cost control process for construction
TRANSCRIPT
i
Helwan University
Faculty of Engineer matarya
Civil Department
Cost Control Process for Construction Projects
Dissertation Research in Partial Fulfillment of the Requirements for the Degree of master
Prepared By
Yasser M. Abouzeid
Supervision by
Prof. Dr. Adel El-Samadony
Prof. Dr. Randa kamel
ii
ACKNOWLEDGMENTS
First and foremost, I would like to extend my heartiest gratitude to Prof. Dr. Adel El‐Samadony, as my supervisor during obtain M.SC degree. He
gave me the chance to finish the study and with his guidance, the study can finish smoothly. Besides that, his patience and encouragement leads me to complete this study in time.
In addition, I would like to thank Eng. Amr Dawood, as the representative from the staff in Rowad modern Engineer (RME) for their kindly advised and assistance in giving the information to complete this study.
Not forgetting to present this research to spirit of my father. Mother, brothers and sister, for their full support and coaching throughout this research.
Lastly but not the least, to all my friends for their support, advise and their help when the time I need them.
iii
ABSTRACT
With the competition in the construction market is fierce increasingly, profit margin of construction enterprises is getting smaller and smaller, and cost control of construction projects become more and more important. The control of construction project cost becomes one of the cores in project management.
Construction project management is a systematic, comprehensive, dynamic subject, requiring construction project manager to regularize and standardize the organization, goal, quality, safety, and cost of construction project. In order to achieve the project cost control effectively and create greater economic benefits. A study is carried out to study the cost control method in a constructions project, to identify the cost control process method frequently used by contractors in controlling the cost of projects.
From the study, the main problem faced by contractors are shortage of material, Labor costing more than estimated, difficulty in collection of cost data, ever-changing environment of construction work ,qualified expertise ,duration of project and additional costs to carry out the cost control.
iv
INTRODUCTION
The cost control is a process that should be continued through the construction period to ensure that the cost of the project is kept within the agreed cost limits. The cost control can divide into two major areas; the control of cost during design stages and the control of cost by the contractors once the constructions of project have started.
Cost control of a project involves the measuring and collecting the cost record of a project and the work progress. It also involves the comparison of actual progress with planning. The main objective of cost control of a project is to gain the maximum profit within the designated period and satisfactory quality of work
Purpose: Due to the ever increasing competition and current climate in the construction industry, this has lead construction companies to become more competitive in their projects. The aim of this research was to highlight the importance of proper monitoring construction and examine what cost control Process that is in place. This will help all staff realise the importance of monitoring constructions and cost control system by suggesting recommendations to implement in future projects.
Objectives: The objective for this research is:
1- To study cost control Process in a construction project. 2- To identify the cost control method frequently used by contractor
during the construction stage. 3- To identify the main problem faced by contractor in controlling the
cost on site.
Methodology: A comprehensive review was under taken to get a better understanding of cost control system knowledge transfer. For the current research a case study was conducted on medium scale contractors by means of semi- structured interview and questionnaire to look at how their cost control system we monitored and any recommendation for improvement the research will illustrate the basic process used in cost control of construction project, in each process we explain the basic information need to this process and who is responsible to do this process and the form need to do the process (spreadsheets controls).
v
CONTENTS
Title Page Number
INTRODUCTION iv
1 State of Art 1.1 Project Cost Control 1
1.1.1 Purposes of Project Evaluation 1 1.1.2 Cost Control Definition 2
1.2 Important Questions 3 1.2.1 Why we need Cost Management? 3 1.2.2 What the Project Manager Controls? 3 1.2.3 Who Needs Cost Management? 5
1.3 Project Life Cycle and Project Cost 5
1.4 Characteristics of a Project Control System 7 1.4.1 Elements of A Planning And Control System 8
2 Proposed approach to construct model of cost control
2.1 What Information do you need to construct the model?
10
2.1.1 Estimating/Budgeting 10
2.1.2 Work Breakdown Structure (WBS) 33 2.1.2.1 Types of Work Breakdown Structures 36 2.1.2.2 Work Breakdown Structure Development 39
2.1.3 Cost Codes 41
2.1.4 Depreciation 44
2.2 Construct model template –Excel-Format 47 2.2.1 WBS template sheet 47
2.2.1.1 WBS sheet template Consist 47 2.2.1.2 WBS sheet template Form 49
2.2.2 Expenses template sheet 50
2.2.2.1 Expenses template sheet Consist 50
2.2.2.2 Expenses template sheet Form 51
2.2.3 Storage template sheet 53
2.2.3.1 Storage template sheet Consist 53 2.2.3.2 Storage template sheet Form 54
vi
3 the application steps & methods 3.1 Collect Actual Cost data 55
3.1.1 Sources of information 55
3.1.2 Data Required From Procurement Department 59
3.1.3 Data Required From Storages 63
3.1.4 Data Required From Projects 68
3.1.5 Data Required From Finance Department 83
3.2 Actual Cost Allocations 85 3.2.1 WBS Sheet template form 85
3.2.1.1 Client Invoices 86 3.2.1.2 Variations Order 87
3.2.2 Expenses Sheet template form 88
3.2.3 Finance Report 90 3.2.4 Storage sheet template form 91
3.2.4.1 Storage Report 92
3.3 How do you make sure you are getting good information?
93
4
Techniques of outputs & reports
4.1 The Earned Value Measurement System (EVMS) 96
4.1.1 Variance and Earned Value 98
4.1.2 Methods for Physical Progressing 100
4.1.3 Example – Synthetic EVA 104
4.2 Reporting Techniques 108
4.2.1 Report Content 108
4.2.2 Reporting Considerations 109
4.2.3 Sample Reports 110 4.2.4 Responses on Reports 125
4.3 Construction Cost Control Software 126
4.3.1 Advantages of Used Software in Construction Cost Control
127
4.3.2 The Disadvantages of Used Software in Construction Cost Control
130
5 Conclusions 5.1 Common Causes of Cost Control Problems 131
5.2 Keys to Effective Project Cost Control 134
References
144
vii
List of Table
Table number
Title Page number
2.1 Calculating the Estimate 21 2.2 Subcontractor /vendor list 23 2.3 Estimate summary for Office Building 24 2.4 General Overhead 25 2.5 Straight Line Depreciation 45 2.6 Sum of the Years’ Digits 46 2.7 Double Declining Balances 47 2.8 WBS sheet forms 49 2.9 Direct Expenses sheet forms 51 2.10 indirect Expenses sheet forms 52 2.11 Storage sheet forms 54 3.1 Time Cards 57 3.2 Log of material imported 60 3.3 Quotations Comparison Sheet 61 3.4 Recommended Subcontractors for Quotations list 62 3.5 Monthly Report about store movement 65 3.6 Monthly Report about material distributions 66 3.7 Monthly Report about material distributions and
location 67
3.8 Daily man power for Sub contractor 70 3.9 Daily man power for self performed time card 71 3.10 Weekly man power for self performed time card 71 3.11 Subcontractor productivity by location 72
3.12 man power daily production report 73 3.13 man power estimation & actual quantity 73 3.14 man power distribution by work package 74 3.15 Monthly Status log for manpower 75 3.16 Daily Equipment time card 76 3.17 Equipment distribution by work package 77 3.18 Monthly Status log for Equipment 78 3.19 Value of rent Equipment by work package 79 3.20 log for Concrete Casting 80 3.21 Report about Performance by activity 81 3.22 Monitor Report for Finishing item (masonry) 81 3.23 Cost report include labor, Equipment and material 82 3.24 Monthly Report for Finance department 83
viii
3.25 WBS Sheet Form 85 3.26 Sample of Client Invoice 86 3.27 Sample of Cover for Variation Order 87 3.28 Sample of Variation Order 87 3.29 Direct Expenses sheet forms 88 3.30 indirect Expenses sheet forms 89 3.31 Finance Report forms 90 3.32 Deduction /Increase Storage Sheet Form 91 3.33 Storage Sheet Form 92 3.34 equate of (client/subcontractor) quantity 93 3.35 Concrete Casting Report 94 3.36 Steel losses Report 95 4.1 Example of Earned value report 107 4.2 Variance analysis Report 113 4.3 Overall Progress Report 114
ix
List of Figure
Figure
number
Title
Page number
1.1 Project Manager Controls 4
1.2 Project Control Cycle 7 1.3
Project Planning and Control System 9
2.1 Types of Estimates 13 2.2 the Estimating Process 15 2.3 the Estimation Build 16 2.4 Cost estimation Process 27 2.5 Forms of Cost Estimate 28 2.6 Forms of Cost Estimate 29 2.7 Forms of Cost Estimate 30 2.8 Forms of Cost Estimate 31 2.9 Forms of Cost Estimate 32 2.10 Diagram of WBS hierarchy 35 2.11 Product-based WBS 36 2.12 Example of OBS 37 2.13 example of a process-oriented WBS 38 2.14 The cost account intersection 43 2.14 Cost Account code breakdown 43 3.1 data flow between Procurement team and other 59 3.2 step of enter material to the project 63 3.3 data flow between Storage team and other
department 64
3.4 data flow between Projects team and other department
69
3.5 data flow between Finance team and other department
83
4.1
Determining the Status
96 4.2 Controlling both project schedule and cost 97 4.3 Earned value formulae 99 4.4 Analysis showing use of 50/50 rule 102 4.5 Cost data contractual 103 4.6 Physical progress versus time expended 103 4.7 Methods for physical progressing 104 4.8 Representation of Variance on a S- curve 105 4.9 graphical project status 106 4.10 Schedule Performance index 107
x
4.11 Graphical status reports 111 4.12 Data accumulation 111 4.13 Cost control and report flow 112 4.14 Performance Report 112 4.15 Progress Trends Report 113 4.16 Sample cost report 115 4.17 Cumulative cost report 115 4.18 Cumulative cost report 116 4.19 Cumulative cost line graph 117 4.20 Schedule status report 118 4.21 Summary Schedule status report 118 4.22 Weeks Status Performance 118 4.23 millstones Summary report 119 4.24 Sample report instructions 119 4.25 Event report 120 4.26 note on performance report 120 4.27 Critical Issues Report 121 4.28 Traffic signal as indicator of project status 121 4.30 Project Performance metric Definitions 122 4.31 Project Performance report 122 4.32 Sample of other Report 124
xi
LIST OF APPENDIX
APPENDIX
Title Page number
A Cost Control Process Flow Chart 136
B Responsibility Matrix for Cost Control Process 143
Chapter 1 "State of Art"
/91
1-State of Art
1.1-Project Cost Control
1.1.1-Purposes of Project Evaluation Sports teams that practice without reviewing performance may get really good at playing very badly. That is why they review game films to see where they need to improve; there are two kinds of organizations those that are getting better and those that are dying. An organization that stands still is dying. It just doesn’t know it yet. The reason? Your competitors are not sitting by idly. In fact, good project management can give you a real competitive advantage, especially in product development. If you are poor in managing your projects, you don’t have good control of development costs. That means that you have to sell a lot of product or else charge large margins to cover your development costs so that the project is worth doing in the first place. If you can’t sell a lot of widgets, then you have to charge the large margin. In order to learn, people require feedback. Furthermore, people tend to learn more from mistakes than from successes, painful though that may be to admit. If your competitors, on the other hand, have good cost control, they can charge smaller margins and still be sure that they recover their investment and make money. They have a competitive advantage over you because of their better control of project work. In order to learn, people, like the team reviewing game films, require feedback. The last phase of a project should be a final audit so that the management of future projects can be improved. However, such an audit should not be conducted only at the end of the project. Audits should be done at major milestones in the project so that learning can take place as the job progresses. Another reason to do periodic audits is that, if a project is getting into serious trouble, the audit should tell the difficulty so that a decision can be made whether to continue or to terminate the work. Periodic audits should enable you to:
• Improve project performance together with the management of the Project.
• Ensure that quality of project work does not take a back seat to
schedule and cost concerns.
• Reveal developing problems early so that action can be taken to deal with them.
1/144
Chapter 1 "State of Art"
/92
• Identify areas where other projects (current or future) should be managed differently.
• Keep client(s) informed of project status. This can also help ensure
that the completed project will meet the needs of the client.
1.1.2-COST CONTROL Definition Cost control is the process of comparing actual expenditures to the baseline cost plans to determine variances, evaluate possible alternatives, and take appropriate action. To effectively control costs, be sure cost plans are prepared with sufficient detail.
2/144
Chapter 1 "State of Art"
/93
1.2- Important Questions
1.2.1-Why We Need Cost Management? The project manager is primarily concerned with the direct cost of the project, but the trend in project management is that the role of the project manager in cost control will increase to include more of the nontraditional areas of cost control. In the future it will be expected that more project managers will have a great deal of input into the indirect costs and expenses of the project. Regardless of what the project manager is or is not responsible for, it is critical that the project be measured against what the project manager is responsible for and nothing else. If the project manager does not have responsibility for the material cost of the project, then it makes no sense for the project manager to be measured against this metric. Timing of the collection of cost information is also important to the cost measurement system. The project budgets must be synchronized with the collection of the project’s actual cost. For example, if a project team is responsible for material cost, should the budget show the expenditure when the commitment by the project team to buy the product is made, when the item is delivered, when it is accepted, or when it is paid for? Timing issues like these can make project cost control a nightmare. If the project team does not properly control cost, the project will invariably go out of control, and more money will be spent
1.2.2-What the Project Manager Controls? The project manager has to measure many things during the course of a project, and he or she must take actions to guarantee that control (see Figure 1.1). The project manager must.
• Measure and review the project schedule progress against the plan
• Measure and review the project cost progress against the plan
• Measure and review project quality
• Anticipate possible changes and alternatives
• Manage issues and risks
• Control scope creeps through a change management process
• Ensure that delivery of milestones takes place according to client expectations
• Coordinate the project team
• Monitor physical resources by controlling the scheduling of resources during the project
3/144
Chapter 1 "State of Art"
/95
1.2.3-Who Needs Cost Management? In every firm, cost management will exist in some form, usually under the control of the finance function. Our problem as project managers is that often that form is not consistent with the project management function, and that the cost data cannot be integrated with the other project data. As a result, many of the critical management questions concerning cost go unanswered. For instance, if the monthly accounting report notes that Omega Project has accumulated costs of $123,999, is this good or bad? Without integrating the accounting data with the other project data, much of the data is worthless. How do we go about answering such common questions as?
• How much are you going to spend?
• How much did you spend? Is this good or bad?
• How much will you have spent when the project is over? Is this good or bad?
• If I’m in trouble on costs, what can I do to turn things around?
• How shall the costs be distributed?
• How can I control my resource costs?
Effective cost management must address such questions. This requires an integrated schedule and budget plan. It also requires integrated participation by leaders of the projects, resources, and financial disciplines.
1.3-Project Life Cycle and Project Cost
Construction is a dynamic process, and no two projects are ever alike. Even if you have years of experience, every job presents a new set of circumstances and challenges no matter how good a job you do preparing during the pre-construction stage. The project manager and superintendent work together to come up with the best plan they can, trying to anticipate every obstruction and difficulty that might delay progress and put at risk the successful completion of the project, but they still can’t foresee every contingency. Even with this entire expert planning, the project must be monitored from beginning to end to ensure that all of the targets for time, cost, and quality are met. The whole process must be properly managed through a project control system that utilizes the plans, specs, estimate, and schedule. All of these documents taken together establish the road map for getting from the start of construction to the final completion of the project. Using this road map, the project manager and superintendent must maneuver all of the resources in the right direction, making
5/144
Chapter 1 "State of Art"
/96
adjustments as they go, to keep the project on track and on target. Project control requires continuous monitoring and evaluation of actual performance relative to the estimated performance for all aspects of the job that have an impact on cost, time, and quality. The project control cycle begins with the project plan and ends with the final project debriefing and evaluation. There are seven fundamental steps to the process:
• Develop the project plan.
• Establish the project benchmarks.
• Monitor the project performance.
• Identify performance deviations.
• Evaluate corrective options.
• Make adjustments as needed.
• Document, report, and evaluate results. (see Figure 1.2) It is important to track every aspect of project performance all the way back to the planning stage. This is where every project begins, and it is where every project should end with a complete debriefing and evaluation of what worked and what didn’t work. It is also a time to resolve actual costs and labor productivity information to update existing company records in preparation for the next cycle of project planning and estimating. It is an excellent opportunity to capture lessons learned and to create some best practices for future implementation. Unfortunately, many construction teams fail to complete the last step in the cycle and never properly assess their project’s overall performance. Everyone is usually worried to move on to the next project, and it’s very tough to get all of the parties together for even a couple of hours at the end of the job. It takes a great deal of discipline to consistently take advantage of this opportunity and learn from it. In my experience, I have found the project debriefing to be one of the most effective training mechanisms for every member of the team, from the project engineer to the project manager.
6/144
Cha
1.4
All The
1. Tes
pter 1
4 Chara
good projeese include
A focusThe controensure thasystem sho
• What is
• What a
• Which a
• What abe placed
acteris
ect controe:
s on what ol system mat the projould be de
s importan
re we atte
aspects of
re the critd?
stics of
ol systems
is importamust focuect missioesigned wi
nt to the o
empting to
f the work
tical points
/97
f a Pro
have seve
ant. s on proje
on is achieith these q
organizatio
o do?
are most
s in the pr
oject Co
eral chara
ect objectivved. To doquestions
on?
important
rocess at w
"S
ontrol
cteristics
ves. The ao that, thein mind:
t to track
which cont
State of A
Syste
in commo
aim is to e control
and contro
trols shoul
Art"
m
n.
ol?
ld
7/144
Chapter 1 "State of Art"
/98
2. A system for taking corrective action.
A control system should focus on response. If control data do not result in action, then the system is ineffective. That is, a control system must use deviation data to initiate corrective action; otherwise, it is simply a monitoring system, not a control system.
3. An emphasis on timely responses. The response to control data must be timely. If action occurs too late, it will be ineffective. This is frequently a serious problem. Data on project status are sometimes delayed by four to six weeks, making it useless for taking corrective action. Ideally, information on project status should be available on a real-time basis. In most cases, however, that is not possible. For many projects, weekly status reports are adequate. Ultimately, you want to find out how many hours people actually work on your project and compare that figure to what was planned. This means that you want accurate data. Some people may fill out weekly time reports without having kept track of their daily working times. since most of us cannot remember with any accuracy what we did a week ago. When people fill out time reports each week without having written down what they did daily, they are writing fiction. Such made-up data are almost worse than none at all. As difficult as it may be, you need to get people to record their working times daily so that the data will mean something when you collect them. What’s in it for the workers? Perhaps nothing. However, their better estimates (made as a result of collecting accurate information on this project) will help everyone who works on the next project. In any case, you need accurate data, or it isn’t worth the effort at all. When information collection is delayed for too long, the manager may wind up making things worse instead of better
1.4.1-Elements of Planning and Control System Figure 1-3 shows a generic model for a project planning and control system that allows a project to react to the changing conditions of the world.
• Define the problem or opportunity. The first phase of project planning is to clearly define the problem to be solved by the project or the opportunity of which the project will take advantage. This includes understanding the business reasons for the project and the client’s motive in requesting it.
8/144
Cha
• E Oncis tsco
• D Witdevreq
• B WhPer
• M As infodevact
• C
pter 1
Establish p
ce you havo define th
ope.
Develop th
thin the fraveloped, inuired to coBegin proj
hen all plarsonnel, pr
Monitor.
project wormation aviations froion should
Close proje
project obj
ve clearly he basic o
he plan.
amework oncluding thomplete thect work.
ns are in roject wor
work progreand compaom the plad be taken
ect.
jectives.
identified bjectives
of the projhe activitiehe project
place, appk can beg
esses, theare it to than are the.
/99
the probleof the proj
ject objectes, schedut work.
proved, anin.
e project mhe plan to n analyzed
em or oppject in ter
tives, detaules, cost p
nd commun
manager gdetermined to deter
"S
portunity, trms of time
ailed plansplans, and
nicated to
ather state variancemine if co
State of A
the next se, cost, an
s are d resources
project
us s. These rrective
Art"
step nd
s
9/144
Chapter 2 " Proposed approach to construct model of cost control "
2- Proposed approach to
construct model of cost control
Chapter 2 "Proposed approach to construct model of cost control"
/451
2-Proposed approach to construct model of cost control
2.1-What Information do you need to construct the model?
So exactly what kind of information should you be gathering to create your system of control which will maintain control of your Project? Below are listed the specific pieces of information you should be requesting
2.1.1-Estimating/Budgeting
What Is an Estimate? An estimate is an educated guess. We are all familiar with estimates. We have obtained estimates for work on our car, for getting our house painted, or for closing costs on a mortgage. And most of us have actually engaged in doing an estimate. We’ve guessed or estimated or calculated how many gallons of paint we needed to paint the living room. The main differences between these simple estimating activities and the estimates used to price construction are the complexity and what’s at stake. When you estimate how many gallons of paint are needed to paint your living room and you are off by a gallon or two, the stakes are pretty small. But when you estimate the cost to build a nuclear plant or a super highway or a hospital or even a house, the stakes are much, much higher. The estimate is a summary, based on the best information available, of probable quantities and costs of materials, labor, equipment, and subcontracts to complete a project, including taxes, overhead, and profit. It is the number used to develop the project bid price. The bid price is what goes in the contract, and the contract obligates you to perform all work needed to complete the project in accordance with the plans and specifications. The consequences of any errors or omissions in the estimate are borne by the contractor, and the contractor will not actually know what the true cost of the construction is until the project is complete. If the estimated cost is equal to or greater than the actual cost, the project makes money for the contractor. If the estimated cost is less than the actual cost, the contractor loses money on the project. As you can see, estimators have an awesome responsibility. First, they must come up with an accurate but competitive estimate that will win the job. Second, their planning and calculations set the stage for the overall management targets for the entire project. Once the estimator turns the project over to the project manager and the on-site team, the estimator shifts to a support role and really has no direct management duties
10/144
Cha
assa joIt isTherisk
Types
The amoestimateestimateestimate(2-1).
Conno in twhespe
pter 2
sociated wob and subs a high-ste construck to a succ
of Esti
ount of infoe that can es are not e. But som
1. Concenceptual edrawings the idea orether theirending mo
"Propo
ith the daybmit a bidtakes gamtion manacessful out
mates
ormation a be prepar equal the
metimes ow
eptual Eestimates aavailable ar concept sr idea is eney on de
osed appr
y-to-day o, they are
mble, and magement tetcome.
available rred. Howev less inforwners don’
Estimateare often cat all. Youstage of aconomical
esign until
roach to c
/452
operations taking a rmany facteam is on
regarding ver, you mmation av’t need a h
es called ballp can use c project. Oly feasible they know
construct
s. Every timrisk. ors may in the front
the projecmust keep vailable, thhigh level
park estimconceptuaOften an oe, and theyw that the
model of
me contra
nfluence thlines of m
ct will dicta in mind th
he less accof accurac
mates. Typl estimate
owner doesy don’t wa project is
f cost con
ctors estim
he outcommanaging t
ate the tyhat all curate the cy see Fig
pically theres when yosn’t really ant to stars at least
ntrol"
mate
me. his
pe of
ure
re are ou are know
rt
11/144
Chapter 2 "Proposed approach to construct model of cost control"
/453
possible. An experienced estimator can help out in a situation like this by offering a rough order of magnitude (ROM) estimate. These estimates are based upon a cost per primary unit for the facility. For example, for hospitals, the primary unit of measure would be beds, and you would multiply the proposed number of beds by the appropriate unit cost. For a school, the calculation would be cost per pupil; for a highway, the estimate would be based on a cost per mile. Once the owner suggests how many primary units they would like to build, an estimator can whip out a rough order of magnitude estimate within minutes; however, the accuracy is limited.
2. Preliminary Estimates If you have a preliminary set of drawings with overall dimensions, you can move to the next level of estimating. Preliminary estimates provide a somewhat higher level of accuracy and may be used to establish initial budgets and preliminary financing scenarios. However, these estimates should never be used to commit to a contract price because too many factors can influence the reliability of the numbers. Although there are numerous preliminary estimate methodologies, the most common is probably the square foot method. In its simplest form, the estimator calculates the area of the floor plan and multiplies that number by a unit price. There are various levels of skill and detail that can be applied to the square foot estimating method, and the degree of accuracy increases with each step up, as will the time it takes to calculate the price.
3. Detailed Estimates Whenever you have a complete set of plans and specs, you should do a detailed estimate. This is where you count every brick and stick, so to speak. Quantities and costs are calculated for every aspect of the project, and this is by far the most reliable estimate if the contractor is being asked to give a firm bid on a project. Detailed estimates are the most accurate. But keep in mind that as the accuracy increases, so does the time, effort, and skill required to complete the estimate. Although computerized estimating has reduced the time needed to compile project costs, it can still take two to three weeks and a team of estimators to put together a detailed estimate for a large, multistory commercial building such as an office or retail complex. The estimators still have to put the bid packages together and spend time soliciting subcontractor and vendor pricing. Throughout the rest of this chapter, I will be talking about detailed estimates.
12/144
Cha
The Acccongrecon
Thetheestbe look
Get Althof ateasubbas Than teadoi
pter 2
Estima
curacy andnstruction eater than nstruction
• How m• How m• How lo
ese three c managemimate setsused throuk at what
tting Sthough an ean estimatm. Fellow
bcontractose when tr
e team woedge in thm becomeng the foll
"Propo
ating Pr
d completeestimate. or equal testimate,
many (quanmuch (priciong (produ
componenment targes the paraughout theit actually
tarted estimator te improve estimatorrs, materi
rying to m
orks togethe bidding es completlowing:
osed appr
rocess
eness are The ultimto the actu you are c
ntities) ing) uctivity)
nts make uets for the meters fore construc
y takes to
can work es when thrs, projectal supplieake decisi
ther to dev process. Itely famili
Figure
roach to c
/454
the fundaate goal is
ual cost ofoncerned
up the con project ter the projection proceput an est
alone in dhere is inpt managerrs, and othons during
velop a unIn preparaar with th
2-1 Types
construct
mental obs to have tf the projewith three
struction eeam. You wect budgetess to montimate tog
developingput from ots, superinhers can ag the estim
ique stratation for the requirem
s of Estim
model of
bjectives othe estimact. When e things:
estimate awill discovt and schenitor succegether see
g an estimther memtendents,
all add to tmating pha
egy that mhe estimatments of th
ates
f cost con
f the ated cost byou do a
and establver that thedule and wess. Now l Figure (2
ate, the qbers of the the resourase.
might provting task, he project
ntrol"
be
ish e will et’s -2).
uality e
rce
vide the
t by
13/144
Chapter 2 "Proposed approach to construct model of cost control"
/455
1. thoroughly reviewing the plans and specs 2. developing a list of questions and needed clarifications 3. attending the pre bid meeting 4. visiting the project site
1. Reviewing the Plans and Specs
It is important to get a “big picture” perspective of the project before you get into the details of the work. Having an overall understanding of the difficulty of the construction will assist the estimator when making judgment calls that inevitably affect the accuracy of the estimate. Ideally, the plans and specs are reviewed in detail before any estimating takes place. Among the first things to look for when making the initial review are any special conditions, clauses, or criteria that could adversely affect the project schedule or cause unusual risks to be taken. Such items should be highlighted during this process and red flagged for the project team when the job is passed from the estimator to the project manager. Remember the earlier example regarding the imported Italian marble tile. Many of these red flag clauses are found at the front end of the project manual in the instructions to bidders and supplemental conditions. Taken into account during the estimating process.
2. Developing a list of Questions and needed Clarifications In addition to discovering red flag issues, the plan and spec review provides an opportunity for the estimator to uncover details that require clarification or questions about the project that are not addressed in the contract documents. As the estimator thumbs through the drawings, they will prepare a query list in anticipation of the pre bid meeting, site visit, or phone conference with the designer. The designer typically responds to each of the questions in writing. Those responses that result in a change to the original plans and specifications become official addendum to the contract. Checklists are a common tool used to make sure that nothing gets left out or overlooked.
14/144
Cha
Prioprean ansrepsenthethoat t
No areplanof tultimeassmit
Figurestimat
pter 2
3. The Por to biddie bid meetopportunitswered. It presentativnt, simply project atrough revthis meetin
4. The S
one shoul site condns and spethe land, wmately affeting, it is
sociated wtigate thos
e 2-2 the ting Proce
"Propo
Pre bid Mng, it is coing. This mty for the is very imve to this mbecause tt this stag
view of theng, and co
Site Visit
d ever estitions thatecs. Only which will fect your ps your obliith the bidse risks
ess
osed appr
Meeting ommon fomeeting ofbidding co
mportant thmeeting. That is the
ge and whoe plans andontractors
t
timate a jot just cannby walkinghelp you mpricing. Evgation to
d. Visiting
roach to c
/456
r the owneften occurontractors hat each oThe estima person who has deved specs. S who fail t
ob withoutnot be undg around wmake the ven if the smake evethe site is
construct
er and/or rs at the p to get ma
of the biddator is ofteho is the oeloped a q
Some projeto attend a
t first visitderstood bwill you genecessarysite visit isry effort to
s one way
model of
designer troject siteany of theding contraen the repone most fquery list aects requirare not allo
ting the joby merely et a good sy judgments not part o mitigatein which y
f cost con
to conducte and provir questionactors senpresentativfamiliar wiafter a re attendaowed to b
b site. Thelooking atsense of tt calls tha of the pree risks you can
ntrol"
t a ides ns ds a
ve ith
ance id.
ere the he lay t
e bid
15/144
Cha
Est
How Youfacidivi EaconedecconIn tconest
FiguEstim
pter 2
imators sh
• Distan• Site co• Site ac• Soil da• Ground• Securit• Traffic • adjace• possib• Water,• Obstru• Parking• Debris• Local w• Local l
w You Bu build an ility. Geneisions of th
ch CSI divie of the mcide to orgnsistent fothis way, tnsulted forimate see
ure 2-3 thmation Bu
"Propo
hould cons
ce from ofonditions ccess ata dwater ty needs considera
ent structule contam, electricityuctions g and stor disposal weather paabor and s
uild theestimate i
erally, you he 2004 C
ision is broost comm
ganize the rmat, evethe estimar every pro Figure (2
he uild
osed appr
sider the f
ffice
ations ures ination y, and tele
rage
atterns sub trades
e Estimin very mu start from
CSI Master
oken downon ways t estimate,n if some ate outlineoject to m-3).
roach to c
/457
following w
ephone se
s
ate? uch the sam the grour Format o
n into detao organize it is very divisions a
e acts as aake sure t
construct
when visiti
ervice
ame order und up andoutline.
ailed itemse the estim importantare not ap master chthat nothin
model of
ng the site
that you bd work thr
s of work. mate. Howt to stick wpplicable tohecklist thng gets lef
f cost con
e:
build the arough the
This formwever you with a o every prhat should ft out of th
ntrol"
actual 48
mat is
roject. be he
16/144
Chapter 2 "Proposed approach to construct model of cost control"
/458
Organizing the Work of the Estimate Estimating the cost of a multistory office building, high-tech manufacturing facility, or state-of-the-art concert hall is no easy task. It is a big job and takes great deal of planning and organization. So, how do you conquer this challenge? Well, the same way you eat an elephant—one bite at a time! Although the CSI Master Format 2004 gives us an overall outline to follow, thousands of activities and materials must be considered before you can begin to price the project. As large as the task may seem, there actually is a logical method for organizing all of the work activities, materials, and labor associated with a project. Let’s take a look at just how you eat this elephant!
1. The Work Breakdown Structure The primary organizational tool utilized by the construction estimator is the work breakdown structure (WBS). The work breakdown structure establishes the basic building blocks of both the estimate and the schedule. The purpose of the work breakdown structure as it applies to the estimate is to organize and identify the work of the project by breaking each division of work into a separate work package or bid package. The work package identifies each step in the process of that work item. Work packages are usually assembled around the work activities typically performed by a single subcontractor or work group. Obviously, being familiar with construction materials and methods is pretty important here. One of the primary goals in creating a work package is to not overlook any of the steps needed to complete the work. A sample work package looks something like this: Work Package—Concrete Floor Slab
• Excavate the footings. • Install the edge forms. • Install under slab fill. • Install vapor barrier. • Install the reinforcing. • Place anchor bolts. • Place the concrete. • Finish the concrete. • Strip the form work.
Once each step associated with a particular item of work is identified, it can be quantified and priced. But let me stop here and back up a minute to make sure that you remember how the work of the project is actually accomplished. The contractor has two options:
• self-perform the work with their own forces • Subcontract the work to various trade contractors.
17/144
Chapter 2 "Proposed approach to construct model of cost control"
/459
The contractor will have to do all of the quantifying and pricing of each step of the work if the contractor decides to self-perform a particular section of work. If the contractor decides to subcontract out some of the work, then the subcontractor will quantify and price the work and submit a bid to the general contractor. The greatest challenge either way is to make sure that nothing gets overlooked or left out of the estimate. Sometimes the general contractor calculates their own quantities and estimates for subcontracted work even though the subcontractor will be submitting a bid. This is called a fair value estimate; it’s done as a check to guard against inaccurate quantity surveying by the subcontractor and unreasonable pricing.
2. Calculating Quantities Now that you have assembled all of your work packages and identified all of the steps necessary to do the work, you can start doing your quantity takeoff. You must quantify all of your materials, labor, and general conditions before you can price any of the work. You need to calculate “how many” before you can calculate “how much.” Once you determine the quantities, you can apply a unit price factor to the equation. Junior estimators often start off as quantity surveyors. The primary attributes of a good quantity surveyor are the ability to read and interpret plans, knowledge of common units of measure for construction materials and labor, and basic estimating mathematics. You will use algebra to measure ratio and proportion, plane geometry for lineal and area measurements, solid geometry for cubic measurements, and plane trigonometry for lineal, area, and cubic measurements.
3. Quantifying Materials Quantifying materials is the least risky of all the estimating activities. You are simply counting and calculating all of the parts and pieces that will go into the project. Quantity surveying represents more of the science of estimating. That’s because you are working with known sizes and dimensions depicted in the drawings. If the plans are drawn correctly and include all of the information needed to do the takeoff, the estimator should be able to come up with very accurate quantities, assuming the estimator doesn’t overlook anything and doesn’t make mathematical errors. The estimator reviews the plans, the elevations, the sections, and the details; pulls the dimensions needed to make the appropriate calculations; and comes up with the lengths, areas, and volumes of work and material required for the project. Probably the most difficult part of the quantity survey is making sure that the quantity is taken off in the proper unit of measure. The unit of measure
18/144
Cha
for exatakconlearkno In tof cof a
FooWaTot
24.
2.6
253The
4 Quadeahumandthabeccomcha Thisall afor
pter 2
takeoff mample, cone off all co
nvert to curn all of thowledge is
this typicaconcrete na foot. Her
• Sectionoting = 2.0ll = 0.66 f
tal section
• Perime0 feet + 2
• Section4 square f
• Conve3.44 cubic e answer is
4. Quant
antifying laal with creman factord fast dimet can be p
cause of simplexity ofapter.
s is whereabout judg any given
"Propo
ust be thencrete is poncrete byubic yards he pricing an absolu
al quantity needed for re are the
n area of f0 feet *0.6feet *2.0 f area = 1.
eter of bui24.0 feet +
n area*pefeet *96 fe
rt to cubic feet ÷ 27s 9.39 cub
ifying La
abor and ew sizes anrs of constensions onplaced or ite conditiof the proje
e estimatingment. Thn crew reg
osed appr
e same as riced by th
y the cubic to match units for tute necess
surveying this found steps
foundation66 feet = feet = 1.332 square
lding: + 24.0 fee
rimeter =eet = 253
c yards (un7 cubic feebic yards o
abor and
equipmentnd producttruction is n a set of dnstalled inons, weathect, and se
ng moves he individuarding any
roach to c
/4510
the unit ohe cubic yc foot (lengthe pricing
the varioussity if you
g exercise,dation. All
n: 1.32 squa2 square f
e feet + 1.
et + 24.0 f
cubic feet.44 cubic
nit of meaet = 9.39 cof concrete
d Equipm
t is a littletivity rates not quite drawings. n a specifieher, crew everal oth
way over ual estimaty given ite
construct
of measureyard. The qgth × widtg unit. It ts materialare an est
, you will e inches ar
re feet feet .32 square
feet = 96 f
t feet
sure for cocubic yarde in found
ment
e riskier. Ts. In other the same Productived unit of makeup, cer factors
on the arttor will detem of work
model of
e for pricinquantity suth × depthtakes a litts and labotimator.
estimate tre converte
e feet = 2.
feet
oncrete): s ation.
hat’s becar words, we as workinity is the atime. Prodcrew skill discussed
t side of thtermine thk. Fortuna
f cost con
ng. For urveyor mh) and thetle time toor, but this
the cubic yed to deci
.64 square
ause you mworking witng with haamount ofductivity vlevel,
d earlier in
he equatiohe productately,
ntrol"
must en o s
yards mals
e feet.
must th the
ard f work varies
the
on. It’s tivity
19/144
Cha
proconcanequsize
5
Alsoassof mestThemoof g
6 SupJobMatTemPorDumJobOn-JobPricOncyouequextwhe
pter 2
oductivity instruction n help the uipment ques and pro
5. Quanto called jo
sociated wmeasure foimator is te estimatonths, or ygeneral co
6. Generpervision (b trailer (reterial storamporary utrtable toilempsters (rb photogra-site webc
b office supcing the Wce all of you have to duipment, aensions diere the co
"Propo
is somethiindustry, estimator uantity takoductivity
ifying Gob overheaith any givor generalto come uor must maears the c
ondition ite
ral Cond(salary) Went) Monthage trailertilities (us
ets (rent) Mrent) Montphs Lump
cam Lump pplies Lum
Work our quantido is plug and generaisplayed insts will co
osed appr
ing that is and there make senkeoffs. In rates for c
eneral Cad, generaven projecl conditionp with a tiake an educonstructioems and th
ition IteWeek h rs (rent) Msage) MontMonth th
p sum sum
mp sum
ities are ca in the unial condition Table 2.1ome from a
roach to c
/4511
studied q are databnsible judgthe follow
concrete w
Conditioal conditionct. Time, nns. Therefoime estimaucated guon will takeheir respec
em Comm
Month th
alculated, t cost for
ons in your1. As an eand their r
construct
uite extenbases and gment reg
wing, I showork:
ns ns make unot producore, the prate for theess as to he to compctive units
mon Uni
you are heach itemr estimateestimator, reliability.
model of
nsively in t referencearding labw some av
up the indictivity, is trimary tase overall johow manylete. Heres of measu
it of Mea
alfway them of materi
. You can your prim
f cost con
the s available
bor and verage cre
irect costshe norma
sk of the ob duratioy days, wee’s a sampure:
asure
ere. Now aial, labor, see the p
mary conce
ntrol"
e that
ew
s l unit
on. eeks, ling
all
rice ern is
20/144
Cha
SomtheandWh“allthe OncdowIf tsurclie Alloregmaabledril
7 Pricmabuisucma Manhistoveperplachavpric Theestthe
Table 2
pter 2
metimes it time of th
d quality then this haowance” n time.
ce the infown to reflehe actual plus funds
ent pays th
owances aarding styy also be e to accurling.
7. Sourcecing informterials, yolding supp
ch as R.S. terial, and
ny construtorical perer a numberformed woce, then thve such a scing.
ere is one imators chn calculat
-1
"Propo
t is not pohe estimathat simplyappens, it number, fu
ormation nect the actcost is less to the clihe differen
re often uyle, color, used when
rately quan
es of Infmation comou can obvpliers. Or y Means. Thd equipme
uction comrformance.er of yearsork. If a chis may besystem in
more altehoose to ue their ow
osed appr
ssible to ate becausey can’t be is a commully disclos
needed is aual cost os than theient. If thence.
sed for finor quality n there arntify the c
formatiomes from aviously getyou can chhey list unnt.
mpanies cre. They tracs and comompany he the best place, and
rnative whuse the prown unit pric
roach to c
/4512
accurately e there aremade unt
mon practicsed to the
available, f the iteme allowance cost is g
nish items such as ce simply tost of the
on a variety ot prices dirheck the vnit costs fo
eate their ck actual j
me up withas an exc
t way to god many re
hen it comoductivity ces by usi
construct
determinee decisionil the projece for estim client, ba
the allowa.
ce, the estreater tha
that requcarpet, tiletoo many u work, suc
of sourcesrectly fromarious con
or every se
own cost job costs f average uellent costo. Howeveely on pub
mes to pricdata fromng local w
model of
e the costss regardinect is undemators to
ased upon
ance is adj
imator retn the allow
ire owner e, or light funknown vch as rock
. When it m your vennstruction ection of w
databasesfrom variounit pricest reportinger, not all lished cos
ing labor. m the variowage rates
f cost con
s of items ng quantitier constru plug in an a best gu
justed up
turns the wance, the
involvemefixtures. Tvariables t excavatio
comes to ndors and cost guidework for la
s based onous projects for their g system icompaniest data for
Some ous guides in the for
ntrol"
at es
uction. n ess at
or
e
ent They to be on or
retail es bor,
n ts self-n s their
but mula.
21/144
Cha
8
TheTodestWhperthe Theequvercovprothe
9 Aftelist of wvensub
pter 2
8. Obtain
e final comday, subcoimate. ile the est
rformed wo work they
e team muuipment asry importavered, theroblem on b subcontra
• Solicit • Receiv• Analyz• Choose
9. Solicit
er a comp or chart rwork or trandor quotebcontracto
"Propo
ning Sub
mponents oontractor a
timating teork, they y are not g
ust also bessociated wnt. If one re will be abid day. Thacted wor
the bids. ve the bidsze the bidse the bids
ing the
lete reviewrepresentinades will bes, and whr/vendor l
osed appr
bcontrac
of your estand vendo
eam is putmust also going to s
e solicitingwith the w of the traa big hole here are fok and ven
s. s. .
Bids
w of the png all the be self-perhich will relist.
roach to c
/4513
ctor and
timate arer bids mak
tting toget be gatherelf-perform
vendor pwork. The des neede in the estour steps tdor pricing
lans and swork of thrformed, wequire both
construct
Vendor
e subcontrke up the
ther their ring pricesm.
ricing for amanagem
ed to comptimate, whto ensure g are com
specs, the he contracwhich will rh. Table 2
model of
r Bids
ractor and bulk of th
own pricins from sub
all of the ment of thisplete the phich will le that the splete and
estimatorct, showingrequire su.2 shows a
f cost con
vendor bie construc
ng for self-bcontracto
materials as process project is nad to a big
solicitation thorough
r will creatg which arbcontractoa sample
ntrol"
ids. ction
-rs for
and is not g of :
te a reas or or
22/144
Cha
AftevenAlthconconquohavrep It isto gtheof wnotquoestcan AndplayPutsubon as wnumMasnumtheup ons
Table 2-2
pter 2
er it is detndor or a shough subnstruction ntractors dotation to ve a past hpresenting
s importangive the suir decisionwhom theyt want to bote that doimated co
n to avoid
d even thoy it safe thtting It All bcontractethe materwell. The embers. As ster Formambers hav project, ywith your
s.
"Propo
termined wsubcontracbcontractonews serv
do, most ea selectedhistory. Th the same
nt that theubcontractn not to biy can expebe left hanoesn’t arrivst of the wthis situat
ough it takhan to be Together d work intrial takeoffestimator you can sat discusseve been adyou must a final bid.
osed appr
which areactor, a formrs and venvices for bstimators
d list of suhey usually trade.
ese requestors enougd on the pect to recenging on bve. At thework in qution.
kes a lot ofleft standi It’s time tto one estf sheets ar must be vsee in Tabled earlier dded downalso applyThese last
roach to c
/4514
as of work mal solicitndors watcid notices choose tobcontractoy send out
sts go out gh time toproject. It eive quoteid day wa last minuestion mig
f time to sing withouto compileimate sumre transfervery carefule 2.3, the in the chan at the boy taxes, get few item
construct
will requitation procch the trad as closelyo send out ors and vet requests
very earlyo put toget is crucial tes from on iting for a
ute, you wght be. Es
solicit all out a trade e all of yoummary. Allrred to theul to accure estimate apter. Howottom. Onceneral oves are ofte
model of
re a price cess gets ude journaly as the ge their own
endors wit to severa
y in the esther a pricthat the e bid day. Tn expecteill be left ttimators d
of the bidscovered b
ur self-perf of the sue estimaterately tran summary
wever, a fece you calrhead, andn referred
f cost con
quote frounderway.s and
eneral n requests h whom thal compani
stimating pce or notifystimator bTrust me, d subcontto guess wdo everyth
, it is far bby a reliablformed wobtotals cae summarynsfer all ofy follows thew very imculate thed profit to
d to as pro
ntrol"
m a .
for hey ies
process y you of be aware you do ractor
what the hing they
better to le price. ork and lculated y sheet f the he CSI
mportant e cost of come
oject add-
23/144
Cha
1 Youpaycoluwormuthefampayto k Whappmualontheclas
Table 2-3
pter 2
10. Taxes
u include tyroll taxesumns: mark and equst be adde labor colu
miliar with yroll add-okeep it sim
en I was rproximatelch “burdene will cauy might sessifying as• Employ• Worke• Unemp• Employ
holiday
3
"Propo
s
two types . That’s wterial, labuipment bed to the mumn. We a payroll taons are nomple.
running mly 14 to 20n” labor reuse a geneelf-performs payroll tayer’s portirs’ compeployment tyee benefys, and so
osed appr
of taxes inhy it is imor, equipmids will alrmaterial call know wxes (also t taxes at
y own con0 people, ieally did peral contram. The peraxes includion of Socnsation tax its (health
o on)
roach to c
/4515
n your conmportant toment, and ready haveolumn, an
what sales referred to all, but yo
nstruction it really su
put on the actor to surcentage ide the follial Securit
h insurance
construct
nstruction o divide yo subcontrae taxes incnd payroll t taxes areo as labor ou merely
company,urprised m payroll. Subcontracts significaowing:
ty tax
e, life insu
model of
estimate: our summaacts. The scluded, butaxes mus, but you burden). refer to t
, employinme to learnSometimes work thatnt. Those
urance, va
f cost con
sales tax ary into fosubcontracut sales taxst be addemay not bSome of them as ta
ng n just how s this factot otherwis costs that
cation, pa
ntrol"
and our cted x
ed to be as the axes
or e t I am
aid
24/144
Chapter 2 "Proposed approach to construct model of cost control"
/4516
11. General Overhead I’ve already mentioned job-specific overhead. These costs include such things as the job site office trailer, portable toilets, and job photographs. They are estimated item by item relative to a specific job. General overhead is a different story. Basically, general overhead represents the cost of doing business. These are expenses that would be incurred by the company whether they had a job to build or not, such as office expenses, executive salaries, and automobile insurance. General overhead is applied to the estimate as a percentage of total cost. This percentage will vary from company to company see Table (2-4).
Table 2-4 General Overhead
25/144
Chapter 2 "Proposed approach to construct model of cost control"
/4517
12. Profit The goal for every project is to make a profit. Profit is what’s left after all costs and expenses associated with the job have been paid. The estimate represents the contractor’s best guess as to what those costs and expenses are going to be. Profit is expressed as a percentage of the total estimated cost. Profit is rarely a fixed percentage in construction. The estimating team will make a determination as to how much that percentage should be for any given job. As previously stated, when times are tight in construction and there is very little work to bid, profit margins may be quite small. On the other hand, when there is a lot of construction going on in a particular market and demand is high, profit margins will be adjusted upward. Either way, profit is an estimated number just like every other number in the bid. It is highly unusual for the actual cost of the project to exactly match the estimated cost of the project. If we consider each division of our estimate summary, and each of our add-ons, the most likely scenario will be that some divisions (and add-ons) will be over the individual division estimates, and some will be under the individual estimates. However, it’s the final number that you are most concerned with. The goal is to have the actual overall cost of the project at the estimate or under after all point we described we can illustrate the cost estimation in figure (2-4).
26/144
Cha
Sa
pter 2
ample F
"Propo
Forms o
Fig
osed appr
of Cost E
gure 2-5 F
roach to c
/4519
Estimat
Forms of
construct
te
Cost Esti
model of
imate
f cost conntrol"
28/144
Cha pter 2
"Propo
Figure
osed appr
e 2-6 Form
roach to c
/4520
ms of Cos
construct
st Estima
model of
ate
f cost conntrol"
29/144
Cha pter 2
"Propo
Figu
osed appr
ure 2-7 Fo
roach to c
/4521
orms of C
construct
Cost Estim
model of
mate
f cost conntrol"
30/144
Cha
pter 2
"Propo
Figure
osed appr
2-8 Form
roach to c
/4522
ms of Cos
construct
st Estimat
model of
te
f cost conntrol"
31/144
Cha
pter 2
"Propo
Figure
osed appr
2-9 Form
roach to c
/4523
ms of Cos
construct
t Estimat
model of
te
f cost conntrol"
32/144
Chapter 2 "Proposed approach to construct model of cost control"
/4524
2.1.2- Work Breakdown Structure (WBS)
To plan the project we must convert these into individual pieces of work that must be done to complete the project. For this we need the ‘‘work breakdown structure,’’ or WBS .The work breakdown structure is the most central item in the project plan. Without it we do not have a definition of the work that has to be done to complete the project. Without knowing the work that has to be done we cannot possibly determine the cost of the project or determine the schedule of the project. Without knowing the cost or schedule of the project how will it be possible to control the project or determine how much should be spent to complete it? The amount of resources that must be used on the project and when they must be made available cannot be determined without knowing the schedule. Funding to do the project cannot be scheduled to be in place when the project needs it without a time-phased budget for the project. According to the Guide to the PMBOK, the definition of a work breakdown structure is: ‘‘a deliverable oriented grouping of project components that organizes and defines the total scope of the project work. To create a WBS is a simple task: the project is first broken down into a group of subprojects. Each of these subprojects can be broken down to sub subprojects. The sub-subprojects can be broken down again and again until the desired level of detail is reached. The level of detail is termed the' work package’’ level. The work package is the lowest level of management that the project manager needs to manage. Below the work package other project team members may break down their parts of the project into additional levels .Work packages can be broken down into ‘‘activities,’’ and activities can be further broken down into ‘‘tasks.’’ The reason that technique is so effective is that it follows the principle of ‘‘divide and conquer. 'So, initially the project is broken up into a group of subprojects. These subprojects are further broken down into sub-subprojects, and so on. In this way the largest project we can imagine could be broken down into subprojects. Since each of these subprojects could be considered to be a project in its own right, any large project can be thought of as a family of smaller projects that are interrelated. The important thing about project management is that it is a powerful Methodology that adapts to any size project or program. The tools and methodology that are used are similar in all projects. The WBS is the tool that allows all projects to be broken down into smaller, more manageable projects. The end result of the WBS is a group of individual pieces of work defined. Each of these small individual pieces of work must be assigned to. It is then
33/144
Chapter 2 "Proposed approach to construct model of cost control"
/4525
possible to break the work packages down further before the actual work assignments at the detail level are made. The WBS is a hierarchical structure in which all of the major phases of project work are organized in a logical manner. Simply stated, it is a layout of how the work of the project ought to be performed and managed. The WBS links together the project scope, the schedule, and the cost elements, and forms the basis for the entire project information structure. It provides the framework that captures the project’s work information flows, as well as the mechanism for tracking the project’s schedule and progress. It also provides the basis for summarizing and reporting the project’s cost data. In essence, the WBS creates a common framework that.
• Presents the entire project as a series of logically interrelated elements
• Facilitates project planning
• Provides the basis for estimating and determining project costs and
budgets
• Provides the mechanism for tracking project performance, cost, and schedule
• Provides the basis for determining the resources needed to
accomplish project objectives
• Provides the mechanism for generating project schedule and status Reports
• Triggers the development of the project network and control
systems
• Facilitates the assignment of responsibilities for each work element of the project
• Graphically, we can imagine a WBS along the lines shown in Figure
2.10
34/144
Cha
Thprothrofiniselemact Aloof dProtheterm
pter 2
ere are sooject activiough specshing withmental tasivities for
ng with a detail is anject scope appropriams of reso
"Propo
ome importies is hie
cific projech work pacsks at the which dur
well-definn invaluabe can easilate work pources and
Figur
osed appr
rtant featurarchical,
ct deliverackages. Ac lowest levration and
ned projectle tool for y be expa
packages, d schedule
re 2-10
roach to c
/4526
ures to notmoving frbles (and ccording tovel in the W budget fig
t scope do managing
anded or dand by ma
es.
construct
te here. Fiom the ovsometimeo the ProjeWBS and gures can
ocument, ag scope chiminished aking the
model of
rst, the brverall projees sub deliect work prepresent be assign
a WBS withange. by includnecessary
f cost con
reakdown ect level, dverables),
packages a basic projed.
th sufficien
ing or elimy adjustme
ntrol"
of down , and are the ject
nt levels
minating ents in
35/144
Cha
2.1.2 It isusegento utheuse Coninfobuytha Pro
Outprorelaultifaciproexa orgunitinteestarepcom
pter 2
2.1- Ty
s importaned in projenerate the use the W identifica
ed that sho
ntractualormation ayer. It is ut is going
oduct-bas
tcome, sucototype. Inatively easmately intilitates cos
ovides a baample of a
ganizationts responsegrated intablishes, i
porting relampleting th
"Propo
pes of W
nt to recogects. The W individuaBS to devetion of woould not b
WBS (CWand the timsually not to be don
sed WBS
ch as the n these kinsy to breakto managest estimatasis for co product-b
nal breaksible for coto the strun a hierarationships he work. E
osed appr
Work B
gnize that WBS that wl pieces ofelop anyth
ork less effe confused
WBS). Thimeliness ot as detailee.
is most su
design andnds of prodk the projeeable workion of the mparison based WBS
kdown strompleting ucture. Thrchical form for the vaExample o
Figure
roach to c
/4527
Breakdo
there are we have bf work thahing else wfective. Otd With the
is breakdoof informated as the W
uitable for
d construcduct-basedect into dek packages various pwith the pS is shown
ructure, k the work e clear admat, accouarious orgaf OBS is s
2-11
construct
own Str
many otheen discust must be would confther breake WBS are
own is usetion that aWBS that
projects t
ction of a td work breeliverabless. A produroduct comproject’s an in Figure
known as requiremevantage ountability, anizationahown in F
model of
ructures
her types ossing mus done in thfuse the ekdown stru:
d to defina supplier wis used to
that have
tunnel, or eakdown ss, sub delivuct-based mponents,ctual cost e 2.11
OBS, the ents of theof an OBS responsib
al units thaigure 2.12
f cost con
s
of breakdost be used he projectffort and m
uctures tha
e the repowill supply
o plan the
a tangible
a new figstructures,verables, WBS Also , which in Performa
organizatie project ais that it
bility, and at are invo2 that proj
ntrol"
owns only to t. To try make at are
orting y to the work
e
hter Jet , it is and turn nce. An
onal are
olved in ject
36/144
Cha
invoproProproprointelowprocombe
pter 2
olves a seoject, ocess-orieocess-orienoject evolvegrated wi
west level, oduct cost\mbination used. An e
"Propo
ries of pha
ented WBnted WBS ves over timith the ove while the \ informatof featureexample o
osed appr
ases or ta
BS is more involves cme. In generall proje product-bion. In adds from bot
of a proces
Figure 2
roach to c
/4528
sks, such
e appropricompletionneral, a prct, becaus
based WBSdition, a hth productss-oriented
-12
construct
as in an in
ate. Unliken of majorrocess-oriese the taskS is most uhybrid strut- and prod WBS is s
model of
nformation
e a producr tasks in sented WBSks can be useful for cture thatcess-baseshown in F
f cost con
n systems
ct-based Wsequence aS can be bdelineatedaccumulatt involves ed structurFigure 2.1
ntrol"
WBS, a as the better d to the ting a res can 3
37/144
Cha
In tprobe puroth BillBOMof a
pter 2
the presenoject manaused. Howrpose, the er organiz
l of mateM in a hierassembly a
"Propo
nt-day proagement swever, the organizatzational un
rial (BOMrarchical ware shown
Figure 2-
osed appr
oject enviroystems, b choice re
tion’s infornits, and,
M). The vaway. Produn as a ‘‘goe
-13
roach to c
/4529
onment, woth types ally depenrmation syultimately
arious products produes into’’ hi
construct
with its pro (product nds on theystem and , how use
duct compuced, subaierarchy
model of
oliferation and proce
e particula how it intful it is as
ponents areassemblies
f cost con
of compuess) of WBr project, terfaces w a plannin
e includeds, and lowe
ntrol"
terized S can its
with the ng aid.
d in the er level
38/144
Chapter 2 "Proposed approach to construct model of cost control"
/4530
2.1.2.2 Work Breakdown Structure Development
Before any Work Breakdown Structure can be produced, it is essential that careful thought is given to the number and size of networks required. Not only is it desirable to limit the size of network, so we should be considered in relation to the following aspects:
1. The geographical location of the various portions of the project.
2. The size and complexity of each Project.
3. The process or work being carried out in the Project when the plant is complete.
4. The engineering disciplines required during the design and construction stage
5. The erection procedures.
6. The stages at which individual Project or systems have to be
completed.
7. The site organization envisaged.
8. Any design or procurement priorities. So Constructing a WBS is a group effort. The responsibility for the top three levels usually lies with the project manager, who typically works with other managers to develop the major deliverables found there. At the lower levels, however, input into the details should come from that Responsible for the day-to-day work. In addition to the project team, each person responsible for a specific work package must be consulted. There are no universal standards as to the number of levels to use in a WBS. This is typically dictated by the complexity of the project, and the number and nature of the activities. Most have three or four levels at a minimum, although more may be needed if there are significantly more sub deliverables and work packages. As a rule, the greater the number of work packages, the greater the amount of time, effort, and cost incurred in developing the WBS. However, the increased number of packages also significantly enhances the accuracy of project status monitoring and reporting. On the other hand, larger but fewer work packages reduce the cost of WBS development, but the accuracy of project status monitoring and reporting suffers. In most practical situations, a compromise on the number and size of work packages is struck. The most important levels in the WBS development process are the top few levels, which represent the project and associated major deliverables, and the lowest levels, which represent the work activities that are to be scheduled and resourced.
39/144
Chapter 2 "Proposed approach to construct model of cost control"
/4531
Typically, the intermediate levels are an aggregation of the lower-level activities, and serve as the mechanism for reporting. The intermediate levels can also be used to set up cost accounts through which cost and budgetary information can be gathered and monitored. A WBS should be constructed by separating the total work, in a hierarchical framework, into discrete and logical sub elements that reflect completeness, compatibility, and linkage to the project’s end item. This hierarchical structure facilitates the aggregation of budget and actual costs incurred into larger cost accounts. In this way, the total value of the work at one level is an aggregation of all the work completed one level below, which enables project work and cost performance to be monitored. The WBS should also reflect all of the project requisites, as well as functional requirements, and should incorporate both recurring and nonrecurring costs. In a WBS, the lowest level consists of tasks of short duration that have a discrete start and end point. Because they consume resources, costs are often reported at this work package level. Work packages serve as control point mechanisms for monitoring and reporting performance, in terms of whether associated tasks were completed according to specifications, on time, and within budget. The responsibility for completing work Packages should be assigned to the appropriate organizational units and individuals, and the resulting WBS should reflect the reporting requirements of the organization. We can develop a WBS by one of two methods:
• Top-down approach begins with the total work required to produce the project’s end product. This is successively broken down, First into major work blocks and then into more detailed work package levels until a required level of detail has been achieved.
• Bottom-up approach begins with a comprehensive list of all the
activities or tasks required to complete the project. Then it moves up, in a hierarchical format, first to work packages, then to cost accounts, and so on, until the top level represents the total work to be performed. It is highly unlikely that the first version of the WBS will be the last.
More often than not, it will undergo frequent revisions in response to Feedback that works must be broken into more detailed tasks. Clearly, only individuals who have a thorough knowledge of the work to be performed can conduct the appropriate level of detailed breakdown. In addition, it is impossible to establish estimates of task duration, resource requirements, and the network of precedence relationships among activities without complete agreement on details at the lowest level.
40/144
Chapter 2 "Proposed approach to construct model of cost control"
/4532
2.1.3- Cost Codes
Once the budget, WBS is confirmed, each activity in the budget is assigned a cost code. Cost codes are used to track all items of work contributing to the overall project Costs. That includes material, labor, equipment, subcontracts, and overhead. All job information regarding cost is tracked via these cost codes as shown in Figure 2.14 Every item on a material invoice, every man-hour logged on a time card, and every subcontractor payment are assigned a cost code and recorded. These codes are used to compare actual job costs with the estimated job costs throughout the construction process. These cost codes usually start with the original CSI reference number associated with the activity, and then for further detail another number is assigned that represents the type of cost. For example: Activity Code
• Material 1 • Self-performed labor 2 • Subcontracted labor 3 • Equipment 4 • Job site overhead 5
So, if I were the job superintendent tracking building insulation cost on a project, I would assign the following cost codes to the invoices that came across my desk: Item Cost Code (CSI Number — Type of Cost)
• Material invoice 07 21 00-1 • Subcontractor bill 07 21 00-2 • Equipment rental 07 21 00-3
Larger contractors will also assign a year and job number to the cost code. For example, assuming that the previous project was a large contractor’s 14th job of this year, the material invoice might be coded as follows:
• Year project started: 2010 • Project no.: 14 • CSI division: 07 21 00 • Type of cost: 1 (material) • Cost code: 2010 14 07 21 00-1
41/144
Chapter 2 "Proposed approach to construct model of cost control"
/4533
Smaller contractors might simply identify each of the invoices by the client name along with the cost code. Smith 07 21 00-1 the point is to make the codes as user-friendly as possible while still providing the level of detail needed to properly analyze the project costs. Each invoice amount would be recorded according to the cost code assigned to it by the superintendent. Material costs, labor costs, and equipment costs could be tracked separately, or you could combine them into a single work package total. Either way, you could compare the actual cost to do the building insulation with the budgeted amount and note any discrepancies. All invoices and subcontractor billings are eventually transferred to the contractor’s cost accounting department. The accounting department also tracks the project according to the cost codes and submits reports identifying total material, labor, subcontract, equipment, and overhead costs incurred on the job. The project manager uses these and other reports to monitor the project performance from a big-picture perspective. Spot Check the Cost Coding It’s not uncommon for a vendor to list more than one cost code item on a single invoice. For example, the same invoice could have materials that fall under three different divisions — let’s say lumber (Work packages 6), mortar (Work packages 4), and rebar (Work packages 3). When this happens, it is important to make sure that someone is taking the time to separate the material costs according to their respective Codes as shown in Figure 2.14. Unfortunately, people get lax, and they start lumping all of the material under one code. This, of course, taints the accuracy of the information, which results in faulty reporting. As a construction manager, I was always vigilant about doing random checks on job tickets just to make sure everything was being properly coded. It was part of my management systems quality assurance program.
42/144
Cha
Figur
pter 2
re 2-14
Figu
"Propo
ure 2-14
osed apprroach to c
/4534
construct model off cost conntrol"
43/144
Chapter 2 "Proposed approach to construct model of cost control"
/4535
2.1.4- Depreciation
Depreciation is a necessary function in financial management, because without Depreciation the irregularities in the fundamental financial reports of a company would vary considerably and make it difficult to compare one year or one quarter to the next. This is because large investments in assets do not occur on a regular basis.
If the total cost of an investment were reflected in the financial time period in which it occurred, the effect on net profits would be considerable in this period, and then the net profit would rise significantly in the next period. What is done with depreciation? The cost of the new asset is spread out over the life of the asset. This allows the company to claim some of the cost each year rather than the total cost of the asset all at one time.
• Straight Line Depreciation
Straight line depreciation is the depreciation method that allows an equal amount of depreciation to be taken each year. The amount of depreciation is determined by subtracting the salvage value of the asset at the end of its useful life from the purchase price of the asset. The remaining value is called the book value. The book value is divided by the number of years, and this amount is expensed from the asset each year.
For example, a company buys a large machine for $1 million. The purchase is made with cash. In the accounts for this transaction, the cash account is reduced by $1 million, and the machine account is increased by the amount of $1 million. There is no effect on the liabilities or owner’s equity side of the accounting equation and it remains balanced.
The cost of this machine must eventually be recognized. The machine has a useful life of ten years and is worth $100,000 at the end of its useful life in terms of scrap value or the ability to sell the machine to someone else. This means that the value of the machine that must be depreciated is $900,000. Since the life of the machine is ten years, the value depreciated each year is $90,000. This is known as straight line depreciation (table 2-5).
44/144
Cha
AccdepTheredamis tmu Thispaidthe Beyeaaccdou
T
pter 2
• Accele
celerated dpreciated fe reason fouced in a ount. In ahe same ach earlier
s means td in the ea taxes wil
cause of tars allow ucelerated duble declin
Table 2-5
"Propo
erated De
depreciatiofrom the aor this is tgiven yeaccelerated
as in straig in the use
hat more arly part ol be highe
the presenus to use tdepreciationing balanc
osed appr
epreciatio
on methodassets to bto reduce tr, the amod depreciaght line deeful life of
equipmenof the usefr than in s
nt value ofhat moneyon are comces.
roach to c
/4536
on
ds are usebe applied the net proount of taxtion meth
epreciation the asset.
nt expenseful life of tstraight lin
f the money in the pr
mmonly us
construct
d to allow earlier in ofit after tx that a coods the to
n, but the .
e is recognhe asset p
ne depreci
ey, taxes tresent Yeased: sum o
model of
the expenthe usefultaxes (NOompany paotal amountime that
nized and lpurchasedation.
that are dears. Two tyof the yea
f cost con
nses that l life of thePAT). If Nays is lessnt of depre it is taken
ower taxe. In later y
eferred to ypes of rs’ digits a
ntrol"
are e asset. OPAT is s by this eciation n is
es are years
later
and
45/144
Cha
Thefinaaccthe6, f
Thehigyeanumlowdivi
Likthemestadepremreayea
T
pter 2
• Sum oere is no sancial reascounting p years of tfor a ten Y
e amount ohest digit ar the last mber is the
wer year’s iding 9 by
• Doubl
ke the sum double dethod for andard accopreciable vmaining deched. With
ars is much
Table 2-6
Table 2-7
"Propo
of the Yeacientific bason for usiractice. Ththe useful
Year usefu
of depreciyear and year’s digen multipldigit is use 55. Each
le Declini
m of the yeeclining bacceleratinounting prvalue of thepreciable h this meth higher t
osed appr
ars’ Digitsasis for thng this cahe calculat life of thel life, the t
ation in thdividing th
git is used,ied by theed. In the year the n
ing Balan
ears’ digitsalance calcg the deprractice. Thhe item. Th value of tthod the ahan in the
roach to c
/4537
ts. e sum of tlculation etion is made equipmetotal is 55
he first yeahis by the , making te book val second yenumerator
ces
s depreciaculation eireciation ohe percenthe next yehe item, amount tak
e later yea
construct
the Years’except thade by totant. Thus,
ar is deter sum of ththe calculaue. In theear the der declines
tion, thereither. It isof equipmet of deprecear’s depreand so on ken as deprs (table 2
model of
’ digits meat it has bealing the das can be
rmined by he years’ dation 10 di remaining
epreciationby one ye
e is no scie, howeverent and haciation is teciation is until the spreciation 2-7).
f cost con
ethod. Theecome a sigits repre seen in ta
taking thedigits. In thivided by 5g years, thn is calculaear.
entific basr, a consistas becometaken on th taken on salvage va in the ear
ntrol"
re is no tandard esenting able 2-
e he first 55. This he next ated by
sis for tent e a he the alue is rly
46/144
Chapter 2 "Proposed approach to construct model of cost control"
/4538
2.2- Construct model template –Excel-Format
2.2.1- WBS template sheet
2.2.1.1- WBS sheet template consist:
The sheet consist of a group of column which we will fill it with date which we will knowing later the kind of date but first we will know the format of data but before illustrate the sheet format we must know the difference between budget & price
Budget: it consist of dry cost only the direct cost of item
Price: it consist of direct cost, percentage of in direct cost & over head
1- The first set will consist of WBS code according to BOQ 2- The second set will consist of item description and unit of measure 3- Third set it will consist of rate the budget rate (direct cost) & price rate 4- it will the Quantities column that is:
• Contract Quantity which we sign our contract about this Quantity • Actual Quantity it describe the situation of our quantity if it is above or
below the contract quantities • Invoice Quantity it describe the quantity we take from the client • Provision Quantity it describe we are execute but it doesn't add to the
invoice quantity
5- it will the Budget / price column that is • Contract Amount it describe the amount of money according to Price this
by multiply the contract rate with contract quantity • Budget Amount it describe the amount of money according to budget this
by multiply the budget rate with contract quantity • budget Forecast Amount it describe the amount of money according to
budget after change of quantity this by multiply the budget rate with Actual Quantity
• budget Allowance Amount it describe the amount of money according to budget but for invoice quantity this by multiply the budget rate with Invoice Quantity and Provision Quantity
• invoice Amount it describe the amount of money according to Price but for invoice quantity this by multiply the Price rate with Invoice Quantity and Provision Quantity
47/144
2.2.
Ta
Cha
1.2- WBS
ble (2-8) W
pter 2
S sheet te
WBS shee
"Propo
emplate
et forms
osed appr
forms: a
roach to c
/4539
as shown
construct
in table
model of
(2-8)
f cost conntrol"
48/144
Chapter 2 "Proposed approach to construct model of cost control"
/4540
2.2.2- Expenses template sheet
2.2.2.1- Expenses sheet template consist:
Expenses sheet it contain with every pent we spend on the project which consist of two major item
1- Direct Expenses which are • first set of column it describe the codes which we used with direct
expenses • The second ser will consist of item description and unit of measure • the third set of columns it describe the monthly expenses (unit, cost) • that last set is the cumulative cost , units
2- indirect Expenses which are
• first set of column it describe the codes which we used with direct expenses
• The second ser will consist of item description and unit of measure • the third set of columns it describe the monthly expenses (unit, cost) • That last set is the cumulative cost , units
49/144
Cha
2.2.2
pter 2
2.2- Expe
• Direct
"Propo
enses sh
Expenses
Table (
osed appr
eet temp
sheet form
(2-9) Dire
roach to c
/4541
plate for
ms
ct Expens
construct
rms: as s
es sheet f
model of
hown in ta
forms
f cost con
ble (2-9),
ntrol"
(2-10)
50/144
Cha pter 2
• Indirec
T
"Propo
ct Expense
Table (2-10
osed appr
es sheet te
0) indirect
roach to c
/4542
emplate fo
t Expenses
construct
orms
s sheet for
model of
rms
f cost conntrol"
51/144
Chapter 2 "Proposed approach to construct model of cost control"
/4543
2.2.3- Storage template sheet
2.2.3.1- Storage template sheet consist:
1- material storage • first set of column it describe the codes which we used with material
• The second ser will consist of item description and unit of measure
• the third set of columns it describe the amount of material that will
deduct or increase about expenses sheet (unit, cost) this material that doesn't include in work
2- Subcontractors reserve • first set of column it describe the codes which we used with material
• The second ser will consist of item description and unit of measure
• the third set of columns it describe the amount of work that will deduct
or increase about expenses sheet (unit, cost) but to Subcontractors
52/144
Cha
2.2.3
pter 2
3.2- Stor
"Propo
age tem
Table (2-
osed appr
plate sh
-11) Stora
roach to c
/4544
eet form
age sheet
construct
ms: as sho
forms
model of
own in table
f cost con
e (2-11)
ntrol"
53/144
Chapter 3 " the application steps & methods "
/421
3- The application steps & methods
3.1-Collect Actual Cost data Once project work begins, the project manager systematically collects status information according to the methods and frequency previously determined. When status information is collected, the project manager compares it with the schedule, budgets, and scope identified in the project plan to determine the variances.
So before the project begins, the project manager should consult with the project team, the customer, and the client to determine the information needs, data collection methods, and frequency of data collection.
3.1.1- Sources of information
At the heart of every project control system are information and a good reporting process. Successful construction management and project control depend on sound information, which comes from actual project performance data. This data originates in the field and is reported on a daily, weekly, and monthly basis. The following are some of the sources of information used to track job performance and feedback into the project control system:
1. Job logs 2. Diaries 3. Daily field reports 4. Time cards 5. Visual Records 6. Correspondence 7. Subcontractor billing statements
However, this information serves two critical functions: It is used to detect variances between the actual cost, time, and productivity performance and the planned estimate and schedule. It is used to develop the historical estimating databases and productivity factors used on future projects. Let’s take a look at some of these mechanisms now.
1. Job Logs
Logs are used to track a number of regular activities occurring on the job site.
• Transmittal logs track the dates and addressees of all transmittals as well as the actual information being transmitted, such as shop drawings; product cut sheets, samples, or some other submittal.
54/144
Chapter 3 " the application steps & methods "
/422
• Delivery logs help keep up with all of the material and equipment deliveries that are made to the site. The log contains the date of the delivery and the material received, and it notes any problems with the order and the actions taken.
• RFI logs track all requests for information submitted to the project participants and their responses. The date the RFI was sent and the date that the response was received are also noted in the log.
2. Diaries
Every member of the project team, but especially the superintendent, should be encouraged to keep a project diary. The diary is used to track all of the day’s events in a summarized fashion and in the individual’s own words. Diaries are used to note daily work activities, conversations, observations, and any other information worth recording. It is important that each member of the team keeps their own diary, because different people will have different interactions and conversations throughout the day. The diaries provide a reliable historic record and can become very important when disagreements or discrepancies arise on the job. Handwritten diaries are often permissible in courts as evidence of actual events and conversations.
3. Daily Field Reports
In addition to the informal project diaries, most construction companies require that a more formal record be kept. These field reports are intended to simplify the capture of some fundamental information needed to track job progress and confirm that various project requirements are being met the following are the types of information recorded:
• The name of the individual making the report • The date, project name, and location • A brief description of the day’s activities • The temperature and general weather conditions • The contractor’s own work forces on the job • The subcontractors’ personnel on the job site • Materials or equipment delivered • Equipment used on the job • Visitors to the job site • Other notable events
Daily reports are often summarized into weekly or monthly reports that are distributed to upper management within the company. These reports make up some of the data used to analyze project performance and make adjustments to the overall project plan.
55/144
Cha
4. T
If tgrelabomaext Theto cespcarma
On eacworcarfor Thelabosupasppurthetea
pter 3
Time card
he populaeatest risk or recordsnagers in remely va
e time cardcalculate wpecially if yds providenager to t
large projch trade orrkers recods are com accuracy
e informator report, perintendepects of thrpose of thm with bum keep th
ds
r adage “T to the cons is one of the field. aluable to t
ds providewages andyou are one the fundtrack and m
jects, timer labor grord their hompleted, tbefore bei
ion gather typically p
ent. The ree work. La
he report iudgeted lahe project
Time is monstruction the most The data tthe constr
e the payrod distributene of the wamental inmonitor pr
e cards areoup workinours on a hey shoulding sent to
red from tprepared beport trackabor is cats to summbor costs. on target
Table (3-1)
" the a
/423
oney” hold schedule importantthat they ruction com
oll clerk we paycheckworkers exnformationroductivity
e usually fng on the jweekly timd be revieo the payr
he time caby the supks labor hotegorized amarize cum This infor for meeti
Time Cards
applicatio
ds true, th and budget functionscollect by mpany.
with all of tks which ixpecting a n needed by and labo
filled out bjob. If it isme card. Iewed and croll clerk s
ards is useperintendeours and dand tracke
mulative larmation heng its cost
s
on steps &
en labor ret Keepins of constr way of tim
the informs pretty im check. Inby the con
or expendit
by superviss a small jn either inchecked byee table (
ed to creatent or assisdollars speed by costabor costs elps the mt and sche
& method
representsng accurateruction me cards i
ation needmportant, addition,
nstruction tures.
sory persoob, the in
nstance, oy the supe3-1).
te a weekstant
ent on varit codes, th and comp
managemeedule goals
ds "
s the e
s
ded
time
onnel for dividual nce the erintenden
ly
ous he pare nt s.
nt
56/144
Cha
5. V Youcertrecconwrit 6. C
Evepararcsupgrotheincl
pter 3
Visual Re
u’ve heardtainly the ording wo
nstruction tten repor
Correspon ery day, nurticipants. hitects, en
ppliers, tesoups. All of duration lude the fo
• Submi• Payme• Punch • Chang• Reques• Letters• Emails• Faxes
cords
the expre case in cork progresmethods,
rts.
ndence
umerous c Emails, lengineers, osting organf the correof the proollowing:
ttals ent reques lists e orders sts for infos s
ession “A ponstructionss on the j highlight
communicetters, andowner repnizations, espondencoject. The
sts
ormation
" the a
/424
picture is wn. There ajob site. Pand captu
ations ared faxes fly s, building governmece must betypes of d
applicatio
worth a thre many rrogress ph
ure problem
e generate back and g officials, ent agencie field andocuments
on steps &
housand wreasons fohotos helpm areas, a
d among t forth amo subcontraes, and co recorded
s that mus
& method
words.” Thir visually
p documenand supple
the projecong the actors, maommunity througho
st be saved
ds "
is is
nt ement
ct
aterial ut d
57/144
Chapter 3 " the application steps & methods "
/425
3.1.2- Data Required From Procurement Department
1. Requirements
• Log every 15 days with all material imported to each project log contain (material item ,code of material , supplier name , unit of price & quantity of PO)
• List of material that finished its finance benefits to double check on the
data from finance department.
• The procurement team shall record every material item in this log and attached with statement.
• The sub contractor contract shall be review by control team and soft copy of the contract shall be send to our team.
2. Flow chart It describe the process between Procurement team and other department as shown in figure (3-1)
58/144
Cha
3. ForWe we
pter 3
rms will descr shown in
ribe differe table (3-2
Figure
ent form re2), (3-3), (
e (3-1) data
" the a
/426
equired fr(3-4)
a flow betw
applicatio
om Procur
ween Procu
on steps &
rement De
rement tea
& method
epartment
am and othe
ds "
as
er
59/144
Chapter 3
Taable (3-2) L
" the a
/427
Log of mate
applicatio
erial import
on steps &
ted
& methodds "
60/144
Chapter 3
Taable (3-3) Q
" the a
/428
Quotations
applicatio
s Compariso
on steps &
on Sheet
& methodds "
61/144
Chapter 3
Table (3--4) Recommfor Quo
" the a
/429
mended Suotations list
applicatio
bcontractot
on steps &
ors
& methodds "
62/144
Cha
3.1.3-
1. Req
• da
• T
2. Ste
• H
i.
ii.
iii.
iv.
v.
• O
i.
ii.
iii.
• T
i.
ii.
pter 3
- Data R
quiremen
deliver perasset in pr
The import
eps of wo
How we en
Record th The man
The storaafter chec
The storamanger
The accoumaterial d
Out of mat The sign The place The purp
The roll of Get daily The accoumust invo
Require
nts
riodic reporoject and
tant of thi
ork
nter the m
he importe
on the ga
age man reck of exist
age make
unt take tdaily ,wee
terial from
of the For
e will take
ose of tak
site accou
report fro
unt make olve the co
Figure (3
ed From
ort from th date of in
s report to
material to
ed materia
ate sign off
eceive thet the sign
material c
he informaekly month
m the stora
rman or en
it
ken materi
unt
om the sto
every 15 ode of ma
-2) step of
" the a
/4210
m Storag
he storagen and out t
o specify t
the projec
al on the e
f the bill o
e material of entranc
card and ta
ation and hly
age
ngineer
al
orage abou
day reporterial the
enter mate
applicatio
ges
e team conthe value o
the accura
ct see figu
entrance g
or receiving
and take cce gate
ake the ap
make the
ut in/out m
t about in amount of
erial to the
on steps &
ntain the cof bill if it
ate losses o
ure (3-2)
ate
g balance
copy of th
pproval fro
report of
material
/out matef money fr
project
& method
code of ma exist.
of materia
e bill or PO
om the pro
received
erial the rerom the b
ds "
aterial , all
al
O
oject
eport ill
l
63/144
Cha
iii.
iv.
3. Flo
It dsho
pter 3
The accoreceived The reporraises to
ow chart
describe thown in figu
ount makeand purpo
rt will raiscontrol m
he processure (3-3)
e every 15ose of usag
es to the anger
s between
Figure
" the a
/4211
day reporge.
project ma
Storage t
(3-3) datao
applicatio
rt about o
anger then
eam and o
a flow betwother depar
on steps &
ut materia
n after app
other depa
ween Storagrtment
& method
al the plac
proval will
artment as
ge team and
ds "
ce of
l
s
d
64/144
Cha
4. For
We sho
pter 3
rms
will descrown in tab
ribe differele (3-5), (
Table
ent form re(3-6), (3-7
e (3-5) Monm
" the a
/4212
equired fr7)
nthly Repormovement
applicatio
om Storag
rt about sto
on steps &
ge Departm
ore
& method
ment as w
ds "
we
65/144
Chapter 3
Table (3-6) Momaterial
" the a
/4213
nthly Repo distributio
applicatio
ort about ns
on steps && methodds "
66/144
Cha
pter 3
Tablemate
e (3-7) Monerial distribu
" the a
/4214
nthly Reporutions and
applicatio
rt about location
on steps && methodds "
67/144
Chapter 3 " the application steps & methods "
/4215
3.1.4- Data Required From Projects
1. Requirements
• Site send to the control team the client invoices with its supported survey.
• Sub contractor invoices.
• The pouring log for concrete to get the actual losses and for sure the quantity we pied to the supplier
• Bar binding list for steel to get the actual quantity &looses for steel and comparison with tender quantity.
• Summary for labor work during the period every 15 day with their activity attached with labor time card.
• Summary for the rent equipment and the activity the make during the period attached with their invoices.
• The equivalent between the client invoices and sub contractor.
• Periodic report for finishing item to know the actual quantity this will help us and the tender to make actual estimate for this items.
• The technical office update the quantity of the contract to get good forecasting to this contract.
• The technical office will submitted every variation order.
68/144
Cha
2. Flo
It dsho
pter 3
ow chart
describe thown in figu
he processure (3-4)
Figure (
s between
(3-4) data ot
" the a
/4216
Project te
flow betwether depart
applicatio
eam and o
een Projecttment
on steps &
ther depa
ts team and
& method
rtment as
d
ds "
69/144
Cha
3. For
We
• La
Rep(3-
pter 3
rms
will descr
abor
ports requ12), (3-13
ribe differe
ired for la3), (3-14),
Table
ent form re
bor as we, (3-15)
e (3-8) Dai
" the a
/4217
equired fr
shown in
ly man pow
applicatio
om Projec
table (3-8
wer for Sub
on steps &
ct Team
8), (3-9),
b contractor
& method
(3-10), (3
r
ds "
3-11),
70/144
Chapter 3
Ta
Table
able (3-10)
(3-9) Daily
Weekly m
" the a
/4218
y man powe
an power f
applicatio
er for self p
for self perf
on steps &
performed t
formed tim
& method
time card
e card
ds "
71/144
Cha
pter 3
TTable (3-111) Subcontr
" the a
/4219
ractor prod
applicatio
uctivity by
on steps &
location
& methodds "
72/144
Chapter 3
Tab
Table
ble (3-13) m
e (3-12) ma
man power
" the a
/4220
an power d
r estimation
applicatio
daily produc
n & actual q
on steps &
ction repor
quantity
& method
rt
ds "
73/144
Cha
pter 3
Tabble (3-14) mman power
" the a
/4221
distributio
applicatio
on by work
on steps &
package
& methodds "
74/144
Cha
pter 3
Taable (3-15)
" the a
/4222
Monthly St
applicatio
tatus log fo
on steps &
or manpowe
& method
er
ds "
75/144
Cha
• Eq Re18
pter 3
quipment
eports req8), (3-19)
t
uired for E
Table
Equipment
e (3-16) Da
" the a
/4223
t as we sh
aily Equipm
applicatio
hown in tab
ent time ca
on steps &
ble (3-16)
ard
& method
), (3-17),
ds "
(3-
76/144
Chapter 3
TTable (3-177) Equipme
" the a
/4224
nt distribut
applicatio
tion by wor
on steps &
rk package
& method
ds "
77/144
Chapter 3
Table (3--18) Month
" the a
/4225
ly Status lo
applicatio
og for Equip
on steps &
pment
& methodds "
78/144
Cha
pter 3
Table (3-199) Value of
" the a
/4226
f rent Equip
applicatio
pment by w
on steps &
work packag
& method
ge
ds "
79/144
Cha
• Rep
Re(3
pter 3
port
eports req3-22), (3-2
uired for D23)
Table (3
Different it
-20) log fo
" the a
/4227
tems as w
r Concrete
applicatio
we shown i
Casting
on steps &
n table (3
& method
-20), (3-2
ds "
21),
80/144
Cha
pter 3
Ta
Tab
able (3-21)
ble (3-22)
Report abo
Monitor Re
" the a
/4228
out Perform
eport for Fin
applicatio
mance by a
nishing item
on steps &
ctivity
m (masonry
& method
y)
ds "
81/144
Cha
pter 3
Tabble (3-23) CCost report
" the a
/4229
t include lab
applicatio
bor, Equipm
on steps &
ment and m
& method
material
ds "
82/144
Cha
3.1.5-
1. Req
• Thexpr
• Fix
• Fode
2. Flo
It dsho
pter 3
- Data R
quiremen
he finance xpenses onroject duri
xed asset
or fully depepartment
ow chart
describe thown in figu
Require
nts
departmenly the exng the mo
and the a
preciated at.
he processure (3-5)
Figure
ed From
ent gives tpenses heonth maxim
mount of
asset we p
s between
e (3-5) data
" the a
/4230
m Financ
the controe had the smum after
depreciate
put rent a
Finance te
a flow betw
applicatio
ce Depa
l departmsupported r 7 day of
ed per mo
mount wit
eam and o
ween Finan
on steps &
artment
ent the ex document the new m
onth.
th help of
other depa
ce team an
& method
t
xpenses nots-of the month.
procureme
artment as
nd other de
ds "
ot all
ent
s
partment
83/144
Cha
3. ForRep
pter 3
rms ports required for Di
Table (3-24
ifferent ite
4) Monthly
" the a
/4231
ems as we
Report for
applicatio
e shown in
r Finance de
on steps &
table (3-2
epartment
& method
24)
ds "
84/144
Cha
3.2-Ac
Nowtypthe
3.2.As
pter 3
ctual Co
w after wee of data cost cont
1- WBS s2- Expens3- Storag
1-WBS shown in T
ost Allo
e create thhow we altrol model
heet ses sheet
ge sheet
Sheet tTable (3-2
ocations
he model fllocate this in
templat25)
Table (3-2
" the a
/4232
s
for cost cos data in o
te form
25) WBS Sh
applicatio
ntrol and our model
m
heet Form
on steps &
we get the before we
& method
e differente summari
ds "
t ize
85/144
Cha
3.2
AfteWBupdlast
pter 3
.1.1-cli
er we get BS form wedate to thet invoice th
ient inv
the client e put the fe cost conthis shown
T
voices
invoices wfinal quanttrol we rep in Table (
Table (3-26
" the a
/4233
we start totity in the place the o(3-26)
6) Sample o
applicatio
o take the form of Wold quanti
of Client Inv
on steps &
data and WBS sheet
ty with ne
voice
& method
fill it into and in evew quantit
ds "
the ery
ty in
86/144
Cha
3.2
pter 3
.1.2-Va
In casevariatiquantitcolumn28)
ariation
e of approons activaty columnn in WBS f
Table (3-
Ta
ns Order
oved changate in WBS and we pform the v
27) Sample
ble (3-28)
" the a
/4234
r
ge order (vS form andput zero quvariation o
e of Cover f
Sample of
applicatio
variationsd put the nuantity in order show
for Variatio
Variation
on steps &
) we insernew quantcontract q
wn in table
on Order
& method
rt the tity in actuquantity e (3-27), (
ds "
ual
3-
87/144
Cha
3.2.2• DiW
pter 3
2- Expeirect expene put the
enses Snses Direct exp
Ta
Sheet te
panses in t
able (3-29)
" the a
/4235
emplate
that form
) Direct Exp
applicatio
e form
that show
penses she
on steps &
wn in table
eet forms
& method
(3-29)
ds "
88/144
Cha
• InW
pter 3
ndirect expe put the
penses indirect ex
Tabl
xpanses in
le (3-30) in
" the a
/4236
n that form
ndirect Exp
applicatio
m that sho
enses shee
on steps &
own in tab
et forms
& method
le (3-30)
ds "
89/144
Cha
3.2.3
Thewe this
pter 3
3-Finan
e finance d take this s shown in
nce Rep
departmendata and p
n table (3-
T
port
nts make tput it in th31).
Table (3-31
" the a
/4237
the report he expense
1) Finance R
applicatio
of monthes sheet if
Report form
on steps &
ly expensef it direct o
ms
& method
es for projor indirect
ds "
ject t
90/144
Cha
3.2.4
It is cor valshown
pter 3
4-Stora
ontain theue of workn in table (
Ta
age She
e deduct ok for sub c(3-32)
able (3-32)
eet tem
r increasecontractor
) Deduction
" the a
/4238
plate F
e value of m that will d
n /Increase
applicatio
orm
money if ideduct fro
e Storage S
on steps &
t material om expens
Sheet Form
& method
in store ases sheet t
ds "
area that
91/144
Cha
3.2.4
pter 3
4.1-Sto
The stothe stotake frFinanc
orage R
orage deporage thatrom ce departm
Ta
eport
partment s you dedu
ment that s
able (3-33)
" the a
/4239
sent monthuct from yo
shown in t
Storage Sh
applicatio
hly report our month
table (3-33
heet Form
on steps &
about thehly expens
3)
& method
e quantity ses that yo
ds "
in ou
92/144
Cha
3.3- HInform
1-yandtak
a-co
b-cocli
pter 3
How Do mation?
you must ed the subce less tha
- you increontractor a
- You deduolumn thatient.
You Ma?
equate betontractor n the subc
ease the qand the ad
uct from tht in case y
ake Sur
tween the invoice ascontractor
uantity of dd quantity
he sub conyou are su
Ta(client
" the a
/4240
re You A
quantity ys Shown inr so you ha
client till y putted in
ntractor core that yo
able (3-34)t/subcontr
applicatio
Are Get
you puttedn table (3-ave to two
it equivalen the prov
olumn in su will take
) equate ofractor) qua
on steps &
tting Go
d in the cl-34) in somo solutions
ent to the vision colum
storage shee this quan
f ntity
& method
ood
ient invoicme cases ys.
sub mn.
eet in dedntity from
ds "
ce you
uct the
93/144
Cha
2-ytoldthesupputincr
3-yconof squathe
pter 3
you must sd you wha project sh
ppler impot still you drease the
you must tncrete quasteel rebarantity of st same cas
sure that tt we paid hown in tart the statdon’t paid quantity o
take the suntity in clir as shownteel imporse of concr
Table
the quantit almost eqable (3-35tement de so you mof concrete
urvey of stient invoicn in table rted to therete
e (3-35) Co
" the a
/4241
ty of concqual to the) this hap
elayed so aust sure fre in storag
teel rebar ce you ma(3-36) als
e site and t
oncrete Cas
applicatio
rete in thee pouring lpen becauactually yorom this pge sheet
in case ofke this to
so you musthe quanti
sting Report
on steps &
e Finance og that youse some tou poured point in thi
f RFT incluget the acst sure thaity of stee
t
& method
report thaou take frotime the this quanis case you
ude in ctual losseat from thl in financ
ds "
at om
tity u
es e
ce it
94/144
Cha
4 - aquyoyode
5 - afin
6 - yty
7 - fdaan
pter 3
also you muantity in sou must mou take froecision
also you mnance repo
you must ype of work
final to maate to comnalysis
must trackstorage re
make someom them t
must trackort and nu
have repok package
ake sure ompare and
Tab
k and compeport and fe communthe inform
k and compumber of la
ort that Dise
of date you reach to t
ble (3-36) S
" the a
/4242
pare betwefinance reication betation to m
pare betweabor you g
stributed t
u must havthe accura
Steel losses
applicatio
een the daport and itween the
make sure
een the nuget from p
the non sk
ve greaterte data yo
s Report
on steps &
ate you han case of
e different and get th
umber of lproject
kill labor o
r than oneou based o
& method
ave like thany conflic party thathe final
labor from
n different
e source ofon it your
ds "
e ct t
m
t
f
95/144
Cha
4.1- T
In tmabelishowerwanfor,abilmo Simuseusesmaplottabnegschsch It mmame
Fi
pter 4
4- T
he Earn
the early ynagers weieved thatown in (Figre managinted costs, or reportlities to mment's no
mply put, e to monitoe is not limall and metting both le. Once u
gative variedule alonedule and
may very wking it unpasured sim
igure (4-1)
Techn
ned Val
years of prere havingt status cogure 4–1).ng costs os to be mted. Projeconitor and
otice. Earn
earned vaor, track,
mited just tedium size the projeused, the pances. Thne and mad that the
well be theprofitable.multaneou
iques
lue Mea
roject mang difficulty ould be det The critic
or just momanaged ct managed report aced value o
alue is a prand reportto the suped projectsct schedulproject mae project
ake the asproject is
e case tha This is w
usly to gain
" Tech
5/31
of ou
asureme
nagement determinitermined ocal questionitoring co rather th
ers need toccurately ooffers this
roject techt on the p
per projects. The techle and cosanager canmanager csumption doing wel
t the projehy both scn a more a
hniques o
utputs
ent Sys
, it becaming projectonly by a on was whosts. The han just o have theon their pr ability.
hnique thaerformancts, as it aphnique lenst values on very quicannot justhat projel.
ect is excechedule anaccurate p
of output
s & rep
stem (E
me evident t status. Smystical aether proj project mmonitorede necessarroject perf
at project mce of any ppplies equands itself ton an S-cuckly highlist measureect tasks a
eeding prond cost hapicture (se
ts & repor
ports
EVMS)
that projeSome peo
approach, ject managmanagers d, accountery tools anformance
managers project. Itally to boto jointly rve chart ight positive the projeare ahead
oject costsve to be
ee Figure 4
rts"
ect ople as gers ed
nd at a
can ts h
or ve or ect of
s,
4.2).
96/144
Cha
ThisEarplanvaluthema The
• a• E• E• B
The
• W• W• W• W• W
Figur
pter 4
s need resrned valuenning to ue manag primary tnagement
e EVMS p
accurate dEarly and aEarly and aBasis for c
e EVMS c
What is thWhat are tWhat can bWhat is thWhat are t
re (4-2)
sulted in the is a m schedulesement (EVtool for intt? Without
provides t
isplay of paccurate idaccurate idourse corr
an answe
e true statthe problebe done toe impact othe presen
he creatioanagemens and tecVM) is a sytegrating ct using the
the follow
project stadentificatidentificatirections
er the fol
tus of the ms? o fix the pof each pront and futu
" Tech
5/32
n of the Ent techniqchnical peystematic cost, schede EVMS, de
wing bene
atus on of trenon of prob
lowing qu
project?
roblems? oblem? ure risks?
hniques o
VMS. The que that erformance process thdule, and etermining
efits:
ds blems
uestions:
of output
basis for relates rese requiremhat uses etechnical g status ca
:
ts & repor
the EVMSsource ments. Eaearned valperformanan be diffic
rts"
.
arned ue as nce cult.
97/144
Chapter 4 " Techniques of outputs & reports"
5/33
4.1.1- Variance and Earned Value
The EVMS emphasizes prevention over cures by identifying and resolving problems early. The EVMS is an early warning system allowing for early identification of trends and variances from the plan. The EVMS provides an early warning system, thus allowing the project manager sufficient time to make course corrections in small increments. It is usually easier to correct small variances as opposed to large variances. Therefore, the EVMS should be used continuously throughout the project in order to detect the variances while they are small and possibly easy to correct. Large variances are more difficult to correct and run the risk that the cost to correct the large variance may displease management to the point where the project may be canceled.
A variance is defined as any schedule, technical performance, or cost deviation from a specific plan. Variances must be tracked and reported. They should be mitigated through corrective actions and not eliminated through a baseline change unless there is a good reason. Variances are used by all levels of management to verify the budgeting system and the scheduling system.
The budgeting and scheduling system variance must be compared because:
• The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.
• The scheduling variance provides a comparison between planned and actual
performance but does not include costs.
• Budgeted cost for work scheduled (BCWS) is the budgeted amount of cost for work scheduled to be accomplished in a given time period.
• Budget cost for work performed (BCWP) is the budgeted amount of cost for
completed work, within a given time period. This is sometimes referred to as “earned value".
• Actual cost for work performed (ACWP) is the amount reported as actually
expended in completing the work accomplished within a given time period. BCWS represents the time-phased budget plan against which performance is measured. For the total contract, BCWS is normally the negotiated contract plus the estimated cost of authorized but UN priced work.
It is time-phased by the assignment of budgets to scheduled increments of work. For any given time period, BCWS is determined at the cost account level by totaling budgets for all work packages, plus the budget for the portion of in-process work.
● Cost variance (CV) calculation:
CV = BCWP - ACWP
A negative variance indicates a cost-overrun condition.
● Schedule variance (SV) calculation:
98/144
Cha
S
A necostworpro
C
S
TheAs afirst$32alon
Howschesimform
Fig
pter 4
SV= BCWP
egative vart and schedrds, the schblem, the v
Cost varian
Schedule va
e schedule van examplet four week25K. Therefne, there ar
wever, if BCedule and oultaneously
mulae show
gure (4-3)
– BCWS
riance indicdule, costs hedule variavariances a
ce % (CVP
ariance % (
variance me, consider ks of the prfore, BCWSre several p
CWP is nowoverrunningy monitor a
wn in (Figur
cates a beh are used aance is givere usually c
) =CV/BCW
(SVP) =SV/
ay be repre a project troject. The S $400K andpossible ex
w known, sag costs Usiand control re 4.3).
" Tech
5/34
ind-schedus the lowesen as a funconverted t
WP
/BCWS
esented by hat is scheactual exped ACWP $3
xplanations
ay $300K, ang earned both sched
hniques o
ule conditiost commonction of costo percenta
hours, dayduled to spenditures a25K. From as to proje
and then thvalue, projdule and co
of output
n. In the an denominatst. To allevages:
ys, weeks, pend $100Kt the end o these two ect status.
he project isect manag
ost using th
ts & repor
nalysis of btor. In othe
viate this
or even doK for each oof week fou parameter
s behind ers are able
he set of
rts"
both er
llars. of the ur are rs
e to
99/144
Chapter 4 " Techniques of outputs & reports"
5/35
4.1.2- Methods for Physical Progressing (The 50-50 and 0–100 Rules)
Many project managers traditionally report project schedule progress by using an incremental estimation method. This method normally starts by estimating tasks at levels such as 15 percent, 40 percent, 78 percent, or 98 percent, incrementally moving forward until 100 percent complete.
This process is based on no proper quantitative measurement and is often inaccurate. Additionally, this information is, in turn, submitted to either the project office or executives to review, and perceptions at the senior level are based on inaccurate project data. Project managers could possibly consider adopting a more accurate method of reporting on project progress.
In the project world, two of these methods are the 50-50 and 0–100 rules. However, the 50-50 rule is more commonly used. The important thing to remember is to keep it simple .Remember that keeping the schedule variance simple on the progress reporting side makes calculating the EV easier to manage.
The way to implement the 50-50 rule is fairly straightforward.
• Assign 50 percent of the BCWP to the task the moment the task is started. At this point it is assumed that half the work has been done already.
• Assign 100 percent of the BCWP the moment the task ends. This is only allocated once the task actually finishes.
The cost variance relates to the real cost. However, the problem with SV is how it relates to the real schedule. The schedule variance is determined from cost account or work package financial numbers and does not necessarily relate to the real schedule. The schedule variance does not distinguish between critical path and non–critical path work packages.
The schedule variance by itself does not measure time. A negative schedule variance indicates a behind-schedule condition but does not mean that the critical path has slipped. On the contrary, the real schedule (i.e., precedence networks or the arrow diagramming networks) could indicate that the project will be ahead of schedule. A detailed analysis of the real schedule is still required irrespective of the value for the schedule variance.
Permitted variances may be dependent on such factors as:
• Life-cycle phase • Length of life-cycle phase • Length of project • Type of estimate • Accuracy of estimate
100/144
Chapter 4 " Techniques of outputs & reports"
5/36
By using both cost and schedule variance, we can develop an integrated cost/schedule reporting system that provides the basis for variance analysis by measuring cost performance in relation to work accomplished. This system ensures that both cost budgeting and performance scheduling are constructed on the same database. In addition to calculating the cost and schedule variances in terms of dollars or percentages, we also want to know how efficiently the work has been accomplished.
The formulas used to calculate the performance efficiency as a percentage of EV are:
Cost performance index (CPI) =BCWP/ACWP
Schedule performance index (SPI) =BCWP/BCWS
The difficulty in performing variance analysis is the calculation of BCWP because one must predict the percent complete.
The simplest formula for calculating BCWP is:
BCWP = (% complete) X BAC
Most people calculate “percent complete” based upon task durations. However, a more accurate representation would be to calculate “percent work complete.” However, this requires a schedule that is resource loaded. To eliminate this problem, many companies use standard dollar expenditures for the project, regardless of percent complete.
For example, we could say that 10 percent of the costs are to be “booked” for each 10 percent of the time interval. Another technique, and perhaps the most common, is the 50/50 rule: Half of the budget for each element is recorded at the time that the work is scheduled to begin, and the other half at the time that the work is scheduled to be completed.
For a project with a large number of elements, the amount of distortion from such a procedure is minimal. (Figures 4-4, 4-5 and 4–6 illustrate this technique.) One advantage of using the 50/50 rule is that it eliminates the necessity for the continuous determination of the percent complete.
However, if percent complete can be determined, then percent complete can be plotted against time expended, as shown in (Figure 4–6). There are techniques available other than the 50/50 rule:
• 0/100: Usually limited to work packages (activities) of small duration (i.e., less than one month). No value is earned until the activity is complete.
• Milestone: This is used for long work packages with associated interim milestones, or a functional group of activities with a milestone
101/144
Cha
emm
pter 4
establishedmilestone milestone
Figure (4-4)
d at identiis completrather tha
)
fied contrted. In thean the wor
" Tech
5/37
ol points. ese cases,rk package
hniques o
Value is e a budget es.
of output
earned whe is assigne
ts & repor
en the ed to the
rts"
102/144
Cha
• P(v
• Ee
Figure
pter 4
Percent c(i.e., threevalue earn
Equivalenearnings a
(4-5)
Figure (4
complete:e months oned would
nt units: re on com
4-6)
: Usuallyor more) w be the rep
Used formpleted un
" Tech
5/38
y invoked where mileported per
r multiple its, rather
hniques o
for long-destones carcent of th
similar-unr than labo
of output
uration woannot be idhe budget.
nit work paor.
ts & repor
ork packadentified. T
ackages, w
rts"
ges The
where
103/144
Cha
• Cd
• Loep
4.1.3-
Contha$66ove
• B• B• A• E
It is
• R
6
• C
6
Not56.$78thasign
pter 4
Cost formduration w
Level of often usedearned is bphysical pr
- Examp
nsider the t the Budg
60,000 corerall projec
Budget at Budget VaActual ValuEarned Va
s possible
Resource F
660,000–7
Cost Varia
621,280–7
te that $4048% prog
8,720 are t was schen indicates
Figure (4
mula (80/work packa
effort: d for supebased on trogressing
ple – Sy
case-examget Value rrespondinct provide
Completiolue (BV) =ue (AV) = lue (EV) =
to compu
Flow Varia
700,000 =
nce = EV
700,000 =
0,000 are gress, whethe costs eduled to s loss of v
-7)
/20): A ages.
This metervision antime (Figug
ynthetic
mple discuat 10 mon
ng to 60%s the follo
on (BAC) == BCWS = ACWP =
= BCWP =
te the var
nce = BV
–40,000$
– AV
–78,720$
the accouere the minthat will bbe performalue.
" Tech
5/39
variation o
thod is band managere 4-7) illu
c EVA
ussed thronth into th
% of progrewing:
= $1,100,0 $660,000$700,000 $621,280
riances of
– AV
$
$
unted extranus sign mbe consummed within
hniques o
of percent
ased on ement woustrates th
oughout thhe project ess. Recall
000 0 0
the overa
a costs comeans a loed to attan 10 mont
of output
t complete
the passark packaghree meth
his chapterwas scheding of the
ll project:
nsumed toss of mon
ain the 60%ths. Here a
ts & repor
e for long-
age of times. The va
hods for
r and suppduled to be figures fo
o reach ey. Althou
% progresalso the m
rts"
me, alue
pose e
or the
ugh, ss minus
104/144
Cha
Also
• S
ThavarcosSynsumma
Alsotim(daquiccorEarpretheind Thebelobetfrom Cloindeweishoagg
Figure (4-
pter 4
o, the sch
SV = 621,
at is exactriance. Thist than estnthetic calms of prognager for
o, resource/cost cha
ashed line ck graphicrective actrned Valueesented wi referenceicates the
e best caseow the EVtter than sm the PV o
se reasonexes: aggighted sumowing thatgregate SI
-8)
edule vari
280–660,0
ly the diffes tells tha
timated, asculation o
gress and ocommunic
ce, cost anart using Sin Fig. 4-8
cal understions to th
e S-curvesth Fig. 4-9e curve lin project is
e-scenarioV: in this ccheduled.one, the la
ing can beregate ind
m of activi the best c for a proj
ance is:
000 = –38
erence bett the projes well as $f varianceoverall valcation and
nd schedulS-curves o8) and BCWtanding of
he project s can have9. One mue: whethe
s over bud
o is the onase both t The morearger the l
e conductedexes can ty performcase-scenject are m
" Tech
5/310
8,720$
tween theect is cons$38,720 toes for the olues, is of
d rapid rep
e varianceof BCWS (dWP (solid f the proje strategy. e six possibust look at er the AV oget or is b
e where bthe cost ane the distaloss or gai
ed for Cost be obtainemance indeario is wh
more than 1
hniques o
cost and suming $4o perform overall pro great conporting.
es can be dotted lineline in Fig
ect status Planned (ble arrang the positior the PV abehind sch
both the AVnd the durance of thein of value
t and Scheed for the exes. (Figuen both th1.
of output
the resou40,000 as the schedoject, usinvenience t
representee in Fig. 4-. 4-8). Thfor suggesScheduledements, aion of the above the
hedule.
V and the ration are e AV and Be and sche
edule perf overall prure 4-10) he aggrega
ts & repor
rce flow more actu
dule delay.g weighteto the pro
ed in a -8), ACWPis enablesstion of gld), Actual as in the c EV S-curv EV curve
BV curves performinBV curve liedule.
formance roject by is a chart ate CI and
rts"
ual . d ject
P s a obal and hart ve as
s are ng ines
d
105/144
Cha
Whinfoissuof tdetaboin f
Earscha siTheis wrec
pter 4
ereas a syormation oues, analythe job statailed repoout the pafinding out
rned valueedule delaimilar situe Cost Varworth notinording a p
ynthetic reoverload totic EVA pr
atus throuort based orts of a jot why the j
e (EV). Foray, with mation, whe
riance Repng that thepositive va
eport of tho direct throvides gregh investion activityb that arejob is in it
r example,more seriouere scheduort for thee activity “
alue of the
Figure (4
" Tech
5/311
e overall phe project’eater detagation of i
y breakdow behind scts current
, A1 indicaus problemule delay ie example“Columns RV. This
4-9) graphica
hniques o
project pes decisionils to allowindividual wn informschedule anstatus.
ates both cms on costs more sig-project is procuremis pretty t
al project sta
of output
erformance-makers tw a better activity pes the projend over bu
cost overrt than on sgnificant ts given in
ment” is thericky: inde
atus
ts & repor
e prevent to the maj understanerformancect managudget and
uns and schedule. han extra (Table 4.1e only oneeed, that t
rts"
from or nding ce. A ger helps
A2 is cost 1). It e task
106/144
Cha
is tan
Dela wprowoupro
pter 4
he one witincreased
ay. The rewhole: it seovide mateuld have b
oject team
Figur
th the bigg unit cost
eason mayeems that erials up tobeen highl tightly wo
Table (4
re (4-10)
gest probland a sch
y be found the pre-co a 49% oighted theork with th
-1)
" Tech
5/312
ems (a needule
d in the proast colum
of units. A e supply prhe supplie
hniques o
egative CV
ocuremenns manufatimely perroblem ahr and avoi
of output
V of $43,20
t process acturer storformanceead of timid the inco
ts & repor
00) with b
of columnopped to e reportingme to haveonveniency
rts"
both
ns as
g e the y.
107/144
Chapter 4 " Techniques of outputs & reports"
5/313
4.2–Reporting Techniques
4.2.1- Report Content
The program team member may receive a team critical variance report that lists variances in his organization at the lowest level of the work breakdown structure at the division cost center level by cost element. Upon request of the program manager, analyses of variances contributing to the variances on the team critical variance report are summarized by the responsible program team member and reviewed with the program manager. The preparation of status reports, whether they are for internal management or for the customer, should, at minimum, answer fundamental questions: • Where are we today (with respect to time and cost)? • Where will we end up (with respect to time and cost)? • What is the problem causing the variance? • What is the impact on time, cost, and performance? • What is the impact on other efforts, if any? • What corrective action is planned or under way? • What are the expected results of the corrective action?
The information necessary to answer these questions can be obtained from the following formulas:
• Budgeted cost for work scheduled (BCWS) • Budgeted cost for work performed (BCWP) • Actual cost for work performed (ACWP) • Estimated cost at completion • Budgeted cost at completion • Cost and schedule variances/explanations • Traceability • Percent complete • Percent money spent • Estimate at completion (EAC) • the remaining critical path • SPI (trend analysis) • CPI (trend analysis)
108/144
Chapter 4 " Techniques of outputs & reports"
5/314
We can use CPI and SPI to forecast the expected final cost and the expected end date of the project. We can express the cost at completion, EAC, as:
EAC =BAC/CPI The time at completion uses SPI for the forecast and can be expressed as: ETC New project length = original project length/SPI
Care must be taken with the use of SPI to calculate the new project length because a favorable vale for SPI (i.e., 1.0) could be the result of work packages that are not on the critical path. Once EAC and the new project length are calculated, we can calculate the variance at completion (VAC) and the estimated cost to complete (ETC) using the following two formulas:
VAC = BAC - EAC and ETC = EAC – ACWP Percent complete and percent money spent can be obtained from the following formulas:
Percent complete =BCWP/BAC Percent money spent =ACWP/BAC
Where BAC is the budget at completion. The program manager uses this information to review the program status with upper level management. This review is normally on a monthly basis on large projects.
4.2.2- Reporting Considerations
As you prepare reports, use the following guidelines: Maintain concise, top-quality project plans and status reports. Be sure everything you publish is accurate. Keep all stakeholders appropriately informed, including team members, customers, clients, functional managers, and senior management. Determine for each audience what information they need to perform their functions and design reports accordingly. Keep them informed—but not over-informed—with the information they need to make decisions and take corrective action. Use exception reporting by including only major variations from the plan. Stakeholders don’t have time to digest pages and pages of project information, and there is little need to report on items where status matches the plans. Use software programs to analyze project information and report on variances from the project plans. Establish problem-reporting thresholds. Determine how significant a variation from the plan needs to be before you report on it. For example, establish thresholds for how many dollars over budget or how many days late. Choose the best format for the report, such as a table, line graph, histogram, or bar or Gantt chart. On each report, clearly state the purpose of the report and the action to be taken.
109/144
Chapter 4 " Techniques of outputs & reports"
5/315
4.2.3- SAMPLE REPORTS
1. STATUS REPORTING
One of the best ways of reducing executive meddling on projects is to provide executives with frequent, meaningful status reports. Figure 4–11 shows a relatively simple status report based upon data accumulation in the form of Figures 4–12, 4–13, 4-14 and 4-15. These types of status reports should be short and concise, containing pertinent information only. Status can also be shown graphically. As the available project management software becomes more sophisticated, so does project reporting. There are four types of reports that are generally printed out from the earned value measurement system: • Performance Reports: These reports indicate the physical progress to
date, namely, BCWS, BCWP, and ACWP. The report might also include information on material procurement, delivery, and usage, but most companies have separate reports on materials.
• Status Reports: These reports identify where we are today and use the information from the performance reports to calculate SV and CV.
• Projection Reports: These reports calculate EAC, ETC, SPI, and CPI as
well as any other forward-looking projections. These reports emphasize where we will end up.
• Exception Reports: These reports identify exceptions, problems, or situations that exceed the threshold limits on such items as variances, cash flow, resources assigned, and other such topics. Reporting procedures for variance analysis should be as brief as possible. The reason for this is simple: the shorter and more concise the report, the faster that feedback can be generated and responses developed. Time is critical if rescheduling must be accomplished with limited resources. The two most common situations providing constraints on resource rescheduling are that:
⎯ The end date is fixed
⎯ The resources available are constant (or limited) With a fixed end date, program rescheduling generally requires that additional resources be supplied. In the second situation, program slippage may be the only alternative unless a constant stream of resources can be redistributed so as to shorten the length of the critical path. Once the variance analysis is completed, both project and functional management must diagnose the problem and search for corrective actions. This includes: finding the cure for the problem & developing a plan to recover the position
110/144
Chapter 4
Figure (4-13)
Figure (4-1
" Tech
5/317
14) Performa
hniques o
ance Report
of outputts & reporrts"
112/144
Cha
2. VarAs
pter 4
riance anshown in t
F
nalysis table (4-2
Figure (4-15
Table (4-2
), (4-3)
) Progress T
2) Variance
" Tech
5/318
Trends Repor
analysis Rep
hniques o
rt
port
of outputts & repor
rts"
113/144
Cha
3. CO
Thescha g • C
• C Therep
pter 4
ST SUMM
e simple spedule repoiven perio
Cumulativ
The spreashows cumcompletio
Cumulativ
e report inport, but in
MARY
preadsheeorts, but p
od.
ve Cost R
adsheet in mulative cn of the p
ve Cost L
Figure 4-n graphica
Tab
et in Figureprovides fi
Report.
Figure 4-costs to daroject.
Line Graph
-19 shows l form.
ble (4-3) Ove
" Tech
5/319
e 4-16 listnancial da
17, 4-18 iate and the
h
the same
erall Progres
hniques o
ts the samata (rather
s similar te anticipat
informati
ss Report
of output
me steps asr than sch
to the costted total c
on as the
ts & repor
s the prevedule data
t report bucosts at the
previous
rts"
ious a) for
ut e
114/144
Chapter 4
Figure (4-18) Cu
" Tech
5/321
umulative co
hniques o
ost report
of outputts & reporrts"
116/144
Cha
4. SCH
Becplanrepactand • S Thethesteinfo
pter 4
HEDULE S
cause evern, a projec
port on proivities are d actual st
Summary
e chart in F individuaps. This reormation.
Figure (4-19
SUMMARY
ryone invoct manageogress thro completeart and Fi
Schedule
Figure 4-1l activitieseport is se It is also
9)
Y
olved with er may deoughout thd, solid linnish dates
Status Re
12,4-13 is s have beeent to recip called a m
" Tech
5/322
the projeccide to usehe life of tnes are dras appear in
eport
identical ten removepients whomilestone s
hniques o
ct is famile the samthe projectawn throun the appr
to the chaed, leavingo only requschedule a
of output
iar with the chart tot (see Figugh the gra
ropriate co
rt in Figurg only the uire summas seen in
ts & repor
he baseline monitor aure 4-11). ay activityolumns.
re 4-11 exsummary
mary figure 4-1
rts"
e and As
y bars
xcept
14.
117/144
Cha
Figure (4
Figure (
F
pter 4
4-20)
(4-21)
Figure (4-22) Weeks Staatus Perform
" Tech
5/323
ance
hniques oof outputts & reporrts"
118/144
Cha
5. Ins
Reprepone
.
pter 4
structions
ports are mport and the company
Figure (4-2
s on Repo
most helpfhe action ry division t
Figure (4-2
4)
orts
ful when trequested.to another
3) millstone
" Tech
5/324
hey clearly Consider r.
s Summary
hniques o
y explain t the repor
report
of output
the purposrt in Figure
ts & repor
se of the e 4-15 from
rts"
m
119/144
Cha
6. Exc
ExcplanPercomreq
pter 4
ception &
ception repn as showrcent compmpleted onuired for t
Figure
& note Re
port a repwn in Figureplete. A mn an activithe activity
e (4-25)
Figure
port
port that se 4-16, 4-ethod of rty is exprey
e (4-26) note
" Tech
5/325
hows only-17 and 4-reporting wessed as a
e on perform
hniques o
y major de-18 ratherwhere the a percent o
mance report
of output
eviations frr than all d amount oof the tota
t
ts & repor
rom the pdeviations.of work al work
rts"
roject .
120/144
Cha
7. GR
It isrepwheThis A spagsignGrered
pter 4
RAPHICAL
s importanports contaether the s is particu
imple pie ge full of tenal as a vieen means.
Figure
L REPORT
nt to makeain only threports caularly usef
chart or liext or numisual indicas the proje
Figur
(4-28)
TS
e reports ee informa
an be furthful in sum
ne graph mbers. Somator of proect is on tr
e (4-27) Crit
" Tech
5/326
easy to reation neede
her simplifmary repo
may be mme reportoject staturack, yello
tical Issues
hniques o
ad. The fired by the fied by conorts sent t
much easies use the
us (see Figow indicate
Report
of output
rst step is recipient.
nverting dato upper m
r to interpsymbol of
gure 4-19,es minor t
ts & repor
to be sure Next, detata to gra
manageme
pret than af a traffics 4-20 & 4rouble, an
rts"
e ermine phics.
ent.
a -21).
nd
121/144
Cha
pter 4
Figure (4-29
Figure (4-3
9) Project Pe
30) Project P
" Tech
5/327
erformance m
Performance
hniques o
metric Defin
report
of output
itions
ts & reporrts"
122/144
Cha
8. Oth As
pter 4
her Form shown in
of Repor figure 4-2
rt 22
" Tech
5/328
hniques oof outputts & reporrts"
123/144
Cha
pter 4
Figure (44-31) Sampl
" Tech
5/329
e of other Re
hniques o
eport
of outputts & reporrts"
124/144
Chapter 4 " Techniques of outputs & reports"
5/330
4.2.4- Responses on Reports
This by no means implies that all variances require corrective action. There are four major responses to a variance report:
• Ignoring it.
• Functional modification.
• Re planning.
• System redesign Permissible variances exist for all levels of the organization. If the variance is within these permitted deviations, then there will be no response, and the variance may be ignored.
In some situations where the variance is marginal (or even within limits), corrective action may be required. To avoid dual standards and red tape, management must establish the decision-making policies associated with cost and control systems. The following is a policy guide.
• Approving all estimates, and negotiating all estimates and the definition
of work requirements with the respective organizations.
• Approving the budget, and directing distribution and budgeting of available funds to all organizational levels by program element.
• Defining the work required and the schedule.
• Authorizing work release. The manager may not, however, authorize
work beyond the scope of the contract.
• Approving the program bill-of-materials, detailed plans, and program schedules for need and compliance with program requirements.
• Approving the procuring work statement, the schedules, the source selection,
the negotiated price, and the type of contract on major procurement.
• Monitoring the functional requirements.
• When cost performance is unacceptable, taking appropriate action with the affected organization to modify the work requirements or to stimulate corrective action within the functional organization so as to reduce cost without changing the contracted scope of work.
• Being responsible for all communications and policy matters on
contracted pro- grams so that no communicative directives shall be issued without the signature or concurrence of the program manager.
125/144
Chapter 4 " Techniques of outputs & reports"
5/331
4.3– Construction Cost Control Software
Project control software enables real-time and historic job and project cost management designed for use by your operational teams. Project control provides performance indicators on all project cost areas providing valuable insight to make quick decisions resulting in profit margin increases on every job. Centralization of key information provides collaboration and reporting across multiple jobs, projects and organizational departments. The project control system is outside the company’s sensitive accounting system providing the flexibility and manipulation capabilities required for testing alternatives and maximizing profit outcomes. Project control provides integration to over 50 different accounting systems, out of the box, which eliminates re-entry of data between systems saving personnel time and eliminating reproduction errors. Although many construction companies are still using spreadsheets and shoeboxes to manage their projects, the use of industry-specific project management software is becoming more prevalent. One reason for this is that more construction software providers are developing integrated project management modules to compete with the leading stand-alone project management systems. In my experience, there are two important aspects of cost management that separate it from the other project management functions. The first is that each firm has a very specific way that they do it and a very specific set of terms that they apply. It would be difficult to apply a pre-defined practice and a canned program, out of the box, that would satisfy the firm’s accounting requirements. We need only look at the Enterprise Resource Planning (ERP) applications to see the effect of this situation. Firms such as Oracle, PeopleSoft, Baan, SAP, and J.D. Edwards sell project financial management systems for several hundred thousand dollars (or more) and then charge that much again to tweak the system to the client’s specific needs. now let's see some kind of cost control software like, Project Costing System (PCS), Construction Industry Software (COINS), and WinQS. The general purpose Microsoft Excel spreadsheet is also used by some professionals. In fact, the largest option is Bespoke/in-house Systems, which is used by 29% of contractors and 38% consultants in UK. Software packages used for project cost control in UK
Contractors Consultants
Bespoke/in-house Systems 29% 38%
Microsoft Project 20% 32%
Project Costing System (PCS) 15% 11%
Asta Power Project 15% 5%
Primavera SureTrak 8% 5%
Microsoft Excel 7% 3%
COINS 5% 3%
126/144
Chapter 4 " Techniques of outputs & reports"
5/332
4.3.1- Advantages of Used Software in Construction Cost Control
1- Timesheets and Time Management Tracking
Enter timesheets and daily diary information for projects from wherever they happen to be. Record hours worked by cost code, quantities completed, and daily diary notes, and synch that information with the home office using a laptop or handheld device. Analyze fresh data to optimize resources for the next day and provide real-time integration with accounting to accelerate cash flow for faster project billing.
2- Direct Accounting Integration
Collect and store timesheet data from jobsites, while sharing data electronically with accounting systems to eliminate double entry. Maintain time sheet standards with labor classifications, and other user defined tags. Import timesheet data from third-party systems or to any accounting system. Record notes for each cost item including assumptions, jobsite observations, and more. Increase communication for issues that include staging and additional information to the field operators. Provides crew based timesheets with pre-defined data streamlining foreman or supervisor completion.
3- Field Resource Tracking
Manage field resources efficiently. Analyze information about productivity and accurately track customer information including account status, equipment usage and service history. Easily make changes when a resource is identified with high performance. Ownership costs and operation costs can include information on depreciation, insurance, and other unique resource costs in order to determine true ownership cost as well as operational use cost.
4- Anywhere Project Analysis
Web-based reporting and dashboards make it easy to get information from anywhere. Meet with customers on-site to discuss projects with total access to historical information, as well as the ability to develop preliminary budget estimates for project or job budget creation on the fly. Eliminate printing unnecessary reports by remotely focusing what the customer is looking for.
5- Provide Progress, Resource and "Actual Cost" Updates
Updating Software with data from your other systems is easy when using the Software API. The Software API (Application Programming Interface) provides an automated method for updating Software with data from other systems to create new records, update existing records, or delete records automatically. By extracting the data from your other systems into an XML format supported by Software and submitting the XML data, Software will “listen” for the data and automatically update the appropriate projects. Currently, the Software API supports two types of data, Resource Rates and Job Tracking Details.
127/144
Chapter 4 " Techniques of outputs & reports"
5/333
6- Monitor "Actual" Project Costs without Accounting Delays
Stay up to speed on job and project progress on a daily basis without waiting for accounting information. Preliminary and actual cost data is available daily to assess the need to make potential changes while there's still time to have an impact on the project's success and gross profit margin. Recognize time and other valuable information the moment it is entered without waiting for accounting and not having to re-enter data into multiple systems.
7- Remote Time Management Tracking
Control and monitor vendor commitments and activity, including original contract project components, insurance and bond monitoring status, change orders, invoices, requisitions, retention processing, and payments.
8- Collaboration and Updates
Save valuable man-hours eliminating the need to hand off estimates from one team member to the next. Allow last-minute updates until the bid is due, leveraging last minute pricing changes on materials and resources, while allowing multiple estimators to work on a single, or multiple estimates simultaneously.
9- Remote Data Access
Save gas, time and frustration by accessing information from anywhere including the office, remote offices, home, or client sites. Leverage un-tethered information access with synchronization, putting everything at your fingertips without being connected to the internet or network. Updates are entered throughout the day into a laptop or handheld device, and when convenient, a connection is made to the network to receive and send changes. Entry straight from the field eliminates duplicate data entry into numerous systems. Provide remote project access to managers, foremen and superintendents providing complete access to critical information needed to manage jobs remotely in one central location. Track cost and productivity positions of projects, responsibilities of team members, related documents, and ongoing project activities.
10- Centralize Project Information
Eliminate storing project information on local drives and multiple network locations. Project job tracking data is conveniently stored in one location and shared for easy access to all team members. Multi-office estimating provides synchronization between team members to accommodate real-time estimation updates.
128/144
Chapter 4 " Techniques of outputs & reports"
5/334
11- You can access it from anywhere
To many people, the biggest advantage of cloud software is that it’s truly available on any computer or device anywhere in the world. This is particularly useful when the project team members are in the office, in the field and in a variety of geographical locations. There’s no hassle with synchronizing data or uploading changes to a centralized server. Everything is centralized already – so collaboration is built-in. You no longer face moments of not knowing if you’re looking at the most up-to-date version of a report; or those crushing times when you’re on your way to a customer meeting and, whoops, the report you need is on Dave’s laptop and, too bad, Dave’s in Mexico this week. Everything’s connected, integrated and constantly current
With Construction Cost Control Software solution you will have greater access to the following information:
Which materials are due during this week, and which ones are still on back order?
What's our profit margin for all approved change orders? Which change orders are pending on this project? We haven't received the new design changes for the final phase. When
was the last time we requested this information? Our actual labor hours are about the same as the original estimated
hours and yet we're not finished. Where can I find the "projected to complete" hours?
How many downtime hours (non productive time) did we accumulate last year? Are we doing any better this year?
Now that this project is complete, are all vendor invoices accounted for? I don't want to be blindsided with any "surprise billings" later on.
The bonding company is asking for future receivables, unbilled contract dollars, work-in-progress, contracts won but not started, current retained dollars, budgeted hours remaining on projects, and more. Is there one source that pulls all this information together?
Which workers have been assigned tools and equipment on this project? What's our percent complete vs. percent billed – can we do another
progress bill? What are the committed dollars remaining on this project? Can we attach job site pictures to the project so we can look at them
during our meeting with the owner? What's our total cost on returned materials for this project? Which items
were returned to the vendors for credit and which were returned to inventory?
129/144
Chapter 4 " Techniques of outputs & reports"
5/335
4.3.3- The Disadvantages of Software in Construction Cost Control
1- Disadvantages in Percentage-of-Completion
Points to problems in the percentage-of-completion method as a distinct
disadvantage of cost control. This method, used to estimate costs under
cost control, uses a mathematical formula to determine how much of a
project a company can finish in a period, usually a financial quarter or
year. Percentage-of-completion is based entirely upon estimation,
meaning gross differences may occur between projected goals and
actual achievement, giving rise to misleading figures in cost control
analysis. Furthermore, the government may elect to tax a company
based on estimated percentage-of-completion rather than actual
completion rates. If significant disparities arise between estimates and
actual completion, companies suffer tax problems.
2- Disadvantages in Interlocking Systems
Bhabatosh Banerjee, author of "Cost Accounting Theory And Practice,"
points to problems in interlocking cost control systems. These systems
create cost control budget estimates and actual totals for different
aspects of a company's business and production. The disadvantage of
this lies in bookkeeping methods. If a single cost or expenditure applies
to two areas of a company with separate cost control budgets, that cost
or expenditure appears twice in the company's books.
3- Mismanagement of Cost Control
Mismanagement in cost control can lead to severe problems for
companies. For instance, cost control requires the consideration of a
broad palette of variables. If a company uses the wrong variables in
creating estimates for cost control or when creating figures displaying
total expenditure and total profit, the system produces widely inaccurate
figures regarding the cost effectiveness of procedures and processes.
What's more, human error may lead to severe inaccuracies -- all
employees involved in the process of calculating cost control, which
includes managers, foremen and more, must understand the system and
its requisite procedures
130/144
Chapter 5 " Conclusions "
/51
5- Conclusions
5.1- Common Causes of Cost Control Problems
1. Poor budgeting practices, such as basing the estimates on vague information from similar projects rather than the detailed specifications of the project at hand.
2. Failure to plan sufficient contingency budget.
3. Failure to correctly estimate research and development activities.
4. Failure to consider the effects of inflation on the cost of materials or labor.
5. Receiving or analyzing status information too late to take corrective action.
6. A climate that does not support open and honest disclosure of information.
7. Indiscriminate use of the contingency budget by activities that overrun their budgeted cost.
8. Failure to re budget when flaws are discovered, technical performance
falls below performance standards, or changes in project scope are approved. During the course of the project.
9. Many small decisions are made that ultimately impact costs. For
example, when engineering decides on the final design of a product feature, conventional accounting reports may not show the impact of these design decisions on production costs. In that case, the project manager must make sure that the cost impact is known before such decisions are made.
10. Weather conditions: Weather is probably the most common and
most obvious reason for work slowdown resulting in cost overruns. Work proceeds much more slowly under adverse weather conditions, and such conditions can impact the quality of the work as well.
11. Quality of the workforce: As a general contractor who hires
subcontractors, you don’t really have any control over the subcontractors’ workforce. Therefore, you have to trust that your subcontractors will provide experienced workers on your job. This is why, in my opinion, all subcontractors should be prequalified.
The risks associated with poor work quality are significant. If there is a problem, the poor quality will result in rework, and rework slows down job progress and can impact safety. The potential losses due to poor quality can put the entire project in a tailspin, and if this occurs, the project manager must take immediate steps to mitigate the situation.
131/144
Chapter 5 " Conclusions "
/52
12. Quality of the supervision: Obviously, if you don’t have proper supervision on the job, there are going to be problems. Many issues have to be addressed every single day on the job, and everyone looks to the superintendent for direction and clarification regarding those issues. If you have an inexperienced superintendent who is not up to speed on the project, the type of work, or the systems in place to manage the project, you are going to have a disaster, plain and simple. As I’ve said before, this is why good superintendents are worth their weight in gold.
13. Incorrect sequencing of work: Unfortunately, there are times
when pressure from an owner or from the main office can cause a superintendent to schedule work out of sequence and before it is ready, just to appease some unrealistic demand for action. But no one knows better than the superintendent and the field personnel how the work needs to be scheduled to keep things on track. Sometimes a work activity is initiated just to give the appearance of making progress when in reality these artificial starts just waste time and cause all kinds of havoc on the job. If this occurs too often, the inefficiencies will eventually show up and expose the real story.
14. Change orders: Change orders can be one of the most insidious
factors influencing project performances. A little change here or there often seems like no big deal. Many contractors fail to ask for additional time when they process the cost of the change, thinking that they can wiggle the extra work into the existing schedule. Then all of a sudden, these seven or eight little change orders are causing the job to run two weeks behind, and then it is a big deal!
15. Overcrowded job site: One of the things that can actually hinder
work productivity is having too many people on the job. I have heard more than one subcontractor complain about packing too many workers in tight quarters trying to get a job done. It becomes so counterproductive that it actually slows down the job instead of speeding it up as planned.
16. Defective materials: Discovering that the material or equipment
that you were planning to install is defective is a real problem. It is certainly one that can be avoided with proper quality control. But in some cases, this defective material is not discovered until the workers are on the job ready to start the project. By this time, it is way too late. The time has already been wasted, and it will take time to reorder the material and reschedule the crews to install it.
132/144
Chapter 5 " Conclusions "
/53
17. Inadequate tools and equipment: Having the right tools and equipment on a construction job may seem like a no-brainer. But again, when so much of the work of the contract is passed on to subcontractors, you don’t always have control over even these simple aspects of the job. I can’t tell you how many times I have seen work installed improperly because the craftspeople didn’t have the right piece of equipment
18. Late deliveries: Late deliveries are probably one of the most
frustrating causes of schedule delays and cost growth in construction. Once again, the contractor has very little influence or control over the manufacturing or fabrication processes involved in the making of many of the products or equipment used on the project. However, the stakes can be very high for the project if items arrive late. That’s why on projects with critical lead- time items, it is best to assign someone to do nothing but expedite deliveries and stay on top of the project buyout schedule.
19. Subcontractors Risks: Sometimes a subcontractor reneges on a
price before the subcontract is executed. When this happens, the general contractor has three options: contact one of the other original bidders and try to negotiate a price that both parties can live with; rebid the section of work altogether; or go out and negotiate on the open market, trying to secure the original pricing or better.
The most difficult situation to remedy is when a subcontractor gets into financial trouble and goes out of business before the job is complete. When this happens, it puts the project in a real tailspin, especially if the subcontractor in trouble ends up being one of your primary subcontractors such as steel or mechanical. Often the bonding company will step in and provide another specialty contractor to complete the work, but you can imagine what this sort of disruption does to the schedule and therefore the budget. The ramifications can be severe, and there may be no recovery from the damages. During a crisis like this, it is best for the owner, the contractor, and the architect to sit down and come up with a plan to mitigate the potential losses for everyone.
20. Quantity errors: When a simple quantity takeoff error into our
budget calculations. When this happens, it is best to find the error as soon as possible, preferably before you has committed to any purchase order or subcontract. If you find the error before committing to any pricing, you still have time to go out and negotiate your very best deal on the affected materials and labor in an effort to mitigate the obvious loss that you will suffer because of the inaccurate takeoff.
133/144
Chapter 5 " Conclusions "
/54
21. Labor expenses are exceeding budget: The cause of this problem may be that phases are taking longer than estimated. Several actions should be taken:
22. Variable expenses are exceeding budgeted levels: This may occur because original assumptions were wrong or because you are not exercising enough control over spending. Consider these actions:
23. Out-of-sequence starting and completion of activities and events.
24. Inadequate work breakdown structure.
25. No management policy on reporting and control practices.
26. Poor work definition at the lower levels of the organization.
27. Management reducing budgets or bids to be competitive or to eliminate “fat”.
28. Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort
29. Poor comparison of actual and planned costs
30. Comparison of actual and planned costs at the wrong level of management.
31. Unforeseen technical problems.
32. Schedule delays that require overtime or idle time costing.
33. Material escalation factors those are unrealistic.
5.2-Keys to Effective Project Cost Control Effective project cost management is an extremely complex process that begins very early during a project life cycle, and long before its actual start. Among the factors that influence success is a reasonable and accurate system for estimating costs. Highlights some of the most important considerations when creating a cost management system.
1. A clear, complete, of the project and the scope of work involved.
2. A thorough assessment of the potential risks involved, with well
thought- out action plans to minimize their possible impact
3. A well-trained and competent project manager
4. A thorough understanding, by all stakeholders, of the various types of costs that are likely to be incurred throughout the life of the project
5. A project organizational culture where there is a free flow of
communication, so that all project participants clearly understand their responsibilities
134/144
Chapter 5 " Conclusions "
/55
6. A well-defined project work structure where work packages are broken down into manageable sizes
7. Meaningful budgets, where each work package is allocated its
appropriate share of the total budget, adequate to the work involved
8. An accounting system and coding scheme that are well aligned with
the work breakdown structure and are compatible with the organization’s management information system
9. A cost accounting system that will accumulate costs and allocate
them to their relevant cost accounts as and when they are incurred
10.A prioritized and detailed work schedule, drawn from the work breakdown structure, which assigns and tracks the progress of individual tasks
11.Effective management of well-motivated staff, to ensure that
progress meets the work schedule
12.A mechanism for comparing actual and planned expenditures for individual tasks, with the results extrapolated to cover the entire project
13.The ability to bring critical tasks that are late back on schedule,
including providing for additional resources or taking other prompt remedial measures
14.Adequate and effective supervision to ensure that all activities are
done right the first time
15.Supervision of staff time sheets so that only legal times are booked to various cost codes
16.Proper drafting of specifications and contracts
17.Careful investigation to confirm that the customer is of sound
financial standing, with sufficient funds to make all contracted payments
18.Similar investigation, though not necessarily as discreet, of all
significant suppliers and subcontractors (especially those new to the contractor’s experience)
19.Effective use of competitive tendering for all purchases and
subcontractors to ensure the lowest cost adequate with quality and to avoid committing to costs that exceed estimates and budgets
20.Proper consideration and control of modifications and contract
variations, including charging all justifiable claims for price increases to the customer
135/144
Gathering supporting document
Create cost Control model
Collect Current Cost data
Actual Cost Allocations
Analysis data with EV
Reporting
Decision making
Cost Control Processes for Construction Project
Basic Process of Cost Control in Construction Project
Level 1
Level 2
Level 3
Level 4
Level 5
Level 6
Level 7
1/7
136/144
Baseline Contract Document
Contract ofSub Contractor
Time Baseline Cash flow Baseline BOQ Drawings Specification
Level 1Gathering supporting
document
Estimated Budget
Direct Cost Indirect Cost/ Overhead
2/7
137/144
From BOQ, Budget Estimation, Sub
contractor, supplier contract
Create WBS
Fixed AssetSheet
Deprecations system
Expenses Sheet
Storage Sheet
Coding system
Develo
p
cost
Contro
l m
odel
Level 2 Create cost Control model
3/7
138/144
Finances Department Report
Storage Department Report
Technical Office Report
Material Expenses Labor Expenses Other Expenses Material storage
Report
Concrete pouring logVariations orderClient Invoices/
SubcontractorLabor number & allocation report
Quantity survey according to shop drawing
Equipment Expenses
Level 3Collect Current Cost data
4/7
139/144
Cost Control model
fixed assets sheet
WBS sheet Expenses sheet
Storage sheet
Technical Office Report
Equipment Expanses according to
Deprecations system
All Expenses Report
Subcontractor Invoices
Storage Report
Level 4
Client Invoices
Finances Department
Report
Finances Department
Report
Material storage Report
Actual Cost Allocations
5/7
140/144
Earned Value Rule Earned Value Parameter
Earned Value Analysis
Earned Value Report
Analysis Data with Earned ValueLevel 5
6/7
141/144
Project Summery original/update
Payment status according to client
invoice
Analysis of WBS Reason of profit or loose
Time Mony Direct Indirect
Decision making
Forecasting
ReportingLevel 6,7
7/7
142/144
References [1] Preparing for the Project Management Professional (PMP) Certification Exam Second Edition Michael W. Newell, PMP, ENP, pp. (25-30) & (77-102) [2] Project management step-by-step / Larry Richman pp.(49-51),(136-143)&(153,165) [3] Project Management Nation—Tools, Techniques, and Goals for the New and Practicing IT Project manager by Jason Charvat Copyright? 2002 by John Wiley & Sons, Inc., New York. (Chapter 7 - Controlling the Project) [4] Construction management jumpstart Second Edition by Barbara J. Jackson Copyright © 2010 by Wiley Publishing, Inc., Indianapolis, Indiana pp. (140-168) & (260-280) [5] Cost and Value Management in Projects. Ray R. Venkataraman and Jeffrey K. Pinto Copyright @2008 John Wiley & Sons, Inc. pp.(32-38),(43-56) ,(105-114) & (127-148) [6] Fundamentals of Project Management Third Edition by JAMES P. LEWIS [7] Practical Project Management Tips, Tactics, and Tools by Harvey A. Levine Copyright © 2002 by Harvey A. Levine.pp(159-162) [8] PROJECT MANAGEMENT A Systems Approach to Planning, Scheduling, and Controlling Tenth Edition by HAROLD KERZNER, P h. D. Senior Executive Director for Project Managenment, Copyright © 2009 by John Wiley & Sons, Inc.pp(633,685) [9] Project Management Gary R. Heerkens, PMP Copyright © 2002 by the McGraw-Hill Companies, Inc.(159,183)
[10] Project Planning and Control Fourth Edition Eur Ing Albert Lester, CEng, FICE, FIMechE, FIStructE, FAPM.pp(25-38)&(220-256) [11] Project Management for Facility Constructions A Guide for Engineers and Architects by Alberto De Marco.pp(119-136) [12] Skills & Knowledge of Cost Engineering Fifth Edition With New Appendix Listings Edited by Dr. Scott J. Amos, PE.
144/144
Resource Responsibility
P - Primary Responsibility A - Approval Authority S - Supporting Responsibility (Contributor or Reviewer) I - Information Only
(Select from drop down list)
P
roje
ct M
an
ag
er
P
rocu
rem
en
t M
an
ag
er
Ten
der
Man
ag
er
Fin
an
cial
An
aly
st
C
on
tract
Man
ag
er
Con
toro
l M
an
ag
er
P
roje
ct S
ched
ule
r
Q
uali
ty M
an
ag
er
Tech
nic
al
Man
ag
er
Ad
min
istr
ati
ve S
taff
Su
pp
ort
Sto
arg
e M
an
ger
Gathering supporting document
Time base line A S P IBudget base line I I P I I ICash flow A S A I P IBOQ I I P I I IDrawings P I I ISpecification P I I ISub contractor Contract A P I A I I
Cost Control model
Create WBS P S IFixed Asset Amount A P I I I IDeprecations system I S P A I SExpenses Amount I S P S I S SStorage Amount I I I S S PCoding system S S P I I
Collect data status
Material expenses I P S I S ALabor expenses I S I S POther expenses P S I SEquipment expnses P S I SSubcontracto/client invoices A S I PVariations order A I I I PQuantity survey I PConcrete pouring log I PLabor number & allocation report I I A PMaterial storage report I I I A P
Requirements Analysis
Actual Cost Allocations PAnalysis data with EV PReporting I I P I
1/1
143/144