Copyright 2012 John Wiley & Sons, Inc.
Chapter 9
Resource Allocation
![Page 2: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/2.jpg)
8-8-22
Critical Path Method—Crashing a Project
Time and costs are interrelatedFaster an activity is completed, more is
the costChange the schedule and you change the
budgetThus many activities can be speeded up
by spending more money
![Page 3: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/3.jpg)
8-8-33
What is Crashing / Crunching?
To speed up, or expedite, a project Of course, the resources to do this must be
available Crunching a project changes the schedule for
all activities This will have an impact on schedules for all the
subcontractors Crunching a project often introduces
unanticipated problems
![Page 4: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/4.jpg)
8-8-44
Activity Slope
Crash Cost Normal Cost
Crash Time Normal TimeSlope
![Page 5: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/5.jpg)
8-8-55
An Example of Two-Time CPM
Table 9-1
![Page 6: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/6.jpg)
8-8-66
Activity Slopes—Cost per Period for Crashing
Table 9-2
![Page 7: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/7.jpg)
8-8-77
Crashing the Project
Figure 9-1a
![Page 8: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/8.jpg)
8-8-88
Seven Day Schedule
Figure 9-1b
![Page 9: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/9.jpg)
8-8-99
Six Day Schedule
Figure 9-1c
![Page 10: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/10.jpg)
8-8-1010
Five Day Schedule
Figure 9-1d
![Page 11: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/11.jpg)
8-8-1111
Four Day Schedule
Figure 9-1e
![Page 12: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/12.jpg)
8-8-1212
Cost-Crash Curve
Figure 9-2
![Page 13: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/13.jpg)
8-8-1313
Fast-Tracking
Fast-tracking is another way to expedite a project– Mostly used for construction projects– Can be used in other projects
Refers to overlapping design and build phases
Increases number of change orders Increase is not that large
![Page 14: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/14.jpg)
8-8-1414
The Resource Allocation Problem
CPM/PERT ignore resource utilization and availability
With external resources, this may not be a problem
It is, however, a concern with internal resources
Schedules need to be evaluated in terms of both time and resources
![Page 15: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/15.jpg)
8-8-1515
Time Use and Resource Use
Time limited: A project must be finished by a certain time
Resource limited: A project must be finished without exceeding some specific level of resource usage
System-constrained: A project has fixed amount of time and resources
![Page 16: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/16.jpg)
8-8-1616
Resource Loading
Resource loading describes the amount of resources an existing schedule requires
Gives an understanding of the demands a project will make of a firm’s resources
![Page 17: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/17.jpg)
8-8-1717
Resource A
Figure 9-6a
![Page 18: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/18.jpg)
8-8-1818
Resource B
Figure 9-6b
![Page 19: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/19.jpg)
8-8-1919
Resource Leveling
Less hands-on management is requiredMay be able to use just-in-time inventory Improves moraleFewer personnel problemsWhen an activity has slack, we can move
that activity to shift its resource usage
![Page 20: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/20.jpg)
8-8-2020
Resource Leveling Continued
May also be possible to alter the sequence of activities to levelize resources
Small projects can be levelized by handSoftware can levelize resources for larger
projectsLarge projects with multiple resources are
complex to levelize
![Page 21: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/21.jpg)
8-8-2121
Constrained Resource Scheduling
Heuristic Approach
An approach, such as a rule of thumb, that yields a good solution that may or may not be optimal
Optimization Approach
An approach, such as linear programming, that yields the one best solution.
![Page 22: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/22.jpg)
8-8-2222
Heuristic Methods
They are the only feasible methods used to attack large projects
While not optimal, the schedules are very good
Take the CPM/PERT schedule as a baseline
![Page 23: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/23.jpg)
8-8-2323
Optimization Methods
Finds the one best solutionUses either linear programming or
enumerationNot all projects can be optimized
![Page 24: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/24.jpg)
8-8-2424
Multi-Project Scheduling and Resource Allocation
Scheduling and resource allocation problems increase with more than one project
The greater the number of projects, the greater the problems
One way is to consider each project as the part of a much larger project
![Page 25: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/25.jpg)
8-8-2525
Multi-Project Scheduling and Resource Allocation Continued
However, different projects have different goals so combining may not make sense
Must also tell us if there are resources to tackle the new projects we are considering
![Page 26: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/26.jpg)
8-8-2626
Standards to Measure Schedule Effectiveness
Schedule slippage Resource utilization In-process inventory
![Page 27: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/27.jpg)
8-8-2727
Schedule Slippage
The time past a project’s due dateSlippage may cause penaltiesDifferent projects will have different
penaltiesExpediting one project can cause others
to slipTaking on a new project can cause
existing projects to slip
![Page 28: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/28.jpg)
8-8-2828
Resource Utilization
The percentage of a resource that is actually used
We want a schedule that smoothes out the dips and peaks of resource utilization
This is especially true of labor, where hiring and firing is expensive
![Page 29: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/29.jpg)
8-8-2929
In-Process Inventory
This is the amount of work waiting to be processed because there is a shortage of some resource
Similar to WIP (work in progress) in manufacturing
Holding cost is incurred
![Page 30: Copyright 2012 John Wiley & Sons, Inc. Chapter 9 Resource Allocation](https://reader036.vdocument.in/reader036/viewer/2022062313/56649f425503460f94c616ee/html5/thumbnails/30.jpg)
8-8-3030
Heuristic Techniques
Multi-projects are too complex for optimization approaches
Many of the heuristics are extensions of the ones used for one project