conventional facilities – mmf presentation outline
DESCRIPTION
Conventional Facilities – MMF Presentation Outline. Facility Design Criteria Site Location Facility Design Schedule. Facility Design Criteria. Facility Use Space Requirements Environmental Stability Temperature +/- 0.1 deg. C. Humidity VibrationTRANSCRIPT
![Page 1: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/1.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20041
Conventional Facilities – MMF Presentation Outline
Facility Design Criteria
Site Location
Facility Design
Schedule
![Page 2: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/2.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20042
Facility Design Criteria
Facility UseSpace RequirementsEnvironmental Stability
Temperature +/- 0.1 deg. C.Humidity
Vibration <0.5 micronsUtility Requirements
ElectricalOther
![Page 3: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/3.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20043
MMF Facility Uses
Undulator magnet tuning – 2 magnet measuring machine test stands
Aligned with same orientation to Earth’s magnetic field as LCLS Undulator Hall.
Undulator fiducialization – large coordinate measuring machineCradle assembly areaMagnet storage/temperature acclimationWork desks in lab and office space for 2 employees
![Page 4: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/4.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20044
Resultant Building Criteria
~4800 sq. ft. floor space (inc. ~3000 laboratory space) + mezzanine
Locate within an existing building to aid in temperature control
Adequate ceiling height for overhead cranes
Accessible for magnet delivery using trucks and forklifts
Availability of required utilities, esp. electrical service – 600A, 480v 3f
![Page 5: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/5.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20045
Building 081 Location
LCLS Undulator Hall
Research Yard
PEP Ring Road
![Page 6: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/6.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20046
Building 081 Site Layout
![Page 7: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/7.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20047
Building 081 Current Uses
![Page 8: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/8.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 20048
New Space Allocation for Bldg. 081
SHIPPING & RECEIVING
EQUIPMENT REPAIR
VEHICLE SHOP
Offices
![Page 10: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/10.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200410
MMF Ground Floor Plan
Magnet Measuring Lab
~1600 ft. sq.
![Page 11: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/11.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200411
MMF Ground Floor Plan
Coordinate Measuring
Area~ 1000 ft. sq.
![Page 12: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/12.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200412
MMF Ground Floor Plan
Cradle Assembly Area~325 ft. sq.
![Page 13: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/13.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200413
MMF Ground Floor Plan
Magnet Loading and Storage~850 ft. sq.
![Page 14: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/14.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200414
Mezzanine Floor Plan
Mezzanine for Mechanical Equipment
![Page 16: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/16.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200416
Rear Elevation
Roll up door for magnet delivery
Mechanical Access
Staff Access
![Page 17: Conventional Facilities – MMF Presentation Outline](https://reader035.vdocument.in/reader035/viewer/2022062805/56814d62550346895dbab1c1/html5/thumbnails/17.jpg)
Jo Beth Folger
MMF Site and Construction [email protected]
October 14, 200417
Schedule
Completion of Title II drawings December 2004
Bid and contract with general contractor January – April 2005
Construction May – November 2005 (Early Finish) February 2006 (Beneficial Occupancy)