contract hse management/part i - نفت و گاز پارس hse management parti... · contract hse...
TRANSCRIPT
Pars Oil & Gas Company
Contract HSE Management/Part I
HEALTH, SAFETY AND ENVIRONMENT PROCEDURE
Contract HSE Management/Part I
DOCUMENT ID - PR-10-POGC-001
REVISION - 1.0
Contract HSE Management/Part II
HSE Department Document ID. PR-10-POGC-001
Revision 1.0
Pages 9
Contract HSE Management/Part I
Document Authorization
Document Custodian Document
Authority/Owner Security Classification Document Type
HSE P.O.G.C Unrestricted HSE Procedure
Approved By Document Author
Ansari.Mazaher HSE – 564815
Pars Oil & Gas Company
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page a REVISION 1.0
Contents
1 Introduction 1
1.1 Background 1
1.2 Purpose 1
1.3 Distribution/Target Audience 2
2 Contract HSE Management Procedure 3
2.1 Scope 3
2.2 Description 3
2.3 Contract Owner’s Responsibilities 4
2.4 Contract Holder’s Responsibilities 4
2.5 Minor Contract 4
3 Contract Phase: Planning and Invitation to Tender 6
Task 1 Appoint Contract Holder 6
Task 2 Prepare Contract Scope of Work 6
Task 3 Preparation of the Contract Schedule 7
Task 4 Develop Contract Strategy 8
Task 5 Approval of the Contract Strategy 8
Task 6 Conduct HSE Assessment 9
Task 7 Prepare Exhibit L of Contract, (HSE Requirements) 10
Task 8 Prepare POGC Contract HSE Management Schedule 11
Task 9 Approve POGC Contract HSE Management Schedule 11
Task 10 Development of HSE Prequalification Criteria 12
Task 11 Tender Board – Endorse HSE Prequalification Criteria 13
Task 12 Prequalify Contractors 14
Task 13 Tender Board – Approve Contractor Bid List 14
4 Contract Phase: The Tender Period 15
Task 14 Contractor Submission: Document HSE Requirements 15
Task 15 Site Visit 15
Task 16 Clarification Meeting 16
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page b REVISION 1.0
5 Contract Phase: Evaluation and Contract Award 17
Task 17 Review Contractor Submission – Document HSE Requirements 17
Task 18 Evaluate Contractor Submission – Document HSE Requirements 17
Task 19 Review Contractor Ability to Manage HSE Risk 17
Task 20 Contractor HSE Assessment 18
Task 21 Contract Award Recommendation to Tender Board 18
Task 22 Advise Contractor of Company (POGC) Representative 19
Task 23 Advise Contractor of Company (POGC) Site Representative 19
Task 24 Contractor Appoints Key HSE Personnel 20
Task 25 Approve Contractor Key HSE Personnel 20
6 Contract Phase: Mobilization 21
Task 26 On Site HSE Workshop 21
Task 27 Contractor to Prepare HSE Management Plan 22
Task 28 Review Contractor’s HSE Management Plan 24
Task 29 Approve Contractor’s HSE Management Plan 24
Task 30 Contract Holder Develops POGC HSE Monitoring Program 24
Task 31 Contract Owner Review HSE Monitoring Program 29
Task 32 Contract Owner Approve HSE Monitoring Program 29
Task 33 POGC and Contractor Training 29
Task 34 Contractor Mobilization 29
Task 35 Pre-execution HSE Audit of Contractor 30
Task 36 Contractor Completes Pre-execution HSE audit Items 32
Task 37 Contractor – Readiness to Commence 32
Task 38 Issue HSE Certificate 32
7 Contract Phase: Execution 33
Task 39 Supervision 33
Task 40 Monitor Contractor’s implementation of HSE Management Plan 34
Task 41 Additional HSE Requirements 35
Task 42 Contractor - Revise HSE Management Plan 35
Task 43 Review Revised Contractor’s HSE Management Plan 36
Task 44 Approve Revised Contractor’s HSE Management Plan 36
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page c REVISION 1.0
Task 45 Implement POGC HSE Deviations and Amendments 36
Task 46 Contractor – Revise HSE Management Plan 37
Task 47 Review Contractor revised HSE Management Plan 37
Task 48 Approve Contractor revised HSE Management Plan 38
Task 49 HSE Penalties and Defaults 38
Task 50 Contract HSE Performance Reports 39
8 Contract Phase: Demobilization 40
Task 51 Site Restoration – Compliance 40
Task 52 Site Restoration Certificate Approval 40
9 Contract Phase: Close Out 41
Task 53 Final Contract HSE Performance Report 41
Appendix MC HSE Checklist for Minor Contracts 42
Appendix A Summary - Contract HSE Management Procedure 44
Appendix A1 Contract HSE Management Schedule 54
Appendix B HSE Prequalification Questionnaire 65
Appendix C HSE Monitoring Program 79
Appendix D Template, Contract HSE Performance Report 80
Appendix E HSE Certificate 84
Appendix F Site Restoration Certificate 85
Appendix G Variation to Contract – Tenders’ Law 88
Appendix H Accessing POGC and Shell Web Documents 91
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 1 REVISION 1.0
PART I: Mandatory for POGC personnel involved in Contract Management
1. Introduction
1.1 Background
POGC’s Policy Document, HSE Policy requires that a systematic approach to HSE management be applied
which shall require Contractors to manage HSE in line with POGC’s HSE Policy. POGC’s Code of Practice
Document, MA-12-POGC-001 (HSE Management System Manual), requires that POGC Asset Managers
shall ensure Contractors are made aware of POGC’s HSE management requirements and have adequate
business controls in place to meet them.
The International Organization for Standardization (ISO 14001) requires that procedures be established
and maintained to ensure that relevant environmental requirements are communicated to Contractors.
With the development of the Contract Holder ship Certification Scheme (CHCS) it became apparent that a
complete review and re-write of the suite of HSE Management of Contracts documents was desirable.
1.2 Purpose
Document PR-10-POGC-001 (Contract HSE Management) has two parts:
Part I: Mandatory for POGC Personnel involved in Contract Management
Part II: Mandatory for Contract Holders and Contractors
Part I follows the material delivered to Contract Holders during the Contract Holder ship Certification
Scheme. Each of the 53 activities related to Contract HSE management issues are described, together
with any Deliverable(s) and relevant Reference Document (s) that are obtainable on the POGC intranet
system (http://portal.pogc.org). Refer to Appendix H for assistance in accessing POGC Web Documents.
Part I describes the flow of activities to be executed by Contract Holders, from strategy definition to
close-out of a contract, to ensure that Contractors achieve the same (or higher) HSE standards as those
required by POGC for its own operations. The Procedure is based on a planned approach with attention
being paid to HSE issues in the early Contract Phases in order to properly address HSE through the entire
contract process.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 2 REVISION 1.0
Part II is referenced, in document Exhibit L of Contract, to enable Contractors, together with Contract
Holders, to carry out POGC prescribed HSE activities in the manner and at the level required by POGC. Of
particular importance in this section is the detail given for the preparation of the Contractor’s HSE
Management Plan. This information is to be used by both Contract Holders and Contractors, and is also
referenced throughout Part I where appropriate.
The input to each Contract Phase and the depth of analysis (the “Tasks”) primarily depends on the level
of HSE risk presented by the contract activities, which consequently determines the actions and input
required for the contract execution.
Whether a contract is large or small in scope and value the Tasks are all the same. Preparations for all
contracts shall utilize the same systematic process of hazard identification, assessment, control,
mitigation and recovery (Hazards and Effects Management Process - HEMP), together with the
demonstration that a system is in place to manage these hazards.
1.3 Distribution/Target Audience
This Procedure is a mandatory requirement for Contract Owners and Contract Holders.
Part I of this Procedure is targeted at Contract Owners, Contract Holders, Company Representatives,
Company Site Representatives and other POGC personnel tasked with the HSE aspects of contract
planning, tender preparation, evaluation and subsequent contract management.
Part II of this Procedure contains HSE instructions for Contractors. It is the obligation of Contract
Holders to ensure that Part II is supplied to Contractors and that the instructions in it are followed.
Distribution of this document is controlled by the Document Custodian.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 3 REVISION 1.0
2. Contract HSE Management Procedure
2.1 Scope
This Procedure applies to all contracts tendered by POGC regardless of size and value.
2.2 Description
This Procedure follows the HSE sequence of Tasks in contract management as detailed in the
Contract Holder ship Certification Scheme. These activities, specific to HSE in the preparation,
evaluation and execution of a contract, are summarized in Appendix A, “Summary - Contract
HSE Management Procedure”.
The sequence of events in any contract can be described in seven Contract Phases:
1. Planning and Invitation to Tender
2. The Tender Period
3. Evaluation of the Tenders and Contract Award
4. Mobilization
5. Execution
6. De-mobilization
7. Close Out
The succeeding sections of Part I of Contract HSE Management (PR-10-POGC-001) detail the
Tasks contained in these seven Contract Phases, finalizing with the summary in Appendix A.
In some of the Tasks, form(s) must be completed for the Contract to proceed. These are detailed in each Task where
required, including any reference documents that relate to the forms. All forms necessary for the HSE Management of a
Contract are given in the various Appendixes in this document.
Each Task paragraph also contains instructions for any relevant Deliverable(s), as well as the
document number and title for any reference material pertinent to that Task.
Appendix H provides guidance for retrieving documents from the POGC electronic system.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 4 REVISION 1.0
2.3 Contract Owner’s Responsibilities
Contract Owner shall be an individual with the right level of authority to direct the contracting
process to protect overall POGC and Asset objectives. Where relevant, Contract Owners should
attend Tender board presentations to support Contract Holders. Contract Owner should at all
times be cognizant of HSE issues in each Contract.
2.4 Contract Holder’s Responsibilities
Contract Holder shall have single point responsibility for the activity management of the
Contract and verification that the control mechanisms are in place.
Contract Holder shall have single point responsibility for advising Contractor and/or Contractor
Personnel of activities, stated in each relevant Task, requiring their action(s). These activities
are not necessarily repeated in Part II of Contract HSE Management (PR-10-POGC-001), as they
generally arise from the responsibilities and activities of the Contract Holder as stated in each
Task.
It is not expected that Contract Holders can carry out all the activities listed in the following
sections. Rather, Contract Holders shall call upon professional personnel from relevant POGC
departments when assistance with HSE issues is required. This does not in any way remove
from Contract Holders the absolute responsibility for ensuring that advice received and ensuing
actions taken are the best possible solutions to any point in the execution of a Contract.
2.5 Minor Contract
Contract Holder shall: Contract Holder shall complete the necessary sections of the table in
Appendix MC.
Contract Holder shall ensure that the Contractor is fully aware of and understands the
requirements of this table.
Contract Holder shall ensure that the Contractor is fully aware of and understands the following
statement:
“Contractor shall operate, and shall cause all sub-contractors and Contractor Personnel to
operate, with the utmost care for the health and safety of Contractor Personnel, Company
DOCUMENT TITLE: Contract HSE Management Part I Page 5 REVISION 1.0
Pars Oil & Gas Company
personnel and third parties, and for the environment, and in accordance with the Company's health, safety and environmental regulations (the HSE Specification) in force at the Effective Date, or as subsequently amended by the Company, and the Contractor shall exercise the strongest discipline in this regard."
DOCUMENT TITLE: Contract HSE Management Part I Page 6 REVISION 1.0
Pars Oil & Gas Company
3. Contract Phase: Planning and Invitation to Tender
Task 1 Appoint Contract Holder
Contract Owner shall initiate the development and implementation of the Contract Management
Plan, covering all aspects of the integrity management of the Contract.
Contract Owner shall provide the necessary resources for the implementation of, and
compliance with, Contract HSE Management (PR-10-POGC-001), Contract HSE Management
Procedure.
Contract Owner shall appoint the Contract Holder, who shall have single point responsibility for
the activity management of the Contract and verification that the control mechanisms are in
place. In a technically complex or very large contract, the appointment of the Company (POGC)
Representative, by the Contract Owner, may also be required.
Contract Holder shall initiate the implementation and monitoring of the Contract Management
Plan. This shall include all aspects of the HSE Management Schedule in relation to the activity
management of the Contract. It is not to be expected that the Contract Holder shall personally
execute all the HSE activities detailed below; but it is mandatory that sufficient, suitable
professional assistance shall be called in by the Contract Holder when such assistance is
required.
The Contract Holder (CH) may delegate the execution of an activity to a Company (POGC)
Representative and/or Company (POGC) Site Representative (CR/CSR); however the Contract
Holder shall remain responsible for the execution of that activity. The outcomes of this
responsibility are subject to inspection and audit.
Deliverable(s): Memo to Contract File, recording appointment(s)
Reference Document(s): Transactions Regulation (of POGC)
Task 2 Prepare Contract Scope of Work
Contract Holder shall define the HSE aspects of the Contract Scope of Work and/or Services in
sufficient detail to identify the major hazards and provide a basis for executing the Hazard and
Effects Management Process (HEMP) for the contract (refer Task 6). This shall be determined
DOCUMENT TITLE: Contract HSE Management Part I Page 7 REVISION 1.0
Pars Oil & Gas Company
from a separate appraisal of the business area and activities themselves and shall include
aspects such as:
• type of work activities;
• location of site(s) and the workplace;
• location of Contractor’s base;
• mobilization/ demobilization point;
• personnel;
• plant and equipment used;
• materials and consumables.
Experience gained from previous projects should be utilized by reference to:
• Environmental Impact Assessments (EIAs) and close-out reports from similar
projects
• Formal records of previous HSE performance by Contractors on similar projects
• Quantitative Risk Assessments (QRAs) and HSE audits carried out in recent years
on similar activities
• General background information on planned areas of operations
Deliverable(s): Memo to file detailing HSE major hazards
Reference Document(s): -Exhibit A of Contract, (Scope of Works, part I,II,III)
-Exhibit L of Contract, (HSE Requirements)
-Transactions Regulation (of POGC)
Task 3 Preparation of the Contract Schedule
Contract Holder shall prepare the Contract Schedule by inserting planned dates to coordinate
with the execution of the Scope of Works
Deliverable(s): Memo to Contract file detailing Contract Schedule
Reference Document(s): Transactions Regulation (of POGC)
DOCUMENT TITLE: Contract HSE Management Part I Page 8 REVISION 1.0
Pars Oil & Gas Company
Task 4 Develop Contract Strategy
Contract Holder shall determine the work and/or services required from mobilization to
demobilization (including site restoration). Using the Scope of Works and Schedule developed
above, the Contract Strategy can be developed; HSE exposure to risk shall be minimized during
execution of the Contract. The strategy document shall detail both POGC and Contractor HSE
obligations. It is recommended that suitable project management software be used to
determine the critical path for a Contract to assist in Contract Strategy development.
The factors to be considered in formulating the Contract Strategy shall include:
• Availability of suitable existing contracts (for example, service, call-off, etc.)
• Contractor resources and skills
• POGC supervision resources and skills
• POGC/Contractor responsibilities
• local environment
• project schedule
• competitive situation
• Iranian law, local rules and regulations
• influence of POGC to control the Contractor
• define boundaries of the contract (mobilization, demobilization)
• define limits of transport control
• provisions for delay or forfeit of contract payments
• extent to which project management control is relinquished to or shared with the
Contractor
• Results of HSE audit findings, unsatisfactory completion of action items.
• non-submission or late submission of key HSE Plans and documents shall be linked to
contract payments and penalties
Deliverable(s): Memo to Contract files detailing Contract Strategy
Reference Document(s): Transactions Regulation (of POGC)
Task 5 Approval of the Contract Strategy
Contract Owner shall approve the Contract Strategy document(s).
DOCUMENT TITLE: Contract HSE Management Part I Page 9 REVISION 1.0
Pars Oil & Gas Company
Deliverable(s): Memo to Contract File approving Contract Strategy
Reference Document(s): Transactions Regulation (of POGC)
Task 6 Conduct HSE Assessment
Contract Holder shall conduct a structured, formal HSE Assessment of the Contract, using the
Scope, Schedule and Strategy documents (as well as any existing HSE information from prior
documents related to the same package of work) with a view to minimizing the HSE exposure
and level of risk for the Contract.
Contract Holder shall use suitably qualified POGC personnel in developing the HSE Assessment.
These personnel shall include Professional HSE Advisors, personnel who will participate in the
work to be carried out under the contract, or those who have prior experience in the execution
of contracts.
The primary objectives of the HSE Assessment are:
• Identify and assess the major hazards and risks associated with the contract
• Determine methods for control, mitigation and recovery from risk – the Hazards and
Effects Management Process (HEMP)
• Provide the necessary input to prepare document HSE Requirements.
• Provide the necessary input to prepare the POGC Contract HSE Management Schedule
(refer Task 8)
The HSE Assessment shall include or enable:
• Hazard and Effects Management Process (HEMP), in accordance with instructions in
document MA-12-POGC-001 (HSE Management System Manual),
• Define the level of HSE risk presented by the contract
• Determine the levels of controls necessary to manage the risk
• Identify the applicable HSE legislation
• Identify the POGC standards to be applied
DOCUMENT TITLE: Contract HSE Management Part I Page 10 REVISION 1.0
Pars Oil & Gas Company
• Identify the HSE project organization/interfaces
• Evaluate critical time schedules with respect to HSE impact
• Evaluate resource limitations with respect to HSE impact
• Determine communication needs including scope and schedules for meetings
• Identify minimum competency for both POGC and Contractor personnel
• Identify the training requirements for both POGC and Contractor personnel
• Prepare a training schedule for both POGC and Contractor personnel, paying particular
attention to training needs for exceptional activities
Details shall be formally recorded with future actions identified and, wherever possible, action
parties nominated.
Contract Holder shall confirm the suitability of the HSE Assessment against contract scope,
schedule and strategy with the view to minimizing the HSE exposure and level of risk for the
contract.
Deliverable(s): Note to Contract file, HSE Assessment
Reference Document(s):
-Exhibit L of Contract, (HSE Requirements)
-MA-12-POGC-001 (HSE Management System Manual),
Task 7 Prepare Exhibit L of Contract (HSE Requirements)
The purpose of Section Exhibit L of Contract of the standard contract documentation is to: -
• Highlight the hazards and consequences related to the Works or Services being
provided under a contract.
• Act as the enforceable contractual link to the applicable POGC HSE Management System
documentation.
Detail the requirements for Contractors to examine the proposed Scope of Works (Exhibit A of Contract, (Scope of Works, part I,II,III)),determine the hazards and consequences and define how those hazards will be managed so that risk is minimized.
Document Exhibit L of Contract, (HSE Requirements) defines what the Contractor is required to
do to minimize the HSE risk to POGC and it provides the framework for the successful
Contractor’s HSE Management Plan.
DOCUMENT TITLE: Contract HSE Management Part I Page 11 REVISION 1.0
Pars Oil & Gas Company
Contract Holder shall use the results of the HSE Assessment to develop Document Exhibit L of
Contract, (HSE Requirements) for inclusion in Tender Documents. Exhibit L of Contract, (HSE
Requirements) shall be used by the Contract Holder and the successful Contractor for the
duration of the Contract.
Incorporating an incentive scheme for HSE management, involving additional payment in a
contract, requires very careful consideration. It can absorb a significant degree of effort to
administer and the longer-term effectiveness is questionable. Incentive schemes for HSE
management are STRONGLY discouraged and are not covered in the scope of this document.
Deliverable(s): Contract HSE requirements
Reference Document(s): Exhibit L of Contract, (HSE Requirements)
Task 8 Prepare POGC Contract HSE Management Schedule
Contract Holder shall use the results developed in the Contract Scope, Schedule and Strategy
documents, Exhibit L of Contract,(HSE Requirements) and the HSE Assessment, to complete the
column titled “Date (Planned/Actual)” in Appendix A1, thus preparing the POGC Contract HSE
Management Schedule for approval by the Contract Owner.
This schedule may be tracked by the Contract Holder by completing the actual dates in the
relevant columns in Appendix A1.
Deliverable(s): POGC Contract HSE Management Schedule for approval
Reference Document(s): -MA-12-POGC-001 (HSE Management System Manual),
-Exhibit L of Contract, (HSE Requirements)
Task 9 Approve POGC Contract HSE Management Schedule
Contract Owner shall review and approve Contract HSE Management Schedule
Deliverable(s): -Approved Contract HSE Management Schedule
-Memo to Contract File
DOCUMENT TITLE: Contract HSE Management Part I Page 12 REVISION 1.0
Pars Oil & Gas Company
Reference Document: MA-12-POGC-001 (HSE Management System Manual),
Task 10 Development of HSE Prequalification Criteria
POGC has a policy of encouraging Local Contractors, suppliers and manufacturers. These
Contractors often have little or no background in HSE Management, and a plan to overcome
these shortcomings shall be developed. Such a plan may require additional supervision, more
explicit procedures or additional training before Local Contractors, suppliers and manufacturers
can be deemed qualified to tender. Contract Holders should supervise this activity, but not
necessarily take an active part in it. However, Contract Holders shall remain responsible for
determining when to prequalify Local Community Contractors.
Contract Holders shall be responsible for the decision to pre-qualify Contractor(s).
In any contract of technical complexity and/or high value, or where a Contractor wishes to be
placed on POGC’s bid list, prequalification of Contractors may be carried out. This enables
POGC to ensure that the contract requirements are met for all technical and financial issues, as
well as meeting document Exhibit L of Contract, (HSE Requirements).
To ensure that HSE prequalification data obtained on each Contractor are standardized and thus
fully comparable, the use of common criteria is essential. Appendix B gives the base case
questionnaire and subsequent scoring system to be used for HSE prequalification. Only the
questionnaire shall be given to each Contractor for completion and return to the Contract
Holder. Contractor submissions can then be assessed by a scoring mechanism which is
consistent, transparent and can be presented to the Tender Board for endorsement.
Document HSW0800 (HSE Contractor Management system evaluation) shall also be used in
conjunction with the HSE prequalification document where Contract Holders deem
prequalification is necessary.
The HSE prequalification questionnaire as provided is a base case only and should be expanded
(or reduced) to meet any specific HSE management skills defined in the Exhibit L of Contract, (HSE
Requirements) for each contract. The questionnaire aims to discover the information required
to assess the extent to which the management of HSE is systematically organized by the
Contractor.
DOCUMENT TITLE: Contract HSE Management Part I Page 13 REVISION 1.0
Pars Oil & Gas Company
Contractor line management shall complete the questionnaire. The Contractor should be
advised by the Contract Holder to cover all activities relating to a contract (including off-site
support) and not just those conducted on POGC sites.
Contract Holders should emphasize the need for complete answers substantiated by supporting
documentation as far as is practicable. It should be remembered that increasing amounts of
detail (and therefore information required to support it) will need to be requested as risk
increases.
If extreme HSE risks are expected then the detail should extend to an HSE Case. An HSE Case
is typically described in a seven-part document. Full details can be obtained from document
MA-12-POGC-001 (HSE Management System Manual). HSE Cases shall be developed by
suitably qualified HSE Professionals, and it is not expected that the Contract Holder will be
personally required to develop any HSE Case necessary for a Contract.
All HSE requirements must be met before any Contractor is allowed to commence work (refer
also Tasks 37 and 38).
Contractors should be encouraged to identify where they exceed POGC requirements and this
excellence should be recognized.
For additional information to assist understanding of the questionnaire, refer to MA-13-POGC-
001(Management of Contractor HSE).
In all cases where it is deemed necessary that a Contractor shall be pre-qualified, the document
references given below must be used in addition to the HSE prequalification questionnaire in
Appendix B.
Deliverable(s): Contractor prequalification assessment for Tender Board endorsement
Reference Documents:
-MA-12-POGC-001(HSE Manual Management)
-MA-13-POGC-001(Management of Contractor HSE)
-Transactions Regulation (of POGC)
-HSW0800 (HSE Contractor Management system evaluation)
Task 11 Tender Board – Endorse HSE Prequalification Criteria
Tender Board shall review and endorse as appropriate the HSE prequalification criteria
submitted by the Contract Holder.
Deliverable(s): -Tender Board minutes, endorsing Prequalification Criteria
DOCUMENT TITLE: Contract HSE Management Part I Page 14 REVISION 1.0
Pars Oil & Gas Company
-Minutes of Meeting to Contract Holder
Reference Document(s): Transactions Regulation (of POGC)
Task 12 Requalify Contractors
Contract Holders, having taken the decision that prequalification is required, shall follow the
procedures given in Task 10.
When Contractor submissions are received, the Contract Holder will rate the submissions as
described in Appendix B. The resulting Contractor Bid List will be submitted to the Tender
Board with recommendation to approve. Contractors who are not approved shall be advised
and assistance to prequalify for future Contracts shall be given, particularly in the case of Local
Contractors, suppliers and manufacturers.
Deliverable(s): Contractor Bid List to Tender Board
Reference Document(s): Transactions Regulation (of POGC)
Task 13 Tender Board – Approve Contractor Bid List
Tender Board shall review and endorse as appropriate the Contractor Bid List.
Deliverable(s): -Approved Bid List
-Minutes of Meeting to Contract Holder
Reference Document(s): Transactions Regulation (of POGC)
DOCUMENT TITLE: Contract HSE Management Part I Page 15 REVISION 1.0
Pars Oil & Gas Company
4. Contract Phase: The Tender Period
Task 14 Contractor Submission: Document HSE Requirements
Contractor(s) shall execute a Hazards and Effects Management Process (HEMP), based on the
information provided in the Contract Scope of Works and Document Exhibit L of Contract, (HSE
Requirements).
Contractor(s) shall detail all HSE issues discovered, including those advised in Exhibit L of
Contract (HSE Requirements) and detail how these risks will be controlled, mitigated and
managed. Details provided shall fully describe the manpower, equipment and broad details of
the Contractor’s HSE policies that will be applied to the management of HSE risk for the
Contract. The Contractor will fully describe the manpower that will be applied to the HSE
management of the Contract, including names, qualifications and experience. Copies of each
individuals CV will be included in the Tender documentation for HSE Requirements.
Contractor(s) shall cover all Contract Phases from mobilization through execution,
demobilization and site restoration.
Contractor(s) shall clearly indicate the policy, procedures and standards to be adopted during
each phase of the Contract.
Deliverable(s): HSE Requirements Submission in Tender Documents
Reference Document(s): Exhibit L of Contract (HSE Requirements)
Task 15 Site Visit
Contract Holder shall arrange a site visit if requested by Contractor(s) or deemed appropriate by
the Contract Holder. The purpose is to allow familiarization with the Contract Scope of Works
and the impact that site conditions may have on all aspects of the Contract including HSE.
In any contract of technical complexity and/or high value, the Contract Holder shall visit the site
to become familiar with site conditions, prior to receipt of Tender Documents.
Deliverable(s): Memo to Contract File detailing site visit
Reference Document(s): Exhibit A of Contract, (Scope of Works, part I,II,III)
DOCUMENT TITLE: Contract HSE Management Part I Page 16 REVISION 1.0
Pars Oil & Gas Company
Task 16 Clarification Meeting
Contract Holder shall hold a clarification meeting with Contractor(s) if requested. See
Mandatory statement below.
Mandatory
Tender clarifications shall be approached with extreme care. Clarifications shall be required
where the evaluation cannot be completed from the Tender due to either ambiguities or
discrepancies.
All Tender clarifications and responses shall be issued in written form using the standard
template in http://portal.pogc.org and shall be forwarded by post or fax. The Unit Contract
Section shall draft and issue the clarifications to the tendered to ensure that the risk of soliciting
a price adjustment is avoided.
Where clarification meetings are held with the individual Contractors these shall be minted and
the minutes agreed with the Contractors. Unit Contract Section shall be present at any
meeting. All technical meetings shall commence with the statement by the Company that no
price change shall result from these technical discussions. Where technical discussions identify
a price impact, the technical issues only shall be discussed.
Meetings and discussions shall be immediately suspended if commercial/financial
issues are raised.
Minutes of a clarification meeting shall be formalised by a letter to the Contractors identifying
the points of discussion and agreement. The Contractors shall confirm, by return, agreement
with the contents of the letter and identify any further points not covered.
Deliverable(s): Minutes of Meeting; Letter to Contractors
Reference Document(s): Transactions Regulation (of POGC)
DOCUMENT TITLE: Contract HSE Management Part I Page 17 REVISION 1.0
Pars Oil & Gas Company
5. Contract Phase: Evaluation and Contract Award
Task 17 Review Contractor Submission – Document HSE Requirements
Contract Holder shall carry out an initial review of each Contractor(s) HSE Requirements
submission(s), and compare it (them) against the requirements of Exhibit L of Contract (HSE
Requirements). A gap analysis shall be made between the requirements of HSE Requirements
and each Contractor submission.
Deliverable(s): Gap Analysis Memo to Contract File
Reference Document(s): Contractor(s) HSE Requirements Tender Submission(s)
Task 18 Evaluate Contractor Submission – Document HSE Requirements
Contract Holder shall meet with Contractor(s) if further clarification is needed for Tender
submission of HSE Requirements. This meeting, if required to be held following written
requests for clarification, shall establish where improvements in proposed HSE risk management
will be required if contract is awarded. Refer to Mandatory statements in Task 16 for the
conduct of any meeting with Contractor(s) during this Contract Phase.
Minutes of a clarification meeting shall be formalised by a letter to the Contractors identifying
the points of discussion and agreement. The Contractors shall confirm, by return, agreement
with the contents of the letter and identify any further points not covered.
Deliverable(s): Minutes of Meeting; Letter to Contractors
Reference Document(s): -HSE Requirements Tender Submission Document
-Transactions Regulation (of POGC)
Task 19 Review Contractor Ability to Manage HSE Risk
Contract Holder shall determine the likelihood that levels and classes of manpower, equipment,
any other resources and policies detailed in the Contractor(s) HSE Requirements Tender
submission will enable the Contractor(s) to manage Contract risk.
HSE equipment and resources would normally include such items as:
• safety equipment, personal protective equipment (PPE)
DOCUMENT TITLE: Contract HSE Management Part I Page 18 REVISION 1.0
Pars Oil & Gas Company
• HSE audits, induction and training, emergency response resources
• medical facilities, first aid training, Medieval, health surveillance
• waste disposal, promotion schemes, journey management
• financial resources of the Contractor that are available for HSE management
The resources allocated for HSE provide only an indication of the Contractor's preparedness (at
the time of tender) to comply with POGC’s HSE requirements. Low HSE resource allocation
could indicate that the Contractor’s organization is at a high level of HSE implementation.
Conversely, it could indicate the Contractor does not understand POGC’s requirements.
Contract Holders should be conscious of the fact that thorough understanding of a Contractor’s
abilities to manage HSE issues can only be obtained by careful study of the whole of a
Contractor’s HSE management system.
Deliverable(s): Memo to Contract File
Reference Document(s): HSE Requirements Tender Submission Document(s)
Task 20 Contractor HSE Assessment
Contract Holder shall evaluate which Contractor(s) will and will NOT require additional POGC
supervision to ensure that the management of HSE risk is carried out correctly. The gap
analysis developed in Task 17 shall be part of the evaluation.
The evaluation may be used as part of the Contract Holder’s award recommendation
presentation to the Tender Board.
Deliverable(s): Memo to Contract File
Reference Document(s): Contractor(s) Exhibit L of Contract (HSE Requirements) Tender
submission(s)
Task 21 Contract Award Recommendation to Tender Board
Contract Holder shall make a Contract award recommendation to the Tender Board, based on
the technical and commercial reports as well as the Contractor HSE assessment. The award
DOCUMENT TITLE: Contract HSE Management Part I Page 19 REVISION 1.0
Pars Oil & Gas Company
recommendation shall highlight any anomalies or additional qualifications accepted from the
original Tender documentation issued.
Deliverable(s): Tender Board presentation
Reference Document(s): Transactions Regulation (of POGC)
Task 22 Advise Contractor of Company (POGC) Representative
Contract Holder shall, upon award of a Contract and using document LE-01-POGC-001 (Letter of
Approval), notify the Contractor of any duly appointed Company (POGC) Representative(s) for
the Contract. This notification of delegated authority shall detail the name of the POGC
employee, the position and reference indicator of that employee and the appropriate delegated
responsibilities and authorities for the given Contract.
POGC shall accept only those authorisation levels specifically delegated in writing by the
Contract Holder.
Contract Holder shall ensure that the delegated Company personnel are fully conversant with
their authorities and responsibilities under the Contract. Authorities defined in the Manual of
Authorities shall not be delegated by the Contract Holder.
Contract Holder shall notify the Contractor, in writing, of all subsequent alterations in authority
levels or personnel.
Document LE-01-POGC-001(Letter of Approval), contains the approved letter to be used for
Contractor notification.
Deliverable(s): Letter to Contractor
Reference Document(s):
- LE-01-POGC-001(Letter of Approval)
-Transactions Regulation (of POGC)
Task 23 Advise Contractor of Company (POGC) Site Representative
Contract Holder shall, upon award of a Contract and using document LE-01-POGC-001(Letter of
Approval), notify the Contractor of any duly appointed Company (POGC) Site Representative(s)
for the Contract. This notification of delegated authority shall detail the name of the POGC
employee, the position and reference indicator of that employee and the appropriate delegated
responsibilities and authorities for the given Contract.
DOCUMENT TITLE: Contract HSE Management Part I Page 20 REVISION 1.0
Pars Oil & Gas Company
POGC shall accept only those authorisation levels specifically delegated in writing by the
Contract Holder.
Contract Holder shall ensure that the delegated Company personnel are fully conversant with
their authorities and responsibilities under the Contract. Authorities defined in the Manual of
Authorities shall not be delegated by the Contract Holder.
Contract Holder shall likewise notify the Contractor, in writing, of all subsequent alterations in
authority levels or personnel.
Document LE-01-POGC-001(Letter of Approval) contains the approved letter to be used for
Contractor notification.
Deliverable(s): Letter to Contractor
Reference Document(s):
-LE-01-POGC-001(Letter of Approval)
-Transactions Regulation (of POGC)
Task 24 Contractor Appoints Key HSE Personnel
Contract Manager shall appoint the key HSE personnel advised in document HSE Requirements
Tender submission. The Contractor’s letter shall include the name(s), qualification(s),
experience and CV(s) of the key HSE personnel. Approval shall be requested from Contract
Holder for the list provided.
Deliverable(s): Letter to Contract Holder
Reference Document(s): Contractor’s Exhibit L of Contract (HSE Requirements) Contract
document
Task 25 Approve Contractor Key HSE Personnel
Contract Holder shall determine that the Contractor’s key HSE personnel are described in the
Contractor’s HSE Requirements Tender submission (refer Task 14). If the list provided in the
Contractor’s advisory letter (refer Task 24) are not the same as in Exhibit L of Contract (HSE
Requirements), the Contract Holder may withhold approval until the Contractor provides
satisfactory explanations and assurances that no reduction in the quality of key HSE personnel
will result from the changes. CVs shall be provided for any replacement personnel different
DOCUMENT TITLE: Contract HSE Management Part I Page 21 REVISION 1.0
Pars Oil & Gas Company
from those described in Exhibit L of Contract (HSE Requirements). In all cases, POGC reserve
the right to interview Contractor’s HSE personnel.
Contract Holder shall approve the Contractor’s appointed key HSE personnel when satisfied that
the quality of management of HSE risk will be maintained to POGC standards.
Contract Holder shall not “unreasonably” withhold approval of the Contractor’s appointed key
HSE personnel.
Deliverable(s): Letter to Contract Manager
Reference Document(s): Contractor’s Exhibit L (HSE Requirements) Contract document
DOCUMENT TITLE: Contract HSE Management Part I Page 22 REVISION 1.0
Pars Oil & Gas Company
6. Contract Phase: Mobilization
Task 26 On Site HSE Workshop
Contract Holder shall conduct a separate on site HSE Workshop. Following both kick-off meetings
(which discuss all issues in a contract, not exclusively HSE – see below) the Contract Holder shall
schedule an onsite HSE Workshop to focus on all outstanding HSE issues relating to a contract.
An HSE Workshop is particularly relevant if the risks within a contract are high to extreme or if
the Scope of Work has changed significantly since the contract award. In the case of Contracts
and/or Contractors where all parties agree in writing that an HSE Workshop may not be
required, the Contract Holder shall obtain clear, written permission from the Contract Owner
that an HSE Workshop need not be held.
The HSE workshop is an interactive session in which both POGC and Contractor should
contribute if it is to be successful. For Contractors with no previous experience of POGC’s HSE
requirements a workshop is a useful mechanism to introduce the Contractor to the details of
POGC’s HSE Management Schedule. If however the workshop requires POGC to teach the
Contractor basic HSE skills, then the effectiveness of the HSE pre-qualification system should be
questioned as this is not the correct role of the workshop and Contract Holders should not find
themselves in this position.
Contract Holder shall hold a POGC internal kick off meeting to ensure that:
• Company Representative and Company Site Representative(s) are fully aware of their
delegated powers under the Contract.
• All personnel involved with the Contract understand the contents of the Contract.
• Key factors considered during the Tender period are explained.
• Presentation and understanding of the penalties objectives and structures.
• Process of instructions, administration and reporting requirements are understood.
• Clarification of handover from existing Contractor (where applicable).
As a minimum, the Contract Holder, Company Representative, Company Site Representative(s),
HSE Professional(s) responsible for the Contract and Unit Contracts Sections shall attend the
POGC internal kick off meeting.
Contract Holder shall conduct a kick off meeting with the Contractor immediately after Contract
award and before the execution of any work. This is essential to ensure that all contractual
DOCUMENT TITLE: Contract HSE Management Part I Page 23 REVISION 1.0
Pars Oil & Gas Company
obligations, including HSE, are thoroughly and mutually understood. The kick-off meeting is the
first formal meeting between Contract Holder and Contractor after the award of a contract.
The agendas of the kick-off meetings and the HSE workshop are entirely at the discretion of the
Contract Holder. Should the Contract Holder require HSE assistance with either kick-off
meeting or the HSE workshop, an HSE professional shall be requested to assist.
During either or both of these meetings, the Contract Holder shall ensure the following
minimum objectives are covered:
• Demonstrate to the Contractor that POGC is fully committed to HSE
• Establish that the Contractor completely understands the risks within the Scope of Work
and has committed the resources detailed in the Contractors tender submission HSE
Requirements. Ensure that the Contractor has or can put systems in place to manage
risk and these are suitable and sufficient to meet standards
• Highlight any areas for improvement in the Contractors HSE Requirements Tender
submission, and agree on any actions necessary, by either POGC or the Contractor, to remove deficiencies
• Resolve any issues arising from a variation to contract since the award
• Introduce any new Contractor(s) to the details of POGC’s HSE policies, standards and
systems
Deliverable(s): Minutes of meetings to Contract file
Reference Document(s): Transactions Regulation (of POGC)
Task 27 Contractor to Prepare HSE Management Plan
Contract Manager shall prepare the Contractor’s HSE Management Plan following the kick off
meeting and the HSE Workshop. This HSE Management plan shall incorporate any POGC
comments arising from the kick off meeting and the HSE Workshop, and also any mandatory
POGC training. Full details for the preparation of an HSE Management Plan are given in
Contract HSE Management (PR-10-POGC-001) Part II.
Contract Manager shall submit the Contractor’s HSE Management Plan to the Contract Holder
for approval.
DOCUMENT TITLE: Contract HSE Management Part I Page 24 REVISION 1.0
Pars Oil & Gas Company
Deliverable(s): Contractor’s HSE Management Plan to Contract Holder
Reference Document(s): HSE Requirements, Tender Submission
Task 28 Review Contractor’s HSE Management Plan
Contract Holder shall review the Contractor’s HSE Management Plan. Any modifications
required by the Contract Holder shall be advised to the Contract Manager. Contract Holder shall
use HSE professional assistance if necessary.
Deliverable(s): Modifications Letter to Contract Manager (if required)
Reference Document(s): Contractor’s HSE Management Plan
Task 29 Approve Contractor’s HSE Management Plan.
Contract Holder shall approve the Contractor’s HSE Management Plan once all modifications
required by the Contract Holder (if any) have been incorporated.
Deliverable(s): Approval Letter to Contract Manager
Reference Document(s): Contractor’s HSE Management Plan
Task 30 Contract Holder Develops POGC HSE Monitoring Program
Contract Holder shall, throughout the period of a Contract, monitor the Contractor’s HSE
performance against the Contractor’s HSE Requirements Contract document and its HSE
Management Plan. Implementation of the POGC HSE monitoring program shall take place when
the Contractor commences mobilization (refer Task 34). The HSE Monitoring Program shall
include a pre-execution HSE audit (refer Task 35).
Contract Holder shall prepare the POGC HSE Monitoring Program using the form contained in
Appendix C. The Program shall be submitted to the Contract Owner for review and approval
(see Tasks 31 & 32).
DOCUMENT TITLE: Contract HSE Management Part I Page 25 REVISION 1.0
Pars Oil & Gas Company
POGC Contract personnel shall complete Contract HSE Performance Reports to detail the results
of all monitoring activities. A template for these reports is provided in Appendix D. Assistance
with using the template is also provided in Appendix D.
The following information provides guidelines on how monitoring is to be carried out to ensure
maximum effectiveness. Refer to the various monitoring methods detailed below on monitoring
objectives (Table 1).
The monitoring program should be adapted to suit the length and nature of the contract. For
short duration contracts monitoring should be weighted to the earliest stages of the work if it is
to have significant influence on the remainder of the contract. As the contract duration gets
longer then monitoring can be spread throughout the contract period. It is however still
desirable to have a significant monitoring effort in the early stages as this will have the most
benefit over the life of the contract.
In addition, the monitoring program should take account of the level of HSE systems 'maturity'
of the Contractor i.e. for the same scope of work, a more experienced Contractor may need less
monitoring than one who is new to working with POGC. The monitoring program shall be
periodically reviewed during the contract and revised according to findings of HSE audits and
inspections. If performance and compliance is found to be good, it may be possible to reduce
the frequency of monitoring. However if performance is poor it may be necessary to increase
monitoring activities. It may also indicate a need to increase direct POGC supervision and
allocate more resources to the contract if the work is to carry on in a safe manner.
An effective monitoring program will take account of these factors and will blend the various
approaches to determine the most effective approach. All monitoring programs shall be agreed
with the Contractor prior to their execution. The kick off meeting is the recommended time to
clarify and agree the program with the Contractor.
Monitoring Methods
The management of any activity requires monitoring, verification and reporting to ensure that
activities are carried out and standards are maintained. The Contractor is expected to have a
framework for monitoring, verification and reporting of the activities covered by the Contract.
The Contract Holder, in turn, is expected to have a framework for verification and reporting to
ensure that the Contractor has adequate control over its activities. This framework is
documented in the POGC HSE Monitoring Program for each contract.
DOCUMENT TITLE: Contract HSE Management Part I Page 26 REVISION 1.0
Pars Oil & Gas Company
Effective control requires a process of monitoring through observation and/or measurement of what is actually happening, comparison with specified requirements, feedback and where necessary, correction. To be effective, the monitoring must be performed at several different levels of detail. Table 11ists a range of monitoring methods.
DOCUMENT TITLE: Contract HSE Management Part I Page 27 REVISION 1.0
Pars Oil & Gas Company
Table 1: Monitoring Methods
Monitoring Method Monitoring Objective
Unsafe act auditing A measure of how well individuals understand basic HSE standards.
A demonstration of management commitment to detail.
Supervisory checks A demonstration of management commitment to HSE.
A reinforcement of the role of the HSE supervisor.
HSE inspection A management check to ensure standards are being achieved.
Non compliance is recorded and remedial action instigated.
Localized improvements should result from an HSE inspection.
HSE audit A management check to ensure, commensurate with risk, that the agreed
systems are in place and standards are achieved.
Non compliances are recorded and remedial action is instigated.
Contract wide improvements should result from an HSE audit.
HSE Review A management check that all action being taken to manage HSE is suitable and
sufficient to ensure business objectives are being met.
Current systems are challenged and new systems instigated if considered
necessary.
Recommendations are recorded and remedial action agreed.
A complete change of approach towards HSE management should result from a
review.
Monthly Contract
Review Meetings
Good practice for commercial, technical and HSE monitoring.
Shall review the results of all the above monitoring methods plus results of any
performance indicators reported during the contract.
A formal agenda shall be set and minutes recorded.
The first meeting shall be chaired by the Contract Holder; thereafter the
Company Site Representative.
The Contract Manager should be present plus any other parties, both POGC and
Contractor, who are directly influenced by the subject(s) under discussion.
Meetings should be held on site.
A clear distinction should be made between an HSE audit and an HSE inspection in the HSE monitoring
program:
DOCUMENT TITLE: Contract HSE Management Part I Page 28 REVISION 1.0
Pars Oil & Gas Company
HSE audits are reviews of management controls to ensure contractual HSE requirements are fulfilled
HSE inspections seek to identify specific deficiencies in meeting contractual HSE requirements
For example, an inspection may note that a vehicle has a defective rear light and require it to be fixed; an audit would seek to establish that there is a defect reporting system which would ensure such deficiencies are identified, reported and corrected in a timely manner.
Although POGC representatives may carry out unsafe act auditing, hardware inspections and supervisory
checks, these are essentially the responsibility of the Contractor. The main emphasis of the inspections
and audits performed by the POGC Contract Holder (or his representatives) is to verify and report that
the Contractor’s systems for Unsafe Act Auditing, hardware inspections, supervision checks etc. are in
place and being implemented effectively. In order to encourage improvement in Contractor performance, POGC's responses to deviations from the
Contractor’s Exhibit L (HSE Requirements) Contract document and the Contractor’s HSE Management Plan
must be predictable and consistent. This requires clear standards against which the Contractor is
monitored, transparent criteria for assessing performance and a fixed procedure for deciding upon the
appropriate response when non-compliance is found. Work scopes are rarely static and changes are inevitable, especially in longer contracts. Contract Holder
shall have in place a procedure, agreed with the Contractor, for amendments to the Contractor’s HSE
Management Plan. The procedure for any amendments to the HSE Management Plan shall, at all stages,
include the Contractor – all changes shall be made only with their knowledge and agreement. As the HSE
Management Plan is frequently a contractual document, major alterations may require agreement on
variations to contract. The HSE monitoring program is an internal POGC program but, as a matter of courtesy and for smooth
working relationships, changes shall be communicated in advance and in writing to the Contractor, whose
confirmation of and relevant comments on the changes shall be returned in writing. Deliverable(s): proposed HSE Monitoring Program
Reference Document(s): Contractor’s Exhibit L (HSE Requirements) Contract document
Contractor’s HSE Management Plan
DOCUMENT TITLE: Contract HSE Management Part I Page 29 REVISION 1.0
Pars Oil & Gas Company
Task 31 Contract Owner Review HSE Monitoring Program Contract Owner shall review the proposed HSE monitoring program, confirming resources, competencies
and capabilities of Contract Holder, Company (POGC) Representative and Company (POGC) Site
Representative to discharge their duties taking into account level of HSE Risk. Deliverable(s): None
Reference Document(s): proposed HSE Monitoring Program
Task 32 Contract Owner Approve HSE Monitoring Program
Contract Owner shall approve the proposed HSE monitoring program once confirmation is obtained that all
necessary resources, competencies and capabilities of Contract Holder, Company (POGC) Representative
and Company (POGC) Site Representative to discharge their duties are in place and appropriate for the
level of risk in the Contract. Deliverable(s): Memo to Contract File Approving HSE Monitoring Program
Reference Document(s): approved HSE Monitoring Program
Task 33 POGC and Contractor Training
Contract Holder shall ensure that all POGC and Contractor personnel training has been completed with all
personnel involved receiving approval from HSE trainers. Training records will contain name(s) of
trainee(s), name of training course and completion grade (Satisfactory or Unsatisfactory). Deliverable(s): POGC and Contractor Training records
Reference Document(s): Tasks 6, 7 and 27 above.
Task 34 Contractor Mobilization
Contract Manager shall commence mobilization activities only upon satisfactory completion of Tasks 24 and
27 and having confirmed receipt of all necessary POGC approvals on file.
DOCUMENT TITLE: Contract HSE Management Part I Page 30 REVISION 1.0
Pars Oil & Gas Company
Contract Holder shall, concurrent with Contractor mobilization, implements the HSE Monitoring Program.
Deliverable(s): Contract HSE Performance Report – Mobilization Status
Reference Document(s): -Contract HSE Monitoring Program
-Contractor’s HSE Management Plan
-Contractor’s Exhibit L (HSE Requirements) Contract document
Task 35 Pre-execution HSE Audit of Contractor Contract Holder shall conduct a pre-execution HSE audit to determine that the Contractor has achieved the
pre-execution targets stated in the Contractor’s Exhibit L (HSE Requirements) Contract document and HSE
Management Plan, and that mobilization is complete. The execution of the post mobilization phase of Contract work shall not be initiated until the requirements
of the pre-execution HSE audit have been met. For some contracts it may not be possible to carry out a
pre-execution HSE audit at a single point in time. This often occurs with long mobilization periods. It may
then be necessary to specify a list of HSE audits/checks/verifications to be completed during the
mobilization period. The Contract Holder must approve each of the checks before subsequent actions can
be started. For example, the Contractor cannot start transporting material from the Coast until drivers
have been qualified and vehicles have passed inspection checks. In such a situation, the pre-execution
HSE audit may consist of the Contract Holder determining the satisfactory completion of driver training and
vehicle inspection before the field site is audited and fieldwork begins. Mobilization payments may be
attached to specific pre-execution requirements. The pre-execution HSE audit should focus on the pre-execution requirements as stated in the Contract, the
Exhibit L (HSE Requirements), and the general capability of the Contractor to meet and maintain the
required standards of HSE during the execution of the contract. It should be built around the standards
specified in the Exhibit L (HSE Requirements) and in the HSE Management Plan. It should provide the
Contract Holder with confidence that the Contractor in the field understands these standards and that the
systems put in place by the Contractor will ensure these standards are met. These systems should ensure
that failure to meet standards will be quickly recognized either by the Contractor's Site Representative or
by the Company (POGC) Site Representative. Any action agreed to eliminate any recognized deficiency in the Contractor’s HSE Management Plan should
be verified in the field and at Contractor’s offices during the HSE audit. HSE Management Plans and their
DOCUMENT TITLE: Contract HSE Management Part I Page 31 REVISION 1.0
Pars Oil & Gas Company
remedial action plans, which are acceptable on paper, have sometimes been found to be lacking in the
field, and it is essential for all aspects of HSE in a Contract that the working relationship between POGC
personnel and Contractor personnel is continuously one of mutual respect, courtesy and cooperation. Following any HSE audit, or any inspection in support of an audit, the resulting findings should be
discussed with the Contractor's site and office management. This will help to avoid misunderstandings and
aid the implementation of the inspection/HSE audit recommendations. Discussions shall be minuted, with
a copy to the Contractor; Contractor shall respond to the Contract Holder, confirming the minutes and
advising the remediation schedule and/or confirming that all audit recommendations will be or have been
carried out. The Contract Holder should agree with the Contractor on a procedure for monitoring the implementation of
the inspection/HSE audit findings. The Contract Holder can delegate the necessary authority to the
Contractor for undertaking the administration of these procedures if regular status reports are presented at
the contract review meetings. Contractor shall ensure that the Contract Holder documents this approval. Effective follow up of inspection/HSE audit findings is a prime indicator of management commitment. As a
consequence it is important that all findings are followed up and cleared in a satisfactory manner. Inspection/HSE Audit finding reports should:
• detail personnel responsible for correcting each finding
• be measurable - i.e. state exactly what remedy is required by each finding
• state completion dates for each finding
Deliverable(s):
-Contract Holder letter to Contractor giving minutes of inspection/HSE audit findings meeting
-Contractor letter to Contract Holder confirming minutes of inspection/HSE audit findings meeting
-Contract Holder letter to Contractor documenting delegation of authority to undertake remediation of
inspection/HSE audit findings.
Reference Document(s): - HSE Requirements Tender submission
-Contractor’s HSE Management Plan
DOCUMENT TITLE: Contract HSE Management Part I Page 32 REVISION 1.0
Pars Oil & Gas Company
Task 36 Contractor Completes Pre-execution HSE audit Items
Contract Manager shall complete remediation of all findings resulting from the pre-execution HSE Audit
Deliverable(s): Remediation completed and action items “Signed off” by Contract Manager
Reference Document(s): Minutes of Pre-execution HSE Audit meeting.
Task 37 Contractor – Readiness to Commence
Contract Manager shall advise, in writing, Contract Holder that all items from the pre-execution audit
requiring remediation have been completed.
Contract Manager shall issue Pre-execution Completion Report and request HSE Certificate.
Deliverable(s): -Letter to Contract Holder
-Pre-execution Completion Report
-HSE Certificate request
Reference Document(s): Minutes of Pre-execution HSE Audit meeting
Task 38 Issue HSE Certificate
Contract Holder shall issue the HSE Certificate (refer Appendix E) to Contract Manager, subject to any
exceptions noted on the HSE Certificate.
Contract Holder shall withhold issuing the HSE Certificate if any of the activities listed on the HSE
Certificate require exception that leads to unsafe operating conditions.
Deliverable(s): HSE Certificate
Reference Document(s): -Minutes of Pre-execution HSE Audit meeting
-HSE Certificate (Appendix E)
DOCUMENT TITLE: Contract HSE Management Part I Page 33 REVISION 1.0
Pars Oil & Gas Company
7. Contract Phase: Execution
Mandatory
Contract Holder shall assume single point responsibility to ensure the effective execution of the Contract
by the Contractor. This shall require proper management of POGC resources and provisions involved in
the execution of the Contract (personnel, facilities, equipment, materials, expenditure forecasts, user
requirements etc), and full compliance with the Contract requirements.
Contract Holder shall include as a minimum:
• Supervision of the Work/Services period.
• Verification and enforcement of HSE requirements.
• Verification and enforcement of the Contractor’s Quality system.
• Monitoring of financial controls; commitments to date; values of work done; invoices received and
payments made, as well as performance against Company controls.
• Certification of Work/Services and acceptance of Milestones.
• Monitor usage of Company provided facilities and materials throughout Contract period.
• Any other specific Contract requirements.
• Maintain up-to-date register of all correspondence between Contractor and the Company, this
register shall include as a minimum: - date of receipt or dispatch together with date of relevant response.
• Claims Register update.
Deliverable(s): All necessary memos, letters to Contractor and reports.
Reference Document(s): Transactions Regulation (of POGC)
Task 39 Supervision
Company (POGC) Representative/Site Representative shall have continuous assurance and verification
that Contractor HSE systems are performing in accordance with the Contractor’s HSE Management Plan.
Deliverable(s): Contract HSE Performance Reports (refer Appendix D)
Reference Document(s): Contractor’s HSE Management Plan
DOCUMENT TITLE: Contract HSE Management Part I Page 34 REVISION 1.0
Pars Oil & Gas Company
Task 40 Monitor Contractor’s implementation of HSE Management Plan
Contract Owner/Holder/Site Representative shall monitor the Contractor’s performance against the
Contractor’s HSE Management Plan, using the POGC HSE Monitoring Program.
Contract Owner/Contract Holder shall participate in all HSE audits, incident investigations, meetings and
reviews.
Deliverable(s): Contract HSE Performance Reports (refer Appendix D)
Reference Document(s):
-Contractor’s HSE Management Plan
-POGC HSE Monitoring Program
DOCUMENT TITLE: Contract HSE Management Part I Page 35 REVISION 1.0
Pars Oil & Gas Company
Task 41 Additional HSE Requirements
Contract Holder shall maintain, continuously monitor, update and make available on a quarterly basis
the Health Safety & Environment performance criteria in accordance with Transactions Regulation (of
POGC).
Contract Holder shall perform a Hazards and Effects Management Process (HEMP) periodically in the
execution of a Contract. In particular, revised HEMP shall be triggered by any additional requirements
that lead to an increased Scope of Works, thereby requiring a Variation in the Contract.
Revision will also allow the incorporation of any additional HSE requirements arising from the process of
Contract execution. Any additional POGC-originated HSE requirements discovered, including those
arising from “Substantial Completion”, shall be advised to the Contract and Procurement Systems and
Procedures Department (SUPPORT SERVICES) and to the Contractor.
Deliverable(s):
Note to Contract File, Variation to Contract – POGC HSE Requirements
Memo to SUPPORT SERVICES, Variation to Contract – POGC HSE Requirements
Letter to Contractor, Variation to Contract – POGC HSE Requirements
Reference Document(s): -Contractor’s HSE Management Plan
-Transactions Regulation (of POGC)
Task 42 Contractor - Revise HSE Management Plan
Contract Manager shall revise the HSE Management Plan as often as required to accommodate POGC’s
advice that additional HSE requirements need to be incorporated. All unforeseen work activities shall
be assessed and incorporated. Authorization for all deviations from and/or amendments to the
Contractor’s HSE Management Plan shall be sought from the Contract Holder.
Deliverable(s):
Letter to Contract Holder advising revised Contractor’s HSE Management Plan
Reference Document(s):
Letter to Contractor, Variation to Contract – POGC HSE Requirements
Contractor’s HSE Management Plan
DOCUMENT TITLE: Contract HSE Management Part I Page 36 REVISION 1.0
Pars Oil & Gas Company
Task 43 Review Revised Contractor’s HSE Management Plan
Contract Holder shall review Contractor’s revised HSE Management Plan. Any further revisions required
by POGC shall be advised to Contractor.
Deliverable(s): -Note to Contract file
-Letter to Contractor as required by additional revisions
Reference Document(s):
Letter to Contractor, Variation to Contract – POGC HSE Requirements
Letter to Contract Holder advising revised Contractor’s HSE Management Plan
Revised Contractor’s HSE Management Plan
Task 44 Approve Revised Contractor’s HSE Management Plan
Contract Holder shall approve revised Contractor’s HSE Management Plan when all proposed revisions
fulfill POGC’s HSE requirements.
Deliverable(s): Letter to Contractor approving revised HSE Management Plan
Reference Document(s):
-Letter to Contractor, Variation to Contract – POGC HSE Requirements
-Letter to Contract Holder advising revised Contractor’s HSE Management Plan
-Revised Contractor’s HSE Management Plan
Task 45 Implement POGC HSE Deviations and Amendments
Contract Holder shall notify Contract Manager that any POGC HSE deviations and/or amendments to the
Contractor’s HSE Management Plan are to be implemented.
Deliverable(s): Letter to Contractor authorizing implementation of Contractor’s revised HSE
Management Plan
Reference Document(s):
-Letter to Contractor, Variation to Contract – POGC HSE Requirements
DOCUMENT TITLE: Contract HSE Management Part I Page 37 REVISION 1.0
Pars Oil & Gas Company
-Letter to Contract Holder advising revised Contractor’s HSE Management Plan
-Revised Contractor’s HSE Management Plan
Task 46 Contractor – Revise HSE Management Plan
Contract Manager shall revise the HSE Management Plan as often as required by circumstances arising
from the execution of the Contract. The Contract Holder shall be advised of any required variations
and/or amendments.
Contract Manager shall advise Contract Holder of variations to Contract Scope of Works as required by
revised HSE Management Plan.
Deliverable(s):
Letter to Contract Holder advising required variations and/or amendments
Reference Document(s): Contractor’s HSE Management Plan
Task 47 Review Contractor revised HSE Management Plan
Contract Holder shall review the Contractor revised HSE Management Plan and variations to the
Contract Scope of Works. Any further revisions required by POGC shall be advised to Contractor.
Deliverable(s):
-Note to Contract file
- Letter to Contractor as required by additional revisions
Reference Document(s):
-Letter to Contract Holder advising required variations and/or amendments
-Contractor revised HSE Management Plan
DOCUMENT TITLE: Contract HSE Management Part I Page 38 REVISION 1.0
Pars Oil & Gas Company
Task 48 Approve Contractor revised HSE Management Plan
Contract Holder shall advise Contract Manager that the Contractor revised HSE Management Plan is
approved.
Deliverable(s):
-Note to Contract file
-Letter to Contractor approving revised HSE Management Plan
-Memo to SUPPORT SERVICES advising of amendments to HSE Management Plan
Reference Document(s):
-Contractor revised HSE Management Plan
- Exhibit A of Contract, (Scope of Works, part I,II,III)
NOTE TO POGC PERSONNEL INVOLVED IN MANAGEMENT OF CONTRACTS:
TASKS 42 THROUGH 48 ARE ITERATIVE AND SHALL BE REPEATED AS OFTEN AS REQUIRED THROUGHOUT THE EXECUTION OF A CONTRACT.
Task 49 HSE Penalties and Defaults
Company (POGC) Representative/Site Representative(s) shall apply HSE penalties and defaults on the
Contractor, as allowed in the Contract, for unauthorized deviation(s) from the Contractor’s HSE
Management Plan and Exhibit L (HSE Requirements). The Contract Manager is to be advised in writing
of all Penalties and Defaults being imposed.
HSE Penalties and Defaults shall be determined from the POGC HSE Monitoring Program and its related
inspections and audits, as well as any Contract HSE Performance Reports detailing unauthorized
deviations.
Deliverable(s): Letter to Contractor advising HSE Penalties and Defaults
Reference Document(s): -POGC HSE Monitoring Program
-Contract HSE Performance Reports
DOCUMENT TITLE: Contract HSE Management Part I Page 39 REVISION 1.0
Pars Oil & Gas Company
-Contractor’s HSE Management Plan
-Contractor’s HSE Requirements, Tender submission
Task 50 Contract HSE Performance Reports
Contract Holder shall prepare Contract HSE Performance Reports (refer Appendix D) providing feedback
to POGC Management on the overall HSE performance of the Contractor and any sub-Contractors.
Reports to be submitted as frequently as required (usually annually in a long-term contract), or as
requested, to Contract Owner and Service Group Custodian.
Deliverable(s): Contract HSE Performance Reports
Reference Document(s): -POGC HSE Monitoring Program
-Contract HSE Performance Reports
DOCUMENT TITLE: Contract HSE Management Part I Page 40 REVISION 1.0
Pars Oil & Gas Company
8. Contract Phase: Demobilization
Task 51 Site Restoration – Compliance
Company (POGC) Representative/Site Representative shall ensure that the Contractor demobilizes from
the site of work in accordance with all contractual agreements including the Contractor’s HSE
Management Plan.
Company (POGC) Representative/Site Representative shall issue the HSE Site Restoration Certificate
(refer Appendix F) for approval when demobilization and site restoration are complete and satisfy all
contractual agreements.
Deliverable(s): Site Restoration Certificate for Approval by Contract Holder
Reference Document(s):
All relevant Contract documents, including the Contractor’s HSE Management Plan.
Task 52 Site Restoration Certificate Approval
Contract Holder shall approve the Site Restoration Certificate (refer Appendix F) and issue it to the
Contractor.
Company (POGC) Representative/Site Representative may sign the Site Restoration Certificate at the
discretion and approval of the Contract Holder.
Deliverable(s): Approved Site Restoration Certificate
Reference Document(s):
All relevant Contract documents, including the Contractor’s HSE Management Plan.
DOCUMENT TITLE: Contract HSE Management Part I Page 41 REVISION 1.0
Pars Oil & Gas Company
9. Contract Phase: Close Out
Task 53 Final Contract HSE Performance Report
Contract Holder shall prepare the Final Contract HSE Performance Report to be submitted to the
Contract Owner and Service Group Custodian. The report is to be finalized and submitted not later than
90 days after demobilization.
Service Group Custodian shall review report, update the Service Group as necessary and file the report
for future use.
Close Out Responsibilities for Contracts over US $200,000:
Mandatory for Contract Close Out Reports
Contract Holder shall:
• Agree and confirm physical status of the Work /Services against the Contract.
• Issue substantial completion certificate for Lump Sum Contracts.
• Note all items to be completed and/or rectified and formally document with Contractor.
• Prepare a Contractor Performance Report to record the execution of the Contract, including technical
competence, Organization and all HSE aspects.
• Conclude all claims and disputes in line with Company Procedures.
• Ensure any penalties have been applied in accordance with the Contract.
• Issue the Completion Certificate, applicable for all Contracts.
• Compile the Contract feedback report, for Contract values of over US$10M
• Consolidate all documentation to support close out.
• Confirm that all charges made under the Contract are valid.
• Agree and sign the statement of final account, applicable for all Contracts.
Note: The Contract Holder’s responsibility for management of the Contract shall end on completion of
the statement of final account
Deliverable(s): Final Contract HSE Performance Report
Reference Document(s): -CONTRACT HSE MANAGEMEN (PR-10-POGC-001),Appendix D
-According current national laws and regulations in Lump Sum Contract
-Transactions Regulation (of POGC)
DOCUMENT TITLE: Contract HSE Management Part I Page 42 REVISION 1.0
Pars Oil & Gas Company
Appendix MC: HSE Checklist for Minor Contracts
Contract Holder Name: Contracting Company:
Contract Number:
Item
No.
Contract Holder Action Required for Contract?
Coastal Interior
If Required,
Action
Completed?
Pre-execution of Contract:
1 POGC Emergency number/procedure explained MANDATORY MANDATORY NO
2 Permit To Work requirements explained MANDATORY MANDATORY NO
3 Report ability of HSE incidents explained MANDATORY MANDATORY NO
4 POGC Road Journey Management Procedures
explained
Not required MANDATORY NO
5 Vehicle(s) meet POGC standards Not required MANDATORY NO
6 Area Coordinator briefed about interior visit Not required
NO
NO
7 HSE workshop with contractor completed
NO
NO
NO
8 Identification of Hazards & Effects completed
for Contract Scope of Work
NO
NO
NO
9 HSE Certificate signed
NO
NO
NO
10 HSE Training requirements explained
NO
NO
NO
11 HSE Training commenced
NO
NO
NO
During Execution of Contract:
11 Contractor working practices monitored by
Company Site Rep.
NO
NO
NO
12 HSE Training completed
NO
NO
NO
DOCUMENT TITLE: Contract HSE Management Part I Page 43 REVISION 1.0
Pars Oil & Gas Company
Post-execution of Contract:
13 Site Restoration Certificate Issued
NO
NO
NO
14 Contract HSE Report filed
NO
NO
NO
All Mandatory and Contract Requirements completed
Signed:
Date:
Contract Holder
All Mandatory and Contract HSE Requirements explained and understood.
Signed: Date:
Contractor
Pars Oil & Gas Company
Appendix A: Summary - Contract HSE Management Procedure
Contract Number: Contract Title:
Prepared by: Contract Holder
Approved by: Contract Owner
Name and Reference Indicator:
Name and Reference Indicator:
Date:
Date:
Contract Phase: Planning and Invitation to Tender
Task
Number
Activity
Action
Activity Description
Reference
Deliverable(s)
1
Appoint Contract Holder
Owner
Appoint Contract Holder (CH) and, if required, Company (POGC) Representative (CR)
Transactions Regulation (of
POGC)
Memo to file
2
Prepare Contract Scope
of Work
Holder
Define work and/or services required for Contract:
assess activities required for each contract commensurate with level of HSE risk
evaluate resources required to manage HSE in the contract
Exhibit L (HSE
Requirements)contract
Doc.
Memo to file
3
Prepare Contract
Schedule
Holder
Prepare contract schedule by inserting planned dates
Transactions Regulation (of
POGC)
Contract Schedule
4
Develop Contract
Strategy
Holder
Summarize work and/or services required from mobilization to demobilization, with particular
attention to all interfaces and define the boundaries of the contract
Transactions Regulation (of
POGC)
Contract Strategy
5
Approval of Contract
Owner
Contract Owner (CO) to approve Contract Strategy
Transactions Regulation (of
Memo to file
DOCUMENT TITLE: Contract HSE Management Part I REVISION 1.0 Page 45
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 46 REVISION 1.0
Strategy POGC)
6
Conduct HSE
Assessment
Holder
Conduct a structured, formal HSE Assessment of the contract, using the Scope, Schedule
and Strategy documents. Identify major hazards and methods for their control (Hazards and
Effects Management Process – HEMP)
Exhibit L (HSE
Requirements) contract
Doc.
MA-12-POGC-001 (HSE
Management System
Manual),
Formal HSE Assessment
for doc.HSE
Requirements
7
Prepare Exhibit L (HSE
Requirements)contract
Doc.
Holder
Use the results of the HSE Assessment to develop document Exhibit L (HSE
Requirements)contract Doc.
for inclusion in Tender
Exhibit L (HSE
Requirements)contract
Doc.
Exhibit L (HSE
Requirements)contract
Doc.
8
Prepare POGC Contract
HSE M’gmnt Schedule
Holder
Prepare POGC Contract HSE Management Schedule using the results of the HSE Assessment.
Send to CO for approval
MA-12-POGC-001 (HSE
Management System
Manual),
POGC Contract HSE
M’gmnt Schedule
9
Approve POGC Contract
HSE M’gmnt Schedule
Owner
Approve POGC Contract HSE Management Schedule. Make necessary resources available.
MA-12-POGC-001 (HSE
Management System
Manual),
Memo to file
10
Develop HSE Pre-
Qualification Criteria
Holder
Develop HSE Pre-qualification criteria based on the HSE Assessment and HSE Requirements.
Submit to Tender Board for endorsement.
MA-12-POGC-001(HSE
Manual Management) &
MA-13-POGC-001(HSE
Manual Management)
HSE Pre-qualification
criteria
11
Endorse HSE Pre-
Qualification Criteria
Tender
Board
Tender Board to endorse HSE Pre-qualification Criteria
Transactions Regulation (of
POGC)
Memo to Contract File
12
Pre-qualify Contractors
Holder
Perform HSE pre-qualification exercise to ensure contractors invited to bid meet or exceed
POGC’s HSE standards. Submit to Tender Board for approval
Transactions Regulation (of
POGC)
Contractor bid list
13
Approve Contractor bid
Tender
Tender Board to approve Contractor Bid list
Transactions Regulation (of
Approved Contractor Bid
DOCUMENT TITLE: Contract HSE Management Part I Page 47 REVISION 1.0
Pars Oil & Gas Company
list
Board POGC)
List
Appendix A: (Continued)
Contract Phase: The Tender Period
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
14
Contractor Submission
HSE Requirements
Contract
Manager
Perform HEMP. Detail all HSE issues discovered including those in Exhibit L (HSE
Requirements)contract Doc.
as issued and detail how these risks will be controlled, mitigated and managed. Detail any
HSE issues additional to those outlined in Exhibit L (HSE Requirements) Contract Doc.
and include how these will be controlled, mitigated and managed.
Exhibit L (HSE
Requirements)contract Doc.
HSE Requirements
submission
15
Site Visit
Holder
Arrange any Contractor requested site visits.
Scope of Work
Minutes of Site Visit
16
Clarification Meeting
Holder
Arrange any Contractor requested tender clarification meeting. Arrange meeting(s) to
clarify technical (including HSE) aspects of bid documents if necessary.
Transactions Regulation (of
POGC)
Letter to
Contractors;
Minutes of Meet.
Contract Phase: Evaluation and Contract Award
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
17
Review Contractor
HSE Requirements
Submission
Holder
Initial review of Contractor’s submission against the requirements of Exhibit L (HSE
Requirements) Contract Doc. . Carry out gap analysis between Scope of Works and
Contractor’s HSE Requirements submission.
Exhibit L (HSE
Requirements) Contract
Doc.
Gap Analysis Memo
to file
DOCUMENT TITLE: Contract HSE Management Part I Page 48 REVISION 1.0
Pars Oil & Gas Company
18
Evaluate Contractor HSE
Requirements Submission
Holder
Meet with Contractors and clarify HSE Requirements Submission to make bid compliant.
Establish where improvements will be required if contract is awarded.
Exhibit L (HSE
Requirements) Contract
Doc.
Letter(s) to
Contractor(s)
19
Review Contractor(s)
Ability to Manage HSE
Risk
Holder
Determine the likelihood that levels and classes of manpower, equipment, other resources
and policies proposed in Contractor(s) Exhibit L (HSE Requirements) Contract Doc.
Submission will enable the Contractor(s) to manage contract HSE risk.
Exhibit L (HSE
Requirements) Contract
Doc.
Memo to Contract
file
20
Contractor HSE
assessment
Holder
Assess which Contractor(s) will require additional POGC supervision to ensure Exhibit L (HSE
Requirements) Contract Doc. Submission is carried out correctly; assess which
Contractor(s) will NOT require additional POGC supervision. Advise SUPPORT SERVICES.
Exhibit L (HSE
Requirements) Contract
Doc.
Memo to Contract
file
21
Make recommendation
Holder
The CH shall make a recommendation for contract award to the Tender Board, highlighting
any anomalies or qualifications relating to each Contractor.
Transactions Regulation (of
POGC)
Tender Board
presentation
22
Advise Contractor of
POGC Representative
Holder
Confirm appointment of Company (POGC) Representative (CR) and advise Contractor by
letter using document LE-01-POGC-001(Letter of Approval).
Transactions Regulation (of
POGC)
LE-01-POGC-
001(Letter of
Approval)
23
Advise Contractor of
POGC Site Representative
Holder
Appoint Company (POGC) Site Representative and advise Contractor by letter, using
document LE-01-POGC-001(Letter of Approval).
Transactions Regulation (of
POGC)
LE-01-POGC-
001(Letter of
Approval)
24
Appoint Contractor key
personnel
Contract
Manager
Appointment of Contractor’s HSE key personnel listed in Exhibit L (HSE Requirements)
Contract Doc. . Advise CH.
Exhibit L (HSE
Requirements) Contract
Doc.
Letter to Contract
Holder
25
Approve Contractor key
personnel
Holder
Confirm to Contract Manager POGC’s acceptance of HSE key personnel listed in the contract.
Exhibit L (HSE
Requirements) Contract
Doc.
Letter to Contract
M’ger
DOCUMENT TITLE: Contract HSE Management Part I Page 49 REVISION 1.0
Pars Oil & Gas Company
Appendix A: (Continued)
Contract Phase: Mobilization
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
26
Kick off meetings and
HSE workshop
Holder
Conduct POGC internal kick off meeting and POGC/Contractor Kick off meeting to ensure
that HSE and other contractual obligations are thoroughly understood. Hold a separate HSE
Workshop at site.
Transactions Regulation (of
POGC)
Minutes of meetings
and HSE workshop
27
Prepare HSE Management
Plan
Contract
Manager
Prepare HSE Management Plan, incorporating any POGC comments arising from the kick off
meeting and the HSE Workshop, including any necessary POGC mandatory training, for
submission to CH
Exhibit L (HSE
Requirements) Contract
Doc.
HSE Management
Plan
28
Review Contractor’s HSE
Management Plan
Holder
Review Contractor’s HSE Management Plan; issue Modifications Letter if required.
Exhibit L (HSE
Requirements) Contract
Doc.
Modifications letter
if required.
29
Approve Contractor’s HSE
Management Plan
Holder
Advise Contract Manager of CH’s approval of HSE Management Plan
Contractor’s HSE M’gmnt
Plan
Letter to Contractor
30
Develop HSE monitoring
program
Holder
Detail how the performance of the Contractor will be monitored against the Contractor’s
HSE Management Plan. Prepare the HSE Monitoring Program documentation
HSE M’gmnt Plan
Proposed HSE
Monitoring Plan
31
Review HSE Monitoring
Program
Owner
Contract Owner shall review HSE Monitoring Plan
Proposed plan
32
Approve HSE Monitoring
Program
Owner
Contract Owner shall approve HSE Monitoring Plan and advise CH
Approved plan
Memo to file
33
POGC & Contractor HSE
training
Holder
Schedule and complete all necessary POGC and Contractor staff training as identified in the
POGC and Contractor’s HSE assessments
Tasks 6,7, and 27
Training records
DOCUMENT TITLE: Contract HSE Management Part I Page 50 REVISION 1.0
Pars Oil & Gas Company
34
Contractor Mobilization
Contract
Manager
Contractor to commence mobilization activities. CH to monitor, inspect and audit to ensure
that Contractor complies with the Contractor’s HSE Management Plan and Exhibit L (HSE
Requirements) Contract Doc.
HSE Monitoring Program
Contract HSE
Performance
Report.
35
Pre-execution HSE Audit
of Contractor
Holder
Conduct an audit against the Contractor’s HSE Management Plan to determine if the
Contractor has achieved the pre-execution targets stated in the Exhibit L (HSE
Requirements) Contract Doc. and Contractor’s HSE Management Plan, and that mobilization
is complete. Forward report to Contract Manager.
HSE M’gmnt Plan
Minutes of Pre-
execution meeting
36
Complete Pre-execution
HSE Audit Items
Contract
Manager
Contractor completes all items flagged in the pre-execution HSE audit.
Minutes of Pre-exec.
meeting
37
Contractor – Readiness to
Commence
Contract
Manager
Contractor confirms to CH that all pre-execution items are completed and issues Pre-
execution Completion report. CM also forwards Contractor’s HSE certificate (CONTRACT
HSE MANAGEMENT (PR-10-POGC-001), Parts II, Appendix 1) for authorization by CH
Minutes of Pre-exec.
meeting
Completion report &
HSE Certificate
38
Issue HSE Certificate
Holder
If no unsafe operating conditions exist, CH issues the HSE Certificate (refer Appendix E) to
Contract Manager, subject to any exceptions noted on the HSE Certificate.
Minutes of Pre-exec.
meeting
HSE Certificate
DOCUMENT TITLE: Contract HSE Management Part I Page 51 REVISION 1.0
Pars Oil & Gas Company
Appendix A: (Continued)
Contract Phase: Execution
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
39
Supervision
POGC
Rep/Site
Rep
Continuous assurance and verification that Contractor systems are performing in accordance
with the Contractor’s HSE Management Plan
HSE M’gmnt Plan
Contract HSE
Performance
Reports
40
Monitor implementation of
HSE M’gmnt Plan
Owner/Ho
lder/ Site
Rep.
Monitor Contractor’s performance against the Contractor’s HSE Management Plan using the
HSE Monitoring Program. CO and CH to participate in audits, incident investigations,
meetings and reviews.
HSE M’gmnt Plan
Contract HSE
Performance
Reports
41
Additional HSE
Requirements
Holder
Carry out HEMP to incorporate any additional HSE requirements arising from contract
execution leading to enlarged Scope of Work. Advise SUPPORT SERVICES and Contractor of
any additional POGC HSE requirements.
Transactions Regulation (of
POGC)
Variation letter to
Contractor; memo
to file
42
Contractor – revise HSE
Management Plan
Contract
Manager
Following on from the variation letter received from POGC, any unforeseen work activities
shall be assessed and the Contractor shall revise HSE Management Plan accordingly.
Authorization for all deviations and amendments to HSE Management Plan shall be sought
from CH.
HSE M’gmnt Plan
Letter to CH
43
Review revised HSE
Management Plan
Holder
CH shall review revised HSE Management Plan received from CM. Advise Contractor of any
further revisions required by POGC to HSE Management Plan.
Revised HSE M’gmnt Plan
Letter to Contractor
44
Approve revised HSE
Management Plan
Holder
CH shall advise CM when revised HSE Management Plan is approved
Revised HSE M’gmnt Plan
Letter to Contractor
45
Implement POGC HSE
deviations and
Holder/Re
p/
CH shall notify CM that any POGC deviations and/or amendments to the HSE Management
Plan are to be implemented.
Revised HSE M’gmnt Plan
Letter to Contractor;
memo to file
DOCUMENT TITLE: Contract HSE Management Part I Page 52 REVISION 1.0
Pars Oil & Gas Company
amendments
Site Rep
46
Contractor - revise HSE
Management Plan
Contract
Manager
CM shall revise the HSE Management Plan as required by circumstances arising from the
execution of the contract. CH shall be notified of any required variations and/or
amendments.
HSE M’gmnt Plan
Letter to CH
47
Review revised HSE
Management Plan
Holder
CH shall review Contractor revised HSE Management Plan received from CM
HSE M’gmnt Plan
48
Approve revised HSE
Management Plan
Holder
CH shall advise CM that Contractor revised HSE Management Plan is approved
HSE M’gmnt Plan
Letter to Contractor
NOTE: Task Numbers 42 through 48 are iterative and shall be repeated as often as required throughout the execution of a contract
49
HSE Penalties and
Defaults
POGC
Rep/Site
Rep.
Applications of HSE defaults and penalties on the Contractor, as allowed in the contract for
unauthorized deviation from the Contractor’s HSE Management Plan and Exhibit L (HSE
Requirements) Contract Doc. CM to be notified in writing
HSE M’gmnt Plan
Letter to Contractor;
memo to file
50
Contract HSE Performance
Reports
Holder
Prepare Contract HSE Performance Report(s) providing feedback to POGC management on
the overall HSE performance of the Contractor and any sub-contractors. Reports to be
submitted annually to CO and Service Group Custodian (SGC).
HSE Monitoring Program
Contract HSE
Performance
Report(s)
Contract Phase: De-mobilization
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
51
Site Restoration –
compliance
Holder/
Site Rep
Ensure Contractor de-mobilizes from site of work in accordance with HSE Management Plan.
Site Rep. Shall issue HSE Site Restoration Certificate (CONTRACT HSE MANAGEMENT (PR-
10-POGC-001) Part I, Appendix F)
HSE M’gmnt Plan
Site Restoration
Certificate
52
Site Restoration
Certificate
Holder/
Site Rep.
Approve Site Restoration Certificate and issue to Contractor. CSR can sign Site Restoration
Certificate at the discretion of the CH.
HSE M’gmnt Plan
Site Restoration
Certificate
DOCUMENT TITLE: Contract HSE Management Part I Page 53 REVISION 1.0
Pars Oil & Gas Company
Contract Phase: Close-out
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
53
Final Contract HSE
Performance Report
Holder
Prepare Final Contract HSE Performance Report to be submitted to CO and Service Group
Custodian (SGC). Report to be finalized and submitted not later than 90 days after de-
mobilization. SGC to review report, update Service Group as necessary and file report for
future use.
CONTRACT HSE
MANAGEMENT (PR-10-
POGC-001), Part I,
Appendix D
Final Contract HSE
Performance Report
DOCUMENT TITLE: Contract HSE Management Part I Page 54 REVISION 1.0
Pars Oil & Gas Company
Appendix A1: Contract HSE Management Schedule
Contract Number: Contract Title:
Prepared by: Contract Holder Approved by: Contract Owner
Name and Reference Indicator:
Name and Reference Indicator:
Date:
Date:
Contract Phase: Planning and Invitation to Tender
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/actu
al)
Mandays
(Planned/Actual
)
1
Appoint Contract
Holder
Owner
Appoint Contract Holder (CH) and, if required, Company (POGC) Representative
(CR)
Transaction
s
Regulation
(of POGC)
Memo to file
2
Prepare Contract
Scope of Work
Holder
Define work and/or services required for Contract:
assess activities required for each contract commensurate with level of HSE risk
evaluate resources required to manage HSE in the contract
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Memo to file
P: A:
P: A:
3
Prepare Contract
Schedule
Holder
Prepare contract schedule by inserting planned dates
Transaction
s
Regulation
(of POGC)
Contract
Schedule
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 55 REVISION 1.0
Pars Oil & Gas Company
4
Develop Contract
Strategy
Holder
Summarize work and/or services required from mobilization to demobilization, with
particular attention to all interfaces and define the boundaries of the contract
Transaction
s
Regulation
(of POGC)
Contract
Strategy
P: A:
P: A:
5
Approval of
Contract Strategy
Owner
Contract Owner (CO) to approve Contract Strategy
Transaction
s
Regulation
(of POGC)
Memo to file
P: A:
P: A:
6
Conduct HSE
Assessment
Holder
Conduct a structured, formal HSE Assessment of the contract, using the Scope,
Schedule and Strategy documents. Identify major hazards and methods for their
control (Hazards and Effects Management Process – HEMP)
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
MA-12-
POGC-001
(HSE
Manageme
nt System
Manual),
Formal HSE
Assessment
for doc.
Exhibit L (HSE
Requirements
) Contract
Doc.
P: A:
P: A:
7
Prepare Exhibit L
(HSE
Requirements)
Contract Doc.
Holder
Use the results of the HSE Assessment to develop document Exhibit L (HSE
Requirements) Contract Doc. for inclusion in Tender
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Exhibit L (HSE
Requirements
) Contract
Doc.
P: A:
P: A:
8
Prepare POGC
Contract HSE
M’gmnt Schedule
Holder
Prepare POGC Contract HSE Management Schedule using the results of the HSE
Assessment. Send to CO for approval
MA-12-
POGC-001
(HSE
POGC
Contract HSE
M’gmnt
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 56 REVISION 1.0
Pars Oil & Gas Company
Manageme
nt System
Manual),
Schedule
9
Approve POGC
Contract HSE
M’gmnt Schedule
Owner
Approve POGC Contract HSE Management Schedule. Make necessary resources
available.
MA-12-
POGC-001
(HSE
Manageme
nt System
Manual),
Memo to file
P: A:
P: A:
10
Develop HSE Pre-
Qualification
Criteria
Holder
Develop HSE Pre-qualification criteria based on the HSE Assessment and HSE
Requirements. Submit to Tender Board for endorsement.
MA-12-
POGC-
001(HSE
Manual
Manageme
nt)& MA-
13-POGC-
001 (HSE
Manual
Manageme
nt)
HSE Pre-
qualification
criteria
P: A:
P: A:
11
Endorse HSE Pre-
Qualification
Criteria
Tender
Board
Tender Board to endorse HSE Pre-qualification Criteria
Transaction
s
Regulation
(of POGC)
Memo to
Contract File
P: A:
P: A:
12
Pre-qualify
Contractors
Holder
Perform HSE pre-qualification exercise to ensure contractors invited to bid meet or
exceed POGC’s HSE standards. Submit to Tender Board for approval
Transaction
s
Regulation
Contractor bid
list
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 57 REVISION 1.0
Pars Oil & Gas Company
(of POGC)
13
Approve
Contractor bid list
Tender
Board
Tender Board to approve Contractor Bid list
Transaction
s
Regulation
(of POGC)
Approved
Contractor Bid
List
Appendix A1: (Continued)
Contract Phase: The Tender Period
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/Actu
al)
Mandays
(Planned/Actual
)
14
Contractor
Submission
Exhibit L (HSE
Requirements)
Contract Doc.
Contract
Manager
Perform HEMP. Detail all HSE issues discovered including those in Exhibit L (HSE
Requirements) Contract Doc. as issued and detail how these risks will be
controlled, mitigated and managed. Detail any HSE issues additional to those
outlined in Exhibit L (HSE Requirements) Contract Doc. and include how these will
be controlled, mitigated and managed.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Exhibit L (HSE
Requirements
) Contract
Doc.
submission
15
Site Visit
Holder
Arrange any Contractor requested site visits.
Scope of
Work
Minutes of
Site Visit
P: A:
P: A:
16
Clarification
Meeting
Holder
Arrange any Contractor requested tender clarification meeting. Arrange meeting(s)
to clarify technical (including HSE) aspects of bid documents if necessary.
Transaction
s
Regulation
(of POGC)
Letter to
Contractors;
Minutes of
Meet.
P: A:
P: A:
Contract Phase: Evaluation and Contract Award
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/Actu
al)
Mandays
(Planned/Actual
)
DOCUMENT TITLE: Contract HSE Management Part I Page 58 REVISION 1.0
Pars Oil & Gas Company
17
Review Contractor
Exhibit L (HSE
Requirements)
Contract Doc.
Submission
Holder
Initial review of Contractor’s submission against the requirements of Exhibit L (HSE
Requirements) Contract Doc. Carry out gap analysis between Scope of Works and
Contractor’s Exhibit L (HSE Requirements) Contract Doc. submission.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Gap Analysis
Memo to file
P: A:
P: A:
18
Evaluate
Contractor Exhibit
L (HSE
Requirements)
Contract Doc.
Submission
Holder
Meet with Contractors and clarify Exhibit L (HSE Requirements) Contract Doc.
Submission to make bid compliant. Establish where improvements will be required
if contract is awarded.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Letter(s) to
Contractor(s)
P: A:
P: A:
19
Review
Contractor(s)
Ability to Manage
HSE Risk
Holder
Determine the likelihood that levels and classes of manpower, equipment, other
resources and policies proposed in Contractor(s) Exhibit L (HSE Requirements)
Contract Doc. Submission will enable the Contractor(s) to manage contract HSE
risk.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Memo to
Contract file
P: A:
P: A:
20
Contractor HSE
assessment
Holder
Assess which Contractor(s) will require additional POGC supervision to ensure
Exhibit L (HSE Requirements) Contract Doc. Submission is carried out correctly;
assess which Contractor(s) will NOT require additional POGC supervision. Advise
SUPPORT SERVICES.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Memo to
Contract file
P: A:
P: A:
21
Make
recommendation
Holder
The CH shall make a recommendation for contract award to the Tender Board,
highlighting any anomalies or qualifications relating to each Contractor.
Transaction
s
Regulation
(of POGC)
Tender Board
presentation
P: A:
P: A:
22 Advise Contractor
of POGC
Holder
Confirm appointment of Company (POGC) Representative (CR) and advise Transaction
s
LE-01-POGC-
001(Letter of
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 59 REVISION 1.0
Pars Oil & Gas Company
Representative
Contractor by letter using document LE-01-POGC-001(Letter of Approval).
Regulation
(of POGC)
Approval) to
Contractor
23
Advise Contractor
of POGC Site
Representative
Holder
Appoint Company (POGC) Site Representative and advise Contractor by letter, using
document LE-01-POGC-001(Letter of Approval).
Transaction
s
Regulation
(of POGC)
LE-01-POGC-
001(Letter of
Approval) to
Contractor
P: A:
P: A:
24
Appoint
Contractor key
personnel
Contract
Manager
Appointment of Contractor’s HSE key personnel listed in Exhibit L (HSE
Requirements) Contract Doc. . Advise CH.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Letter to
Contract
Holder
25
Approve
Contractor key
personnel
Holder
Confirm to Contract Manager POGC’s acceptance of HSE key personnel listed in the
contract.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Letter to
Contract
M’ger
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 60 REVISION 1.0
Pars Oil & Gas Company
Appendix A1: (Continued)
Contract Phase: Mobilization
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/Actu
al)
Mandays
(Planned/Actual
)
26
Kick off meetings
and HSE
workshop
Holder
Conduct POGC internal kick off meeting and POGC/Contractor Kick off meeting to
ensure that HSE and other contractual obligations are thoroughly understood. Hold
a separate HSE Workshop at site.
Transaction
s
Regulation
(of POGC)
Minutes of
meetings and
HSE workshop
P: A:
P: A:
27
Prepare HSE
Management Plan
Contract
Manager
Prepare HSE Management Plan, incorporating any POGC comments arising from the
kick off meeting and the HSE Workshop, including any necessary POGC mandatory
training, for submission to CH.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
HSE
Management
Plan
P: A:
P: A:
28
Review
Contractor’s HSE
Management Plan
Holder
Review Contractor’s HSE Management Plan; issue Modifications Letter if required.
Exhibit L
(HSE
Requiremen
ts) Contract
Doc.
Modifications
letter if
required.
P: A:
P: A:
29
Approve
Contractor’s HSE
Management Plan
Holder
Advise Contract Manager of CH’s approval of HSE Management Plan
Contractor’s
HSE
M’gmnt
Plan
Letter to
Contractor
P: A:
P: A:
30
Develop HSE
monitoring
program
Holder
Detail how the performance of the Contractor will be monitored against the
Contractor’s HSE Management Plan. Prepare the HSE Monitoring Program
documentation
HSE
M’gmnt
Plan
Proposed HSE
Monitoring
Plan
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 61 REVISION 1.0
Pars Oil & Gas Company
31
Review HSE
Monitoring
Program
Owner
Contract Owner shall review HSE Monitoring Plan
Proposed
plan
P: A:
P: A:
32
Approve HSE
Monitoring
Program
Owner
Contract Owner shall approve HSE Monitoring Plan and advise CH
Approved
plan
Memo to file
P: A:
P: A:
33
POGC &
Contractor HSE
training
Holder
Schedule and complete all necessary POGC and Contractor staff training as
identified in the POGC and Contractor’s HSE assessments
Tasks 6,7,
and 27
Training
records
P: A:
P: A:
34
Contractor
Mobilization
Contract
Manager
Contractor to commence mobilization activities. CH to monitor, inspect and audit to
ensure that Contractor complies with the Contractor’s HSE Management Plan and
Exhibit L (HSE Requirements) Contract Doc.
HSE
Monitoring
Program
Contract HSE
Performance
Report.
35
Pre-execution HSE
Audit of
Contractor
Holder
Conduct an audit against the Contractor’s HSE Management Plan to determine if the
Contractor has achieved the pre-execution targets stated in the Exhibit L (HSE
Requirements) Contract Doc. and Contractor’s HSE Management Plan, and that
mobilization is complete. Forward report to Contract Manager.
HSE
M’gmnt
Plan
Minutes of
Pre-execution
meeting
P: A:
P: A:
36
Complete Pre-
execution HSE
Audit Items
Contract
Manager
Contractor completes all items flagged in the pre-execution HSE audit.
Minutes of
Pre-exec.
meeting
37
Contractor –
Readiness to
Commence
Contract
Manager
Contractor confirms to CH that all pre-execution items are completed and issues
Pre-execution Completion report. CM also forwards Contractor’s HSE certificate
(CONTRACT HSE MANAGEMENT (PR-10-POGC-001), Parts II, Appendix 1) for
authorization by CH
Minutes of
Pre-exec.
meeting
Completion
report & HSE
Certificate
38
Issue HSE
Certificate
Holder
If no unsafe operating conditions exist, CH issues the HSE Certificate (refer
Appendix E) to Contract Manager, subject to any exceptions noted on the HSE
Certificate.
Minutes of
Pre-exec.
meeting
HSE
Certificate
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 62 REVISION 1.0
Pars Oil & Gas Company
Appendix A1: (Continued)
Contract Phase: Execution
Task
Number
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/Actual
)
Mandays
(Planned/Actual
)
39
Supervision
POGC
Rep/Site
Rep
Continuous assurance and verification that Contractor systems are performing in
accordance with the Contractor’s HSE Management Plan
HSE
M’gmnt
Plan
Contract HSE
Performance
Reports
P: A:
P: A:
40
Monitor
implementation of
HSE M’gmnt Plan
Owner/Hol
der/ Site
Rep.
Monitor Contractor’s performance against the Contractor’s HSE Management Plan
using the HSE Monitoring Program. CO and CH to participate in audits, incident
investigations, meetings and reviews.
HSE
M’gmnt
Plan
Contract HSE
Performance
Reports
P: A:
P: A:
41
Additional HSE
Requirements
Holder
Carry out HEMP to incorporate any additional HSE requirements arising from
contract execution leading to enlarged Scope of Work. Advise SUPPORT
SERVICES and Contractor of any additional POGC HSE requirements.
Transaction
s
Regulation
(of POGC)
Variation letter
to Contractor;
memo to file
P: A:
P: A:
42
Contractor –
revise HSE
Management Plan
Contract
Manager
Following on from the variation letter received from POGC, any unforeseen work
activities shall be assessed and the Contractor shall revise HSE Management Plan
accordingly. Authorization for all deviations and amendments to HSE Management
Plan shall be sought from CH.
HSE
M’gmnt
Plan
Letter to CH
43
Review revised
HSE Management
Plan
Holder
CH shall review revised HSE Management Plan received from CM. Advise
Contractor of any further revisions required by POGC to HSE Management Plan.
Revised
HSE
M’gmnt
Plan
Letter to
Contractor
P: A:
P: A:
44
Approve revised
HSE Management
Plan
Holder
CH shall advise CM when revised HSE Management Plan is approved
Revised
HSE
M’gmnt
Letter to
Contractor
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 63 REVISION 1.0
Pars Oil & Gas Company
Plan
45
Implement POGC
HSE deviations
and amendments
Holder/Rep
/
Site Rep
CH shall notify CM that any POGC deviations and/or amendments to the HSE
Management Plan are to be implemented.
Revised
HSE
M’gmnt
Plan
Letter to
Contractor;
memo to file
P: A:
P: A:
46
Contractor -
revise HSE
Management Plan
Contract
Manager
CM shall revise the HSE Management Plan as required by circumstances arising
from the execution of the contract. CH shall be notified of any required variations
and/or amendments.
HSE
M’gmnt
Plan
Letter to CH
P: A:
P: A:
47
Review revised
HSE Management
Plan
Holder
CH shall review Contractor revised HSE Management Plan received from CM
HSE
M’gmnt
Plan
P: A:
P: A:
48
Approve revised
HSE Management
Plan
Holder
CH shall advise CM that Contractor revised HSE Management Plan is approved
HSE
M’gmnt
Plan
Letter to
Contractor
P: A:
P: A:
NOTE: Task Numbers 42 through 48 are iterative and shall be repeated as often as required throughout the execution of a contract
49
HSE Penalties and
Defaults
POGC
Rep/Site
Rep.
Applications of HSE defaults and penalties on the Contractor, as allowed in the
contract for unauthorized deviation from the Contractor’s HSE Management Plan
and Exhibit L (HSE Requirements) Contract Doc. CM to be notified in writing
HSE
M’gmnt
Plan
Letter to
Contractor;
memo to file
P: A:
P: A:
50
Contract HSE
Performance
Reports
Holder
Prepare Contract HSE Performance Report(s) providing feedback to POGC
management on the overall HSE performance of the Contractor and any sub-
contractors. Reports to be submitted annually to CO and Service Group
Custodian (SGC).
HSE
Monitoring
Program
Contract HSE
Performance
Report(s)
P: A:
P: A:
DOCUMENT TITLE: Contract HSE Management Part I Page 64 REVISION 1.0
Pars Oil & Gas Company
Contract Phase: De-mobilization
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/Actual
)
Mandays
(Planned/Actual
)
51
Site Restoration –
compliance
Holder/
Site Rep
Ensure Contractor de-mobilizes from site of work in accordance with HSE
Management Plan. Site Rep. Shall issue HSE Site Restoration Certificate
(CONTRACT HSE MANAGEMENT (PR-10-POGC-001), Part I, Appendix F)
HSE
M’gmnt
Plan
Site
Restoration
Certificate
P: A:
P: A:
52
Site Restoration
Certificate
Holder/
Site Rep.
Approve Site Restoration Certificate and issue to Contractor. CSR can sign Site
Restoration Certificate at the discretion of the CH.
HSE
M’gmnt
Plan
Site
Restoration
Certificate
P: A:
P: A:
Contract Phase: Close-out
Task
Numb
er
Activity
Action
Activity Description
Reference
Deliverable(s)
Date
(Planned/Actual
)
Mandays
(Planned/Actual
)
53
Final Contract
HSE Performance
Report
Holder
Prepare Final Contract HSE Performance Report to be submitted to CO and Service
Group Custodian (SGC). Report to be finalized and submitted not later than 90 days
after de-mobilization. SGC to review report, update Service Group as necessary and
file report for future use.
CONTRACT
HSE
MANAGEME
NT (PR-10-
POGC-001),
Part I,
Appendix D
Final Contract
HSE
Performance
Report
P: A:
P: A:
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 65 REVISION 001
Appendix B: HSE Prequalification Questionnaire
This Pre-Qualification questionnaire shall be given to contractors. Refer Tasks 10, 11, 12.
BASE CASE HSE PRE-QUALIFICATION QUESTIONNAIRE
Section 1: Leadership and Commitment
Commitment to HSE
Through leadership
a) Are senior managers personally involved in HSE management?
b) Is there evidence of commitment at all levels of the organization?
c) Is there a positive culture towards HSE matters?
Section 2: Policy and Strategic Objectives
(I) HSE policy
document
a) Does your Company have an HSE policy document? (If YES please
attach a copy).
b) Who has overall and final responsibility for HSE in your organization?
c) Who is the most senior person in the organization responsible for this
policy being carried out on site where employees are working? (Provide
name, title and experience).
(ii) Employee access to
HSE policy document
a) Itemize the methods by which you have drawn your HSE policy
document to the attention of all your employees.
b) What are your arrangements for advising employees of changes in the
policy?
Section 3: Organization, Responsibilities, Resources, Standards and Documentation
(I) Commitment and
communication
a) How is management involved in HSE activities, objective-setting and
monitoring?
b) How is your Company structured to manage and communicate HSE
effectively?
c) What provision does your Company make for HSE communication
meetings?
(ii) Competence and
training of managers/
supervisors/senior site
staff/ HSE advisers
a) Have the managers and supervisors at all levels received formal HSE
training in their responsibilities with respect to conducting work to HSE
standards? (If YES please give details. Where the training is given in-
house please describe the content and duration of courses).
(iii) Competence and
General HSE training
a) What arrangements does your Company have to ensure new employees
have knowledge of work related HSE issues, and to keep this knowledge up
to date?
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 66 REVISION 001
b) What arrangements does your Company have to ensure new employees
have knowledge of your specific HSE policies and practices?
c) What arrangements does your Company have to ensure new employees
have been instructed and have received information on any specific
hazards arising out of their work scope?
d) What training do you provide to ensure that all employees are aware of
Company HSE requirements?
e) What arrangements does your Company have to ensure that the HSE
knowledge of existing staff is up to date? (If training is provided in-house
please give details of course contents.)
(iv) Specialized training a) Have you identified areas of your Company operations where specialized
training is required to deal with major hazards? (If YES please itemize and
provide details of training given.)
b) If the specialized work involves the following hazards, how are the
hazards identified, assessed and controlled?
Road transport
Working in heat
Camp hygiene
Waste disposal
Communication to a multi-cultural workforce
Radiation
Chemical handling
(v) HSE qualified staff –
additional training
a) Do any of your staff conduct HSE training? If so, what are their
qualifications?
(vi) Assessment of
suitability of
subcontractors/ other
companies
a) For your sub-contractors, how do you assess:
HSE competence
HSE performance
b) How do you ensure your sub-contractors meet your HSE standards?
(vii) Standards a) Where do you record your HSE standards
b) How do you ensure these are met and verified?
c) Is there a system for producing, updating and disseminating standards?
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 67 REVISION 001
Section 4: Hazards and Effects Management
(I) Hazards and effects
assessment
a) What techniques are used within your Company for the identification,
assessment, control and recovery of hazards and effects?
(ii) Exposure of the
workforce
a) Do you have in place any systems to monitor the exposure of your
workforce to chemical or physical agents?
(iii) Handling of
chemicals
a) How is your workforce advised on the properties of chemicals
encountered in the course of their work?
(iv) Personal protective
equipment
a) What arrangements does your Company have for provision and upkeep
of protective clothing, both standard issue, and that required for
specialized activities?
(v) Waste management a) Does your Company have in place systems for identification,
classification and management of waste?
Section 5: Planning and Procedures
(I) HSE or operations
manuals
a) Do you have a Company HSE manual (or Operations manual with
relevant sections on HSE) which describes in detail your Company
approved HSE working practices relating to your work activities? (If the
answer is YES please attach a copy of supporting documentation.)
b) How do you ensure that the working practices and procedures used by
your employees on-site are consistently in accordance with your HSE policy
objectives and arrangements?
(ii) Equipment control
and maintenance
a) How do you ensure that plant and equipment used within your
premises, on-site, or at other locations, by your employees are correctly
registered, controlled and maintained in a safe working condition?
(iii) Road Safety
Management
a) What arrangements does your Company have for combating road and
vehicle incidents?
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 68 REVISION 001
Section 6: Implementation and Performance Monitoring
(i) Management and
performance
monitoring of work
activities
a) What arrangements does your Company have for supervision and
monitoring of performance?
b) What type of performance criteria are used in your Company; give
examples
c) What arrangements does your Company have for passing on any results
and findings of this supervision and monitoring to your:
Management
site employees?
(ii) HSE performance
achievement awards
a) Has your Company received any award for HSE performance
achievement?
(iii) Statutory modifiable
incidents/dangerous
occurrences
a) Has your Company suffered any statutory notifiable incidents in the last
five years (safety, occupational health and environmental)?
(Answers with details including dates, most frequent types, causes and
follow-up preventative measures taken.)
(iv) Improvement
requirement and
prohibition notices
a) Has your Company suffered any improvement requirement or prohibition
notices by the relevant national body, regulatory body for HSE or other
enforcing authority (including POGC or another Operating Company) or
been prosecuted under any HSE legislation in the last five years? (If your
answer is YES please give details.)
(v) HSE performance
records
a) Have you maintained records of your incidents and HSE performance for
the last five years? (If YES, please give following details for each year:-
number of Non Lost Time Injuries, number of Lost Time Injuries, numbers
and types of injuries, total hours worked by workforce for each
corresponding year, Frequency Rates, your Company definition of a Lost
Time incident).
b) How is health performance recorded?
c) How is environmental performance recorded?
d) How often is HSE performance reviewed? By whom?
(vi) Incident
investigation and
reporting
a) Who conducts incident investigations?
b) How are the findings following an investigation, or a relevant incident
occurring elsewhere, communicated to your employees?
c) Are near misses reported?
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 69 REVISION 001
Section 7: Auditing and Review
(I) Auditing a) Do you have a written procedure on HSE auditing and how does this
specify the standards for auditing (including unsafe act auditing)?
b) Do your Company’s HSE Plans include schedules for auditing and what
range of auditing is covered?
c) How is the effectiveness of auditing verified and how does management
report and follow up audits?
Section 8: HSE Management – Additional Features
(i) Memberships of
Associations
a) Does your Company hold membership of any industry, trade or HSE
organization?
(ii) Additional features
of your HSE
management
a) Does your Company have any other HSE features or arrangements not
described elsewhere in your response to the questionnaire?
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 70 REVISION 001
Appendix B (Continued)
Evaluation of Base Case HSE Pre-qualification Questionnaire
General guidelines for evaluation.
1 The contractor's response to the questionnaire should be evaluated by attaching a score to
the selected response for each category. A suggested scoring system would be as follows
A B C D
Above satisfactory
response
Satisfactory response Below satisfactory
response
Unacceptable response
An evaluation that includes one or more ‘D’ ratings, (with the exception of section 8 where only
credit shall be given) shall lead to disqualification.
An evaluation that includes 50% of ‘C’ and 50% of ‘B’ shall be acceptable provided all responses
relating to the management of the major hazards recorded in the HSE Specification are rated ‘B’ or
above.
2 Responses should be evaluated against recorded standards such as found in document
MA-12-POGC-001 (HSE Management System Manual),
3 Evaluations should be recorded and maintained in the event that the evaluation is
challenged at a later date.
4 Contract Holders shall complete the evaluation and ensure the Contract Owner endorses
the evaluation and the Service Group Custodian accepts the evaluation.
5 Feedback to the contractor of the evaluation is encouraged but must first be cleared with
SUPPORT SERVICES. The evaluation preformed shall not be released to the contractor.
WARNING:
A questionnaire such as this relies upon contractor honesty and integrity to be effective. If the
responses are considered ‘inappropriate’ then the questionnaire should be verified by personal
inspection of the contractor’s operations. Note; this may only be practicable for high risk, high
cost contracts.
The evaluation process should be aware that honest reporting, especially of HSE performance
statistics can result in an honest contractor’s performance appearing worse that of a dishonest
contractor. For example, contractor A reports all near misses, FAC’s, MTC’s, LTI’s diligently and
has extensively educated their work force to report against a wide range of hazards. Contractor B
only reports when it suspects it is obliged to. Its employees are only aware of and therefore only
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 71 REVISION 001
report against major safety hazards. In this situation, the LTI and overall HSE performance of A
will appear to be worse than B. However, it is clear that A is the preferred contractor.
A similar situation could occur if contractor A always undertakes high-risk work in difficult locations
and therefore incurs incidents, despite working hard to avoid them. Contractor B only undertakes
lower risk work where the Client takes greater responsibility for HSE management and so has a
near perfect incident record. Awarding the high risk, remote location work to B would be a
mistake.
These and other similar problems must be considered during the evaluation. No contractor is
perfect, but some contractors try harder to improve than others.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 72 REVISION 001
Appendix B (Continued)
BASE HSE PRE-QUALIFICATION QUESTIONNAIRE EVALUATION SCHEME
Section 1: Leadership and Commitment
Commitment to HSE through leadership: Item (i) - a) to c)
A B
C
D
Evidence of a positive
HSE culture in senior
management and at all
levels
Evidence of active senior
management
involvement in HSE
aspects
HSE disciplines
delegated to line
managers – no direct
involvement by senior
management
No commitment from
senior management
Section 2: Policy and Strategic Objectives
HSE policy documents and availability: Items (i) – a) to c) and (ii) – a) to b)
A
B
C
D
HSE Policy with clearly
established responsibility
and accountability; is
distributed to all
employees; is
prominently displayed.
A satisfactory HSE policy
establishes responsibility
for HSE, but is not
widely distributed.
An unsatisfactory HSE
policy statement exists;
is not widely distributed
No written HSE policy.
A ‘satisfactory’ HSE Policy contains all the basic elements in POGC’s HSE Policy. Further guidance is
provided in ,MA-12-POGC-001(HSE Manual Management) detailed guidance can be obtained from
POGC personnel.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 73 REVISION 001
Section 3: Organization, Responsibilities, Resources, Standards and Documentation
HSE communication and meeting programs: Item (I) – a) to c)
A
B
C
D
In addition to B,
employees are actively
involved in meetings.
Effective management
review of the entire
structure.
Structured involvement
and HSE meetings
Ad hoc involvement,
structure and HSE
meetings.
No management
involvement, no
structure, no meetings.
Staff HSE training Item (ii)
Specialized HSE training
given comprehensively
and formally to all
management.
Specialized HSE training
given to all managers
but not comprehensively
covered.
Specialized HSE training
given to a specific
person on location.
No specialized staff
training.
Employee orientation and training program: Item (iii) - (a) - (e)
All under B together
with a follow-up
mechanism and
reorientation as roles
change.
Employee induction
(handbook?) provided
supported by site
orientation. Supervisor
outlines, explains and
demonstrates new
employee's job
Verbal instructions only.
Basic orientation booklet
(or similar) provided for
new employees.
No formal program.
Specialized training: Item (iv) - (a) to (b) and (v)
Formal HSE training
programs have been
developed in all areas
and are conducted on a
regular basis.
Retraining periods are
established. Training
staff suitably qualified.
HSE training is given for
specialized operations,
but no routine training
conducted. Staff not
formally qualified.
On-site basic HSE
training conducted
occasionally.
No HSE training
established
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 74 REVISION 001
Appendix B (Continued)
Subcontractors: Item (vi) - (a) to (b)
As for B but
comprehensive.
Included as part of
standard HSE
Procedures
Structured
arrangements in place
and recorded but not
comprehensive.
Arrangements in place
on ad hoc basis.
No arrangements.
Standards : Item (vii) - (a) to (c)
Contractor has a system
of specifying, monitoring
compliance and
updating HSE standards.
Contractor has written
HSE standards to cover
all major hazards.
Basic HSE standards
exist.
No HSE standards
available.
Section 4: Hazards and Effects Management **
Hazards and Effects Assessment : Item (i)
A
B
C
D
HSE system has a
comprehensive set of
methods for the
assessment of all HSE
hazards and effects and
applies them to all of its
contracts. Supporting
documentation
maintained.
HSE system includes
methods for the
assessment of major
hazards and effects
HSE system makes
reference to the need to
assess hazards and
effects but has no
comprehensive structure
to carry this out.
HSE system does not
include hazards and
effects assessment.
Exposure of the workforce: Item (ii)
Formal methods (linked
to hazards and effects
assessment method) in
place for advising and
monitoring exposure to
all foreseeable hazards
Does advise the
workforce and monitor
exposure to the major
hazards.
Does advise the
workforce of the major
hazards that they are
likely to be exposed to.
Does not actively advise
the workforce nor
monitor exposure
Handling of chemicals: Item (iii)
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 75 REVISION 001
Maintains a database of
the properties of all
chemicals encountered
and has formal methods
of information
distribution to all
personnel and trains its
workforce in handling,
etc.
Distributes information
to individuals in the
workforce at start of
their involvement on-site
Provides information to
workforce in the
workplace on properties
of chemicals
No provision for advising
the workforce about
properties of chemicals
Personal protective equipment : Item (iv)
Procedures in place to
assess all PPE
requirements, monitor
and enforce usage and
replacement needs.
Stock inventories
monitored, kept above
demand levels. Training
in use provided where
needed
PPE requirements
formally assessed with
spot checks on usage.
PPE requirements
assessed by job but little
effort made to ensure
correct usage.
Basic PPE provided
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 76 REVISION 001
Waste management: Item (v)
Formal system for waste
management (including
identification and
classification), which
actively seeks to
minimize environmental
impact.
Procedures for the
disposal of each of the
main categories of site
wastes but makes no
provision for minimizing
environmental impact.
General procedures for
waste disposal.
No methods for the
control of waste.
** This section of the evaluation shall relate directly to the HSE Specification. The example shows chemicals and waste for
demonstration purposes only. The specific hazards of the work scope should be assessed using similar criteria. Section 3-
(iv) b) in the pre-qualification questionnaire considers hazards commonly encountered in general operational work scopes.
Section 5: Planning and Procedures
HSE or operations manuals : Item (i) - (a) to (b)
A B C D
Contractor has
Procedures to cover all
HSE precautions; typical
HSE Management Plan
requirements with a
system of updating and
dissemination.
Contractor has written
HSE Procedures to cover
all major hazards.
Basic HSE Procedures
exist.
No HSE Procedures
available.
Equipment control and maintenance : Item (ii)
In addition to B routine
inspections conducted
by management or by
specialists
Formal control through
written procedures
outlining supervisory
guidelines,
responsibilities,
frequency and follow-up.
Ad hoc control on site
only.
No control.
Road Safety Management : Item (iii)
A strategy and set of
plans and procedures
covering vehicles,
drivers and operations
management in place
and shown to be
working.
A general management
strategy in place with
some procedures.
Importance of road
safety acknowledged but
left to supervisors to
manage individually.
No special attention paid
to road safety as an
area of hazardous
activities.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 77 REVISION 001
Appendix B (Continued)
Section 6: Implementation and Performance Monitoring
Management and performance monitoring of work activities : Items (i) – a) to b) and (ii) a)
A
B
C
D
Comprehensive system
for monitoring
performance in all areas
with feedback to
employees for
improvement. Has
received awards for HSE
achievement.
Systematic monitoring of
HSE performance in key
areas.
Ad hoc performance
monitoring carried out.
No monitoring of HSE
performance.
Statutory modifiable incidents / dangerous occurrences and improvement requirements and
prohibition notices: Items (iii) and (iv)
No occurrences in the
last five years.
Occurrences relate to
minor incident(s) only.
One occurrence of a
major incident in the last
five years.
More than one
occurrence of major
incident in last five
years.
HSE Performance records (Latest year injury rate comparison to contractors three preceding years
average) : Item (v) - (a) to (d)
Rate steadily improving
by more than 5 per cent
per year.
Rate shows minor
improvement.
Rate not improving.
Contractor supplied
insufficient information
to establish rate or rate
increases.
Criteria for absolute performance
Rate better than that of
POGC.
Rate under 120 per cent
that of POGC.
Rate under 200 per cent
that of POGC.
Rate over 200 per cent
that of POGC.
Incident Investigation and reporting : Item (vi) (a) to (c)
As in B but with the
evidence that
improvement has taken
place
Structured investigation
with findings
communicated to all
employees.
Investigation ad hoc
with poor
communication of
findings and limited
follow up.
No investigation.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 78 REVISION 001
Section 7: Auditing and Review
Auditing: Item (i) - (a) to (c)
A
B
C
D
As in B but additionally
specifies management's
role in audit and follow-
up on action items
HSE documents include
details of how auditing
is to be implemented
with schedules/coverage
for the key areas
Auditing occurs but
there are no specific
details about scheduling
and coverage.
No audit process, or
process is cursory only.
Section 8: HSE Management – Additional Features
Membership of Associations : Items (I) and (ii)
A
B
C
D
Company is an active
participant in at least
one HSE association.
Company is a member
of at least one HSE
association.
Company has
membership of an
association but with no
prominence given to
HSE.
No memberships or
additional features.
DOCUMENT TITLE: Contract HSE Management Part I Page 79 REVISION 1.0
Pars Oil & Gas Company
Appendix C: HSE Monitoring Program
Contract Number Contract Name
Prepared by: Contract Holder/ Rep. Name / Reference Ind.
Approved by: Contract Owner Name / Reference Ind.
Activity Responsible Person
(Leader)
Participants Resources Frequency T I M I N G
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Meetings
Inspections
Management
Walkabouts
Audits
Emergency Exercises
/ Drills
Follow-up
Note. Template should be expanded as required
DOCUMENT TITLE: Contract HSE Management Part I Page 80 REVISION 1.0
Appendix D: Template, Contract HSE Performance Report
These reports shall contain factual information on the HSE performance of POGC and Contractor
throughout the contract. The analysis and summary at the conclusion should address the
following:
• assess the effectiveness of the Contractor’s HSE Management Plan (including the quality of
follow-up to inspections, audits and accidents);
• identify those areas unanticipated in the plan, how they were overcome and the future
approach to be taken;
• highlight successful positive aspects that should be used in the future;
• provide a concise analysis of both POGC’s and the Contractor's HSE performance for discussion
with the Contractor's management as a means of improvement;
• provide input information on the Contractor for POGC's bid list to identify actions needed in
assessments for future tenders.
A formal record of HSE performance shall be kept on each Contractor by the Service Group
Custodian for future reference.
Suggestions to aid completion of this template are provided in italics in the ‘comment’ column.
The ratings can be: U = Unsatisfactory; J = Just Satisfactory; F = Fully Satisfactory. (See
SUPPORT SERVICES for definitions). In the event of an unsatisfactory rating, the reason for the
rating shall be given in the comments column. In the event of an item being not being assessed it
will be assumed that the item is rated as Fully Satisfactory unless otherwise indicated. Comments
should be kept as brief as possible.
DOCUMENT TITLE: Contract HSE Management Part I Page 81 REVISION 1.0
Contractor HSE Performance Report
CONTRACTOR
CONTRACT NUMBER
CONTRACT NAME
DATE(S) OF CONTRACT
SUBJECT RATING COMMENT
Leadership and Commitment Did management promote a strong HSE culture?
Were sufficient resources allocated to manage HSE?
Were all deficiencies cleared promptly and effectively?
Implementation of HSE Policy Was Policy communicated and enforced?
Implementation of Contract HSE
Plan Was the Contract HSE Plan followed and updated as
required?
Effectiveness of HSE
Organization
Were the resources provided adequate?
Did all systems perform to standard?
Did the organization learn from mistakes?
Employee HSE Induction and
Training Completed to standard and on time?
Sub-Contractor HSE
Management
Did sub contractors perform to the same standard as
the contractor?
Were efforts made to improve when deficiencies were
noted?
HSE Personnel: Competence Were personnel competent?
Did they provide effective training and advice?
Did management respect their role?
HSE Meetings Was a cascaded hierarchy of meetings in place,
effective and attended by all personnel?
Tool Box Talks Were these conducted to standard?
Driving/Journey Management Were all vehicles to specification?
Was journey management followed and controlled?
DOCUMENT TITLE: Contract HSE Management Part I Page 82 REVISION 1.0
Quality of Contractor’s HSE
Manual and Documentation Was documentation available, comprehensive, in
correct languages and used?
Emergency Response
Procedures
Were all credible scenarios supported by procedures?
Were procedures tested and improved when found
lacking?
Safety Rules/Job Instructions Were correct rules in place based upon job hazard
analysis?
Accident Investigation Procedure Were all incidents investigated to standard?
Implementation of HSE
Standards Manual
Were the requirements of the Manual followed and
incorporated in to contractor standards?
Briefly summarize major contravention’s of standards
FATALITIES Describe in detail any fatalities (cross reference to
reports), comment on contractor response to
investigation recommendations
LTIF Brief comment on reasons for LTIs. Comment on
contractor response to investigation recommendations
TRCF
Man-hours worked/Total
workforce
Maintenance and Control of
Plant Was equipment maintained and capable of completing
the work?
Maintenance and Control of
Other Equipment Was equipment maintained and capable of completing
the work?
Camp Facilities/Hygiene Were standards maintained?
Were there any outbreaks of illness?
Site Restoration Completed to the standard required?
Waste Management Conducted according to standard?
HSE Audits Summarize the main findings and conclusions
HSE Inspections Summarize the main findings and conclusions
DOCUMENT TITLE: Contract HSE Management Part I Page 83 REVISION 1.0
Management Review Was this carried out?
Was this a ‘learning’ organization prepared to improve?
Data Compiled By Reviewed By
Date
Recommendations on Future Use of Contractor
Unconditional Conditional
(list conditions below)
Not to be used again
(list reasons why)
Contract Holder Contract Owner
Date Date
DOCUMENT TITLE: Contract HSE Management Part I Page 84 REVISION 1.0
Appendix E: HSE Certificate
National Iranian Oil Company H S E C E R T I F I C A T E
Contract Title
Contractor Contract No.
Sub-Contractors
Contract Plan Activity Date Completed Exceptions
Contract HSE Plan Endorsed
Kick Off Meeting Held
HSE Workshop Held
Residential Camp Accepted
Industrial Site Accepted
Vehicle/Plant Accepted
Training Completed: (Part II Appendix 3)
Required to attend prior to commencing, C:
Required to attend within 2 months, M:
Recommended only, R:
Pre-execution Audit Completed
Essential Audit Items Completed
Notes:
On behalf of the Contractor I confirm that the activities stated above have been carried out and we
are capable of performing the work in a healthy, safe, and environmentally responsible manner.
Name Date Responsibility Signature
Contract Manager
We hereby agree that the HSE status of this Contract allows work to proceed, subject to the above
exceptions.
Name Ref. Ind. Responsibility Signature
Contract Holder
Representative*
DOCUMENT TITLE: Contract HSE Management Part I Page 85 REVISION 1.0
Pars Oil & Gas Company
*At Contract Holder's discretion
DOCUMENT TITLE: Contract HSE Management Part I Page 86 REVISION 1.0
Pars Oil & Gas Company
Appendix F: Site Restoration Certificate
National Iranian Oil Company S I T E R E S T O R A T I O N C E R T I F I C A T E
Contract Title
Contractor Contract No.
Sub-Contractors
Site Restoration Activity Date Completed Exceptions
Demobilization Date Approved
Requirement for Isolation of Facilities
(telecoms, electricity, water) notified to
POGC
Residential Camp Inspection Completed
Office Inspection Completed
Industrial Area Inspection Completed
Work-site Inspection Completed
All POGC Assets handed over to POGC
All Outstanding materials handed over to
POGC
Summary file of Contract Waste Log
handed over to POGC
Notes:
On behalf of the Contractor I confirm that the activities stated above have been carried out and we
have restored the site(s) according to the Contract Requirements
DOCUMENT TITLE: Contract HSE Management Part I Page 87 REVISION 1.0
Pars Oil & Gas Company
Name Date Responsibility Signature
Contract Manager
We hereby agree that the HSE status of this Contract allows the Contractor to Demobilize subject to
the exceptions listed above.
Name Date Ref.
Ind.
Responsibility Signature
Contract Holder
Representative *
* At Contract Holder's discretion
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 88 REVISION 1.0
Appendix G: Variation to Contract – Transactions Regulation (of POGC)
Mandatory
A Variation to Contract shall be required to formalise and execute changes to the original
Contract scope, work, specification or Conditions of the Contract.
A Variation to Contract shall be required for the following:
• Change in Scope of Work/Services (positive or negative).
• Change in execution of the Work/Services.
• Change in resources or facilities required.
• Rate Revisions, where applicable.
• Extension of time, where applicable.
• Settlement of a claim arising from the Contract, adjusting scope or Contract Value.
• Change to the Terms and Conditions of the Contract.
All changes to the General Conditions of the Contract shall be agreed only after consultation with
Procurement & Contract Dept (Support Services) and the Legal Dept (POGC – Legal Dept).
Contract Holder shall be responsible to ensure that all changes are correctly covered by a
Variation to Contract, authorised in accordance with the Manual of Authorities and executed to
completion by the Contractor.
Advisory
Asset Manager may approve, if necessary, the execution of operational restrictions or items of
urgency, providing formal documentation is completed retrospectively.
Additional Work/Services that is unrelated to the originally tendered scope shall be provided for
under a separate Contract. However, where there is an economic advantage or synergy in
undertaking the unrelated work, such an addition may be considered and approved by Asset
Manager and Tender Board as appropriate.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 89 REVISION 1.0
Establishing a Variation to Contract
Mandatory
Where a Change Order form or Variation to Contract form is required the standard forms in
http://portal.pogc.org shall be used. Assistance from SUPPORT SERVICES shall be requested.
The finalisation of a Variation to Contract and assessment of value shall be undertaken by the
Contract Holder with assistance from the Unit Contracts Section and specialist functional advice.
All Variations to Contracts shall be agreed and signed by the Contractor and authorised according
to the Manual of Authorities unless further Tender Board approval is required.
All Variations to Contracts shall be circulated in accordance with the standard circulation and checklist
and in accordance with Transactions Regulation (of POGC).
Variations shall be logged on to the http://portal.pogc.org system by Procurement & Contracts
Dept ,as part of the approval circulation.
The signed original of the Variation to Contract shall be retained as follows:
Contracts in excess of US$ 200,000 by the Procurement & Contracts Dept (SUPPORT SERVICES).
Contracts up to US$ 200,000 to be retained by the Unit Contracts Section with original Contract
documentation and information advised for updating to Procurement & Contracts Dept (SUPPORT
SERVICES).
Contract Holder shall ensure adequate budgetary cover exists and the approved limit of
expenditure/Review Limit of the Contract is not exceeded.
Contract Holder shall require prior Tender Board approval in all cases stipulated in Transactions
Regulation (of POGC) Advisory.
The Contract Holder, Company Representative, Company Site Representative or Contractor may
identify the requirement for a Change Order and subsequent Variation to Contract to reflect
financial, scope change or program schedule impacts.
Discussion may take place with the Contractor to establish the magnitude of the change and
requirements prior to approval of the Variation to Contract. Such discussions may only occur on a
‘No commitment’ basis with the Contractor.
Variations to Contract with a nil value, or a reduction in Contract Price, or inclusion of additional
rates/work elements shall be reviewed by the Unit Contracts Section. The background to the
Variation to Contract shall be fully documented.
Pars Oil & Gas Company
DOCUMENT TITLE: Contract HSE Management Part I Page 90 REVISION 1.0
Appendix H: Accessing POGC Web Documents
Throughout this document, references are made to documents from one source:
Access to POGC documents:
1. Open the internet browser to the POGC Home Page at http://portal.pogc.org/SitePages/Home.aspx
2. Left click on Health, Safety and Environment.
3. Left click on “Control Documents”. This opens the POGC Business Control Documents in
"portal.pogc.org "page.
4. Enter the document title in the dialog box on the left hand side. A hit is more likely if only key
words such as “HSE” are used. It is helpful to sort the documents by document number rather than
document title.
5. If the document number is known, left click on the “Detailed” button in the lower left hand
corner. This opens the “Business Control Documents Detailed Search” dialog box.
6. Enter the EXACT document number in the “Document ID” box. Use title only to ensure
maximum returns for the search.
7. DO NOT try to print the document from this window. Copy the document to a blank Word
document as follows:
a) Open Word in a separate window with a new, blank document
b) Left click once in the "portal.pogc.org" document, and type “Ctrl + A”. This selects the entire
document.
c) Type “Ctrl + C”. This copies the entire document
d) Go to the new blank Word document and left click in it.
e) Type “Ctrl + V. This pastes the entire document
f) The document can now be manipulated as required.