cornerstone engineering group the foundation for your civil engineering needs camanche reservoir...

24
Cornerstone Engineering Group Cornerstone Engineering Group The Foundation for Your Civil Engineering Needs Camanche Reservoir Water Camanche Reservoir Water Treatment Plant Treatment Plant Project Project Cecilia Zamora Evangelina Reyes Kathryn Garcia Michael Bockrath 04/28/04 Camanche Reservoir South Shore (CASS) Camanche Reservoir North Shore (CANS) Final Design Final Design

Post on 21-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Cornerstone Engineering Cornerstone Engineering GroupGroup

The Foundation for Your Civil Engineering NeedsCamanche Reservoir Water Camanche Reservoir Water Treatment PlantTreatment Plant Project Project

Cecilia Zamora

Evangelina Reyes

Kathryn Garcia

Michael Bockrath

04/28/04

Camanche Reservoir South Shore (CASS)

Camanche Reservoir North Shore (CANS)

Final DesignFinal Design

Overview Project Review

– Overview Approach– Alternatives

Design Features– Membrane Selection Obstacles– Constructability Sustainability– Environmental Impact

Final Design– Final Recommendations Future Requirements– Vendor Selection Costs

Schedule Summary

Project Review Overview

– Single Water Treatment Plant Serving both South Shore and North Shore Supply pipeline through Camanche reservoir to existing North

Shore storage tanks

– Minimum Capacity 0.5 Million Gallons Per Day 100% redundancy

– Expandable to up to 2 Million Gallons Per Day– Water quality regulations

Current and Future

– Reduce O&M cost

Project Review (continued)

Existing

Proposed

Project Review (continued)

Approach– Evaluate Alternatives

No Build Retrofit Existing Plants New Consolidated Plant

– Regulations Existing Future

– Cost Analysis– Calculations & Drawings

Overview Project Review

– Overview Approach– Alternatives

Design Features– Membrane Selection Obstacles– Constructability Sustainability– Environmental Impact

Final Design– Final Recommendations Future Requirements– Vendor Selection Costs

Schedule Summary

Design Features Membrane Selection

– Types of Membranes Micro Filtration Ultra Filtration Nano Filtration Reverse Osmosis

– Ultra Filtration Selected Log credits Budgetary Costs Chemical Byproducts (TTHM)

Design Features (continued)

Obstacles– Obtaining information from vendors

Data Sheets & Technical Information Costs and Pricing System Specifications & Drawings

– Creation of profile from incompatible programs 3D TopoQuads AutoCAD

– Unavailability of topographic data Utilize project drawings from client

Design Features (continued)

Constructability– Pre-fabricated fully assembled system

Skid mounted modules ready for operation Easily expandable up to 2.0 Million Gallons per Day

– Fully-automated controls Remote monitoring limits operator attention Automated chemical dosing for disinfection Cleaning in place

Design Features (continued)

Constructability (continued)

– Operator training provided by Manufacturer Ultraviolet system

– Operation, cleaning, sampling, maintenance

– Building layout Adequate space for system expansion Adequate clearance and spacing for operators

– Performing maintenance and daily procedures

Design Features (continued)

Sustainability– Building

Storage space Office space Laboratory testing space Repair/shop space/work space

– Maintenance Calibration of equipment Building maintenance Annual Water System inspections

Design Features (continued)

Sustainability (continued)

– Chemicals Purchase chemicals as needed

Environmental Impact– Mitigated Negative Impact Statement

No Significant Potential Impacts

Overview Project Review

– Overview Approach– Alternatives

Design Features– Membrane Selection Obstacles– Constructability Sustainability– Environmental Impact

Final Design– Final Recommendations Future Requirements– Vendor Selection Costs

Schedule Summary

Final Design Final Recommendations

– Ultra Filtration Membrane System– Ultraviolet Disinfection

Multiple Barrier

– Supply Lines 10-inch Diameter Pipe from Aqueduct 8-inch Diameter Pipe to Storage Tanks Booster Pump to North Shore Tanks

Future Requirements– Room for Additional Skids– Expansion of Ultraviolet System– Additional pumps to South Shore Tanks

Final Design

Final Design (continued)

Vendor Selection

– Vendor scored 1 to 3 (3 for best 1 for worst)

Attributes WeightNormalized weight Aquasource Zenon Hydranautics

Log credit removal (Giardia, Cryptosporidium, viruses)

Pass or Fail P F P

Particle size removal 0.10 0.26 2 2 2Applied feed pressure 0.09 0.24 3 1 2Number of modules 0.08 0.21 3 1 2Chemical addition 0.05 0.13 2 3 1Recovery 0.03 0.08 3 1 2Vendor relationship 0.01 0.03 3 1 2Backwash duration 0.01 0.03 2 1 3Backwash frequency 0.01 0.03 3 1 2

 Totals 0.38 1.00 2.13 1.94 1.92

Evaluation Criteria Vendor Scores

Final Design (continued)

Costs– Estimated price

Obtained from Aquasource manufacturer 16-module skid, strainer, backwash pump, clean in place

system, and controls.

$1 Million +/- 10%– One year operation and maintenance cost

estimated from MWH costs

$171,000 +/- 25%

Final Design (continued)

Costs– Pipeline cost

including tees, fittings and valves for all connections

$1.1 Million +/- 10%– Pipeline across water

$962,500 +/- 25%

– Ultraviolet System Megatron 250M with digital monitor and automatic wiper

– Excluding Installation, Training and Power required

$28,175

Overview Project Review

– Overview Approach– Alternatives

Design Features– Membrane Selection Obstacles– Constructability Sustainability– Environmental Impact

Final Design– Final Recommendations Future Requirements– Vendor Selection Costs

Schedule Summary

ScheduleSchedule Causes for delay

– Vendor Selection and Participation Costs, Specifications, and drawings

– Difficulties obtaining profile data

Modification– Environmental Impact Checklist– Risk Analysis

ID WBS Task Name Duration

1 1 Camanche resevoir water treatment plant 76 days

2 1.1 Proposal 38 days

3 1.1.1 cover letter 2 days

4 1.1.2 scope of work and objectives 5 days

5 1.1.3 schedule 5 days

6 1.1.4 Preliminary Proposal 0 days

7 1.1.5 Proposal Presentation 0 days

8 1.1.6 Revised Proposal 3 days

9 1.2 Research Phase 48 days

10 1.2.1 Watershed surveying 5 days

14 1.2.2 Camanche Water Facility 6 days

19 1.2.3 Regulations 35 days

25 1.2.4 Environmental assessment 33 days

29 1.2.5 Possible Alternatives 15 days

34 1.2.6 Evaluation of Alternatives 20 days

39 1.2.7 Progress Presentation 0 days

40 1.3 Design Phase 35 days

41 1.3.1 Water Treatment Design 18 days

42 1.3.1.1 Selection of Membrane system selection(based on cost and performance)18 days

43 1.3.2 Drawings 18 days

44 1.3.3 Specifications 35 days

45 1.3.4 Project cost analysis 15 days

46 1.3.5 Risk Analysis 15 days

47 1.3.6 Ethical considerations 5 days

48 1.3.7 Constructability 5 days

49 1.3.8 Sustainability 5 days

50 1.3.9 Final draft ready for evaluation 0 days

51 1.4 Group Meeting 76 days

83 1.5 Website 70 days

84 1.6 Final Presentation 0 days

85 1.7 Final Report 0 days

1/23

2/2

3/10

4/30

Mike

4/28

5/3

Jan 4, '04 Jan 25, '04 Feb 15, '04 Mar 7, '04 Mar 28, '04 Apr 18, '04 May 9, '04

Overview Project Review

– Overview Approach– Alternatives

Design Features– Membrane Selection Obstacles– Constructability Sustainability– Environmental Impact

Final Design– Final Recommendations Future Requirements– Vendor Selection Costs

Schedule Summary

Summary Single Water Treatment Plant

– South Shore Location– Mokelumne Aqueduct water source– Membrane filtration system

Ultra Filtration Modules Ultraviolet Disinfection

AcknowledgementsMentors

Andy Enos – East Bay Municipal Utility District

Dr. Gary Litton – University of the Pacific

 InstructorsDr. David Fletcher – University of the Pacific

Dr. Abel Fernandez – University of the Pacific

Dr. Camilla Saviz – University of the Pacific

OrganizationsMichael Price – Montgomery Watson

Simon Morris – Infilco Degremont, Inc.

Joseph Spano – Department of Health Services

Dave Remick – Department of Health Services

Questions