Copyright Reserved GreenTech Malaysia PROJECT :IGEM 2013 REPORTING PERIOD : NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco products exhibition Size – 500 booths Theme for 2013 – Advancing Green Growth & Global Entrepreneurship Objectives To showcase the latest innovative and creative development of Green Technology and Eco Products To generate commercial opportunities for industry players To encourage partnerships and technology transfer in Green Technology To facilitate the establishment of green standards, certification and legislation Project Fund: RM 4.9 Million Duration: April – Oct 2013 Expected Outcomes RM1.2 Billion of business leads 60,000 visitorship Status Completed.

Upload: winfred-knight

Post on 05-Jan-2016

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Copyright Reserved GreenTech Malaysia PROJECT:IGEM 2013 REPORTING PERIOD: NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco

Copyright Reserved GreenTech Malaysia

PROJECT:IGEM 2013REPORTING PERIOD: NOV 2013

1

Project Brief/Summary• The region’s largest green technology and eco

products exhibition

• Size – 500 booths

• Theme for 2013 – Advancing Green Growth & Global Entrepreneurship

Objectives• To showcase the latest innovative and

creative development of Green Technology and Eco Products

• To generate commercial opportunities for industry players

• To encourage partnerships and technology transfer in Green Technology

• To facilitate the establishment of green

standards, certification and legislation

Project Fund: RM 4.9 Million

Duration: April – Oct 2013

Expected Outcomes

• RM1.2 Billion of business leads

• 60,000 visitorship

Status

• Completed.

Page 2: Copyright Reserved GreenTech Malaysia PROJECT:IGEM 2013 REPORTING PERIOD: NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco

Copyright Reserved GreenTech Malaysia

PROJECT:IGEM 2013REPORTING PERIOD: NOV 2013

2

Activities Completed (During reporting period)• Confirmed booths : 467• Business Opportunity Forum held on 7th Oct at MO. 120 participants.• Islamic Financing Forum held on 8th Oct at KLCC with 220 participants.• MGBC Conference held on 9th Oct at MO with 130 participants.•Itrain IT Conference held on 11th Oct at MO with 250 participants.•Matrade Business Matching held on 10th Oct at MO with 30 meetings. (More details is being compiled)

% completed: 100%

% funds utilised: 100%

Activities Planned (For next reporting period)•Post mortem meeting on 7th November 2013

Page 3: Copyright Reserved GreenTech Malaysia PROJECT:IGEM 2013 REPORTING PERIOD: NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco

Copyright Reserved GreenTech Malaysia

PROJECT:IGEM 2013REPORTING PERIOD: NOV 2013

3

Impacts of the Project in year 2013• 235 million of business leads• 51,852 visitors from 10-13 October 2013.

Photos of activities for the period of reportingLaunching of IGEM2013

Challenges- Contract with Expomal is

still pending.- KLCC booking for 2014 &

2015

Actions

Page 4: Copyright Reserved GreenTech Malaysia PROJECT:IGEM 2013 REPORTING PERIOD: NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco

Copyright Reserved GreenTech Malaysia

PROJECT: KIA 2013REPORTING PERIOD: NOV 2013

4

Project Brief/Summary• The KIA 2013 is organised by the Ministry of Energy, Green Technology & Water,Malaysia (KeTTHA) and co-organised by GreenTech Malaysia, Sustainable Energy Development Authority Malaysia (SEDA), Suruhanjaya Tenaga (ST) and Suruhanjaya Perkhidmatan Air Negara (SPAN), to honour Malaysian-based energy, green technology and water industries players that have contributed to driving the nation’s agenda.

Objectives• Recognize and appreciate the effort

and industry excellence. This will also motivate them to continue to perform excellent service delivery;

• Demonstrate leadership in leading and driving KeTTHA energy industry, green technology and water reserve;

• Strengthening the relationship between the government / industry under KeTTHA, and

• National award winners can also be nominated for an internationalaward events, such as the ASEAN Energy Awards and others.

Project Fund: RM 180,000

Duration: Oct – Nov 2013

Expected Outcomes

• To complete the award night with PM’s presence and to acknowledge 25 winners.

Status

• On going

Page 5: Copyright Reserved GreenTech Malaysia PROJECT:IGEM 2013 REPORTING PERIOD: NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco

Copyright Reserved GreenTech Malaysia

PROJECT: KIA 2013REPORTING PERIOD: NOV 2013

5

Activities Completed (During reporting period)• Event Manager White Wizard has been appointed on 6th November 2013.• Design for invitation card has been approved and sent for printing.• MC Halim Othman has been booked.• Steering Committee to finalise the winners will be held on 7th Nov.• Food tasting is on 7th Nov.

% completed: 30%

% funds utilised: 0%

Activities Planned (For next reporting period)•Updates on the award night which will be held on 21st November.

Page 6: Copyright Reserved GreenTech Malaysia PROJECT:IGEM 2013 REPORTING PERIOD: NOV 2013 1 Project Brief/Summary The region’s largest green technology and eco

Copyright Reserved GreenTech Malaysia

PROJECT:KIA 2013REPORTING PERIOD: NOV 2013

6

Impacts of the Project in year 2013• Industry players in Energy, Water and Green Technology will be recognised.

Photos of activities for the period of reportingLaunching of KIA 2013

Challenges- PM’s confirmation is still

pending.- Budget is very much low,

thus we have to work with a very reasonable setup.

Actions