cost-driven scheduling of grid workflows using partial critical paths

32
28 October 2010 Challenge the future Delft University of Technology Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths Dick Epema Delft University of Technolog Delft, the Netherlands Saeid Abrishami and Mahmoud Naghibzadeh Ferdowsi University of Mashhad Mashhad, Iran Grid 2010, Brussels, Belgium

Upload: alyn

Post on 10-Feb-2016

42 views

Category:

Documents


0 download

DESCRIPTION

Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths. Saeid Abrishami and Mahmoud Naghibzadeh Ferdowsi University of Mashhad Mashhad, Iran. Dick Epema Delft University of Technology Delft, the Netherlands. Grid 2010, Brussels, Belgium. Introduction. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

28 October 2010

Challenge the future

DelftUniversity ofTechnology

Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

Dick EpemaDelft University of TechnologyDelft, the Netherlands

Saeid Abrishami and Mahmoud NaghibzadehFerdowsi University of MashhadMashhad, Iran

Grid 2010, Brussels, Belgium

Page 2: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

2Partial Critical Paths

Introduction• Utility Grids versus Community Grids

• main difference: QoS and SLAs• Workflows: a common application type in distributed systems• The Workflow Scheduling Problem

• community grids: many heuristics try to minimize the makespan of the workflow

• utility grids: other QoS attributes than execution time, e.g., economical cost, play a role, so it is a multi-objective problem

• We propose a new QoS-based workflow scheduling algorithm called Partial Critical Paths (PCP)

Page 3: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

3Partial Critical Paths

The PCP Algorithm: main idea• The PCP Algorithm tries to create a schedule that

1. minimizes the total execution cost of a workflow2. while satisfying a user-defined deadline

• The PCP Algorithm• first schedules the (overall) critical path of the workflow such that

• its execution cost is minimized • it completes before the user’s deadline

1. finds the partial critical path to each scheduled task on the critical path and executes the same procedure in a recursive manner

overall critical pathpartial critical path

Page 4: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

4Partial Critical Paths

Scheduling System Model (1)• Workflow Model

• an application is modeled by a directed acyclic graph G(T,E)• T is a set of n tasks {t1, t2, …, tn}• E is a set of arcs between two tasks

• each arc ei,j = (ti, tj) represents a precedence constraint• dummy tasks: tentry and texit

tentry

t2

texit

t1

t3

t4

t5 t6

e1,4

Page 5: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

5Partial Critical Paths

Scheduling System Model (2)• Utility Grid Model

• Grid Service Providers (GSPs)• Each task can be processed by a number of services on different

GSPs• ET(ti,s) and EC(ti,s)

• estimated execution time and execution cost for processing task ti on service s

• TT(ei,j,r s) and TC(ei,j,r,s)• estimated transfer time and transfer cost of sending the required

data along ei,j from service s (processing task ti) to service r (processing task tj)

• Grid Market Directory (GMD)

Page 6: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

6Partial Critical Paths

Basic Definitions• Minumum Exection Time:

• Minimum Transfer Time:

• Earliest Start Time:

• SS(ti): the selected service for processing the scheduled task ti• AST(ti): the actual start time of ti on its selected service

),(min)( stETtMET iSsii

),,(min)( ,,, rseTTeMTT jiSrSsjiji

EST(tentry ) = 0

EST(ti) = maxt p ∈parents( ti )

EST(t p ) + MET(t p ) + MTT(ep,i)

used for finding thepartial critical paths

Page 7: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

7Partial Critical Paths

The PCP Scheduling AlgorithmPROCEDURE ScheduleWorkflow(G(T,V), deadline)

• Request available services for each task in T from GMD• Query available time slots for each service from related GSPs• Add tentry and texit and their corresponding edges to G • Compute MET(ti) for each task in G• Compute MTT(ei,j) for each edge in G• Compute EST(ti) for each task in G

1. Mark tentry and texit as scheduled 2. Set AST(tentry)=0 and AST(texit) = deadline3. Call ScheduleParents(texit) 4. If this procedure was successful make advance reservations

for all tasks in G according to the schedule, otherwise return failure

Page 8: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

8Partial Critical Paths

ScheduleParents (1)• The Critical Parent of a node t is the unscheduled parent

p of t for which EST(p)+MET(p)+MTT(ep,t) is maximal

• The Partial Critical Path of node t is:• empty if t does not have unscheduled parents • consists of the Critical Parent p of t and the Partial

Critical Path of p if t has unscheduled parents• Critical parent and partial critical path change over time

p t

126

69

281

Page 9: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

9Partial Critical Paths

ScheduleParents (2)PROCEDURE ScheduleParents(t)

• If t has no unscheduled parents then return success• Let CriticalPath be the partial critical path of t• Call SchedulePath(CriticalPath)• If this procedure is unsuccessful, return failure and a

suggested start time for the failed node (try to repair)• For all ti on CriticalPath /* from start to end */

Call ScheduleParents(ti) 1. Iterate over all non-scheduled parents of t

Page 10: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

10Partial Critical Paths

SchedulingPath (1)• SchedulePath tries to find the cheapest schedule for

a Path without violating the actual start times of the scheduled children of the tasks on Path

• SchedulePath is based on a backtracking strategy• A selected service for a task is admissible if the

actual start times of the scheduled children of that task can be met

Page 11: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

11Partial Critical Paths

SchedulingPath (2)• Moves from the first task in Path to the last task

• For each task, it selects an untried available service

• If the selected service creates an admissible (partial) schedule, then it moves forward to the next task, otherwise it selects another untried service for that task

• If there is no available untried service for that task left, then it backtracks to the previous task on the path and selects another service for it

• This may lead to failure

Page 12: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

12Partial Critical Paths

An Example (1)

S

1

2

3

E

4

5

6

7

8

9

Start: Call ScheduleParents(E)

Page 13: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

13Partial Critical Paths

An Example (2)

S

1

2

3

E

4

5

6

7

8

9

find the Partial Critical Path for node E(this is the overall critical path of the workflow)

Page 14: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

14Partial Critical Paths

An Example (3)

S

1

2

3

E

4

5

6

7

8

9

Call SchedulePath for path 2-6-9Call ScheduleParents for nodes 2, 6, and 9, respectively

Page 15: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

15Partial Critical Paths

An Example (4)

S

1

2

3

E

4

5

6

7

8

9

Node 2 has no unscheduled parents,so its partial critical path is empty

Page 16: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

16Partial Critical Paths

An Example (5)

S

1

2

3

E

4

5

6

7

8

9

Node 6: find its partial critical path and then call SchedulePathScheduleParents is called for node 3 but it has no

unscheduled parentsIf SchedulePath cannot schedule this path, then it returns failure, which causes the path 2-6-9 to be rescheduled.

Page 17: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

17Partial Critical Paths

An Example (6)

S

1

2

3

E

4

5

6

7

8

9

Node 9: find its partial critical path and then call SchedulePathScheduleParents is called for the nodes 5 and 8 but they have no

unscheduled parentsIf SchedulePath cannot schedule this path, then it returns failure, which causes the path 2-6-9 to be rescheduled.

Page 18: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

18Partial Critical Paths

An Example (7)

S

1

2

3

E

4

5

6

7

8

9

Now scheduling of the path 2-6-9 has been finished, and ScheduleParents is called again for node E to find its next partial critical path and to schedule that path

Page 19: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

19Partial Critical Paths

Performance Evaluation

• Simulation Software: GridSim• Grid Environment: DAS-3, a multicluster grid in the

Netherlands • 5 clusters (32-85 nodes)• Average inter-cluster bandwidth: between 10 to 512 MB/s• Processor speed: have been changed to make a 10 times

difference between the fastest and the slowest cluster • Processor price: fictitious prices have been assigned to each

cluster (faster cluster has a higher price)

Experimental Setup (1): the system

Page 20: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

20Partial Critical Paths

• Five synthetic workflow applications that are based on real scientific workflows (see next page)

• Montage• CyberShake• Epigenomics• LIGO • SIPHT

• Three sizes for each workflow: • small (about 30 tasks)• medium (about 100 tasks) • large (about 1000 tasks)

• Each task can be executed on every cluster

Performance EvaluationExperimental Setup (2): the workflows

Page 21: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

21Partial Critical Paths

MontageLIGO

SIPHT

CyberShake Epigenomics

Performance EvaluationExperimental Setup (3): the workflows

Page 22: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

22Partial Critical Paths

• Three scheduling algorithms to schedule each workflow:• HEFT: a well-known makespan minimization algorithm• Fastest: submits all tasks to the fastest cluster• Cheapest: submits all tasks to the cheapest (and

slowest) cluster

• The Normalized Cost and the Normalized Makespan of a workflow:

• CC : the cost of executing that workflow with Cheapest• MH : the makespan of executing that workflow with HEFT€

NC = total schedulecos tCC HM

makespanscheduleNM

Performance EvaluationExperimental Setup (4): metrics

Page 23: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

23Partial Critical Paths

Performance EvaluationExperimental Results (1)

Normalized Makespan (left) and Normalized Cost (right) of scheduling workflows with HEFT, Fastest and Cheapest

Page 24: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

24Partial Critical Paths

Performance EvaluationExperimental Results (2)

Normalized Makespan (left) and Normalized Cost (right) of scheduling small workflows with the Partial Critical Paths algorithm

deadline=deadline-factor x MH

Page 25: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

25Partial Critical Paths

Performance EvaluationExperimental Results (3)

Normalized Makespan (left) and Normalized Cost (right) of scheduling medium workflows with the Partial Critical Paths algorithm

Page 26: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

26Partial Critical Paths

Performance EvaluationExperimental Results (4)

Normalized Makespan (left) and Normalized Cost (right) of scheduling large workflows with the Partial Critical Paths algorithm

Page 27: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

27Partial Critical Paths

• One of the most cited algorithms in this area has been proposed by Yu et al.:• divide the workflow into partitions • assign each partition a sub-deadline according to the minimum

execution time of each task and the overall deadline of the workflow• try to minimize the cost of execution of each partition under the

sub-deadline constraints

Performance EvaluationComparison to Other Algorithms (1)

Page 28: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

28Partial Critical Paths

Performance EvaluationComparison to Other Algorithms (2): Cost

CyberShake Epigenomics

LIGO them

us

Page 29: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

29Partial Critical Paths

Performance EvaluationComparison to Other Algorithms (3): Cost

Montage SIPHT

Page 30: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

30Partial Critical Paths

Related Work• Sakellariou et al. proposed two scheduling algorithms

for minimizing the execution time under budget constraints:

• Initially schedule a workflow with minimum execution time, and then refine the schedule until its budget constraint is satisfied

• Initially assign each task to the cheapest resource, and then refine the schedule to shorten the execution time under budget constraints

Page 31: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

31Partial Critical Paths

Conclusions• PCP: a new algorithm for workflow scheduling in utility

grids that minimizes the total execution cost while meeting a user-defined deadline

• Simulation results: • PCP has a promising performance in small and medium

workflows• PCP’s performance in large workflows is variable and depends

on the structure of the workflow

• Future work:• To extend our algorithm to support other economic grid models • Try to enhance it for the cloud computing model

Page 32: Cost-driven Scheduling of Grid Workflows Using Partial Critical Paths

32Partial Critical Paths

Information

• PDS group home page and publications database: www.pds.ewi.tudelft.nl

• KOALA web site: www.st.ewi.tudelft.nl/koala

• Grid Workloads Archive (GWA): gwa.ewi.tudelft.nl

• Failure Trace Archive (FTA): fta.inria.fr