cost control process for construction

162
i Helwan University Faculty of Engineer matarya Civil Department Cost Control Process for Construction Projects Dissertation Research in Partial Fulfillment of the Requirements for the Degree of master Prepared By Yasser M. Abouzeid Supervision by Prof. Dr. Adel El-Samadony Prof. Dr. Randa kamel

Upload: yasser-abouzeid

Post on 12-Jan-2017

251 views

Category:

Documents


27 download

TRANSCRIPT

i  

Helwan University

Faculty of Engineer matarya

Civil Department

Cost Control Process for Construction Projects

Dissertation Research in Partial Fulfillment of the Requirements for the Degree of master 

 

Prepared By 

Yasser M. Abouzeid  

Supervision by

Prof. Dr. Adel El-Samadony

Prof. Dr. Randa kamel

ii  

ACKNOWLEDGMENTS

First and foremost, I would like to extend my heartiest gratitude to Prof. Dr. Adel El‐Samadony, as my supervisor during obtain M.SC degree. He

gave me the chance to finish the study and with his guidance, the study can finish smoothly. Besides that, his patience and encouragement leads me to complete this study in time.

In addition, I would like to thank Eng. Amr Dawood, as the representative from the staff in Rowad modern Engineer (RME) for their kindly advised and assistance in giving the information to complete this study.

Not forgetting to present this research to spirit of my father. Mother, brothers and sister, for their full support and coaching throughout this research.

Lastly but not the least, to all my friends for their support, advise and their help when the time I need them.

iii  

ABSTRACT

With the competition in the construction market is fierce increasingly, profit margin of construction enterprises is getting smaller and smaller, and cost control of construction projects become more and more important. The control of construction project cost becomes one of the cores in project management.

Construction project management is a systematic, comprehensive, dynamic subject, requiring construction project manager to regularize and standardize the organization, goal, quality, safety, and cost of construction project. In order to achieve the project cost control effectively and create greater economic benefits. A study is carried out to study the cost control method in a constructions project, to identify the cost control process method frequently used by contractors in controlling the cost of projects.

From the study, the main problem faced by contractors are shortage of material, Labor costing more than estimated, difficulty in collection of cost data, ever-changing environment of construction work ,qualified expertise ,duration of project and additional costs to carry out the cost control.

iv  

INTRODUCTION

The cost control is a process that should be continued through the construction period to ensure that the cost of the project is kept within the agreed cost limits. The cost control can divide into two major areas; the control of cost during design stages and the control of cost by the contractors once the constructions of project have started.

Cost control of a project involves the measuring and collecting the cost record of a project and the work progress. It also involves the comparison of actual progress with planning. The main objective of cost control of a project is to gain the maximum profit within the designated period and satisfactory quality of work

Purpose: Due to the ever increasing competition and current climate in the construction industry, this has lead construction companies to become more competitive in their projects. The aim of this research was to highlight the importance of proper monitoring construction and examine what cost control Process that is in place. This will help all staff realise the importance of monitoring constructions and cost control system by suggesting recommendations to implement in future projects.

Objectives: The objective for this research is:

1- To study cost control Process in a construction project. 2- To identify the cost control method frequently used by contractor

during the construction stage. 3- To identify the main problem faced by contractor in controlling the

cost on site.

Methodology: A comprehensive review was under taken to get a better understanding of cost control system knowledge transfer. For the current research a case study was conducted on medium scale contractors by means of semi- structured interview and questionnaire to look at how their cost control system we monitored and any recommendation for improvement the research will illustrate the basic process used in cost control of construction project, in each process we explain the basic information need to this process and who is responsible to do this process and the form need to do the process (spreadsheets controls).

v  

CONTENTS

Title Page Number

INTRODUCTION iv

1 State of Art 1.1 Project Cost Control 1 

1.1.1 Purposes of Project Evaluation 1  1.1.2 Cost Control Definition 2 

1.2 Important Questions 3 1.2.1 Why we need Cost Management? 3  1.2.2 What the Project Manager Controls? 3  1.2.3 Who Needs Cost Management? 5 

1.3 Project Life Cycle and Project Cost 5 

1.4 Characteristics of a Project Control System 7  1.4.1 Elements of A Planning And Control System 8 

2 Proposed approach to construct model of cost control

2.1 What Information do you need to construct the model?

10

2.1.1 Estimating/Budgeting 10 

2.1.2 Work Breakdown Structure (WBS) 33 2.1.2.1 Types of Work Breakdown Structures 36  2.1.2.2 Work Breakdown Structure Development 39 

2.1.3 Cost Codes 41 

2.1.4 Depreciation 44 

2.2 Construct model template –Excel-Format 47 2.2.1 WBS template sheet 47 

2.2.1.1 WBS sheet template Consist 47  2.2.1.2 WBS sheet template Form 49 

2.2.2 Expenses template sheet 50 

2.2.2.1 Expenses template sheet Consist 50 

2.2.2.2 Expenses template sheet Form 51 

2.2.3 Storage template sheet 53 

2.2.3.1 Storage template sheet Consist 53  2.2.3.2 Storage template sheet Form 54

vi  

3 the application steps & methods 3.1 Collect Actual Cost data 55

3.1.1 Sources of information 55 

3.1.2 Data Required From Procurement Department 59 

3.1.3 Data Required From Storages 63 

3.1.4 Data Required From Projects 68 

3.1.5 Data Required From Finance Department 83 

3.2 Actual Cost Allocations 85 3.2.1 WBS Sheet template form 85 

3.2.1.1 Client Invoices 86 3.2.1.2 Variations Order 87 

3.2.2 Expenses Sheet template form 88 

3.2.3 Finance Report 90  3.2.4 Storage sheet template form 91 

3.2.4.1 Storage Report 92 

3.3 How do you make sure you are getting good information?

93 

4

Techniques of outputs & reports

4.1 The Earned Value Measurement System (EVMS) 96 

4.1.1 Variance and Earned Value 98 

4.1.2 Methods for Physical Progressing 100 

4.1.3 Example – Synthetic EVA 104 

4.2 Reporting Techniques 108

4.2.1 Report Content 108 

4.2.2 Reporting Considerations 109 

4.2.3 Sample Reports 110 4.2.4 Responses on Reports 125 

4.3 Construction Cost Control Software 126

4.3.1 Advantages of Used Software in Construction Cost Control

127 

4.3.2 The Disadvantages of Used Software in Construction Cost Control

130 

5 Conclusions 5.1 Common Causes of Cost Control Problems 131 

5.2 Keys to Effective Project Cost Control 134 

References

144

vii  

List of Table

Table number

Title Page number

2.1 Calculating the Estimate 21 2.2 Subcontractor /vendor list 23 2.3 Estimate summary for Office Building 24 2.4 General Overhead 25 2.5 Straight Line Depreciation 45 2.6 Sum of the Years’ Digits 46 2.7 Double Declining Balances 47 2.8 WBS sheet forms 49 2.9 Direct Expenses sheet forms 51 2.10 indirect Expenses sheet forms 52 2.11 Storage sheet forms 54 3.1 Time Cards 57 3.2 Log of material imported 60 3.3 Quotations Comparison Sheet 61 3.4 Recommended Subcontractors for Quotations list 62 3.5 Monthly Report about store movement 65 3.6 Monthly Report about material distributions 66 3.7 Monthly Report about material distributions and

location 67

3.8 Daily man power for Sub contractor 70 3.9 Daily man power for self performed time card 71 3.10 Weekly man power for self performed time card 71 3.11 Subcontractor productivity by location 72

3.12 man power daily production report 73 3.13 man power estimation & actual quantity 73 3.14 man power distribution by work package 74 3.15 Monthly Status log for manpower 75 3.16 Daily Equipment time card 76 3.17 Equipment distribution by work package 77 3.18 Monthly Status log for Equipment 78 3.19 Value of rent Equipment by work package 79 3.20 log for Concrete Casting 80 3.21 Report about Performance by activity 81 3.22 Monitor Report for Finishing item (masonry) 81 3.23 Cost report include labor, Equipment and material 82 3.24 Monthly Report for Finance department 83

viii  

3.25 WBS Sheet Form 85 3.26 Sample of Client Invoice 86 3.27 Sample of Cover for Variation Order 87 3.28 Sample of Variation Order 87 3.29 Direct Expenses sheet forms 88 3.30 indirect Expenses sheet forms 89 3.31 Finance Report forms 90 3.32 Deduction /Increase Storage Sheet Form 91 3.33 Storage Sheet Form 92 3.34 equate of (client/subcontractor) quantity 93 3.35 Concrete Casting Report 94 3.36 Steel losses Report 95 4.1 Example of Earned value report 107 4.2 Variance analysis Report 113 4.3 Overall Progress Report 114

ix  

List of Figure

Figure

number

Title

Page number

1.1 Project Manager Controls 4

1.2 Project Control Cycle 7 1.3

Project Planning and Control System 9

2.1 Types of Estimates 13 2.2 the Estimating Process 15 2.3 the Estimation Build 16 2.4 Cost estimation Process 27 2.5  Forms of Cost Estimate 28 2.6  Forms of Cost Estimate 29 2.7  Forms of Cost Estimate 30 2.8  Forms of Cost Estimate 31 2.9  Forms of Cost Estimate 32 2.10 Diagram of WBS hierarchy 35 2.11  Product-based WBS 36 2.12  Example of OBS 37 2.13  example of a process-oriented WBS 38 2.14  The cost account intersection 43 2.14  Cost Account code breakdown 43 3.1  data flow between Procurement team and other 59 3.2  step of enter material to the project 63 3.3  data flow between Storage team and other

department 64

3.4  data flow between Projects team and other department

69

3.5  data flow between Finance team and other department

83

4.1

Determining the Status

96 4.2  Controlling both project schedule and cost 97 4.3  Earned value formulae 99 4.4  Analysis showing use of 50/50 rule 102 4.5  Cost data contractual 103 4.6  Physical progress versus time expended 103 4.7  Methods for physical progressing 104 4.8  Representation of Variance on a S- curve 105 4.9  graphical project status 106 4.10  Schedule Performance index 107

x  

4.11 Graphical status reports 111 4.12  Data accumulation 111 4.13  Cost control and report flow 112 4.14  Performance Report 112 4.15  Progress Trends Report 113 4.16  Sample cost report 115 4.17  Cumulative cost report 115 4.18  Cumulative cost report 116 4.19  Cumulative cost line graph 117 4.20  Schedule status report 118 4.21  Summary Schedule status report 118 4.22  Weeks Status Performance 118 4.23  millstones Summary report 119 4.24  Sample report instructions 119 4.25  Event report 120 4.26  note on performance report 120 4.27  Critical Issues Report 121 4.28  Traffic signal as indicator of project status 121 4.30  Project Performance metric Definitions 122 4.31  Project Performance report 122 4.32  Sample of other Report 124

xi  

LIST OF APPENDIX

APPENDIX

Title Page number

A Cost Control Process Flow Chart 136

B Responsibility Matrix for Cost Control Process 143

Chapter  1  State of Art""  

1-State of Art 

Chapter 1  "State of Art"  

/91 

1-State of Art

1.1-Project Cost Control

1.1.1-Purposes of Project Evaluation Sports teams that practice without reviewing performance may get really good at playing very badly. That is why they review game films to see where they need to improve; there are two kinds of organizations those that are getting better and those that are dying. An organization that stands still is dying. It just doesn’t know it yet. The reason? Your competitors are not sitting by idly. In fact, good project management can give you a real competitive advantage, especially in product development. If you are poor in managing your projects, you don’t have good control of development costs. That means that you have to sell a lot of product or else charge large margins to cover your development costs so that the project is worth doing in the first place. If you can’t sell a lot of widgets, then you have to charge the large margin. In order to learn, people require feedback. Furthermore, people tend to learn more from mistakes than from successes, painful though that may be to admit. If your competitors, on the other hand, have good cost control, they can charge smaller margins and still be sure that they recover their investment and make money. They have a competitive advantage over you because of their better control of project work. In order to learn, people, like the team reviewing game films, require feedback. The last phase of a project should be a final audit so that the management of future projects can be improved. However, such an audit should not be conducted only at the end of the project. Audits should be done at major milestones in the project so that learning can take place as the job progresses. Another reason to do periodic audits is that, if a project is getting into serious trouble, the audit should tell the difficulty so that a decision can be made whether to continue or to terminate the work. Periodic audits should enable you to:

• Improve project performance together with the management of the Project.

• Ensure that quality of project work does not take a back seat to

schedule and cost concerns.

• Reveal developing problems early so that action can be taken to deal with them.

1/144

Chapter 1  "State of Art"  

/92 

• Identify areas where other projects (current or future) should be managed differently.

• Keep client(s) informed of project status. This can also help ensure

that the completed project will meet the needs of the client.

1.1.2-COST CONTROL Definition Cost control is the process of comparing actual expenditures to the baseline cost plans to determine variances, evaluate possible alternatives, and take appropriate action. To effectively control costs, be sure cost plans are prepared with sufficient detail.

2/144

Chapter 1  "State of Art"  

/93 

1.2- Important Questions

1.2.1-Why We Need Cost Management? The project manager is primarily concerned with the direct cost of the project, but the trend in project management is that the role of the project manager in cost control will increase to include more of the nontraditional areas of cost control. In the future it will be expected that more project managers will have a great deal of input into the indirect costs and expenses of the project. Regardless of what the project manager is or is not responsible for, it is critical that the project be measured against what the project manager is responsible for and nothing else. If the project manager does not have responsibility for the material cost of the project, then it makes no sense for the project manager to be measured against this metric. Timing of the collection of cost information is also important to the cost measurement system. The project budgets must be synchronized with the collection of the project’s actual cost. For example, if a project team is responsible for material cost, should the budget show the expenditure when the commitment by the project team to buy the product is made, when the item is delivered, when it is accepted, or when it is paid for? Timing issues like these can make project cost control a nightmare. If the project team does not properly control cost, the project will invariably go out of control, and more money will be spent

1.2.2-What the Project Manager Controls? The project manager has to measure many things during the course of a project, and he or she must take actions to guarantee that control (see Figure 1.1). The project manager must.

• Measure and review the project schedule progress against the plan

• Measure and review the project cost progress against the plan

• Measure and review project quality

• Anticipate possible changes and alternatives

• Manage issues and risks

• Control scope creeps through a change management process

• Ensure that delivery of milestones takes place according to client expectations

• Coordinate the project team

• Monitor physical resources by controlling the scheduling of resources during the project

3/144

Cha

 

pter 1 

/94 

"S State of AArt"

4/144

Chapter 1  "State of Art"  

/95 

1.2.3-Who Needs Cost Management? In every firm, cost management will exist in some form, usually under the control of the finance function. Our problem as project managers is that often that form is not consistent with the project management function, and that the cost data cannot be integrated with the other project data. As a result, many of the critical management questions concerning cost go unanswered. For instance, if the monthly accounting report notes that Omega Project has accumulated costs of $123,999, is this good or bad? Without integrating the accounting data with the other project data, much of the data is worthless. How do we go about answering such common questions as?

• How much are you going to spend?

• How much did you spend? Is this good or bad?

• How much will you have spent when the project is over? Is this good or bad?

• If I’m in trouble on costs, what can I do to turn things around?

• How shall the costs be distributed?

• How can I control my resource costs?

Effective cost management must address such questions. This requires an integrated schedule and budget plan. It also requires integrated participation by leaders of the projects, resources, and financial disciplines.

1.3-Project Life Cycle and Project Cost

Construction is a dynamic process, and no two projects are ever alike. Even if you have years of experience, every job presents a new set of circumstances and challenges no matter how good a job you do preparing during the pre-construction stage. The project manager and superintendent work together to come up with the best plan they can, trying to anticipate every obstruction and difficulty that might delay progress and put at risk the successful completion of the project, but they still can’t foresee every contingency. Even with this entire expert planning, the project must be monitored from beginning to end to ensure that all of the targets for time, cost, and quality are met. The whole process must be properly managed through a project control system that utilizes the plans, specs, estimate, and schedule. All of these documents taken together establish the road map for getting from the start of construction to the final completion of the project. Using this road map, the project manager and superintendent must maneuver all of the resources in the right direction, making

5/144

Chapter 1  "State of Art"  

/96 

adjustments as they go, to keep the project on track and on target. Project control requires continuous monitoring and evaluation of actual performance relative to the estimated performance for all aspects of the job that have an impact on cost, time, and quality. The project control cycle begins with the project plan and ends with the final project debriefing and evaluation. There are seven fundamental steps to the process:

• Develop the project plan.

• Establish the project benchmarks.

• Monitor the project performance.

• Identify performance deviations.

• Evaluate corrective options.

• Make adjustments as needed.

• Document, report, and evaluate results. (see Figure 1.2) It is important to track every aspect of project performance all the way back to the planning stage. This is where every project begins, and it is where every project should end with a complete debriefing and evaluation of what worked and what didn’t work. It is also a time to resolve actual costs and labor productivity information to update existing company records in preparation for the next cycle of project planning and estimating. It is an excellent opportunity to capture lessons learned and to create some best practices for future implementation. Unfortunately, many construction teams fail to complete the last step in the cycle and never properly assess their project’s overall performance. Everyone is usually worried to move on to the next project, and it’s very tough to get all of the parties together for even a couple of hours at the end of the job. It takes a great deal of discipline to consistently take advantage of this opportunity and learn from it. In my experience, I have found the project debriefing to be one of the most effective training mechanisms for every member of the team, from the project engineer to the project manager.

6/144

Cha

 

1.4

All The

1. Tes

pter 1 

4 Chara

good projeese include

A focusThe controensure thasystem sho

• What is

• What a

• Which a

• What abe placed

acteris

ect controe:

s on what ol system mat the projould be de

s importan

re we atte

aspects of

re the critd?

stics of

ol systems

is importamust focuect missioesigned wi

nt to the o

empting to

f the work

tical points

/97 

f a Pro

have seve

ant. s on proje

on is achieith these q

organizatio

o do?

are most

s in the pr

oject Co

eral chara

ect objectivved. To doquestions

on?

important

rocess at w

"S

ontrol

cteristics

ves. The ao that, thein mind:

t to track

which cont

State of A

Syste

in commo

aim is to e control

and contro

trols shoul

Art"

m

n.

ol?

ld

7/144

Chapter 1  "State of Art"  

/98 

2. A system for taking corrective action.

A control system should focus on response. If control data do not result in action, then the system is ineffective. That is, a control system must use deviation data to initiate corrective action; otherwise, it is simply a monitoring system, not a control system.

3. An emphasis on timely responses. The response to control data must be timely. If action occurs too late, it will be ineffective. This is frequently a serious problem. Data on project status are sometimes delayed by four to six weeks, making it useless for taking corrective action. Ideally, information on project status should be available on a real-time basis. In most cases, however, that is not possible. For many projects, weekly status reports are adequate. Ultimately, you want to find out how many hours people actually work on your project and compare that figure to what was planned. This means that you want accurate data. Some people may fill out weekly time reports without having kept track of their daily working times. since most of us cannot remember with any accuracy what we did a week ago. When people fill out time reports each week without having written down what they did daily, they are writing fiction. Such made-up data are almost worse than none at all. As difficult as it may be, you need to get people to record their working times daily so that the data will mean something when you collect them. What’s in it for the workers? Perhaps nothing. However, their better estimates (made as a result of collecting accurate information on this project) will help everyone who works on the next project. In any case, you need accurate data, or it isn’t worth the effort at all. When information collection is delayed for too long, the manager may wind up making things worse instead of better

1.4.1-Elements of Planning and Control System Figure 1-3 shows a generic model for a project planning and control system that allows a project to react to the changing conditions of the world.

• Define the problem or opportunity. The first phase of project planning is to clearly define the problem to be solved by the project or the opportunity of which the project will take advantage. This includes understanding the business reasons for the project and the client’s motive in requesting it.

8/144

Cha

 

• E Oncis tsco

• D Witdevreq

• B WhPer

• M As infodevact

• C

pter 1 

Establish p

ce you havo define th

ope.

Develop th

thin the fraveloped, inuired to coBegin proj

hen all plarsonnel, pr

Monitor.

project wormation aviations froion should

Close proje

project obj

ve clearly he basic o

he plan.

amework oncluding thomplete thect work.

ns are in roject wor

work progreand compaom the plad be taken

ect.

jectives.

identified bjectives

of the projhe activitiehe project

place, appk can beg

esses, theare it to than are the.

/99 

the probleof the proj

ject objectes, schedut work.

proved, anin.

e project mhe plan to n analyzed

em or oppject in ter

tives, detaules, cost p

nd commun

manager gdetermined to deter

"S

portunity, trms of time

ailed plansplans, and

nicated to

ather state variancemine if co

State of A

the next se, cost, an

s are d resources

project

us s. These rrective

Art"

step nd

s

9/144

Chapter  2  " Proposed approach to construct model of cost control "  

2- Proposed approach to

construct model of cost control 

Chapter 2  "Proposed approach to construct model of cost control"  

/451  

2-Proposed approach to construct model of cost control

2.1-What Information do you need to construct the model?

So exactly what kind of information should you be gathering to create your system of control which will maintain control of your Project? Below are listed the specific pieces of information you should be requesting

2.1.1-Estimating/Budgeting

What Is an Estimate? An estimate is an educated guess. We are all familiar with estimates. We have obtained estimates for work on our car, for getting our house painted, or for closing costs on a mortgage. And most of us have actually engaged in doing an estimate. We’ve guessed or estimated or calculated how many gallons of paint we needed to paint the living room. The main differences between these simple estimating activities and the estimates used to price construction are the complexity and what’s at stake. When you estimate how many gallons of paint are needed to paint your living room and you are off by a gallon or two, the stakes are pretty small. But when you estimate the cost to build a nuclear plant or a super highway or a hospital or even a house, the stakes are much, much higher. The estimate is a summary, based on the best information available, of probable quantities and costs of materials, labor, equipment, and subcontracts to complete a project, including taxes, overhead, and profit. It is the number used to develop the project bid price. The bid price is what goes in the contract, and the contract obligates you to perform all work needed to complete the project in accordance with the plans and specifications. The consequences of any errors or omissions in the estimate are borne by the contractor, and the contractor will not actually know what the true cost of the construction is until the project is complete. If the estimated cost is equal to or greater than the actual cost, the project makes money for the contractor. If the estimated cost is less than the actual cost, the contractor loses money on the project. As you can see, estimators have an awesome responsibility. First, they must come up with an accurate but competitive estimate that will win the job. Second, their planning and calculations set the stage for the overall management targets for the entire project. Once the estimator turns the project over to the project manager and the on-site team, the estimator shifts to a support role and really has no direct management duties

10/144

Cha 

assa joIt isTherisk

Types

The amoestimateestimateestimate(2-1).

Conno in twhespe

pter 2

sociated wob and subs a high-ste construck to a succ

of Esti

ount of infoe that can es are not e. But som

1. Concenceptual edrawings the idea orether theirending mo

"Propo

ith the daybmit a bidtakes gamtion manacessful out

mates

ormation a be prepar equal the

metimes ow

eptual Eestimates aavailable ar concept sr idea is eney on de

osed appr

y-to-day o, they are

mble, and magement tetcome.

available rred. Howev less inforwners don’

Estimateare often cat all. Youstage of aconomical

esign until

roach to c

/452 

operations taking a rmany facteam is on

regarding ver, you mmation av’t need a h

es called ballp can use c project. Oly feasible they know

construct

s. Every timrisk. ors may in the front

the projecmust keep vailable, thhigh level

park estimconceptuaOften an oe, and theyw that the

model of

me contra

nfluence thlines of m

ct will dicta in mind th

he less accof accurac

mates. Typl estimate

owner doesy don’t wa project is

f cost con

ctors estim

he outcommanaging t

ate the tyhat all curate the cy see Fig

pically theres when yosn’t really ant to stars at least

ntrol"

 

 

mate

me. his

pe of

ure

re are ou are know

rt

11/144

Chapter 2  "Proposed approach to construct model of cost control"  

/453  

possible. An experienced estimator can help out in a situation like this by offering a rough order of magnitude (ROM) estimate. These estimates are based upon a cost per primary unit for the facility. For example, for hospitals, the primary unit of measure would be beds, and you would multiply the proposed number of beds by the appropriate unit cost. For a school, the calculation would be cost per pupil; for a highway, the estimate would be based on a cost per mile. Once the owner suggests how many primary units they would like to build, an estimator can whip out a rough order of magnitude estimate within minutes; however, the accuracy is limited.

2. Preliminary Estimates If you have a preliminary set of drawings with overall dimensions, you can move to the next level of estimating. Preliminary estimates provide a somewhat higher level of accuracy and may be used to establish initial budgets and preliminary financing scenarios. However, these estimates should never be used to commit to a contract price because too many factors can influence the reliability of the numbers. Although there are numerous preliminary estimate methodologies, the most common is probably the square foot method. In its simplest form, the estimator calculates the area of the floor plan and multiplies that number by a unit price. There are various levels of skill and detail that can be applied to the square foot estimating method, and the degree of accuracy increases with each step up, as will the time it takes to calculate the price.

3. Detailed Estimates Whenever you have a complete set of plans and specs, you should do a detailed estimate. This is where you count every brick and stick, so to speak. Quantities and costs are calculated for every aspect of the project, and this is by far the most reliable estimate if the contractor is being asked to give a firm bid on a project. Detailed estimates are the most accurate. But keep in mind that as the accuracy increases, so does the time, effort, and skill required to complete the estimate. Although computerized estimating has reduced the time needed to compile project costs, it can still take two to three weeks and a team of estimators to put together a detailed estimate for a large, multistory commercial building such as an office or retail complex. The estimators still have to put the bid packages together and spend time soliciting subcontractor and vendor pricing. Throughout the rest of this chapter, I will be talking about detailed estimates.

12/144

Cha 

The Acccongrecon

Thetheestbe look

Get Althof ateasubbas Than teadoi

pter 2

Estima

curacy andnstruction eater than nstruction

• How m• How m• How lo

ese three c managemimate setsused throuk at what

tting Sthough an ean estimatm. Fellow

bcontractose when tr

e team woedge in thm becomeng the foll

"Propo

ating Pr

d completeestimate. or equal testimate,

many (quanmuch (priciong (produ

componenment targes the paraughout theit actually

tarted estimator te improve estimatorrs, materi

rying to m

orks togethe bidding es completlowing:

osed appr

rocess

eness are The ultimto the actu you are c

ntities) ing) uctivity)

nts make uets for the meters fore construc

y takes to

can work es when thrs, projectal supplieake decisi

ther to dev process. Itely famili

Figure

roach to c

/454 

the fundaate goal is

ual cost ofoncerned

up the con project ter the projection proceput an est

alone in dhere is inpt managerrs, and othons during

velop a unIn preparaar with th

2-1 Types

construct

mental obs to have tf the projewith three

struction eeam. You wect budgetess to montimate tog

developingput from ots, superinhers can ag the estim

ique stratation for the requirem

s of Estim

model of

bjectives othe estimact. When e things:

estimate awill discovt and schenitor succegether see

g an estimther memtendents,

all add to tmating pha

egy that mhe estimatments of th

ates

f cost con

f the ated cost byou do a

and establver that thedule and wess. Now l Figure (2

ate, the qbers of the the resourase.

might provting task, he project

ntrol"

 

 

be

ish e will et’s -2).

uality e

rce

vide the

t by

13/144

Chapter 2  "Proposed approach to construct model of cost control"  

/455  

1. thoroughly reviewing the plans and specs 2. developing a list of questions and needed clarifications 3. attending the pre bid meeting 4. visiting the project site

1. Reviewing the Plans and Specs

It is important to get a “big picture” perspective of the project before you get into the details of the work. Having an overall understanding of the difficulty of the construction will assist the estimator when making judgment calls that inevitably affect the accuracy of the estimate. Ideally, the plans and specs are reviewed in detail before any estimating takes place. Among the first things to look for when making the initial review are any special conditions, clauses, or criteria that could adversely affect the project schedule or cause unusual risks to be taken. Such items should be highlighted during this process and red flagged for the project team when the job is passed from the estimator to the project manager. Remember the earlier example regarding the imported Italian marble tile. Many of these red flag clauses are found at the front end of the project manual in the instructions to bidders and supplemental conditions. Taken into account during the estimating process.

2. Developing a list of Questions and needed Clarifications In addition to discovering red flag issues, the plan and spec review provides an opportunity for the estimator to uncover details that require clarification or questions about the project that are not addressed in the contract documents. As the estimator thumbs through the drawings, they will prepare a query list in anticipation of the pre bid meeting, site visit, or phone conference with the designer. The designer typically responds to each of the questions in writing. Those responses that result in a change to the original plans and specifications become official addendum to the contract. Checklists are a common tool used to make sure that nothing gets left out or overlooked.

14/144

Cha 

Prioprean ansrepsenthethoat t

No areplanof tultimeassmit

Figurestimat

pter 2

3. The Por to biddie bid meetopportunitswered. It presentativnt, simply project atrough revthis meetin

4. The S

one shoul site condns and spethe land, wmately affeting, it is

sociated wtigate thos

e 2-2 the ting Proce

"Propo

Pre bid Mng, it is coing. This mty for the is very imve to this mbecause tt this stag

view of theng, and co

Site Visit

d ever estitions thatecs. Only which will fect your ps your obliith the bidse risks

ess

osed appr

Meeting ommon fomeeting ofbidding co

mportant thmeeting. That is the

ge and whoe plans andontractors

t

timate a jot just cannby walkinghelp you mpricing. Evgation to

d. Visiting

roach to c

/456 

r the owneften occurontractors hat each oThe estima person who has deved specs. S who fail t

ob withoutnot be undg around wmake the ven if the smake evethe site is

construct

er and/or rs at the p to get ma

of the biddator is ofteho is the oeloped a q

Some projeto attend a

t first visitderstood bwill you genecessarysite visit isry effort to

s one way

model of

designer troject siteany of theding contraen the repone most fquery list aects requirare not allo

ting the joby merely et a good sy judgments not part o mitigatein which y

f cost con

to conducte and provir questionactors senpresentativfamiliar wiafter a re attendaowed to b

b site. Thelooking atsense of tt calls tha of the pree risks you can

ntrol"

 

 

t a ides ns ds a

ve ith

ance id.

ere the he lay t

e bid

15/144

Cha 

Est

How Youfacidivi EaconedecconIn tconest

FiguEstim

pter 2

imators sh

• Distan• Site co• Site ac• Soil da• Ground• Securit• Traffic • adjace• possib• Water,• Obstru• Parking• Debris• Local w• Local l

w You Bu build an ility. Geneisions of th

ch CSI divie of the mcide to orgnsistent fothis way, tnsulted forimate see

ure 2-3 thmation Bu

"Propo

hould cons

ce from ofonditions ccess ata dwater ty needs considera

ent structule contam, electricityuctions g and stor disposal weather paabor and s

uild theestimate i

erally, you he 2004 C

ision is broost comm

ganize the rmat, evethe estimar every pro Figure (2

he uild

osed appr

sider the f

ffice

ations ures ination y, and tele

rage

atterns sub trades

e Estimin very mu start from

CSI Master

oken downon ways t estimate,n if some ate outlineoject to m-3).

roach to c

/457 

following w

ephone se

s

ate? uch the sam the grour Format o

n into detao organize it is very divisions a

e acts as aake sure t

construct

when visiti

ervice

ame order und up andoutline.

ailed itemse the estim importantare not ap master chthat nothin

model of

ng the site

that you bd work thr

s of work. mate. Howt to stick wpplicable tohecklist thng gets lef

f cost con

e:

build the arough the

This formwever you with a o every prhat should ft out of th

ntrol"

 

 

actual 48

mat is

roject. be he

16/144

Chapter 2  "Proposed approach to construct model of cost control"  

/458  

Organizing the Work of the Estimate Estimating the cost of a multistory office building, high-tech manufacturing facility, or state-of-the-art concert hall is no easy task. It is a big job and takes great deal of planning and organization. So, how do you conquer this challenge? Well, the same way you eat an elephant—one bite at a time! Although the CSI Master Format 2004 gives us an overall outline to follow, thousands of activities and materials must be considered before you can begin to price the project. As large as the task may seem, there actually is a logical method for organizing all of the work activities, materials, and labor associated with a project. Let’s take a look at just how you eat this elephant!

1. The Work Breakdown Structure The primary organizational tool utilized by the construction estimator is the work breakdown structure (WBS). The work breakdown structure establishes the basic building blocks of both the estimate and the schedule. The purpose of the work breakdown structure as it applies to the estimate is to organize and identify the work of the project by breaking each division of work into a separate work package or bid package. The work package identifies each step in the process of that work item. Work packages are usually assembled around the work activities typically performed by a single subcontractor or work group. Obviously, being familiar with construction materials and methods is pretty important here. One of the primary goals in creating a work package is to not overlook any of the steps needed to complete the work. A sample work package looks something like this: Work Package—Concrete Floor Slab

• Excavate the footings. • Install the edge forms. • Install under slab fill. • Install vapor barrier. • Install the reinforcing. • Place anchor bolts. • Place the concrete. • Finish the concrete. • Strip the form work.

Once each step associated with a particular item of work is identified, it can be quantified and priced. But let me stop here and back up a minute to make sure that you remember how the work of the project is actually accomplished. The contractor has two options:

• self-perform the work with their own forces • Subcontract the work to various trade contractors.

17/144

Chapter 2  "Proposed approach to construct model of cost control"  

/459  

The contractor will have to do all of the quantifying and pricing of each step of the work if the contractor decides to self-perform a particular section of work. If the contractor decides to subcontract out some of the work, then the subcontractor will quantify and price the work and submit a bid to the general contractor. The greatest challenge either way is to make sure that nothing gets overlooked or left out of the estimate. Sometimes the general contractor calculates their own quantities and estimates for subcontracted work even though the subcontractor will be submitting a bid. This is called a fair value estimate; it’s done as a check to guard against inaccurate quantity surveying by the subcontractor and unreasonable pricing.

2. Calculating Quantities Now that you have assembled all of your work packages and identified all of the steps necessary to do the work, you can start doing your quantity takeoff. You must quantify all of your materials, labor, and general conditions before you can price any of the work. You need to calculate “how many” before you can calculate “how much.” Once you determine the quantities, you can apply a unit price factor to the equation. Junior estimators often start off as quantity surveyors. The primary attributes of a good quantity surveyor are the ability to read and interpret plans, knowledge of common units of measure for construction materials and labor, and basic estimating mathematics. You will use algebra to measure ratio and proportion, plane geometry for lineal and area measurements, solid geometry for cubic measurements, and plane trigonometry for lineal, area, and cubic measurements.

3. Quantifying Materials Quantifying materials is the least risky of all the estimating activities. You are simply counting and calculating all of the parts and pieces that will go into the project. Quantity surveying represents more of the science of estimating. That’s because you are working with known sizes and dimensions depicted in the drawings. If the plans are drawn correctly and include all of the information needed to do the takeoff, the estimator should be able to come up with very accurate quantities, assuming the estimator doesn’t overlook anything and doesn’t make mathematical errors. The estimator reviews the plans, the elevations, the sections, and the details; pulls the dimensions needed to make the appropriate calculations; and comes up with the lengths, areas, and volumes of work and material required for the project. Probably the most difficult part of the quantity survey is making sure that the quantity is taken off in the proper unit of measure. The unit of measure

18/144

Cha 

for exatakconlearkno In tof cof a

FooWaTot

24.

2.6

253The

4 Quadeahumandthabeccomcha Thisall afor

pter 2

takeoff mample, cone off all co

nvert to curn all of thowledge is

this typicaconcrete na foot. Her

• Sectionoting = 2.0ll = 0.66 f

tal section

• Perime0 feet + 2

• Section4 square f

• Conve3.44 cubic e answer is

4. Quant

antifying laal with creman factord fast dimet can be p

cause of simplexity ofapter.

s is whereabout judg any given

"Propo

ust be thencrete is poncrete byubic yards he pricing an absolu

al quantity needed for re are the

n area of f0 feet *0.6feet *2.0 f area = 1.

eter of bui24.0 feet +

n area*pefeet *96 fe

rt to cubic feet ÷ 27s 9.39 cub

ifying La

abor and ew sizes anrs of constensions onplaced or ite conditiof the proje

e estimatingment. Thn crew reg

osed appr

e same as riced by th

y the cubic to match units for tute necess

surveying this found steps

foundation66 feet = feet = 1.332 square

lding: + 24.0 fee

rimeter =eet = 253

c yards (un7 cubic feebic yards o

abor and

equipmentnd producttruction is n a set of dnstalled inons, weathect, and se

ng moves he individuarding any

roach to c

/4510 

the unit ohe cubic yc foot (lengthe pricing

the varioussity if you

g exercise,dation. All

n: 1.32 squa2 square f

e feet + 1.

et + 24.0 f

cubic feet.44 cubic

nit of meaet = 9.39 cof concrete

d Equipm

t is a littletivity rates not quite drawings. n a specifieher, crew everal oth

way over ual estimaty given ite

construct

of measureyard. The qgth × widtg unit. It ts materialare an est

, you will e inches ar

re feet feet .32 square

feet = 96 f

t feet

sure for cocubic yarde in found

ment

e riskier. Ts. In other the same Productived unit of makeup, cer factors

on the arttor will detem of work

model of

e for pricinquantity suth × depthtakes a litts and labotimator.

estimate tre converte

e feet = 2.

feet

oncrete): s ation.

hat’s becar words, we as workinity is the atime. Prodcrew skill discussed

t side of thtermine thk. Fortuna

f cost con

ng. For urveyor mh) and thetle time toor, but this

the cubic yed to deci

.64 square

ause you mworking witng with haamount ofductivity vlevel,

d earlier in

he equatiohe productately,

ntrol"

 

 

must en o s

yards mals

e feet.

must th the

ard f work varies

the

on. It’s tivity

19/144

Cha 

proconcanequsize

5

Alsoassof mestThemoof g

6 SupJobMatTemPorDumJobOn-JobPricOncyouequextwhe

pter 2

oductivity instruction n help the uipment ques and pro

5. Quanto called jo

sociated wmeasure foimator is te estimatonths, or ygeneral co

6. Generpervision (b trailer (reterial storamporary utrtable toilempsters (rb photogra-site webc

b office supcing the Wce all of you have to duipment, aensions diere the co

"Propo

is somethiindustry, estimator uantity takoductivity

ifying Gob overheaith any givor generalto come uor must maears the c

ondition ite

ral Cond(salary) Went) Monthage trailertilities (us

ets (rent) Mrent) Montphs Lump

cam Lump pplies Lum

Work our quantido is plug and generaisplayed insts will co

osed appr

ing that is and there make senkeoffs. In rates for c

eneral Cad, generaven projecl conditionp with a tiake an educonstructioems and th

ition IteWeek h rs (rent) Msage) MontMonth th

p sum sum

mp sum

ities are ca in the unial condition Table 2.1ome from a

roach to c

/4511 

studied q are databnsible judgthe follow

concrete w

Conditioal conditionct. Time, nns. Therefoime estimaucated guon will takeheir respec

em Comm

Month th

alculated, t cost for

ons in your1. As an eand their r

construct

uite extenbases and gment reg

wing, I showork:

ns ns make unot producore, the prate for theess as to he to compctive units

mon Uni

you are heach itemr estimateestimator, reliability.

model of

nsively in t referencearding labw some av

up the indictivity, is trimary tase overall johow manylete. Heres of measu

it of Mea

alfway them of materi

. You can your prim

f cost con

the s available

bor and verage cre

irect costshe norma

sk of the ob duratioy days, wee’s a sampure:

asure

ere. Now aial, labor, see the p

mary conce

ntrol"

 

 

e that

ew

s l unit

on. eeks, ling

all

rice ern is

20/144

Cha 

SomtheandWh“allthe OncdowIf tsurclie Alloregmaabledril

7 Pricmabuisucma Manhistoveperplachavpric Theestthe

Table 2

pter 2

metimes it time of th

d quality then this haowance” n time.

ce the infown to reflehe actual plus funds

ent pays th

owances aarding styy also be e to accurling.

7. Sourcecing informterials, yolding supp

ch as R.S. terial, and

ny construtorical perer a numberformed woce, then thve such a scing.

ere is one imators chn calculat

-1

"Propo

t is not pohe estimathat simplyappens, it number, fu

ormation nect the actcost is less to the clihe differen

re often uyle, color, used when

rately quan

es of Infmation comou can obvpliers. Or y Means. Thd equipme

uction comrformance.er of yearsork. If a chis may besystem in

more altehoose to ue their ow

osed appr

ssible to ate becausey can’t be is a commully disclos

needed is aual cost os than theient. If thence.

sed for finor quality n there arntify the c

formatiomes from aviously getyou can chhey list unnt.

mpanies cre. They tracs and comompany he the best place, and

rnative whuse the prown unit pric

roach to c

/4512 

accurately e there aremade unt

mon practicsed to the

available, f the iteme allowance cost is g

nish items such as ce simply tost of the

on a variety ot prices dirheck the vnit costs fo

eate their ck actual j

me up withas an exc

t way to god many re

hen it comoductivity ces by usi

construct

determinee decisionil the projece for estim client, ba

the allowa.

ce, the estreater tha

that requcarpet, tiletoo many u work, suc

of sourcesrectly fromarious con

or every se

own cost job costs f average uellent costo. Howeveely on pub

mes to pricdata fromng local w

model of

e the costss regardinect is undemators to

ased upon

ance is adj

imator retn the allow

ire owner e, or light funknown vch as rock

. When it m your vennstruction ection of w

databasesfrom variounit pricest reportinger, not all lished cos

ing labor. m the variowage rates

f cost con

s of items ng quantitier constru plug in an a best gu

justed up

turns the wance, the

involvemefixtures. Tvariables t excavatio

comes to ndors and cost guidework for la

s based onous projects for their g system icompaniest data for

Some ous guides in the for

ntrol"

 

 

at es

uction. n ess at

or

e

ent They to be on or

retail es bor,

n ts self-n s their

but mula.

21/144

Cha 

8

TheTodestWhperthe Theequvercovprothe

9 Aftelist of wvensub

pter 2

8. Obtain

e final comday, subcoimate. ile the est

rformed wo work they

e team muuipment asry importavered, theroblem on b subcontra

• Solicit • Receiv• Analyz• Choose

9. Solicit

er a comp or chart rwork or trandor quotebcontracto

"Propo

ning Sub

mponents oontractor a

timating teork, they y are not g

ust also bessociated wnt. If one re will be abid day. Thacted wor

the bids. ve the bidsze the bidse the bids

ing the

lete reviewrepresentinades will bes, and whr/vendor l

osed appr

bcontrac

of your estand vendo

eam is putmust also going to s

e solicitingwith the w of the traa big hole here are fok and ven

s. s. .

Bids

w of the png all the be self-perhich will relist.

roach to c

/4513 

ctor and

timate arer bids mak

tting toget be gatherelf-perform

vendor pwork. The des neede in the estour steps tdor pricing

lans and swork of thrformed, wequire both

construct

Vendor

e subcontrke up the

ther their ring pricesm.

ricing for amanagem

ed to comptimate, whto ensure g are com

specs, the he contracwhich will rh. Table 2

model of

r Bids

ractor and bulk of th

own pricins from sub

all of the ment of thisplete the phich will le that the splete and

estimatorct, showingrequire su.2 shows a

f cost con

vendor bie construc

ng for self-bcontracto

materials as process project is nad to a big

solicitation thorough

r will creatg which arbcontractoa sample

ntrol"

 

 

ids. ction

-rs for

and is not g of :

te a reas or or

22/144

Cha 

AftevenAlthconconquohavrep It isto gtheof wnotquoestcan AndplayPutsubon as wnumMasnumtheup ons

Table 2-2

pter 2

er it is detndor or a shough subnstruction ntractors dotation to ve a past hpresenting

s importangive the suir decisionwhom theyt want to bote that doimated co

n to avoid

d even thoy it safe thtting It All bcontractethe materwell. The embers. As ster Formambers hav project, ywith your

s.

"Propo

termined wsubcontracbcontractonews serv

do, most ea selectedhistory. Th the same

nt that theubcontractn not to biy can expebe left hanoesn’t arrivst of the wthis situat

ough it takhan to be Together d work intrial takeoffestimator you can sat discusseve been adyou must a final bid.

osed appr

which areactor, a formrs and venvices for bstimators

d list of suhey usually trade.

ese requestors enougd on the pect to recenging on bve. At thework in qution.

kes a lot ofleft standi It’s time tto one estf sheets ar must be vsee in Tabled earlier dded downalso applyThese last

roach to c

/4514 

as of work mal solicitndors watcid notices choose tobcontractoy send out

sts go out gh time toproject. It eive quoteid day wa last minuestion mig

f time to sing withouto compileimate sumre transfervery carefule 2.3, the in the chan at the boy taxes, get few item

construct

will requitation procch the trad as closelyo send out ors and vet requests

very earlyo put toget is crucial tes from on iting for a

ute, you wght be. Es

solicit all out a trade e all of yoummary. Allrred to theul to accure estimate apter. Howottom. Onceneral oves are ofte

model of

re a price cess gets ude journaly as the ge their own

endors wit to severa

y in the esther a pricthat the e bid day. Tn expecteill be left ttimators d

of the bidscovered b

ur self-perf of the sue estimaterately tran summary

wever, a fece you calrhead, andn referred

f cost con

quote frounderway.s and

eneral n requests h whom thal compani

stimating pce or notifystimator bTrust me, d subcontto guess wdo everyth

, it is far bby a reliablformed wobtotals cae summarynsfer all ofy follows thew very imculate thed profit to

d to as pro

ntrol"

 

 

m a .

for hey ies

process y you of be aware you do ractor

what the hing they

better to le price. ork and lculated y sheet f the he CSI

mportant e cost of come

oject add-

23/144

Cha 

1 Youpaycoluwormuthefampayto k Whappmualontheclas

Table 2-3

pter 2

10. Taxes

u include tyroll taxesumns: mark and equst be adde labor colu

miliar with yroll add-okeep it sim

en I was rproximatelch “burdene will cauy might sessifying as• Employ• Worke• Unemp• Employ

holiday

3

"Propo

s

two types . That’s wterial, labuipment bed to the mumn. We a payroll taons are nomple.

running mly 14 to 20n” labor reuse a geneelf-performs payroll tayer’s portirs’ compeployment tyee benefys, and so

osed appr

of taxes inhy it is imor, equipmids will alrmaterial call know wxes (also t taxes at

y own con0 people, ieally did peral contram. The peraxes includion of Socnsation tax its (health

o on)

roach to c

/4515 

n your conmportant toment, and ready haveolumn, an

what sales referred to all, but yo

nstruction it really su

put on the actor to surcentage ide the follial Securit

h insurance

construct

nstruction o divide yo subcontrae taxes incnd payroll t taxes areo as labor ou merely

company,urprised m payroll. Subcontracts significaowing:

ty tax

e, life insu

model of

estimate: our summaacts. The scluded, butaxes mus, but you burden). refer to t

, employinme to learnSometimes work thatnt. Those

urance, va

f cost con

sales tax ary into fosubcontracut sales taxst be addemay not bSome of them as ta

ng n just how s this factot otherwis costs that

cation, pa

ntrol"

 

 

and our cted x

ed to be as the axes

or e t I am

aid

24/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4516  

11. General Overhead I’ve already mentioned job-specific overhead. These costs include such things as the job site office trailer, portable toilets, and job photographs. They are estimated item by item relative to a specific job. General overhead is a different story. Basically, general overhead represents the cost of doing business. These are expenses that would be incurred by the company whether they had a job to build or not, such as office expenses, executive salaries, and automobile insurance. General overhead is applied to the estimate as a percentage of total cost. This percentage will vary from company to company see Table (2-4).

Table 2-4 General Overhead

25/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4517  

12. Profit The goal for every project is to make a profit. Profit is what’s left after all costs and expenses associated with the job have been paid. The estimate represents the contractor’s best guess as to what those costs and expenses are going to be. Profit is expressed as a percentage of the total estimated cost. Profit is rarely a fixed percentage in construction. The estimating team will make a determination as to how much that percentage should be for any given job. As previously stated, when times are tight in construction and there is very little work to bid, profit margins may be quite small. On the other hand, when there is a lot of construction going on in a particular market and demand is high, profit margins will be adjusted upward. Either way, profit is an estimated number just like every other number in the bid. It is highly unusual for the actual cost of the project to exactly match the estimated cost of the project. If we consider each division of our estimate summary, and each of our add-ons, the most likely scenario will be that some divisions (and add-ons) will be over the individual division estimates, and some will be under the individual estimates. However, it’s the final number that you are most concerned with. The goal is to have the actual overall cost of the project at the estimate or under after all point we described we can illustrate the cost estimation in figure (2-4).

26/144

Cha 

pter 2

Figure 2

"Propo

-4

osed apprroach to c

/4518 

construct model off cost con

 

ntrol"

 

 

27/144

Cha 

Sa

pter 2

ample F

"Propo

Forms o

Fig

osed appr

of Cost E

gure 2-5 F

roach to c

/4519 

Estimat

Forms of

construct

te

Cost Esti

model of

imate

f cost conntrol"

 

 

28/144

Cha  pter 2

"Propo

Figure

osed appr

e 2-6 Form

roach to c

/4520 

ms of Cos

construct

st Estima

model of

ate

f cost conntrol"

 

 

29/144

Cha  pter 2

"Propo

Figu

osed appr

ure 2-7 Fo

roach to c

/4521 

orms of C

construct

Cost Estim

model of

mate

f cost conntrol"

 

 

30/144

Cha 

pter 2

"Propo

Figure

osed appr

2-8 Form

roach to c

/4522 

ms of Cos

construct

st Estimat

model of

te

f cost conntrol"

 

 31/144

Cha 

pter 2

"Propo

Figure

osed appr

2-9 Form

roach to c

/4523 

ms of Cos

construct

t Estimat

model of

te

f cost conntrol"

 

 

32/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4524  

2.1.2- Work Breakdown Structure (WBS)

To plan the project we must convert these into individual pieces of work that must be done to complete the project. For this we need the ‘‘work breakdown structure,’’ or WBS .The work breakdown structure is the most central item in the project plan. Without it we do not have a definition of the work that has to be done to complete the project. Without knowing the work that has to be done we cannot possibly determine the cost of the project or determine the schedule of the project. Without knowing the cost or schedule of the project how will it be possible to control the project or determine how much should be spent to complete it? The amount of resources that must be used on the project and when they must be made available cannot be determined without knowing the schedule. Funding to do the project cannot be scheduled to be in place when the project needs it without a time-phased budget for the project. According to the Guide to the PMBOK, the definition of a work breakdown structure is: ‘‘a deliverable oriented grouping of project components that organizes and defines the total scope of the project work. To create a WBS is a simple task: the project is first broken down into a group of subprojects. Each of these subprojects can be broken down to sub subprojects. The sub-subprojects can be broken down again and again until the desired level of detail is reached. The level of detail is termed the' work package’’ level. The work package is the lowest level of management that the project manager needs to manage. Below the work package other project team members may break down their parts of the project into additional levels .Work packages can be broken down into ‘‘activities,’’ and activities can be further broken down into ‘‘tasks.’’ The reason that technique is so effective is that it follows the principle of ‘‘divide and conquer. 'So, initially the project is broken up into a group of subprojects. These subprojects are further broken down into sub-subprojects, and so on. In this way the largest project we can imagine could be broken down into subprojects. Since each of these subprojects could be considered to be a project in its own right, any large project can be thought of as a family of smaller projects that are interrelated. The important thing about project management is that it is a powerful Methodology that adapts to any size project or program. The tools and methodology that are used are similar in all projects. The WBS is the tool that allows all projects to be broken down into smaller, more manageable projects. The end result of the WBS is a group of individual pieces of work defined. Each of these small individual pieces of work must be assigned to. It is then

33/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4525  

possible to break the work packages down further before the actual work assignments at the detail level are made. The WBS is a hierarchical structure in which all of the major phases of project work are organized in a logical manner. Simply stated, it is a layout of how the work of the project ought to be performed and managed. The WBS links together the project scope, the schedule, and the cost elements, and forms the basis for the entire project information structure. It provides the framework that captures the project’s work information flows, as well as the mechanism for tracking the project’s schedule and progress. It also provides the basis for summarizing and reporting the project’s cost data. In essence, the WBS creates a common framework that.

• Presents the entire project as a series of logically interrelated elements

• Facilitates project planning

• Provides the basis for estimating and determining project costs and

budgets

• Provides the mechanism for tracking project performance, cost, and schedule

• Provides the basis for determining the resources needed to

accomplish project objectives

• Provides the mechanism for generating project schedule and status Reports

• Triggers the development of the project network and control

systems

• Facilitates the assignment of responsibilities for each work element of the project

• Graphically, we can imagine a WBS along the lines shown in Figure

2.10

34/144

Cha 

Thprothrofiniselemact Aloof dProtheterm

pter 2

ere are sooject activiough specshing withmental tasivities for

ng with a detail is anject scope appropriams of reso

"Propo

ome importies is hie

cific projech work pacsks at the which dur

well-definn invaluabe can easilate work pources and

Figur

osed appr

rtant featurarchical,

ct deliverackages. Ac lowest levration and

ned projectle tool for y be expa

packages, d schedule

re 2-10

roach to c

/4526 

ures to notmoving frbles (and ccording tovel in the W budget fig

t scope do managing

anded or dand by ma

es.

construct

te here. Fiom the ovsometimeo the ProjeWBS and gures can

ocument, ag scope chiminished aking the

model of

rst, the brverall projees sub deliect work prepresent be assign

a WBS withange. by includnecessary

f cost con

reakdown ect level, dverables),

packages a basic projed.

th sufficien

ing or elimy adjustme

ntrol"

 

 

of down , and are the ject

nt levels

minating ents in

35/144

Cha 

2.1.2 It isusegento utheuse Coninfobuytha Pro

Outprorelaultifaciproexa orgunitinteestarepcom

pter 2

2.1- Ty

s importaned in projenerate the use the W identifica

ed that sho

ntractualormation ayer. It is ut is going

oduct-bas

tcome, sucototype. Inatively easmately intilitates cos

ovides a baample of a

ganizationts responsegrated intablishes, i

porting relampleting th

"Propo

pes of W

nt to recogects. The W individuaBS to devetion of woould not b

WBS (CWand the timsually not to be don

sed WBS

ch as the n these kinsy to breakto managest estimatasis for co product-b

nal breaksible for coto the strun a hierarationships he work. E

osed appr

Work B

gnize that WBS that wl pieces ofelop anyth

ork less effe confused

WBS). Thimeliness ot as detailee.

is most su

design andnds of prodk the projeeable workion of the mparison based WBS

kdown strompleting ucture. Thrchical form for the vaExample o

Figure

roach to c

/4527 

Breakdo

there are we have bf work thahing else wfective. Otd With the

is breakdoof informated as the W

uitable for

d construcduct-basedect into dek packages various pwith the pS is shown

ructure, k the work e clear admat, accouarious orgaf OBS is s

2-11

construct

own Str

many otheen discust must be would confther breake WBS are

own is usetion that aWBS that

projects t

ction of a td work breeliverabless. A produroduct comproject’s an in Figure

known as requiremevantage ountability, anizationahown in F

model of

ructures

her types ossing mus done in thfuse the ekdown stru:

d to defina supplier wis used to

that have

tunnel, or eakdown ss, sub delivuct-based mponents,ctual cost e 2.11

OBS, the ents of theof an OBS responsib

al units thaigure 2.12

f cost con

s

of breakdost be used he projectffort and m

uctures tha

e the repowill supply

o plan the

a tangible

a new figstructures,verables, WBS Also , which in Performa

organizatie project ais that it

bility, and at are invo2 that proj

ntrol"

 

 

owns only to t. To try make at are

orting y to the work

e

hter Jet , it is and turn nce. An

onal are

olved in ject

36/144

Cha 

invoproProproprointelowprocombe

pter 2

olves a seoject, ocess-orieocess-orienoject evolvegrated wi

west level, oduct cost\mbination used. An e

"Propo

ries of pha

ented WBnted WBS ves over timith the ove while the \ informatof featureexample o

osed appr

ases or ta

BS is more involves cme. In generall proje product-bion. In adds from bot

of a proces

Figure 2

roach to c

/4528 

sks, such

e appropricompletionneral, a prct, becaus

based WBSdition, a hth productss-oriented

-12

construct

as in an in

ate. Unliken of majorrocess-oriese the taskS is most uhybrid strut- and prod WBS is s

model of

nformation

e a producr tasks in sented WBSks can be useful for cture thatcess-baseshown in F

f cost con

n systems

ct-based Wsequence aS can be bdelineatedaccumulatt involves ed structurFigure 2.1

ntrol"

 

 

WBS, a as the better d to the ting a res can 3

37/144

Cha 

In tprobe puroth BillBOMof a

pter 2

the presenoject manaused. Howrpose, the er organiz

l of mateM in a hierassembly a

"Propo

nt-day proagement swever, the organizatzational un

rial (BOMrarchical ware shown

Figure 2-

osed appr

oject enviroystems, b choice re

tion’s infornits, and,

M). The vaway. Produn as a ‘‘goe

-13

roach to c

/4529 

onment, woth types ally depenrmation syultimately

arious products produes into’’ hi

construct

with its pro (product nds on theystem and , how use

duct compuced, subaierarchy

model of

oliferation and proce

e particula how it intful it is as

ponents areassemblies

f cost con

of compuess) of WBr project, terfaces w a plannin

e includeds, and lowe

ntrol"

 

 

terized S can its

with the ng aid.

d in the er level

38/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4530  

2.1.2.2 Work Breakdown Structure Development

Before any Work Breakdown Structure can be produced, it is essential that careful thought is given to the number and size of networks required. Not only is it desirable to limit the size of network, so we should be considered in relation to the following aspects:

1. The geographical location of the various portions of the project.

2. The size and complexity of each Project.

3. The process or work being carried out in the Project when the plant is complete.

4. The engineering disciplines required during the design and construction stage

5. The erection procedures.

6. The stages at which individual Project or systems have to be

completed.

7. The site organization envisaged.

8. Any design or procurement priorities. So Constructing a WBS is a group effort. The responsibility for the top three levels usually lies with the project manager, who typically works with other managers to develop the major deliverables found there. At the lower levels, however, input into the details should come from that Responsible for the day-to-day work. In addition to the project team, each person responsible for a specific work package must be consulted. There are no universal standards as to the number of levels to use in a WBS. This is typically dictated by the complexity of the project, and the number and nature of the activities. Most have three or four levels at a minimum, although more may be needed if there are significantly more sub deliverables and work packages. As a rule, the greater the number of work packages, the greater the amount of time, effort, and cost incurred in developing the WBS. However, the increased number of packages also significantly enhances the accuracy of project status monitoring and reporting. On the other hand, larger but fewer work packages reduce the cost of WBS development, but the accuracy of project status monitoring and reporting suffers. In most practical situations, a compromise on the number and size of work packages is struck. The most important levels in the WBS development process are the top few levels, which represent the project and associated major deliverables, and the lowest levels, which represent the work activities that are to be scheduled and resourced.

39/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4531  

Typically, the intermediate levels are an aggregation of the lower-level activities, and serve as the mechanism for reporting. The intermediate levels can also be used to set up cost accounts through which cost and budgetary information can be gathered and monitored. A WBS should be constructed by separating the total work, in a hierarchical framework, into discrete and logical sub elements that reflect completeness, compatibility, and linkage to the project’s end item. This hierarchical structure facilitates the aggregation of budget and actual costs incurred into larger cost accounts. In this way, the total value of the work at one level is an aggregation of all the work completed one level below, which enables project work and cost performance to be monitored. The WBS should also reflect all of the project requisites, as well as functional requirements, and should incorporate both recurring and nonrecurring costs. In a WBS, the lowest level consists of tasks of short duration that have a discrete start and end point. Because they consume resources, costs are often reported at this work package level. Work packages serve as control point mechanisms for monitoring and reporting performance, in terms of whether associated tasks were completed according to specifications, on time, and within budget. The responsibility for completing work Packages should be assigned to the appropriate organizational units and individuals, and the resulting WBS should reflect the reporting requirements of the organization. We can develop a WBS by one of two methods:

• Top-down approach begins with the total work required to produce the project’s end product. This is successively broken down, First into major work blocks and then into more detailed work package levels until a required level of detail has been achieved.

• Bottom-up approach begins with a comprehensive list of all the

activities or tasks required to complete the project. Then it moves up, in a hierarchical format, first to work packages, then to cost accounts, and so on, until the top level represents the total work to be performed. It is highly unlikely that the first version of the WBS will be the last.

More often than not, it will undergo frequent revisions in response to Feedback that works must be broken into more detailed tasks. Clearly, only individuals who have a thorough knowledge of the work to be performed can conduct the appropriate level of detailed breakdown. In addition, it is impossible to establish estimates of task duration, resource requirements, and the network of precedence relationships among activities without complete agreement on details at the lowest level.

40/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4532  

2.1.3- Cost Codes

Once the budget, WBS is confirmed, each activity in the budget is assigned a cost code. Cost codes are used to track all items of work contributing to the overall project Costs. That includes material, labor, equipment, subcontracts, and overhead. All job information regarding cost is tracked via these cost codes as shown in Figure 2.14 Every item on a material invoice, every man-hour logged on a time card, and every subcontractor payment are assigned a cost code and recorded. These codes are used to compare actual job costs with the estimated job costs throughout the construction process. These cost codes usually start with the original CSI reference number associated with the activity, and then for further detail another number is assigned that represents the type of cost. For example: Activity Code

• Material 1 • Self-performed labor 2 • Subcontracted labor 3 • Equipment 4 • Job site overhead 5

So, if I were the job superintendent tracking building insulation cost on a project, I would assign the following cost codes to the invoices that came across my desk: Item Cost Code (CSI Number — Type of Cost)

• Material invoice 07 21 00-1 • Subcontractor bill 07 21 00-2 • Equipment rental 07 21 00-3

Larger contractors will also assign a year and job number to the cost code. For example, assuming that the previous project was a large contractor’s 14th job of this year, the material invoice might be coded as follows:

• Year project started: 2010 • Project no.: 14 • CSI division: 07 21 00 • Type of cost: 1 (material) • Cost code: 2010 14 07 21 00-1

41/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4533  

Smaller contractors might simply identify each of the invoices by the client name along with the cost code. Smith 07 21 00-1 the point is to make the codes as user-friendly as possible while still providing the level of detail needed to properly analyze the project costs. Each invoice amount would be recorded according to the cost code assigned to it by the superintendent. Material costs, labor costs, and equipment costs could be tracked separately, or you could combine them into a single work package total. Either way, you could compare the actual cost to do the building insulation with the budgeted amount and note any discrepancies. All invoices and subcontractor billings are eventually transferred to the contractor’s cost accounting department. The accounting department also tracks the project according to the cost codes and submits reports identifying total material, labor, subcontract, equipment, and overhead costs incurred on the job. The project manager uses these and other reports to monitor the project performance from a big-picture perspective. Spot Check the Cost Coding It’s not uncommon for a vendor to list more than one cost code item on a single invoice. For example, the same invoice could have materials that fall under three different divisions — let’s say lumber (Work packages 6), mortar (Work packages 4), and rebar (Work packages 3). When this happens, it is important to make sure that someone is taking the time to separate the material costs according to their respective Codes as shown in Figure 2.14. Unfortunately, people get lax, and they start lumping all of the material under one code. This, of course, taints the accuracy of the information, which results in faulty reporting. As a construction manager, I was always vigilant about doing random checks on job tickets just to make sure everything was being properly coded. It was part of my management systems quality assurance program.

42/144

Cha 

Figur

pter 2

re 2-14

Figu

"Propo

ure 2-14

osed apprroach to c

/4534 

construct model off cost conntrol"

 

 

43/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4535  

2.1.4- Depreciation

Depreciation is a necessary function in financial management, because without Depreciation the irregularities in the fundamental financial reports of a company would vary considerably and make it difficult to compare one year or one quarter to the next. This is because large investments in assets do not occur on a regular basis.

If the total cost of an investment were reflected in the financial time period in which it occurred, the effect on net profits would be considerable in this period, and then the net profit would rise significantly in the next period. What is done with depreciation? The cost of the new asset is spread out over the life of the asset. This allows the company to claim some of the cost each year rather than the total cost of the asset all at one time.

• Straight Line Depreciation

Straight line depreciation is the depreciation method that allows an equal amount of depreciation to be taken each year. The amount of depreciation is determined by subtracting the salvage value of the asset at the end of its useful life from the purchase price of the asset. The remaining value is called the book value. The book value is divided by the number of years, and this amount is expensed from the asset each year.

For example, a company buys a large machine for $1 million. The purchase is made with cash. In the accounts for this transaction, the cash account is reduced by $1 million, and the machine account is increased by the amount of $1 million. There is no effect on the liabilities or owner’s equity side of the accounting equation and it remains balanced.

The cost of this machine must eventually be recognized. The machine has a useful life of ten years and is worth $100,000 at the end of its useful life in terms of scrap value or the ability to sell the machine to someone else. This means that the value of the machine that must be depreciated is $900,000. Since the life of the machine is ten years, the value depreciated each year is $90,000. This is known as straight line depreciation (table 2-5).

44/144

Cha 

AccdepTheredamis tmu Thispaidthe Beyeaaccdou

T

pter 2

• Accele

celerated dpreciated fe reason fouced in a ount. In ahe same ach earlier

s means td in the ea taxes wil

cause of tars allow ucelerated duble declin

Table 2-5

"Propo

erated De

depreciatiofrom the aor this is tgiven yeaccelerated

as in straig in the use

hat more arly part ol be highe

the presenus to use tdepreciationing balanc

osed appr

epreciatio

on methodassets to bto reduce tr, the amod depreciaght line deeful life of

equipmenof the usefr than in s

nt value ofhat moneyon are comces.

roach to c

/4536 

on

ds are usebe applied the net proount of taxtion meth

epreciation the asset.

nt expenseful life of tstraight lin

f the money in the pr

mmonly us

construct

d to allow earlier in ofit after tx that a coods the to

n, but the .

e is recognhe asset p

ne depreci

ey, taxes tresent Yeased: sum o

model of

the expenthe usefultaxes (NOompany paotal amountime that

nized and lpurchasedation.

that are dears. Two tyof the yea

f cost con

nses that l life of thePAT). If Nays is lessnt of depre it is taken

ower taxe. In later y

eferred to ypes of rs’ digits a

ntrol"

 

 

are e asset. OPAT is s by this eciation n is

es are years

later

and

45/144

Cha 

Thefinaaccthe6, f

Thehigyeanumlowdivi

Likthemestadepremreayea

T

pter 2

• Sum oere is no sancial reascounting p years of tfor a ten Y

e amount ohest digit ar the last mber is the

wer year’s iding 9 by

• Doubl

ke the sum double dethod for andard accopreciable vmaining deched. With

ars is much

Table 2-6

Table 2-7

"Propo

of the Yeacientific bason for usiractice. Ththe useful

Year usefu

of depreciyear and year’s digen multipldigit is use 55. Each

le Declini

m of the yeeclining bacceleratinounting prvalue of thepreciable h this meth higher t

osed appr

ars’ Digitsasis for thng this cahe calculat life of thel life, the t

ation in thdividing th

git is used,ied by theed. In the year the n

ing Balan

ears’ digitsalance calcg the deprractice. Thhe item. Th value of tthod the ahan in the

roach to c

/4537 

ts. e sum of tlculation etion is made equipmetotal is 55

he first yeahis by the , making te book val second yenumerator

ces

s depreciaculation eireciation ohe percenthe next yehe item, amount tak

e later yea

construct

the Years’except thade by totant. Thus,

ar is deter sum of ththe calculaue. In theear the der declines

tion, thereither. It isof equipmet of deprecear’s depreand so on ken as deprs (table 2

model of

’ digits meat it has bealing the das can be

rmined by he years’ dation 10 di remaining

epreciationby one ye

e is no scie, howeverent and haciation is teciation is until the spreciation 2-7).

f cost con

ethod. Theecome a sigits repre seen in ta

taking thedigits. In thivided by 5g years, thn is calculaear.

entific basr, a consistas becometaken on th taken on salvage va in the ear

ntrol"

 

 

re is no tandard esenting able 2-

e he first 55. This he next ated by

sis for tent e a he the alue is rly

46/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4538  

2.2- Construct model template –Excel-Format

2.2.1- WBS template sheet

2.2.1.1- WBS sheet template consist:

The sheet consist of a group of column which we will fill it with date which we will knowing later the kind of date but first we will know the format of data but before illustrate the sheet format we must know the difference between budget & price

Budget: it consist of dry cost only the direct cost of item

Price: it consist of direct cost, percentage of in direct cost & over head

1- The first set will consist of WBS code according to BOQ 2- The second set will consist of item description and unit of measure 3- Third set it will consist of rate the budget rate (direct cost) & price rate 4- it will the Quantities column that is:

• Contract Quantity which we sign our contract about this Quantity • Actual Quantity it describe the situation of our quantity if it is above or

below the contract quantities • Invoice Quantity it describe the quantity we take from the client • Provision Quantity it describe we are execute but it doesn't add to the

invoice quantity

5- it will the Budget / price column that is • Contract Amount it describe the amount of money according to Price this

by multiply the contract rate with contract quantity • Budget Amount it describe the amount of money according to budget this

by multiply the budget rate with contract quantity • budget Forecast Amount it describe the amount of money according to

budget after change of quantity this by multiply the budget rate with Actual Quantity

• budget Allowance Amount it describe the amount of money according to budget but for invoice quantity this by multiply the budget rate with Invoice Quantity and Provision Quantity

• invoice Amount it describe the amount of money according to Price but for invoice quantity this by multiply the Price rate with Invoice Quantity and Provision Quantity

47/144

2.2.

Ta

Cha 

1.2- WBS

ble (2-8) W

pter 2

S sheet te

WBS shee

"Propo

emplate

et forms

osed appr

forms: a

roach to c

/4539 

as shown

construct

in table

model of

(2-8)

f cost conntrol"

 

 48/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4540  

2.2.2- Expenses template sheet

2.2.2.1- Expenses sheet template consist:

Expenses sheet it contain with every pent we spend on the project which consist of two major item

1- Direct Expenses which are • first set of column it describe the codes which we used with direct

expenses • The second ser will consist of item description and unit of measure • the third set of columns it describe the monthly expenses (unit, cost) • that last set is the cumulative cost , units

2- indirect Expenses which are

• first set of column it describe the codes which we used with direct expenses

• The second ser will consist of item description and unit of measure • the third set of columns it describe the monthly expenses (unit, cost) • That last set is the cumulative cost , units

49/144

Cha 

2.2.2

pter 2

2.2- Expe

• Direct

"Propo

enses sh

Expenses

Table (

osed appr

eet temp

sheet form

(2-9) Dire

roach to c

/4541 

plate for

ms

ct Expens

construct

rms: as s

es sheet f

model of

hown in ta

forms

f cost con

ble (2-9),

ntrol"

 

 

(2-10)

50/144

Cha  pter 2

• Indirec

T

"Propo

ct Expense

Table (2-10

osed appr

es sheet te

0) indirect

roach to c

/4542 

emplate fo

t Expenses

construct

orms

s sheet for

model of

rms

f cost conntrol"

 

 

51/144

Chapter 2  "Proposed approach to construct model of cost control"  

/4543  

2.2.3- Storage template sheet

2.2.3.1- Storage template sheet consist:

1- material storage • first set of column it describe the codes which we used with material

• The second ser will consist of item description and unit of measure

• the third set of columns it describe the amount of material that will

deduct or increase about expenses sheet (unit, cost) this material that doesn't include in work

2- Subcontractors reserve • first set of column it describe the codes which we used with material

• The second ser will consist of item description and unit of measure

• the third set of columns it describe the amount of work that will deduct

or increase about expenses sheet (unit, cost) but to Subcontractors

52/144

Cha 

2.2.3

pter 2

3.2- Stor

"Propo

age tem

Table (2-

osed appr

plate sh

-11) Stora

roach to c

/4544 

eet form

age sheet

construct

ms: as sho

forms

model of

own in table

f cost con

e (2-11)

ntrol"

 

 

53/144

Chapter  3  " the application steps & methods "  

3- the application steps & methods

Chapter 3  " the application steps & methods "

 

/421  

3- The application steps & methods

3.1-Collect Actual Cost data Once project work begins, the project manager systematically collects status information according to the methods and frequency previously determined. When status information is collected, the project manager compares it with the schedule, budgets, and scope identified in the project plan to determine the variances.

So before the project begins, the project manager should consult with the project team, the customer, and the client to determine the information needs, data collection methods, and frequency of data collection.

  

3.1.1- Sources of information

At the heart of every project control system are information and a good reporting process. Successful construction management and project control depend on sound information, which comes from actual project performance data. This data originates in the field and is reported on a daily, weekly, and monthly basis. The following are some of the sources of information used to track job performance and feedback into the project control system:

1. Job logs 2. Diaries 3. Daily field reports 4. Time cards 5. Visual Records 6. Correspondence 7. Subcontractor billing statements

However, this information serves two critical functions: It is used to detect variances between the actual cost, time, and productivity performance and the planned estimate and schedule. It is used to develop the historical estimating databases and productivity factors used on future projects. Let’s take a look at some of these mechanisms now.

1. Job Logs

Logs are used to track a number of regular activities occurring on the job site.

• Transmittal logs track the dates and addressees of all transmittals as well as the actual information being transmitted, such as shop drawings; product cut sheets, samples, or some other submittal.

54/144

Chapter 3  " the application steps & methods "

 

/422  

• Delivery logs help keep up with all of the material and equipment deliveries that are made to the site. The log contains the date of the delivery and the material received, and it notes any problems with the order and the actions taken.

• RFI logs track all requests for information submitted to the project participants and their responses. The date the RFI was sent and the date that the response was received are also noted in the log.

2. Diaries

Every member of the project team, but especially the superintendent, should be encouraged to keep a project diary. The diary is used to track all of the day’s events in a summarized fashion and in the individual’s own words. Diaries are used to note daily work activities, conversations, observations, and any other information worth recording. It is important that each member of the team keeps their own diary, because different people will have different interactions and conversations throughout the day. The diaries provide a reliable historic record and can become very important when disagreements or discrepancies arise on the job. Handwritten diaries are often permissible in courts as evidence of actual events and conversations.

3. Daily Field Reports

In addition to the informal project diaries, most construction companies require that a more formal record be kept. These field reports are intended to simplify the capture of some fundamental information needed to track job progress and confirm that various project requirements are being met the following are the types of information recorded:

• The name of the individual making the report • The date, project name, and location • A brief description of the day’s activities • The temperature and general weather conditions • The contractor’s own work forces on the job • The subcontractors’ personnel on the job site • Materials or equipment delivered • Equipment used on the job • Visitors to the job site • Other notable events

Daily reports are often summarized into weekly or monthly reports that are distributed to upper management within the company. These reports make up some of the data used to analyze project performance and make adjustments to the overall project plan.

55/144

Cha

4. T

If tgrelabomaext Theto cespcarma

On eacworcarfor Thelabosupasppurthetea

pter 3 

Time card

he populaeatest risk or recordsnagers in remely va

e time cardcalculate wpecially if yds providenager to t

large projch trade orrkers recods are com accuracy

e informator report, perintendepects of thrpose of thm with bum keep th

ds

r adage “T to the cons is one of the field. aluable to t

ds providewages andyou are one the fundtrack and m

jects, timer labor grord their hompleted, tbefore bei

ion gather typically p

ent. The ree work. La

he report iudgeted lahe project

Time is monstruction the most The data tthe constr

e the payrod distributene of the wamental inmonitor pr

e cards areoup workinours on a hey shoulding sent to

red from tprepared beport trackabor is cats to summbor costs. on target

Table (3-1)

" the a

/423 

oney” hold schedule importantthat they ruction com

oll clerk we paycheckworkers exnformationroductivity

e usually fng on the jweekly timd be revieo the payr

he time caby the supks labor hotegorized amarize cum This infor for meeti

Time Cards

applicatio

ds true, th and budget functionscollect by mpany.

with all of tks which ixpecting a n needed by and labo

filled out bjob. If it isme card. Iewed and croll clerk s

ards is useperintendeours and dand tracke

mulative larmation heng its cost

s

on steps &

en labor ret Keepins of constr way of tim

the informs pretty im check. Inby the con

or expendit

by superviss a small jn either inchecked byee table (

ed to creatent or assisdollars speed by costabor costs elps the mt and sche

& method

representsng accurateruction me cards i

ation needmportant, addition,

nstruction tures.

sory persoob, the in

nstance, oy the supe3-1).

te a weekstant

ent on varit codes, th and comp

managemeedule goals

ds "

 

 

s the e

s

ded

time

onnel for dividual nce the erintenden

ly

ous he pare nt s.

nt

56/144

Cha

5. V Youcertrecconwrit 6. C

Evepararcsupgrotheincl

pter 3 

Visual Re

u’ve heardtainly the ording wo

nstruction tten repor

Correspon ery day, nurticipants. hitects, en

ppliers, tesoups. All of duration lude the fo

• Submi• Payme• Punch • Chang• Reques• Letters• Emails• Faxes

cords

the expre case in cork progresmethods,

rts.

ndence

umerous c Emails, lengineers, osting organf the correof the proollowing:

ttals ent reques lists e orders sts for infos s

ession “A ponstructionss on the j highlight

communicetters, andowner repnizations, espondencoject. The

sts

ormation

" the a

/424 

picture is wn. There ajob site. Pand captu

ations ared faxes fly s, building governmece must betypes of d

applicatio

worth a thre many rrogress ph

ure problem

e generate back and g officials, ent agencie field andocuments

on steps &

housand wreasons fohotos helpm areas, a

d among t forth amo subcontraes, and co recorded

s that mus

& method

words.” Thir visually

p documenand supple

the projecong the actors, maommunity througho

st be saved

ds "

 

 

is is

nt ement

ct

aterial ut d

57/144

Chapter 3  " the application steps & methods "

 

/425  

3.1.2- Data Required From Procurement Department

 1. Requirements

• Log every 15 days with all material imported to each project log contain (material item ,code of material , supplier name , unit of price & quantity of PO)

• List of material that finished its finance benefits to double check on the

data from finance department.

• The procurement team shall record every material item in this log and attached with statement.

• The sub contractor contract shall be review by control team and soft copy of the contract shall be send to our team.

2. Flow chart It describe the process between Procurement team and other department as shown in figure (3-1)

58/144

 

Cha

3. ForWe we

pter 3 

rms will descr shown in

ribe differe table (3-2

Figure

ent form re2), (3-3), (  

e (3-1) data

" the a

/426 

equired fr(3-4)

a flow betw

applicatio

om Procur

ween Procu

on steps &

rement De

rement tea

& method

epartment

am and othe

ds "

 

 

as

er

 

59/144

Chapter 3 

Taable (3-2) L

" the a

/427 

Log of mate

applicatio

erial import

on steps &

ted

& methodds "

 

 

 

60/144

  

Chapter 3 

Taable (3-3) Q

" the a

/428 

Quotations

applicatio

s Compariso

on steps &

on Sheet

& methodds "

 

 

 

61/144

Chapter 3 

Table (3--4) Recommfor Quo

" the a

/429 

mended Suotations list

applicatio

bcontractot

on steps &

ors

& methodds "

 

 

 

62/144

Cha

3.1.3-

1. Req 

• da

• T

 2. Ste 

• H

i.

ii.

iii.

iv.

v.

• O

i.

ii.

iii.

• T

i.

ii.

pter 3 

- Data R

quiremen

deliver perasset in pr

The import

eps of wo

How we en

Record th The man

The storaafter chec

The storamanger

The accoumaterial d

Out of mat The sign The place The purp

The roll of Get daily The accoumust invo

Require

nts 

riodic reporoject and

tant of thi

ork

nter the m

he importe

on the ga

age man reck of exist

age make

unt take tdaily ,wee

terial from

of the For

e will take

ose of tak

site accou

report fro

unt make olve the co

Figure (3

ed From

ort from th date of in

s report to

material to

ed materia

ate sign off

eceive thet the sign

material c

he informaekly month

m the stora

rman or en

it

ken materi

unt

om the sto

every 15 ode of ma

-2) step of

" the a

/4210 

m Storag

he storagen and out t

o specify t

the projec

al on the e

f the bill o

e material of entranc

card and ta

ation and hly

age

ngineer

al

orage abou

day reporterial the

enter mate

applicatio

ges

e team conthe value o

the accura

ct see figu

entrance g

or receiving

and take cce gate

ake the ap

make the

ut in/out m

t about in amount of

erial to the

on steps &

ntain the cof bill if it

ate losses o

ure (3-2)

ate

g balance

copy of th

pproval fro

report of

material

/out matef money fr

project

& method

code of ma exist.

of materia

e bill or PO

om the pro

received

erial the rerom the b

ds "

 

 

aterial , all

al

O

oject

eport ill

l

63/144

Cha

iii.

iv.

3. Flo

It dsho

 

pter 3 

The accoreceived The reporraises to  

ow chart  

describe thown in figu

 

ount makeand purpo

rt will raiscontrol m

he processure (3-3) 

e every 15ose of usag

es to the anger

s between

Figure

" the a

/4211 

day reporge.

project ma

Storage t

(3-3) datao

applicatio

rt about o

anger then

eam and o

a flow betwother depar

on steps &

ut materia

n after app

other depa

ween Storagrtment

& method

al the plac

proval will

artment as

ge team and

ds "

 

 

ce of

l

s

d

 

64/144

 

Cha

4. For

We sho

pter 3 

rms

will descrown in tab

ribe differele (3-5), (

Table

ent form re(3-6), (3-7

e (3-5) Monm

" the a

/4212 

equired fr7)

nthly Repormovement

applicatio

om Storag

rt about sto

on steps &

ge Departm

ore

& method

ment as w

ds "

 

 

we

 

65/144

Chapter 3 

Table (3-6) Momaterial

" the a

/4213 

nthly Repo distributio

applicatio

ort about ns

on steps && methodds "

 

 

 

66/144

Cha

pter 3 

Tablemate

e (3-7) Monerial distribu

" the a

/4214 

nthly Reporutions and

applicatio

rt about location

on steps && methodds "

 

 

 

67/144

Chapter 3  " the application steps & methods "

 

/4215  

3.1.4- Data Required From Projects

1. Requirements

• Site send to the control team the client invoices with its supported survey.

• Sub contractor invoices.

• The pouring log for concrete to get the actual losses and for sure the quantity we pied to the supplier

• Bar binding list for steel to get the actual quantity &looses for steel and comparison with tender quantity.

• Summary for labor work during the period every 15 day with their activity attached with labor time card.

• Summary for the rent equipment and the activity the make during the period attached with their invoices.

• The equivalent between the client invoices and sub contractor.

• Periodic report for finishing item to know the actual quantity this will help us and the tender to make actual estimate for this items.

• The technical office update the quantity of the contract to get good forecasting to this contract.

• The technical office will submitted every variation order. 

  

 

 

 

 

 

 

 

 

 

 

 

 

68/144

Cha

2. Flo

It dsho

 

pter 3 

ow chart

describe thown in figu

he processure (3-4)

Figure (

s between

(3-4) data ot

" the a

/4216 

Project te

flow betwether depart

applicatio

eam and o

een Projecttment

on steps &

ther depa

ts team and

& method

rtment as

d

ds "

 

 

 

69/144

 

Cha

3. For

We

• La

Rep(3-

  

pter 3 

rms

will descr

abor 

ports requ12), (3-13

ribe differe

ired for la3), (3-14),

Table

ent form re

bor as we, (3-15)

e (3-8) Dai

" the a

/4217 

equired fr

shown in

ly man pow

applicatio

om Projec

table (3-8

wer for Sub

on steps &

ct Team

8), (3-9),

b contractor

& method

(3-10), (3

r

ds "

 

 

3-11),

 

70/144

Chapter 3 

Ta

Table

able (3-10)

(3-9) Daily

Weekly m

" the a

/4218 

y man powe

an power f

applicatio

er for self p

for self perf

on steps &

performed t

formed tim

& method

time card

e card

ds "

 

 

 

 

71/144

Cha

 

pter 3 

TTable (3-111) Subcontr

" the a

/4219 

ractor prod

applicatio

uctivity by

on steps &

location

& methodds "

 

 

 

72/144

 

Chapter 3 

Tab

Table

ble (3-13) m

e (3-12) ma

man power

" the a

/4220 

an power d

r estimation

applicatio

daily produc

n & actual q

on steps &

ction repor

quantity

& method

rt

ds "

 

 

 

 

73/144

Cha

 

pter 3 

Tabble (3-14) mman power

" the a

/4221 

distributio

applicatio

on by work

on steps &

package

& methodds "

 

 

 

74/144

Cha

 

pter 3 

Taable (3-15)

" the a

/4222 

Monthly St

applicatio

tatus log fo

on steps &

or manpowe

& method

er

ds "

 

 

 

75/144

Cha

• Eq  Re18 

  

pter 3 

quipment

eports req8), (3-19) 

uired for E

Table

Equipment

e (3-16) Da

" the a

/4223 

t as we sh

aily Equipm

applicatio

hown in tab

ent time ca

on steps &

ble (3-16)

ard

& method

), (3-17),

ds "

 

 

(3-

 

76/144

 

Chapter 3 

TTable (3-177) Equipme

" the a

/4224 

nt distribut

applicatio

tion by wor

on steps &

rk package

& method

ds "

 

 

 

77/144

 

Chapter 3 

Table (3--18) Month

" the a

/4225 

ly Status lo

applicatio

og for Equip

on steps &

pment

& methodds "

 

 

 

78/144

Cha

  

pter 3 

Table (3-199) Value of

" the a

/4226 

f rent Equip

applicatio

pment by w

on steps &

work packag

& method

ge

ds "

 

 

 

79/144

Cha

• Rep

Re(3

 

  

pter 3 

port 

eports req3-22), (3-2

uired for D23) 

Table (3

Different it

-20) log fo

" the a

/4227 

tems as w

r Concrete

applicatio

we shown i

Casting

on steps &

n table (3

& method

-20), (3-2

ds "

 

 

21),

 

80/144

Cha

 

 

pter 3 

Ta

Tab

able (3-21)

ble (3-22)

Report abo

Monitor Re

" the a

/4228 

out Perform

eport for Fin

applicatio

mance by a

nishing item

on steps &

ctivity

m (masonry

& method

y)

ds "

 

 

 

 

81/144

Cha

  

pter 3 

Tabble (3-23) CCost report

" the a

/4229 

t include lab

applicatio

bor, Equipm

on steps &

ment and m

& method

material

ds "

 

 

 

82/144

 

Cha

3.1.5-

1. Req

• Thexpr

• Fix

• Fode

2. Flo

It dsho

pter 3 

- Data R

quiremen

he finance xpenses onroject duri

xed asset

or fully depepartment

ow chart

describe thown in figu

Require

nts

departmenly the exng the mo

and the a

preciated at.

he processure (3-5)

Figure

ed From

ent gives tpenses heonth maxim

mount of

asset we p

s between

e (3-5) data

" the a

/4230 

m Financ

the controe had the smum after

depreciate

put rent a

Finance te

a flow betw

applicatio

ce Depa

l departmsupported r 7 day of

ed per mo

mount wit

eam and o

ween Finan

on steps &

artment

ent the ex document the new m

onth.

th help of

other depa

ce team an

& method

t

xpenses nots-of the month.

procureme

artment as

nd other de

ds "

 

 

ot all

ent

s

partment

 

83/144

 

Cha

3. ForRep 

pter 3 

rms ports required for Di

Table (3-24

ifferent ite

4) Monthly

" the a

/4231 

ems as we

Report for

applicatio

e shown in

r Finance de

on steps &

table (3-2

epartment

& method

24)  

ds "

 

 

 

84/144

Cha

3.2-Ac

Nowtypthe

3.2.As

pter 3 

ctual Co

w after wee of data cost cont

1- WBS s2- Expens3- Storag

1-WBS shown in T

ost Allo

e create thhow we altrol model

heet ses sheet

ge sheet

Sheet tTable (3-2

ocations

he model fllocate this in

templat25)

Table (3-2

" the a

/4232 

s

for cost cos data in o

te form

25) WBS Sh

applicatio

ntrol and our model

m

heet Form

on steps &

we get the before we

& method

e differente summari

ds "

 

 

t ize

85/144

Cha

3.2

AfteWBupdlast

pter 3 

.1.1-cli

er we get BS form wedate to thet invoice th

ient inv

the client e put the fe cost conthis shown

T

voices

invoices wfinal quanttrol we rep in Table (

Table (3-26

" the a

/4233 

we start totity in the place the o(3-26)

6) Sample o

applicatio

o take the form of Wold quanti

of Client Inv

on steps &

data and WBS sheet

ty with ne

voice

& method

fill it into and in evew quantit

ds "

 

 

the ery

ty in

86/144

Cha

3.2

pter 3 

.1.2-Va

In casevariatiquantitcolumn28)

ariation

e of approons activaty columnn in WBS f

Table (3-

Ta

ns Order

oved changate in WBS and we pform the v

27) Sample

ble (3-28)

" the a

/4234 

r

ge order (vS form andput zero quvariation o

e of Cover f

Sample of

applicatio

variationsd put the nuantity in order show

for Variatio

Variation

on steps &

) we insernew quantcontract q

wn in table

on Order

& method

rt the tity in actuquantity e (3-27), (

ds "

 

 

ual

3-

87/144

Cha

3.2.2• DiW

pter 3 

2- Expeirect expene put the

enses Snses Direct exp

Ta

Sheet te

panses in t

able (3-29)

" the a

/4235 

emplate

that form

) Direct Exp

applicatio

e form

that show

penses she

on steps &

wn in table

eet forms

& method

(3-29)

ds "

 

 

88/144

Cha

• InW

pter 3 

ndirect expe put the

penses indirect ex

Tabl

xpanses in

le (3-30) in

" the a

/4236 

n that form

ndirect Exp

applicatio

m that sho

enses shee

on steps &

own in tab

et forms

& method

le (3-30)

ds "

 

 

89/144

Cha

3.2.3

Thewe this

pter 3 

3-Finan

e finance d take this s shown in

nce Rep

departmendata and p

n table (3-

T

port

nts make tput it in th31).

Table (3-31

" the a

/4237 

the report he expense

1) Finance R

applicatio

of monthes sheet if

Report form

on steps &

ly expensef it direct o

ms

& method

es for projor indirect

ds "

 

 

ject t

90/144

Cha

3.2.4

It is cor valshown

pter 3 

4-Stora

ontain theue of workn in table (

Ta

age She

e deduct ok for sub c(3-32)

able (3-32)

eet tem

r increasecontractor

) Deduction

" the a

/4238 

plate F

e value of m that will d

n /Increase

applicatio

orm

money if ideduct fro

e Storage S

on steps &

t material om expens

Sheet Form

& method

in store ases sheet t

ds "

 

 

area that

91/144

Cha

3.2.4

pter 3 

4.1-Sto

The stothe stotake frFinanc

orage R

orage deporage thatrom ce departm

Ta

eport

partment s you dedu

ment that s

able (3-33)

" the a

/4239 

sent monthuct from yo

shown in t

Storage Sh

applicatio

hly report our month

table (3-33

heet Form

on steps &

about thehly expens

3)

& method

e quantity ses that yo

ds "

 

 

in ou

92/144

Cha

3.3- HInform

1-yandtak

a-co

b-cocli

pter 3 

How Do mation?

you must ed the subce less tha

- you increontractor a

- You deduolumn thatient.

You Ma?

equate betontractor n the subc

ease the qand the ad

uct from tht in case y

ake Sur

tween the invoice ascontractor

uantity of dd quantity

he sub conyou are su

Ta(client

" the a

/4240 

re You A

quantity ys Shown inr so you ha

client till y putted in

ntractor core that yo

able (3-34)t/subcontr

applicatio

Are Get

you puttedn table (3-ave to two

it equivalen the prov

olumn in su will take

) equate ofractor) qua

on steps &

tting Go

d in the cl-34) in somo solutions

ent to the vision colum

storage shee this quan

f ntity

& method

ood

ient invoicme cases ys.

sub mn.

eet in dedntity from

ds "

 

 

ce you

uct the

93/144

Cha

2-ytoldthesupputincr

3-yconof squathe

pter 3 

you must sd you wha project sh

ppler impot still you drease the

you must tncrete quasteel rebarantity of st same cas

sure that tt we paid hown in tart the statdon’t paid quantity o

take the suntity in clir as shownteel imporse of concr

Table

the quantit almost eqable (3-35tement de so you mof concrete

urvey of stient invoicn in table rted to therete

e (3-35) Co

" the a

/4241 

ty of concqual to the) this hap

elayed so aust sure fre in storag

teel rebar ce you ma(3-36) als

e site and t

oncrete Cas

applicatio

rete in thee pouring lpen becauactually yorom this pge sheet

in case ofke this to

so you musthe quanti

sting Report

on steps &

e Finance og that youse some tou poured point in thi

f RFT incluget the acst sure thaity of stee

t

& method

report thaou take frotime the this quanis case you

ude in ctual losseat from thl in financ

ds "

 

 

at om

tity u

es e

ce it

94/144

 

Cha

4 - aquyoyode

5 - afin

6 - yty

7 - fdaan

pter 3 

also you muantity in sou must mou take froecision

also you mnance repo

you must ype of work

final to maate to comnalysis

must trackstorage re

make someom them t

must trackort and nu

have repok package

ake sure ompare and

Tab

k and compeport and fe communthe inform

k and compumber of la

ort that Dise

of date you reach to t

ble (3-36) S

" the a

/4242 

pare betwefinance reication betation to m

pare betweabor you g

stributed t

u must havthe accura

Steel losses

applicatio

een the daport and itween the

make sure

een the nuget from p

the non sk

ve greaterte data yo

s Report

on steps &

ate you han case of

e different and get th

umber of lproject

kill labor o

r than oneou based o

& method

ave like thany conflic party thathe final

labor from

n different

e source ofon it your

ds "

 

 

e ct t

m

t

f

95/144

Chapter  4  "Reporting Techniques"

 

4- Reporting Techniques 

Cha

4.1- T

In tmabelishowerwanfor,abilmo Simuseusesmaplottabnegschsch It mmame

Fi

pter 4 

4- T

he Earn

the early ynagers weieved thatown in (Figre managinted costs, or reportlities to mment's no

mply put, e to monitoe is not limall and metting both le. Once u

gative variedule alonedule and

may very wking it unpasured sim

igure (4-1)

Techn

ned Val

years of prere havingt status cogure 4–1).ng costs os to be mted. Projeconitor and

otice. Earn

earned vaor, track,

mited just tedium size the projeused, the pances. Thne and mad that the

well be theprofitable.multaneou

iques

lue Mea

roject mang difficulty ould be det The critic

or just momanaged ct managed report aced value o

alue is a prand reportto the suped projectsct schedulproject mae project

ake the asproject is

e case tha This is w

usly to gain

" Tech

5/31

of ou

asureme

nagement determinitermined ocal questionitoring co rather th

ers need toccurately ooffers this

roject techt on the p

per projects. The techle and cosanager canmanager csumption doing wel

t the projehy both scn a more a

hniques o

utputs

ent Sys

, it becaming projectonly by a on was whosts. The han just o have theon their pr ability.

hnique thaerformancts, as it aphnique lenst values on very quicannot justhat projel.

ect is excechedule anaccurate p

of output

s & rep

stem (E

me evident t status. Smystical aether proj project mmonitorede necessarroject perf

at project mce of any ppplies equands itself ton an S-cuckly highlist measureect tasks a

eeding prond cost hapicture (se

ts & repor

ports

EVMS)

that projeSome peo

approach, ject managmanagers d, accountery tools anformance

managers project. Itally to boto jointly rve chart ight positive the projeare ahead

oject costsve to be

ee Figure 4

rts"

 

 

ect ople as gers ed

nd at a

can ts h

or ve or ect of

s,

4.2).

96/144

Cha

ThisEarplanvaluthema The

• a• E• E• B

The

• W• W• W• W• W

Figur

pter 4 

s need resrned valuenning to ue manag primary tnagement

e EVMS p

accurate dEarly and aEarly and aBasis for c

e EVMS c

What is thWhat are tWhat can bWhat is thWhat are t

re (4-2)

sulted in the is a m schedulesement (EVtool for intt? Without

provides t

isplay of paccurate idaccurate idourse corr

an answe

e true statthe problebe done toe impact othe presen

he creatioanagemens and tecVM) is a sytegrating ct using the

the follow

project stadentificatidentificatirections

er the fol

tus of the ms? o fix the pof each pront and futu

" Tech

5/32

n of the Ent techniqchnical peystematic cost, schede EVMS, de

wing bene

atus on of trenon of prob

lowing qu

project?

roblems? oblem? ure risks?

hniques o

VMS. The que that erformance process thdule, and etermining

efits:

ds blems

uestions:

of output

basis for relates rese requiremhat uses etechnical g status ca

:

ts & repor

the EVMSsource ments. Eaearned valperformanan be diffic

rts"

 

 

.

arned ue as nce cult.

97/144

Chapter 4  " Techniques of outputs & reports"

 

5/33  

4.1.1- Variance and Earned Value

The EVMS emphasizes prevention over cures by identifying and resolving problems early. The EVMS is an early warning system allowing for early identification of trends and variances from the plan. The EVMS provides an early warning system, thus allowing the project manager sufficient time to make course corrections in small increments. It is usually easier to correct small variances as opposed to large variances. Therefore, the EVMS should be used continuously throughout the project in order to detect the variances while they are small and possibly easy to correct. Large variances are more difficult to correct and run the risk that the cost to correct the large variance may displease management to the point where the project may be canceled.

A variance is defined as any schedule, technical performance, or cost deviation from a specific plan. Variances must be tracked and reported. They should be mitigated through corrective actions and not eliminated through a baseline change unless there is a good reason. Variances are used by all levels of management to verify the budgeting system and the scheduling system.

The budgeting and scheduling system variance must be compared because:

• The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.

• The scheduling variance provides a comparison between planned and actual

performance but does not include costs.

• Budgeted cost for work scheduled (BCWS) is the budgeted amount of cost for work scheduled to be accomplished in a given time period.

• Budget cost for work performed (BCWP) is the budgeted amount of cost for

completed work, within a given time period. This is sometimes referred to as “earned value".

• Actual cost for work performed (ACWP) is the amount reported as actually

expended in completing the work accomplished within a given time period. BCWS represents the time-phased budget plan against which performance is measured. For the total contract, BCWS is normally the negotiated contract plus the estimated cost of authorized but UN priced work.

It is time-phased by the assignment of budgets to scheduled increments of work. For any given time period, BCWS is determined at the cost account level by totaling budgets for all work packages, plus the budget for the portion of in-process work.

● Cost variance (CV) calculation:

CV = BCWP - ACWP

A negative variance indicates a cost-overrun condition.

● Schedule variance (SV) calculation:

98/144

Cha

S

A necostworpro

C

S

TheAs afirst$32alon

Howschesimform

Fig

pter 4 

SV= BCWP

egative vart and schedrds, the schblem, the v

Cost varian

Schedule va

e schedule van examplet four week25K. Therefne, there ar

wever, if BCedule and oultaneously

mulae show

gure (4-3)

– BCWS

riance indicdule, costs hedule variavariances a

ce % (CVP

ariance % (

variance me, consider ks of the prfore, BCWSre several p

CWP is nowoverrunningy monitor a

wn in (Figur

cates a beh are used aance is givere usually c

) =CV/BCW

(SVP) =SV/

ay be repre a project troject. The S $400K andpossible ex

w known, sag costs Usiand control re 4.3).

" Tech

5/34

ind-schedus the lowesen as a funconverted t

WP

/BCWS

esented by hat is scheactual exped ACWP $3

xplanations

ay $300K, ang earned both sched

hniques o

ule conditiost commonction of costo percenta

hours, dayduled to spenditures a25K. From as to proje

and then thvalue, projdule and co

of output

n. In the an denominatst. To allevages:

ys, weeks, pend $100Kt the end o these two ect status.

he project isect manag

ost using th

ts & repor

nalysis of btor. In othe

viate this

or even doK for each oof week fou parameter

s behind ers are able

he set of

rts"

 

 

both er

llars. of the ur are rs

e to

99/144

Chapter 4  " Techniques of outputs & reports"

 

5/35  

4.1.2- Methods for Physical Progressing (The 50-50 and 0–100 Rules)

Many project managers traditionally report project schedule progress by using an incremental estimation method. This method normally starts by estimating tasks at levels such as 15 percent, 40 percent, 78 percent, or 98 percent, incrementally moving forward until 100 percent complete.

This process is based on no proper quantitative measurement and is often inaccurate. Additionally, this information is, in turn, submitted to either the project office or executives to review, and perceptions at the senior level are based on inaccurate project data. Project managers could possibly consider adopting a more accurate method of reporting on project progress.

In the project world, two of these methods are the 50-50 and 0–100 rules. However, the 50-50 rule is more commonly used. The important thing to remember is to keep it simple .Remember that keeping the schedule variance simple on the progress reporting side makes calculating the EV easier to manage.

The way to implement the 50-50 rule is fairly straightforward.

• Assign 50 percent of the BCWP to the task the moment the task is started. At this point it is assumed that half the work has been done already.

• Assign 100 percent of the BCWP the moment the task ends. This is only allocated once the task actually finishes.

The cost variance relates to the real cost. However, the problem with SV is how it relates to the real schedule. The schedule variance is determined from cost account or work package financial numbers and does not necessarily relate to the real schedule. The schedule variance does not distinguish between critical path and non–critical path work packages.

The schedule variance by itself does not measure time. A negative schedule variance indicates a behind-schedule condition but does not mean that the critical path has slipped. On the contrary, the real schedule (i.e., precedence networks or the arrow diagramming networks) could indicate that the project will be ahead of schedule. A detailed analysis of the real schedule is still required irrespective of the value for the schedule variance.

Permitted variances may be dependent on such factors as:

• Life-cycle phase • Length of life-cycle phase • Length of project • Type of estimate • Accuracy of estimate

100/144

Chapter 4  " Techniques of outputs & reports"

 

5/36  

By using both cost and schedule variance, we can develop an integrated cost/schedule reporting system that provides the basis for variance analysis by measuring cost performance in relation to work accomplished. This system ensures that both cost budgeting and performance scheduling are constructed on the same database. In addition to calculating the cost and schedule variances in terms of dollars or percentages, we also want to know how efficiently the work has been accomplished.

The formulas used to calculate the performance efficiency as a percentage of EV are:

Cost performance index (CPI) =BCWP/ACWP

Schedule performance index (SPI) =BCWP/BCWS

The difficulty in performing variance analysis is the calculation of BCWP because one must predict the percent complete.

The simplest formula for calculating BCWP is:

BCWP = (% complete) X BAC

Most people calculate “percent complete” based upon task durations. However, a more accurate representation would be to calculate “percent work complete.” However, this requires a schedule that is resource loaded. To eliminate this problem, many companies use standard dollar expenditures for the project, regardless of percent complete.

For example, we could say that 10 percent of the costs are to be “booked” for each 10 percent of the time interval. Another technique, and perhaps the most common, is the 50/50 rule: Half of the budget for each element is recorded at the time that the work is scheduled to begin, and the other half at the time that the work is scheduled to be completed.

For a project with a large number of elements, the amount of distortion from such a procedure is minimal. (Figures 4-4, 4-5 and 4–6 illustrate this technique.) One advantage of using the 50/50 rule is that it eliminates the necessity for the continuous determination of the percent complete.

However, if percent complete can be determined, then percent complete can be plotted against time expended, as shown in (Figure 4–6). There are techniques available other than the 50/50 rule:

• 0/100: Usually limited to work packages (activities) of small duration (i.e., less than one month). No value is earned until the activity is complete.

• Milestone: This is used for long work packages with associated interim milestones, or a functional group of activities with a milestone

101/144

Cha

emm

pter 4 

establishedmilestone milestone

Figure (4-4)

d at identiis completrather tha

)

fied contrted. In thean the wor

" Tech

5/37

ol points. ese cases,rk package

hniques o

Value is e a budget es.

of output

earned whe is assigne

ts & repor

en the ed to the

rts"

 

 

102/144

Cha

• P(v

• Ee

Figure

pter 4 

Percent c(i.e., threevalue earn

Equivalenearnings a

(4-5)

Figure (4

complete:e months oned would

nt units: re on com

4-6)

: Usuallyor more) w be the rep

Used formpleted un

" Tech

5/38

y invoked where mileported per

r multiple its, rather

hniques o

for long-destones carcent of th

similar-unr than labo

of output

uration woannot be idhe budget.

nit work paor.

ts & repor

ork packadentified. T

ackages, w

rts"

 

 

ges The

where

103/144

Cha

• Cd

• Loep

4.1.3-

Contha$66ove

• B• B• A• E

It is

• R

6

• C

6

Not56.$78thasign

pter 4 

Cost formduration w

Level of often usedearned is bphysical pr

- Examp

nsider the t the Budg

60,000 corerall projec

Budget at Budget VaActual ValuEarned Va

s possible

Resource F

660,000–7

Cost Varia

621,280–7

te that $4048% prog

8,720 are t was schen indicates

Figure (4

mula (80/work packa

effort: d for supebased on trogressing

ple – Sy

case-examget Value rrespondinct provide

Completiolue (BV) =ue (AV) = lue (EV) =

to compu

Flow Varia

700,000 =

nce = EV

700,000 =

0,000 are gress, whethe costs eduled to s loss of v

-7)

/20): A ages.

This metervision antime (Figug

ynthetic

mple discuat 10 mon

ng to 60%s the follo

on (BAC) == BCWS = ACWP =

= BCWP =

te the var

nce = BV

–40,000$

– AV

–78,720$

the accouere the minthat will bbe performalue.

" Tech

5/39

variation o

thod is band managere 4-7) illu

c EVA

ussed thronth into th

% of progrewing:

= $1,100,0 $660,000$700,000 $621,280

riances of

– AV

$

$

unted extranus sign mbe consummed within

hniques o

of percent

ased on ement woustrates th

oughout thhe project ess. Recall

000 0 0

the overa

a costs comeans a loed to attan 10 mont

of output

t complete

the passark packaghree meth

his chapterwas scheding of the

ll project:

nsumed toss of mon

ain the 60%ths. Here a

ts & repor

e for long-

age of times. The va

hods for

r and suppduled to be figures fo

o reach ey. Althou

% progresalso the m

rts"

 

 

me, alue

pose e

or the

ugh, ss minus

104/144

Cha

Also

• S

ThavarcosSynsumma

Alsotim(daquiccorEarpretheind Thebelobetfrom Cloindeweishoagg

Figure (4-

pter 4 

o, the sch

SV = 621,

at is exactriance. Thist than estnthetic calms of prognager for

o, resource/cost cha

ashed line ck graphicrective actrned Valueesented wi referenceicates the

e best caseow the EVtter than sm the PV o

se reasonexes: aggighted sumowing thatgregate SI

-8)

edule vari

280–660,0

ly the diffes tells tha

timated, asculation o

gress and ocommunic

ce, cost anart using Sin Fig. 4-8

cal understions to th

e S-curvesth Fig. 4-9e curve lin project is

e-scenarioV: in this ccheduled.one, the la

ing can beregate ind

m of activi the best c for a proj

ance is:

000 = –38

erence bett the projes well as $f varianceoverall valcation and

nd schedulS-curves o8) and BCWtanding of

he project s can have9. One mue: whethe

s over bud

o is the onase both t The morearger the l

e conductedexes can ty performcase-scenject are m

" Tech

5/310

8,720$

tween theect is cons$38,720 toes for the olues, is of

d rapid rep

e varianceof BCWS (dWP (solid f the proje strategy. e six possibust look at er the AV oget or is b

e where bthe cost ane the distaloss or gai

ed for Cost be obtainemance indeario is wh

more than 1

hniques o

cost and suming $4o perform overall pro great conporting.

es can be dotted lineline in Fig

ect status Planned (ble arrang the positior the PV abehind sch

both the AVnd the durance of thein of value

t and Scheed for the exes. (Figuen both th1.

of output

the resou40,000 as the schedoject, usinvenience t

representee in Fig. 4-. 4-8). Thfor suggesScheduledements, aion of the above the

hedule.

V and the ration are e AV and Be and sche

edule perf overall prure 4-10) he aggrega

ts & repor

rce flow more actu

dule delay.g weighteto the pro

ed in a -8), ACWPis enablesstion of gld), Actual as in the c EV S-curv EV curve

BV curves performinBV curve liedule.

formance roject by is a chart ate CI and

rts"

 

 

ual . d ject

P s a obal and hart ve as

s are ng ines

d

105/144

Cha

Whinfoissuof tdetaboin f

Earscha siTheis wrec

pter 4 

ereas a syormation oues, analythe job statailed repoout the pafinding out

rned valueedule delaimilar situe Cost Varworth notinording a p

ynthetic reoverload totic EVA pr

atus throuort based orts of a jot why the j

e (EV). Foray, with mation, whe

riance Repng that thepositive va

eport of tho direct throvides gregh investion activityb that arejob is in it

r example,more seriouere scheduort for thee activity “

alue of the

Figure (4

" Tech

5/311

e overall phe project’eater detagation of i

y breakdow behind scts current

, A1 indicaus problemule delay ie example“Columns RV. This

4-9) graphica

hniques o

project pes decisionils to allowindividual wn informschedule anstatus.

ates both cms on costs more sig-project is procuremis pretty t

al project sta

of output

erformance-makers tw a better activity pes the projend over bu

cost overrt than on sgnificant ts given in

ment” is thericky: inde

atus

ts & repor

e prevent to the maj understanerformancect managudget and

uns and schedule. han extra (Table 4.1e only oneeed, that t

rts"

 

 

from or nding ce. A ger helps

A2 is cost 1). It e task

106/144

Cha

is tan

Dela wprowoupro

pter 4 

he one witincreased

ay. The rewhole: it seovide mateuld have b

oject team

Figur

th the bigg unit cost

eason mayeems that erials up tobeen highl tightly wo

Table (4

re (4-10)

gest probland a sch

y be found the pre-co a 49% oighted theork with th

-1)

" Tech

5/312

ems (a needule

d in the proast colum

of units. A e supply prhe supplie

hniques o

egative CV

ocuremenns manufatimely perroblem ahr and avoi

of output

V of $43,20

t process acturer storformanceead of timid the inco

ts & repor

00) with b

of columnopped to e reportingme to haveonveniency

rts"

 

 

both

ns as

g e the y.

107/144

Chapter 4  " Techniques of outputs & reports"

 

5/313  

4.2–Reporting Techniques

4.2.1- Report Content

The program team member may receive a team critical variance report that lists variances in his organization at the lowest level of the work breakdown structure at the division cost center level by cost element. Upon request of the program manager, analyses of variances contributing to the variances on the team critical variance report are summarized by the responsible program team member and reviewed with the program manager. The preparation of status reports, whether they are for internal management or for the customer, should, at minimum, answer fundamental questions: • Where are we today (with respect to time and cost)? • Where will we end up (with respect to time and cost)? • What is the problem causing the variance? • What is the impact on time, cost, and performance? • What is the impact on other efforts, if any? • What corrective action is planned or under way? • What are the expected results of the corrective action?

The information necessary to answer these questions can be obtained from the following formulas:

• Budgeted cost for work scheduled (BCWS) • Budgeted cost for work performed (BCWP) • Actual cost for work performed (ACWP) • Estimated cost at completion • Budgeted cost at completion • Cost and schedule variances/explanations • Traceability • Percent complete • Percent money spent • Estimate at completion (EAC) • the remaining critical path • SPI (trend analysis) • CPI (trend analysis)

108/144

Chapter 4  " Techniques of outputs & reports"

 

5/314  

We can use CPI and SPI to forecast the expected final cost and the expected end date of the project. We can express the cost at completion, EAC, as:

EAC =BAC/CPI The time at completion uses SPI for the forecast and can be expressed as: ETC New project length = original project length/SPI

Care must be taken with the use of SPI to calculate the new project length because a favorable vale for SPI (i.e., 1.0) could be the result of work packages that are not on the critical path. Once EAC and the new project length are calculated, we can calculate the variance at completion (VAC) and the estimated cost to complete (ETC) using the following two formulas:

VAC = BAC - EAC and ETC = EAC – ACWP Percent complete and percent money spent can be obtained from the following formulas:

Percent complete =BCWP/BAC Percent money spent =ACWP/BAC

Where BAC is the budget at completion. The program manager uses this information to review the program status with upper level management. This review is normally on a monthly basis on large projects.

4.2.2- Reporting Considerations

As you prepare reports, use the following guidelines: Maintain concise, top-quality project plans and status reports. Be sure everything you publish is accurate. Keep all stakeholders appropriately informed, including team members, customers, clients, functional managers, and senior management. Determine for each audience what information they need to perform their functions and design reports accordingly. Keep them informed—but not over-informed—with the information they need to make decisions and take corrective action. Use exception reporting by including only major variations from the plan. Stakeholders don’t have time to digest pages and pages of project information, and there is little need to report on items where status matches the plans. Use software programs to analyze project information and report on variances from the project plans. Establish problem-reporting thresholds. Determine how significant a variation from the plan needs to be before you report on it. For example, establish thresholds for how many dollars over budget or how many days late. Choose the best format for the report, such as a table, line graph, histogram, or bar or Gantt chart. On each report, clearly state the purpose of the report and the action to be taken.

109/144

Chapter 4  " Techniques of outputs & reports"

 

5/315  

4.2.3- SAMPLE REPORTS

1. STATUS REPORTING

One of the best ways of reducing executive meddling on projects is to provide executives with frequent, meaningful status reports. Figure 4–11 shows a relatively simple status report based upon data accumulation in the form of Figures 4–12, 4–13, 4-14 and 4-15. These types of status reports should be short and concise, containing pertinent information only. Status can also be shown graphically. As the available project management software becomes more sophisticated, so does project reporting. There are four types of reports that are generally printed out from the earned value measurement system: • Performance Reports: These reports indicate the physical progress to

date, namely, BCWS, BCWP, and ACWP. The report might also include information on material procurement, delivery, and usage, but most companies have separate reports on materials.

• Status Reports: These reports identify where we are today and use the information from the performance reports to calculate SV and CV.

• Projection Reports: These reports calculate EAC, ETC, SPI, and CPI as

well as any other forward-looking projections. These reports emphasize where we will end up.

• Exception Reports: These reports identify exceptions, problems, or situations that exceed the threshold limits on such items as variances, cash flow, resources assigned, and other such topics. Reporting procedures for variance analysis should be as brief as possible. The reason for this is simple: the shorter and more concise the report, the faster that feedback can be generated and responses developed. Time is critical if rescheduling must be accomplished with limited resources. The two most common situations providing constraints on resource rescheduling are that:

⎯ The end date is fixed

⎯ The resources available are constant (or limited) With a fixed end date, program rescheduling generally requires that additional resources be supplied. In the second situation, program slippage may be the only alternative unless a constant stream of resources can be redistributed so as to shorten the length of the critical path. Once the variance analysis is completed, both project and functional management must diagnose the problem and search for corrective actions. This includes: finding the cure for the problem & developing a plan to recover the position

110/144

Cha

F

pter 4 

Figure (4-11)

Figure (4-

)

-12)

" Tech

5/316

hniques oof outputts & reporrts"

 

 

111/144

Chapter 4 

Figure (4-13)

Figure (4-1

" Tech

5/317

14) Performa

hniques o

ance Report

of outputts & reporrts"

 

 

112/144

Cha

2. VarAs

pter 4 

riance anshown in t

F

nalysis table (4-2

Figure (4-15

Table (4-2

), (4-3)

) Progress T

2) Variance

" Tech

5/318

Trends Repor

analysis Rep

hniques o

rt

port

of outputts & repor

rts"

 

 

113/144

Cha

3. CO

Thescha g • C

• C Therep

pter 4 

ST SUMM

e simple spedule repoiven perio

Cumulativ

The spreashows cumcompletio

Cumulativ

e report inport, but in

MARY

preadsheeorts, but p

od.

ve Cost R

adsheet in mulative cn of the p

ve Cost L

Figure 4-n graphica

Tab

et in Figureprovides fi

Report.

Figure 4-costs to daroject.

Line Graph

-19 shows l form.

ble (4-3) Ove

" Tech

5/319

e 4-16 listnancial da

17, 4-18 iate and the

h

the same

erall Progres

hniques o

ts the samata (rather

s similar te anticipat

informati

ss Report

of output

me steps asr than sch

to the costted total c

on as the

ts & repor

s the prevedule data

t report bucosts at the

previous

rts"

 

 

ious a) for

ut e

114/144

Cha

F

pter 4 

Figure (4-1

Figure (4-17

16) 

)  

" Tech

5/320

hniques oof outputts & reporrts"

 

 

115/144

Chapter 4 

Figure (4-18) Cu

" Tech

5/321

umulative co

hniques o

ost report

of outputts & reporrts"

 

 

116/144

Cha

4. SCH

Becplanrepactand • S Thethesteinfo

pter 4 

HEDULE S

cause evern, a projec

port on proivities are d actual st

Summary

e chart in F individuaps. This reormation.

Figure (4-19

SUMMARY

ryone invoct manageogress thro completeart and Fi

Schedule

Figure 4-1l activitieseport is se It is also

9)  

Y

olved with er may deoughout thd, solid linnish dates

Status Re

12,4-13 is s have beeent to recip called a m

" Tech

5/322

the projeccide to usehe life of tnes are dras appear in

eport

identical ten removepients whomilestone s

hniques o

ct is famile the samthe projectawn throun the appr

to the chaed, leavingo only requschedule a

of output

iar with the chart tot (see Figugh the gra

ropriate co

rt in Figurg only the uire summas seen in

ts & repor

he baseline monitor aure 4-11). ay activityolumns.

re 4-11 exsummary

mary figure 4-1

rts"

 

 

e and As

y bars

xcept

14.

117/144

Cha

Figure (4

Figure (

F

pter 4 

4-20) 

(4-21) 

Figure (4-22) Weeks Staatus Perform

" Tech

5/323

ance

hniques oof outputts & reporrts"

 

 

118/144

Cha

5. Ins

Reprepone

.

pter 4 

structions

ports are mport and the company

Figure (4-2

s on Repo

most helpfhe action ry division t

Figure (4-2

4) 

orts

ful when trequested.to another

3) millstone

" Tech

5/324

hey clearly Consider r.

s Summary

hniques o

y explain t the repor

report

of output

the purposrt in Figure

ts & repor

se of the e 4-15 from

rts"

 

 

m

119/144

Cha

6. Exc

ExcplanPercomreq

pter 4 

ception &

ception repn as showrcent compmpleted onuired for t

Figure

& note Re

port a repwn in Figureplete. A mn an activithe activity

e (4-25) 

Figure

port

port that se 4-16, 4-ethod of rty is exprey

e (4-26) note

" Tech

5/325

hows only-17 and 4-reporting wessed as a

e on perform

hniques o

y major de-18 ratherwhere the a percent o

mance report

of output

eviations frr than all d amount oof the tota

t

ts & repor

rom the pdeviations.of work al work

rts"

 

 

roject .

120/144

Cha

7. GR

It isrepwheThis A spagsignGrered

pter 4 

RAPHICAL

s importanports contaether the s is particu

imple pie ge full of tenal as a vieen means.

Figure

L REPORT

nt to makeain only threports caularly usef

chart or liext or numisual indicas the proje

Figur

(4-28) 

TS

e reports ee informa

an be furthful in sum

ne graph mbers. Somator of proect is on tr

e (4-27) Crit

" Tech

5/326

easy to reation neede

her simplifmary repo

may be mme reportoject staturack, yello

tical Issues

hniques o

ad. The fired by the fied by conorts sent t

much easies use the

us (see Figow indicate

Report

of output

rst step is recipient.

nverting dato upper m

r to interpsymbol of

gure 4-19,es minor t

ts & repor

to be sure Next, detata to gra

manageme

pret than af a traffics 4-20 & 4rouble, an

rts"

 

 

e ermine phics.

ent.

a -21).

nd

121/144

Cha

pter 4 

Figure (4-29

Figure (4-3

9) Project Pe

30) Project P

" Tech

5/327

erformance m

Performance 

hniques o

metric Defin

report 

of output

itions 

ts & reporrts"

 

 

122/144

Cha

8. Oth As

pter 4 

her Form shown in

of Repor figure 4-2

rt 22

" Tech

5/328

hniques oof outputts & reporrts"

 

 

123/144

Cha

pter 4 

Figure (44-31) Sampl

" Tech

5/329

e of other Re

hniques o

eport 

of outputts & reporrts"

 

 

124/144

Chapter 4  " Techniques of outputs & reports"

 

5/330  

4.2.4- Responses on Reports

This by no means implies that all variances require corrective action. There are four major responses to a variance report:

• Ignoring it.

• Functional modification.

• Re planning.

• System redesign Permissible variances exist for all levels of the organization. If the variance is within these permitted deviations, then there will be no response, and the variance may be ignored.

In some situations where the variance is marginal (or even within limits), corrective action may be required. To avoid dual standards and red tape, management must establish the decision-making policies associated with cost and control systems. The following is a policy guide.

• Approving all estimates, and negotiating all estimates and the definition

of work requirements with the respective organizations.

• Approving the budget, and directing distribution and budgeting of available funds to all organizational levels by program element.

• Defining the work required and the schedule.

• Authorizing work release. The manager may not, however, authorize

work beyond the scope of the contract.

• Approving the program bill-of-materials, detailed plans, and program schedules for need and compliance with program requirements.

• Approving the procuring work statement, the schedules, the source selection,

the negotiated price, and the type of contract on major procurement.

• Monitoring the functional requirements.

• When cost performance is unacceptable, taking appropriate action with the affected organization to modify the work requirements or to stimulate corrective action within the functional organization so as to reduce cost without changing the contracted scope of work.

• Being responsible for all communications and policy matters on

contracted pro- grams so that no communicative directives shall be issued without the signature or concurrence of the program manager.

125/144

Chapter 4  " Techniques of outputs & reports"

 

5/331  

4.3– Construction Cost Control Software

Project control software enables real-time and historic job and project cost management designed for use by your operational teams. Project control provides performance indicators on all project cost areas providing valuable insight to make quick decisions resulting in profit margin increases on every job. Centralization of key information provides collaboration and reporting across multiple jobs, projects and organizational departments. The project control system is outside the company’s sensitive accounting system providing the flexibility and manipulation capabilities required for testing alternatives and maximizing profit outcomes. Project control provides integration to over 50 different accounting systems, out of the box, which eliminates re-entry of data between systems saving personnel time and eliminating reproduction errors. Although many construction companies are still using spreadsheets and shoeboxes to manage their projects, the use of industry-specific project management software is becoming more prevalent. One reason for this is that more construction software providers are developing integrated project management modules to compete with the leading stand-alone project management systems. In my experience, there are two important aspects of cost management that separate it from the other project management functions. The first is that each firm has a very specific way that they do it and a very specific set of terms that they apply. It would be difficult to apply a pre-defined practice and a canned program, out of the box, that would satisfy the firm’s accounting requirements. We need only look at the Enterprise Resource Planning (ERP) applications to see the effect of this situation. Firms such as Oracle, PeopleSoft, Baan, SAP, and J.D. Edwards sell project financial management systems for several hundred thousand dollars (or more) and then charge that much again to tweak the system to the client’s specific needs. now let's see some kind of cost control software like, Project Costing System (PCS), Construction Industry Software (COINS), and WinQS. The general purpose Microsoft Excel spreadsheet is also used by some professionals. In fact, the largest option is Bespoke/in-house Systems, which is used by 29% of contractors and 38% consultants in UK. Software packages used for project cost control in UK

Contractors Consultants

Bespoke/in-house Systems 29% 38%

Microsoft Project 20% 32%

Project Costing System (PCS) 15% 11%

Asta Power Project 15% 5%

Primavera SureTrak 8% 5%

Microsoft Excel 7% 3%

COINS 5% 3%

126/144

Chapter 4  " Techniques of outputs & reports"

 

5/332  

4.3.1- Advantages of Used Software in Construction Cost Control

1- Timesheets and Time Management Tracking

Enter timesheets and daily diary information for projects from wherever they happen to be. Record hours worked by cost code, quantities completed, and daily diary notes, and synch that information with the home office using a laptop or handheld device. Analyze fresh data to optimize resources for the next day and provide real-time integration with accounting to accelerate cash flow for faster project billing.

2- Direct Accounting Integration

Collect and store timesheet data from jobsites, while sharing data electronically with accounting systems to eliminate double entry. Maintain time sheet standards with labor classifications, and other user defined tags. Import timesheet data from third-party systems or to any accounting system. Record notes for each cost item including assumptions, jobsite observations, and more. Increase communication for issues that include staging and additional information to the field operators. Provides crew based timesheets with pre-defined data streamlining foreman or supervisor completion.

3- Field Resource Tracking

Manage field resources efficiently. Analyze information about productivity and accurately track customer information including account status, equipment usage and service history. Easily make changes when a resource is identified with high performance. Ownership costs and operation costs can include information on depreciation, insurance, and other unique resource costs in order to determine true ownership cost as well as operational use cost.

4- Anywhere Project Analysis

Web-based reporting and dashboards make it easy to get information from anywhere. Meet with customers on-site to discuss projects with total access to historical information, as well as the ability to develop preliminary budget estimates for project or job budget creation on the fly. Eliminate printing unnecessary reports by remotely focusing what the customer is looking for.

5- Provide Progress, Resource and "Actual Cost" Updates

Updating Software with data from your other systems is easy when using the Software API. The Software API (Application Programming Interface) provides an automated method for updating Software with data from other systems to create new records, update existing records, or delete records automatically. By extracting the data from your other systems into an XML format supported by Software and submitting the XML data, Software will “listen” for the data and automatically update the appropriate projects. Currently, the Software API supports two types of data, Resource Rates and Job Tracking Details.

127/144

Chapter 4  " Techniques of outputs & reports"

 

5/333  

6- Monitor "Actual" Project Costs without Accounting Delays

Stay up to speed on job and project progress on a daily basis without waiting for accounting information. Preliminary and actual cost data is available daily to assess the need to make potential changes while there's still time to have an impact on the project's success and gross profit margin. Recognize time and other valuable information the moment it is entered without waiting for accounting and not having to re-enter data into multiple systems.

7- Remote Time Management Tracking

Control and monitor vendor commitments and activity, including original contract project components, insurance and bond monitoring status, change orders, invoices, requisitions, retention processing, and payments.

8- Collaboration and Updates

Save valuable man-hours eliminating the need to hand off estimates from one team member to the next. Allow last-minute updates until the bid is due, leveraging last minute pricing changes on materials and resources, while allowing multiple estimators to work on a single, or multiple estimates simultaneously.

9- Remote Data Access

Save gas, time and frustration by accessing information from anywhere including the office, remote offices, home, or client sites. Leverage un-tethered information access with synchronization, putting everything at your fingertips without being connected to the internet or network. Updates are entered throughout the day into a laptop or handheld device, and when convenient, a connection is made to the network to receive and send changes. Entry straight from the field eliminates duplicate data entry into numerous systems. Provide remote project access to managers, foremen and superintendents providing complete access to critical information needed to manage jobs remotely in one central location. Track cost and productivity positions of projects, responsibilities of team members, related documents, and ongoing project activities.

10- Centralize Project Information

Eliminate storing project information on local drives and multiple network locations. Project job tracking data is conveniently stored in one location and shared for easy access to all team members. Multi-office estimating provides synchronization between team members to accommodate real-time estimation updates.

128/144

Chapter 4  " Techniques of outputs & reports"

 

5/334  

11- You can access it from anywhere

To many people, the biggest advantage of cloud software is that it’s truly available on any computer or device anywhere in the world. This is particularly useful when the project team members are in the office, in the field and in a variety of geographical locations. There’s no hassle with synchronizing data or uploading changes to a centralized server. Everything is centralized already – so collaboration is built-in. You no longer face moments of not knowing if you’re looking at the most up-to-date version of a report; or those crushing times when you’re on your way to a customer meeting and, whoops, the report you need is on Dave’s laptop and, too bad, Dave’s in Mexico this week. Everything’s connected, integrated and constantly current

With Construction Cost Control Software solution you will have greater access to the following information:

Which materials are due during this week, and which ones are still on back order?

What's our profit margin for all approved change orders? Which change orders are pending on this project? We haven't received the new design changes for the final phase. When

was the last time we requested this information? Our actual labor hours are about the same as the original estimated

hours and yet we're not finished. Where can I find the "projected to complete" hours?

How many downtime hours (non productive time) did we accumulate last year? Are we doing any better this year?

Now that this project is complete, are all vendor invoices accounted for? I don't want to be blindsided with any "surprise billings" later on.

The bonding company is asking for future receivables, unbilled contract dollars, work-in-progress, contracts won but not started, current retained dollars, budgeted hours remaining on projects, and more. Is there one source that pulls all this information together?

Which workers have been assigned tools and equipment on this project? What's our percent complete vs. percent billed – can we do another

progress bill? What are the committed dollars remaining on this project? Can we attach job site pictures to the project so we can look at them

during our meeting with the owner? What's our total cost on returned materials for this project? Which items

were returned to the vendors for credit and which were returned to inventory?

129/144

Chapter 4  " Techniques of outputs & reports"

 

5/335  

4.3.3- The Disadvantages of Software in Construction Cost Control

1- Disadvantages in Percentage-of-Completion

Points to problems in the percentage-of-completion method as a distinct

disadvantage of cost control. This method, used to estimate costs under

cost control, uses a mathematical formula to determine how much of a

project a company can finish in a period, usually a financial quarter or

year. Percentage-of-completion is based entirely upon estimation,

meaning gross differences may occur between projected goals and

actual achievement, giving rise to misleading figures in cost control

analysis. Furthermore, the government may elect to tax a company

based on estimated percentage-of-completion rather than actual

completion rates. If significant disparities arise between estimates and

actual completion, companies suffer tax problems.

2- Disadvantages in Interlocking Systems

Bhabatosh Banerjee, author of "Cost Accounting Theory And Practice,"

points to problems in interlocking cost control systems. These systems

create cost control budget estimates and actual totals for different

aspects of a company's business and production. The disadvantage of

this lies in bookkeeping methods. If a single cost or expenditure applies

to two areas of a company with separate cost control budgets, that cost

or expenditure appears twice in the company's books.

3- Mismanagement of Cost Control

Mismanagement in cost control can lead to severe problems for

companies. For instance, cost control requires the consideration of a

broad palette of variables. If a company uses the wrong variables in

creating estimates for cost control or when creating figures displaying

total expenditure and total profit, the system produces widely inaccurate

figures regarding the cost effectiveness of procedures and processes.

What's more, human error may lead to severe inaccuracies -- all

employees involved in the process of calculating cost control, which

includes managers, foremen and more, must understand the system and

its requisite procedures

130/144

Chapter  5  Conclusions ""  

5- Conclusions 

Chapter 5  " Conclusions "

 

/51  

5- Conclusions

5.1- Common Causes of Cost Control Problems

1. Poor budgeting practices, such as basing the estimates on vague information from similar projects rather than the detailed specifications of the project at hand.

2. Failure to plan sufficient contingency budget.

3. Failure to correctly estimate research and development activities.

4. Failure to consider the effects of inflation on the cost of materials or labor.

5. Receiving or analyzing status information too late to take corrective action.

6. A climate that does not support open and honest disclosure of information.

7. Indiscriminate use of the contingency budget by activities that overrun their budgeted cost.

8. Failure to re budget when flaws are discovered, technical performance

falls below performance standards, or changes in project scope are approved. During the course of the project.

9. Many small decisions are made that ultimately impact costs. For

example, when engineering decides on the final design of a product feature, conventional accounting reports may not show the impact of these design decisions on production costs. In that case, the project manager must make sure that the cost impact is known before such decisions are made.

10. Weather conditions: Weather is probably the most common and

most obvious reason for work slowdown resulting in cost overruns. Work proceeds much more slowly under adverse weather conditions, and such conditions can impact the quality of the work as well.

11. Quality of the workforce: As a general contractor who hires

subcontractors, you don’t really have any control over the subcontractors’ workforce. Therefore, you have to trust that your subcontractors will provide experienced workers on your job. This is why, in my opinion, all subcontractors should be prequalified.

The risks associated with poor work quality are significant. If there is a problem, the poor quality will result in rework, and rework slows down job progress and can impact safety. The potential losses due to poor quality can put the entire project in a tailspin, and if this occurs, the project manager must take immediate steps to mitigate the situation.

131/144

Chapter 5  " Conclusions "

 

/52  

12. Quality of the supervision: Obviously, if you don’t have proper supervision on the job, there are going to be problems. Many issues have to be addressed every single day on the job, and everyone looks to the superintendent for direction and clarification regarding those issues. If you have an inexperienced superintendent who is not up to speed on the project, the type of work, or the systems in place to manage the project, you are going to have a disaster, plain and simple. As I’ve said before, this is why good superintendents are worth their weight in gold.

13. Incorrect sequencing of work: Unfortunately, there are times

when pressure from an owner or from the main office can cause a superintendent to schedule work out of sequence and before it is ready, just to appease some unrealistic demand for action. But no one knows better than the superintendent and the field personnel how the work needs to be scheduled to keep things on track. Sometimes a work activity is initiated just to give the appearance of making progress when in reality these artificial starts just waste time and cause all kinds of havoc on the job. If this occurs too often, the inefficiencies will eventually show up and expose the real story.

14. Change orders: Change orders can be one of the most insidious

factors influencing project performances. A little change here or there often seems like no big deal. Many contractors fail to ask for additional time when they process the cost of the change, thinking that they can wiggle the extra work into the existing schedule. Then all of a sudden, these seven or eight little change orders are causing the job to run two weeks behind, and then it is a big deal!

15. Overcrowded job site: One of the things that can actually hinder

work productivity is having too many people on the job. I have heard more than one subcontractor complain about packing too many workers in tight quarters trying to get a job done. It becomes so counterproductive that it actually slows down the job instead of speeding it up as planned.

16. Defective materials: Discovering that the material or equipment

that you were planning to install is defective is a real problem. It is certainly one that can be avoided with proper quality control. But in some cases, this defective material is not discovered until the workers are on the job ready to start the project. By this time, it is way too late. The time has already been wasted, and it will take time to reorder the material and reschedule the crews to install it.

132/144

Chapter 5  " Conclusions "

 

/53  

17. Inadequate tools and equipment: Having the right tools and equipment on a construction job may seem like a no-brainer. But again, when so much of the work of the contract is passed on to subcontractors, you don’t always have control over even these simple aspects of the job. I can’t tell you how many times I have seen work installed improperly because the craftspeople didn’t have the right piece of equipment

18. Late deliveries: Late deliveries are probably one of the most

frustrating causes of schedule delays and cost growth in construction. Once again, the contractor has very little influence or control over the manufacturing or fabrication processes involved in the making of many of the products or equipment used on the project. However, the stakes can be very high for the project if items arrive late. That’s why on projects with critical lead- time items, it is best to assign someone to do nothing but expedite deliveries and stay on top of the project buyout schedule.

19. Subcontractors Risks: Sometimes a subcontractor reneges on a

price before the subcontract is executed. When this happens, the general contractor has three options: contact one of the other original bidders and try to negotiate a price that both parties can live with; rebid the section of work altogether; or go out and negotiate on the open market, trying to secure the original pricing or better.

The most difficult situation to remedy is when a subcontractor gets into financial trouble and goes out of business before the job is complete. When this happens, it puts the project in a real tailspin, especially if the subcontractor in trouble ends up being one of your primary subcontractors such as steel or mechanical. Often the bonding company will step in and provide another specialty contractor to complete the work, but you can imagine what this sort of disruption does to the schedule and therefore the budget. The ramifications can be severe, and there may be no recovery from the damages. During a crisis like this, it is best for the owner, the contractor, and the architect to sit down and come up with a plan to mitigate the potential losses for everyone.

20. Quantity errors: When a simple quantity takeoff error into our

budget calculations. When this happens, it is best to find the error as soon as possible, preferably before you has committed to any purchase order or subcontract. If you find the error before committing to any pricing, you still have time to go out and negotiate your very best deal on the affected materials and labor in an effort to mitigate the obvious loss that you will suffer because of the inaccurate takeoff.

133/144

Chapter 5  " Conclusions "

 

/54  

21. Labor expenses are exceeding budget: The cause of this problem may be that phases are taking longer than estimated. Several actions should be taken:

22. Variable expenses are exceeding budgeted levels: This may occur because original assumptions were wrong or because you are not exercising enough control over spending. Consider these actions:

23. Out-of-sequence starting and completion of activities and events.

24. Inadequate work breakdown structure.

25. No management policy on reporting and control practices.

26. Poor work definition at the lower levels of the organization.

27. Management reducing budgets or bids to be competitive or to eliminate “fat”.

28. Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort

29. Poor comparison of actual and planned costs

30. Comparison of actual and planned costs at the wrong level of management.

31. Unforeseen technical problems.

32. Schedule delays that require overtime or idle time costing.

33. Material escalation factors those are unrealistic.

5.2-Keys to Effective Project Cost Control Effective project cost management is an extremely complex process that begins very early during a project life cycle, and long before its actual start. Among the factors that influence success is a reasonable and accurate system for estimating costs. Highlights some of the most important considerations when creating a cost management system.

1. A clear, complete, of the project and the scope of work involved.

2. A thorough assessment of the potential risks involved, with well

thought- out action plans to minimize their possible impact

3. A well-trained and competent project manager

4. A thorough understanding, by all stakeholders, of the various types of costs that are likely to be incurred throughout the life of the project

5. A project organizational culture where there is a free flow of

communication, so that all project participants clearly understand their responsibilities

134/144

Chapter 5  " Conclusions "

 

/55  

6. A well-defined project work structure where work packages are broken down into manageable sizes

7. Meaningful budgets, where each work package is allocated its

appropriate share of the total budget, adequate to the work involved

8. An accounting system and coding scheme that are well aligned with

the work breakdown structure and are compatible with the organization’s management information system

9. A cost accounting system that will accumulate costs and allocate

them to their relevant cost accounts as and when they are incurred

10.A prioritized and detailed work schedule, drawn from the work breakdown structure, which assigns and tracks the progress of individual tasks

11.Effective management of well-motivated staff, to ensure that

progress meets the work schedule

12.A mechanism for comparing actual and planned expenditures for individual tasks, with the results extrapolated to cover the entire project

13.The ability to bring critical tasks that are late back on schedule,

including providing for additional resources or taking other prompt remedial measures

14.Adequate and effective supervision to ensure that all activities are

done right the first time

15.Supervision of staff time sheets so that only legal times are booked to various cost codes

16.Proper drafting of specifications and contracts

17.Careful investigation to confirm that the customer is of sound

financial standing, with sufficient funds to make all contracted payments

18.Similar investigation, though not necessarily as discreet, of all

significant suppliers and subcontractors (especially those new to the contractor’s experience)

19.Effective use of competitive tendering for all purchases and

subcontractors to ensure the lowest cost adequate with quality and to avoid committing to costs that exceed estimates and budgets

20.Proper consideration and control of modifications and contract

variations, including charging all justifiable claims for price increases to the customer

135/144

Appendix A   

Appendix A

Cost Control Process Flow Chart

Gathering supporting document

Create cost Control model

Collect Current Cost data

Actual Cost Allocations

Analysis data with EV

Reporting

Decision making

Cost Control Processes for Construction Project

Basic Process of Cost Control in Construction Project

Level 1

Level 2

Level 3

Level 4

Level 5

Level 6

Level 7

1/7

136/144

Baseline Contract Document

Contract ofSub Contractor

Time Baseline Cash flow Baseline BOQ Drawings Specification

Level 1Gathering supporting

document

Estimated Budget

Direct Cost Indirect Cost/ Overhead

2/7

137/144

From BOQ, Budget Estimation, Sub

contractor, supplier contract

Create WBS

Fixed AssetSheet

Deprecations system

Expenses Sheet

Storage Sheet

Coding system

Develo

p

cost

Contro

l m

odel

Level 2 Create cost Control model

3/7

138/144

Finances Department Report

Storage Department Report

Technical Office Report

Material Expenses Labor Expenses Other Expenses Material storage

Report

Concrete pouring logVariations orderClient Invoices/

SubcontractorLabor number & allocation report

Quantity survey according to shop drawing

Equipment Expenses

Level 3Collect Current Cost data

4/7

139/144

Cost Control model

fixed assets sheet

WBS sheet Expenses sheet

Storage sheet

Technical Office Report

Equipment Expanses according to

Deprecations system

All Expenses Report

Subcontractor Invoices

Storage Report

Level 4

Client Invoices

Finances Department

Report

Finances Department

Report

Material storage Report

Actual Cost Allocations

5/7

140/144

Earned Value Rule Earned Value Parameter

Earned Value Analysis

Earned Value Report

Analysis Data with Earned ValueLevel 5

6/7

141/144

Project Summery original/update

Payment status according to client

invoice

Analysis of WBS Reason of profit or loose

Time Mony Direct Indirect

Decision making

Forecasting

ReportingLevel 6,7

7/7

142/144

Appendix B   

Appendix B

Responsibility Matrix for Cost Control Proces

References [1] Preparing for the Project Management Professional (PMP) Certification Exam Second Edition Michael W. Newell, PMP, ENP, pp. (25-30) & (77-102) [2] Project management step-by-step / Larry Richman pp.(49-51),(136-143)&(153,165) [3] Project Management Nation—Tools, Techniques, and Goals for the New and Practicing IT Project manager by Jason Charvat Copyright? 2002 by John Wiley & Sons, Inc., New York. (Chapter 7 - Controlling the Project) [4] Construction management jumpstart Second Edition by Barbara J. Jackson Copyright © 2010 by Wiley Publishing, Inc., Indianapolis, Indiana pp. (140-168) & (260-280) [5] Cost and Value Management in Projects. Ray R. Venkataraman and Jeffrey K. Pinto Copyright @2008 John Wiley & Sons, Inc. pp.(32-38),(43-56) ,(105-114) & (127-148) [6] Fundamentals of Project Management Third Edition by JAMES P. LEWIS [7] Practical Project Management Tips, Tactics, and Tools by Harvey A. Levine Copyright © 2002 by Harvey A. Levine.pp(159-162) [8] PROJECT MANAGEMENT A Systems Approach to Planning, Scheduling, and Controlling Tenth Edition by HAROLD KERZNER, P h. D. Senior Executive Director for Project Managenment, Copyright © 2009 by John Wiley & Sons, Inc.pp(633,685) [9] Project Management Gary R. Heerkens, PMP Copyright © 2002 by the McGraw-Hill Companies, Inc.(159,183)

[10] Project Planning and Control Fourth Edition Eur Ing Albert Lester, CEng, FICE, FIMechE, FIStructE, FAPM.pp(25-38)&(220-256) [11] Project Management for Facility Constructions A Guide for Engineers and Architects by Alberto De Marco.pp(119-136) [12] Skills & Knowledge of Cost Engineering Fifth Edition With New Appendix Listings Edited by Dr. Scott J. Amos, PE.

144/144

Resource Responsibility

P - Primary Responsibility A - Approval Authority S - Supporting Responsibility (Contributor or Reviewer) I - Information Only

(Select from drop down list)

P

roje

ct M

an

ag

er

P

rocu

rem

en

t M

an

ag

er

Ten

der

Man

ag

er

Fin

an

cial

An

aly

st

C

on

tract

Man

ag

er

Con

toro

l M

an

ag

er

P

roje

ct S

ched

ule

r

Q

uali

ty M

an

ag

er

Tech

nic

al

Man

ag

er

Ad

min

istr

ati

ve S

taff

Su

pp

ort

Sto

arg

e M

an

ger

Gathering supporting document

Time base line A S P IBudget base line I I P I I ICash flow A S A I P IBOQ I I P I I IDrawings P I I ISpecification P I I ISub contractor Contract A P I A I I

Cost Control model

Create WBS P S IFixed Asset Amount A P I I I IDeprecations system I S P A I SExpenses Amount I S P S I S SStorage Amount I I I S S PCoding system S S P I I

Collect data status

Material expenses I P S I S ALabor expenses I S I S POther expenses P S I SEquipment expnses P S I SSubcontracto/client invoices A S I PVariations order A I I I PQuantity survey I PConcrete pouring log I PLabor number & allocation report I I A PMaterial storage report I I I A P

Requirements Analysis

Actual Cost Allocations PAnalysis data with EV PReporting I I P I

1/1

143/144