copyright © 2009 t.l. martin & associates inc. chapter 6 practical methods to reveal cpm covert...
TRANSCRIPT
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Chapter 6Chapter 6Practical Methods to Practical Methods to Reveal CPM Covert Reveal CPM Covert
ActivitiesActivities
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
A. Schedule comparison A. Schedule comparison softwaresoftware
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Schedule comparison softwareSchedule comparison software
• The comparison software notes changes between updates or between an update and the baseline schedule.
• One such system, which compares Primavera CPM schedules, is called “Primaplan Project Investigator.”
• Another system that compares Primavera schedules is called “Claim Digger.”
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Schedule comparison softwareSchedule comparison software• These systems note the differences between the two
compared schedules. – Activities added and deleted, – revised activity durations, – start and finish dates, – calendars, constraints, – changes in float, – changes in critical paths, – resources, – quantities, and – changes in relationships.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
B. Physical versus B. Physical versus metaphysical metaphysical dependenciesdependencies
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Physical versus metaphysical Physical versus metaphysical dependenciesdependencies
• Physical relationships are those which are required based on the nature of the work. – A footing must be excavated prior to concrete
placement, formwork must be completed to a certain extent prior to rebar placement, rebar must be completed to a joint prior to concrete
• Contractor sequence preference sometimes is just mere metaphysical dependency. – Logic between activities becomes that of abstract
and speculative reasoning.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Physical versus metaphysical Physical versus metaphysical dependenciesdependencies
• Very good examples of metaphysical relationships occur within industrial plant projects, which are more controlled by labor resources than by physical dependencies. (With thousands of feet of pipe work to be installed, work location timing is scheduled primarily by preference not due to physical dependencies.)
• In this case the critical path goes through resources and the sequencing of activities, for the most part, becomes physically unrestricted.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Physical versus metaphysical Physical versus metaphysical dependenciesdependencies
• The productive work can be performed out-of-sequence requiring the next schedule update to include the revised logic.
• Since the change affected non-physical activity dependencies, the update should indicate that the revised logic did not delay project completion, since the critical path is driven by resource use which was simply shifted to a new location.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Physical versus metaphysical Physical versus metaphysical dependenciesdependencies
• However, if the contractor does not have sufficient resources during the period, the project will be critically delayed.
• The contractor will argue that the directed change stopped work on the critical path, and thus it is entitled to a compensable time extension.
• Depending on the wording of the project contract, the contractor may be correct.
• One of the owner’s defenses is that the contractor has a duty to mitigate delay and damages by, among other things, re-sequencing work.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Physical versus metaphysical Physical versus metaphysical dependenciesdependencies
• A CPM schedule, if it is to be a viable tool to determine delay cause and resulting damage, must include work quantities and key resources.
• Otherwise, the CPM schedule becomes a meaningless magic trick, producing wildly conflicting results depending which side produces it, to the bewilderment of the audience.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
C. Standard delay C. Standard delay evaluation techniquesevaluation techniques
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniquestechniques
• Delay may result from contractor responsible issues, subcontractor failure to perform and/or supplier problems.
• Generally, the contractor is not entitled to time for its causes of delay and, if critical, may have to accelerate the work at its own cost to ensure timely completion.
• These delays are inexcusable and non-compensable.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniquestechniques
• Delay can also result from “neutral events” or from causes outside the control of both the contractor and the owner.
• Delays associated with extraordinary weather and “Acts of God” fall under this category.
• Under most contracts, this type of delay entitles the contractor to an extension of time but no compensation.
• This type of delay is considered excusable but non-compensable.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniquestechniques
• The third group of delays fall under the responsibility of the owner and is defined by the contract.
• Generally, owner directed changes, differing site conditions, owner furnished materials and/or equipment, owner responsible approvals and designs, are a few of the areas an owner may cause delay that would result in a compensable time extension for a contractor.
• The owner responsible delay is considered excusable and compensable.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniquestechniques
• Only excusable delays that fall along the projects CPM critical path or paths are to be considered with respect to contract time extensions.
• A CPM schedule is a dynamic tool, as a project progresses and the schedule is updated, the critical path or paths shift.
• A delay to a prior update path may use all available float plus require additional time, thus shifting the critical path through the delay event.
• Additionally, actual and potential re-sequencing of work activities mitigating delay events should be analyzed.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation
techniquestechniques “As-planned vs. As-built”“As-planned vs. As-built”
• The first delay analysis method compares the original baseline or as planned schedule with the completed as built schedule.
• Delay events and delay mitigation are determined supported by contemporaneous project documents (daily reports, meeting minutes, memos, letters, etc.)
• The credibility of the analysis rests in the accuracy of the as planned and as built schedules and the extent to which delay can be tied to project factual events.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “But For”“But For”
• The second approach is called the “But For” or collapsing method.
• An as built schedule is developed including all known delay events, regardless of contractual responsibility.
• Owner causes of delay are removed, leaving contractor and non-compensable neutral delay events.
• The difference between the actual completion date including owner, contractor and neutral delay and the forecast completion without owner impacts, represents the period of compensable delay.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “But For”“But For”
• The next step is to remove owner and neutral delay events from the as built schedule.
• The difference between the actual completion date including owner, contractor and neutral delay and the forecast completion without owner and neutral impacts represents the period of inexcusable delay.
• The difference between the completion dates computed based on contractor delay alone and the original contract completion represents the period the contractor may be subject to liquidated damages.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “Window”“Window” analysis analysis
• The third delay determination technique is called a “Snapshot” or “Window” analysis.
• This approach generally starts with a reasonable as planned schedule or baseline and at selected points in time, chronologically includes delay events.
• Once a time impact is identified and founded upon contemporaneous project documents, the original baseline schedule is revised incorporating the delay. This revised schedule is then used as the basis for adjustment with the next identified delay.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “Window”“Window” analysis analysis
• This sequential approach is followed consecutively through the life of the project by identifying a delay event and then revising the previously adjusted schedule, until all impacts are incorporated into the schedule.
• If this approach is chosen, contractor and owner delay mitigation efforts such as activity re-sequencing, reduction in critical activity durations and/or deletion of work tasks, must also be included timely into the various “Windows.”
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “Window”“Window” analysis analysis
• This approach can be used during performance to demonstrate delay. A subnet or fragnet is the best way to demonstrate a delay.
• A subnet or fragnet is a sequence of new activities and/or network revisions that are proposed to be added to the existing schedule to illustrate (graphically and mathematically) the method for incorporating changed work that may result in project delay.
• Owners should also prepare independent Time Impact Analyses (“TIA”) using fragnets inserted into the CPM.
– Discuss, negotiate, and timely resolve the question of impact at the earliest opportunity.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “Window”“Window” analysis - How analysis - How
– Determine which activity or activities on the project schedule were affected by the changed work and/or by the delay.
– Review and determine the event timing and duration of all affected activities.
– From the project record keeping systems and key staff, determine impacted activity status.
– Prepare a fragnet analysis showing the sequence of activities necessary to perform the work required, and/or identifying the effects of the delay.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniques techniques “Window”“Window” analysis – How analysis – How
Example 1Example 1• On February 10, two weeks after the project began,
the project was halted due to a strike. • At the time of the strike, the general contractor was on
schedule and in the process of clearing and grubbing the job site.
• Accordingly, on February 14, the contractor wrote the owner and requested a three (3) day time extension.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Time Extension Analysis - Time Extension Analysis - Example 1Example 1
Clear & Grub SiteStart Excavation for
BuildingComplete Excavation for
Building
Start Building Footings
StartA27 JAN
Finish10 FEB
302301 303
304
Start11 FEB
As-Planned
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Example #1Example #1
Clear & Grub Site
Start Excavation for Building
Complete Excavation forBuilding
Start Building Footings
StartA27 JAN
FinishA12 FEB
302
301
303
304
StartA13 FEB
As-Built
Strike Delay(3 Day Delay)
StartA10 FEB
FinishA12 FEB
TIA01
MF 12 FEB
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Time Extension Analysis - Time Extension Analysis - Example 2Example 2
• Shortly thereafter and during the construction of the building foundation, a field directive was issued by the owner at the start of work on February 19, instructing the contractor to change the fill requirements.
• On March 31 the contractor wrote the owner and requested a seven (7) day time extension.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Time Extension Analysis - Time Extension Analysis - Example 2Example 2
2/21
Res
tart
Bui
ldin
g Fo
otin
gs
2/19
Cha
nge
Fill
Req
uire
men
ts
302
Start Excavation for Building 304
Start Building FootingsStart
A13 FEBStart
A18 FEB
303
Complete Excavation for Builidng
Start Structural Columns & Walls
Complete Footings
308
306
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Example #2Example #2
2/21
Res
tart
Bui
ldin
g Fo
otin
gs
2/19
Cha
nge
Fill
Req
uire
men
ts
302
Start Excavation for Building
304A
Start Building Footings
StartA13 FEB
StartA18 FEB
TIA02
Changed Fill RequirementsShut Down Fill (2 Day Delay)
304B
Restart Building Footings
303
Complete Excavation for Builidng
StartA19 FEB
FinishA20 FEB
StartA21 FEB
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Time Extension Analysis - Time Extension Analysis - Example 3Example 3
• During the construction of the building structure, a field directive added four columns and a new structural wall. The owner at the start of work on February 26, asked the contractor to determine the impact on completion, if any, for this work, if starting March 1.
• On February 27 the contractor wrote the owner and requested a ten (10) day time extension because of this issue.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Time Extension Analysis - Example 3Time Extension Analysis - Example 3
304B
Restart Building Footing
StartA21 FEB
StartA18 FEB
306
Complete Footings
Install Deck for 1st FloorColumns & Walls Grd Floor
310
FinishA24 FEB
StartA25 FEB
StartA25 FEB
Finish1 MAR
Start2 MAR
As-Planned
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Time Extension Analysis - Example 3Time Extension Analysis - Example 3
Restart Building Footing
Columns & Walls Grnd Floor
Wate on NTP Changed FND Work
Construct New FTG'sInstall New Columns
& Wall
Fab & Deliver NewSteel Columns
Install Deck 1st Floor
StartA21 FEB
FinishA24 FEB
StartA25 FEB
Finish1 MAR
StartA26 FEB
Finish28 FEB
Start1 MAR
Finish5 MAR
Start1 MAR
Finish3 MAR
Start6 MAR
Finish7 MAR
Contractor Claimed 10 Day Delay26 FEB through 7 MAR
Start8 MAR
304B
310
Contractor’s Analysis #3
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Example #3Example #3
304B
Restart Building Footing
StartA21 FEB
TA03A
Wate on NTP ChangedFND Work
Install Deck for 1st Floor
Columns & Walls Grd Floor
FinishA24 FEB
StartA25 FEB
StartA26 FEB
Finish28 FEB
TA03B
Construct New FTGs
TA03D
Install New Columns
TA03C
Fab & Deliver NewSteel Columns
Start1 MAR
Finish5 MAR
Start1 MAR
Finish3 MAR
Start6 MAR
Finish7 MAR
Actual Delay3/2 through3/5 - 4 days
Start6 MAR
Finish1 MAR Owner’s TIA #3
Deck was planned to start 3/2 and due to the new columns is delayed through 3/5. Deck can actually start prior to completion of new columns.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Standard delay evaluation Standard delay evaluation techniquestechniques
• There are certain requirements of a credible delay analysis.– The as planned or baseline schedule must be reasonable
and represent an accurate plan to timely build the project. – Delay issues identified must be founded in the
contemporaneous project record. – The CPM schedule must be updated through the life of the
project reflecting actual performance. – The results of the analysis should pass the “common sense”
test. – The foundation of the alleged delay must be physically real
not developed through imaginary scheduling tricks.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
D. Performance D. Performance MonitoringMonitoring
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
The Schedule Update ProcessThe Schedule Update Process
• Review of the final update package:– Verify accuracy of submitted information.– Run comparison software– Review critical path graphic– Review update narrative– Review submitted database calculation settings– Review resource usage
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Performance Monitoring and Steps to Performance Monitoring and Steps to Maintain a Proper CPMMaintain a Proper CPM
1. Are all required deliverables submitted?
Compare with General Conditions
2. Is the NTP on the correct day?
Schedule Execution Report or Total Float Report
3. Is the contract duration correct
Schedule Execution Report or Total Float Report
4. Is the contract amount correct
Schedule Resource Report
5. How many activities?
Schedule Execution Report
What to Check on Updated Schedule
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Performance Monitoring and Steps to Performance Monitoring and Steps to
Maintain a Proper CPMMaintain a Proper CPM 6. Does the critical path seem reasonable?
Critical Path Bar Chart or Total Float Report
7. Does the cost loading look reasonable?
Cumulative Cost Curve
8. Is there too much float on activities?
Total Float Report
9. How many constraints? Are they reasonable?
Schedule Execution Report
10. How many open ends? Are they reasonable?
Schedule Execution Report
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
11. Is there unusual logic, especially on the critical path?
Time Scaled Logic Diagram
Detailed Predecessor/Successor Report
12. Cost loading?
Independent Cost Analysis
Resources Loading Report
13. Manpower loading?
Independent Manpower Analysis
Performance Monitoring and Steps to Performance Monitoring and Steps to Maintain a Proper CPMMaintain a Proper CPM
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Performance Monitoring and Steps to Performance Monitoring and Steps to
Maintain a Proper CPMMaintain a Proper CPM 14. Are activity durations appropriate
Bar Chart by Area
Resource Loading Report
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Performance Monitoring and Steps to Performance Monitoring and Steps to
Maintain a Proper CPMMaintain a Proper CPM
Within budget and on-time performance are goals.
The simplest means of achieving budget and performance is for each participant in the project execute its duties properly, accept responsibility and to have a good plan for performance of the work, updated and communicated properly among the project team.
Copyright © 2009Copyright © 2009T.L. Martin & Associates Inc.T.L. Martin & Associates Inc.
Please continue with Chapter 7
Example Development of a Critical Path Schedule