Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 1 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
1
By Regd. Post with AD
भारत सरकार / Government of India
रेऱ मतं्राऱय / Ministry of Railways
दक्षिण मध्य रेऱवे / South Central Railway
ववजयवाडा मडंऱ / Vijayawada Division
मडंऱ रेऱ प्रबन्धक का कायााऱय
Office of the Divisional Railway Manager
काया शाखा / Works Branch
ववजयवाडा / Vijayawada.
No. B/W.496/I/4/T No.04/South/2016/T-I Dt. 19.05.2016
Shri. A. Koti Reddy, S/o Subba Reddy, House No. HIG-18,
APHB Colony, Nallapadu Road,
GUNTUR 522 005
Sir,
Sub: Tender No 04/South/2016 for the work “SW-I: Gudur-Repairs to Galvalume sheet on platform
Nos 1,2 & 3 shelter. SW-II: (i) Replacement of corroded G.I sheet, broken AC sheet and
corroded gutter sheet on platform shelters in Nellore sub-division.(ii) Replacement of corroded
G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-
division.” -Issue of Letter of Acceptance - Reg”
Ref: Your offer in above tender submitted 30.03.2016 valid upto 27.06.2016
***
1. The competent authority has accepted your offer in the above said tender at the following rates
quoted by you:
Schedule‟A‟
USSR-2010 (-)20.79% Minus Twenty point seven nine percent.
For a total value of Rs. 37,41,993/- (Rupees Thirty-seven lakhs forty-one thousand nine
hundred and ninety-three only).
2. The work should be completed within 06 Months from the date of issue of letter of acceptance of
tender. Maintenance period of Six Months.
3. The sum of Rs 94,490/- submitted vide DD No : 083429 dt.29.03.2016 (realized vide MCR No.
309611 dt . 13.04.2016) Issued by State Bank of India, Guntur, towards EMD has been adjusted as
part amount of the security deposit. The balance security deposit of Rs. 92,610/- shall be recovered
at 10% of the bill amount till the full security deposit of Rs. 1,87,100/- is recovered.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 2 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
2
4. In terms of special conditions of the contract, you shall furnish a performance guarantee either in the
form of irrevocable Bank guarantee (Proforma enclosed) amounting to 5% of the contract value i.e.,
Rs. 1,87,100/- or in any form as mentioned in special conditions of contract provided in the tender
document vide clause 9 (b) before signing of the agreement. The performance guarantee should be
valid up to the period of physical completion of the work plus 60 days beyond that. You shall have
to submit a Performance Guarantee (PG) within 30 (thirty) days from the date of issue of Letter of
Acceptance (excluding date of issue of Letter of Acceptance). Extension of time for submission of
PG beyond 30(thirty) days and up to 60 days from the date of issue of LOA (excluding date of issue
of Letter of Acceptance) may be given by the Authority who is competent to sign the contract
agreement. However, a penal interest of 15% per annum shall be charged for the delay beyond 30
(thirty) days, i.e., from 31st day after the date of issue of LOA. In case the contractor fails to submit
the requisite PG even after 60 days from the date of issue of LOA, the contract shall be terminated
duly forfeiting EMD and other dues, if any payable against that contract. You shall be debarred
from participating in re-tender for that work. Performance guarantee shall be released after
satisfactory completion of the work based on “completion certificate” issued by competent
authority. For failure to submit performance guarantee as above and sign the agreement within the
stipulated time, action will be taken under relevant clauses of tender conditions/General conditions
of the contract.
5. Until a formal agreement is executed, acceptance of the Tender shall constitute a binding contract
between you and the administration.
6. You have to abide by the contract labour regulations and Abolition Act 1970) and rules, regulations
and amendments thereto that may be followed from time to time are binding on you in respect of
this contract. You have to submit the application in the prescribed form (Form-V) in triplicate for
license under contract labour (Regulation and abolition) Act for 20 or more workers and under
BOCW Act for less than 20 workers together with the demand draft towards security deposit and
license fee to the undersigned to forward the same to the concerned Licensing Officer for issue of
the license irrespective of the number of labour employed for the work. The work should not
be executed without a valid labour license.
7. Failure to start the work within ten days, the contractor is liable for penal action as per
clause 62 of the General conditions of contract.
Encl: Schedule with conditions and the bank guarantee Pro-forma
Yours faithfully
(B. Venkata Rao)
Sr.Divisional Engineer/South
S.C.Railway/Vijayawada.
For and on behalf of the President of India Copy to: 1) Sr DFM/BZA (2) ADEN/NLR & OGL (3) SSE/Works/NLR, GDR & OGL (4) Ch.OS/WA-South (5)
SSE/Drg./bldgs.(6) OS/Budget (7)Asst Labour Commissioner (Central), 5th Floor, Central Govt. Office Complex, Plot
No.G.2, Industrial Estate, Autonagar, Vijayawada – 520 0007 for kind information.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 3 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
3
South Central Railway Vijayawada Division
Tender No. 04/South/2016
SW-I: Gudur-Repairs to Galvalume sheet on platform Nos 1,2 & 3 shelter. SW-II: (i)
Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division.(ii) Replacement of corroded G.I sheet, broken AC sheet and
corroded gutter sheet on platform shelters in Ongole sub-division.
Aggregate awarded Value: Rs.37,41,993/-
Est. Sanctioned No&date Allocation Amount Rs.
SW-I: B/W.375/V/1292/Plg, dt.18-11-2015 04-420-32 20,35,214/-
SW-II: B/W.375/V/1297/Plg, dt.20-01-2016 04-420-32 26,88,928/-
Period of Completion Six Months
Period of Maintenance Six Months
Name of the Tenderer/
Contractor
A. Koti Reddy, S/o Subba Reddy, House No. HIG-18,
APHB Colony, Nallapadu Road, GUNTUR 522 005.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 4 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
4
SCHEDULE-A
List of items of works that are covered in Indian Railways Unified SSR 2010
Sl. No.
SSR No. Description of work SW-I Qty
SW-II Qty Total Qty
Rate Rs
Unit Amount
Rs NLR OGL
1 021140
Leading miscellaneous materials such as iron work, rails, fitting & fastenings, pipes, wooden logs, stones over pitching stone size, RCC/PCC beams / slabs etc. and all similar articles (each individual article or bundle being not more than 3.5 metres long in the longest direction) including picking up unloading and stacking, lead upto 50m.
6.5 0 0 6.5 113.46 MT 737
2 021141
Additional lead for every subsequent 50m or part thereof, over 50m and upto 500m over item no. 021140.
6.5 0 0 6.5 31.58 MT 205
3 101060
Providing flashing of 40cm overall width in plain, G.S. sheet, 1.00mm thick with zinc coating not less than 275gm/ sqm., fixed with polymer coated J or L hooks, bolts and nuts, G,I, limpet and bitumen washer complete, bent to shape and fixed in wall with cement mortar 1:3 (1cement: 3coarse sand)
132 0 0 132 289.66 metre 38235
4 109150
Supplying, fabricating and erecting valley gutter having 1.00 meter width, made out of 0.91mm thick aluminum sheets, the joints shall be made by aluminum welding to make water tight including supplying manufacturing and fixing brackets made out of MS flats 50mm x 6mm at the spacing of 75 cm center to center. The rate will be including supply of all materials, labours, tools, plants, equipments, scaffolding and staging etc. Complete work shall be carried out as directed by engineer in charge
266 829 1130 2225 865.10 metre 1924848
5 109230
Supply and Installation, including lifting to all heights as required, trapezoidal/corrugated sheeting system in galvalume colour coated steel having cover width of 1000 mm, 35 mm crest at a pitch of 250 mm stiffened with 8 mm deep intermittent corrugations or profiling approved by engineer-in-charge. Sheet should be made from base metal having 0.52 mm (±0.02 mm) thickness in steel of grade 345 as per ASTM A792M, .. coated with alloy of Aluminum & Zinc to grade AZ150 (min. alloy mass 150 gsm total both sides) with colour coating having complete dip tank pre-treatment process with Chromate Conversion (Cr +3) as main pre-treatment followed by PU primer (Permaprime grade) of min. 5 micron DFT on each surface; finished with special polyester paint to grade EPG-20 of minimum 20 micron DFT on exposed surface and 5 micron in grey shade on unexposed surface. Fixing shall be done with self-tapping screws meeting requirement of Class-3 of AS 3566 with EPDM washers at suitable intervals as per site requirement and as directed by Engineer Incharge complete work
3056.4 0 0 3056.4 543.10 Sqm 1659931
6 184081
Dismantling roofing including ridges, hips valleys and gutters etc. and stacking the material within 50m lead of G.I. sheet. NOTE : At Kavali, Ongole all platforms during dismantling GI sheets, the sheets to be removed carefully without any damages and to be fixed after fixing of gutters, the necessary self drilling screws for fixing of GI sheets to be prouned by the contractor at his own cost. Rate to quoted accordingly.
3010.2 829 290 4129.2 35.21 sqm 145389
7 184082
Dismantling roofing including ridges, hips valleys and gutters etc. and stacking the material within 50m lead of Asbestos sheet
0 1246 460 1706 16.57 Sqm 28268
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 5 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
5
Sl. No.
SSR No. Description of work SW-I Qty
SW-II Qty Total Qty
Rate Rs
Unit Amount
Rs NLR OGL
8 109200
Providing and fixing permanently colour coated trapezoidal profiled sheet of depth 28-30mm at195-205mm pitch distance with precisely engineered “Rib & Flute” design. Profiled sheets shall be min. 0.5mm TCT/0.45mm BMT high tensile zinc aluminium alloy coated zincalume /galvalume steel sheet (550 mpa yield strength) having a coating of mass of 150 gsm zinc- aluminium coating AZ-150 total on both sides as per, AS 1397:1993 finished with 20 microns approved colour coating of Silicon Modified Polyester (SMP) / Super Polyester paint coat on exposed surface over a primer coat of 5 microns and a back coat of 5 microns on reverse side over a 5 microns primer coat. There shall be 2 small ribs/square flutes between profiles for providing additional strength. The sheet to be fixed over the purlins with hexagonal head self drilling suitable fasteners with neoprene / EPDM washer on crests of the sheet
0 1246 460 1706 543.10 Sqm 926529
(Items Eight Only) Total of Schedule - A 4724142
PERCENTAGE RATE QUOTED
IN FIGURES (-)20.79%
PERCENTAGE RATE QUOTED
IN WORDS Minus Twenty point seven nine percent.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 6 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
6
CONDITIONS
1. The tenders are required to quote a uniform percentage rate above or below or at per of
USSR-2010 for all the items included in the Sch-A both in figures and in words. If there
is variation between the rates quoted in figures and words, the rate quoted in words will
be taken as correct. Tenderer should not quote different rates for different items of the
schedule. Offers with different rates are liable for rejection.
2. The quantities furnished in the schedule are approximate and the work will be carried out
as directed by the Engineer-in-charge. Payment will be made for the quantities actually
executed.
3. The rates quoted by the contractor will be inclusive of the cost of all the materials, labour,
tools & Plants etc., complete including transportation of the same at his own cost
including loading and unloading.
4. The Railway reserves the right to reject or alter any part of the work executed by the
contractor, which in the judgment of Railway does not comply with the requirements of
the specifications. The decision of the Railway shall be final and conclusive for all
purposes.
5. All the works executed by the tenderer/contractor covered in USSR-2010 should comply
with Indian Railways Unified Specifications for Works & Materials-2010 (Vol-I &
II). 6. All the works executed by the tenderer/contractor shall in accordance with Indian
Railways Works Manual-2000 and Code for the Engineering department-2012. 7. All the works executed by the tenderer/contractor shall be followed/comply/in
accordance with engineering standing orders issued by Principal Chief Engineer,
S.C.Railway from time to time.
8. Conservancy charges as applicable and as modified from time to time will be recovered
from Contractor‟s running bills.
9. Vehicles and equipment of contractors can be drafted by Railway Administration in case
of accidents/natural calamities involving human lives.
10. The Railway administration will not be responsible for the safety of contractor‟s labour
deployed on this work.
11. The Work should be completed within 6 ( Six) months period from the date of issue of
Acceptance letter.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 7 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
7
ANNEXURE „A‟
SPECIFICATIONS FOR ROOFING WITH COLOUR COATED GALVALUME
SHEETS.
1. Providing and fixing profiled, colour coated galvalume sheet 975-1000 mm cover width
25 to 45mm crest height at 195 – 255 mm centers, in lengths to suit site requirements.
2. Base material shall be cold rolled steel, 550 M Pa yield strength with metallic coating of
alluminium zinc alloy ( Galvalunic 150 gms / sqm total of both sides AZ 150 as per
ASTMA 792 or AS 1397) or equivalent.
3. The total coated thickness of the profile sheet shall 0.5 mm including polyster coating
(SAIP – Silicon Modified Polyester coating.)
4. The payment shall be made for the laid area inclusive of flashing, capping large boards
etc., and no extra payment shall be made for overlaps.
5. Coated sheets should be erected as soon as possible after their arrival at job site. If
temporary storage is necessary, it shall be done at the cost of the Contractor and shall be
stacked in such a way to prevent entry of moisture into the bundle.
6. In seal tape (Golvi strips) of 9mm wide and 2.5mm thickness shall be provided at side
laps and end laps between metal roofing sheet and polycarbonate sheet used for strip
lighting.
7. The roof sheets may be supplied in one length to avoid end laps in roof sheeting based on
the length of the sheet required to cover roofing on either side of the symmetrical ridge.
FIXING:
1. Roofing sheets shall be factory cut and supplied in required lengths to suit shop drawings.
2. Roofing sheet shall be crest fixed to purlins with hot dip galvanized self drilling fasteners
with integral PRDM washers. (One fastener on each crest)
3. Also, fasteners to be provided on side laps with one crest width including lip with
minimum sheet overlap at end laps shall be 150mm.
4. Penetration and over lappings in sheets shall be sealed by using proper sealent.
5. Prefilled MDPE fillers shall be provided wherever required to close voids between over
lapping of the sheets, to provide a weather tight exterior.
HL STRIP LIGHTING IN ROOFING/WALLING:
1. Embossed Polycarbonate sheet 2mm thick to match the profile of metal coated
sheets shall be used.
2. Width of the profilled polycarbonate sheet shall be 0.8 to 1.2 m wide and a
maximum length of 3 metres with overlap on either side in metal coated sheets
equal to one crest width and lip on one side and one crest width other side with a
minimum longitudinal lap of 150mm per sheet.
3. Fixing shall be done with bolts and nuts, neoprene washers/self lapping screws
with suitable washers as required.
4. Works shall be executed in high roof shed which involves carrying of materials,
fixing in position at the desired elevation as directed and approved by the
Engineer-in-charge.
5. The work shall also include hiring of tools, plants for the work using scaffolding
materials required for erection at Contractor‟s own cost.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 8 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
8
6. Payment shall be made only for the lighting area in roofing and no extra payment
shall be made for over laps.
SPECIAL CONDITIONS AND SPECIFICATIONS FOR STEEL WORK FOR COVER
OVER PLATFORM SHELTERS (IRS TYPE WITH CURVED / CRIMPLED FACIA
BOARDS): 1. Materials mild steel should confirm to I.S. Specification I.S. 2062-2006. Necessary steel Test
Certificate should be furnished before taking up the work along with purchase bills for the
proof.
2. The steel used for the bridges/cover over platforms shall confirm to specification No. IS
2062-2006 Grade-„B‟ and it is to be ensured that the steel used for FOB/COP shall not be of
re-rolled variety and should be from the stock yards of SAIL/TISCO/IISCO/VSP firms to the
above Specifications for the Materials used for this work of S.C.Railway.
3. The painting with red lead should confirm to the red lead dry pigment to Specification IS type
– „C‟ of 57-1965 with pure boiled linseed oil to IS Specification 77-1976 mixed in properties
of 3.3 Kgs., red lead pigment to one litre of boiled linseed oil.
4. The painting with Alluminium should confirm to IS 3339-63.
5. All rivet steel to comply with IS Specification 1148/64.
6. Fabrication of steel work should comply with IRS Specification BI-79.
7. Welding should confirm to IS 823/64 if so, where ever required.
8. Any work shall be executed by the contractor on running track in a workman like manner to
the satisfaction of the Engineer-in-charge. In the event of an accident occurring wholly or
partly due to any act of tantamounts to the negligence on the part of the contractor or his
labour, the contractor shall render himself liable for the damages and also legal prosecution if
loss of life is involved.
9. The Railway reserves the right to reject or alter any part of the work executed by the
contractor which in the judgment of Rly. does not comply with the requirements of the
specification. The decision of Railway shall be final and conclusive for all proposes.
10. The Steel cribs/Wooden blocks required for the work will be supplied at the nearest stores of
SSE/Br/P-Way/concerned. The Contractor has to transport them to and fro at his own cost.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 9 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
9
CONDITIONS OF CONTRACT
1. The rates include all lead and if the materials obtained by rail all freight charges including
loading charges.
2. Sales tax, Royalties and Octroi duties, if any, that may be payable under Provincial
Government Sales Tax Act or Local Bodies Act or rules on any of the material that may be
used or supplied by the contractor will be payable by the contractor. The Railway will neither
pay the taxes or duties nor be bound to compensate the contractor for any amounts paid by him
by way of these taxes or duties.
Sales Tax at 4% on the materials portion of the contract will be deducted from each on account
bill where identifiable. Where the labour and material portion is not clearly identifiable, the
labour element shall be taken as 30%. On the balance 70% of the value of the work, 4% shall
be deducted pro-rata from each “on account bill” towards Sales tax.
Seigniorage charges recoverable from bills:- Seigniorage charges for supply of earth, mooram, sand and other minerals as fixed by the State
Government and payable to them as revised from time to time during the currency of contract
will be recovered by Railway from the contractors “on account” and “final bills” and remitted
to the state government. The rates quoted by the Tenderer shall be inclusive of these charges.
Claims regarding revision of seigniorage charges and consequent enhancement of the accepted
rate will not be entertained. However, no seigniorage charges / fee shall be recovered from the
bills of the contractor, if the contractor produces documentary evidence e.g. “Transit Passes”
issued by State Govt. Officials in token of having paid seigniorage fee. In such cases, the
genuineness of such documentary evidence produced along with proof of payment of
seigniorage charges, shall be got verified by the Railway from the concerned Mining and
Geology Dept
3. WATER:- A charge of One percent will be made by the Railway for the supply by the
Railway of piped water from existing pipe lines and calculated on the amount of all items of
work (USSR/NS items) appearing in the bills payable to the contractor in respect of which
work such water has been issued to the Contractor and such charges should be deducted from
sums due or payable by the Railway to the Contractor from time to time.
4. In the event of water having to be brought by the Railway to the site of the work in traveling
tanks, the actual freight at Public Tariff rate and all other charges incurred therein including any
demurrage that may be levied shall be payable by the Contractor and deducted from sums due
or payable by the Railways to the Contractor from time to time.
In addition to the charges of one percent referred to above, if additional pipe lines to
those already existing are called for by the contractor, the cost of the same and all charges
incurred by the Railway in their laying including supervision charges will be paid by the
contractor or the contractor provides and lay his own piping at the discretion of Divisional
Engineer.
5. The Railway does not guarantee work under each items of the Master Schedule. For example if
a gate-lodge or gang huts are to be built between stations and the work order issued to the
sectional contractors additional payment on account of lead or freight charges for the materials
that may have to be brought by rail or by road, will not be admissible.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 10 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
10
6. If there arises any discrepancy between the printed Unified Standard Schedule of Rates 2010 as
amended by addendum and corrigendum slips issued from time to time upto date and the
schedule attached to the Tender pertaining to this work, the former shall be treated as
authentative and binding in all purposes.
7. Rubble masonry shall be first sum of Railways Specification No 503 according to South
Central Railway Specification for materials and works. Contractors attention is particularly
invited to dressing of stone as laid down in the Railway‟s specification.
8. The Special conditions supplemented to the conditions of Tender and contracts the General
conditions of contract and the notes appearing under the relevant chapter and sub chapters of
the Unified Standard Schedule of Rates 2010 should be considered as part of the contract
papers where the provisions of these conditions are at variance with General Conditions of
Contract these special conditions shall prevail.
9. Performance Guarantee (P.G.):-
a. The successful bidder shall have to submit a Performance Guarantee (PG) within 30
(thirty) days from the date of issue of Letter of Acceptance (excluding the date of LOA
(Ref: CE/Works/SC Lr.W.148/P/GCC/Vil.II, dt.30.05.2014). Extension of time for
submission of PG beyond 30 (thirty) days and upto 60 days from the date of issue of
LOA may be given by the Authority who is competent to sign the contract agreement.
However, a penal interest of 15% per annum shall be charged for the delay beyond 30
(thirty) days, i.e., from 31st day after the date of issue of LOA (excluding the date of
LOA). In case the contractor fails to submit the requisite PG even after 60 days from
the date of issue of LOA, the contract shall be terminated duly forfeiting EMD and
other dues, if any payable against that contract. The failed contractor shall be debarred
from participating in re-tender for that work.
b. The successful bidder shall submit a Performance Guarantee (PG) in any of the
following forms, amounting to 5% of the contract value:-
(i) A deposit of Cash,
(ii) Irrevocable Bank Guarantee,
(iii) Government Securities including State Loan Bonds at 5 percent below the
market value
(iv) Deposit receipts, Pay orders, Demand Drafts and Guarantee Bonds. These
forms of Performance Guarantee could be either of the State Bank of India or
of any of the Nationalized Banks;
(v) Guarantee Bonds executed or Deposits Receipts tendered by all Scheduled
Banks;
(vi) A Deposit in the Post Office Saving Bank;
(vii) A Deposit in the National Savings Certificates;
(viii) Twelve years National Defence Certificates;
(ix) Ten years Defence Deposits;
(x) National Defence Bonds; and
(xi) Unit Trust Certificates at 5 percent below market value or at the face value
whichever is less.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 11 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
11
Also FDR in favour of Senior Divisional Finance Manager, S. C. Railway, Vijayawada
(free from any encumbrance) may be accepted.
1. The Performance Guarantee shall be submitted by the successful bidder after the Letter
Of Acceptance (LOA) has been issued, but before signing of the contract agreement.
This P.G. shall be initially valid up to the stipulated date of completion plus 60 days
beyond that. In case, the time for completion of work gets extended, the contractor
shall get the validity of P.G. extended to cover such extended time for completion of
work plus 60 days.
1.0 The value of PG to be submitted by the contractor will not change for variation upto
25% (either increase or decrease). In case during the course of execution, value of the
contract increases by more than 25% of the original contract value, an additional
Performance Guarantee amounting to 5%(five percent) for the excess value over the
original contract value should be deposited by the Contractor.
1.1 The Performance Guarantee (PG) shall be released after physical completion of the
work based on the „Completion Certificate‟ issued by the competent authority stating
that the contractor has completed the work in all respects satisfactorily. The security
deposit, however, shall be released only after the expiry of the maintenance period
and after passing the final bill based on „No Claim Certificate‟ from the contractor.
1.2 Whenever the contract is rescinded, the security deposit shall be forfeited and the
Performance Guarantee shall be encashed. The balance work shall be got done
independently without risk and cost of the failed contractor. The failed contractor
shall be debarred from participating in the tender for executing the balance work. If
the failed contractor is a JV or a partnership firm, then every member/ partner of such
a firm shall be debarred from participating in the tender for the balance work either in
his / her individual capacity or as a partner of any other JV / partnership firm.
1.3 The Engineer shall not make a claim under the Performance Guarantee except for
amounts to which the President of India is entitled under the contract (not
withstanding and / or without prejudice to any other provisions in the contract
agreement) and this shall be in the event of:
i) Failure of the contractor to extend the validity of the Performance Guarantee as
described herein above, in which event the Engineer may claim the full amount
of the Performance Guarantee.
ii) Failure of the contractor to pay President of India any amount due, either as
agreed by the contractor or determined under any of the Clauses / Conditions of
the agreement, within 30 days of the service of notice to this effect by Engineer.
iii) The contract being determined or rescinded under provision of the GCC the
Performance Guarantee shall be forfeited in full and shall be absolutely at the
disposal of the President of India
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 12 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
12
10. Security Deposit:-
The scale of Security Deposit that is to be recovered from the contractor shall be as follows.
i) Security Deposit should be 5% of the contract value.
ii) The rate of recovery will be at the rate of 10% of the bill amount till the full Security Deposit is recovered.
iii) Security Deposit will be recovered only from the running bills of the contract and no other mode of collecting SD such as SD in the form of instruments like Bank Guarantee, Fixed Deposit Receipt etc., shall be accepted towards Security deposit.
iv) Conversion of Security Deposit into FDR after recovery of full stipulated SD (FA& CAO/SC letter No.AFX/EMD/Policy/ Vol.I dt.26.8.2010 circulated vide PCE/SC lr. No.W.148/ SCRCA dt.30.9..2010):- If the contractor so desires, the cash deposits in the form of security deposit may be allowed to be converted into FDRs (in favour of respective Accounts Officers and on account of contractor), after full recovery, at the discretion of the Railway, duly collecting necessary charges of conversion by the Railway Administration.
The security deposit shall be released only after the expiry of the maintenance period and after passing the final bill based on „No Claim Certificate‟.
After the work is physically completed, security deposit recovered from the running bills of a contractor can be returned to him if he so desires, in lieu of FDR/irrevocable bank guarantee for equivalent amount to be submitted by him.
In case of contracts of value Rs.50 crores and above, irrevocable bank guarantee can also be accepted as a mode of obtaining security deposit.
11. REVISED COMPREHENSIVE CLAUSE 46A OF GCC– PRICE VARIATION CLAUSE: As per Railway Board Letter No.2007/CE-CT/18/Pt.19 dt.14.12.2012-Price Variation Clause shall be applicable only for contracts of value (contract agreement value) Rs.50 lakh and more, irrespective of the contract completion period and Addendum & Corrigendum Slip (ACS) No.6 to GCC, July 2013; Amendment to Clause 46A.7 (a sub-clause of PVC) to GCC, communicated vide PCE/SC Lr.No.W.148/P/ G.C.C./Vol.II dt.05.06.2014. Amendment to Clause 46A1 (ACS No.2 to GCC, July-2014), communicated vide PCE/SC Lr.No.W.148/P/G.C.C./Vol.II dt.12.12.2014.
Clause 46A-Price Variation clause:
46A.1. Price Variation clause shall be applicable only for contracts of value as prescribed by the Ministry of Railways through instructions/circulars issued from time to time and irrespective of the contract completion period. Variation in quantities shall not be taken into account for applicability of PVC in the contract. Materials supplied free of cost by Railway to the contractors shall fall outside the purview of Price Variation clause. If, in any case, accepted offer includes some specific payment to be made to consultants or some materials supplied by Railway free or at fixed rate, such payments shall be excluded from the gross value of the work for the purpose of payment/recovery of price variation. Applicability of PVC based on original contract value is illustrated as under: “If estimated value of tender (NIT value) is Rs.55 lakhs; but value of the contract as per contract agreement is Rs.45 laksh, then PVC shall not apply, even if the actual final value is Rs.50 laksh or more due to variation in quantities during execution of the contract. Thus, variation in quantities after signing of contract agreement is not relevant for deciding whether PVC is applicable to a contract or not”.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 13 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
13
46A.2. The Base Month for „Price Variation clause‟ shall be taken as month of opening of tender
including extensions. If any, unless otherwise stated elsewhere. The quarter for applicability of PVC shall commence from the month following the month of opening of tender. The Price Variation shall be based on the average Price Index of the quarter under consideration.
46A.3. Rates accepted by Railway Administration shall hold good till completion of work and no additional individual claim shall be admissible on account of fluctuations in market rates, increase in taxes/any other levies/tolls etc., except that payment/recovery for overall market situation shall be made as per Price Variation Clause given hereunder.
46A.4. Adjustment for variation in prices of material, labour, fuel, explosives detonators, steel, concreting, ferrous, non-ferrous, insulators, zinc and cement shall be determined in the manner prescribed.
46A.5. Components of various items in a contract on which variation in prices be admissible , shall be Material, Labour, Fuel, Explosives, Detonators, Steel, Cement, concreting, Ferrous, Non-ferrous, Insulator, Zinc, erection etc., However, for fixed components, no price variation shall be admissible.
46A.6. The percentages of labour component, material component, fuel component etc., in various types of Engineering Works shall be as under:
Component Percentage Component Percentage
A) Earthwork contracts:
Labour
component
50% Other material
components
15%
Fuel
component
20% Fixed
component*
15%
B) Ballast and Quarry Products contracts
Labour
component
55% Other material
components
15%
Fuel
component
15% Fixed
component*
15%
C) Tunnelling Contracts
Labour
component
45% Detonators
component
5%
Fuel
component
15% Other material
components
5%
Explosive
component
15% Fixed
component*
15%
D) Other Works Contracts
Labour
component
30% Fuel component 15%
Material
component
40% Fixed
component*
15%
*it shall not be considered for any price variation.
46A.7. The Amount of variation in prices in several components (labour material etc., )
shall be worked out by the following formulae:
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 14 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
14
i) L= W x (LQ-LB) x LC LB 100
ii) M = W x (MQ-MB) x MC MB 100
iii) F = W x (FQ-FB) x FC FB 100
iv) E = W x (EQ-EB) x EC EB 100
v) D = W x (DQ-DB) x DC DB 100
vi) S = SW x (SQ-SB) vii) C = CV x (CQ-CB)/CB
For Railway Electrification works:
viii) T = {(CS – CO) /CO X 0.4136} X Tc
ix) R = { (RT – RO) / RO + ( ZT - ZO ) / ZO x 0.06 } x Rc
x) N = { (PT – PO ) / PO } x Nc
xi) Z = { ( ZT – ZO ) / ZO } x Zc
xii) I = { ( IT – IO ) / IT } x 85
Where
L Amount of price variation in labour
M Amount of price variation in Materials
F Amount of price variation in fuel
E Amount of price variation in Explosives
D Amount of price variation in Detonators
S Amount of price variation in Steel
C Amount of price variation in Cement
T Amount of price variation in Concreting
R Amount of price variation in Ferrous Items
N Amount of price variation in Non-Ferrous Items
Z Amount of price variation in Zinc
I Amount of price variation in Insulator
LC % of Labour component
MC % of Material component
FC % of Fuel component
EC % of Explosive component
DC % of Detonators component
Tc % of Concreting Component
Rc % of Ferrous Component
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 15 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
15
Nc % of Non-Ferrous Component
Zc % of Zinc Component
W Gross value of work done by contractor as per on-account bill(s), excluding cost of materials supplied by Railway at fixed price, minus the price values of cement and steel. This will also exclude specific payment, if any, to be made to the consultants engaged by contractors (such payment shall be indicated in the contractor‟s offer)
LB
Consumer Price Index Number for Industrial Workers- All India- Published in RBI Bulletin for the base period.
LQ Consumer Price Index Number for Industrial Workers- All India-Published in RBI Bulletin for the average price index of the 3 months of the quarter under consideration.
MB Index Number of Wholesale Prices- By Groups and sub-Groups-All commodities- as published in the RBI Bulletin for the base period.
MQ Index Number of Wholesale Prices- By Groups and Sub-groups-All commodities- as published in the RBI Bulletin for the average Price index of the 3 months of the quarter under consideration.
FB Index Number of Wholesale Prices- By Groups and sub-Groups for Fuel and Power as published in the RBI Bulletin for the base period.
FQ Index Number of Wholesale Prices- By groups and sub-groups for Fuel and Power as published in the RBI Bulletin for the average price index of the 3 months of the quarter under consideration.
EB Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from whom purchases of explosives are made by the contractor for the base period.
EQ Cost of explosives as fixed by DGS&D in the relevant rate contract of the firm from whom purchases of explosives are made by the contractor for the average price index of the 3 months of the quarter under consideration
DB Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from whom purchases of detonators are made by the contractor for the base period.
DQ Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm from whom purchases of detonators are made by the contractor for the average price index of the 3 months of the quarter under consideration.
SW Weight of steel in tonne supplied by the contractor as per the „on-account‟ bill for the month under consideration
SQ SAILs (Steel Authority of India Limited) ex-works price plus Excise Duty thereof (In rupees per tone) for the relevant category of steel supplied by the contractor as prevailing on the first day of the month in which the steel was purchased by the contractor (or) as prevailing on the first day of the month in which steel was brought to the site by the contractor whichever is lower.
SB SAILs ex-works price plus Excise Duty thereof ( in Rs. Per tonne) for the relevant category of steel supplied by the contractor as prevailing on the first day of the month in which the tender was opened.
CV Value of cement supplied by contractor as per „on account‟ bill in the quarter under consideration.
CB Index no. of Wholesale Price of sub-group (of Cement & Lime) as published in RBI Bulletin for the base period.
CQ Index no. of Wholesale Price of sub-group (of Cement & Lime) as published in RBI Bulletin for the average price index of the 3 months of the quarter under consideration.
Cs RBI Wholesale Price index for cement and lime for the month which is six months prior to date of casting of foundation.
Co RBI Wholesale Price index for cement and lime for the month which is one month prior to date of opening of tender.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 16 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
16
RT IEEMA Price index for Iron & Steel for the month which is two months prior to date of inspection of material.
Ro IEEMA Price index for Iron & Steel for the month which is one month prior to date of opening of tender.
PT IEEMA Price for Copper wire bar for the month which is two months prior to date of inspection of material.
Po IEEMA Price for Copper wire bar for the month which is one month prior to date of opening of tender.
ZT IEEMA Price for Zinc for the month which is two months prior to date of inspection of material.
Zo IEEMA Price for Zinc for the month which is one month prior to date of opening of tender.
IT RBI Wholesale Price index for structural clay products for the month which is two months prior to date of inspection of material.
Io RBI Wholesale Price index for structural clay products for the month which is one month prior to date of opening of tender.
46A,
8.
The demands for escalation of cost shall be allowed on the basis of provisional indices made available by Reserve Bank of India. Any adjustment needed to be done based on the finally published indices shall be made as and when they became available.
46A.
9.
Relevant categories of steel for the purpose of operating Price Variation formula, as mentioned in this clause, based on Sails Ex-Works Price Plus Excise Duty thereof, shall be as under:
Sl.
No. Category of Steel supplied in Railway work
Category of Steel produced by SAIL Whose Ex-works Price Plus Excise Duty would be adopted to determine Price Variation.
1. Reinforcement bars and other rounds TMT 8mm IS 1786 Fe 415/Fe 500
2. All types and sizes of angles Angle 65x65x6mm IS 2062 E250A SK
3. All types and sizes of plates PM plates above 10-20mm IS 2062 E250A SK
4. All Types and sizes of channels and joists Channels 200x75mm IS 2062 E250A SK 5. Any other section of steel not covered in the
above categories and excluding HTS Average of price for the 3 categories covered under SL 1, 2, & 3 above.
46A.10 Price variation During Extended Period of contract.
The price adjustment as worked out above, ie., either increase or decrease shall be applicable up to the stipulated date of completion of work including the extended period of completion where such extension has been granted under Clause 17-1 Of the General Conditions of Contract. However, where extension of time has been granted due to contractors failure under Clause-17B of the General conditions of Contract, price adjustments shall be done as follows:
a) In case the indices increase above the indices applicable to the last month of original completion period or the extended period under clause 17-A, the price adjustment for the period of extension granted under Clause 17-B shall be limited to the amount payable as per the Indices applicable to the last month of the original completion period or the extended period under clause 17-A of the General conditions of contract; as the case may be.
b) In case the indices fall below the indices applicable to the last month of original/extended period of completion under clause 17-A, as the case may be; then the lower indices shall be adopted for the price adjustment for the period of extension under clause 17-B of the General Conditions of Contract.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 17 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
17
12. DEDUCTION OF INCOME TAX AT SOURCE
In terms of new Section 194-C inserted by the Finance Act 1972 , in the income tax Act 1961
the Railway shall at the time of arranging payments to the contractor and/or sub contractor(in
the case of sub contractor only when the Railway is responsible for payment of consideration
to him under the contract) for carrying out any work (including supply of labour for carrying
out any work) under the contract be entitled to deduct income tax at source on Income
comprised in the sum of such payments.
The deduction towards income tax to be made at source from the payments due to non-
residents shall continue to be governed by Section 195 of the Income Tax Act 1961.
No Income Tax will be deducted by the Railway on payments made for supply of materials
where such value of supply portion is distinct and ascertainable such as supply of Timber, tiles,
bricks, ballast including track/ballast etc. The deductions towards Income Tax to be made at
source from the payment due to non/residents shall continue to be governed by Section 195 of
the Income Tax Act 1961.
13. LIABILITY OF CONTRACTOR(S) - ANY DAMAGE SUSTAINED BY RAILWAYS
DURING ACCIDENTS ETC., CAUSED DUE TO CONTRACTOR(S) FAILURES, FAULT
OR NEGLIGENCE. Railway will post an Engineer-in-charge who may be SSE/SE/JE or Supervisor of any grade at
site for Technical Supervision of the work. This Engineer-in-charge will be responsible for
safety of the traffic. The work shall be executed by the contractor in a workman like manner to
the satisfaction of the Engineer-in-charge. The Contractor and his labour shall be guided by the
instructions of the Engineer-in-Charge. In the event of any accident occurring at the work site
and it is established during the departmental enquiry by the Railway or by Statutory enquiry of
CRS, that the accident occurred wholly or partly due to any act tantamounting to negligence on
the part of the contractor or his labour in not adhering to the instructions of the engineer-in-
charge, the contractor shall render himself liable for damages and also legal prosecution if loss
of life is involved.
14. Implementation of – the Building and other construction Workers (RECS) Act, 1996
and the Building and other Construction Workers Welfare Cess Act, 1996 in Railway
Contracts. “The Tenderer for carrying out any construction work in Andhra Pradesh (name of State) must
get themselves registered from the Registering Officer under Section-7 of the Building and
other Construction Workers Act, 1996 and rules made thereto by the Andhra Pradesh (name of
State)Government and submit certificate of registration issued from the Registering Officer of
the Andhra Pradesh(name of the State) Government (Labour Department). For enactment of
this act, the Tenderer shall be required to pay cess @ 1% of cost of construction work to be
deducted from each bill, Cost of material shall be outside the purview of cess, when supplied
under a separate schedule item.”
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 18 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
18
ANNEXURE- “III”
WORKS CONTRACT CLAUSE-13
1. In case cement, Steel, AC sheet with or without accessories, GI sheets with or without
accessories, glasses or any other materials/items are issued to the contractor(s) either free of
cost or on cost to be recovered for use on the work as stipulated in the agreement the supply
thereof shall be made in stages depending on the progress of the work, limited to the quantity
/quantities computed by the Railway, according to the prescribed specification and approved
drawings as per agreement.
The materials supplied should conform to Railway‟s Specification in all respects should be
in accordance with approved sample.
All such materials supplied to the contractor(s) for the work either free of charge or on
payment as the case may be will be issued to contractor(s) at the Railway depot/godown/goods
shed and will have to be transported by the contractor to the site of work at his cost. All such
materials shall be used by the Contractor for the work in such quantities as are indicated in the
schedule or in the relevant specifications or drawings or as approved by the Engineer, whose
decision thereon shall be final. Wastage or damages of such materials in any manner shall be
totally avoided. The contractor(s) shall be liable to the accountal for all such materials issued
by Railway either free of cost or on payment excluding the permissible wastage which incase
of steel materials should not in any case exceed 1% of the total quantity required for the work
as per the approved drawings. No wastage under other items is permissible. Short lengths of
rods should also be utilized to the extent possible by overlapping joints.
The Cement, Steel, A.C.Sheets with or without accessories, G.I sheets with or without
accessories glasses or any other materials issued in excess of the requirement(s) as above, shall
be returned in perfectly good condition by the contractor(s) to the Railway at the Railway
depot/Godown/Goods shed at________immediately after completion or termination of the
contract. If the contractor fails to return the said materials then the cost of such materials issued
in excess of the requirement as computed by Railway according to the specification and
approved drawings will be recovered from the contractor(s) at twice the prevailing procurement
cost at the time of last issue viz., 2 x (purchases price +5% freight only). This will be without
prejudice to the right of Railway to take action against the contractors under the condition of
the contract for not doing/completing the work according to the prescribed specification and
approved drawings. If it is discovered that the quantity of cement, steel or any other material
used is less than the quantity computed by the Railway, according to specifications and
approved drawings the cost of materials not returned will be recovered at the same rates as
applicable to excess issue of materials, indicated in the preceding para.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 19 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
19
2. It shall be the responsibility of the contractor to keep in safe custody any Railway material
plant or equipment issued for the work. The contractor shall at his own expense provide
suitable temporary shed/sheds for this purpose on the Railway land made available by the
Railway free of rent and shall remove the shed/sheds when no longer required in terms of
clause 30 of General conditions of contract.
3. If due to any reason the Railway is not in a position to make available the Railway land the
Railway Engineer-in-charge of the work may permit the contractor to erect at his own cost
shed/sheds or secure private accommodation outside the Railway premises. In such a case the
contractor may be permitted to take the Railway material required for the works outside the
railway premises and to store in the Shed so erected or private accommodation so secured. It
shall be the responsibility of the contractor to keep the railway material in safe custody and the
same should be kept entire separate from the contractors material and the Railway shall have
liberty to inspect the same from time to time.
4. The code Nos. description and rates given in the schedule are based on the printed USSR -
2010, of S.C.Railway. Any discrepancy noticed during the execution of the work, in the
working rates quantity of cement etc. should be rectified by reference to the printed schedule,
which shall be treated as authoritative and binding on the contract. The relevant notes
applicable to the respective sub chapters will apply to the items of the Tender schedule and
should be considered as having been incorporated in the contract agreement and binding on the
Contractor.
5. For any other items not specially shown in the schedule of rates appended to the tender
document, the Divisional/Executive Engineer will offer rates as shown for the_________ zone
in the South central railway printed USSR - 2010, of S.C.Railway subject to the same
percentage adjustment accepted in the contract being applicable to the additional items.
6. Railway shall not supply from its own quota to the contractors controlled or imported
commodities. Assistance will, however given by recommending to appropriate authorities.
Contractor applications for issue of import licenses and release of controlled commodities if the
Engineer is satisfied that this material is actually required by contractor for carrying out the
work and is not available in the country.
7. VARIATION OF COSTS
Price variation clause is not applicable for contract agreement value upto Rs.50 lakhs.
Time is the essence of contract 8. (a) PERIOD OF COMPLETION: The Railway expects that a resourceful and experienced
contractor should be able to complete the work in all respects within the period as
specified in the Tender Notice and in the Schedule where items of work are furnished from the date of letter of acceptance of the Tender
(b) Extension of time of completion will be governed by clause 17 of General Conditions
of Contract. However, while granting the extension of time under clause 17(B) of
GCC, a token penalty as deemed fit based on the circumstances of the case can be
imposed on the contractor without prejudice to other rights of Railway
Administration as provided under GCC.
9. MAINTENANCE PERIOD: The work shall be maintained after completion for a period as
specified in the Schedule where items of work are furnished by the contractor and he shall
make good any defects, imperfections, shrinkages or faults which may appear at his own cost.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 20 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
20
10. It is HEREBY AGREED that it shall be the duty of the contractor to keep himself informed of
all corrections, and amendments of the said General conditions of contract made up to the date
of the execution of these presents and no objection shall be taken by the contractor on the
ground that he was not aware of such amendments and corrections of the said General
Conditions of Contract or to any of them.
11. VARIATION IN CONTRACT QUANTITIES:-
The procedure as detailed below shall be adopted for dealing with variations in quantities
during execution of works contracts: a) The Railway reserves the right to alter the designs and drawings. If due to change of
drawing or design or any other reasons, there be variations, either increase or decrease in
quantities, payment will be made only for the actual quantities executed at the accepted
rates. If there be sufficient cause the Railway may grant extension of the date of
completion suitably. Such circumstances shall in no way affect or vitiate the contract or
alter the character thereof, or entitle the contractor to damages or compensation thereof
except as provided for in this contract.
b) The quantities of each item of work furnished in the Schedule are approximate and are
intended for the guidance of Tenderer/Contractor. In actual execution of work there may
be some increase in the quantities specified. Such variation upto 25% shall in no degree
affect the validity of the contract and it shall be performed by the contractor as provided
therein and be subjected to the same conditions, stipulations and obligations originally
and expressly included and provided for in specifications and drawings and the amount
to be paid there for shall be calculated in accordance with accepted schedule rates.
(1) Prior Finance concurrence is necessary for varying the individual quantities
beyond 25% or where the gross agreement value exceeds 25% of the agreement
value.
(2) Individual NS items in contracts shall be operated with variations of plus or minus
25% and payment would be made as per the agreement rate. For this, no Finance
concurrence would be required.
(3) In case an increase in quantity of an individual item by more than 25% of the
agreement quantity is considered unavoidable, the same shall be got executed by
floating a fresh tender. If floating a fresh tender for operating that item is
considered not practicable, quantity of that item may be operated in excess of
125% of the agreement quantity (100% i.e. the original quantity +25% i.e. quantity
over and above the original quantity) subject to the following conditions.
a) Operation of an item by more than 125% of the agreement quantity needs
the approval of an officer of the rank not less than S.A. Grade:
i) Quantities operated in excess of 125% but upto 140% of the
agreement quantity of the concerned item, shall be paid at 98% of the
rate awarded for that item in that particular tender;
ii) Quantities operated in excess of 140% but upto 150% of the
agreement quantity of the concerned item shall be paid at 96% of the
rate awarded for that item in that particular tender;
iii) Variation in quantities of individual items beyond 150% will be
prohibited and would be permitted only in exceptional unavoidable
circumstances with the concurrence of associate finance and shall be
paid at 96% of the rate awarded for that item in that particular tender
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 21 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
21
b) The variation in quantities as per the above formula will apply only to the
Individual items of the contract and not on the overall contract value.
c) Execution of quantities beyond 150% of the overall agreement value should
not be permitted and, if found necessary should be only through fresh
tenders or by negotiating with existing contractor, with prior personal
concurrence of FA&CAO/ FA&CAO(C) and approval of General Manager.
4. The limit for varying quantities for minor value items shall be 100% (as against
25% prescribed for other items). A minor value item for this purpose is defined as
an item whose original agreement value is less than 1% of the total original
agreement value.
5. No such quantity variation limit shall apply for foundation items.
6. As far as SSR/SOR items are concerned, the limit of 25% would apply to the
value of SSR/SOR schedule as a whole and not on individual SSR/SOR items.
However, in case of NS items, the limit of 25% would apply on the individual
items irrespective of the manner of quoting the rate (single percentage rate or
individual item rate).
7. For the tenders accepted at the Zonal Railways level, variations in the quantities
will be approved by the authority in whose powers revised value of the agreement
lies.
8. For tenders accepted by General Manager, variations upto 125% of the original
agreement value may be accepted by General Manager.
9. For tenders accepted by Board Members and Railway Ministers variations upto
110% of the original agreement value may be accepted by General Manager
10. The aspect of vitiation of tender with respect to variation in quantities should be
checked and avoided. In case of vitiation of the tender (both for increase as well as
decrease of value of contract agreement) sanction of the competent authority as per
single tender should be obtained.
11. In cases where decrease is involved during execution of contract:
a. The contract signing authority can decrease the items upto 25% of
individual item without finance concurrence.
b. For decrease beyond 25% for individual items or 25% of contract
agreement value, the approval of an officer not less than rank of S.A.
Grade may be taken, after obtaining „No claim certificate‟ from the
contractor and with finance concurrence giving detailed reasons for each
such decrease in the quantities.
c. It should be certified that the quantities proposed to be reduced will not be
required in the same work at a later stage
d. In the event of any reduction in the quantity to be executed for any reasons
whatsoever, the contractor shall not be entitled to any compensation but
shall be paid only for the actual amount of work done.
e. The contractor is bound to notify the Engineer at least seven days before the
necessity arises for the execution of any item in excess of 25% of the over
all value of the agreement.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 22 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
22
12. In case the contractor fails to attend the meeting after being notified to do so or in
the event of no settlement being arrived at, the Railway shall be entitled to execute
the extra works by other means and the contractor shall have no claim for loss or
damage that result from such procedure
12. Employment of Civil Engineering Graduates/Diploma-holders:
The contractor shall employ the following technical staff during the execution of this work.
i) One graduate engineer when the cost of the work to be executed is Rs.2 Crores and
above.
ii) One qualified diploma holder (over-seer) when the cost of the work to be executed is
more than Rs.25 lakhs but less than Rs.2 Crores. Technical staff should be available at
site whenever required by the Engineer-in-charge to take instructions. In case the
contractor fails to employ the technical staff as aforesaid, he shall be liable to pay a
reasonable amount not exceeding a sum of Rs.40,000/- (forty thousand only) for each
month of default in case of graduate engineer and Rs.25,000/- (twenty five thousand
only) for each month of default in case of diploma holder (over-seer)
(Modification of Cl.26 and introduction of new Cl.26A to IR‟s GCC Ref: Rly. Bd.
Lr.No.2012/CE-I/CT/0/20, dt.10.05.2013.)
The decision of the Engineer-in-charge as to the period for which the required technical staff
was not employed by the contractor and as to the reasonableness of the amount to be deducted
on this account shall be final and binding on the contractor.
iii) Individuals having Diploma in Railway Engineering awarded by IPWE (India) shall also
be considered as qualified Diploma holder Engineers and contractors for track contract
works can employ such individuals at their worksite on Indian Railways.
(Ref: Rly. Bd. Lr.No.2012/CE-I/CT/0/20, dt.12.07.2013.)
Note: The above clause is not applicable for contracts for Welding of Rail joints.
13. Railway Contractors / Extension of Provident Fund Act to the Employees working under
Railway Contractors:-
The Contractor shall comply with the provisions of EPF & MP Act, 1952 and obtain code
number from the concerned authorities whenever workmen employed by him are 20 or more.
He shall also indemnify Railways from and against any claim, penalties, recoveries under the
above Act and Rules. Contractors to get the code number under the EPF so as to enable the PF
Commissioners to extend the social security benefits to the workmen engaged by the Railway
contractors. The first month‟s bill will be released only after code number is taken from the PF
Office and a copy of coverage intimation produced. Subsequently for each month, bills will be
released only on submission of challans & 12 A monthly return copy in proof of remittance of
PF dues for previous month.”
14. Conservancy charges as applicable and as modified from time to time will be recovered
from Contractor‟s running bills.
Tender No. 04/South/2016
Contractor Sr.DEN/South/BZA Page 23 of 23
BZA Divn., SCR, T.No.04/South/2016 invited vide Open Tender Notice No.DRM/Works/BZA/04/2016 dt. 23 .02.2016, date of opening on 30.03.2016 for the work of SW-I: Gudur-Repairs to Galvalume sheet on PF.No.1,2 & 3 shelter. SW - II – (i) Replacement of corroded G.I.sheet, broken AC sheet and corroded gutter sheet on platform
shelters in Nellore sub-division, (ii) Replacement of corroded G.I sheet, broken AC sheet and corroded gutter sheet on platform shelters in Ongole sub-division..//LOA//
23
SPECIAL CONDITIONS
MODIFICATION TO CLAUSE 63 & 64 OF
GENERAL CONDITIONS OF CONTRACT
1. The Provision of Clause 63 and 64 of the General Conditions of Contract will be
applicable only for settlement of claims /disputes, for values less than or equal to
20% of the original value (excluding the cost of materials supplied free by
Railway) of the contract or 20% of the actual value of the work done (excluding the
value of the work rejected) under the contract whichever is less. When
claims/disputes are of value more than 20% of the value of the original contract or
20% of the value of the actual work done under the contract, whichever is less, the
contractor will not be entitled to seek such disputes/claims for reference to
arbitration and the provisions of Clause No; 63 &64 of the General Conditions of
Contract will not be applicable for referring the disputes to be settled through
arbitration
2. The Contractor shall furnish his monthly statement of claims as per Clause 43(1) of
General Conditions of Contract. But the Contractor should seek reference to
arbitration to settle the disputes only once, subject to the conditions as per Para 1
3. The Special conditions shall prevail over the existing Clause 63 & 64 of General
Conditions of contract