convergence bidding issues eric hildebrandt, ph.d. caiso department of market monitoring cpuc...
TRANSCRIPT
Convergence Bidding Issues
Eric Hildebrandt, Ph.D. CAISO Department of Market Monitoring
CPUC Convergence Bidding WorkshopJuly 26, 2010
Average hourly LMPs: PG&E LAP, Q3 2010
Slide 2
$0
$10
$20
$30
$40
$50
$60
$70
$80
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
IFM
RTD
IFM RTD DifferencePeak $39.02 $39.36 -1%
Off-peak $25.32 $21.10 17%Total $34.46 $33.27 3%
Virtual demand profitable
Virtual supply profitable
Virtual supply
profitable
Potential benefits of LSE participation in convergence bidding.
Virtual demand Can commit generation unit in DA needed to meet real-time demand
e.g. extra generation during specific peak hours.
Virtual supply Can displace physical supply if market participant believes that less
physical supply will be needed in real time e.g. due to extra generation from unscheduled generation in off-peak
Can also prevent virtual demand by generators from undermining local market power mitigation procedures.
In these cases, convergence bidding can reduce the total cost of meeting overall demand and should be profitable (on average).
Slide 3
Safeguards against potential detrimental use of virtual bidding
Position limits
CRR “clawback” rule
Ability to temporarily suspend virtual bidding
Referral to FERC for market manipulation
Deep and liquid market for virtual bidding, including participation by LSE’s.
Slide 4
Illustrative Examples: Base Case (with no virtual bids)
Potential impact of virtual demand bids.
Potential impact with addition of relatively high priced virtual supply bids (e.g. traders).
Potential impact with addition of competitively priced virtual supply bids (e.g. LSEs).
Based on examples originally presented at August 10, 2007 MSC/Stakeholder meeting. Whitepaper available at: http://www.caiso.com/1c8f/1c8ff4236e8e0.pdf
Virtual Bidding and Local Market Power Mitigation
Base Case Example: Generation within non-competitive load pocket)
$160 Day Ahead
$150 Unit 6 Unit 7 Market Bid (Physical)
$140
$130
$120
$110
$100
$90
$80 Unit 5 Unit 7 DEB (Physical)
$70 Unit 4 Unit 6
$60 Unit 3 Unit 5
$50 Unit 2 Unit 4
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500 1,700
Unit MW DEB Bid1 200 $15 $352 200 $25 $453 200 $35 $554 200 $45 $655 200 $55 $756 200 $65 $1457 200 $75 $145
Competitive Constraints run of pre-IFM local market power mitigation procedures
$160 Day Ahead
$150 Unit 7 Market Bid (Physical)
$140
$130
$120
$110
$100
$90
$80 Unit 5 Unit 7 DEBs
$70
$60 Unit 3 Unit 5
$50 Unit 2
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500 1,700
Competitive Constraints (CC)
Dispatch Unit 6
Unit 6Unit 4
Unit 4
Generation clearing in load pocket with competitive constraints enforced
(under CAISO demand forecast)
All Constraints run of pre-IFM local market power mitigation procedures
$160 Day Ahead
$150 Unit 7 Market Bid (Physical)
$140
$130
$120
$110
$100
$90
$80 Unit 5 Unit 7 DEBs
$70
$60 Unit 3 Unit 5
$50 Unit 2
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500 1,700
Competitive Constraints (CC)
Dispatch
Unit 6
Unit 6Unit 4
Unit 4
All Constraints (AC) Dispatch
Generation clearing in load pocket with all constraints enforced
Mitigation of bids based on pre-IFM local market power mitigation procedures.
$160
$150 Unit 7
$140
$130 Final Day Ahead
$120 Market Bids
$110 (After Mitigation)
$100
$90
$80 Unit 5 Unit 7 DEB s
$70
$60 Unit 3 Unit 5
$50 Unit 2
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500 1,700
Competitive Constraints
(CC) Dispatch
Unit 6
Unit 6Unit 4
Unit 4
All Constraints (AC) Dispatch
Base Case (no virtual demand or supply): Final IFM market results
Day Ahead Demand Curve (physical)
$160 Final Day Ahead
$150 Unit 7 Market Bids
$140 (After Mitigation)
$130
$120
$110
$100
$90
$80 Unit 5 Unit 7 DEB (Physical)
$70 MCP = $65
$60 Unit 3 Unit 5
$50 Unit 2
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500
MCQ = 1,100 MW
Unit 6
Unit 4
Unit 4
Unit 6
Potential Impact of Virtual Demand Bids by Generators
Generator’s can be expected to submit virtual demand bids to “hedge” risk of outages in real time.
Local market power mitigation procedures may be undermined if virtual demand not offset by competitively priced virtual supply.
Although generator may loose on virtual demand bid, this may be profitable due to increase in revenues from DA sales from generation portfolio
This problem may be mitigated by competitively priced virtual supply bids from LSEs.
Example of potential impact of virtual demand on day-ahead market (without virtual supply)
Day Ahead Demand Bids (with virtual demand)
$160
$150 MCP = $145
$140
$130 Final Day Ahead
$120 Market Bids
$110 (After Mitigation)
$100
$90 DEBs
$80
$70
$60 Unit 3 Unit 5
$50 Unit 2
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500
Unit 4
Unit 4
Unit 6
Virtual Demand Bid
Unit 7
Unit 7Unit 5
Example of potential impact with relatively high priced virtual supply bids (e.g. by traders).
Day Ahead Demand Bids (with Virtual Demand)
$160
$150
$140
$130 Final Day Ahead
$120 Market Bids
$110 (After Mitigation)
$100
$90 DEBs
$80
$70
$60 Unit 3 Unit 5
$50 Unit 2
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500
Unit 4
Unit 4
Unit 6
Unit 7
Unit 7Unit 5
Virtual Supply Bid
Virtual Demand Bid
Example of potential impact with competitively priced virtual supply bids (e.g. LSE).
Day Ahead Demand Bids (with Virtual Demand)
$160
$150
$140
$130 Final Day Ahead
$120 Market Bids
$110 (After Mitigation)
$100
$90
$80
$70
$60 Unit 3 Unit 5
$50 Unit 2 DEBs
$40 Unit 1 Unit 3
$30 Unit 2
$20 Unit 1
$10
100 300 500 700 900 1,100 1,300 1,500
Unit 4
Unit 4
Unit 6
Unit 7
Unit 7Unit 5
Virtual Supply Bids
Virtual Demand Bid
Other issues
CPUC reporting and review Virtual bidding can provide “external” benefits by mitigating
supplier market power (which can lower overall costs and risks). Direct profits/losses from virtual bidding can be tracked/reported
on frequent basis (even daily). Portfolio level limits and/or review triggers could be established
to control/review losses.
Unregulated affiliate issues DMM will monitor for indications of any potential use of virtual
bidding by regulated entities to increase CRR revenues by unregulated affiliates.
CRR activity by regulated entities cannot be used to increase profitability of virtual bidding by unregulated affiliates.
Slide 15