corps of engineers section 404 individual permit evaluation process july 22, 2005

44
CORPS OF ENGINEERS CORPS OF ENGINEERS SECTION 404 SECTION 404 INDIVIDUAL PERMIT INDIVIDUAL PERMIT EVALUATION PROCESS EVALUATION PROCESS July 22, 2005 July 22, 2005

Upload: susanna-paul

Post on 12-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

CORPS OF ENGINEERSCORPS OF ENGINEERS

SECTION 404SECTION 404

INDIVIDUAL PERMITINDIVIDUAL PERMIT

EVALUATION PROCESSEVALUATION PROCESS

July 22, 2005July 22, 2005

Page 2: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005
Page 3: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005
Page 4: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Typical IP ProcessPre-application

meetings

Application Submitted

Incomplete

Public Notice Issued (15 days)

Public/Agency Comments Received

& EvaluatedApplicant

Coordination

Is Public Hearing

Needed?Applicant Responds

Corps Evaluates Response

Decision TimeNEPA

404(b)(1)Public Interest

Other Legal Requirements

Page 5: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Individual PermitEvaluation Process

• Application Completeness Review• Scope of Analysis• Public Notice• Purpose and Need• Alternatives Assessment• 404(b)(1) Guidelines• Public Hearing• Mitigation• Water Quality Certification• Cultural Resources• Threatened and Endangered Species• Public Interest Evaluation

Page 6: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Complete Application

• Review information submitted

• Within 15 days, determine if complete or request additional information

• Application complete when sufficient information is received to prepare the Public Notice.

Page 7: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Complete Application

• Information needed for complete application– Name & address of applicant/agent– Description of proposed activity– Wetland delineation (if applicable)– Adjacent landowners– Project location– Completed work– Signature of applicant agent– Drawings, plans, sketches

Page 8: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Scope of Analysis

• Determine the Corps Federal action area (permit area)

• Determine how the Corps will evaluate indirect (secondary) adverse environmental effects as well as cumulative effects

Page 9: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Scope of AnalysisPermit Area

• All waters of the United States, as well as any additional area of non-waters where the Corps determines there is adequate federal control and responsibility

• Area of jurisdiction + Areas where impacts are caused by (or “a product of”) the Corps permitted activity

Page 10: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Permit Area FactorsNEPA (App. B)

• Activity “merely a link” in corridor type project

• Nearby upland facility location affects location of permitted activity (& visa versa)

• Extent of entire project in Corps jurisdiction

• Extent of cumulative Federal control and responsibility

Page 11: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Permit Area FactorsNHPA (App. C)

• Upland activity integrally related to permitted activity in waters of United States

• Activity Directly associated with activity in waters of the U.S.

• Project couldn’t occur “but for” a Corps permit

Page 12: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Permit Area

Permit Area for a Simple Road Crossing

• No Federal Involvement Other Than Corps Permit

• No Other Impacts in Waters of U.S.

• Permit Area Limited to Directly-Affected Waters of U.S., and Uplands in

Immediate Vicinity Affecting/Affected by Regulated Activity

(e.g., Adjacent Road Alignments, Clearing for

Staging Area, Equipment Access, etc.)

Page 13: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

5 mi.

Permit Area for Multiple Road Crossings

NWR

• Substantial Federal Control (Corps permit + NWR Land)• Substantial Impacts (Waters of U.S., Endangered Species,

Cultural Resources)• 1 Permit Area

Permit Area

Page 14: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Permit Area in Subdivisions - Case A

• Limited Direct Impacts

• Limited Indirect Impacts

• Limited Federal Control

• No Other Impacts to Waters of U.S.

Permit Area

Page 15: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Permit Area in Subdivisions - Case D

Permit Area

= Historical / Cultural Resource

= T/E Species / Critical Habitat

• Substantial Direct Impacts

• Indirect Impacts Close to Permitted Activities

• Several Activities Require Permits

• Federal Control Over Much of Project

Page 16: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public Notice

• The Public Notice is the primary method of advising all interested parties of a proposed activity for which a permit is sought.

• The Public Notice solicits agency and public comment for input in the decision making process.

Page 17: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public Notice

• The PN must contain:– Statutory Authority– Name and address of the applicant– Location– Project description– Plan and cross-section drawings– Other regulatory authorizations– Statement on endangered species– Statement on cultural resources

Page 18: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public Notice

• (Con’t):– Statement on need for an Environmental

Impact Statement (EIS)– Evaluation factors– Length of comment period (15-30 days)– Statement on public hearing– Additional information to assist reviewer

Page 19: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public Notice

• Public Notices must be distributed to:– Post office in the vicinity of the project– Applicant– Applicable government agencies– Congressional representatives– Adjacent property owners– Specific individuals or organizations– In-house support

Page 20: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Purpose and Need

What’s the applicant What should be done

trying to accomplish to address a problem?

Purpose Need

Page 21: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Purpose and Need Project Purpose

• Fundamental, Essential, or Irreducible purpose of proposed project

• Used to determine if project is water dependent

• Required to be addressed as part of 404(b)(1) analysis and NEPA evaluation

• Examples– to provide housing– to provide sufficient water supply– to increase the capacity of the school system– to provide/improve transportation efficiency

Page 22: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Purpose and Need Project Need

• Required to be addressed during public interest review

• Corps generally defers to state or other government agency’s decision to spend money

• Corps may make independent review of public need

Page 23: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Alternatives AssessmentRegulations

• CEQ NEPA regulations: reasonable alternatives

• Corps NEPA regulations: reasonable alternatives– must be feasible– must accomplish purpose and need– alternatives that are reasonable and feasible need not

necessarily be available to the applicant

• 404(b)(1) Guidelines: practicable alternatives– available and capable of being done taking into

consideration cost, existing technology, and logistics in light of overall project purposes

Page 24: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Alternatives Assessment

Types• No-Build (permit denial)

• On-Site– Avoidance– Minimization– Reconfiguration

• Off-Site– Alternate sites

Page 25: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

SUBPART A - PROCEDURESEPA’s Recommended Sequence

AlternativesAlternativesTechnical

EvaluationsSubparts

C-F

TechnicalEvaluationsSubparts

C-F

Disposal SiteDisposal Site

Minimize Impacts(Subpart H)

Minimize Impacts(Subpart H)

FactualDetermination

FactualDetermination

DocumentCompliance

DocumentCompliance

ReviewSubparts

B & H

ReviewSubparts

B & H

ContaminantDetermination

(Subpart G)

ContaminantDetermination

(Subpart G)

Alternatives Assessment404(b)(1) Analysis

Taken from Procedures section of Subpart A of the Guidelines

Page 26: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

404(b)(1) GuidelinesRebuttal Presumptions

• When discharge doesn’t require siting within special aquatic site to achieve basic purpose (i.e., not "water dependent"), practicable alternatives not involving special aquatic sites are presumed available, unless clearly demonstrated otherwise by the applicant

• Practicable alternatives not involving special aquatic sites are presumed to have less adverse impact on aquatic ecosystem, unless clearly demonstrated otherwise

Page 27: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

404(b)(1) GuidelinesPracticability

• An alternative is practicable if it is available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes. If it is otherwise a practicable alternative, an area not presently owned by the applicant which could reasonably be obtained, utilized, expanded or managed in order to fulfill the basic purpose of the proposed activity may be considered

Page 28: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

404(b)(1) GuidelinesRestrictions

• No discharge of dredged or fill material shall be permitted if there is a practicable alternative to the proposed discharge which would have less adverse impact on the aquatic ecosystem, so long as the alternative does not have other significant adverse environmental consequences.”

Page 29: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public Hearing

• A public proceeding to acquire information or evidence to be considered when evaluating a DA permit

• Requests for hearing come from public notice process

• Option – informal public meeting

Page 30: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public HearingRequirements

• Meeting location in vicinity of project• Public notice at least 30 days before

hearing– Time, place, nature of hearing, legal

authority, availability of documents

• Official transcript• Statements only – not a Q&A session• Incorporate written statements• Comment period after hearing of at least

10 days

Page 31: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Mitigation

• No net loss of wetlands/aquatic resources

• 1990 Mitigation MOA with USEPA– Avoidance, minimization, compensation

• RGL 02-2– Watershed approach, long-term

protection

Page 32: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

MitigationTypes of

Compensation• Methods

– Preservation– Enhancement– Restoration– Creation

• Concepts– Project-specific mitigation– Banking– In-lieu fee

Page 33: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

MitigationPlan Requirements

• Baseline Information• Goals and Objectives• Implementation Plan• Success Criteria• Monitoring• Contingency Plan

Page 34: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Water Quality Certification

• Section 401 of the Clean Water Act

• Certification or Waiver required for permit issuance

• Decision by State agency within 60 days (can extend up to one year)

Page 35: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Cultural Resources

• Section 106 of the NHPA– Federal law

• 36 CFR Part 800– Implementing regulations by ACHP

• Appendix C– Corps regulations– Uses “permit area”

Page 36: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Cultural ResourcesTypes

• Historic structures• Historic properties• Historic districts• Subsurface deposits• Traditional Cultural Properties

Page 37: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Cultural ResourcesCoordination

• Entities– State Historic Preservation Office– Advisory Council on Historic

Preservation– Federally recognized tribes

• Process– Public Notice– Consultation

Page 38: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Cultural ResourcesFindings

• Eligibility Determination– National Register of Historic Places– Made by Keeper– Listed in or eligible for…

• Effect Determination– Made by District Engineer– No effect– No adverse effect– Adverse effect

• Resolution• MOA

Page 39: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Threatened and Endangered Species

• Section 7 of the Endangered Species Act

• Ensure that any Federal action is not likely to jeopardize the continued existence of a T/E species or result in the destruction or adverse modification of critical habitat of the T/E species

Page 40: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

T/E SpeciesCoordination

• Entities– U.S. Fish and Wildlife Service– KDFWR

• Process– Public Notice– Formal Consultation

Page 41: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

T/E SpeciesFindings

• No effect• May affect• Not likely to adversely affect• Jeopardy Opinion• Authorized Take

Page 42: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Public Interest Evaluation

• 20+ factors reviewed– Floodplain– Economics– Aesthetics– Habitat– Cumulative impacts– Weighted according to relevance

• Balancing test/Public interest– Benefits versus detriments– Public and private need– extent and permanence

Page 43: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Decision

• A permit will be issued unless the project is contrary to the public interest

• Compliance with 404(b)(1)/NEPA• Resolution of NHPA/ESA/State issues• Documentation

– SOF/EA/FONSI– ROD/EIS– Denial

Page 44: CORPS OF ENGINEERS SECTION 404 INDIVIDUAL PERMIT EVALUATION PROCESS July 22, 2005

Questions?

James M. TownsendChief, Regulatory Branch

Louisville DistrictP.O. Box 59

Louisville, KY 40201-0059502-315-6675