convergence in mgnregs

42
SUSTAINABLE LIVELIHOOD THROUGH CONVERGENCE UNDER MGNREGA Presented by Dr. Ravindra pastor, Commissioner State of Madhya Pradesh

Upload: dr-ravindra-pastor

Post on 12-Apr-2017

514 views

Category:

Government & Nonprofit


3 download

TRANSCRIPT

Page 1: Convergence in MGNREGS

SUSTAINABLE LIVELIHOOD THROUGH CONVERGENCE

UNDER MGNREGA

Presented by

Dr. Ravindra pastor, Commissioner

State of Madhya Pradesh

Page 2: Convergence in MGNREGS

CONSTRAINTS

Limitations as per MGNERGA Act Labor Material 60:40 ratio.

Contractors not permitted.

Labor replacing machinery not permitted.

Limited permitted works.

Minimum Focus to Livelihood.

Page 3: Convergence in MGNREGS

APPROACH Transit walk. Household & Baseline survey. Participatory Net Planning (PNP) Identification of area of convergence. Need based action plan. Participatory Execution.

Page 4: Convergence in MGNREGS

GRAM PANCHAYATLa

bour

Bud

get

Freezing of accounts

Job card Up-

dationUpdate MIS data base

Job Card Register

SOPAS/TS

GRS

Door to door Survey by GRS & Mate

Active Job card holders ready to work as labour

Page 5: Convergence in MGNREGS

Active Job card holders ready to work Organisation as Activity Based labour

Groups

With Land Without LandGroups (45-50 Jobcard

Holders)

G-1 G-2 G-n G-1 G-2 G-n

Mate Mate Mate Mate Mate Mate

Wage Employme

nt to Sustainable Livelihood

1. Active job card holder

2. 8th class pass3. Anonymous

Choice of group

Qualifications ….. Job Chart …..1. End to end service provider 2. Demand of work, attendance,

providing payment slip to labours, site supervision and ensuring payment of wages.

3. Secretary of Society

Register as MACS Agri- cooperative

society

Register as MACS Labour cooperative

society

Page 6: Convergence in MGNREGS

Group

Demand Work

MATE

GRS Register the demand

Receipt

Work Allotment

Sarpanch/Sachiv

SOPAs per priority

Anx -4 will have the day

of start of work

GRS will inform the

group through MATE

Rojgar Diwas

Page 7: Convergence in MGNREGS

P1 Mon Tue Wed Thu Fri Sat

P2 Tue Wed Thu Fri Sat Mon

P3 Wed Thu Fri Sat Mon Tue

P4 Thu Fri Sat Mon Tue Wed

P5 Fri Sat Mon Tue Wed Thu

P6 Sat Mon Tue Wed Thus FriClus

ter

Faci

litat

ion

Team

Rojgar SaptahDay

1. Sub Engineer, Sachiv, Mate. Group members, Sarpanch , GRS

2. Sub Engineer will give the layout, Explain about estimates , task rates and procedure and site facilities.

Rojgar

Diwas

Page 8: Convergence in MGNREGS

GRS

Janpad (PO)

MIS Entry

Mate

Sub Engineer

Daily Attendance

GRSLast day of

Rojgar Saptah

Gram Panchayat

e Muster1. Unique ID2. Jobcard nos

and name of labours

3. Sign & Seal by PO

1. Total attendance in Site Order Book

2. Rough note of task performed

MR, MB, Bills of material purchased, Rough note of task performed

1. Site inspection2. Quality monitoring3. Measurement

verification4. Entry of valuation in

MR5. Sign of M&E

committeeGRS

Pay SlipLabourMate

On Rojgar Diwas

Page 9: Convergence in MGNREGS

GRS

Janpad (PO)

MIS Entry

PO + AAO

FTO

Next day of Rojgar Diwas

Finacials to be checked by AAO

Measurements to be checked

by AE

New eMuster

Records• Jobcard Register • Labour Group Registration• Shelf of Project• Work Register• Labour Budget• Muster Roll Register• Wage List• Material Register• Measurement Book• Employment Demand• Assets Register• Financial Records like –

Voucher folders, Grant Register, Cash Book, Ledger, Stock Register, Monthly Receipt & Payments, Bank/Post Office Reconciliation Register etc.

PCR

Page 10: Convergence in MGNREGS

MAJOR AREAS OF CONVERGENCE

Integrated Natural Resource Management.

Agriculture & Allied Activities for Sustainable Livelihood. Development of Required Infrastructures.

Page 11: Convergence in MGNREGS

GAP ANALYSIS

Gap Analysis at Family Level

Improving productivity of lands.

Improving & creating livelihood opportunities.

Development of fellow & waste land.

Improving civic amenities at household level.

Creating common infrastructure for community

organisation

Page 12: Convergence in MGNREGS

GAP ANALYSIS

Gap Analysis at Village level

Water conservation & water harvesting structures.

Micro & Minor irrigation structures.

Afforestation – Tree plantation & Horticulture.

Land Development works.

Improving forward-backward linkages.

Constructions of service/ office buildings.

Page 13: Convergence in MGNREGS

MAJOR CONVERGENCE PLAYERS WITH ACTIVITIES

(On gap analysis report)

{ NRM based }MGNREGA Activity Convergence Activities Convergence

Departments Irrigation facility - Dug well

{Kapildhara - Category(4c)}Pump Set Tribal, Agriculture

& SGSY

Irrigation facility -Watercourses/Field channel

{Sahastradhara-Category (4a)}

Implementation through WUA Departmental Technical Support

WRD & NVDA

Cluster Area Development

{Integrated Micro project- Category(1a)}

CSO’s as PIA, Convergence of Agriculture &

Livelihood Schemes

Agriculture, Horticulture,

Animal Husbandry Department

Narmada Valley Catchment Area Treatment

{ Category(1a) }

Technical Support & Monitoring Implementation by CSO’s PIA.

NVDA

Page 14: Convergence in MGNREGS

NREGA Activity Convergence Activities Convergence Players

Horticulture {Nandan Phalodhyan - Category(4e)}

Convergence with NHM, Technical Support

Horticulture Department

Fishries{Minakshi - Category(4d)}

Departmental Schemes, Technical Support

Fisheries Department

Nadep Composting

Training & Technical SupportAgriculture Department

Vermi CompostingLiquid bio-manures

Sanjeevak or Amrit pani{Agri. related works –

Category (10a/10b/10c)}

MAJOR CONVERGENCE PLAYERS WITH ACTIVITIES

{ Agri. & allied based }

Page 15: Convergence in MGNREGS

MGNREGA Activity Convergence Activities

Convergence Players

Poultry shelter

Livestock, Training, Departmental Schemes

Animal Husbandry Department

Goat shelter

Cattle Shed

Azolla as cattle-feed supplement{Livestock related works -

Category(11a/11b/11c/11d)}

Sericulture{Resham & Vanya - Category(4h)}

Subsidy, Technical & Marketing

Sericulture Department

MAJOR CONVERGENCE PLAYERS WITH ACTIVITIES

{Agri. & allied based }

Page 16: Convergence in MGNREGS

MGNREGA Activity Convergence Activities

Convergence Players

Village Internal C.C. Road {Panch Parmeshwar - Category(8d)}

Financial Part to Maintain 60:40 Ratio

Panchayat & Planning Department

Gravel Road {CMGSY - Category(8b)}

Construction of Bridges & Financial Support to Maintain

60:40 Ratio

BRGF & State Plan

BNRGSK (MGNREGA Part Rs.10.00 lacks)

{Panchayat Bhawan - Category(9a)}

Financial Part to Maintain 60:40 Ratio

BRGF, IAP, Performance Grant

MAJOR CONVERGENCE PLAYERS WITH ACTIVITIES

{ Rural infrastructure based }

Page 17: Convergence in MGNREGS

MGNREGA Activity Convergence Activities

Convergence Players

Playground {Grameen Kridangan - Category(15c)}

Sports Material

{upto 1.00 lac Village & upto 5.00 lac block level}

PYKKA (Panchayat Yuva Krida &

khel Abhiyan)

Rural Sanitation (IHHL){NBA - Category (15a)}

Financial Part to Maintain 60:40 Ratio

TSC

Rural Drinking Water well {Nirmal Neer - Category (14c)}

Technical Support Public Health & Engineering Department

MAJOR CONVERGENCE PLAYERS WITH ACTIVITIES

{ Rural infrastructure based }

Page 18: Convergence in MGNREGS

END TO END ACTION APPROACH

(Our Learning Example)

Activity Output Outcome Learning Value Chain ComponentsDug Well with

Pump set

Avg. 1.5 ha. Additional

area irrigated during RABI Yielded 7.34

Qtl. Of Wheat/ Gram

Rs.14680/- Additional

income generated in farmer family

Land has potentiality

to bring additional income to

family with support of irrigation

Backward Linkage• Land Development• Irrigation facilities• Pump sets• Quality Seed • Improved POP (Package of Practice) Forward Linkage• Proper Storage facility.• Collective marketing through

farmer producers company (FPC) for input & output management

• Village seed bank• Value addition

Page 19: Convergence in MGNREGS

MGNREGA 3.83 Lac sanctioned 2.85 Lac Wells Completed 3374 Cr. Expenditure

CONVERGENCE PARTNERS FOR LIFTING DEVICE -

RKVY, SGSY, ITDP, BSP

Amount – 135 Cr. Units - 90,670

AGRICULTURE SECTOR MODULEDUGWELL FOR IRRIGATION FACILITY

(KAPILDHARA)

Page 20: Convergence in MGNREGS

MGNREGA 5489 Works/ 12569 KM Sanctioned 2569.83 Cr. Cost 3646 Works Completed 1363.41 Cr. Expenditure

CONVERGENCE PARTNERS

ROAD SECTOR MODULECONSTRUCTION OF GRAVEL ROADS (CMGSY)

MGNREGS (State fund /BRGF)

Profile Correction

Embank-ment

Sub grade/ Base course GSB C D’s

Convergence Amount – 951.78 Cr. Units - 5489 roads

Page 21: Convergence in MGNREGS

MGNREGA 74,606 Works/ 9062 KM

Sanctioned 2626.48 Cr. Cost 45182 Works/ 5357 KMs

Completed 2009.34 Cr. Expenditure

CONVERGENCE PARTNERS- 13th Finance, State Finance Commission,

Stamp-Duty, Mining Royalty, Panchayat Fund, MP/MLA LAD's.

Convergence Amount – 531.33 cr. Units - 45182 roads

ROAD SECTOR MODULECONSTRUCTION OF INTERNAL C.C. ROADS

(PANCH PARMESHWAR)

Page 22: Convergence in MGNREGS

22

Nirmal Bharat Abhiyan

MGNREGA 206448 IHHL toilets Sanctioned 78945 Completed 62.55 Cr. Expenditure

CONVERGENCE PARTNERS FOR MATERIAL-

NBA

Amount – 96.97 Cr.

Page 23: Convergence in MGNREGS

Play ground / Area Development Plan

MGNREGA 12743 Works Sanctioned 4756 Works Completed 407.98 Cr. Cost 166.98 Cr. Expenditure

CONVERGENCE PARTNERS FOR SPORTS MATERIAL-

PYKKA

Amount – 66.29 Cr.

Page 24: Convergence in MGNREGS

24

Horticulture • 30710 Hect. Sanctioned Area• 650.53 Cr. Cost• 122.49 Cr. Expenditure• 32492 Beneficiaries

Convergence with NHM2.36 Cr.

• 10065 Beneficiaries benefited with irrigation facility through dug wells.

Integrated Natural Resource Development

Page 25: Convergence in MGNREGS

MGNREGA 1951 Works Sanctioned 944 Works Ongoing 124.02 Cr. Cost 11.34 Cr. Expenditure

CONVERGENCE PARTNERS - BRGF, IAP, ICDS, Finance

Commission

Amount – 5.64 Cr.

Rural Infrastructure SectorAGANWADI Centre

Page 26: Convergence in MGNREGS

SERICULTUREMGNREGA

658.64 Hect. Area Sanctioned 293 SHGs beneficiaries 7.13 Cr. Expenditure

CONVERGENCE PARTNERS - Sericulture Dept.

- Raring House, Kakoon, Training, Bank & Market linkages

Action plan for Additional 2 lac Hect. Area to be covered in next 3 to 6 years.

Page 27: Convergence in MGNREGS

IMPACT ASSESSMENT… FEW REFERENCES

Reduction in Distress Migration-20-92% (GIZ-P-26), 48% (As per AKRSP-P-20), 36-75% (IIF) 34% (IIM)

Increase in the Average No. of days of water availability 190-365 days. Higher as compare to Andhra Pradesh, Karnatka & Rajastathan (GIZ-P-12).

A significant improvement in cropping pattern (as per MPISSR 2010, MoRD 2012 report) GIZ report P-12 (39%-IIM), 16 Villages of study area MCM.

Page 28: Convergence in MGNREGS

AS OTHERS EVALUATED US..

Increase in irrigated area using surface water bodies like stop dam, pond and renovation of existing ponds–34.9-100 % and increase in the no. of days in water availability 108-240 days (GIZ-P-13).

Also Increase in irrigated area through construction of wells and increase in pumping time of water by– 62.5 % – 100% (GIZ-P-14, 15) from 48877 Ha. (2008-09) to 184934 Ha. upto June 2013 - (MP Agriculture economic survey report 2013-P-67)

Significant increase in Agriculture productivity (78% - IIM)

Page 29: Convergence in MGNREGS

IMPACT ASSESSMENT… FEW REFERENCES

Improvement in drinking water availability through open wells(GIZ-P-15) –

i. distance travel has decrease by 44.2% - 63.2%.

ii. Time required for water collection has decrease by an average 20%.

Major quantum of works implemented by G.P.s (IIM). More than 70% assets created are excellent/ good quality (IIFM).

80% of the funds utilized by the GP’s. 50% of the total expenditure utilize for livelihood activity.

Page 30: Convergence in MGNREGS

IMPACT ASSESSMENT… FEW REFERENCES

74% durable assets created in MGNREGA which is higher than National Avg. (NREGA soft).

30% Increase in student’s enrolment (IIM) 4-44% (IIFM). Improvement in standard of living, Food consumption,

quality & status of livestock (IIFM). Fair-weather roads provided critical link with market,

schools & health sectors (IIM).

Page 31: Convergence in MGNREGS

A MODEL CASE STUDY

Village – Tilgara

Block - Badnawar

District – Dhar (M.P.)

Page 32: Convergence in MGNREGS

IMPLEMENTATION OF MGNREGA

Work Category

Completed Work

Expenditure (In Lacs)

Up to year 2012-13

Up to year 2012-13

Water conservation and water harvesting 13 272.41

Drought proofing 19 29.01

Irrigation facility to land owned by beneficiaries 133 68.65

Land development 15 11.26

Rural connectivity 18 61.77

17%

30%

0%

50%03%

Water conservation andwater harvesting

Drought proofing

Irrigation facility to landowned by beneficiaries

Land development

Rural connectivity (In nos. & length in kms)

Page 33: Convergence in MGNREGS

MGNREGAConvergence with other departments

ITDP SGSY Agriculture Horticulture

Dug wells 101 45 26 2 20

Cost 75.63 8.40 lacs 13.00 lacs 0.60 lacs 20.00 lacs

101 dug well Total Convergence

(117.63 lacs)

ITDP 8.40 lacs

SGSY(13 lacs

Horticulture (20.00 Lacs)

Agriculture (0.60 lacs)

CONVERGENCE

Page 34: Convergence in MGNREGS

CONVERGENCE

MGNREGA(Nistar tank + Drinking

WaterWell)MLA FUND

(Electrification to well)

PHE Dep.(Pipeline+Motor+Sumpwell+Overhead

tank)

All season drinking water avialable

Jal Aawardhan Yojana (PHE Dep.) Cast 22.50 lacs.

Nistar Tank (NREGA)

(34.00 Lacs)

Electrification to well by MLA Fund

(2.5 Lack)

Drinking Water Well MGNREGA (1.82 lacs)

Water Supply to

Village

Tilgara

Wall

Recharg

e

Nistar ta

nk

Project Convergence (60.82 lacs )

CONVERGENCE (for Drinking Water Supply)

Page 35: Convergence in MGNREGS

Increase in irrigated Area

Type of Work No. of works Amount (in lacs)

Storing Capacity Generated

(MCFT)

Irrigated Area (hec.)

Nistar tank 18 185.97 28.86 76

Percolation Tank 4 14.94 2.45 -

Kapil Dhara 101 75.07 - 190

Nirmal Neer 4 13.31 - -

Stop Dam 2 96.92 18.6 149

Total 129 385.61 49.91 415

MGNREGS – ACHIEVEMENT

Page 36: Convergence in MGNREGS

148.92 Hect land of 87 farmers

irrigated.

69000 feet Pipe line installed by

farmers

for irrigation from stop dams.

40 electric/ Diesel pumps installed by

farmers.

41 farmers were Provided Subsidy

from Horticulture Department.

MGNREGS – ACHIEVEMENT(Milestone Structures of MGNREGS)

Page 37: Convergence in MGNREGS

MGNREGS – ACHIEVEMENT

(Irrigated Area)

492.81

945.2

0

200

400

600

800

1000

2006-07 2012-13

Irrigated Area (In Hec.)

Page 38: Convergence in MGNREGS

PRE MGNREGACrops

Area (in

ha.)

Production (in

qt./ha.)

Annual Production

(in qt.)

Chili 70 52 3640tomat

o 45 240 10800

Ginger 6 200 1200

Cotton 175 16 2800

Gram 41 8 328Whea

t 145 10 1450

POST MGNREGACrops

Area (in ha)

Production (in

qt./ha.)

Annual Productio

n (in qt.)

Capsicum 60 400 2400

Yellow chilli 30 50 1500

Chili 280 52 145600

Tomato 50 320 16000Ginger 8 250 2000cotton 150 28 4200

Chick pea 50 12 600

wheat 250 40 10000Other 67 0 0

MGNREGS – ACHIEVEMENT (Crop Area & Agri. Horti.Production)

Page 39: Convergence in MGNREGS

MGNREGS – ACHIEVEMENT (New Agri. – Horti. Interventions)

Capsicum

Strawberry

(Nandan falodyan) Lemon

Garadu

Lemon

Pomegranate

Tomato

Chili

Page 40: Convergence in MGNREGS

MGNREGS – ACHIEVEMENT (Impact on Livestock and Dairy Farming)

811

1225

0

200

400

600

800

1000

1200

1400

2006-07 2012-13

525

1115

0

200

400

600

800

1000

1200

2006-07 2012-13

Perday (in

ltrs)Per Year

Total Income

705 257325 51.46L

Increase in milk producetion (ltr/day)

Increase in livestock

Page 41: Convergence in MGNREGS

• 9KM Road for connectivity of majras with main road.

• Marketing accessibility of Agriculture Produces to metro cities, Rajasthan, Gujrat, M.P. etc.

• Connectivity helped in declaration of Nirmal gram panchayat and increase of institution deliveries resulting in less mother child Mortality rate.

DagarPada Road

Imlipada Road

MGNREGS - ACHIEVEMENTCONNECTIVITY

Page 42: Convergence in MGNREGS