather.

Page 29: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Electrical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 16

• Breaker size and transformer size shall be calculated as per related section of CEC Code.

5.5 RECEPTACLES AND POWER OUTLETS

15A general purpose receptacles shall be provided throughout the expansion space. They will be fed from the new installed power panel board. For each office computer work stations, two duplex receptacles shall be provided. Separated circuits are required for high power electrical apparatus, such as microwave, etc. Ground fault circuit interrupter (GFCI) receptacles are required to be installed in washroom as well as counter power outlets within 1.5m to the sink. Convenient receptacles shall be provided in the corridor area. Power shall be provided to the mechanical equipments as per Mech. section.

Additional 15A duplex receptacles shall be provided to suit the refurbished trailer layout.

5.6 LIGHTING AND LIGHTING CONTROLS

A complete lighting system shall be provided for the expansion space. They should be practical for the areas they serve. Lighting circuits will be fed by the new installed lighting panel board installed at the corridor or office in the expansion space. Switching shall be planed to provide the different levels of illumination as dictated by the task, thus reducing the overall energy use.

In summary the following shall be provided:

1. Minimum illuminance shall be as follows;

• All modules: 500 Lux (50 fc)

2. Lighting Fixture shall be as follows;

• Fluorescent type utilizing T8 lamps complete with rapid start electronic ballast for energy efficient, long life and economical usage

• Fixture to have high reflectance reflector and diffuser/louver

3. Switching shall be as follows;

• Line voltage switching will be used throughout.

• Local switches shall control lighting in the respective area.

• Multiple switching arrangements to control individual lighting fixtures, or separate lamps within the lighting fixtures shall be utilized.

• Designated night light will be un-switched.

Page 30: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Electrical Design Criteria August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 17

5.7 EMERGENCY LIGHTING AND EXIT SIGNS

All exit paths/door to exterior shall be equipped with emergency lighting and exit sign. Supplementary battery pack emergency lights will be utilized. Exit sign will be LED type to NFPA 170. Unit shall have minimum life expectancy of 25 years continuous operation.

5.8 FIRE ALARM

Provide fire alarm system as required by the BC Building Code.

5.9 TELECOMMUNICATION SYSTEM

Data/Voice outlets (DVOs) shall be provided throughout the expansion space with minimum one DVO per each workstation. Provide cable tray and conduit system from the existing patch panel in the electrical closet of existing main dispersal building to each DVOs. Cat 5e cabling will be carried out by City of Richmond. The maximum horizontal cable run shall not exceed 90 meters.

Cable trays shall be wire basket type, prefabricated structure with 200mm in width or greater. They should be bonded to telecommunication main ground bus and are coated to prevent rust and galvanic action.

5.10 GENERAL INSTALLATION REQUIREMENTS

1. All building wiring shall be installed in conduits with minimum size of 19mm.

2. Minimum wire sizes are based on the use of copper conductors.

3. Minimum wire size is #12 AWG.

4. Use XLPE RW90 for interior and XLPE RWU90 for exterior wiring.

5.11 DATA / NETWORK SYSTEM

Computer workstation terminals are proposed to be installed in each sanitary, storm, pumps dispersal modules and office module. In addition to the workstation computers, three SCADA terminal computers are proposed, 2 in the office module , and 1 in the pumps module. Provide one quadruplex receptacle and two data drops for each terminal. Install all power systems and data cabling through conduit system. Install all data conduit and boxes including devices and covers. Data cabling to be carried out by City of Richmond. Terminate all data drops back to the patch panel in the existing building. Power circuits shall be routed back to the power panel board at the corridor.

Page 31: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Site Development, Site works and Site Servicing August 10, 2009

lv v:\1145\active\114501313\report\final report\rpwy dispersal expansion rfp technical section_final.doc 18

6.0 Site Development, Site works and Site Servicing

6.1 EXISTING ASHPHALT

Make good existing asphalt and parking stalls after construction

6.2 WORK BY OTHERS

Sanitary, DCW, DHW and Storm water connections by City of Richmond forces

Underground electrical connection

Removal, relocation and reinstallation of lockers

Parking space line painting

Page 32: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

City of Richmond Contract 3713P Request for Proposal Design-build of Works Yard Dispersal Expansion

2714939

Appendix III – City of Richmond Supplementary Conditions to CCDC2

Page 33: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 DRAFT APRIL 29, 2005 2684546

SUPPLEMENTARY GENERAL CONDITIONS For use with CCDC2 1994

These Supplementary General Conditions modify and amend Standard Construction Document CCDC-2 - 1994 and form a part of this Contract. In the event of any conflict between the provisions of the Contract Documents and any provision of these Supplementary General Conditions, these Supplementary General Conditions shall govern.

DEFINITIONS

1. Immediately before the word “amendments” in the second line of paragraph 2, insert “written”.

GENERAL CONDITIONS OF THE CONTRACT

2. In GC 1.1.9.1:

(a) insert “• the Instructions to Tenderers,” immediately after “• the Agreement between the Owner and the Contractor,” and immediately before “• the Definitions”; and

(b) insert “• Tender Form, including all appendices,” immediately after “Supplementary Conditions” and immediately before “• the General Conditions”.

3. In GC 2.2.6, delete the words “, except with respect to GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER” from the second and third lines.

4. In GC 2.2.7, delete the words “, except for GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER,” from the second and third lines.

5. Add the following GC 3.5.2:

“The Contractor will perform the Work in compliance with the construction schedule. If, for any reason, the Work falls behind the schedule for the Work set forth in the construction schedule the Contractor shall as part of the Work either:

(a) if in accordance with the Contract Documents the delay entitles the Contractor to a time extension the Contractor shall forthwith prepare and deliver to the Consultant a revised construction schedule to the reasonable satisfaction of the Consultant indicating the revised dates for the remaining activities of the Work; or

(b) if in accordance with the Contract Documents the delay does not entitle the Contractor to a time extension then the Contractor shall take such steps as required to bring the Work back into conformity with the construction schedule.

Failure to comply with the requirements of this section shall be deemed to be a default under the Contract to which the provisions of GC 7.1.2 apply.”

6. Add Paragraph 3.7.3 as follows:

Page 34: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

2

“Any superintendent, foreman, or other mechanic whose work is unsatisfactory to the Consultant or to whom the Consultant may have a reasonable objection, shall be promptly dismissed from the work up on receipt of written notice from the Consultant.”

7. Add the following at the end of GC 3.8.2:

“The Contractor shall not employ any Subcontractor, or change Subcontractor, without the written approval of the Owner, which approval will not be unreasonably withheld.”

8. Add the following GC 3.9.4:

“Immediately upon receiving from the Consultant a written notice stating the Consultant’s reasonable objection to the work conduct of any superintendent, foreman or worker on the Project site, the Contractor will remove such persons from the Project site.”

9. In GC 3.10, following the words “Contract Documents,” in the first line, insert “reviewed shop drawings,”.

10. Add the following at the end of GC 3.11.4:

“The shop drawings provided by the Contractor will be complete and show the entire extent of the relevant portion of the Work.”

11. Add the following GC 3.11.7:

“Upon Substantial Performance of the Work, the Contractor will submit all reviewed and revised shop drawings to the Owner as a permanent record of the Work. As of the date of issuance of a final certificate for payment, the shop drawings will be retained by the Owner as the Owner’s property.”

12. Add the following GC 3.11.8:

“The Contractor shall not proceed with the Work to which a shop drawing applies before the Consultant has reviewed and approved the shop drawing as provided by GC 3.11.5.”

13. Delete GC 5.1, including all of GC 5.1.1 and GC 5.1.2, in its entirety.

14. Add the following at the end of GC 5.2.2:

“The Contractor will identify separately, with reference to the applicable Change Order, any application for payment for Work performed pursuant to a Change Order. No payment for extras or changes will be made before the issuance of the applicable Change Order.”

15. Delete GC 5.2.6. in its entirety and insert:

“No claim shall be made for any Product which is delivered to the Place of the Work until it is incorporated into the Work and any claim for Products which are

Page 35: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

3

incorporated into the Work shall be supported by such evidence as the Consultant may reasonably require to estimate the value of such Products.”

16. Add the following GC 5.3.3:

“The Owner may set off from payments owing to the Contractor costs, expenses and damages the Owner incurs or suffers as a result of the Contractor’s wrongful or negligent act or omission, or which the Owner incurs on the Contractor’s behalf.”

17. Add the following GC 5.3.4:

“The Owner may, in addition to other holdbacks as provided by the Contract Documents, hold back an amount equal to any lien which has been filed with respect to the Work, plus 10% as security for costs. The Owner may, at its option, after five days written notice to the Contractor, pay such amount into court to discharge the lien. If the lien is discharged without payment of the holdback into court, then the Owner shall pay such holdback to the Contractor, without interest.”

18. Add the following GC 5.4.5:

“In addition to builders lien holdbacks, the Owner may retain holdbacks to cover deficiencies in the Work, in an amount equal to twice the amount the Consultant estimates as the total cost to complete the deficiencies.”

19. Add the following GC 5.4.6:

“The Contractor’s application for Substantial Performance of the Work will constitute a waiver by the Contractor of all claims except those previously made in writing to the Owner.”

20. Delete GC 5.5.3 in its entirety.

21. Add the following GC 5.7.5:

“The Consultant will not issue the final certificate for payment until the Contractor has submitted a release from the Workers Compensation Board covering work of the Contract to completion, plus inspections and approval certificates of all authorities with jurisdiction.”

22. Add the following GC 5.7.6:

“The issuance of a final certificate for payment in no way relieves the Contractor from correcting defects or deficiencies not apparent at the time the certificate is issued.”

23. Add the following GC 6.1.3:

“Whenever the Consultant delivers a written request to the Contractor for a quotation of a possible change, the Contractor will within 10 days after receiving such request provide to the Consultant in writing a quotation of the value of the contemplated change (increase or decrease) and a statement of the effect, if

Page 36: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

4

any, of the contemplated change on the construction schedule. The Contractor’s written quotation and statement will be interpreted to include all costs, including any indirect or “impact” costs, and all effects on the construction schedule. The Contractor will not be entitled to claim on account of any cost or schedule effect not included specifically in the quotation and statement unless the quotation and statement specifically itemize and describe such cost or schedule effect.”

With respect to any change, the allowance for overhead shall be 10% and the allowance for profit shall be 5%, each applied to the cost of the change, (including indirect costs, if any) as described in the previous paragraph, as full payment owing for the change.

24. Add the following at the end of GC 6.5.4:

“No claim for additional payment arising from a delay will be payable to the Contractor unless the Contractor has prepared, or caused to be prepared, records of all Work and the costs of the Work, on a daily basis as the Work proceeds, and submits such records in support of the claim.”

25. Add the following GC 6.5.6:

“The Owner may, at any time, give written direction to the Contractor for the Contractor to accelerate the Work, in which event the Contractor shall use reasonable best efforts to proceed with the Work more quickly, which may include hiring additional labour and equipment and/or working additional hours or shifts. If at the time of such direction by the Owner the Contractor is behind the approved construction schedule due to a cause within the control of the Contractor, then the cost of such acceleration shall be borne by the Contractor. If at such time the Contractor is not behind the construction schedule, or is not behind due to a cause within the Contractor’s control, then the cost of such acceleration shall be for the account of the Owner.”

26. Add the following GC 6.5.7:

“If, for any reason, the Contractor deems it necessary to accelerate the Work, then the Contractor shall provide written notice of its intention to accelerate at least 24 hours prior to doing so.”

27. Add the following GC 6.5.8:

“In the event of a delay which results in a stoppage of the Work, the Contractor shall take all reasonable steps to protect the Work for the entire period of the delay. The cost of such protection shall be paid as follows:

(i) if under 6.5.1, or 6.5.2, the Owner will pay,

(ii) if under 6.5.3 the Contractor will pay.”

28. In GC 7.1.2, delete the words “and if the Consultant has given a written statement to the Owner and Contractor that sufficient cause exists to justify such action” from the second and third lines.

Page 37: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

5

29. Delete GC 7.2.3.1.

30. Delete paragraph 8.2.6 and 8.2.7. and substitute the following:

“If a dispute cannot be resolved by mediation, it shall be referred to a Court having jurisdiction.”

31. In GC 9.2.4, following the word “costs,” in the second line, insert “and posting security in an amount and in a form reasonably satisfactory to the Owner,”.

32. Delete GC 9.3.2.

33. Delete GC 9.3.3.

34. Delete GC 9.3.4.

35. In GC 9.3.5, delete the words “which were not disclosed by the Owner, as required under paragraph 9.3.2, or which were disclosed but have not been dealt with as required under paragraph 9.3.4,”.

36. In GC 9.3.5.3, following the words “stopping the Work” in the first line, insert “if necessary”.

37. Add the following at the end of GC 10.2.1:

“This Contract shall be construed according to the laws of British Columbia. The Contractor will undertake all Work in full compliance with all applicable building, environmental and other laws, including without limitation building codes, regulations and bylaws applicable in the City of Richmond.”

38. In GC 10.2.5, delete the words “knowing it to be” from the second line.

39. Delete GC 10.4 in its entirety and substitute the following:

The Contractor agrees that it will at its own expense procure and carry or cause to be procured and carried and paid for, full Workers' Compensation Board coverage for itself and all workers, employees, servants and others engaged in or upon any work or service which is the subject of this Contract. The Contractor agrees that the City has the unfettered right to set off the amount of the unpaid premiums and assessments for such Workers' Compensation Board coverage against any monies owing by the City to the Contractor. The City will have the right to withhold payment under this Contract until the Workers' Compensation Board premiums, assessments or penalties in respect of work done or service performed in fulfilling this Contract had been paid in full.

The Contractor agrees that it is the Prime Contractor for the purposes of the Workers' Compensation Board Occupational Health and Safety Regulations for the Province of British Columbia. The Contractor will have a safety program acceptable to the Workers' Compensation Board and will ensure that all Workers' Compensation Board safety rules and regulations are observed during performance of this Contract, not only by the Contractor but by all subcontractors, workers, material men and others engaged in the performance of this Contract. Prior to commencement of construction, the Contractor will complete and file a "Construction Notice of Project" with the Workers' Compensation

Page 38: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

6

Board and will provide a copy of the same to the City confirming that the Contractor will be the Prime Contractor responsible for coordination of safety and health under Part 3 of the Workers Compensation Act and Part 20 of the WCB Occupational Health and Safety Regulations.

The Contractor will provide the City with the Contractor's Workers' Compensation Board registration number and a letter from the Workers' Compensation Board confirming that the Contractor is registered in good standing with the Workers' Compensation Board and that all assessments have been paid to the date thereof prior to the City having any obligation to pay monies under this Contract. The Contractor will also provide a signed copy of the Prime Contractor Designation Document.

The Contractor will indemnify the City and hold harmless the City from all manner of claims, demands, costs, losses, penalties and proceedings arising out of or in any way related to unpaid Workers' Compensation Board assessments owing from any person or corporation engaged in the performance of this Contract or arising out of or in any way related to the failure to observe safety rules, regulations and practices of the Workers' Compensation Board, including penalties levied by the Workers' Compensation Board.

40. Delete GC 11.1 in its entirety and substitute the following:

“The Contractor shall, at his own expense, through the terms of the contract secure, maintain, and pay for the following coverage’s:

(a) Wrap-Up Comprehensive Liability Insurance

The Owner shall provide, maintain and pay the premiums for Wrap-Up Comprehensive Liability Insurance. The minimum shall be mutually agreed upon by the Owner and the Construction Manager and shall be inclusive for personal injury (including death) and property damage. The foregoing insurance coverage shall name the Owner and the Construction Manager and all consultants and contractors as additional insureds. The Wrap-Up Comprehensive General Liability Insurance shall be maintained continuously from commencement of the Work until Substantial Performance of the Work and shall cover a further period of 24 months from and after date of Substantial Performance of the Work with respect to completed operations.

(b) “All Risks” Course of Construction Insurance

The Owner shall provide, maintain and pay the premiums for “All Risks” Course of Construction Insurance, insuring the full value of any work in the amount of the Contract Price and the full value, as stated, of products that are specified to be provided by the Owner for incorporation into any Work, to a maximum occurrence limit or as mutually agreed upon by the Owner and the Construction Manager. The policy shall insure against all risks of direct loss or damage consistent with commercial underwriting practice, and will apply to all products, labour and supplies, the property of the insureds or others for which the insured have assumed responsibility, to be used in or pertaining to site preparation, demolition of existing structures, erection and/or fabrication and/or reconstruction and/or repair of any insured project while on site or in transit. The policy excludes any and all direct loss to the equipment of the Owner, contractors, subcontractors and consultants.

Page 39: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

7

The “All Risks Course of Construction Insurance” coverage shall name the Owner, the Construction Manager and all consultants and contractors, as additional insured. The foregoing insurance coverage shall contain a waiver of subrogation as against the owner, consultants and contractors except for the gross negligence on the part of the Owner, consultants and contractors.

The Trade Contractor and his Trade Subcontractors understand and agree that the Owner provides no warranty or representation as to insurance coverage. The Trade Contractor and his Trade Subcontractors shall rely solely upon the certified proof of coverage of the insurance underwriters to determine for themselves the nature and extent of the insurance coverage in place.

The Construction Manager shall be responsible to pay the deductible with respect to claims made under the Wrap-Up Comprehensive Liability Insurance or the All Risks Course of Construction Insurance, or both in respect of, or in any way related to, the Work except for Earthquake and Flood.

(c) Automobile Liability Insurance

The Construction Manager shall provide, maintain and pay the premiums and any applicable deductible, for all automobile liability insurance with respect of licensed vehicles which insurance shall have limits of not less than two million dollars ($2,000,000) inclusive per occurrence for bodily injury, death, and/or damage to property, and shall be in the following form:

(a) standard owner’s form automobile policy providing third party liability and

accident benefits insurance and covering licensed vehicles owned or operated by or on behalf of the Construction Manager.

(b) standard non-owned automobile including standards contractual liability

endorsement. (d) “All Risks Trade Contractors” Equipment Insurance

The Trade Contractor shall provide, maintain and pay the premiums, and any applicable deductible for “All Risks Trade Contractors” equipment insurance covering construction machinery and equipment used by the Trade Contractor or his Trade Subcontractors, or both for the performance of the Work, including boiler insurance on temporary boilers, and pressure vessels and shall not allow subrogation claims by the insurer against the Owner, the Consultant or the Construction Manager. Subject to proof satisfactory to the Owner of the financial capability of the Trade Contractor to self-insure the aforesaid machinery and equipment, the Owner agrees to waive this equipment insurance requirement.

11.1.2 Furnishing by the Owner of any insurance will in no way relieve or limit any responsibility or obligation imposed by the Contract Documents on the Construction Manager or any subcontractor of any tier. In addition, the Owner controlled insurance will not apply to vendors, suppliers, material men, and others who merely transport, pick up, deliver or carry materials, personnel, parts, equipment, or any other items or persons

Page 40: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

8

to or from the project site. The Owner makes no representations, guarantees, or warranties, express or implied, as to the fitness and/or quality of coverage.

11.1.3 Insurance Primary

With the exception of 11.1a and 11.1b, all coverage required of the Construction Manager will be primary over any other insurance that might be carried by the Owner.

11.1.4 No Reduction or Limit of obligation

By providing or requiring insurance, the Owner does not represent that coverage and limits will necessarily be adequate to protect the Construction Manager. Additional insurance effected or procured by the Construction Manager will not reduce or limit the Construction Manager’s contractual obligation to indemnify and defend the Owner for claims or suits which result from or are connected with the performance of this contract.

11.1.5 Duration of Coverage

All required coverage will be maintained without interruption during the entire term of this contract.

11.1.6 Construction Manager’s Insurance

The Construction Manager will use reasonable efforts to cause each Trade Contractor employed by the Construction Manager to purchase and maintain insurance of the types specified herein. If requested by the Owner, the Construction Manager will furnish copies of certificates of insurance evidencing coverage for each subcontractor.

11.1.7 Cross Liability & Severability of Interests

Wherever permissible by law, the Construction Manager supplied insurance policies will contain a cross liability and severability of interests clause.

41. Delete GC 11.2.1 in its entirety and substitute the following:

“The Contractor will, prior to commencement of the Work, furnish

(1) a Performance Bond in the amount of 50% of the Contract Price covering the faithful performance of the Contract, including the corrections after completion, and the payment of all obligations arising under the Contract, on a form approved by the Insurance Bureau of Canada, and with such sureties as the Owner may approve.

(2) a Labour and Materials Payment Bond in the amount of 50% of the Contract Price, covering the prompt payment of all claimants and all labour and material used, or reasonably required for use, in the performance of the Contract, including all extra works and the corrections after completion, on a form approved by the Insurance Bureau of Canada, and with such sureties as the Owner may approve.”

Page 41: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

MZM/1301411 APRIL 29, 2005 2684546

9

42. Delete GC 12.1 in its entirety and substitute the following:

“The Contractor will indemnify, hold, and save harmless the Owner from and against all claims, losses, damages, costs, actions, and other proceedings, made, sustained, brought or prosecuted in manner, based upon, occasioned by, attributable to any injury, including death, property damage, infringement, or damage arising from any act or omission of the Contractor, his employees, officers, volunteers, servants, or agents or persons from whom the Contractor has assumed responsibility in the performance or purported performance of this agreement.”

43. In GC 12.2.1.4, delete the words “a period of 6 years from the date of Substantial Performance of the Work, as set out in the certificate of Substantial Performance of the Work, or within such shorter period” from the first and second lines and substitute “such periods”.

Page 42: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

2720316

City of Richmond 6911 No. 3 Road Richmond, BC V6Y 2C1 www.richmond.ca

September 14, 2009 File:

Business & Financial Services Department Telephone: 604-276-4219 Fax: 604-276-4162

TO THOSE WHO HAVE RECEIVED COPIES OF 3713P Dear Sir/Madam: Re: Contract 3731P

Addendum No. 1 Design-Build for the Works Yard Dispersal Expansion

This addendum forms part of the Contract Documents and shall be read, interpreted and coordinated with all other parts. The costs of all work contained herein shall be included in the Contract Price. The following revisions supersede the information contained in the original Contract Document to the extent referenced and shall become part thereof. 1. Please see attachment. Regards,

Sumita Dosanjh Buyer II – Contracting Specialist

Page 43: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA

i

Table of Contents

1.0 FUNCTIONAL REQUIREMENTS..........................................................................................1 1.1 GENERAL BUILDING PLANNING PRINCIPLES ..................................................................1

1.1.1 Summary of Requirements .....................................................................................1 1.1.2 Relationships / Functionality ...................................................................................2 1.1.3 Site Related Relationships......................................................................................2 1.1.4 Construction Related Issues and Relationships .....................................................2 1.1.5 Conceptual Relationships .......................................................................................3 1.1.6 Millwork in contract .................................................................................................4 1.1.7 Not in contract.........................................................................................................4

2.0 ARCHITECTURAL DESIGN CRITERIA ...............................................................................5 2.1 BUILDING CODE SUMMARY ...............................................................................................5

2.1.1 Standards................................................................................................................5 2.1.2 Building data ...........................................................................................................5 2.1.3 Major Occupancy ....................................................................................................5 2.1.4 Construction............................................................................................................5

2.2 EXTERIOR WALLS ...............................................................................................................5 2.3 EXTERIOR WINDOWS .........................................................................................................5 2.4 PLATFORM / RAMPS / STAIRS............................................................................................6 2.5 ROOF SYSTEM.....................................................................................................................6 2.6 DOORS 6 2.7 FLOOR FINISHES.................................................................................................................6 2.8 INTERIOR PARTITIONS .......................................................................................................6 2.9 CEILINGS ..............................................................................................................................7 2.10 MILLWORK............................................................................................................................7 2.11 RODENT CONTROL .............................................................................................................7

3.0 STRUCTURAL DESIGN CRITERIA......................................................................................8 3.1 GENERAL DESIGN REQUIREMENTS .................................................................................8 3.2 DESIGN LOADS AND SERVICEABILITY REQUIREMENTS ...............................................8 3.3 FOUNDATIONS.....................................................................................................................9

4.0 MECHANICAL DESIGN CRITERIA ....................................................................................10 4.1 GENERAL DESIGN REQUIREMENTS ...............................................................................10 4.2 REGULATIONS AND STANDARDS ...................................................................................10 4.3 BUILDING DESCRIPTION ..................................................................................................10 4.4 CLIMATIC DESIGN CONDITIONS AND DESIGN CRITERIA.............................................10 4.5 HEATING (TYPICAL FOR ALL SPACES) ...........................................................................11 4.6 COOLING (OFFICE MODULE ONLY).................................................................................11 4.7 VENTILATION .....................................................................................................................11 4.8 PLUMBING ..........................................................................................................................12

Page 44: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Table of Contents

ii

4.8.1 Plumbing Systems ................................................................................................12 4.8.2 Plumbing Systems ................................................................................................12

4.9 DOMESTIC COLD WATER.................................................................................................12 4.10 DOMESTIC HOT WATER SYSTEM....................................................................................13 4.11 SANITARY WASTE SYSTEM .............................................................................................13 4.12 STORM DRAINAGE SYSTEM ............................................................................................13 4.13 FIRE SUPPRESSION..........................................................................................................14

5.0 ELECTRICAL DESIGN CRITERIA .....................................................................................15 5.1 GENERAL DESIGN REQUIREMENTS ...............................................................................15 5.2 REGULATIONS AND STANDARDS ...................................................................................15 5.3 UTILITY SERVICES ............................................................................................................15 5.4 POWER DISTRIBUTION.....................................................................................................15 5.5 RECEPTACLES AND POWER OUTLETS..........................................................................16 5.6 LIGHTING AND LIGHTING CONTROLS ............................................................................16 5.7 EMERGENCY LIGHTING AND EXIT SIGNS ......................................................................17 5.8 FIRE ALARM .......................................................................................................................17 5.9 TELECOMMUNICATION SYSTEM .....................................................................................17 5.10 GENERAL INSTALLATION REQUIREMENTS ...................................................................17 5.11 DATA / NETWORK SYSTEM ..............................................................................................17

6.0 SITE DEVELOPMENT, SITE WORKS AND SITE SERVICING .........................................18 6.1 EXISTING ASHPHALT ........................................................................................................18 6.2 WORK BY OTHERS............................................................................................................18 APPENDIX A – FLOOR PLAN DRAWING

Page 45: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 1

1.0 Functional Requirements

At the City of Richmond Public Works Yard, located at 5599 Lynas Lane, Richmond British Columbia, the Storm, Sanitary and Pumps crews are dispersed from a temporary trailer. A larger modular dispersal building is required to accommodate these three crews. Functional spaces required include offices and dispersal/lunch areas for each 18-25 person crew. The temporary trailer will then removed and credited by the contractor.

As a result of these requirements, the following is required:

Dispersal Building Expansion (the “Work”):

• Modular dispersal building comprised of 4 units (total approximate area 250 m2)

• Removal of the temporary trailer currently located adjacent to the existing main dispersal building.

1.1 GENERAL BUILDING PLANNING PRINCIPLES

1.1.1 Summary of Requirements

Program areas that satisfy Richmond Public Works Yard (RPWY) requirements to disperse the Storm, Sanitary and Pump crews from a new building located in the City of Richmond Public Works yard is summarized in Table 1-1

Seria

l

Description

Ref

eren

ce

Sum

mer

O

ccup

ancy

Win

ter

Occ

upan

cy

Proposed Area (m²)

1 Office Optional Work ‘B’

6 6 61.5

2 Pumps Crews Optional Work ‘C’

25 20 61.5

3 Storm Crew 25 18 61.5 4 Sanitary Crew

Base Work ‘A’ 25 18 61.5

Subtotal Net Area 246 Approximate Gross Up

Factor (15%) 36.9

Total Gross Building Area 282.9

Table 1-1

• Net area requirements for the building, excluding Design and Mechanical/Service space, shall be considered a minimum requirement for each space, and for the building as a whole.

Page 46: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Functional Requirements Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 2

• Staff will use shower rooms in the existing main dispersal building

o Women’s locker room / showers are located in the Existing Female Dispersal Washroom Building

o Men’s showers are located in the Existing Main Dispersal building

• Crews occasionally eat lunch in trailers

1.1.2 Relationships / Functionality

• Three crew areas are to be adjacent to each other

• Office area to be adjacent to crew area, and closest to existing main dispersal building.

• Crews will arrive, dress and disperse before shift start. Occasionally crew members will return to eat lunch mid-shift. At the end of shift, crew members prepare paper work and leave at 4PM

1.1.3 Site Related Relationships

• Provide direct exterior man door access from each crew area

• No internal access between functional spaces required

• No additional parking stalls required

• No landscaping required

• No fencing required

• Pedestrian access path from expansion to existing main dispersal building

• Adjacent to existing main dispersal building (lockers area and dispersal for Park, Roads, Water and Fleet crews)

1.1.4 Construction Related Issues and Relationships

• Maintain existing main dispersal building operations throughout construction

• Minimize Storm, Sanitary and Pumps dispersal crew operations disruption

• Lay down area to be confirmed with City of Richmond Public Works prior to construction start (including access, extents of lay down area)

Page 47: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Functional Requirements Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 3

1.1.5 Conceptual Relationships

Conceptual relationships that satisfy RPWY requirements to disperse the Storm, Sanitary and Pump crews from a new building located in the City of Richmond Public Works Yard are shown in Figure 1-1

Figure 1-1

Page 48: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Functional Requirements Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 4

1.1.6 Millwork in contract

Wash sink cabinet

Microwave stand

Stationery / Forms boards

Bulletin boards

1.1.7 Not in contract

Work stations

Computer stations

Microwaves

Chairs

Lockers

Tables

Benches

Building signage

Page 49: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Architectural Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 5

2.0 Architectural Design Criteria

2.1 BUILDING CODE SUMMARY

2.1.1 Standards

British Columbia Building Code of Canada (BCBC) 2006, division B, part 9

2.1.2 Building data

Building Area: 246 m2

Building Height: 1 storey

2.1.3 Major Occupancy

Group D, Business and personal services

2.1.4 Construction

Article 3.2.2.55. Group 2 up to 2 storeys

Combustible or non-combustible construction used singly or in combination. Load bearing walls and columns supporting an assembly required to have a fire-resistance rating not less than 45 minute.

2.2 EXTERIOR WALLS

The building envelope will consist of exterior pre-finished metal cladding (rain screen wall system) supported by wood frame construction or other structural system with R-15 average insulation value for the wall. Interior finish of exterior walls in the office and lockers area will be either painted gypsum wall board on a 25mm cavity with a minimum of 75mm semi-rigid or foam insulation applied over a waterproof membrane.

2.3 EXTERIOR WINDOWS

Exterior windows are to be operable, energy efficient type with double-glazing and low-e coating installed in thermally broken aluminum frames. Glazing will be provided in functional spaces that benefit from natural lighting for both operational and user requirements. Clerestory may be used near lockers.

Page 50: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Architectural Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 6

2.4 PLATFORM / RAMPS / STAIRS

Platform and ramps to be of treated tongue and groove wood construction supported on treated wood posts maximum spacing 2500mm on centres and treated wood beams and joists as required.

Ramps to have a minimum slope of 1:10 and minimum clear distance of 915mm as per sentence 3.4.6.6 (5) and table 3.4.6.A of British Columbia Building Code 2006.

Stairs to be treated wood stringers attached to beams on the upper end and concrete footings. Treads and risers to be built of treated wood lumber.

A 38mm diameter painted steel guardrail at 1070mm above finished floor, a 38mm diameter painted steel handrail at 960mm above finished floor or edge of nosing supported on 38mm diameter painted steel posts at maximum 1500mm on centres, with 16mm X 16mm balustrades at 100mm OC welded to upper handrail and guardrail and a 38 mm painted steel lower rail placed 100mm above finished floor or edge of nosing.

All platform, ramps and stairs to be painted

2.5 ROOF SYSTEM

Roofing for the facility will be EPDM membrane type on flat roofs. Roofing membrane will be installed over rigid insulation with an insulation value of minimum R-30 on an air/vapour barrier on deck sheathing over structural deck. Overflow drains or roof scuppers are to be provided for all flat roofs.

2.6 DOORS

Exterior doors will be insulated hollow metal in pressed steel and thermally broken frames. Interior doors are to be painted hollow metal type with honeycomb cores in metal frames. All doors to have kick plates. Door hardware is to be medium duty. Lock specification by City of Richmond.

2.7 FLOOR FINISHES

Flooring will be industrial grade sheet vinyl with rubber cove base.

2.8 INTERIOR PARTITIONS

Interior walls are painted gypsum wall board (Latex G3 finish).

Page 51: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Architectural Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 7

2.9 CEILINGS

Ceiling will be suspended acoustic tile and in washroom areas will be epoxy or alkyd painted suspended gypsum board ceilings. Ceiling height will be 2750mm.

2.10 MILLWORK

Kitchenette millwork is to be provided to standard AWMACC grade with plastic laminate.

2.11 RODENT CONTROL

A 200mm wide 600mm deep skirting / curb embedded 300mm in the ground to be built all around the perimeter of the building to deter rodents.

Page 52: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Structural Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 8

3.0 Structural Design Criteria

3.1 GENERAL DESIGN REQUIREMENTS

Structural design and documentation shall conform to the requirements of the 2006 British Columbia building code (2006 BCBC), applicable CSA material standards and municipal bylaws.

The structural design, documentation and contract administration shall be carried out under the direct supervision of the Structural Engineer of Record in accordance with the requirements of the BCBC 2006 and “Guidelines for Structural Engineering Services for Building Projects” by the Association of Professional Engineers and Geoscientists of British Columbia (APEGBC)

The Structural Engineer of Record (SER) shall be a professional engineer registered in the Province of British Columbia.

The SER shall ensure that an independent concept review has been completed prior to the submission for building permit.

A geotechnical investigation shall be carried out under the direct supervision of a professional engineer registered in the province of British Columbia.

Modular Structure to be portable and able to be relocated in future.

3.2 DESIGN LOADS AND SERVICEABILITY REQUIREMENTS

The structure shall be designed for the loads appropriate for the occupancy and climatic conditions. The loads shall satisfy the minimum loading and serviceability requirements for the 2006 BCBC. The Importance Category of the building is “Normal”.

The following minimum floor and roof loads shall apply:

Floor: 4.8 kPa

Roof: 1.0 kPa or snow load (whichever is greater)

The following deflection limits shall apply:

Floor: L/360 for live load

L/240 for long-term dead plus live load

Roof: L/360 for live load

Page 53: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Structural Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 9

The following storey drift limitations shall apply:

Wind: L/500

Seismic: L/50

3.3 FOUNDATIONS

A geotechnical investigation carried out under the direct supervision of a professional engineer registered in the province of British Columbia is required.

Post construction differential settlements shall be limited to ¾ inch over a distance of 25 feet and overall total settlement shall be limited to 2 inches.

Previous soils investigation close to the proposed site indicates the soils to be liquefiable (site class F) and a Dynamic Site Response Analysis is required to provide Site Coefficients (Fa and Fv). A raft foundation is recommended to meet the code requirements and settlement limitations. Preloading may be required if modular building structure can not accommodate these settlements.

Page 54: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 10

4.0 Mechanical Design Criteria

4.1 GENERAL DESIGN REQUIREMENTS

The intent of this section is to outline the design criteria for the mechanical systems of the proposed building modules. These systems include the heating, ventilating and air conditioning (HVAC), plumbing and fire protection systems and will be further developed into final design through the “design-build” process. This section should be read in conjunction with the Architectural, Civil, Structural and Electrical sections of this document.

4.2 REGULATIONS AND STANDARDS

The mechanical systems will be designed and installed by following principles of good engineering practice and by meeting or exceeding requirements of applicable codes and standards currently in effect, including but not limited to the following:

British Columbia Building Code – 2006 (BCBC)

Division B - Part 3 – Section 3.7. Health Requirements

Division B - Part 6 – Heating, Ventilating and Air-conditioning

Division B - Part 9 – Section 9.10. Fire Protection

British Columbia Fire Code – 2006 (BCFC)

City of Richmond Bylaw No. 8306, Fire Protection and Life Safety – 2008-07-14

American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE)

ASHRAE 62.1-2007, Ventilation for Acceptable Indoor Air Quality

ASHRAE 90.1-2007, Energy Standard for Buildings Except Low-Rise Residential Buildings

4.3 BUILDING DESCRIPTION

Refer to Part 1 of this RFP Technical Design Criteria.

4.4 CLIMATIC DESIGN CONDITIONS AND DESIGN CRITERIA

The climatic design data and the design indoor conditions for the building are summarized below:

Page 55: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 11

Outdoor Design Conditions:

Winter Design Temperature (occurs 1% of the time):

Dry Bulb -9°C

Summer Design Temperature (occurs 2.5% of the time):

Dry Bulb 27°C (DB)

Wet Bulb 19°C (WB)

Indoor Design Conditions:

Office Module (summer): 24°C

Sanitary, Storm and Pumps (summer): Not controlled

All areas (winter): 22°C

4.5 HEATING (TYPICAL FOR ALL SPACES)

Provide the following:

Electric heaters to maintain space temperature, based on the maximum ventilation load in winter.

Individual wall mounted thermostats with local adjustment.

4.6 COOLING (OFFICE MODULE ONLY)

Provide an electric air-source heat pump for all-seasons air conditioning (heating/cooling) of the office module only. Control will be by means of a wall-mounted electronic user programmable thermostat. Equipment and controls to be fully compatible one with the other and from a single manufacturer. Where baseboard electric heater(s) are provided for space heating in the same space as the heat pump, provide an automatic lock-out provision within the thermostat to prevent simultaneous heating and cooling. Energy efficiency of the heat pump unit shall meet or exceed the latest requirements of ASHRAE 90.1-2007.

4.7 VENTILATION

Provide mechanical ventilation in accordance with BCBC Section 6.2.2. for each (room) module. Minimum fresh air volumetric flow rate shall be maintained during all occupied periods in conformance with the requirements ASHRAE 62.1-2007. Mechanical exhaust shall be provided in the following areas:

Page 56: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 12

Locker/dressing room area within each (room) module (continuous)

Provide energy recovery ventilators as appropriate.

4.8 PLUMBING

Provide plumbing and drainage conforming to the requirements of BCBC Section 3.7.2. - Plumbing Facilities.

4.8.1 Plumbing Systems

The plumbing systems include:

Sanitary Waste system

Plumbing Fixtures and Trim

Domestic Cold Water System

Domestic Hot Water Supply

4.8.2 Plumbing Systems

Provide the following fixtures:

Shallow, single compartment stainless steel sinks

Low flow single lever sink faucets.

Hose bib on the outside of the Office module

4.9 DOMESTIC COLD WATER

Domestic cold water will be provided by a common connection to the existing Main Dispersal Building. Provide a mains connection point; protect from freezing. Provide shut -off valves at the mains connection point and at every branch line from the primary piped supply and at each plumbing fixture. The domestic cold water mains connection shall be located near the South-west corner of the structure (see Architectural plan) and shall extend 610 mm beyond the face of the structure. Owner will connect the cold water mains supply to the common domestic cold water inlet connection at the point of termination (see 6.2 below). The domestic cold connection water connection shall have a maintained clear space of not less than 910 mm (1200 mm preferred) between it and the common sanitary sewer mains connection (see 4.11 below).

Insulate domestic cold water piping to prevent condensation and winter freeze-up.

Page 57: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 13

Domestic cold water is required for the sinks and outdoor hose bibb.

4.10 DOMESTIC HOT WATER SYSTEM

Domestic hot water will be provided by a common connection to the existing Main Dispersal Building. Provide a mains connection point; protect from freezing. Provide shut -off valves at the mains connection and at every branch line from the primary piped supply and at each plumbing fixture. The domestic hot water mains connection shall be located near the South-west corner of the structure (see Architectural plan) and shall extend 610 mm beyond the face of the structure. Owner will connect the hot water mains supply to the common domestic hot water inlet connection at the point of termination (see 6.2 below). The domestic hot connection water connection shall have a maintained clear space of not less than 910 mm (1200 mm preferred) between it and the common sanitary sewer mains connection (see 4.11 below).

Insulate domestic hot water piping to prevent heat loss and winter freeze-up.

Domestic hot water is required for the sinks

4.11 SANITARY WASTE SYSTEM

Provide sanitary waste and vent piping to all plumbing fixtures. The sanitary system connects by gravity to the site main sanitary sewer. Provide a common sanitary sewer outlet mains connection at the South-west corner of the structure; extend the connection 610 mm beyond the face of the structure (see Architectural plan). Owner will provide for connection of the common sanitary sewer outlet to the site main sanitary sewer (see 6.2 below). The common sanitary sewer outlet shall be separated from the common domestic hot and cold water supply connections of not less than 914 mm clear distance (1200 mm preferred).

Gravity sanitary waste piping will be non-combustible cast iron or copper for above slab interior services.

Readily accessible cleanouts will extend to floor level or will be extended to a wall location in suitable locations for ease of long term maintenance.

4.12 STORM DRAINAGE SYSTEM

Provide storm drain system for the following:

Roof areas of all building (room) modules

Foundations and walkways abutting the buildings.

Conform to the requirements of BCBC Part 9.

Page 58: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Mechanical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 14

Storm runoff shall be diverted to the facility storm drain system or an approved dry well. Direct surface runoff away from foundations and walkways.

4.13 FIRE SUPPRESSION

Provide fire protection in accordance with BCBC and BCFC. Provide an approved fire extinguisher in each building (room) module in accordance with BCBC § 9.10.20.4. – Portable Fire Extinguishers. Mount on a wall near the location of the microwave oven, accessible to the exit.

Page 59: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Electrical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 15

5.0 Electrical Design Criteria

5.1 GENERAL DESIGN REQUIREMENTS

The intent of this section is to outline the proposed electrical systems criteria at the concept stage of the project. These systems include power distribution, power outlets, lighting layout and telecommunication voice/data outlets and will be further developed into final design through the “design-build” process. This section should be read in conjunction with the Architectural, Civil, Structural and Mechanical sections of this document.

5.2 REGULATIONS AND STANDARDS

The electrical systems will conform to the current application of the Canadian Electrical Code and local standards and regulations. This will be achieved by meeting or exceeding, but not limited, to the following:

1. British Columbia Building Code.

2. CSA C22.1-06, Canadian Electrical Code Part 1 (20th Edition).

3. Canadian Standard Association (CSA International).

4. TIA/EIA-568 Commercial Building Telecommunications Cabling Standard.

5.3 UTILITY SERVICES

No addition electrical service from local utility provider is required for the expansion.

5.4 POWER DISTRIBUTION

The electric power for the expansion will be connected to/supplied from the existing main dispersal building.

• Two new 3P breakers shall be installed at the 347/600V, 3 Phase, 4 Wire panel board in the electrical closet of existing main dispersal building.

• 600-120/208V Δ-Y transformer shall be installed in the electrical closet of existing main dispersal building.

• A 100A, 347/600V, 3 phase, 4 wire lighting panel board and a 100A, 120/208V, 3 phase, 4 wire power panel board shall be installed at corridor or office of the expansion space.

• Spare breakers for each panel board shall be at least 30% of connected circuit numbers and all bussing shall be tinned copper.

• Feeder cable from existing main dispersal building to new panel boards shall be marked as suitable for exposed wiring where exposed to the weather.

Page 60: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Electrical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 16

• Breaker size and transformer size shall be calculated as per related section of CEC Code.

5.5 RECEPTACLES AND POWER OUTLETS

15A general purpose receptacles shall be provided throughout the expansion space. They will be fed from the new installed power panel board. For each office computer work stations, two duplex receptacles shall be provided. Separated circuits are required for high power electrical apparatus, such as microwave, etc. Ground fault circuit interrupter (GFCI) receptacles are required to be installed in washroom as well as counter power outlets within 1.5m to the sink. Convenient receptacles shall be provided in the corridor area. Power shall be provided to the mechanical equipments as per Mech. section.

Additional 15A duplex receptacles shall be provided to suit the refurbished trailer layout.

5.6 LIGHTING AND LIGHTING CONTROLS

A complete lighting system shall be provided for the expansion space. They should be practical for the areas they serve. Lighting circuits will be fed by the new installed lighting panel board installed at the corridor or office in the expansion space. Switching shall be planed to provide the different levels of illumination as dictated by the task, thus reducing the overall energy use.

In summary the following shall be provided:

1. Minimum illuminance shall be as follows;

• All modules: 500 Lux (50 fc)

2. Lighting Fixture shall be as follows;

• Fluorescent type utilizing T8 lamps complete with rapid start electronic ballast for energy efficient, long life and economical usage

• Fixture to have high reflectance reflector and diffuser/louver

3. Switching shall be as follows;

• Line voltage switching will be used throughout.

• Local switches shall control lighting in the respective area.

• Multiple switching arrangements to control individual lighting fixtures, or separate lamps within the lighting fixtures shall be utilized.

• Designated night light will be un-switched.

Page 61: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Electrical Design Criteria Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 17

5.7 EMERGENCY LIGHTING AND EXIT SIGNS

All exit paths/door to exterior shall be equipped with emergency lighting and exit sign. Supplementary battery pack emergency lights will be utilized. Exit sign will be LED type to NFPA 170. Unit shall have minimum life expectancy of 25 years continuous operation.

5.8 FIRE ALARM

Provide fire alarm system as required by the BC Building Code.

5.9 TELECOMMUNICATION SYSTEM

Data/Voice outlets (DVOs) shall be provided throughout the expansion space with minimum one DVO per each workstation. Provide cable tray and conduit system from the existing patch panel in the electrical closet of existing main dispersal building to each DVOs. Cat 5e cabling will be carried out by City of Richmond. The maximum horizontal cable run shall not exceed 90 meters.

Cable trays shall be wire basket type, prefabricated structure with 200mm in width or greater. They should be bonded to telecommunication main ground bus and are coated to prevent rust and galvanic action.

5.10 GENERAL INSTALLATION REQUIREMENTS

1. All building wiring shall be installed in conduits with minimum size of 19mm.

2. Minimum wire sizes are based on the use of copper conductors.

3. Minimum wire size is #12 AWG.

4. Use XLPE RW90 for interior and XLPE RWU90 for exterior wiring.

5.11 DATA / NETWORK SYSTEM

Computer workstation terminals are proposed to be installed in each sanitary, storm, pumps dispersal modules and office module. In addition to the workstation computers, three SCADA terminal computers are proposed, 2 in the office module , and 1 in the pumps module. Provide one quadruplex receptacle and two data drops for each terminal. Install all power systems and data cabling through conduit system. Install all data conduit and boxes including devices and covers. Data cabling to be carried out by City of Richmond. Terminate all data drops back to the patch panel in the existing building. Power circuits shall be routed back to the power panel board at the corridor.

Page 62: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

CITY OF RICHMOND PUBLIC WORKS YARD DISPERSAL EXPANSION REQUEST FOR PROPOSALS TECHNICAL DESIGN CRITERIA Site Development, Site works and Site Servicing Revised September 10, 2009

ggm v:\1145\active\114501313\report\addendum 1 - final report 2009.08.10\rpwy dispersal expansion rfp technical section_final.doc 18

6.0 Site Development, Site works and Site Servicing

6.1 EXISTING ASHPHALT

Make good existing asphalt and parking stalls after construction

6.2 WORK BY OTHERS

Sanitary, DCW, DHW and Storm water connections by City of Richmond forces

Underground electrical connection

Removal, relocation and reinstallation of lockers

Parking space line painting

Page 63: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

Appendix A Floor Plan Drawing

Page 64: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract
Page 65: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

2720545

City of Richmond 6911 No. 3 Road Richmond, BC V6Y 2C1 www.richmond.ca

September 15, 2009 File:

Business & Financial Services Department Telephone: 604-276-4219 Fax: 604-276-4162

TO THOSE WHO HAVE RECEIVED COPIES OF 3713P Dear Sir/Madam: Re: Contract 3713P

Addendum No. 2 Design-Build for the Works Yard Dispersal Expansion

This addendum forms part of the Contract Documents and shall be read, interpreted and coordinated with all other parts. The costs of all work contained herein shall be included in the Contract Price. The following revisions supersede the information contained in the original Contract Document to the extent referenced and shall become part thereof. 1. Please delete the following:

Four (4) copies of proposals marked “3709P Design-build for the Works Yard Dispersal Expansion” addressed to the Purchasing Section, will be received at the Information Counter, Main Floor, Richmond City Hall, 6911 No. 3 Road, Richmond BC V6Y 2C1, until 2:00 PM, Local Time on Thursday, September 24, 2009. Submissions received after this time will be returned to the sender.

And replace with:

Four (4) copies of proposals marked “3713P Design-build for the Works Yard Dispersal Expansion” addressed to the Purchasing Section, will be received at the Information Counter, Main Floor, Richmond City Hall, 6911 No. 3 Road, Richmond BC V6Y 2C1, until 2:00 PM, Local Time on Thursday, September 24, 2009. Submissions received after this time will be returned to the sender.

2. Please contact the following if you wish to schedule a site visit: Jason Ho, EIT 604-244-1281

Page 66: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

Regards,

Sumita Dosanjh Buyer II – Contracting Specialist

Page 67: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

2725654

City of Richmond 6911 No. 3 Road Richmond, BC V6Y 2C1 www.richmond.ca

September 22, 2009 File:

Business & Financial Services Department Telephone: 604-276-4219 Fax: 604-276-4162

TO THOSE WHO HAVE RECEIVED COPIES OF 3713P Dear Sir/Madam: Re: Contract 3713P

Addendum No. 3 Request for Proposal for Design-Build for the Works Yard Dispersal Expansion

This addendum forms part of the Contract Documents and shall be read, interpreted and coordinated with all other parts. The costs of all work contained herein shall be included in the Contract Price. The following revisions supersede the information contained in the original Contract Document to the extent referenced and shall become part thereof. 1. Submission deadline date has been extended to 2:00 PM local time Tuesday September 29, 2009. 2. Questions and Answers

1. Question: Clarification required for the exterior wall spec. You show the gypsum to be on a 1” (25 mm) cavity with a minimum of 3” (75 mm) semi-rigid or foam insulation. We are not clear exactly what they are looking for. Drawing looks to show 2x6 walls?

Answer: Please modify Architectural Design Criteria Item 2.2 Exterior Walls as follows. Please also see the attached file as the exterior detail requested

Exterior Walls

The building envelope will consist of exterior pre-finished metal cladding (rain screen wall system) supported by wood frame construction or other structural system, 25mm air cavity, minimum of 75mm semi-rigid or foam insulation which is applied over a waterproof sheathing membrane and exterior gypsum or wood sheathing. Interior finish of exterior walls in the office and lockers area will be painted gypsum wall board.

2. Question: In one portion of the spec it asks for each computer workstation to have 2 – duplex

receptacles & 1 – Data/Voice outlet. Further in the spec it asks for 1 – quad receptacle & 2 – data drops per terminal. Is a workstation different than a terminal? Is a data drop the same as a Data/Voice outlet? If all is referring to the same thing, which would you like?

Page 68: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

Answer: 'Two duplex receptacles' is equivalent to '1 quad receptacle'. Please replace 'DVO' and 'two data drops' with 'DVO with 2-RJ45 jack'.

3. Question: Rodent Control (section 2.11) – Are you referring to concrete curb. I would like to see a

detailed drawing as the dimensions you quote do not make sense.

Answer: Successful proponent to provide detailed design for City approval, based on the trailer detail and foundation design.

4. Question: With a suspended T-bar ceiling at 2750mm you will have very little space above the t-bar

for the light fixtures, duct work etc. as we have a transport height restriction for the total building height based on Ministry of Highways regulations.

Answer: Finished internal elevation is provided in design criteria. Final height of structure is to be determined by successful proponent.

5. Question: Section 3.3 – Who is paying for the geotech engineering study, and how are we supposed

to know how we are to cost out the foundation without details of the said report.

Answer: Successful proponent is responsible for the geotechnical study and assessment. 6. Question: Section 4.6 – Does the office complex have a heat pump only for heat ? ie, there are no

baseboard heaters in the office complex.

Answer: Please refer to Section 4.5 – Heating

7. Question: Section 5.4 – Power distribution – Is the city doing this work ?

Answer: Successful proponent is responsible.

8. Question: Section 5.11 – data network system – Is the city of Richmond doing all this work In this section?

Answer: Please refer to details within Section 5.11 for allocation of responsibilities.

9. Question: Section 6.2 – City of Richmond are doing service connections. Does this mean that we do

not have to provide any plumbers, electricians, civil/site service workers on site ?? The buildings will come from the factory with service connection points stubbed down to the underside of the modular unit ready for connection by the City.

Answer: Please refer to details within Section 6.2 for allocation of responsibilities. 

Regards,

Sumita Dosanjh Buyer II – Contracting Specialist

Page 69: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

2727065

City of Richmond 6911 No. 3 Road Richmond, BC V6Y 2C1 www.richmond.ca

September 25, 2009 File:

Business & Financial Services Department Telephone: 604-276-4219 Fax: 604-276-4162

TO THOSE WHO HAVE RECEIVED COPIES OF 3713P Dear Sir/Madam: Re: Contract 3713P

Addendum No. 4 Request for Proposal for Design-Build for the Works Yard Dispersal Expansion

This addendum forms part of the Contract Documents and shall be read, interpreted and coordinated with all other parts. The costs of all work contained herein shall be included in the Contract Price. The following revisions supersede the information contained in the original Contract Document to the extent referenced and shall become part thereof. ITEM 1 – Project Schedule 1. Under Section 8. Project Schedule please include the following:

It is the City’s intention to have the Expansion operational and available for use before February 1, 2009. Therefore all work under this contract must be completed by the successful proponent no later than January 15, 2009. The City intends to issue Notice of Award for this project one (1) week after the submission deadline date for Contract 3713P.

ITEM 2 – Questions and Answers 1. QUESTION: We have a question on the power distribution mentioned in section 5.0 Electrical

Design Criteria, 5.4 Power distribution. We have done a quick rough calculation and we should only need 128 amps for a 3 phase service for the whole building. This includes all the optional buildings as well. You have asked for a 110A, 347/600V, 3 phase, system, which is much more than required. Do you also require 2 panels, one for the lighting and one for the power? We typically would do 1 main panel & 2 sub panels if all buildings are taken.

Page 70: Contract 3713P Design-Build for the Works Yard Dispersal ... · Contract 3713P Design-Build for the Works Yard Dispersal Expansion 1. Introduction ... 5.1 The award of the contract

ANSWER: Please refer to section 5.4 '100A, 120/208V, 3 phase, 4 wire power panel board' is a panel rating commonly used in industry. 'Breaker size and transformer size shall be calculated as per related section of CEC Code' by successful proponent. 2 panels are required for consistency with existing facilities. Regards,

Sumita Dosanjh Buyer II – Contracting Specialist